Weekly Report for Week Ending September 20, 2001


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  September 24, 2001 will be:

 (Meeting time: 10:30 am Pacific Time)

Open meeting 10:30 - 11:30

  1. Announcements
  2. LSC Issues (Weiss)
  3. Comments on Weekly Report
  4. WBS 1 LIGO I Construction (Lindquist)
  5. WBS 2 LIGO Lab Operations
  6. WBS 3 and 4  Advanced R&D and LIGO II (Sanders)
Executive Committee only 11:30 - noon   Topics:

Special Items:


Special Announcements:


Weekly Report Highlights
 


LSC Issues (Weiss)


No report.


LIGO I Construction/LIGO Laboratory Administration (Lindquist)


WBS 1.2 LIGO Operations--Administration



LIGO Weekly Site Telecon (Lindquist)

Weekly Site Telecon not held this week due to SUS Conceptual Design Review for Advanced LIGO and key personnel on travel.
The list of current actions revised to reflect the status of open actions assigned through September 13, 2001 may be found at ACTION LIST.


PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Cleveland Mak <mak_c@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

ACCOMPLISHMENTS

ACTIVITY
  Packages Faxes
In 39 39
Out 9 35

Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman)

From: Esther Cunningham <esther@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA.

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

From: Florence Kaufman <fkaufman@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@ligo.caltech.edu>

SUPPORT (Wood)

Dorothy Lloyd

Rita Torres Irene Baldon Elizabeth K. Wood

Advanced LIGO (Frey)

From: Thomas Frey <tfrey@ligo.caltech.edu>

Progress Period from 09.14 to 09.20

Accomplishments:

Schedule 09.21 to 09.27:

WBS 1.4.1.2   Project Controls (LIGO Construction)



Reports (Lindquist)

The end-of-August Quarterly Progress Report will be due at the end of September, and I have requested contributions by September 21.  This could be the last Quarterly Progress Report required under this Cooperative Agreement, although we will still have to provide some kind of Annual or Final Report.  Under the new Cooperative Agreement, we think that only an Annual Report will be required.



Change Control/Contingency (Lindquist)

The following Change Requests have been submitted.
 

CR-010006 WBS 1.1.4 (OPS) Roof Shelter for Concrete Pad Adjacent to Erosion Control Pond (Livingston) M. Coles
CR-010007 WBS 1.2.4 Core Optics Components, Repolish/Recoat Beamsplitter S. Whitcomb
CR-010008 WBS 1.1.4 Five-Ton Crane for the Staging Building in Hanford O. Matherny
CR-010009 WBS 1.4.2 (OPS) Additional 10-W Laser for PSL Lab S. Whitcomb
CR-010010 Advanced R&D Seismic Isolation System PD ETF Mechanical Contract (APPROVED) D. Coyne/ G. Stapfer

We scheduled a meeting of the LIGO Change Control Board for Tuesday, September 11, 2001, at 9:00 am PDT. An agenda was distributed electronically (LIGO-M010244-00-P).  This meeting was postponed in light of national events and will be rescheduled.

Press for the latest Contingency Needs Projection.


COST SCHEDULE CONTROL SYSTEMS (Duncan, Akutagawa)

From: Kris Duncan <kris@ligo.caltech.edu>

From: Cindy Akutagawa <cindy@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Jasnow)

From: Ed Jasnow <jasnow@ligo.caltech.edu>


Quality/Safety (Tyler)

>From: Bill Tyler <tyler@ligo.caltech.edu>

No report this week.


LIGO Hanford Observatory (LHO) Operations (Raab)


General Items (F. Raab)

WA2k is up and running again after our mild bakeout of the LVEA.  Work is ongoing on many projects.  Common and differential tidal actuators, intensity servoes, PSL isolation, WA4K Michelson work, wave-front sensors are just a few items. These are either disinteresting right now or reported elsewhere. Now that installation is largely completed, resident staff are getting involved in commissioning issues.

On Sep 17, Mark Coles, Steve Maguire (SLU) and Warren Buck (UW) met at the NSF offices in Arlington, VA with Tim Olson (SKC) on conference phone. Vic Cook had arranged the meeting between us and personnel in the NSF education directorate to try to help us get the ball rolling on efforts to increase the pipeline for african-american and native-american students into the physical sciences as part of LIGO outreach.


LIGO Livingston Observatory (LLO) Operations (Coles)



Networking: LSU is scheduled to come tomorrow to install a router which will allow us to use our second T1 line. There will probably be a brief period when we are not reachable from the outside net, but probably not for more than a few minutes. (Tom Evans)

LDAS: Called cybernetics about the maintenance contract on the tape library. Will be purchasing the contract which requires shipping the library to cybernetics for inspection. Received the shipping box today so the unit should be going out tomorrow to cybernetics. Rebuilding admin here to allow for the disk to disk backups of various machines. I have a couple of finishing touches to do on this, but it is 95 percent complete. Admin will be back up at around 3:00 CT today.
GC: installed some free security software on our windows 2000 server here in LA to block all of the attempted infections of nimda. We applied all of the patches to this box previous to the virus/worm outbreak this week, but just to be safe, I have blocked all connections on port 80.
CDS: Nothing to report (Shannon Roddy)

Detector: Optics and Installation: Installation of the door hardware for the Laser Safety Interlock system continues, as well as additional exterior security cameras at both ends. Visited a Jefferson Parish Sewerage & Water Board pumping station with Mark and Szabi to inspect an acoustical enclosure that had been installed by a potential supplier of panels for the PSL. We made measurements of the effectiveness of the enclosure to isolate over the frequency region relative to the frequency noise induced by the laser table. (Jonathan Kern)

Other: High school physics students from Istrouma High School in Baton Rouge visited LLO today with their teacher - Wilson Doucette. They would like to replicate the SST program begun at LHO. Wilson participated in our pilot IRET program at LLO this summer. He has independent funding from Dow Chemical to support this activity and has gotten in contact with the High School teacher in Portland to get some pointers regarding the program with LHO.


Detector/Technical Support (Whitcomb, Coyne)


Installation& Commissioning:
Hanford
Livingston
Other Science/EngineeringActivities:
Design/Analysis/Fab
Issues/Concerns
See also the Installation web page

1.1 LHO INSTALLATION & COMMISSIONING

2km Commissioning

Matt  Evans, Nergis Mavalvala, Stan Whitcomb
Much of this week was spent aligning the interferometer and the detection port tables after the LVEA heating. Difficulties in locking the interferometer were tracked down to further saturation of the RF photodetectors and now the interferometer is locking reasonably well again. The laser power had steadily drifted up over the course of a few days as the PSL system equilibrated thermally (and was tweaked up) and we had to attenuate the detected power. In getting the full ifo to lock we also remeasured and tweaked up the RF sideband frequency, all RF phases at the detection ports, and of course all the lock acquisition parameters (offsets, slopes, g ratios). Since then we have captured some lock acquisition traces (Matt's thesis data) as well as some single arm data for threshold velocity studies (also Matt's thesis data).

4km Commissioning

Bill Kells, Corey Gray, Nathan Hindeman, Richard McCarthy, Josh Myers, Mike Landry, Bill Butler, Stan Whitcomb
Got the 4 km modecleaner operating again.  Aligned the vertex optics and found that the beam was low on MMT3 and therefore presumably in the recycling cavity.  This was fixed and the full interferometer roughly aligned.  The beam at the antisymmetric port appears to be clipping, though perhaps not enough to interfere with nearterm commissioning. The beam was aligned onto ISCT4 (the antisymmetric port).  This gave good Michelson fringes, and after a little fumbling, the Michelson could be easily locked, giving an end-to-end demo of the digital locking with the digital suspensions.

Attempts to lock the X arm cavity met with less success.  The arm was well aligned, and we had flashes of light on the transmission monitor QPD, but the fringes seemed to be going through too fast.  The problem may be the frequency noise from the modecleaner.  This initiated an effort to level the modecleaner.

A first cut was made at commissioning the WFS for the 4 km modecleaner. The first step in this process, identifying the bounce mode frequencies of the different small optics, immediately lead to a puzzle.  There was only one peak near the expected frequency (16.25 Hz), which was identified as MC1.  Eventually the missing peaks from MC2, MC3, MMT1, MMT2 ans SM1 were found, but near 19.25 Hz!  Finally the mystery was resolved when a mostly used spool of molybdenum wire of the correct diameter was found in the optics lab.  The higher elastic modulus of Mo pretty well matches the higher bounce frequency.  We are still contemplating what, if anything, to do.

1.2LLO INSTALLATION & COMMISSIONING

4 km Commissioning

Rai Weiss reporting
After the unsuccessful attempt to lock the recombined Fabry-Perot/ Michelson the week before, several steps were taken: Possibly due to these steps or simply more experience with the system, the recombined Fabry-Perot/ Michelson did lock for seconds.

The Q of the longitudinal, pitch and yaw motions of the mode cleaner and mode matching telescope masses were measured. All now show simple decay curves with Q between 1000 to 6000 depending on the motion and the amount of recoil loss.

There has been improvement in the frequency stabilization loops. By changing compensation, the fast servo loop unity gain frequency has been increased to 1/2 MHz. The frequency noise spectrum is now dominated by acoustic excitation and the excitation of the vibrational modes of the periscope on the laser table. The acoustic isolation of the laser enclosure and the change in the persicope beam have become pacing items.

PSL

Peter King
During commissioning work, the frequency stabilization servo was modified.  The noise gain compensation for the PA85A, Pockels cell driver, was looked at again.  After going through some numbers the noise gain compensation was installed.  This was found to degrade the performance of the servo and was subsequently removed.  The feedback resistor in the bypass path was reduced and the unity gain of the servo was determined to be greater than 500 kHz.

Whilst the modifications to the frequency servo were contemplated, the spare frequency servo card was examined.  There were a few small differences due to the revision level and a number of components were not present on the board.

2.0 OtherEngineering and Scientific Activities

2.1 Design/Analysis/Fab

IOO PERISCOPE

Mike Smith, Ken Mailand, Mark Barton
The lowest vibration modes with side and back cross braces added were measured to be 213Hz with the Optosigma mirror mount, 231Hz with the Ultima mirror mount, and 260Hz with no mirror mount. The cross braces themselves appear to have resonances between 47Hz and 350Hz, which are adding significant energy around 200Hz. Dennis Coyne modeled a stiffened version of the cross braces using FEA  with the indication that the lowest resonance of the stiffened-cross brace periscope with the Optosigma or Ultima mirror mounts should be above 250Hz. Stiffener channel sections are being welded onto the cross braces on 9/19, and re-testing is expected to be completed on 9/20, with shipment  to LLO possibly on 9/21. A purchase order for the production of 3 more units is in process. Two PZT tilt platforms with strain gage sensors were shipped to LLO.

PSL

Lee Cardenas
126 MOPA  S/N 110 Rick Karwoski, Paul Russel
Our main goal here at Hanford is to close the intensity stabilization loop around the Mode Cleaner. We are situated at the 2K. We have observed large amounts of extremely low frequency laser power variations at the pmc PD, under open-loop conditions. The lo-end excursions are much larger than the baseline noise amplitude and sufficiently large as to saturate the electronics while in closed-loop operation.  We did not see these variations during our last visit.   We are currently running further tests in the vacuum area and evaluating the situation.

We are also wiring in a number of PSL signals to the DAQ system.  We will be using them as an aid in the resolution of our new intensity issue.

Sander Liu

LSC

Rich Abbot, Mohana Mageswaran, Flavio Nocera

Digital Suspension

Jay Heefner
 Module            Needed           Fab Complete      Tested
 SUS PD Interface  29               34                15
 Anti-Image        12               16                7*
 Universal Dewhite 22               25                25
 LOS Coil Driver   14               18                18
 LOS Bias          14               17                16
 SOS Dewhite       11               16                16
 SOS Coil Driver   15               24                24
 Opt. Lever
 Intface           15               16                16

Fabrication and test of modules for the digital suspension upgrade is complete with the exception of the Anti-Image boards. We are waiting for the final delivery of filters from Frequency Devices. They are due by 9/20. We currently have enough Anti-Image boards to complete the first IFO.

Sander Liu
Received 50 each of the 44 pin Positronic Connector for the antialiasing filter chassis. This will help us complete building four LEMO chassis for delivery. Three other boards are still waiting for the four pin LEMO connectors with a mid October delivery date.

LLO Seismic Feed Forward

Jay Heefner Rolf Bork
Working full time (almost) on microseismic feedforward.  I should have a better feel tomorrow (Thursday) whether or not we will be ready for installation at LLO next week.  The basic interface between EPICS and the ASC frontend and between the ASC frontend and the end stations is operational. Spent better part of today figuring out how to pass doubles (digital filter coeffs) across the 32 bit reflected memory from EPICS to the frontend with appropriate endian byte swapping.  This is required to allow "on the fly" filter coeff changes without interrupting the ASC front end, which is performing the control algorithm calculations.  Lori is now expanding the simple test code that I developed to do this transfer into the EPICS interface code.

I will continue on the front end code.  Now that I have the I/O connected and tested, I need to test the filtering algorithms and verify everything in the middle is operational.  If I can get this going tomorrow, then we should be ready for next week.

Diagnostics

Daniel Sigg
A new binary distribution of DTT (Version 1.2) was assembled. Apart from numerous bug fixes, it comes with a new ROOT version (3.0) and it contains lidax/fantom. It will be available shortly through the LIGO tools distribution.

Send the numeric entry widget which was developped for DTT to the ROOT development team for incorporation into the standard ROOT release.

Data Monitoring Tool

John Zweizig
This week I returned to moving the DMT software sources into a new CVS repository. This effort was dropped last July because it would have been difficult to have the new repository ready in time for the E5 run and the Burst/Stochastic MDC. Thus, the modifications needed for these runs were made to the old repository. I have nearly completed transcribing these modifications into the new repository, after which I will return to writing and debugging the make files needed to build the DMT software.


40 Meter Interferometer (Weinstein)



PSL  (Abbott, Ugolini, Vass, Smith, King):
The NPRO in our PSL started tripping off every hour or so, quite regularly, starting on Monday.  Today (Thursday), we opened the Lightwave MOPA box with Peter and found a bit of cooling water leakage; and we found that the cooling water line to the NPRO was almost completely closed. We opened it up, and since then, the NPRO has not tripped off.  Ben will try to eliminate the small leak, later.

Our PSL enclosure wiring still doesn't work; opening the doors  does not set off the alarm or trip the laser.  We have verified that the kill switches DO trip off the laser.  Ben had the Caltech electricians in, and after 2 days, they couldn't fix it. Ben has a new, much simpler, wiring diagram, and will re-wire the whole thing himself (so that it's done right).

We went over different issues with Peter.  He advocates holding off on changing the layout of the PSL until the dust settles, some months from now.

Facilities (Vass, Jones, Smith, AJW):
CES is still constructing custom support legs for the last 3 optical tables.  Larry awaits the shims that are required to bring all the tables up to their desired nominal height.

We expected the new 5'x12' optical table last week, but it turns out that it was never ordered, because the single source justification was not sufficient.  Apparently, they need written quotes from at least 3 vendors, no matter what (and they never told us).  So, we wait another 6 weeks...

We now have several options for in-vacuum cables: Cooner wire can make 25-conductor, twisted pair, braided shield cables with FEP teflon insulation on each conductor; either 5 mil or 3.5 mil.  MDC can do the same, with 2 layers of kapton insulation on each conductor; it will be stiffer than the Cooner wire but less stiff than the MDC wire we have now. We also could ask Santa Fe Textiles to do the twisting and braided shield.

Larry still awaits samples of braided in-vacuum wire for testing; Santa Fe Textiles is 2 weeks late on this. We hope to have samples of the twisted, braided Cooner wire, for testing on our small MCCM seismic stack.

Dennis and Steve has assembled our small MCCM seismic stack on an optical table, and are measuring transfer functions using natural ground motion  and our Wilcoxon 731A accelerometers.  AJW prepared a simple 1-dim (vertical) model of the stack transfer function, and estimated mirror displacement psd.  Results of the transfer function measurements are ambiguous: only getting good readings from 1 to 70 Hz, around the resonant peaks; and there is some evidence that 2 of the 3 stages are shorted....   We just got back our shaker, so will do swept sine measurements with it in the hope of getting to lower and higher frequencies.

Steve has ordered 9 new optical quality viewports with AR coating, and is shipping out 12 lower-quality existing viewports for AR coating, all from Cascade Optical. Larry is designing new viewport seal flanges which will hold the window at a 2.5degree tilt, to minimize backscatter into the IFO.  He's done the drawings and already has CES building them (5 are needed).  Mike Smith has done detailed BRDF calculations of the backscattering, and concludes that 2.5degrees  is sufficient, even for the ETM transmitted beams (which are the worst case).

Steve and Dennis vented the 40m last week to pull off 2 viewports for re-coating, and added another CC gauge at the same time. Venting and pump-down proceeded well.

Suspension controllers (Ben Abbott, Heefner):
Ben continues to work on the detailed Protel drawings for our 10 digital suspension controllers.  We hope to have a mini-review of these, in a couple of weeks.  Estimate that if they are approved in October, they could be ready for assembly and commissioning in January.

Suspensions (Romie):
Submitted drawings to CES for fabrication of 5 test mass suspensions. Included in the package are drawings for magnet fixtures. KineOptics is designing and fabricating the guide rod fixture for these optics.   CES is also reworking the sensor/actuator plates for the small optic suspensions to allow more room for the beam. They are currently working on the magnet fixture for those optics.

Core optics (Billingsley):
Gari received a quote for core optics polishing from CSIRO,  and is awaiting a quote from WavePrecision.  She is also preparing coating specs for the core optics.  AJW prepared transmission values and estimated tolerances.

Scattered Light control (Smith):
An estimate of the scattering of the ETM transmission beam from the output window indicates that a tilt of 2.5 degrees of the window is adequate to reduce the scattering to an acceptable level. Larry Jones has designed a flange holder to tilt the output window at 2.5 deg (see above). The
scattered light phase noise calculations are being reviewed to check the parameters used for the 40m IFO, and to incorporate the effect of the signal recycling mirror.

Computing (Bogue, Ugolini, Bork):
Lisa has mounted the martian network shared disk onto our gateway (rana), read-only.  She has rana samba-serving the GC disk /home/cit40m onto the PCs on the martian network.  We now have well-defined pathways to get code, data, etc., to and from the martian network without compromising security.  Rolf expects to complete the population of the martian network shared disk, when he returns after next week.


Thermal Noise Interferometer (Libbrecht)



This week we began replacing our high-finesse (105) arm cavities with lower-finesse versions (104).  We anticipate that this will significantly improve lock acquisition and robustness, without adversely affecting the noise performance of the instrument.  So far, we have vented and opened the chamber, removed the high-finesse south cavity, and installed the new mirrors.  We have not yet aligned these new mirrors, nor have we yet replaced the north cavity.

We have also placed a Faraday isolator between the in-vacuo Pockels cells and the beamsplitter.  When we locked both arm cavities simultaneously several weeks ago, we noticed significant coupling between the two cavities, and we suspected this coupling to be of optical origin.  Inserting a Faraday isolator was not deemed practical at the time because it would have required significant realignment of the optics.  The new optics will have to be aligned after they are installed, and we are taking advantage of this opportunity to install an isolator.


LASTI (Zucker)



LASTI (Fritschel, Harry, MacInnis, Mason, Miller, Mittleman, Ottaway, Phinney, Rollins, Shoemaker, Zucker)

Rapid test of the proposed adLIGO hydraulic pre-isolators on a BSC equipped with LIGO I seismic isolation has been elevated to top priority.  This is a response to the excessive impulsive disturbances now routinely observed at LLO.  Previously LASTI had not intended to install anything in BSC0 until the adLIGO stack/suspension prototypes were ready next year, so this represents a major perturbation.

LLO has shipped back to MIT the spare downtube and BSC leg element set (thanks Gary, Harry and Ed C.!).  Despite its many travels and months of outdoor storage, the barrier seals appear intact and recleaning/rebaking should not be required.  We are tracking down other spare BSC stack parts throughout the project with the aim to get a stack installed by second week of November.

In the meantime we have accelerated the grouting under the support piers.  Joe Giaime and Brian Lantz have asked us to study the reaction impedance of the piers by temporarily removing the load and measuring their free eigenfrequencies.  This information is needed to inform the hydraulic isolator controller design. The test will commence as soon as the grout reaches full strength (about 1 week after pouring).

Hydraulic pre-isolator design and test (Mason, Phinney)

Springs have been designed for two design scenarios. The first design uses 2 springs per leg with a vertical stiffness of 1 x 10^6 n/m at 8 Hz. The other approach uses 4 springs per leg with a vertical stiffness of 1.5 x 10^6 n/m at 8 Hz. Design sketches for each of these approaches are being created so that a decision by the advanced seismic group can be made on the right approach to pursue.

Pumps, valves, accumulators, and drums of hydraulic fluid are coming in (also a substantial "spill containment pallet" which Stanford tells us is a very good idea).  Joshua is assembling a test stand in the machine shop to evaluate dynamics and noise issues in the proposed actuators.  One key variable is how the performance will be affected by placing the drive pumps and reservoirs remotely in the Observatory mechanical rooms.

LASTI Test Cavity Suspensions (Weaver, MacInnis, Miller, Ottaway)

Betsy Weaver visited us for a week and helped us learn how to suspend and balance the SOS, as well as getting our cleaning and handling infrastructure in shape.  We now have both cavity optics plus a spare ready to go, working OSEMs and working SOS controllers with EPICS support.

We had tentatively scheduled an incursion into HAM13 to install these in vacuum for week of 9/24; due to the new activity associated with the hydraulic pre-isolators, we have now put this installation on hold until some smoke clears.

LASTI PSL (Ottaway, Rollins)

We are expecting delivery of our repaird MOPA from Lightwave sometime next week.  Meanwhile using our NPRO we have started to exercise the electronics and optics together.  Working around two bad boards, a miswire in the crossconnect and a cold solder joint in a detector head, we finally got a good error signal off the pre-modecleaner reflection last night.  Plan is to have the PMC locking on the NPRO beam this weekend and then push on to the frequency servo next week.

LASTI DAQ/GDS/CDS computing (Mike)

Daniel Sigg and John Zweizig took advantage of their attendance at the MDC a couple weeks ago to install GDS and DTT software and give us some advice about how to configure our network.  Unfortunately we had another RAID disk failure (there is a bad batch affecting all LIGO sites) so we did not get as far as wanted.  However we did get together a plan for improving the network architecture so that, for example, our GDS system can simultaneously support local LASTI and observatory data reduction and diagnostic tasks.  We will need to procure additional hardware for this which is not currently budgeted.

A failed router on our CDS subnet knocked us out for a day, interfering with Betsy and Dave's efforts to balance the SOS; Ed Daw, who happened to stay on after the MDC (given no choice, there being no flights last week!) was able to debug and fix the problem for us.

LASTI Infrastructure (Mason, MacInnis, Miller)

A mezzanine for staging the BSC stack in LASTI has been designed and is out for quote.

Cable trays for LASTI have been quoted; an order will be placed today.  We are planning to do installation in-house so we can phase it in gradually as the electronics are added.  This will help keep the trays out of the way for the SEI installation.

Construction of the custom psl enclosure has begun at the outside fabricator's shop. Several issues with the suppliers drawings still remain to be ironed out.

Environmental Issues (Zucker)

We are experiencing severe shaking from pile driving and contamination from trucks at the nearby construction site.  After a lot of running around I woke a sleeping dragon in the form of MIT's real estate director, who has now threatened to revoke the developers' lease (MIT owns the land) unless the contractors shape up.


Data Analysis and Computing (Lazzarini)


Simulation and Modeling (Bhawal)

Weekly E2E Physics Meeting

Biplab discussed mode mismatch calculations for LIGO using time domain modal model in E2E. After that Bill Butler talked about measurements of seismic correlation among stack locations at Hanford. This work was done by Bill and Robert Schofield. The data will be used in Han2k model for obtaining proper seismic noise spectrum.

Modal model calculations

(Hiro) Time domain modal model has been revisited to clarify various uncertainties in calculating various mode decomposition matrices. Also two null tests have been analytically demonstrated to understand how a modal model with finite number of modes work. The LIGO Note T990081 including these works has been updated.

(Biplab) Comparison with an analytical derivation verified that the direction  in which the maximum power points lie in a beam reflected from a tilted mirror is correct in e2e simulation. Also tested: simulations of the beam-shifter module and cavity with lateral shift in mirror (each separately and also when a beam-shifter's output beam is introduced in a cavity with same shift in mirror: a null test).

Alfi

(Ed Maros) Worked on Makefiles for new JAlfi
(Bruce) Currently working on finishing the Alfi5 file parser.
(Melody) Continued on the implementation of the graphics portion of alfi5.  Working on drawing the primitive nodes and ports.
 

LIGO Data Analysis System
Software Systems (Blackburn)

The Parasoft software diagnostic tools, Insure++ and CodeWizard have been installed on a linux and solaris workstation. The LDAS configuration scripts will be modified to detect these and compile with the option to use them to build versions of LDAS that can be processed for coding inconsistencies and errors using these tools.

The confusion within the LDAS CVS repository over where sql files should be placed has been rationalized and corrected. There is now a single place for all database sql files instead of the confusion set of three that previously existed.

Testing of the frameAPI began in order to understand the failure modes that were exhibited during the MDC during heavy frame I/O loads.

The byte swapping bug for complex data that was discovered in the dataConditionAPI during the last MDC has been corrected. Now complex frequency series stored in the database can correctly be interpreted and used in datapipeline jobs.

Work began on adding a heartbeat monitor to each slave process running in a wrapperAPI job. The initial configuration will report a stalled node after 300 seconds of missing heartbeats and after 600 seconds without a heartbeat, the wrapperAPI job will be terminated by the mpiAPI. A dead lock problem that was detected while testing the new maximum memory usage throttle in the wrapperAPI was fixed. Also, the wrapperAPI will be getting a resource file to store start up variables and thereby reduce the amount of information passed on the command line. This will also allow the same wrapperAPI to be used in debug modes by a simple change to the resource
file.

Work also began on added new functionality to the dataConditionAPI to be able to insert results from a database query into the datapipeline for use in the search codes.

The controlMonitorAPI now has a new monitoring tools which lets users see the different search codes by search user and shared object that are running on the individual nodes of the beowulf cluster.

Hardware Systems (Anderson)

Caltech

(Dan Kozak) Some HPSS hand-holding, restarting Sammi and other servers.  Adding tapes to storage classes.  Repacking tapes decreased to nothing by the end of the week since we're out of tapes to repack on the Redwoods.

Solved (we think) Red Hat sendmail problem to allow Linux desktop machines to properly masquerade the return address on outgoing email.

Coordinated install of 9940 drives into new silo and install of ACSLS machine/software for silo.

The LIGO tape silo has physically moved its first tapes, albeit using CACR tape drives.

(Al Wilson) Hardware news -  put a new computer on line, ldas-grid it is in the machine room at mill. Also I am working on a replacement for m27 a 2 Ghz box the old m27 will be used for visitors. getting a nasty uneven field problem on the new lcd in  the machine room. Will continue to troubleshoot.

(A. Lazzarini note: this server is being used to provide an interface to grid resources being developed through GriPhyN)

Software news - still working on the http pages for the " how to make a ldas computer" and as always working on getting cfdef perfect.

(Stuart Anderson) Started the next major round of LDAS hardware procurement to support the Caltech production LDAS system (ldas-archive) and build the LIGO data archive system by planning and discussing possible technical solution with Sun Microsystems.

Rebuilt the one LDAS Alpha processor box with RH7.1 (ldas-alphadev1.ligo.caltech.edu) and released it for LDAS development
and general computing access.

Livingston

(Shannon Roddy) Called cybernetics about the maintenance contract on the tape library.  Will be purchasing the contract which requires shipping the library to cybernetics for inspection.  Received the shipping box today so the unit should be going out tomorrow to cybernetics.  Rebuilding admin here to allow for the disk to disk backups of various machines.  I have a couple of finishing touches to do on this, but it is 95 percent complete.

Hanford

(Greg Mendell)

1)  Continued work on the known pulsar search code DS0.  Debugged code for writing ilwd output for the SNGL_DPERIODIC database table.  Worked with AEI group to debug call to demodulation routine that creates longer time baseline DFTs from shorter base line DFTs.  The code now compiles, runs without errors, and produces reasonable numbers.  The next steps are to add additional error checking, add tests to verify that the code produces correct numbers, and increase efficiency.

2) Added db2 file system on LHO metaserver to backup script that runs daily on the LHO LDAS network.

3) Discussed with CDS and LDAS plans initiated by CDS for network security.

4) A faulty sensor indicated a filter change was needed on our Liebert AC unit.  The sensor was replaced, and some adjustments to the tuning of the unit were made.

Data Analysis Activities

Vicere' and Lazzarini have almost completed an analytical model for how power grid correlations may be continue to exist even over long observation times due to the fact that 60 Hz is a frequency standard slaved over long time scales to GPS (nowadays).

General Computing (Wallace)

MIT

Nothing to report.

Hanford

(Christine) Most of the past week has been spent on procurement and budgeting issues.  Moved a couple of computers around for new hires.  Looked at the video conferencing setup.


LIGO II/Advanced R&D (Sanders)


>From: Helena Armandula <ahelena@ligo.caltech.edu>

"Q" measurements
Sent 2 (3"dia. x 1" tk.) substrates to Sheila Rowan to be measured.  She is leaving for Glasgow shortly, however, she'll  perform the measurements there. Expect to have them finished by the end of October.  There are two more (3" dia. x 1" thick) substrates available to be measured.  G. Harry, at Syracuse for the week, and S. Penn are making steady progress measuring 2 thin substrates.

Advanced LIGO Coatings
Coating absorption studies will start within a few weeks.

We are signing an agreement with Gary DeBell from MLD to do the following coating runs on 1" fused silica aimed at studying the effects of different materials and annealing temperatures on absorption:

1) TA2O5/SiO2
2) Nb2O5/SiO2
3) ZrO2/SiO2
4) TA2O5/Al2O3
The samples will be annealed at 250, 300 and 350C.  The runs can be done at 2 week intervals.

Silicate bonding
Continuing tests to observe the effect of temperature on substrate/bond stress.

>From: Janeen Hazel Romie <romie_j@ligo.caltech.edu>

Advanced LIGO Suspensions
Preparing for the Advanced LIGO Design Requirements and Conceptual Design Reveiw tomorrow. Submitted viewgraphs to Peter Fritschel this afternoon.

>From: Mark Barton <mbarton@ligo.caltech.edu>

I've been working on an improved mathematical model of the Advanced LIGO suspension conceptual design, on the pattern of the one I did for initial LIGO. Unlike the Matlab model provided by GEO, this will be a fully 3D one in Mathematica, incorporating most of the features of the real thing except for violin and internal body modes.

>From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>  (Weekly 16 September 2001)

Both Lia and Florian stranded at Caltech because of the terrorist acts.

Charlotte
Calculated thermal profile of flex joints under different heat loads.
Calculated maximum allowable bend before breaking of joints.

Mathieu
More simulation of stress on silicate bonds, simulating both Glasgow’s and home designed shapes.

Charlotte, Mathieu
Looking into introducing thermal noise and thermoelastic in Ansys

Lia, Riccardo
Acquiring and data analysis of early data analysis of creep.

Wind induced blade oscillations induce heavy (few micron size) aliasing noise on DAQ.
Compared algorithms.  Found that simple average over 40 second (250Hz acquisition) reduces the DAQ noise to below the micron level, for now below the other external noise sources (residual thermal drifts and building movements).  More sophisticated filtering like sinusoidal fitting more effective but not necessary for now.  Implemented 40 second average on-line filtering to clean data and reduce data sample.  Now generating only ~ Megabyte/week.  First logarithmic creep behavior shown above.

Akiteru, et al. @ Hongo
More IP feed forward work.
Preparing for JPS (end of week)

Alessandro @ Pisa
Finishing the mechanics of the last horizontal accelerometer with micro-ground flex joints.  Preparing justificative papers and bids for NC UltraSound sapphire cutting machine.  Preparing to make more Sapphire flex joints with old US machines.  Testing first prototype for vertical accelerometers for Newtonian noise.


For additional information about this report, contact sanders@ligo.caltech.edu