Weekly Report for Week Ending May 31,
2007
Past Weekly Reports
There
will be no LIGO Executive Committee scheduled Monday, June 4, 2007 because a number of key personnel
will be involved in or traveling to other meetings.
Special
Announcements:
Weekly Report
Highlights
LSC Issues (Reitze)
- The second joint LSC-Virgo meeting (and the
first to be hosted by Virgo) was held in Cascina, Italy last week. By all
measures the meeting was a success, with approximately 130 registered
participants; roughly half of the attendees came from the LSC.
Highlights of the five day meeting included a press conference to announce
the beginning of the first Virgo science run and joint running with LIGO
and GEO as well as a site visit to Virgo for the LSC attendees.
Meetings of the joint run planning committee and data analysis council
were held to continue developing scenarios for post-S5 planning. In
addition, there were many reports from analysis groups and instrument
science groups, including a report on the status of the GRB070201 search.
- The LSC has kicked off a congressional letter
writing campaign in support of Advanced LIGO. As of this writing,
approximately 25-30 letters have been sent. Approximately 100
letters will be needed to be considered effective. If you are
reading this and haven't done so, please take the time to write.
- Planning is underway for the next joint L-V
meeting to be held at MIT on July 23-26.
LIGO
Laboratory Administration (Lindquist)
STATUS OF LSC MOUs
(Lloyd)
PROPERTY MANAGEMENT (Luna)
>From: Rod Luna
<rluna@ligo.caltech.edu>
- Working with Rolf Borke
tp close and tag three Fabrication Accounts.
- LIGO.DAQ-3-NSFLIGO.FY02CA
LIGO.DAQ-2-NSFLIGO.FY02CA
- LIGO.DAQ-1-NSFLIGO.FY02CA
Provided
assistance to the Detector Group (H. Armandula) with shipping and the preparation of a
Commercial Invoice for US Customs Clearance of eleven Fused Silica
Substrates to CSIRO in Australia.
Account Number LIGO.OPT - 5.4 - NSFLIGO.FY02ON. Created a
requisition for 21 linear voice coil actuators for Ken Mason @ MIT.
Account Number LIGO.HAMCH-5.9-NSFLIGO.FY02CA $203,000.00
- Working with our broker in getting the
Cylindrical Components shipment for Bob Taylor through US customs.
DOCUMENT CONTROL CENTER (Turner, Mak)
>From: Cleveland Mak
<mak_c@ligo.caltech.edu>
- Continued to process presentations from the
LIGO/Virgo Collaborations Meeting. Worked on trying to identify the DCC
numbers from a list of past year's publications that had no referenced
document numbers. A handful of these papers never made it into the DCC
database.
- Scanning Update - Progress continues on the scanning of all
non-electronic "M" category documents.
Document Management System - Plan B
(Lindquist)
I have no new information to report.
FINANCIAL SYSTEMS (Funaro,
Brambila, Kaufman)
>From: "Funaro,
Catherine" <Catherine.Funaro@caltech.edu>
>From: "Brambila,
Ruth" <Ruth.Brambila@caltech.edu>
- Received the signed mod for Katherine Creath. Inquired and responded to her inquiry
pertaining to the dba name on her file. Resolved
inquiries regarding tax statuses, credits for overbillings,
submission of a duplicate invoice which should have been non-taxable,
delivery inquiries, and order statuses. Responded to inquiries on
active encumbrances. Requested for corrections to be made on
invoices processed as invoice attached, and requested new vendors to be
set up. Closed out completed purchase orders and submitted the monthly
report. There are two pending p.o.'s open one of
which has an outstanding invoice which has been submitted. The
second p.o. shows as unpaid, however, the vendor
stated that the order has been paid. I am waiting to hear back from
Payables. The backordered item on that order had been cancelled by
the vendor. Completed the modification for High Precision Devices and
routed for approval. Received the updated certs
for Hereaus and inquired whether a name change
needs to be made to match the vendor's response. Followed up and received
the signed modification for LSU. The vendor is not submitting an
A-133 for this subcontract. Waiting for the Debarment Cert from ANU to
issue the order. It is expected to be received by Monday. The
request for the certs was sent to PSI. The
certs have not been submitted. I am
working on the order so that it is ready to go by the time the certs come in.
- The order for the 4 plates has been placed.
The vendor informed me that they are still waiting for the drawings
for the modified ports. He expects to receive the drawings within the next
1-2 weeks to meet Aug/Sept. '07 delivery date.
>From: Florence Kaufman <fkaufman>
- Submitted 4 new fabrication requests for Peter
King.
- Continued working on clearing up encumbrances
that need to be closed.
- Submitted requests to close fabrication accounts
where work has been completed.
- Checked on status of fabrication account
requests previously submitted, approval has been delayed because Lucy Molina
has been out of the office. She indicated that she will try to get
to them as soon as possible.
- Financial reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone
<gsalone@ligo.caltech.edu>
- A contract is being prepared for Planning
Systems, Inc., (PSI) for the production of the seismic isolation actuators
for the HAM at LASTI. PSI successfully built the prototype
actuators, and is now being awarded the production contract for LASTI.
>From: Ed Jasnow
<jasnow@ligo.caltech.edu>
- We received an e-mail approval of the HPD
HAM-SEI contract from John Villalpando of the
NSF. As a result, the contract was FedEx'd
to HPD on May 30 for their signature. Upon its return, it will be
executed here at Caltech, and a fully executed contract will be sent to
them. The NSF review resulted in a two-week slippage of the contract
schedule.
- The Caltech Office of General Counsel is
continuing to work on acquiring legal representation and consultant
services for LHO concerning the attempt by Northwest Wind Partners to
build a wind farm near the observatory. The current plan is to have
Pamela Krueger, who served as our attorney last time from Perkins Coie, serve as a consultant, with another associate
from Perkins Coie in a supporting role. A
teleconference is scheduled next week among David Flores, of OGC, Ed Jasnow, Fred Raab, and Ms.
Krueger to confirm this arrangement and discuss strategy regarding the
evaluation of test data generated by Northwest Wind Partners.
PROPOSALS and REPORTS (Lindquist)
Trying to assemble first
draft of the Continuing Operations Proposal (FTY 2009 – 13). Our objective is to have a draft for review by
the PAC by the end of next week. An outline of the text with status and
links to the text has been provided on the Operations Proposal Web page.
Please see me if you need access.
CHANGE CONTROL/CONTINGENCY MANAGEMENT
(Lindquist)
I will put the following change requests on
the agenda for a meeting of the LIGO Change Control Board as soon as
possible. This is likely to be scheduled during the week of June 11.
- Change Request CR070004 submitted by P. Fritschel and D. Coyne requests the release of FY 2007
and FY 2008 budget to cover a priority subset of the Advanced LIGO
"wish list" items.
- Change Request CR-070005, submitted by M. Zucker, D. Ottaway, and R. Mittleman, requests funds to replace the aging main
turbo pumps for the LAST facility at MIT
- Change Request CR070006 submitted by M. Zucker modifies the budget for Advanced LIGO, Enhanced
LIGO (ELI) Fabrications.
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa
<cindy@ligo.caltech.edu>
- The next Staffing Committee meeting is scheduled
for Monday, June 18, 2007.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
- I have nothing significant to report.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of S5
Activities at LIGO Hanford
Observatory (compiled by M. Landry)
This week H1 ran in science mode for 93% of
the time, with typical ranges of 15Mpc. The H2 duty cycle was 84%, while inspiral ranges were more variable due to the same noise
(below) observed over the last two weeks. Typical H2 ranges were about
7Mpc. Some loss of running time on both machines was due to high winds
on Sunday evening, while commissioning hours were logged on H2 (spring
compensation, below).
Some S5
highlights from the LHO elog are bulleted below:
- summaries: Tuesday maintenance,
CDS maintenance,
most recent range
& duty cycle weekly
a new H1 downtime (uptime?) pie
has been produced for nearly all of S5 (up to May 27 this year)... up 77%
of the time, the largest impact on duty cycle is "Other"
(commissioning plus miscellany). Tuesday maintenance accounts
for 2.2%. periodic H2 mystery noise continued to plague
the machine, but not as frequently as previous weeks photon calibrator
photodiode (and DAQ) response was found to be flat
to within 1% from dc out to 300Hz
using the full inspiral waveforms with ringdowns, a test of the blind
injection mechanism was made on H2 H2 RM
coil monitors glitch at times when H2 noise is high.
An electronics checkout
found nothing particularly out of place, yet
- spring compensation for future high power
operations was tested
on H2
LIGO Livingston Observatory (LLO) and
Interferometer Operations (Giaime)
S5 run (Antonio Lucianetti)
- During the last week, L1 collected 75.1 percent
science data. The binary inspiral range
varied between 12 and 15 Mpc, depending on seismic motion.
- On Wed May 23, Thurs May 24, and Fri May 25 we
had three commissioning breaks to
continue our investigations on the DC readout scheme and on the pOMC properties. Every day except Sun May 27 and Mon May
28 (Memorial Day), during daytime, logging continued near the X-end station and caused the
binary inspiral range to stay below/equal to14 Mpc.
CDS computing (Lisa Bogue)
- worked on blind injections software.
- began working on security planning with Dave.
- began building a hot backup for llo1.
LIGO
computing and network security (Roddy)
Reported
under General Computing, see below
General
computing and LDAS admin (Giardina)
Reported
under General Computing, see below
Reported
under LDAS System Administration, see below
Data
analysis & computing (Yakushin)
Storage/Condor/LDAS
admin: Reported under LDAS System Administration,
see below
Data
analysis: Reported under Data Analysis activities, see below
Mechanical and Optical Systems (Coyne)
See Advanced
LIGO
Controls and Data Systems (Bork)
See Advanced LIGO
40-Meter Interferometer (Weinstein)
There
will be a meeting of the 40meter Technical Advisory Committee (TAC) on June 7th
at 08:30 Pacific. At Caltech, we will meet in the SCR. All interested parties are invited. TAC chair Ken Strain says: "Due to
significant changes that have happened or are happening soon, we should try to
take a long term view of the 40m plans this time round. In particular we should look at how the tests
needed for the current projects (such as DR readout, new sensing schemes) fit
with longer term activities (squeezing, other configurations work). Of course we should also have the technical updates
as usual."
IFO Commissioning,
Electronics, Controls, Computers
- Tobin and Rana worked
on restoring lock of the power-recycled FPMI with DC readout. They ran
into a variety of snags, mostly associated with alignment (and some electronics
noise from POX), so they realigned the optics and the oplevs,
and are almost back to full lock; work in progress.
- Tobin built a little contraption to measure RF
oscillator amplitude noise, and took a spectrum of the relative amplitude
noise of the Marconi RF generator from 100 Hz to 100 kHz; it falls from
5e-7 to 5e-8.
- Tobin and Steve did a shootout of three
different HeNe lasers, measuring their RIN for
use as oplevs. The new JDSU model 1103P had the
lowest RIN by far (10^-7) up to 550 Hz. Sam suggested repeating the test
while swapping power supplies to see if that's responsible for the large
differences in RIN between the different lasers.
- Rana is working on retiring op140m by moving all the
directories off of it; Alex will move the YP server off of it, and then it
will be shut down. If it isn't missed, the box will be removed and used as
spares for the computing group.
- Bob tested the eLIGO
OMC glue joints made by Sam; they all look good on the RGA, and they are
now in the cavity ringdown test system. Sam will
be working on the SP table to set up some OMC optics tests.
- Rob returned from S5 shifts to find that the RGA
logger was down. He restarted it, and he suspects a flaky cable or
connector on the iServer, or on the ethernet hub in the EY rack.
DC Detection
- Rob has been on S5 shift at LLO, so no progress
here.
Vacuum
Squeezing
- Go is writing his thesis and preparing final
draft of the squeezing-enhanced interferometer paper.
Lab
Infrastructure, Bake Lab
- We are preparing for the arrival of 5 SURF
students, and making sure thare are working PCs
for them.
Thermal Noise
Interferometer (Black)
- Ilaria is making good progress debugging the mode
cleaner. She had tried to find the arm-cavity axes earlier without
success, and we discovered that the mode cleaner was having problems and
needed to be realigned before we could work with the cavities. This week,
Ilaria successfully aligned the mode
cleaner to lock in the TEM00 mode, with about 90% visibility.
- Riccardo is visiting LMA and has asked them about the
progress on our optimized-coating mirrors. They are still having
trouble with fabrication. They have apparently found a workaround for
periodic coatings, but they do not yet have a solution for aperiodic coatings.
LASTI (Mittleman)
No report
CIT
Science Group (Weinstein)
_________________
Gregory Mendell:
- In the last week I responded to a long list of
internal comments from the pulgroup about the S4 PowerFlux/StackSlide/Hough
paper, and checked the changes into
the pulgroup CVS repository.
_________________
Kent Blackburn:
OPEN SCIENCE GRID APPLICATION ACTIVITIES:
- Organized weekly teleconference and agenda with
Pegasus developersAttend weekly LIGO-Pegasus and
DASWG teleconferencesContinued troubleshooting
of problems running workflows for the H(t) binary inspiral analysis on
OSG sites:
- discovered disk space issue at LIGO_CIT_ITBregenerated sites.xml
and tc.data cataloguesdiscovered
problem with L1 Data transfergenerated workflow
using H1 and H2 data onlymodified properties
file
- checked and fixed several typos
- H(t) binary inspiral
workflow analysis:
- modify segment files to generate workflows of
different node sizemodify
template bank parameters to generate workflows of different durationrun
workflows an ldas-grid and LIGO_CIT_ITB
- compare runtime and diskspace
usage
OPEN SCIENCE GRID INTEGRATION TESTBED
ACTIVITIES:
- Updated several components of the Caltech ITB site.Discovered one of the reasons that binary inpiral workflows were failing early on was from
filling up the temporary disk space used for staged data. Cleaned the
disks space up and workflows progressed successfully beyond the first
attempt to transfer data onto the ITB.
- Tracked down subsequent problem with LLO data
being transfered onto the ITB site due to
all the tape drives on the CIT LDG archive being used for other
activities. To resolve this worked with Britta to change workflows so
that data is staged in from Penn States' archive. Tried similar
staging from UWM but found that certificate's DN wasn't in all the
necessary gridmap-files.
OPEN SCIENCE GRID MANAGEMENT ACTIVITIES:
- Reviewed agenda and discussed plans for upcoming
OSG meeting with new Science Advisory Committee (SAC).Continued
discussion of year two planning for the OSG both for the Caltech
Statement of Work and for the Resources Managers.Discuss
year two science milestones to the OSG with the LSC Computer
Committee to initiate discussion of some of points raised in the
email circulated by the LIGO OSG Council Person.Attended
OSG Executive Board meeting.
- Circulated announcements of the OSG Users and
Applications Workshop to the LIGO-Pegasus, DASWG email lists.
_________________
Patrick Sutton:
- Most of my available time this week was devoted
to working with Siong Heng
on getting X-Pipeline ready to run as a coherent follow-up test for Q
pipeline in the all-sky untriggered burst
search. We succeeded in getting test X-Pipeline jobs to run
following up a few Q triggers. Also, Vicky Kalogera
and I have taken over responsibility from Szabi Marka for editing the GRB07020 paper.
Laboratory
Computing (Anderson)
- A problem with frameCPP not properly
decompressing data when the byte order of the frame file was not that of
the host system has been resolved. The battle for understanding with the diskcacheAPI dead lock continues. The use of mdb and dtrace is being pursued.In
the managerAPI, the bootstrapAPI
proc has been modified to check if diskcacheAPI is down. If so, manager can reboot it regardless. If not, resource WAIT_FOR_API controls whether
manager should hold off rebooting or not.In
the genericAPI, fixed getPid
to compare the first 8 chars of program name against ps
results as ps only returns 8 chars for fname.
- Performed system testing on dev 1.8.561. RDSVerify
reports of frame gaps when run with /archive and /data
in mount points but passed without them. lsync passed without /archive and /data.
- rsync builds from dev to test and run in parallel with dev. ldas-test runs happily without errors with the latest build from dev
and also the fixed dmt
script. But diskcache
shows a leak of 10.647 KB/sec ( +/-
0.007 KB/sec ) 174.177 KB/job which is not seen
on dev.
- fixed dmt test script insertTrigsLoop.test
to open pipe to SeqInsert to
capture it's output for parsing. If
the job has been submitted, then send another else wait. Due to
the large set of mount points and slow job
completion rate, dmt was barely running to completion and got restarted many times
when there are errors resulting in invalid
parent key errors. Now dmt is more coordinated with the job
processing rate of ldas. Also modified dmt to
just create SeqInsert server once instead of each loop of the test.
LDAS System Administration (Anderson)
Caltech
(Dan Kozak)
- Continuing to verify md5sums for data on tape to
detect bit rot and to allow us to relabel tapes.Confirmed that gettapes
run with the right glob was getting the same metadata as when it was first
run (and tapes ejected). Waiting on Greg's gap checking to make that this is _all_ of the data for the week.Filled in raw data (some caused by gettapes problems, others by need to rearchive data at LLO and reship due to a bad
tape).Consulted with Igor on correct installation of Solaris fibre channel patches.Removed
interim (IDR) fibre channel patch from ldas-cit/dataserver-cit and replaced with production patch.Worked on lag plot generation to make it easier
to add/remove data sets from the graphs. (This hasn't gone live
yet.)Wrote /var/sam/virgomv to verify and move
Virgo data from /archive/virgo to it's final
resting place in /archive/frames.Worked with StorageTek on getting a bad 9940 replaced.Generated
list of tapes for relabelling at LLO (some of
them still need to be moved into the silo before then can be relabelled).Generated list of tapes for shelf storage
at LLO.Did some cleanup work on our archive sets
and added a new one for h(t) L1 data.Relabelled 27 L1.2 tapes at CIT.Consulted
on L700 problems at LLO.
- Did some work on LDR problems both kicking it to
get it running again and generating full-update dumps for PSU.
(Phil Ehrens)
- Helped Erik Espinoza update firmware on cluster nodes.Moved the LDAS workstation m8 from it's unused location in Bridge to the cubicle occupied
by Greg McIvor.Discussed integration of the PSU
Attachment X database with the MOU webforms
project with Sam Finn via email.
- Began installing pre-release version of MOU webforms project onto betelgeuse, which will be it's home under the
alias "mou.ligo.caltech.edu".
(Erik Espinoza)
- Expanded Condor spool directory on ldas-grid.Upgraded Condor on cluster to 6.8.5.Migrated
cluster from nfs Condor install to local rpm install.Configured ldasadm1 for OS Committee testing
w/ Ubuntu.Upgraded Cluster 3ware BIOS.Submitted ticket to condor-support for dag concatenation issue.
- Worked with Livio to
get data transfers working with Virgo.
MIT
(Fred Donovan)
- More ldap work on ligo-burst cluster; (proxy ldap,
user account cleanup).
- test/replace various disks lying around (cleaning up equipment).
Livingston(Igor Yakushin)
- SUN analyzed core dump files left from the
recent crashes of gateway and dataserver
machines and confirmed that both were due to the bug 6518348 and
recommended the patches that we just installed ourselves: 125184-02 and
119130-33.Ordered replacement batteries for UPS.The
replication of segments from CIT to LLO is broken.During
the weekend the tape robot got stuck couple times and had to be powercycled.Installed fiber channel card into the new
X4600, patched it and installed QFS 4.6.
- Running burntest on
the new X4500.
(Dwayne Giardina)
- Tape eject for shipment to CIT.Tracked
down a list of old tapes to be reused.
- Replaced power strips on another rack of nodes.
Hanford
(Greg Mendell)
- All RDS and trend data is up-to-date at LHO, LLO,
and CIT. I have sent a list of segments to Keith Riles to update the
segment database with three new short (<=384 s) real gaps that appear
in the LLO data. One is from a Tue. May 8 maintenance period,
and two are from the Mon. May 14 power failure. All are due to times when
both framebuilders were down.
(Ben Johnson)
- Got price quote for node power supplies from
ASA. Will order 10 today.3511-2 had a single disk
failure, but is otherwise functioning ok. Sun is shipping replacement
parts.ldas-pcdev1's HDD finally failed completely. It was replaced, the OS
reinstalled and its package revs brought to sync with ldas-grid.
- Continuing development of LDAS NDS server. My
basic threading + job queueing model has been
tested. I am currently working on the command parser.
General Computing (Wallace)
MIT
(Fred)
- Setting up another dual boot(xp/fc6) for grad studentMonitor issues (solidworks,
aspect ratios)Finished up LDAS/LATSI security reportLicensing
updates(matlab 2007), solaris
ldap client (tls)
working
- Listing offices/ip
addresses for upcoming move; imap tweaking
Livingston
(Dwayne)
- Installed FC6 on a laptop for Natalia, and fixed her wireless problemPatches
on quagmire, created a new DB for Shannon's useCreated
a GC user account for a SURF studentInstalled a UPS
on a couple of computersDreamweaver issues on a
user PC. site settings had been lost, now restoredTroubleshooting lost network connection in an office yielded a
hub with no powerReplaced
a bad cat5 on a printerWorking on trend
graphs/reports on SEC building controls PCApplied
windows patches to kantech serverUsual
user support requests
- Cleared spam trap
LLO mail summary for 10 May 2007 - 17 May
2007:
Rejected: 6,507(502 containing virus)Accepted: 3,694
Total: 10,201
Hanford
(Christine)
- Working with ESnet to
design the BGP peering configuration. Right now looks like we will be ready to test on June
5th.Purchased a new laptop and monitor for a user.Started
setting up computers for the SURF students and other summer visitors.Finished installing all the matlab
patches on Solaris computers and am now
running Matlab 2007a as the GC default.Removed user accounts for a contractor no
longer working for LIGO.Investigating apparent
problems with MRTG not reporting all the bandwidth usage.
- Configured the backup network circuit on the
router. There are link lights
all the way through to ESnet in Seattle. This will be tested
when testing the BGP setup.
CIT
(Veronica)
- LIGO: Ongoing updates of the upcoming NSF
and PAC meetings websites. Helped
Dwight Carter with web-related and general computing issues. Finalized the LASTI installation DVD; it has
been shipped to MIT. Provided a
high resolution image for a print publication. Website updates.
- LSC: Posted the bulk of the presentations
from the last meeting. Started
working on the website for the next meeting in July. Updates of
the database of technical papers.
(Christian)
- Gina Salone- Upgraded
hard drive and added additional memory on Ginašs workstation.Florence
Kaufman- Installed Visio 2003 and Adobe Acrobat 8.Rod Luna- Installed
Adobe Acrobat 8.Bill Tyler- Working on upgrading Billšs workstation from
Windows 2000 to XP.James Covington-
Installed new DVD writer.40 Meter- Computer donšt boot. Working on
replacing old system with new.Continue working
with the installation on WSUS clients for LIGO users.
- Other misc.: Continued onsite software/phone
support.
(Mike)
- Working on upgrading 2003 server (deneb) came across many
issues when trying to upgrade this
server. Larry ordered some
additional memory to get this upgraded and back into service.Ran NTSRV End of Month ghost backups.Additional
work on a Sun box downloading packages that are needed to put this server in service. This is an on going
project.
- More work supporting new SolidWorks
users.
(Larry)
- Went through a number of purchases. Most of the
misc. items and one of the
workstations has arrived. Worked
with Gina and group on a couple of different procurement/contract items. Need
to order a couple more workstations and monitors for different groups.Worked with Mike and Christian in upgrading the
memory on a couple of computers.
Still waiting for new memory for one of the units. One workstation needs to be checked out, it appears to have a problem with one of the boards but will have to wait until
the end-user can give up the box
for a few hours.Debugged a number of web items
for different people. Mostly getting the correct files in the correct locations and the correct syntax on
the url's took
care of most of the problems.Performed the
monthly backup on the home accounts.Moved
another home account over as part of the check for missed items.Setup a couple more new users accounts. Cleaned
up a couple of other accounts.Continual
work with the construction people and PMA on the room modifications. The air-conditioning should be
finished by the end of next week.
- Usual user support; fixing files, printers and
cabling.
Advanced LIGO and
Supporting R&D (Shoemaker)
Advanced
LIGO Systems
Modeling and Simulation
From: Hiroaki Yamamoto hiro@ligo.caltech.edu
Static IFO simulation (Hiro)
- Coupled cavity code is being optimized to run
faster.
- Thermal deformation code used in the code has
been tested by John Miller.
Modeler : e2e simulation engine and ALFI : e2e front end
(Hiro, Bruce, Melody)
- Essentially all known issues of modeler and alfi related to UserDefinedPrimitive
(matlab mex file
equivalent) are addressed. Bruce
and Melody are preparing examples and writing documentations.
- Last week, Hiro
revised triangular cavity code so that frequency control servo can be implement. Executables on Caltech machines are updated.
Mechanical Simulation for advanced LIGO (Sany and SLU team)
- Continued working on AdvLIGO
e2e modeling. With the summation cavity model (called TriCav)
that Hiro modified last week, the locking
performance is much better. There is some uncertainty regarding the
computation time step (related to the way the summation cavity model
handles time derivative). We are testing this effect by running the same
Mode Cleaner model with the standard e2e time step on the order of 10
micro sec and an order of magnitude smaller time step (1 micro sec).
CDS Prestabilized
Laser
No report
Control and Data Systems
No report
Seismic
Isolation
From: Ken Mason kmason@ligo.mit.edu
BSC Seismic Isolation Assembly and
Test
- Riccardo Desalvo took FTIR
samples from the large parts cleaned at Galli
& Morelli. The samples arrived at JPL and we
should get the results on Friday.
- The scaffolding which will go around the test
stand has arrived at MIT and is being cleaned by Myron and Bob.
- The ADE position sensors have returned from calibration
at the factory and are being prepared for cleaning.
- Rolf, Jay, and Alex will be coming to MIT
between 6/11 -6/22 for electronics and software installation.
Single Stage HAM Isolation System
- HPD has completed the assembly drawings,
fabrication drawings, and assembly procedures. Andy Stein has been
checking the drawings. A FDR is scheduled for 6/5 to review the
documentation package.
- The purchase order to HPD for the fabrication of
two systems has been approved by the NSF and will be sent to HPD soon.
- The actuators, GS-13 seismometers, and ADE
position sensors have been ordered for these systems.
From: Brian Lantz
<BLantz@stanford.edu>
SEI telecon notes,
Friday, May 25
HAM contract status
ˇ
verbal OK in from NSF on Thursday, written approval should
be in Friday (5/25) M Zucker & K Mason putting
together contract for HPD for next week.
- table size, cutting corners? Rich Mittleman points
out that it will be difficult to get the HAM doors on and off with the table corners sticking out. Dennis
says (on 5/29 call with HPD) to leave them there, because the optical layout
guys have already used some of that space
for dogs for various optical suspensions.
Progress on the BSC
cleaning status -
- G&M parts scheduled to be done about now.
Then we have to wait for FTIR. Riccardo will do the test.
- Other parts coming back from Caltech to LASTI
- new LASTI scaffolding in
- new 16" flange with 7 x 4.5" flanges
installed
- Ben will ask Bob Taylor to test the
- Tungsten carbide carbon (Balzers)
Trade name ~balanite-B
- Nedox (passed RGA)
- cap sensors ??
- actuators, 80 deg bake didn't get clean enough will rebake at ~150C?
ISI electronics -
- Layout for ETF AA and AI board to be done today
(5/25). Parts should be back next week, panels should be out today. ISI interface
boards almost stuffed, will test next week
- STS-2 interface to be stuffed next week
- AA and AI chassis tested and ready to go.
- MIT should already have a binary IO interface,
and STS-2 board. Please check this.
- still waiting to hear back from SRI hermetics, about the 3 pin feedthrough
for drive. (this is an alternate)
pods at LLO -
- cleaning mostly done
- Ben will send a second readout box, all GS13s seem OK with corrected connectors.
- STS-2 about ready for putting into pods.
Seismometry and Corner station SPI
- seim. noise plots for ground motion still in
progress
- SPI freq noise measurements unbalanced arms 10
cm didn't see noise.
- computer: Rich M and Brett S have worked with quack5 to
fix it up. WARNING: must test
filters after digitization with Matlab sometimes
the digitization process returns crazy results. A bode plot is sufficient
to see that it has gone wrong, or the mag/phase
of a few points wrt the original continuous time
version will show if the c2d process was successful. Also, must test the foton filter after installation into foton. Not sure of the best way to do this part.
Suspensions
From: k mailand
kmailand@ligo.caltech.edu
Adv. LIGO
- All LASTI installation tooling assemblies
arrived at LASTI
- A video document was made describing the
operation of each assembly and sent to Myron.
- I finished a layout of the faraday assembly
suspended in an LOS, and the pick off telescope,
for Mike Smith.
- I'm working on the pick off mirror suspension.
Core Optics
From: Bill Kells
kells@ligo.caltech.edu
- We (with L. Zhang) have continued pursuit of
imaging the beam spot illuminated surface of HRs
in air now with some success. It has been possible to cleanly see the sort
of "globular cluster" pattern that is typical of the LIGO I
surfaces under resonant cavity illumination. Having now established that
this technique works we want to integrate it into the ongoing studies of
surface scatter. Our principle background, uncontrolled at this point, is
the fresh accumulation of dust on the HR surface: each recleaning
of the surface results in substantially different patterns.
From: GariLynn
Billingsley <Billingsley_G@ligo.caltech.edu>
- Four fused silica substrates have been
characterized using the Fizeau interferometer at
Caltech. These substrates are to be used in an annealing study at
Hobart and William Smith. They will be mechanically characterized,
then annealed then recharacterized both at
H&WS and CIT
From: Liyuan
Zhang <zhang_l@ligo.caltech.edu>
- We did a scatter test for the First-Contact (FC)
protection using the current integrating sphere set-up. Helena applied the FC on half of a SPETM. A scan of 2mm (w) x 40 mm (l) crossing
the FC border was done two times before and after applying the FC. By
comparing the two scans, we don't see any FC
induced scatter in the systematic error range of about +- 0.5 ppm. We may do a similar absorption test in a near
term future.
Auxiliary
Optics
From: Phil Willems
willems@ligo.caltech.edu
Photon Calibrator:
- Stefan Hild and I
reviewed his article describing the calculations and measurements of the
corrections to the recoil displacment amplitude
during photon calibration due to the elastic deformation of the test mass
under localized photon pressure. We generated an improved FEM of the
effect that gave good agreement with both the analytical approximation of
the elastic deformation and with the experimental data from GEO600.
Thermal Compensation in LIGO:
- Tobin Fricke performed simultaneous in-loop and
out-of-loop measurements of the intensity noise of our stabilized CO2
laser and found that the out-of-loop PD saw excess noise below 400 Hz,
likely due to beam jitter. The laser is not so rigidly mounted and
so we are looking to improve this first.
- While at the Virgo/LSC meeting in Cascina I learned a great deal more about how Virgo
relates test mass frequency shifts (and other data like arm cavity power)
to optical absorption in the test masses. With Alessio
Rocchi of the Roma Tor Vergata
group I am applying the full Virgo model to LIGO test masses.
Mesa Beam Research:
- John Miller is has calculated how the arm cavity
deformations due to optical absorption would distort a mesa beam
resonating in the cavity. For absorptions above about a watt the
mode shape becomes substantially non-flat-topped. However, the
thermal noise of these distorted modes is calculated to be even lower than
for the undistorted mesa beam. We are trying to independently verify
this surprising result.
Input Optics
From: David tanner@phys.ufl.edu
Wan Wu:
- The test of the wedged crystal modulator has been
finished and current measurement sensitivity is limited by the phase
meter.
ELIGO stuff:
Luke Williams:
- Working on the in-vacuum FI layout for ELIGO
Rodica Martin:
- Thermal lens measurements on DKDP for ELIGO
Antonio Lucianetti:
- Measured the rotation angle for a TGG along the
magnet axis of the compensated Faraday for ELIGO. The incident laser power
was 1 W. The angle varied from zero to +23 degrees as the crystal was
moved along the axis. (22.5 degrees will be
the amount used in the application, as there are two crystals in this
design.
For additional information about this
report, contact Albert Lazzarini or Phil Lindquist