The LIGO Executive Committee Agenda for Monday, April 2, 2007 will be:
(Meeting time: 10:30 am Pacific Time)
1. Announcements
2. Programmatic (Marx) - TBA
3. Comments on Weekly Report
4. LSC and Data Analysis (Reitze)
5. LIGO Lab Operations
- Administration (Lindquist)
- Sites (Raab, Giaime, Shoemaker)
- Commissioning (Fritschel)
- Optical and Mechanical (Coyne)
- Control and Data Systems (Bork)
- 40m (Weinstein)
- TNI (Libbrecht)
- LASTI (Ottaway)
- Lab computing (Anderson)
- Science Group (Weinstein)
6. Enhancements (Zucker)
7. Advanced LIGO (Shoemaker)
8. Change Control Board/Technical Review Board Session as needed
- There are no open change requests
Site and other business issues:
Special Items:
Special Announcements: LIGO & Virgo have agreed to begin data sharing 18 May 2007.
Weekly Report Highlights
LSC Issues (Reitze)
The LSC and Virgo held our first joint collaboration meeting in Baton Rouge, LA last week. After serious deliberations, the LSC Council voted to begin data sharing with the Virgo Collaboration beginning on May 18, 2007. Preparations are under way by the Data Analysis Committee and the Joint Run Planning Committee to exchanging data and joint running.
One paper, the S4 LLO-ALLEGRO stochastic paper "First Cross-Correlation Analysis of Interferometric and Resonant-Bar Gravitational-Wave Data for Stochastic Backgrounds" was submitted to Phys Rev. D. this week.
Three new groups (Eotvos University, Montana State University, and the University of Massachusetts Amherst) have joined the LSC.
LIGO Laboratory Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
The following MOUs were completed, posted and submitted to DCC this reporting period:
MOU |
Attachments |
Goddard |
DAT, OPS, Z |
Penn State |
DAT, OPS, OUT, Z |
Rochester |
DAT, Z |
IAP submitted their revised MOU and it is now being routed for signatures.
PROPERTY MANAGEMENT (Luna)
>From: Rod Luna <rluna@ligo.caltech.edu>
- Provided assistance to the Detector Group (H. Armandula) with packing, shipping, and the preparation of a Commercial Invoice for US Customs Clearance of two Fused Silica Substrates to CSIRO, Australia. Account Number LIGO.OPT - 5.4 - NSFLIGO.FY02ON.
- Reviewing Equipment Purchase Orders for LHO and LLO from Nov. 2006 thru Mar. 2007.
- Tagged and created Property records for a Electrometer (S. Whitcomb at CIT).
- Tagged and created Property records for a Laser NPRO (S. Vass at CIT 40M Lab).
DOCUMENT CONTROL CENTER (Turner, Mak)
Update to Current Document Management System (Lindquist)
There was no meeting of the DCC Upgrade committee Friday, March 23 due to travel for the LSC-VIRGO meeting and other considerations. However, a trial version of DocuShare with licenses for 50 users was set up for the LSC-VIRGO meeting and used for public posting of documents. Some favorable comments have been received. A debrief is planned for Friday, March 30.
SAFETY COMMITTEE
Worked with Dave Beckett on an initial edit and rewrite of the Safety Program since it is outdated. This edit was returned to Bill Tyler to distribute to the committee members as they begin the actual review of the content of the document.
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- Continued to process LIGO/VIRGO Scientific Collaborations Meeting presentations. All documents submitted to the DCC to date have been processed.
- Processing numerous talks from various past conferences.
- Scanning Update - Scanning of non-electronic "E" category documents on file is complete. Scanning has begun on all non-electronic "L" category documents on file.
FINANCIAL SYSTEMS (Funaro, Brambila, Kaufman)
>From: "Funaro, Catherine" <Catherine.Funaro@caltech.edu>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Completed the monthly purchase order close out and submitted the report. There had been several duplicate purchase orders for payment of invoices. The duplicate orders were discovered and the encumbrances released. Several orders had outstanding items returned for credit only, and those orders were also closed out.
- Completed the change order to Superior Steel and entered the change in TechMart.
- Working on the renewal of the maintenance agreement for year 3 for LHO and will be submitting to the vendor today.
- Issued the order for the equipment maintenance for Hanford for the period through 9/30/08. The period after the grant ends will be optional for renewal.
- Transferred funds on MIT to match the invoice.
- Closed out several blanket purchase orders and released funds.
- Followed up on pending items and the status of past due orders that are still open. Updated delivery dates in the system and notified researchers.
>From: Florence Kaufman <fkaufman>
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone <gsalone@ligo.caltech.edu>
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- GariLynn Billingsley, Peter Fritschel, David Ottaway, and Ed Jasnow attended the Advanced LIGO Pathfinder optics polishing contract kick-off meeting with QED Technologies in Rochester, NY. The meeting was very successful, with QED demonstrating their unique processes for polishing and metrology.
PROPOSALS and REPORTS (Lindquist)
I have set up and will be maintaining a web site containing information and useful pointers for the preparation of the proposal for continuing operations (FY 2007 - FY 2013). The web site currently includes the proposal outline and writing assignments for the proposal as well as a schedule and pointers to documentation in NSF FastLane Grants Proposal Guide. We will continue to add material as it becomes available.
A user ID and Password are required.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
- There are no open change requests.
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- The next Staffing Committee meeting is scheduled for Monday, April 23, 2007.
- A Staffing Committee meeting was held on Tuesday, March 27, 2007. The minutes and action items from the meeting are in progress and when completed will be posted on the SC web page.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
Nothing significant to report this week.
LIGO
Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of S5 Activities at LIGO Hanford Observatory (compiled by K. Kawabe)
The duty cycle (Thu Mar/22 to Wed Mar/28 2007) of H1 and H2 were 88.3 and 85.0 percent, with about 15+ and 6-7 Mpc binary range, respectively.
Summaries: Range and Duty Cycle update. Tuesday maintenance summary.
Commissioning etc.: Nothing to report.
Outreach: LIGO was one of several southeastern WA institutions to collaborate on a December 06 proposal to OSPI for a three-year Math Science Partnership program (MSP). Other partners are ESD 123, WSU Tri-Cities, Columbia Basin College, Pasco School District and Othello School District. We have learned that the proposal has been funded ($198K for the first year). Program activities will commence this spring and summer. MSP funds come from the Federal Dept. of Ed. and are connected to No Child Left Behind.
LIGO
Livingston
Observatory (LLO) and Interferometer Operations (Giaime)
S5 run summary (Brian O'Reilly):
- We had a very good week with 81% of our time spent in Science Mode and a Binary Inspiral Range of ~15 Mpc.
- On Friday the ISS gain was increased giving us better sensitivity at high frequencies.
- We changed the limit on the TIDAL_DM inputs to 5000 from 20000 in hopes that this would stop the ETMX HEPI from occasionally tripping when we lose lock. So far this appears to be working with no negative consequences. (Entry Mar 26 by D. Hoak)
- We did notice that the ETMX HEPI signals have some strange behavior, as do the SUSPOS signals from both the X and Y end. The HEPI behavior was seen previously but the SUSPOS glitching is new. Experts have been informed (Entry Mar 26 by D. Hoak).
- Rick Savage and Evan Goetz reported on photon calibrator measurements made the previous week. It seems that the X and Y results are 15% and 8% higher respectively than the official calibration. This is consistent with what is seen at LHO.
- Tuesday maintenance was mainly the nominal checks, however Valera took some frequency noise data for the noise budget. The ETMX, ITMX and ITMY optical levers were centered.
LLO Outreach (John Thacker):
(from 3/23)
- Prepared for SLU Undergraduate Pre-service Teacher class visit
- Prepared and Presented programs for Silliman Institute (High School class; Clinton LA) and St. Jude (5th grade; Baton Rouge, LA)
- Attended LSC Conference on Monday and Wednesday. (Outeach on Tuesday/ Thursday)
- Researched correlations between LIGO Science Concepts and LA Comprehensive Curriculum
- Designed and compiled an exhibit maintenance log.
- Prepared and mailed pre-visit packets
- Long range planning for summer 2007
(current week)
- Improved outline for interference activity
- Created post visit activity for middle schools related to polish portraits/color subtraction and UV Bracelets.
- Prepared post visit packets for groups.
- Prepared pre and post surveys for all groups in the month of April.
- Continued working on suspensions and optics power point presentation
- Worked on exhibit file for web page
- Prepared photo files to upload to web page
- Initial preparations made for F2F SEC Directorate Meeting on May 3rd
LIGO computing and network security (Roddy)
--------------------------------------------------------------------
Reported under General Computing, see below.
General computing and LDAS admin (Giardina)
---------------------------------------------------------------------
Reported under General Computing, see belowReported under LDAS System Administration, see below
Data analysis & computing (Yakushin)
---------------------------------------------------------------------
Storage/Condor/LDAS admin:
Reported under LDAS System Administration, see below
Data analysis:
Reported under Data Analysis activities, see below
Mechanical and Optical Systems (Coyne)
See Advanced LIGO
Controls and Data Systems (Bork)
See Advanced LIGO
40-Meter Interferometer (Weinstein)
- IFO commissioning, DC readout, Electronics, controls, computers:
- Tobin continues to make progress in commissioning the new dither alignment system. He measured the control matrices, inverted them, and set up the servo matrix. The servo restores the proper alignment on the x arm pitch. Yaw, and y arm, come next.
- Rana tuned up the MC WFS system.
- Rob installed two stages of dewhitening, with "design" digital compensation, for all four TMs.
- Steve installed an old HeNe laser for the BS,PRM,SRM oplevs. He and Rana will rebalance the power to each mirror, and will place lenses to get small spots on the oplev QPDs. Steve has ordered two new JDS/uniphase HeNe's for the ITM oplevs.
- Following discussions with Garilynn and Bill Kells, we are planning to perform a series of measurements to determine the amount of scattering and cavity loss in the 40m arms, before and after drag wiping, which we plan to do in about 4 weeks. (cf T070051).
- Rob and Tobin are looking at frame grabbers to document our mirror scattering before and after drag-wiping, and also to analyze HOMs in the OMC.
- We have a new NPRO sent to us from LHO, as a spare. The NPRO in our main laser lost 30% of its power a few weeks ago, but seems to be slowly recovering. Rana and Steve upped the diode current, and we are now almost back to the power we had before.
- Sam and the ELI OMC group are making plans to test OMC assembly, including vacuum compatibility of various epoxies, in Bob's bake lab. They expect to recieve the OMC fSi breadboard in 8-10 weeks. They will assemble the OMC and suspension in E Bridge 56.
- IFO modeling:
- We're thinking about how to implement the new proposed AdLIGO modulation scheme (9/45 MHz) in the 40m.
- DC detection:
- Ben has the new DCPD PCB, and will stuff it soon.
- Vacuum squeezing:
- Go is repeating some measurements on the squeezing obtained with the PPKTP OPO, and responding to reviewers comments on the PPKTP paper. He measured the linewidth and FSR of the OPO cavity.
- Lab Infrastructure, Bake lab:
- Steve checked and labelled circuit breakers & recepticles all over the lab. Daisy changed ac power connections were eliminated.
- The Caltech 40m Bake Lab will be extremely busy for the next 90 days, cleaning and baking BSC ISI parts for LASTI. If you need to have something cleaned and baked please contact Dennis Coyne to have your job prioritized.
Thermal Noise Interferometer (Black)
This week Ilaria and Akira set up the reference cavity and locked the laser to it. They then measured the laser's PZT response and compared it with the value we had been using. Their number came in about 4% higher than what we had been using, but it was within the error bars of the first measurement, which were around 10%. The new error bars are smaller than the old ones. We are working out how much this affects our calibration, but as of now it does not look like the effect is significant.
LASTI (Ottaway)
No report available
CIT Science Group (Weinstein)
Patrick Sutton:
Coherent Network Analysis:
- Editing X-Pipeline functions to process multiple FFT lengths in a single job (multi-resolution time-frequency analysis).Editing Was's scripts for post-processing GRB analysis triggers from X-Pipeline and setting upper limits.
- Editing X-Pipeline functions to straighten out coordinate systems, clean up and simplify the build process.
Other:
- At LSC meeting (until March 22). Had various meetings with Cannon, Chatterji, Heng, and Kanner to discuss various data analysis projects.
- Joined bursts review committee, started attending telecons.
___________________
Kent Blackburn:OPEN SCIENCE GRID VALIDATION TESTBED
- No VTB activity this week.
OPEN SCIENCE GRID INTEGRATION TESTBED
- Successfully tested ws-gram enabled nanoHIPE workflows at OSG_LIGO_PSU and TTU_TESTWULF compute elements both using PBS job schedulers.Worked with Pegasus engineering team on dynamic cleanup analysis of workflows generated on LIGO-CIT-ITB.Chaired ITB weekly telecom.
- Attended Storage, Pegasus, and Glue attributes working group telecoms. The storage meeting reported that effort will be brought on board to address near term milestones associated with SRM relying on existing expertise in dcache at Fermilab. New test suites are being developed to validate storage element (SE) sites on the OSG
OSG MANAGEMENT
- Caltech has finally approved the OSG sub-award contract with the University of Wisconsin Madison. I have been informed that it should be possible to set up the charge number by the end of this week, allowing invoicing to begin.Continue to work on OSG Statements of Work. A few more made incremental steps toward completion this week.The globus development team has asked to use the OSG in an interoperability challenge which will showcase OSG, TeraGrid and EGEE interoperability using both GT2 and WS gram interfaces. The executive team agreed to a 4 month agreement.
- Continued looking for individual to fill the second position at CIT associated with OSG grid administration and integration/validation. Several candidates were contacted this week. Kent is currently waiting to hear back from them regarding follow-up.
___________________
Igor Yakushin:
- Working on my APS presentation.
___________________
Gregory Mendell:
- I attended the March LSC and CW/Pulsar F2F meetings. I am still working on the StackSlide/PowerFlux/Hough S4 paper and still making some minor contributions to the new upcoming hierarchical Einstein@Home search. However, most of my current time is still focused on several LDAS sys admin tasks that I plan to complete by the end of April.
Laboratory Computing (Anderson)
LDAS Software (Maros)
- The issue of leaking file descriptors (PR#3067) has been resolved by fixing the offending constructor.
- Two of the system tests have been integrated into the build/installation process (PR#3069). They are the complex_data and geotest tests.
- Work is under way to resolve the missing .tmp files when running the createRDS command (PR#3040).
- The cmonClient application is being modified to handle list of list in resources.
- System testing of the LDAS software was done using version 1.8.498. The one anomaly that was observed was the core dumping of the lsync application at exit. The cache file compared ok. The core dump happened at exit in code responsible for cleaning up static objects at exit. There was a failure of some nightly loop scripts over the weekend which appears to be related to running the dcmangle script. After terminating the application, the loop jobs successfully completed.
LDAS System Administration (Anderson)
Caltech
(Dan Kozak)
- Worked with Sun/StorageTek repairman on failed 9940 drive. Got a bunch of useful information about the nature of getting tapes replaced by Imation under warranty. Had to jump thru some hoops to get the new drive to work with a new WWN.
- Continued to work on freeing up the "3rd copy" of RDS data here at CIT.
- Restored frame data to nodes 219 & 142.
- Restored some /home data at LLO for lgoggin.
- Installed two 10K drives in opterondata-cit.
- Released lots of files for Duncan Brown, also deleted some.
- Did weekly tape ingest.
- Asked followup questions about Sun's IDR patch (what machines are affected, when will an official patch be available, etc.).
- Computed tapes for shelf storage at LLO.
- Played with ssd_max_throttle on dataserver-cit some more.
- Called in bad Sun 36GB drive, still going 'round and 'round with Sun on this.
- Sent form "use LSCdataFind" letter to lindy.
- Ran Cat5 cable in Booth for temperature sensor in silo.
- Worked with Erik to try to get automount to timeout quickly.
- Staged files by hand on dataserver-cit that were failing to be staged automatically from gateway.
- Rebooted dataserver-cit because of unkillable samsharefsd (had hoped this would fix the staging problem but it's happened a few times since).
- Cleaned up the home disk usage plot generating scripts so that the totals wouldn't need to be run by hand anymore.
(Phil Ehrens)
- The usual mundane certificate and hardware support tasks and duties.
- Development of MOU webforms infrastructure to support the construction and maintenance of LIGO MOU. During the last week I have devoted most of my time to developing library routines for browser input and cgi handling of materials destined to become MOU documentation. Special effort has been made to support the language localization features of modern browsers, and the uploading and archiving of arbitrary object types. The plaintext versions of the MOU Attachment templates which Dorothy Lloyd prepared for me are being converted into html formatted templates with embedded code for automatic generation of fields based on cached state information and user input. As code specific to the handling of these forms is developed, the boilerplate content of the attachments will be abstracted to enhance maintainability.
(Erik Espinoza)
- Opened ticket w/ Sun for Trunking.
- Investigating Condor spool behavior.
- Worked with autofs for Ed Maros on test machine.
- Rebuilt node142 after multiple disk failure.
- Submitted ASA RMA for fans.
- Made old grid/pcdev1 into new node330/node331 (w/ 8 gig and new config).
- Submitted ticket for schedd/quill crash.
- Killed user jobs running on production pcdev1.
MIT
(Fred Donovan)
- Pcraid 4: new sata cabling (almost all) for drives to one of the 3ware boards; replaced disk
- smartmon (including sendmail) just about all set on the data nodes - email notifications working.
- Some cluster room housekeeping.
Livingston
(Igor Yakushin)
- Released L3 data from disk since /archive file system close to be full and the releaser was thrashing.
- Cleaned /usr1 on the nodes since several of them got close to 100%. That might not be enough and we might have to start using the second disk soon.
- Configured ldas-condor but have not integrated it into condor yet.
(Dwayne Giardina)
- Restarted nodes 159 and 190, both appear to be somewhat stable now.
- Cluster_mon modifications for disk usage and condor status.
- Tape eject for storage.
- Tape eject and shipment to CIT.
Hanford
(Greg Mendell)
- Presented "LIGO S5 Reduced Data Set Generation March 2007" at the March LSC meeting (DCC Number: LIGO-G070127-00-W) and discussed plans for RDS generation for the remainder of S5 and after S5. I am running further tests of the zero_suppress_int_float frame compression method (which gives 30% better compression compared with the currently used gzip algorithm). This has been approved for use in RDS frames by the run coordinator, pending successful completion of these tests.
(Ben Johnson)
- Rebooted ldas-pcdev1 after it lost its disks. The fix was apparently cable wiggling, leading me to believe that I need to replace the HDD cables in that box.
- Pursuing OpenSSL as the authentication library/layer for NDS.
- Helping Dave Barker set up Linux-based CDS workstation(s).
General Computing (Wallace)
MIT:
(Fred)
- Setting up two new postdocs;(install fedora, etc);
- Meetingmaker database moved over, in production now.
- Added 2X750 esata disks to tintagel, further work lcc web page (finished)
- Mail issues (spam); built spamassassin, mailscreen on pellinore (backup mail server),
- Will install fuzzy ocr and test. Juggling backup directories tintagel (space issue);
- Some nagios tweaking (working well)
Livingston:
(Dwayne)
- replaced DNS server ns2
- kantech security server patches and reboot
- spam filter cleanup
- other usual user requests and support
Hanford:
(No report this week)
CIT:
(Bruce Sears)
- -iLog Maintenance and Planning: (0.5 days). General iLog maintenance (user adds, keyword adds, systems work, etc.)
(Mike)
- Loaded a Sun workstation for 40meter. I swap them out with this box as well.
- Took care of some printer issues.
- Setup a laptop for Mike Smith to take on travel. I loaded some additional software for him besides our standard GC software load.
- Working with Cindy with some issues on Microsoft office 2007 & Adobe 8. The main thing is getting familiar with this software. I now have this loaded on my windows workstation to get up to speed on this software.
- Work on writing a script to automate the Primavera monthly backups. This is an on going project.
- Replaced some CRT monitors with flat screens for Sam Waldman. Larry gave me a hand with this.
- Doing some clean up work to get ready for end of month backups on the NTSRV’s.
- Other misc. user support and sysadmin tasks.
(Larry)
- Resolved a number of licensing issues. The helix license has been renewed and the ansys license renewal will be wrapped up today. Purchased a number of items for different people. Most items have been delivered. Assisted Gina with a couple of procurement items.
- Going over the couple of server boxes and making some minor changes to the new builds. They will be installed in the next few days.
- Working out items with PMA concerning the installation of another air-conditioning unit in the computer room.
- Worked on a couple of pc's to get them cleaned up and patches up to date.
- Worked with Veronica on a couple of different web issues.
- Added a couple of new users and waiting on paperwork from a couple of others wanting accounts.
- Made a number of modifications to e-mail aliases and working on setup of new mailman lists.
- Assisted the Wilson House people on getting things setup on a new server. Also, had to do some troubleshooting, once again the patches turned on a service which caused some problems on one of their boxes.
(Veronica)
- LSC: Postings of the March meeting's presentation files. Updates of the meeting website, user support. Updates of the database of technical papers, and the website for internal publication reviews.
- LIGO: Continued work on the LAAC backend database. Updates of the internal pages, the homepage and its MIT mirror, other miscellaneous web updates. User support for the LIGO seminar presentation by Braginsky group. High-resolution images for several publishing agencies.
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Systems
Modeling and Simulation
From: Hiroaki Yamamoto hiro@ligo.caltech.edu
AdvLIGO LSC/ASC design using FP arm model with quad suspension (Osamu)
We compared the maximum lockable test mass speed for using raw error signal and for using normalized error signal which is used in iLIGO. We noticed that the normalized signal has no advantage for the lock acquisition time because ringing happens in long and high finesse cavity, and it flips the sign for both raw and normalized signal. We proposed the guidelock algorithm which continuously predicts mirror speed and mirror position and applies maximum force to reduce mirror speed until locking servo can catch lock. Optimizing the guidelock gain which connects the demodulated signal to the mirror position can maximize the lockable mirror speed up to 280nm/sec. This speed is about 11 times faster than the maximum mirror speed using raw/normalized error signal. This guidelock may operate full interferometer all the night and sometimes in the daytime. If we use both the guidelock and SPI we may operate AdLIGO all the time.
Static IFO simulation (Hiro)
- Helped Yanbei, Mihai Bondarescu and John so that they can use SIS program to simulate cavities with Mexican hat and cone mirror. The code was modified so that these anomalous cases can be properly handled.
- Code development for the coupled cavity continued.
- Several calculations to understand the scattering loss issues. Details will be reported as a part of the Thursday meeting with John Stover.
Modeler - e2e simulation engine (Hiro, Bruce, Melody)
- Bruce worked on the Implementation and testing of stand-alone User Defined Primitive files (.udp files) in modeler.
Mechanical Simulation for advanced LIGO (Sany and SLU team)
Continued e2e modeling of AdvLIGO Input Mode Cleaner (IMC). With realistic seismic motion input (translational motion in the X-arm direction only) to the base of HAM-SAS model and the triple suspension model (based on M. Barton’s mathematica model) placed on the HAM table, the IMC locks very stably. The frequency dependence of the computed IMC length fluctuation is similar to the requirement (P. Fritschel, LIGO Note T060075) in the frequency range of 0.1 – 10 Hz (5e-13 m/rtHz at 0.1 Hz and 5e-17 m/rtHz at 10 Hz), except for an order of magnitude higher peak at 1 Hz, and a factor of two higher peaks at 2.8 Hz, 3.8 Hz, and 5 Hz. All these peaks appear in the spectrum of the triple pendulum’s position motion, indicating that the local damping needs to be improved. Currently the triple pendulum model assumes the position Q-value to be infinite.
ALFI : e2e front end (Melody)
- Continue working on ALFI enhancements for the UserDefinedPrimitive support: Finished fixing dialog to display the default MemberDecl and Constructor settings correctly for UDPs and FUNC_X primitives
- Started working on allowing port placements for UDPs.
Seismic Isolation
From: Ken Mason kmason@ligo.mit.edu
BSC Seismic System Assy & Test
- The BSC isolation structure assembly was disassembled and sent out for cleaning. Arland Tool picked up the 9 large componants, removed the helicoil inserts from the optics table, and packed the parts in crates. The crates are scheduled to be picked up friday for shipment to Galli & Morelli. All of the smaller machined parts along with the hardware was shipped to Bob Taylor at Caltech.
Ham Single Stage System Design
- The FDR was held 3/1 at HPD in Boulder Colorado.
From: Ben Abbott abbott_b@ligo.caltech.edu
All new activity since last weekly is written in red.
40m:
DCPD
- The new DCPD PCB is back, and will be stuffed soon.
- I installed the relay and switch for the PSL enclosure interlock. When the enclosure is opened, the shutter trips. When the enclosure is closed again, the shutter does not reset until the reset button is pushed.
HAM-SAS:
Custom Electronics chassis: (# needed + #spares)
- LVDT Driver (2 + 1) -2 Installed the spare is stuffed, but needs boxing and testing
- LVDT Interface (2) Installed
- Stepper Motor Interface (2 + 1) - Installed
- Coil Driver Interface (1) - Installed
- QPD Whitening (2 + 1) - 2 Installed, 1 spare here, needs testing and boxing.
- QPDs (4 + 1) - 4 in electronics lab, 1 is just a bare board and I'll keep it for a spare board.
- Guralps Interface (1 + 1) - 1 installed, 1 built but untested.
- AA Interface Rev 4 (1) - Installed
- AA Interface Rev B5 (1) - Installed
- AI Interface Rev 3 (1) - Installed
- Coil Driver (4 + 1) - Installed
- In-Vac Breakout boards (2) Installed
Commercial Electronics:
- Opteron Processor (1) - Installed
- Stepper Motor Driver (4) - Installed
- I/O Chassis (1) - Installed
- Power Supplies (2) - Installed
Miscellaneous:
- In-Vac Accuglass cables (13) - Installed
- Guralps cables - Specialty cables from Guralps Instruments Ordered 12/21 quoted a 30 day lead. They have been shipped to LASTI, and await installation by Dave or Alberto.
- Special cable connecting the LVDT 25-pin Witness board connector to the 9-pin ADC connector - Installed
- The 5 L-COM cables that were short were delivered to Alberto last week. Marie told me that Riccardo came and picked them up after Alberto had left for the day. I assume that Riccardo installed them.
- The decision has been made to read back the stepper motor steps so we can keep track of the actuator position when we move the steppers. The first stage of this effort will be to move the motors manually via the front panel, and read back the RS232 signal that records the # of steps through the PCIX adapter module to a terminal window. Alex installed computer control of the stepper motors, and it seems to be working fine
- The RS232 to PCIX adapter board has arrived. Alex has been using it to control the stepper motors.
- Of the five coil drivers sent from Italy, two do not work. David and Alberto have installed one of the remaining unmodified coil drivers instead. Chub in the back shop has finished troubleshooting these boards, and he says that they now both work just fine.
- I have finalized the system schematic, and it now agrees with the observed controls pinouts.
- The new in-vac specialty cables from Accuglass and PEEK zipties failed the first clean & bake cycle RGA scan, so Bob will clean and bake them again. They were shipped to LASTI.
- The stainless zip-ties from Accuglass, and bolt-down tabs will go into a bake oven when one opens up.
- I ordered a quick turn-around adapter cable from Accuglass to flip an erroneous pinout in the Vacuum. It is on Riccardo's desk, and he said that he will bake it out using an oven from Italy, and mail it off next week.
ISI:
- ISI Interface - (3 + 1) I sent around an email with the requirements for this board, as I see them. I got some feedback at Friday's meeting, and so I'm working on the schematic now.
- GS-13/L4C Emulation Module -One got stuffed, and needed some modification. I cut another PCB, and it should be coming back early next week. The parts will be here tomorrow.
- GS-13/L4C Control Module - -One got stuffed, and tested O.K. The front panels for both boards are being made now.
- GS-13 Boards - I shipped off four complete boards.
- Coil Driver - (3 + 1) (Mohana) - Two Coil Driver chassis are complete, and look really good. One is tested, and the other awaits testing, two more will be coming soon.
- STS-2 Emulation Module - Mohana has finished testing this board.
- STS-2 Control Module - One board is being stuffed, and it will be tested tomorrow.
Suspensions
From: Norna Robertson <nroberts@ligo.caltech.edu>
- Used MATLAB model of quad suspension to consider the effects of varying the "d" values ( vertical offsets of attachment of wires from plane through centre of mass) to aid in discussion of choice of these values with respect to ease of assembly of stable suspension.
- Updated Adv LIGO SUS schedule with Janeen and Jay.
- Progressed discussion on timing and structure of Enhanced LIGO review
- Call for nominations for OWG election sent out
From: Janeen Romie <janeen@ligo-la.caltech.edu>
Enhanced/Advanced LIGO
- Overseeing fabrication of OMC parts. Communicating with Calum, Chris & Norna daily.
- Coordinating delivery to Caltech of procured and fabricated parts.
- Answered questions from Mike and Ric on OMC and ring heater shield drawings.
- Mike Gerfen said that "it would be tight" to get April 9th delivery of OMC structure.
- Provided a list of initial LIGO osems needed for prototypes and all production suspensions to Norna and Justin.
- Talked to Joe LaCour on the new earthquake stop design.
- Worked with Norna, Helena and Jay on suspensions schedule update for Dwight, submitted yesterday.
- Provided a PowerPoint presentation on Advanced LIGO suspensions to Outreach.
- Attended the LSC last week.
From: k mailand kmailand@ligo.caltech.edu
Adv. LIGO
- The CES shop has completed work on the LASTI tooling assembly parts, the parts are in final assembly.
- The vertical lift elevator was tested with a 1,200# load. The last parts sent out for plating should be finished 3-29.
- All of the fit and function tests done so far on the sub assemblies have been acceptable.
- We are waiting for Ian's outer support frame for the lower SUS, we will use this frame to drill match pin locations, in both the frame, and tooling interface.
From: "Greenhalgh, RJS \(Justin\)" J.Greenhalgh@rl.ac.uk
ALUK held its latest Project Management Committee on 16th March 2007 (See LIGO-M070041-00-K).
A brief activity summary follows:
- RAL: The dirty noise prototype has been assembled and work is in hand to balance the suspension. The only part still awaited is the sleeve for the structure – but the rest of the suspension can be assembled without it. Parts for the second suspension are being cleaned ready for shipment to LASTI – target date now late April, with the critical path item being the welded structure and sleeve. Trial beam splitter structures on order for frequency tests. Most parts for laser welding duplicate machine (for LASTI) have now arrived or are expected shortly.
- Glasgow: Two sample ribbons had been pulled under computer control on the pulling jig, with good profiles. The first one had failed a load test, thought to be due to surface flaws in the silica slide feedstock. For the second ribbon, the feedstock had been flame polished and the ribbon had passed a 20kg load test (double the service load). The welding rig was close to completion. The ERM was expected around the end of March, with a "best guess" for the PM being late May.
- Birmingham/Strathclyde: Parts for 35 OSEMs now being prepared for assembly. IRLED burn-in rig complete and being used. Satellite box (to amplify the OSEM signals) prototyped. Coil driver design has been the subject of extensive discussions but design now close to agreement – need to avoid further delays; hoping to get parts to LASTI in early July. ESD circuits tested satisfactorily.
- Overall: We are still working hard to get the noise prototype to LASTI as soon as possible. A slip of ~six to eight weeks in delivery of the mechanical parts to LASTI, and of ~three months to the monolithic stage assembly, compared to plans of October 2006, seems likely. Current plans/expectations/ambitions are to get mechanical parts to LASTI in mid-late April, to deliver the ERM at the end of March and the PM at the end of May. Close discussion of plans is being maintained with the LIGO/LASTI groups. The PPARC Oversight Committee (OsC) met in March and the outcome was positive overall.
From: Chris Echols <cechols@ligo.caltech.edu>
- Output Mode Cleaner: All parts related to the intermediate mass are being manufactured at the CES shop at Caltech; the coil-holder and brackets are being manufactured by the aero shop at Caltech, and parts for the wire jigs and blades are being manufactured by the physics shop at Caltech. Scheduled deliver for all these parts is 6 April.
- AdLIGO Layout: the endstation vacuum system layout is in progress.
Core Optics
From: Bill Kells kells@ligo.caltech.edu
This week has seen intense effort to appreciate all our to date TM scatter/loss analysis and data. Reason? In preparation for (and occurring as we speak) our meeting with scatter expert and now consultant J. Stover. We have learned a bunch of interesting and informing detail from him, though not profound, view altering, insights. Our measurement program is significantly guided.
Just previous to this (last week, in prep for the lSC) I have prepared a summary of all our observations concerning TM loss. It can be fond at LIGO T070051-00
From: Helena Armandula ahelena@ligo.caltech.edu
The LASTI test mass is on its way to France and expected to arrive this Friday.
As suggested by LMA, we decided to pre-anneal the substrate at 900 degrees C, a standard process used for VIRGO optics. This process last about 9 days and it is done to suppress the residual stress in the substrate incurred during polishing. Then they will then check the quality of the substrate (roughness, defects, wavefront).
The time table for the coating is as follows: Side 1 will take ~ week, including calibration and coating runs. For the AR side, 3-4 days are needed.
At this time, they have not decided yet if they will anneal the optic after the HR coating and also after the AR coating (that means 2 annealing procedures, so, about 1 week time) or, if they'll do only 1 annealing procedure. Complete characterization of the optic (scattering, absorption maps and wavefront measurements will require ~ 1 week) So, if they start at the beginning of April, the mirror can be ready by the end of April.
From: Liyuan Zhang <zhang_l@ligo.caltech.edu>
Two LMA 2" mirrors (T=0.3% and 5% respectively) for Riccardo's experiment have been scanned using the integrating sphere, they both have an averaged scatter of about 5.3 ppm, with a 'microroughness' band around 3-4 ppm and some point scatters of up to hundreds ppm. While the band position is close to that of the REO 1" mirror, the density of point scatters is a bit less, which is consistent with Helena's observation under microscope.
Auxiliary Optics
From: Phil Willems willems@ligo.caltech.edu
Enhanced LIGO TCS
We have gotten our AOM back from IntraAction and are realigning our CO2 laser table at Caltech around it. We're still not getting as much diffraction efficiency as we expect yet but at least the diffracted spot goes in the right direction. We have also measured the voltage noise spectrum of our two new HgCdTe photodetectors and are preparing to measure their saturation curves. We will also look for nonuniformity of sensitivity across their faces due to the transverse structure Mike Zucker alerted us to. We have requested a quote from II-VI Corp. for axicons to efficiently convert the CO2 beam to an annular profile.
(Tobin Fricke, Phil Willems)
Test Mass Absorption Measurements
It was hard to tell from the crappy slides Mathematica displayed during my presentation at the LSC meeting, but the absorption of all twelve test masses has been measured using the frequency shift technique, and the results generally fall at about 4-5 ppm for all the mirrors.
(Sam Waldman, Phil Willems)
Photon Calibration
I began modelling initial LIGO mirrors for their elastic response to photon calibrator pressure and to OSEM forces. In particular, the bowing of the LIGO ETM from the magnetic force applied near the optic's edge causes an apparent surface motion that will introduce displacement error at the ~10% level at 2 kHz. I compared results for GEO600 with Stefan Hild while he was visiting Caltech.
For additional information about this report, contact Albert Lazzarini or Phil Lindquist