The LIGO Executive Committee Agenda for Monday, Monday, April 16, 2007 will be: Status of proposal for LIGO Continuing Operations
(Meeting time: 10:30 am Pacific Time)
1. Announcements
2. Programmatic (Marx)
- Review of Financial Status of LIGO Operations
3. Comments on Weekly Report
4. LSC Issues (Reitze)
5. LIGO Lab Operations
- Administration (Lindquist)
- Sites (Raab, Zucker, Shoemaker)
- Commissioning (Fritschel)
- Optical and Mechanical (Coyne)
- Control and Data Systems (Bork)
- 40m (Weinstein)
- TNI (Libbrecht)
- LASTI (Ottaway)
- Lab computing (
Anderson
)
- Data Analysis Group (Weinstein)
- Instrument Science (Gustafson)
- Science Group (Weinstein)
6. Enhancements (Adhakari, Zucker)
7. Advanced LIGO (Shoemaker)
8. Change Control Board/Technical Review Board Session as needed
- There are no open change requests
Site and other Business Issues:
- P-Card training at LHO. Any requirements for LLO?
- Site staffing status.
- Schedule for LLO bookstore/ gift shop process resolution.
- Property Management
- Wind farm proposal near LHO
Special Items:
Special Announcements:
Weekly Report Highlights
LSC Issues (Reitze)
- The
LSC Executive Committee met on Thursday and approved all of the
observational results talks for the upcoming April APS in
Jacksonville. In addition, the S3/S4 inspiral paper was approved
for publication pending a few minor changes.
- The
S4 burst paper, "Search for gravitational-wave bursts in LIGO data from
the fourth science run" was posted on ArXiv this week.
- The
April 2007 issue of Physics Today had a brief report on the LIGO-Virgo
data sharing agreement in the 'News' section of magazine.
- Plans
continue for the May LIGO-Virgo Meeting in Cascina. A web site
announcing the conference details is expected to be up next week.
LIGO Laboratory Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
- The University of Washington was completed with Attachments OPS and Z, and was posted and will be submitted to the DCC.
PROPERTY MANAGEMENT (Luna)
>From: Rod Luna <rluna@ligo.caltech.edu>
- Worked
with the French Customs Agency in providing supporting documents to
clear the export of a Fused Silica Substrate to VIRGO, France.
- Coordinated the disposal of old monitors. Account Number LIGO.DAT-1.5.3-NSFLIGO.FY2ON.
- Provided
assistance to the Detector Group (K. Mailand) in making arrangements to
ship a crate (49 x 32 x 52 600 lbs) to MIT.
- Met with Jay Marx, Albert Lazzarini, and Ed Jasnow to discuss property management for LLO.
DOCUMENT CONTROL CENTER (Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
- Processed
some LSC presentations that came straggling in this week. To
date, 70 presentations have been received and an additional 32 are
still to be submitted. Final reminders will be sent out tomorrow
to those authors still needing to submit presentations.
OTHER ACTIVITIES
- Finished
compiling an electronic database of existing paper-based record of
incident reports. Each report has been processed into the DCC database,
scanned and made electronically available, and captured on the
spreadsheet with a hyper link that opens each incident report for
instant viewing. Awaiting more incident reports that Bill finds
as he processes through boxes of records from earlier years that might
include occurrences that arose during construction at both sites.
- Began
compiling notes and changes made to the Safety Plan. Will compile
each of the reviewer's comments into one edited document for Bill to
hand out to the safety committee.
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- Processed MOU's and attachments.
- Scanning Update - Progress continues on scanning of all non-electronic "L" category documents on file.
Update to Current Document Management System (Turner)
Worked through the tutorials for Docushare. Compiling notes and questions.
FINANCIAL SYSTEMS (Funaro, Brambila, Kaufman)
>From: "Funaro, Catherine" <Catherine.Funaro@caltech.edu>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Completed change order #18 to Southern Enterprises.
- Completed the orders for LLO and forwarded invoices for processing.
- Coordinated
with end users on the equipment maintenance orders with Dynamic
Systems. There are still two renewals pending.
- Working on change order #10 to University of Michigan.
- Closed orders and followed up on orders with pending shipments.
>From: Florence Kaufman <fkaufman>
- Completed and sent out monthly report as of the end of March for FY2007 Operations. [to be reviewed during Excomm Meeting Monday – pel]
- Completed and sent out reports for three discretionary accounts, MIT Grid Account, and the Low Noise Award.
- Worked on Change Request for Labor adjustments for unfilled positions and to adjust FY07 budget amounts.
- Completed
the report for the Visitor Award as of the end of March. The past
award has reached its final expenditure limits. A Cost Transfer will
need to be prepared to move the overspent amount to the FY07
Award. Notified Project Accounting to put a hold on the Visitor
Award account - LIGO.VISIT/1 NSF.VISITO - so that no additional charges
can be made to it.
- Submitted
budget realignment request to Project Accounting to transfer budget to
the two new fabrication accounts that have now been set up for the
Enchanced LIGO Thermal Compensation Systems at Hanford and Livingston.
- Submitted fabrication request for Pathfinder Input Test Masses.
- Financial reports can be found at: http://docuserv.ligo.caltech.edu/~fireport. (For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone <gsalone@ligo.caltech.edu>
- The
Purchasing Services Department has changed its policy and will no
longer allow non-Caltech employees to submit Supplier Requests to
register new companies in Oracle. This change may result in delays in
registering new suppliers, which in turn will case delays in placing
purchase orders and paying invoices.
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- The
LLO SEC successfully completed its inspection by the Louisiana State
Fire Marshal and received their permanent Certificate of
Occupancy. As a result, we will pay the final invoices for the
architect, Eskew-Dumez-Ripple, and the construction contractor,
Cangelosi-Ward, and close out both contracts.
- Ann
Bussone, of the Caltech Office of General Counsel, has reviewed the
list of items in Advanced LIGO that may be subject to ITAR/EAR
issues. She has recommended that the list be reviewed by a member
of the JPL technical staff, along with a member of the LIGO technical
staff, for the purpose of classifying each item, and see what is
required for the specific country that is applicable for each
item. In some cases, we may require a license from the Department
of Commerce. We are trying to schedule a meeting sometime next
week for the item review.
PROPOSALS and REPORTS (Lindquist)
Proposal
activity for LIGO Continuing Operations (FTY 2009 – FY 2013) included
discussions with Finance regarding the indirect model to be used to
price the cost estimate. The task managers also met to comment on
the staffing plan through FY 2015.
The monthly NSF report for current operations was submitted this week.
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- The next Staffing Committee meeting is scheduled for Monday, April 23.
LIGO
Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of S5 Activities at LIGO Hanford Observatory (compiled by K. Kawabe)
Despite
several windy days hampering both IFOs, H1 and H2 still performed well.
The duty cycle (Thu Apr/5 to Wed Mar/11 2007) of H1 was 83.2 percent
with typically 15 Mpc inspiral binary range. The duty cycle of H2 was
80.4 percent with 6 - 7 Mpc range.
Summaries: Range and Duty Cycle update. Tuesday maintenance summary.
Highlights from the LHO elog:
LIGO
Livingston
Observatory (LLO) and Interferometer Operations (Giaime)
S5 run summary (Brian O'Reilly):
- We
had another good week with 86% of the time spent in Science
Mode and no major problems. The main problem with duty factor
seems to be local seismic noise in the 1-3 Hz band during the day.
- A
very nice study was made of the seismic trends for the 0.03-0.1
Hz and 0.1 to 0.2 Hz band by Doug Lormand (see elog entry on
Friday April 6th). There was a minor hiccup with the new
statevector code that is needed for blind injections. We will try again
next maintenance period. Valera managed to power up to 7.94 W,
this had failed previously for reasons that are not clear. The
"night" option now gives this power whereas the day option is now
7.08 W which we had been using almost all the time.
CDS Computing (Lisa Bogue):
- Dave
Barker's modified statevector code was tested, in preparation for the
blind injection program. A small deviation between LLO
and LHO's channel numbering was found, and a revised installation
will be prepared.
- An syntax error in the framebuilder channel list was corrected.
- Continued work on the VPN.
LLO Outreach (John Thacker):
- Continued work on matching LA Grade Level Expectations with our various activities
- Developing materials for Science Buddies partnership
- Developing new activity on test mass suspensions for HS physics classes
- Worked on pre-visit acitivity (interferometer)
- Developed and delivered 1 High School program
- Posted SEC calendar to web using Meeting Maker
- Continued work on F2F meeting May 3rd.
- Continued work on SEC webpage.
- Assigned SEC staff member to maintain LIGoOP planning webpage
LIGO computing and network security (Roddy)
--------------------------------------------------------------------
Reported under General Computing, see below.
General computing and LDAS admin (Giardina)
---------------------------------------------------------------------
Reported under General Computing, see belowReported under LDAS System Administration, see below
Data analysis & computing (Yakushin)
---------------------------------------------------------------------
Storage/Condor/LDAS admin:
Reported under LDAS System Administration, see below
Data analysis:
Reported under Data Analysis activities, see below
Mechanical and Optical Systems (Coyne)
See Advanced LIGO
Controls and Data Systems (Bork)
See Advanced LIGO
40-Meter Interferometer (Weinstein)
- IFO commissioning, Electronics, controls, computers:
- Rob
and Sam have been exercising the lock acquisition for the PRFPMI, which
has been working well. They had some trouble with the Y-arm violin
modes ringing up during lock acquisition, so they adjusted the notch
filters on SUS-ETMY_LSC, which quieted them down nicely.
- Our
MOPA (main PSL laser) has recovered most of the power lost during
recent "events", and is now hovering above 4 watts. Steve notes that it
has small (~0.1 watt) "hiccups" of lost power, recovering in minutes or
hours. This seems to be associated with the NPRO pump diode head
temperature. We are watching this carefully.
- Steve
is acquiring ethernet cables of appropriate length to move the c1omc
processor away from the AS ISC table, since it is generating
considerable acoustic noise.
- Rob
is getting the controls software running on our new laptops (with
Fedora 6). He's got DTT and dataviewer working, but is having trouble
getting EPICS/medm working. In progress.
- Ben
has stuffed the board for the new DCPD, and has worked around the
American Capacitor part problem. He just needs to put on a connector,
and test it out. We plan to install it into a new vacuum nipple and
then into the vacuum chamber in the next few weeks (when we vent to
drag-wipe the TM optics).
- Rob is setting up the new "headless" controls computer, op340m, to run our standard scripts continuously.
- We continue to have reliability problems with the op540m control computer. Nothing that a weekly reboot can't fix.
- There
will be an AdLIGO ISC meeting at Caltech next week. We will make plans
for a redesign of the 40m to test the new proposed RF scheme for
AdLIGO.
- We are planning out projects for SURF summer students.
- DC detection:
- In
the PRFPMI configuration, Rob notes that the noise spectra look the
same as they did a few months ago. There is still a 1/f^2 noise from
100 - 1000 Hz, of unknown origin. It is not reduced when coil driver
dewhitening is turned on, so that is sub-dominant. Right now, Rob is
focusing on understanding and eliminating the forest of peaks in the
1-2 kHz region, which is suspeced to be due to the input PZT steering
mirrors.
- Vacuum squeezing:
- Go
and Osamu have been tuning up the squeezer after an SHG heater wire
failed, changing the alignment of the SHG. They have gotten back to ~ 3
dB of squeezing at 1 MHz, and are continuing their optimization of
modematching, alignment, etc to get to their goal of > 6 dB.
- Lab Infrastructure, Bake lab:
- We will have 60 sixth-graders from the Hamilton Elementary School visiting the 40m next week.
- Steve is rearranging the office space to make room for another electronics bench and a whiteboard.
- Bob is quite busy with large bake loads for LASTI.
Thermal Noise Interferometer (Black)
Akira
is doing his candidacy exam today (Thursday), Ilaria is studying
control theory and practicing locking the interferometer, and Greg
just finished a literature search on non-Gaussian noise.
LASTI (Ottaway)
HAM SAS
Last
week we determined that the Guralps sensors used to measure the floor
motion were not coherent with each other below 100 mHz over relatively
short baselines. This meant that our used of these to look for
coherence with the excess HAM SAS noise at low frequencies would not be
successful. To improve on this situation we changed to STS2s to perform
this measurement. We borrowed an STS2 from LHO and installed it along
with our one remaining LASTI STS2. With this combination of the 2 STS2
were able to demonstrate that the excess noise on the optics table was
partially coherent (~0.7) with both the tilt signal and the translation
in X signal of the ground. At present we are not sure whether
this is because the system is limited by tilts that are picked up in
both the STS2 and real translation of the optics table or horizontal
translations of the ground are somehow amplified.
Quad/Triple Cavity
Using
feedback to the laser it was possible to show fringe stretching to
about a second. The cause of these lock stretches not being longer was
saturation of the VCO actuation signal. Work continues to find out
whether this can be improved by improved damping of the suspensions. In
addition to this much time was invested in getting the BSC HEPI going
for improved isolation.
Lab Infrastructure
A
lot of time has been spent preparing to receive and assemble the noise
prototype. In addition to this we have been having quite a few computer
related issues that we are working with the CDS group at Caltech to
resolve.
CIT Science Group (Weinstein)
Xavier Siemens:h(t), h(t), and more h(t):
- Finalised S5 V3 digital filters for H1 and L1Prepared segment lists and pipeline configuration files (all set
up at CIT cluster)Edited LAL and LALApps strain computation code for productionGeneral
preparations for gigantic run on cluster to catch up from the beginning
of S5 to now. Will be generating about 40TB of data.
- Spent week doing shifts in Lousiana
Gregory Mendell:
- Working with the CW group, I have made some progress towards responding to the latest reviewers comments to the StackSlide/PowerFlux/Hough S4 paper, with other work currently taking up most of my time.
Patrick Sutton:Network Analysis:
- I
spent a lot of time figuring out how to construct MDC
frames containing inspiral waveforms, for the analysis of
GRB070201. With help from Zweizig and Fairhurst, I made h-of-t
frames for 1.4-1.4 and 1.4-10 solar mass inspirals, and circulated
them to the bursts group. These are in a non-standard format
in which different injections are written to separate channels in
one frame and which cover the same time interval.
- Modified
X-Pipeline to be able to loop over multiple
injections/MDC channels with a single read of "noise" frame
data. This improves efficiency when analysing the same data
repeatedly with different injections, and allows us to analyse the
new MDC frames for GRB070201.
- Other:
- Searching for former S2 authors to finalize the author list for the S2-S3-S4 GRB paper.Recruited scimons for the last two outstanding sets of CIT shifts for the current shift block.
- Acted as LSC-PP editor for reviews of GWDAW11 proceedings papers by Sung, Chatterji, Whelan.
Eirini Messaritaki:
- I worked with Vibha on her proposal for the SURF project, which involves the detection of eccentric binaries with non-eccentric templates.I worked on coding up the null stream test for the inspiral search.
- I worked on the detection of spinning binaries with non-spinning templates.
Kent Blackburn:
- Attended Cybersecurity Conference for LIGO.
- Reviewed and documented comments for Advanced LIGO CDS requirements and design, focusing on cybersecurity and provided these to Vern Sandberg.
OPEN SCIENCE GRID APPLICATION DEVELOPMENT
- Held meeting with Duncan Brown to get an introduction to inspiral analysis codes.Wrote RSL script in using vi editor and executed it on several Open Science Grid sites.Attended Pegasus and DASWG teleconsLearned how to run a workflow using the LIGO WorkFlowPlanner after encountering several road-blocks with getting into needed gridmap files on the Caltech LDG cluster.Learned to run simple jobs on OSG using Pegasus. Began working through on-line OSG tutorial at the suggestion of Ruth Pordes and Kent Blackburn. So far have worked through the following sections:
- Grid introNetwork PrimerGrid NetworksGrid SecurityJob ManagementData Management
- Labs 1, 2, 3, 4
- Registered for Condor-Week Conference.
OPEN SCIENCE GRID INTEGRATION TESTBED
- Worked with Pegasus engineering team on dynamic cleanup algorithm characterization, completed all tests required for analysis.Provided support for Britta Daudert including interface to Caltech RLS/RLI engineers on setting up access control list, setting up defaults for LIGO work flow planner and explanation of interaction between Pegasus planner and other infrastructure components.Tested ws-gram enabled nanoHIPE workflow on the following sites: FNAL_GPFARM_TEST,
IUB-VTB, UC_T2DEV_ITB, TTU-TESTWULF and OUHEP_ITB. Three sites
are still running the workflow at present and one site, TTU-TESTWULF, has completed the workflow. One of the sites was not able to run the workflow.Reconfigured the ws-gram Java container that supports the service on LIGO-CIT-ITB with twice the memory as recommended by the Globus developers. Starting a large number of ws-gram submissions in a small time interval can still bring down the ws-gram service even with the additional memory.
- Attended DASWG, ITB, Pegasus, VDT and OSG attributes working group telecoms.
OPEN SCIENCE GRID MANAGEMENT
- Filed quarterly Caltech PI report to the Open Science Grid Management.Wrote an article on the International Partners Sessions chaired at the Open Science Grid Consortium Meeting in San Diego for the International Science Grid This Week newsletter.
Laboratory Computing (Anderson)
LDAS Software (Lei)
- (ML)
cmonClient - cvs changes for PR3138 and closed out: handling list of
list in resources by removing extra list put in by blt column entry
when value is retrieved.(ML) genericAPI - updated the text wrapping code.(ML) Documentation:
- Updated documentation on upgrading to DB2 fixpak 14.Fixed PR 3141 - by having a hyperlink for each regression test to the PR itself.
- closed PR 3105 - use of exec inside ldas by documenting areas inside ldas that uses exec.
(ML) Testing: Performed system test for ldas 1.8.511.
- lsync
core dumped after catching SIGTERM signal to terminate. Updated
lsync.tcl to wait for threads to finish before terminating due to
signal but not possible to call C++ (getThreadList) inside signal
handler.regression PR2946 failed during the run but ran ok when run separatelyRDS Verification failed but passed when /archive and /data were removed from mount points.
- after
DB2 upgrade to 8.2.7, metadata did not show any big improvements in job
throughput. frame and diskcache detected a slight increase of
1.3% from QFS patch.
- (ML) Other:
- Installed db2 fixpak 14 on ldas-dev metaserver. Jobs ran ok.
- Updated db2utils to display the DB2 version and patch level and made current links to ldas release test results.
LDAS System Administration (Anderson)
Caltech
(Dan Kozak)
- Working with StorageTek to replaced power cables on 9940 tape drives.Continuing to check md5sums so I can relabel more tapes in the near future.Installed QFS 4.6 on various -dev and -test machines and tested the new samfsck on /scratch.Installed
QFS-4.6 and a bunch of Solaris 10 patches on peaches, opterondata-cit
& ldasdata7. Installed Common Array Manager 5.1.0.11 on
peaches and opterondata-cit.Tested
create() and rename() speeds on directories with 100,000 files in them
between QFS 4.5 and 4.6. 4.6 shows a ~3x increase in speed.Finally got replacement 36GB drive from Sun, installed it in ldas-cit.Made a few tweaks to ldas-cit:/var/sam/samstuck.Updated gpsStart for L1,L3,L4 psets in collections.ini.Generated list of tapes for shelf storage at LHO.Rebooted dataserver-cit because of stuck samsharefsd.Set RLS acl for Britta.
- Helped clear out the last of the (known) h(t) issues (missing/corrupt files in various places).
(Phil Ehrens)
- Finished
webform set for MOU Reporting. Implemented SSI structures for MOU
webform handling. Wrote documentation for MOU webforms in MOU_Wiki.
Began coding cgi backend for MOU Initial Setup form.
- Various user support tasks.
(Erik Espinoza)
- Counted and shipped 704 memory sticks back to ASA.RMA'd 8 faulty disks w/ ASA.Diagnosing issues w/ hard drives on nodes (207/329).Worked w/ Gregory Mendell on frog.Working on php fixes for FC4.Diagnosed issue with replacement mail server (gacrux).Looked into OpenSSH issues and how they may affect us on FC4.
- BitTorrent downloads of the CentOS 5 isos.
MIT
(Fred Donovan)
- Added a node ligo-burst, took 9 more nodes offline for ligo-burst cluster.
- Added larger disk to ligo-burst; firewalled.
Livingston
(Igor Yakushin)
- Working
on the procedure to RAIDify /usr1 into RAID 0 and /, /boot into RAID 1
on the nodes now when some of them ran out of /usr1 space for L3 and
h(t) frames.
- Condor crashed on Sunday night and no new jobs could be started until it was fixed on Monday.
(Dwayne Giardina)
- CreateRDS
jobs were failing due to stuck diskcacheAPI. I removed node190
from MOUNT_PT and /etc/auto_data, restarted diskcacheAPI and the
createRDS jobs.Replaced u1d8 in T3-25 with a disk from a spare parts unit.
- Tape eject and shipment to CIT.
Hanford
(Greg Mendell)
- Testing
of RDS generation using the prerelease of LDAS 1.9.0 and
zero_suppress_int_float frame compression at CIT has gone well. The LSC
Data Grid (LDG) 4.4 packages are also being tested at CIT and these
should be ready for general release next week.
(Ben Johnson)
- Helping
test DTT and DataViewer on Linux here. Possibly for Linux-based
operator workstations. Also installing various linuxes for testing.Still
researching openSSL. O'Reilly's OpenSSL book has been very educational
regarding certificate-based authentication (revocation lists, certs in
LDAP, server/client authentication, etc.).
- Applied
the generic_limited_net profile to dataserver. The subsequent NFS
server downtime caused ldas-pcdev1 and ldas-grid to need
rebooting. They worked fine after the reboot.
General Computing (Wallace)
MIT
(Fred)
- Spoke with Bruce S re: ilog, went over structure and layout. more ram for Stephany (solidworks slow); ram for LATSI (re: crashing issues);-Laptops arrived and setup for new hires(dual boot, etc); some purchasing issues;
- Wireless access point nw22 not passing dhcp through; some LATSI conf.
Livingston
(Dwayne)
- Received new MacBook Pro, migrating to it this week. Will install Parallels and perhaps CentOS and (gasp) Windows VistaBuilt a replacement server to host ligo-op, www.ligo-la and GC SecuWiki. Migration was fairly smooth except for one configuration error that was corrected after a google search. The migration included changing a few settings on Bonnie's computer and getting Deborah set up to manage the ligo-op site. Installed software on new operator PCShipped borrowed equipment back to LarryThe UPS supporting the core switch died yesterday around 4:00 PM taking the LLO network with it. Assisted Shannon with installing replacement. Upgraded SolidWorks2007 to sp 3.1 on Janeen's workstationspam filter cleanup
- Other usual user requests and support
(Shannon)
- Unplanned outage on the UPS in the comm room yesterday. Took the opportunity to clean up the room, get rid of an old unusable rack, etc. Rerouted some cabling. The UPS that failed was slated to be replaced in a couple of weeks, unfortunately it died before we could get to it.Installed two new switches in the comm room. Started configuring the VLANs on them. Configuration in progress, this is to replace the old temporary switch.Configured DreamWeaver on Deborah's computer.Finally have the 208 addresses advertised via NLR, so we can start moving more hosts.Sorted through multitude of IDS alerts.Scanned CIT networks by request of Larry.Spent quite a bit of time patching the nameserver.
- Fixed several errors in our DNS tables.
Hanford
(Christine)
- There was a network slow down last night, Wed., between about 6:30 and 9:00 p.m. The network was intermittent with most operations timing out before
completion. I couldn't find any problems on my router, except for
a large number of input errors. Attempts to get to the ESnet web pages also timed out. However, If I logged into canopus at Caltech I had no problems reaching all of the computers and the router at LHO. Finally at about 9 p.m. the network started working normally again. The only possible cause I could find was a scheduled maintenance of a main router at the ESnet Sunny Vale facility. A traceroute showed that traffic from Caltech to LHO does not go through Sunny Vale while traffic from LHO to Caltech does.With help from Symantec Technical Support, The Veritas backup software accepted the license key and completed installation properly. The trick was that their installation software looks for gzip and gunzip in /usr/bin, but I had them installed in /usr/local/bin. Just modified the path and all worked.The correct SCSI host adapters arrived this week so I can now connect the tape robot to the server and get tape backups started again. The new disk RAID systems had to be partitioned into two partitions because Solaris 8 can't create file systems greater than 1 TB and the new RAIDS have 1.4 TB. I should be able to start moving the home directories over to the new RAIDs next week.
- Lockheed Martin is still working on the fiber for the backup network. They've contacted both PNNL and me to get access to the fiber, but otherwise no word on their progress.
- Still trying to get the latest version of DTT working on the GC application server. This latest version works with Solaris 10 and the older version does not. Running in to problems with missing libraries.
CIT
(Mike)
- This week I worked on a lot on SolidWorks issues that users were having. After researching and testing I found that the best way to correct some of these issues was to upgrade to the latest service pack. Christian and I have updated all our SW users to the latest service pack 3.1.Worked on shuffling equipment around to swap out an old SolidWorks workstation. Christian gave me a hand with this. We also ran some ghost backups to reload some SW workstations that are no longer being used. These rebuilds will be used for new hires or visitors.More work on a webserver to replace dccdocs.Worked on some problems with our mail servers this week.
- Added some users to the PDMWorks vault. I did some additional work while being login to the vault as pdmwadmin.
- Some work on Hiro's modeling&simulation servers.
- Other misc. user support and sysadmin tasks.
(Bruce Sears)
- iLog Maintenance and Planning: (1.0 days). General iLog maintenance (user adds, keyword adds, systems work, etc.) Discussions with Fred Donovan at MIT regarding his possible taking over of primary responsibility for iLog maintenance and development.
(Christian)
- Riccardo Desalvo- Created backup of Riccardo¹s files to external drive.Visitor
workstation- Re-imaged system after receiving notice from RuthAnne
about possible virus coming from visitors¹ workstation.Kronos Plug-in Installed Kronos plug-in for Rich Abbott, Britta Baudert and Rolf Bork.Solidworks users- Mike and I upgraded Solidworks users to Service Pack 3.Llaria Taurasi- Installed and configured Mathematica.Toner cartridge replacements- 3flr W/B and Millikan.Todd Etzel- Installed Adobe Acrobat 8 and Office 2003 SP2.Gary McIntyre- Created new system profile after getting multiple system32 DLL errors.Paul Russell- Removed spyware programs on system.
- Other misc.: Continued onsite software/phone support.
(Veronica)
- LIGO: Continued work on a simplified version of the roster database for Cindy. Also, rewrote the front-end for easier updates. Trained Cindy on how to access/update the existing system. The new setup almost ready, need to do some final troubleshooting. Continued work on the homepage redo. Looking at various wikis to migrate the LAAC database to. Addressed an issue of a new video of the interferometer lock per Rai Weiss request, troubleshoot the stream of the existing video. Updates of the PAC website, other misc. web updates.LSC: updates of the databases of technical papers. A change in the policy of positng and pointing to DCC locations only required some code tweaking. Updates of the presentations page from the last LSC meeting.
- CaJAGWR: Website updates/ user support.
(Larry)
- Placed orders for new PC equipment for one of the labs and PC support items for different people. Still a few more orders to place. Worked on configurations for a couple of different units for different people. Still waiting on a decision to whether they want the items ordered or not.
Working on a couple of CISCO items. We presently plan on just doing a minimal upgrade and waiting another year or so to do a major upgrade. All of this depending on costs and ability to handle our present needs, we are waiting for a CISCO tech. to confirm that we can do what we would like to do with the existing equipment. The Campus network group is also assisting to make sure we don't lose any functionality.
- Assisted Veronica with a number of different logistical issues related to the multiple web projects she is currently working on.Still working with PMA on the room upgrades and changes.Updated a few more items for Wilsonhouse.Working on a equipment loan for Osamu.Worked a couple of e-mail issues. One of the old servers now has memory problems and one of the new units needs to be reconfigured to accommodate some lost functionality. Modified some of the e-mail filters to accommodate user requests.Worked on a number of account issues. Mostly, cleanup items.Working on a list to handle logistical issues related to the different conferences that LIGO supports.
- Regular user assistance.
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Systems
Modeling and Simulation
From: Hiroaki Yamamoto hiro@ligo.caltech.eduAdvLIGO LSC/ASC design using FP arm model with quad suspension (Osamu)
- As
a result of simulation for AdLIGO arm cavity, we noticed that pitch
motion of end test mass is excited by coupling from length controls on
bottom three masses. To avoid this excitation, we need to implement
frequency dependent filter for all three masses, which should have
flipped shape of measured TF from each three length control to test
mass pitch motion. We have just started working on it. It may be useful
to find requirements for angle motion, and real experiments for LASTI
triple-sus cavity and AdLIGO in future.
Static IFO simulation (Hiro)
- Summarized
the re-evaluation of the loss due to microroughness, and its
implication for adv.LIGO mirror specification (T070082-03-E). Gave a
summary talk about the loss due to scattering at the telecon of the
coating group (G070240).Writing
LIGO note "Geometrical and diffractive loss : BS and FP" T070052, along
with necessary code development to finish the document. The main topic
are the (1) effect of the finite size and thickness of BS w/ and w/o
flats and the size of RM, (2) thermal effect on the beam shape in FP,
and (3) use of asymmetric FP (ROCITM > ROCETM, wITM<6cm,
wETM>6cm) so that the beam size on BS is smaller.Explained the use of the simulation tool to John and Yanbei's company.
- When
running the code to demonstrate the use, I found that the field in a
mesa beam cavity using concentric design resulted in a normal gaussian
shape steady state mode when the cavity is locked. When the cavity is
not locked, the beam shows a flat center. This may indicate that the
locking process (standard error signal is used) prefers normal gaussian
rather than the mexican hat beam shape. This is very preliminary,
though.
Mechanical Simulation for advanced LIGO (Sany and SLU team)
- Continued
the optimization of the AdvLIGO Mode Cleaner?s length sensing control
gain setting. We are in the spring break this week. Due to the power
down for a routine maintenance, our activity was very limited.
ALFI : e2e front end (Melody, Bruce)
- Working on the front end to support the user defined primitive (corresponds to mex file support of matlab).
CDS Prestabilized Laser
From: Peter King <pking@ligo.caltech.edu>
- Assembly
of the lab prototype 35-W laser was completed. The output power
and beam quality are both good and reproducible. Even when a
cooling problem occurred because of a plumbing fitting not being
connected properly, the amplifier recovered when the problem was
fixed. This in turn revealed a minor software problem which has
since been rectified.Transfer
functions involving the intensity actuators have been measured. The
acousto-optic modulator used handled the 35-W beam without any
problems, although a prolonged period of exposure was not undertaken.A
couple of discrete op-amp topologies for transimpedance amplifiers have
been tested and their performance measured. The noise performance
at 10 Hz has been pretty good, certainly better than most off-the-shelf
op-amps available.
- I have seen the diagnostic breadboard in operation. It's proving to be a handy tool.
Control and Data Systems
From: Rolf Bork rolf@ligo.caltech.eduLasti (Rolf/Alex)Investigating CDS problems at Lasti this week. So far, found a couple of things:
- HEPI
timing slave power supply was bad/erratic, causing HEPI code to suspend
waiting for ADC signal; replaced. This also had the adverse effect that
HEPI timing was being used to clock the FrameBuilder, which would also
then stall.Systems are
set up for max of 32 test points. Recent combined tests on HEPI and HAM
SAS (latter uses some HEPI TP for Guralp data) with >32 causes it to
crash. We have new code to increase this limit and also to avoid error
when >maximum TP are requested. However, this code needs to be
loaded into all Lasti systems at the same time, so we will wait until a
convenient time.
- Alex has managed to compile a version of DTT with the debugger enabled. This should help us debug DTT problems at Lasti.
AdL SUS Noise Prototype (Jay)
- The UK designs are progressing and the UIM coil driver board design will be sent out for manufacture on 4/13.Preliminary design of the noise prototype system and rack wiring is complete.
- Design of the whitening and interface boards will be started following OMC and Tip-Tilt.
OMC Suspension (Jay)
- The system wiring diagram is complete.The
modules and chassis we have on hand, ready to go are-- coil driver, sat
amps, AA chassis, IO chassis, ADC interface, DAC interface, timing
interfaceStill needed
are-- SUS receiver, timing slave, AI chassis. The SUS receiver is being
fab'd, AI chassis is waiting on the interface board which is being
fab'd. The timing slave and a master has been requested from LHO. In
the meantime, a software trigger mode for the system can be used for
initial test and checkout.The ADC and DAC have been received.The
rack and power supplies from the sync lab will be used in room 56. The
movers have been contacted abuot getting the rack to the room. We need
to order an operator station similar to what LHO is now testing.A draft of the controls requirements document has been written and reviewed by Norna.Simulink model of the software should be done next week.
- The network will not be ready in the basement for about 1 month. We can run without it, but it will be awkward.
Tip-Tilt equipment for ANU (Jay)
- The equipment needed for ANU includes:
- 2 ea AA chassis- boards, parts and panels redesigned and on order.
Boards being sent out for stuffing.
- 3 ea AI chassis- boards, parts and panels redesigned and on order.
Boards being sent out for stuffing.
- 3 ea Sat Amp- boards and parts on order2 ea SUS receiver- boards and parts on order
- 8 ch Coil Driver- boards stuffed, panels on order
- IO
chassis components- boards and parts ordered for ADC adapter, DAC
adapter, Timing InterfaceComponents should be ready for shipment by
5/26 assuming no major procurement issues.
AOS
- We may be in need of another CDS test system to support AOS prototyping here at CIT. Mohanna is investigating further.
ISI (Ben)
- ADC
Interface Rev6 and STS2 Breakout box- The boards are back, and I
stuffed one set as a model for the others. The remainder are in
the back shop ready for stuffing.
- ISI
Interface I sent the schematics to Brian Lantz for a quick looking-over
last Friday. I'll give him a call tomorrow to find out what he
thinks.
Seismic Isolation
Brian and Ken preparing a summary of HAM-ISI status as we consider proceeding with fabrication of HAM-ISI
HAM-SAS
team working on characterizing the system and interacting with the
committee considering a possible recommendation to switch to HAM-SAS as
an approach for the HAM.
From: Ben Abbott abbott_b@ligo.caltech.edu
All new activity since last weekly is written in red.
40m:
DCPD
- I
have stuffed the DCPD, and have worked around the American Capacitor
part problem. I just need to put on a connector, and test it out.
HAM-SAS:
Custom Electronics chassis: (# needed + #spares)
- LVDT Driver (2 + 1) -2 Installed the spare is stuffed, but needs boxing and testingLVDT Interface (2) InstalledStepper Motor Interface (2 + 1) - InstalledCoil Driver Interface (1) - InstalledQPD Whitening (2 + 1) - 2 Installed, 1 spare here, needs testing and boxing.QPDs (4 + 1) - 4 in electronics lab, 1 is just a bare board and I'll keep it for a spare board.Guralps Interface (1 + 1) - 1 installed, 1 built but untested.AA Interface Rev 4 (1) - InstalledAA Interface Rev B5 (1) - InstalledAI Interface Rev 3 (1) - InstalledCoil Driver (4 + 1) - Installed
- In-Vac Breakout boards (2) Installed
Commercial Electronics:
- Opteron Processor (1) - InstalledStepper Motor Driver (4) - InstalledI/O Chassis (1) - Installed
- Power Supplies (2) - Installed
Miscellaneous:
- In-Vac Accuglass cables (13) - InstalledGuralps
cables - Specialty cables from Guralps Instruments Ordered 12/21 quoted
a 30 day lead. They have been shipped to LASTI, and await installation
by Dave or Alberto.Special cable connecting the LVDT 25-pin Witness board connector to the 9-pin ADC connector - InstalledThe
5 L-COM cables that were short were delivered to Alberto last
week. Marie told me that Riccardo came and picked them up after
Alberto had left for the day. I assume that Riccardo installed
them.The decision has
been made to read back the stepper motor steps so we can keep track of
the actuator position when we move the steppers. The first stage
of this effort will be to move the motors manually via the front panel,
and read back the RS232 signal that records the # of steps through the
PCIX adapter module to a terminal window. Alex installed computer
control of the stepper motors, and it seems to be working fineThe RS232 to PCIX adapter board has arrived. Alex has been using it to control the stepper motors.Of
the five coil drivers sent from Italy, two do not work. David and
Alberto have installed one of the remaining unmodified coil drivers
instead. Chub in the back shop has finished troubleshooting these
boards, and he says that they now both work just fine.I have finalized the system schematic, and it now agrees with the observed controls pinouts.The
new in-vac specialty cables from Accuglass and PEEK zipties failed the
first clean & bake cycle RGA scan, so Bob will clean and bake them
again. They were shipped to LASTI.The stainless zip-ties from Accuglass, and bolt-down tabs will go into a bake oven when one opens up.
- The
adapter cable from Accuglass to flip an erroneous pinout in the Vacuum
is in Italy being cleaned, and should be back sometime this week for
installation.
ISI:
- ISI Interface
- (3 + 1) I sent around an email with the requirements for this board,
as I see them. I got some feedback at Friday's meeting, and so
I'm working on the schematic now. I've decided to make the design
modular inside the chassis. That way, it'll work in all
application configurations. I sent the
schematics to Brian Lantz for a quick looking-over last Friday.
I'll give him a call tomorrow to find out what he thinks. GS-13/L4C
Emulation Module -One got stuffed, and needed some modification.
I cut another PCB, which arrived yesterday. I will give the parts
to the back shop for stuffing today.GS-13/L4C Control Module - One got stuffed, and tested O.K. The front panels for both boards are in process at Front Panel Express.GS-13 Boards - I shipped off four complete boards.Coil Driver - (3 + 1)
(Mohana) - Two Coil Driver chassis are complete, and look really
good. One is tested, and the other awaits testing, two more will
be coming soon.STS-2 Emulation Module - Mohana has finished testing this board.STS-2 Control Module - (Mohana) One board is being tested now.
- ADC
Interface Rev6 and STS2 Breakout box- The boards are back, and I
stuffed one set as a model for the others. The remainder are in
the back shop ready for stuffing.
Suspensions
From: Janeen Romie <janeen@ligo-la.caltech.edu>Enhanced/Advanced LIGO
- At
Caltech this week to support OMC suspension build and test. Currently,
most of the OMC parts are in the W. Bridge room 56. The OMC structure
is done and is instrumented for resonance testing.
From: k mailand kmailand@ligo.caltech.edu
- The
LASTI tooling assembly parts are in final assembly. All of the fit and
function tests done so far on the sub assemblies have been acceptable.
Ian's outer support frame for the lower SUS arrived, and we will use
this frame to drill match pin locations, in both the frame, and tooling
interface.
Core Optic
Auxiliary Optics
From: Michael Smith smith@ligo.caltech.eduSLC
- I revised the scattered light calculations using the LHO measured surface motion spectra. I derived a requirement for the beam size to be collected by the cavity beam dumps, instead of assuming the 100 ppm diameter Black
glass with an AR coating meets the minimum requirement for the arm
cavity baffle. However, a new design of a light trapping baffle is
being considered to increase the margin of safety for scattered light
noise from this critical baffle.
- I have created a new plot that shows the independent noise spectrum for each of the major scattering noise sources
From: Phil Willems willems@ligo.caltech.eduTest Mass Absorption Measurements
- I
have implemented a time-dependent model of the heat diffusion in the
LIGO test masses and the resulting acoustic frequency shifts under the
inhomogeneous temperature gradients. The model shows a correction
to the naive estimates of heating at the 25% level, roughly as the Rome
group reports in their analysis. This revises our absorption
values downward, from ~4 ppm to ~3 ppm.
The
apparent discrepancy between the LLO TCS calibration of the frequency
shifts and the naive estimates may be in part due to this effect.
However, it may also be that the temperature dependence of the Young's
modulus in the test mass is not what we think it is. We are using
values measured at Caltech for fused silica fibers, but bulk silica may
have a different value- published values for this quantity do differ
over a fairly wide range. This is still under review.
Advanced LIGO TCS
- The
test mass ring heater shield is in the Caltech machine shop and nearly
finished. From there it goes to get a gold coating.
Enhanced LIGO TCS
- We
have ordered axicons to more efficiently convert the CO2 laser profile
from a gaussian to an annulus. Sadly, it will take 10-12 weeks
for them to arrive.
Input Optics
From: David <tanner@phys.ufl.edu>
Luke Williams:
- set bounds on Signal Recycling Cavity length
- looking at ways to remove heat from FI optics in vacuum
Wan Wu:
- Preparing for the experiment to meaure the amplitude and phase noise associated with the wedged-crystal EOM.
Rodica Martin:
- Submitted requests for quotes to vendors for blanks, coatings and polishing.
Muzammil Arain:
- A
paper titled "Adaptive Optical Elements for Future Gravitational Wave
Interferometers" has been submitted to Frontier in Optics meeting
describing adaptive thermal compensation techniques for Advanced LIGO.
Antonio Lucianetti (at LLO):
- Measured
the isolation ratio of an advanced LIGO fariaday isolator in vacuum.
The performace decreased significantly as the pressure dropped into the
mTorr range; using 100 W input power the device delivered 48 dB
isolation at ambient pressure but only 30 dB at a pressure around 1
mTorr. Further experiments in progress.
David Tanner:
- Started
calculating the constraints on modulation frequencies in advanced LIGO
set by the chamber lengths. Both marginal and stable power recycling
cavities were investigated for straight and folded layouts. SRC lengths
were considered at a primitive model level.The
baseline design of 9/180 MHz works for the straight layouts (H1/L1). An
alternative of 9/63 also works but 9/45 may have too long a signal
recycling cavity if the marginal PRC is used. It's OK for the stable
PRC.
- The lowest workable frequency for the folded interferometer (H2) is 27 MHz for the marginal PRC, 18 MHz for the stable case.
For additional information about this report, contact Albert Lazzarini or Phil Lindquist