There will be no LIGO Executive
Committee scheduled Monday, July 16, 2007 due to the meeting
of the LIGO Staffing Committee scheduled at that time.
Special
Announcements:
Weekly Report
Highlights
LSC Issues (Reitze)
LIGO Laboratory
Administration (Lindquist)
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Cleveland Mak
<mak_c@ligo.caltech.edu>
- Processed documents for
the Amaldi Conference.
- Finalizing the last
details of the shipment of the Scatterometer from Stanford.
- Completed the necessary
paperwork for shipment of the Seismic Attenuation Unit to Virgo.
- Packaged and shipped
laptops/projectors to MIT for the upcoming LSC/Virgo Meeting.
- Prepared and made
arrangements for shipment of LASTI Reaction Mass to MIT.
- Assisting with the
process of getting a laser from Germany through customs
procedures. Began preparing forms so we don't have to pay a duty
tax on the importation of this laser.
- Scanning Update -
Progress continues on the scanning of all non-electronic "G" category
documents.
FINANCIAL SYSTEMS
(Funaro, Brambila, Kaufman)
>From: "Funaro,
Catherine" <Catherine.Funaro@caltech.edu>
>From: "Brambila, Ruth"
<Ruth.Brambila@caltech.edu>
- Going through and
checking active encumbrances to remove funds or to request for the
orders to be extended or closed. There are two lists of
encumbrances that have been submitted for me to go through. Both
lists are rather long.
- Responded the auditor's
request on MIT and provided the requested information. Provided
purchase order files to the auditors as requested.
- Received the last
document for HPD and routed the package for review and approval.
- Completed the routing
of the signatures for the mods to Triad and Heraeus Optics.
- Continue chasing
Non-Comps and supporting documents for Techmart requisitions that are
submitted without electronic attachments.
- Provided assistance on
inquiries from the Hotline pertaining to an outstanding LIGO invoice
that is aged several months.
- Have three change
orders to subcontracts for invoice attached orders that do not include
price reasonableness. One order is also expired.
>From: Florence Kaufman
<fkaufman>
- Completed and sent out
all monthly reports for June.
- Prepared 5 Intra Award
Cost Transfers to move expenditures that had been charged to existing
accounts while waiting for fabrication account to be set up.
- Contacted Sponsored
Research to try to find out why there has been a delay in setting up
several fabrication accounts that had been requested.
- Prepared a schedule of
potential budget recapture for unfilled positions for the third quarter
of fiscal year 2007.
- Financial reports can
be found at: http://docuserv.ligo.caltech.edu/~fireport. (For
passwords contact Florence)
SUBCONTRACTS MANAGEMENT
(Jasnow, Salone)
>From: Gina Salone
<gsalone@ligo.caltech.edu>
- Gina Salone is working
with the University of Glasgow to try and finalize the arrangements for
Calum Torrie to work at Caltech under an arrangement whereby LIGO will
pay the University for a portion of his time.
>From: Ed Jasnow
<jasnow@ligo.caltech.edu>
- Ed Jasnow and Peter
King are working with Ann Bussone, of the Office of General Counsel, to
assist the German laser manufacturer, Laser Zentrum, in filling out a
form required by the FDA before a laser can enter the U.S. The
laser is one of those being donated by the Max Planck Institute, and is
now at LAX awaiting completion of this form. Ms. Bussone will be
working with outside counsel and our customs broker to resolve this
issue.
PROPOSALS and REPORTS
(Lindquist)
We are entering the last
few weeks scheduled for preparation of the Continuing Operations
Budgets and Proposal (FY 2009 through FY 2013). Everyone’s
continued support will be appreciated. I will be distributing
some additional requests shortly.
The monthly report to the
NSF is due this week. I have most of the needed contributions.
CHANGE
CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
- There are no open
change requests.
HUMAN RESOURCES
(Akutagawa)
>From: Cindy Akutagawa
<cindy@ligo.caltech.edu>
- The next Staffing
Committee meeting is scheduled for July 16.
- A Staffing Committee
meeting was held on June 18th. The minutes and action items have been
posted on the SC web page. All files for the Staffing Committee
are up-to-date and posted on the SC web page.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
No report.
LIGO
Hanford Observatory (LHO) and Interferometer
Operations (Raab)
Summary of S5 Activities
at LIGO Hanford Observatory (compiled by K. Kawabe)
The duty cycle of H1 for
the last two weeks (from Thu. 28/Jun/2007 to Wed. 11/Jul/2007) was 82
percent, with typical 15.5 Mpc range. For H2 it was 78.9 percent. The
inspiral range of H2 has been hovering low anywhere between 2.5 and 6
Mpc, but it finally got back to 7Mpc later this week.
Summaries: Range
and Duty Cycle update. Tuesday
maintenance summary.
Highlights from the LHO
elog:
Outreach:
- LHO partnered with WSU
GEAR UP on a two-week summer experience for 20 Pioneer Middle School
students (Walla Walla) between 6/18/2007 and 6/29/2007. The Space
and Technology Boot Camp occurred at Pioneer School and included
two visits to LHO.
- "The nature of
Scientific Inquiry", a WSU-TC graduate course for teachers hosted by
LHO, began its two-week run on 7/9. This week over 50% of the LHO staff
have participated in class activities such as job shadows and interviews
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Giaime)
LIGO computing and
network security (Roddy)
--------------------------------------------------------------------
Reported
under General Computing,
see below
General computing and LDAS admin (Giardina)
---------------------------------------------------------------------
Reported under General Computing, see
below
Reported
under LDAS System
Administration, see below
Data analysis
& computing (Yakushin)
---------------------------------------------------------------------
Storage/Condor/LDAS admin:
Reported under LDAS System Administration,
see below
Data analysis:
Reported under Data Analysis activities,
see below
Mechanical and Optical
Systems (Coyne)
See Advanced LIGO
Controls and Data Systems
(Bork)
See Advanced LIGO
40-Meter Interferometer (Weinstein)
- We gave tours of the
lab to 45 HS students from the Summer Science Program in Ojai (last
week), and a dozen exchange students from Zambia (this week).
- Last week, Rob took
spectra of the RF readout frequency noise coupling, before and after
the drag wiping of the ETMs. As expected, the frequency noise coupling
has decreased significantly.
- This week, Rob is at
Amaldi, giving talks on DC readout at the 40m and also on the
stochastic radiometer search.
- We are planning to vent
once again, next week (Wednesday), to drag-wipe ITMX. We may also try
to drag-wipe ITMY, but it is difficult to reach. Rana has a plan for
moving ITMY within reach using teflon skis.
- We have a new and
improved DCPD in-vac preamp, tested by Ben and soon-to-be tested again
by Tobin. We could install it during next week's vent, but we'll
probably wait till Rob gets back from Amaldi.
- Our framebuilder,
fb40m, is dying; when it crashes, we lose data. Alex is working on
diagnosing and fixing the problem. Sonia needs the DAQ to take data for
her suspension optimization work.
- Sonia found that she
couldn't optimize the damping on the suspended optics without first
diagonalizing the OSEM input matrix, so she's working on that. She's
writing a matlab script to fully automate the process.
- Alice has completed a
noise analysis of her new RFPD preamp design, and finds improved SNR
with respect to previous designs. She is getting ready to build a
prototype circuit and test it with Jenne's AM laser.
- Josh has been
frame-grabbing images of the test mass optics illuminated by the laser,
and is analyzing them.
- Josh is developing an
automated mode scanning system, and is testing it out on the PMC. Next,
the OMC.
- Keenan is continuing
his analysis of gravity gradient contributions to the LIGO noise. The
effect of BSC chamber shaking is negligible. Next is the concrete slab.
- Jamie Rollins is
visiting, and is currently working on photodiode characterization.
Thermal Noise Interferometer (Black)
- All issues at LMA with
the optimized coatings appear to be resolved, and the mirrors are
expected to ship this week.
- We are making good
progress with moving the spot to probe thermal noise as a function of spot
position. The tilt weights are installed, and Ilaria and Greg are aligning
the arm cavities in preparation for closing the chamber. SAC's
visibility is between 70 and 80%, and NAC's axis has been found using
the auxiliary laser.
LASTI (Mittleman)
ISI
- Myron,
Hugh, Cory and Stephanie have been working on assembling the BSC-ISI.
Stage 0 has been assembled and is sitting on the test stand. The
second stage is currently being built. There have been a few problems
associated with the cleaning. One of the stage 0 plates is warped; it
mostly flattened out after it was assembled. The second problem is that
the cleaning was not done properly on all of the faces of the plates
this is being remedied with hand cleaning followed by FTIR testing.
Quad
- Ian and
Graham are here from RAL and have started to assemble the noise
prototype quadruple pendulum.
CIT Science Group (Weinstein)
________________
Kent Blackburn, last week:
GRID APPLICATION
DEVELOPMENT
- Write monthly OSG report
- Write agenda for weekly
LIGO-Pegasus telecon
- Attend weekly
LIGO-Pegasus and DASWG telecon
- Request mor disk space
at FNAL_FERMIGRID
- Run LIGO WFs with
V2 data on OSG sites
- Run V3 WFs on ldas-grid
- Prepare for V3 WF runs
on OSG:
- change .ini file
settings
- generate .dax file
- convert .dax to
.dag using Pegasus
- Start V3 WF runs on OSG
sites
- Prepare OSG_USER
meeting presentation
GRID INTEGRATION TESTBED
DEVELOPMENT
- Attend PEGASUS telecon
- Attend OSG VTB telecon
- Attend OSG ITB telecon
- Working to understand
Condor SMP VM setup
- Install new host
certificate on osg-itb (gatekeeper) server because the old one expired
- Audit osg-itb
environment variables setttings
- Audit osg-itb cron job settings
- Audit osg-itb file system settings
(export and mount points)
- Audit osg-itb (gatekeepter),
osg-itb-se(submit node) firewall settings (iptables)
- Monitor/understand
network traffic on osg-itb (gatekeeper) and osg-itb-se (submit) generated
by condor and vdt software using "ethereal" tools and
"netstat" command
- Setup new firewall
rules (IPTABLES) on osg-itb and osg-itb-se server
- Validate the new
firewall rules do not break condor and vdt software by testing multiple LIGO condor
jobs on the osg-itb cluster submit from osg-itb-se server
GRID MANAGEMENT
- Worked with DOEGrids to
have Murali Ramsunder accepted as a new Registration Authority Agent for
the OSG:LIGO VO
- Updated my own status
as a DOEGrids Registration Authority Agent for the OSG:LIGO VO
- Filed Quarterly Report
to OSG as the Caltech PI
- Met with director of
TeraGrid to discuss possibilities for LIGO applications. Included analysis,
CA hosting, windows GSI clients, backfilling of jobs
- Discussed Einstein at
Home backfilling on OSG condor sites with Warren Anderson (OSG LIGO Council
Person) and Ruth Pordes (OSG Director) as a possibility. Warren
will pursue this with Pulsar Group
________________
Kent Blackburn, this week:
GRID APPLICATION
DEVELOPMENT
- Version 3 Calibrated
H(t) Frame data testing:
- discovered change
in segment lists 4 V3 data
- requested and
obtained V3 segment lists
- generated new
segments for V3 analysis
- bug in pipeline.py,
inspiral.py and inspiral_hipe.in was discovered and fixed by Duncan and
Drew
- waiting on: bug fix
in pegasus-site-converter, tag of new glue/lal/lalapps versions
- Face-to-Face Meeting
with ISI:
- Pegasus presentation
- Pegasus hands on
tutorial
- converting from VDS
to Pegasus 2.0 tutorial
- discussion of LIGO
specific changes in Pegasus and Glue
- Preparating talk for
OSG-User and Applications workshop being held at Fermilab
OPEN SCIENCE GRID
INTEGRATION TESTBED
- Attend PEGASUS tutorial
workshop
- Attend DASWG telecon
- Attend OSG ITB telecon
- Audit osg-vtb
environment variables setttings
- Audit osg-vtb cron job
settings
- Audit osg-vtb file
system settings (export and mount points)
- Monitor network traffic
on osg-vtb (gatekeeper) generated by condor and vdt software using
"ethereal" tools and "netstat" command
- Setup new firewall
rules (IPTABLES) on osg-vtb, pass OSG-ITB Grid Exerciser daily testing
- Backup files and
environment on osg-vtb to prepare the vtb upgrade and testing
- Backup files and
environment on osg-itb to prepare the itb upgrade and testing
- Backup files and
envrionment on osg-itb-se to prepare the Pegasus
Upgrade
- Help identify and
trouble-shoot ISI viz-login server firewall problem, made suggestion to the Karan to
resolve login issue from Caltech
- Download the Pegasus
2.0 source code, read new document, compile the new release into the binary
distribution and install the binary release on osg-itb-se server
- Patch the Pegasus 2.0
release
- Setup the new Pegasus
2.0 environment for end user
GRID MANAGEMENT
- Discussing possible
migration of Einstein at Home appication as a backfill application on OSG
Condor clusters
- Working with the OSG
Applications coordinators on areas where Caltech can contribute to the
overall OSG effort.
________________
Eirini Messaritaki:
- I worked with Vibha on
the detection of eccentric binaries using non-eccentric templates. We spent
quite a while debugging the ODE solver that gives the phase, eccentricity
and semi-latus rectum as functions of time. We now have eccentric
waveforms.
- I worked with Romain
and Steve on the automation of the follow-ups in the inspiral pipeline. We are
currently testing the DAG script and trying to add more functionality
to it.
- I worked on debugging
and testing the inspiral null stream code.
________________
Xavier Siemens:
- Attended Cosmology and
Strings conference in Trieste, Italy.
________________
Stephen Fairhurst:
- Final revisions of
paper on Loudest Event statistic prior to submission to P&P committee
for review
- Address internal LIGO
reviewer comments on paper "Interpreting theresults of searches for
gravitational waves from coalescing binaries" prior to submission to
archive/journal
- Work on ability to
automatically run the full inspiral pipeline and followup weekly
- Discuss use of neural
networks in inspiral search with Kari and Becky
________________
Duncan Brown:
- Worked on comparison of
numerical relativity waveforms with post-Newtonian templates
- Helped Diego with the
implementation of the PTF search
- Helped Drew debug a
couple of problems with compression in the inspiral pipeline
- Attended meeting with
ISI computing science group to discuss using the inspiral code on the OSG
- Release a new version
of glue software
- Build ligotools
packages for metaio and the frame library
- Worked with Stuart on
some ZFS issues with the new Sun file servers
________________
Drew Keppel:
________________
Kari Hodge and Becky
Tucker are developing a neural net to use inspiral trigger information
to effectively separate signal (injections) from background (time slides,
accidental coincidence of noise triggers). First results look terrific.
Laboratory Computing (Anderson)
LDAS Software Systems (Maros)
- A milestone with the
diskcacheAPI has been reached. Using tandem-v, it has been shown that hung NFS file
systems can be detected and removed from the hash table allowing
second order results to be returned. When the file system comes back online,
then the primary result is returned. The system has also been shown to
come up with hung NFS file systems. Currently the code base is being
tested on ldas-dev to evaluate performance and stability.
- To increase space
available to the resource table, the resource page of cmonClient was modified to use
menu buttons to display functions for resource modifications and display
of column data. Further real estate was made available by the use of a
notebook to hold command status and resource table.
- The Job statistics page
was modified to have the number of jobs passed, failed, and rejected to be placed
above the users and commands information.
- System testing was done
using version 1.8.603 of the LDAS software. All system tests passed with their
expected results.
- Work has started on
providing a version of ligotools that supports certificate based authentication.
The loop scripts that run on ldas-dev each night along with several
other system tests have been modified to make use of this modified version
of ligotools. All the modified scripts continued to function properly
using the modified ligotools.
LDAS System Administration (Anderson)
Caltech
(Erik Espinoza)
- Wrote initial
migrateuser script for qfs to zfs migration.
- Fixed replacement GC
mail server for authenticated relays.
- Found errant
spamassassin rule to reject spam.
- Worked with Paul Armor
and Stuart on learning ZFS.
- Built and configured
machine to test NX.
MIT
(Fred Donovan)
- /dso-test/home
(exported from data2) multiple hangs from ldas-grid - remove data2 from
automount maps files resolved this.
- Set up pcraid13 (old
datacache11)
- Updated condor (rpm)
added disk (df) output to cluster monitoring.
Livingston
(Dwayne Giardina)
- Tape eject for shipment
to CIT.
- Working on cluster_mon
adding network usage to summary page.
- Gave Doug a run-through
on the tape eject and shipment process, as well as what to watch
for on the T3s and 351x's.
Hanford
(Ben Johnson)
- Wrote script to pull
out user certificates from the doegrid's LDAP database, and extract
their expiry dates. With the other information in the LDAP database
(e.g., email addresses), matching certificate(s) with a unique human
being should be more reliable now.
- LHO publishing scripts
died this weekend due to RLS problems related to the LHO network.
- The design work for the
Asynchronous FrameIO module (for LDAS NDS) is finished. I would guess
the code is 80% of the way to an actual server test (a.k.a. debug
session). Most time has been spend on keeping track of all the I/O
requests and making sure everything is keep in the right order.
General Computing (Wallace)
MIT
(Fred)
- Added more LIGO22
wireless in new space; LIGO17 wep in nw17 control room; more ip address changes;
- Reconfigured the
printers (using built-in acls/exposing to local net);
- Purchasing: RMA,
supplies for conference;
- Added 2TB esata to nova
(burst group) - (some nfs4 issues w\ new kernel);
- ilog work (add
keywords);
- Usual move-related conf
issues.
Livingston
(Dwayne)
- Added rules to the spam
filter for LSC mailing list SPAM
- Xcode Dev Tools and
vPython on a MacBook for a user
- Installed Logger Pro and QuickCam software
on the SEC laptops; received
- Installed the locking storage cabinet on
wheels with electrical for the laptops
- Installed MS Office
Equation Editor on the SURF PCs
- More work on the SEC
building controls PC
- Received and assembled
a rack for the bake lab PC
- Began building a PC for
power monitoring software/hardware
- With Shannon, cleared
errors on a disk array attached to Baronne
- Investigating some
possible solutions to sharing iCal events
- Usual user support
requests
- Cleared spam trap
LLO mail summary for 5
July 2007 - 12 July 2007:
Rejected: 5,748(76
containing virus)
Accepted: 6,283
Total: 12,031
Hanford
(Christine)
- Making some real
progress moving users to the new disk system. I have disk quotas in place now for all
the large disk users.
- Noticed an increase in
ssh directory hack attempts. I modified the access list on the router to block
the source ip addresses of these latest attempts.
- Set up another PC for
the visiting teachers in the Staging Building.
- Added more ip addresses
to the DHCP list for this week and next to accomodate the teacher course.
- Other misc. user
support.
CIT
(Mike)
- Continued work on
finishing up a server to replace Canopus. I’m almost done with this project. Larry gave
me a hand with a latex issue I was having when trying to compile this
software.
- Helped Christian pick
up some equipment from Synchrotron to move Riccardo’s group out of that area.
This is old equipment that may be surplus.
- Ran additional network
cables in our server room 18 B/A to install additional servers in our computer
racks. Also re-routed some cables in Christian’s and my office to clear
up some network issues we were having. Christian gave me a hand
with this.
- Worked on a server
issue; this is our sandbox for Solid Works. It seems that ever since we upgraded to the
latest rev. of Solid Works 2007 we are now having problems running
S/W using remote desktop. Remotely the S/W software runs way to slow even
after making many tweaks to speed up the performance. The only software
that can run on this server remotely is Ansys & Algor, and this is
for analysis purposes only.
- Input more changes to
our ip/equipment database.
- Other misc. user
support/sysadmin tasks.
(Veronica)
- LSC: Ongoing
support of the July meeting. Addressed the issue of server security and migration, and
website configuration on the new machine. Updates of the
database of technical papers. Other website updates.
- LIGO: Addressed a
copyright issue per a request from a publisher. Additional copies of the
installation DVD. Updates of the roster application, other misc. web
updates.
(Christian)
- Updated the laptops
that are traveling to MIT with the latest security patches and virus definitions.
- 40 Meter- Hard drive
failure on visitors¹ workstation. Rebuilt new hard-drive with
our standard ligo image and
transferred all of the settings and data back to new drive.
- Tested the latest
Microsoft security patches.
- Mike and I are testing
webcam software for the meeting next week.
- Finally, got the
surplus equipment picked up. Larry and I spent time getting the people out to CIT and
assisted in getting the equipment loaded.
- Other misc.: Continued
onsite software/phone support.
(Larry)
- Worked a number of
procurement items. Tracked
down a couple of purchases and got them delivered. Tracking down
a recent UPS purchase
that should have arrived a few days ago. Updated a license contract.
Working on documentation
for past P-card purchases. Assisted Gina with a couple of
related items. Worked
with Florence in resolving a purchase documentation issue. Getting pricing on some new
switches needed for a couple of different areas.
- Spent time on the new
imap server. Fortunately, Erik found the problem in the config file and things are
now working. There are a few bugs to still work-out but we will start
moving people over to the new unit next week and build another server for
debugging/enhancement purposes.
- Setup a new website,
for short term use, and installed documentation for a group that Phil L. is
working with.
- Finally, got a disk
image off to Shannon for analysis.
- Setup a number of new
user accounts. New students and more visitors.
- Working with Christian
and Mike on getting a cheap webcam broadcast system setup.
- Resolved a couple of
mailman issues. Still having problems with some of the files updating correctly from
the automated system.
- Working on some of the
logistics for the LSC meeting.
- Still trying to get the
work in the computer room wrapped up. All of the work is now done but we are
having condensation problems with the new unit.
- Setup some new
licensing on a newer server. However, it will need to be updated the first of next year.
- Assisted Rolf/Alex in
getting a another computer for the 40M. One of the frame builder units was having
problems and needed to be replaced. We still have some shuffling to do
but they should have what they need.
- Regular user support.
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Systems
Modeling and Simulation
From: Hiroaki
Yamamoto hiro@ligo.caltech.edu
Static IFO simulation
(Hiro)
- Couple cavity code is
completed, and now it is used to study physics. First will be the
comparison of stable and marginally stable cavities, i.e., the
tolerance of the RM and ITM curvature matching which is very difficult,
almost impossible to realize for the marginally stable case. Studies of the effect of the
thermal deformations and mirror surface aberrations will follow.
Modeler : e2e
simulation engine and ALFI : e2e front end (Hiro, Bruce, Melody)
- Melody found a timing
when the static variables are overwritten during the process of linking
a dynamic library.
- She has implemented a
generic facility to workaround this problem. This made is possible to
build a UDP module which handles fields.
- Melody is adding
routines to support UDP modules which have delays, like DAC.
- Based on the conversion
of existing primitives, we found a few serious problems and have
(almost) resolved.
- More conversions of
existing primitives will continue to uncover issues to be solved before
the UDP release at the end of September.
Mechanical Simulation
for advanced LIGO (Sany and SLU team)
- Simple e2e code to test
outputs from various ports with a typical ground X motion fed into the
corresponding input port. Results of the test are being analyzed.
- The Open Loop transfer
functions of the Adv LIGO Mode Cleaner e2e model that we computed last
week indicate that the frequency control gain is too high as compared
with the MC length gain below the cross over frequency. We changed the
control filters and are about to analyze the resultant OLTF.
_____________________
Our LIGO-Related Science
Initiative (LRSI) workshop for teachers started this Monday on the
campus of Southeastern Louisiana University. We have 23 participants
from middle and high schools in our region (the North and South shores
of the New Orleans area). After covering topics of (a) measurement and
dimension, (b) gravity and kinematics, (c) mechanical wave and (d)
sound waves, the workshop seems to be quite successful. We receive a
number of feedbacks, including very good questions and comments on our
presentations from the participants. The participants have made several
demonstrators (miniature versions of exhibits installed in the LIGO
SEC) for the above topics that will be brought back to their schools.
CDS Prestabilized
Laser
From: Peter King
<pking@ligo.caltech.edu>
- I have fixed a minor
problem with the hour meter circuit relating to the trigger
level. It now correctly drives the hour meter. All other
functions work just fine (reset and power check).
- For reasons I don't
understand the computer touch panel will not work if a fixed IP address
is entered but it does when setup for DHCP. Another one for the
mystery books. I have made some minor progress in getting a
program to work under TwinCAT.
- The 35-W laser shipped
from LZH has arrived in the country. There is a hold up however
because an issue with some paperwork. Our customs broker informed
me that unless he receives an accession number from the FDA then he
cannot retrieve the laser from customs. In order to receive an
accession number a product report has to be submitted to the FDA for
approval. As a result I have been going over a product report and
having to find out what various definitions are as defined in the Code
of Federal Regulations Title 21 (CFR 1040.10). This paperwork is
needed soon otherwise
the laser will be moved to a federal, where presumably it will set next
to the Ark of the Covenant. I've consulted with Ed Jasnow about
this and he is helping to sort this out.
Control and Data Systems
From: Rolf Bork rolf@ligo.caltech.edu
OMC Controls
- Met with Peter and Rana
to review the CDS OMC controls for ELigo. Rack layouts are complete and
procurement/build process has begun. Plan at the moment is to have
single stage ISI components ready for shipment to Boulder to support
testing there in October. This unit will then ship to LHO in December
for integration with the ISC and suspension control components there. A
full OMC control unit is planned to be ready and shipped to LLO in
November. The site engineers have been asked to start looking into rack
placement and DC power feeds. Still an open issue is which flanges the
CDS control signals will hook up to on the HAM (being worked).
DAQ
- AdvLigo controls
prototype software has been updated to allow realtime front end
controllers to write to multiple FrameBuilders.
- Exploring the
possibility of having one FrameBuilder (FB) per IFO at LHO, vs the
present scheme of one FB writing data for both IFO. If this receives
approval, the idea would be to implement this prior to S6.
- Alex is working on a
GUI to aid in DAQ channel configuration.
Seismic Isolation
From: Ken Mason kmason@ligo.mit.edu
BSC Seismic
Isolation Assembly and Test
- We have completed the
assembly of stage 0 and placed it onto the test stand. The lower plate
was out of flat by .025" and had numerous minor dings. The flatness of
the bolted assembly came in under .010" over the 84" diameter with the
more important spring mounting areas considerably less.
- Arland Tool will be
delivering three more plates on Friday 7/6. The remaining two keel
plates will be delivered next week.
- Hugh and Myron are
inserting pins and bolting together the stage 2 optical plates. Our
plan is not to insert only the nitronic inserts that are needed for the
noise prototype and add additional inserts as needed.
- The stage 1-2 actuators
have been cleaned by Kyle Ryan and have arrived at MIT.
Single Stage HAM
Design and Procurement
- HPD has placed nearly
all parts on order with the keel walls and flexure post supports
completed.
- The maraging steel from
Dynamic Metals is scheduled to be delivered to HPD on 8/15. Since they
have already scrapped the first piece we are pursuing procurement of
enough material for three blades from another supplier as backup.
- The fabrication and
assembly drawings are nearly complete by HPD. Andy has spent
considerable time checking these drawings which should help minimize
fabrication problems for the first two Enhanced LIGO systems.
Suspensions
From: Norna
Robertson <nroberts@ligo.caltech.edu>
- Work on the design of
the beamsplitter (BS) /folding mirror (FM) triple suspension continues.
A draft of an updated conceptual design document for this suspension
has been completed and circulated to the ALIGO_SUS team for comment.
The design is going ahead assuming a wire suspension and a horizontal
wedge. It should be noted that the BS and FM suspensions will have the
same design. (The support structure will differ).
- Work on the OMC
prototype suspension is ongoing. Last week a test of locking up the
masses with their stops and releasing it again was carried out. This
revealed some procedural issues from the initial build (bolts not fully
tightened) which were corrected and noted for future builds. After
realignment the behaviour (mode frequencies, transfer functions,
impulse responses) returned to its original state. The MATLAB model has
been updated with current best estimates of as-built masses, moments of
inertia, wire lengths, "d" values and blade frequency info, and the
agreement between measured and modelled frequencies for the modes which
previously had the largest % differences (the lower pitch roll and yaw
modes) are now much better. The agreement is generally to a few
percent, with the lower pitch mode at 7%.
- Modelling of a single
pendulum suspension for the Arm Cavity Baffle is being carried out for
AOS.
From: Janeen Romie
<janeen@ligo-la.caltech.edu>
Advanced LIGO
Recycling Mirror
Suspension
- Working with Greer,
Bob, Calum and Norna on the structure design with respect to mass
budget. We are close to the mass budget goal and the suspension
structure first resonance requirement. Ian from RAL provided a pdf of
the assembly steps of the earthquake stop brackets and stops and Bob
incorporating that design for the recycling mirror. Calum has compared
Ansys to Cosmos results for the structure with non-suspended mass fea
and the comparison is good. They continue to compare fea results to
make sure the results are good. Calum reported that the carpenter shop
is making a full size wooden structure for us to check hand and part
clearances and to do an assembly walk-through.
Enhanced LIGO
OMC
- Bought various parts
and tools for the folks working on the output mode cleaner in room 056 W.
Bridge. Things are going smoothly for that suspension. Calum has
designed another metal bench that is similar to Sam's optical bench.
The wire interface is similar as well. It is with an outside machine
shop now for fabrication.
ELI Earthquake Stops
- Coordinated delivery of
the silica tips to Gary Traylor. Prototype screws should be done by
early next week.
- Worked with Norna and
Jay on the suspension risk registry and monthly schedule status for Carol
& Dwight. Particiapted in our monthly meeting with Carol &
Dwight with Norna and Helena.
From: k mailand kmailand@ligo.caltech.edu
- I'm working on a
faraday 4 wire dampened suspension test setup for Mike Smith. I have
spherical and ball bearing parts in a clean and bake cycle, to see how
they will perform dry I
have been working on an installation procedure for the large and heavy
arm cavity baffle.
Core Optic
From: GariLynn
Billingsley <Billingsley_G@ligo.caltech.edu>
- The CSIRO metrology
review is in progress and going well. One of the most striking parts of
their presentation are new dark field microscope images of different
types of polishing. I will obtain the images and put them
together with appropriate verbiage. The point of the presentation
was that our reliance on the microroughness measurement and the visual
inspection may not be enough to catch all of the surface
characteristics that can lead to scatter. In light of this we
will identify an appropriate substrate to send, which has been tested
by Liyuan, and see how this compares in their instrument. Another point
of the presentation was to highlight the different characteristics
imparted by different types of polishing. There is a new slurry
they are trying that appears quite interesting.
- During a lab tour we
learned about ozone cleaning, used in preparation for coating.
This process apparently removes all organics (given enough time) by
recombining to form CO2 or H2O. Time is related to intensity. This bears investigation for our
purposes as well. Anecdotally, the ozone is created by UV lamps
at a distance of ~4mm from the surface, which do not degrade the
uncoated or coated optic performance. We would want to verify
this at the levels of LIGO performance.
From:
Helena Armandula ahelena@ligo.caltech.edu
Advanced LIGO SUS
Silicate Bonding
- During my visit to
Glasgow University a couple of weeks ago I observed the testing of the
ear bonding fixture. One bond was made with it and it seemed to work
well. Testing of the bond will take place after curing. Using this
fixture looks very straight forward. I am in the process of procuring
and sending to MIT the lab items necessary for bonding.
- We discussed the issue
of de-bonding prisms, there is work to do in that area. De-bonding soon
after the bond is achieved can be done by immersing the bonded area in
an ultrasonic cleaner, but, after the bond has cured and has been
exposed to heat from the welding process it can not be taken apart.
A suitable procedure needs to be developed to replace an ear on a test
mass when a ribbon breaks and some re-work has previously taken place.
There is a limit to the number of times an ear can be reworked before
repeated welding destroys the welding tip.
Ribbon pulling and
welding
- We discussed the
possibility of separating the ribbon pulling machine and the welding
machine necessary for production purposes.
- Norna is assessing the
possibilities of doing this with Justin.
- The LASTI reaction mass
was shipped to MIT.
Advanced LIGO
Coatings
- CSIRO coated two more
substrates with Ti doped Ta, a sample to test "Q" was sent to Andri G.
They have the regular 30 - 1/4 wave layers of TiO2-doped-Ta2O5 and
SiO2. They have been annealed at 600 C for 24 hours. The TiO2 content
is about 20%
instead of the more than 40% we received last time. An absorption
sample will be sent to Stanford for measurements.
From: Liyuan Zhang
<zhang_l@ligo.caltech.edu>
No report
Auxiliary Optics
From: Michael
Smith smith@ligo.caltech.edu
SLC
Arm Cavity Baffle
- Norna has modeled the
motion transfer functions for the suspended arm cavity baffle. The
vertical bounce mode may be problematic. Mike is analyzing the vertical
to horizontal motion coupling caused by the edges of the holes in the
inclined baffle glass. A vertical spring to reduce the vertical bounce
frequency to < 1Hz will be incorporated into the suspension
structure.
- Ken discussed using a
temporary internal trolly mounted to the brackets inside the BSC
chamber as an approach for bringing the Arm Cavity Baffle into the BSC
chamber and moving it around to its mounting location.
- Luke will look at an
alternative design approach for the Arm Cavity Baffle structure using
light-weight tubing. The total weight goal is 50 lbs. He will also
investigate segmenting the glass pieces at the narrow section where the
hole is cut, to avoid the weakness of the glass at that section. The
approach will be to epoxy small tabs to the back of the glass that can
be attached to structural members behind the glass to support the
individual segments of glass. Luke contacted Ken Mason regarding
mounting holes in the HEPI support ring in the BSC chamber for mounting
the suspension point for the Arm Cavity Baffle suspension. The
installation of the Arm Cavity Baffle at LASTI will probably occur
after or during the testing of the quad suspension prototype.
BRDF measuring apparatus
- Dan Riley made a SW
model to show that the scattered light from the specular reflection
beam dump can be reduced significantly by taking advantage of the
imaging properties of the light collection scheme.
- The mounts for the
holey mirror and the aperture are complete. The fixtures for drilling
the hole in the mirror are complete. Purchased parts were received. Dan
has coated the mirror surface with clear lacquer and is preparing to
drill the hole.
Input Optics
No report
For
additional information about this report, contact Albert Lazzarini or Phil Lindquist