Weekly Report for Week Ending September 17, 2009


LSC

Administration

Hanford Observatory

Livingston Observatory

Optical & Mechanical

Controls and Data Systems

40 Meter Facility

TNI

LASTI

CIT Science Group

Laboratory Computing

Adv. LIGO Development & Project

Past Weekly Reports


There will be no meeting of the LIGO Executive Committee on Monday, September 21 because many are in Budapest.

Calendar of future Executive Commitee Meetings


Special Announcements:


Weekly Report Highlights:


LSC Issues (Reitze)

No report received for the current week.


LIGO Laboratory Administration (Lindquist)

PROPERTY MANAGEMENT (Luna)

>From: Rod Luna <rluna@ligo.caltech.edu>

DOCUMENT CONTROL CENTER (Mak)

>From Cleveland Mak <mak@ligo.caltech.edu>

Nothing significant to report.

FINANCIAL SYSTEMS (Lindquist, Oracion)

>From: Karl Oracion <koracion@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Arvizu, Champagnie, Jasnow, Marroquin, Salone)

>From: Rudy Arvizu <arvizu_r@ligo.caltech.edu>

>From: Jacqueline Champagnie and Gina Salone

See Advanced LIGO Report Below.

>From: Steve Marroquin smarroqu@caltech.edu

No report (vacation).

>From: Ed Jasnow <jasnow@ligo.caltech.edu>

> From  Ruth Winstead <winstead_r@ligo.caltech.edu>

See Advanced LIGO Report Below.

PROPOSALS and REPORTS (Lindquist, Beckett)

> From: Dave Beckett <beckett@ligo.caltech.edu>

The monthly report for the end of August has been sent to the NSF.

>From: Phil Lindquist <lindquist_p@ligo.caltech.edu>

CHANGE REQUESTS (Lindquist)

HUMAN RESOURCES (Akutagawa)

>From: Cindy Akutagawa <cindy@ligo.caltech.edu>

No report - vacation.


Quality/Safety (Nolting)

ADVANCED LIGO SAFETY IS BEING REPORTED UNDER ADVANCED LIGO, BELOW

LIGO Lab Safety:

David Nolting:


LIGO Hanford Observatory (LHO) and Interferometer Operations (Raab)

Summary of activities at LIGO Hanford Observatory (compiled by K. Kawabe):

Squeezer update (D. Sigg, S. Dwyer):


LIGO Livingston Observatory (LLO) and Interferometer Operations (Giaime)

Enhanced LIGO commissioning (Valera Frolov):

LLO CDS (Keith Thorne):

Hardware

Software


Mechanical and Optical Systems (Coyne)

See aslo Advanced LIGO

Tiltmeter and SOC (Self Organized Criticality) dissipation R&D (Riccardo DeSalvo).

Luigi:

I did the LVDT and ACTUATOR calibration for the Glassy Blades. I`m starting data acquisition to analyse the ringdown about the two systems.


Controls and Data Systems (Bork)

See Advanced LIGO

No report received for the current week.


40-Meter Interferometer (Adhikari)

Report for the week ending 9-10-09:


Thermal Noise Interferometer (Black)


LASTI (Mittleman)

LASTI:

Jay and Rolf have been here this week updating the frame builder, changing the clock rate on the ISI front end from 2kHz to 4kHz and various other CDS upgrades. Due to the CDS work most other lab work was not possible.

BSC-ISI:

Myron has installed the two Trillium-240 low frequency seismometers on the BSC support beams. We plane to use these to investigate feed forward schemes for additional ISI isolation.


CIT Science Group (Weinstein)

No report received for the current week.


Laboratory Computing (Anderson)

LDAS SOFTWARE SYSTEMS (Maros):

LDAS SYSTEM ADMINISTRATION (Anderson):

Caltech

(Dan Kozak):

(Phil Ehrens):

(Josh Abadie):

MIT

(Fred Donovan):

Livingston

(Igor Yakushin):

(Doug Lormand):

Nothing reported.

Hanford

(Greg Mendell):

(Dan Moraru):

GENERAL COMPUTING (Wallace)

MIT

(Fred):

Livingston

(Dwayne):

Hanford

(Jonathan):

CIT

(Veronica):

(Larry):

(Christian):

(Mike):

(Melody):

DCC:

myLIGO:


Distributed (Grid) Computing R&D (Blackburn)

Grid Application Development

Einstein@Home on the OSG:

Awaiting Robert's return from vacation to ramp up further.

Binary Inspiral Application on Grids:

Open Science Grid Integration & Validation Testbed:

No Report (Robert is on vacation this week).

Grid Management:


Advanced LIGO and Supporting R&D (Shoemaker)

Advanced LIGO Management

Report covers time period from August 31 through September 11

from Carol Wilkinson

Project Controls

Staffing

Procurements

For Ed Jasnow

For Steve Marroquin

No report this week.

For Rudy Arvizu

For Jacqueline Champagnie and Gina Salone

      SI-144            Storage Containers; RFQ issued to Vendors due 30 days.

      SI-145            Counter Balance; RFP issued to Vendors due 30 days.

      CO-102          Optics Metrology; On Hold.

Invoice Administration/Admin Support

For Ruth Winstead

Property Management

Rod Luna

.NSF Acquisition Approvals

Progress Updates

Meetings & Reviews

Advanced LIGO Systems

Dennis Coyne <coyne@ligo.caltech.edu>, Peter Fritschel <pf@ligo.mit.edu>, Calum Torrie<ctorrie@ligo.caltech.edu>, Matt Evans <mevans@ligo.mit.edu>, Ed Chavez <chavez_j@ligo.caltech.edu>, Bob Taylor <taylor_r@ligo.caltech.edu>, Mike Smith <smith@ligo.caltech.edu>, Mike Zucker <mike@ligo.mit.edu>, Hiroaki Yamamoto <hiro@ligo.caltech.edu>

See the Adv. LIGO Systems wiki

Design/Readiness Reviews:

For a list of reviews, see the main AdL wiki page

Reviews currently underway:

Impending reviews:

Procurement Techncial Reviews:

See the procurement wiki.

Technical Review Board (TRB) (see the TRB log):

Nothing significant to report.

UHV & Vacuum Review Board (VRB) (see the VRB log):

UHV compatible materials list (E960050): submitted a revised version to the DCC.

UHV Prep Lab (Bob):

Optical Contamination Cavity Testing (Bob T., Liyuan): continues

Configuration Control & Documentation:

Nothing significant to report.

Design/Planning:

Quad Mock Up (Calum):

We are building a quad ETM lower structure mock up for COC at Caltech. This will be used to test concepts for protecting the optic. Quotes for parts are out or going out today..

Damping Struts (Calum, Kurt):

We have been taking data in the lab on one of the damping strut concepts.

Optic Cake Tin Containers (Calum, Kurt, Ken):

We now have a new design for the CP cake tin and are going out for quote for 2 prototypes.

Opto Mech Meet (Calum):

After a summer break we started back up the opto-mechanical meeting. We covered:
- HAM 2 layout
- Layout of BSC's with ETM with ETM telescope layout, AdvLIGO Systems, BSC5-H2 Top Level Chamber Assembly
- Advanced LIGO Systems Drawings, D0901491

Systems Drawings (Ed):

I updated all BSC (10 total) Chambers System Drawings for H1 and H2 PDF files. I added the location of each chamber with respect to the Stations (Page 1 of 4), I also added the BOM of all components (Page 2 of 4).

Installation/Commissioning Options (Mike):

Held a systems meeting to discuss options for the installation and commissioning of AdL.

Gas Damping (Norna):

Norna Robertson and Jim Hough revisited the question of residual gas induced damping of the test mass, based on recent LISA project measurements (T0900416-v1). The tentative conclusion is that AdL may require lower pressure in the corner station than is currently achieved. Further investigation is required.

Interfaces: (see the RODA status page and the Interface Control page):

Nothing significant to report

Modeling and Simulation

From: Hiroaki Yamamoto hiro@ligo.caltech.edu

No report this week (travel).

Safety

From: David Nolting   dnolting@ligo-la.caltech.edu

Quality Assurance

From: Mick Flanigan flanigan_m@ligo-wa.caltech.edu

QA:

SEI:

COC:

Have been reviewing the DCC documents related to optics coatings to prepare for the upcoming coatings vendor visit.

ICS:

 

Facilities Modifications and Preparations

From: John Worden <worden_j@ligo-wa.caltech.edu>

Seismic Isolation

From: Ken Mason kmason@ligo.mit.edu

aLIGO Project Activities

SEI Electronics Design and Fabrication

HAM ISI Design and Procurement

HEPI Build Status - Eric Allwine, Hugh Radkins, Jim Warner

SEI Activities and Progress at LLO

BSC ISI Design

Stage 2 Design

Suspensions

From Janeen Romie and Norna Robertson
(romie_j@ligo-la.caltech.edu, nroberts@ligo.caltech.edu)

Operations Work:

Project-funded Activities:

Prestabilized Laser

From: Peter King <pking@ligo.caltech.edu>

Operations:

Chasing up a number of quotations for 3mm InGaAs photodiodes

Project

Input Optics

From: Rodica Martin <rmartin@phys.ufl.edu>

ELIGO Comissioning (LLO):

We wrote a Matlab model of the LLO OMC mode matching. From this, I determined the best change possible to improve the mode matching is to replace TT2's 4m ROC optic with a flat mirror. We purchased this mirror, installed it, realigned the beam into the OMC and measured an improvement of 4-5%. (Kate)

Advanced LIGO Design:

Advanced LIGO R&D:

We tested a piece of Class A baked SiC at ~90 W input power and 1.8 mm diameter focused beam for several days and the results are very encouraging: no outgassing has been observed after the initial irradiation. The slight pressure increase when the sample was first illuminated decreased slowly to the cold value while continuing pumping. The temperature of the sample at the location of the beam (back side) was 240 C. (David F.)

Advanced LIGO Procurement:

We received one bid so far for coatings for the mode cleaner and the steering mirrors. The bid period will close on Friday, Sep 18.

Core Optics

From: GariLynn Billingsley <Billingsley_G@ligo.caltech.edu>

Auxiliary Optics

From:   Michael Smith <smith@ligo.caltech.edu>

WORK UNDER PROJECT BUDGET

Optical Layout

WORK UNDER OPERATIONS BUDGET

Output Faraday Isolator

Ken is working with Niem on an additional optical bench and the overhead rail for the 303 lab floor. All the parts for the rail have arrived. Virginio is working with Niem to design the mounting and attachment mechanism for the rubber support cords for the Faraday isolator vibration measurement table. He will order the rubber cord.

Optical Lever

Andrea and Tara are trying to determine the cause of the wide angle diffraction patterns that move when the fiber from the fiber-coupled laser is moved. They are comparing the CCD camera results in real time with the quad diode.

ETM Telescope

Ken has a preliminary design of the ETM Tel/transmon table assembly. He is waiting for comments from Sam Waldman before proceeding.

TCS

Phil and Aidan presented their answers to the TCS PDR committee. They are awaiting the response from the committee.

Photon Cal

Nothing new to report.

CDS

From: Vern Sandberg <sandberg@ligo-wa.caltech.edu>

Operations: R&D, ELIGO DAQ, and Electronics

LHO - Electrical Engineering - R. McCarthy

LHO - Systems/Software - D. Barker

LLO - Electrical Engineering - C. Adams

Worked with the TCS team (Phil, Koji, Chris, and much help from Rich A.) to bring the TCS electronics online, tune them, and characterize them. The TCS laser beams (central, annulus, and aiming) have also been realigned and adjusted after being powered off for some time.

LLO - Systems/Software - K. Thorne

Keith worked with Dave Barker and Jamie Rollins to explain the 'stdenv' setup for control-room scripts and documented scalable font setup for Linux MEDM.

Project: AdvLIGO Systems

SEI - B. Abbott

DAQ - R. Bork

ISC - R. Abbott


For additional information about this report, contact Albert Lazzarini