Weekly
Report for Week Ending March 15, 2007
Past Weekly Reports
There will be no LIGO Executive Committee scheduled
Monday, March 19, 2007 due to the
meeting of the LIGO Scientific Collaboration scheduled next week. A meeting has been scheduled for Monday,
March 26.
Special
Announcements:
Weekly Report
Highlights
No report this week. LSC Meeting next week.
LIGO
Laboratory Administration (Lindquist)
STATUS OF LSC MOUs
(Lloyd)
Received
revised Goddard, Penn State, Rochester,
and Wisconsin MOUs. Penn
State and Rochester were routed for signature to Peter Saulson yesterday.
Goddard and Wisconsin
are in the process of being assigned DCC numbers and then will be routed to
Peter, probably at the end of today.
PROPERTY MANAGEMENT (Luna)
>
- Assisted the LLO (A. Sibley) in requesting
disposition instructions for one GSA Vehicle.
- Attended Caltech's cost transfer training
session presented by the Project Accounting Office.
- Successfully obtained a Carnet to Export /
Import without any restrictions the aluminum parts that are going to be
cleaned by Galli & Morelli
in Italy. Account Number
LIGO.BSCCH-5.18-NSFLIGO.FY02CA.
- LHO FY07 Equipment Inventory is complete; all
assets were accounted for and updated in Oracle (Caltech's property
records system).
- LLO FY07 Equipment Inventory is completed,
twenty seven assets were not found, the rest were updated in Oracle
(Caltech's property records system).
Ed Jasnow, Joe Giaime,
and I are working on the missing items.
- Continued working on LIGO's
Equipment Inventory @ CIT.
- Assisted Joe Giaime by
providing copies of the Property Reports for FY03, FY04, FY05, and FY06.
DOCUMENT CONTROL CENTER (Turner, Mak)
>From: Cleveland Mak
<mak_c@ligo.caltech.edu>
- Processed a number of MOU attachments.
- In the process of transporting/packaging boxes
of miscellaneous documentation and other items currently located in the
hallway right outside of the DCC.
- Scanning Update - Progress continues on scanning
of miscellaneous large/bulky "M" documents on file.
Document Management System - Plan B
(Lindquist)
Notes
from Friday, March 10, 2007:
I.)
David - reported practical experience with DocuShare
including discussions with sales reps and engineers as well as additional
experience with the IceCube system and a trial
version installed at MIT.
Response
times reported as acceptable.
A
trial version with licenses for 50 users will be set up for the upcoming
LSC-VIRGO meeting to be used for public posting of documents. Will work with DocuShare to allow multiple users as needed.
II.)
Albert requested the committee to fix some kind of schedule.
III.)
Question posited by Joe: should we switch to a new number format? In DocDB this would
allow us to latch onto their versioning system.
Minimizes customization. Would need to set up
keywords to capture important document information.
For
the first time we began to get into the needs of Engineering for drawings. Their intent is to download PDM works
documents, etc., into the document management system for archiving.
David
and Joe assumed actions to considering the question of versioning for
engineering during future trials of the systems.
Dennis
suggested that there must be documentation concerning how others have addressed
this problem.
IV.)
We discussed document migration. We do
have the old stuff in a data base that we know how to read. The DocDB developer
(at Fermi) could be hired as a consultant to see what would be required to
convert the database to DocDB. It was suggested that we should start with a
new system without requiring an immediate conversion and possibly leave the old
system as a "frozen skeleton."
FINANCIAL SYSTEMS (Funaro,
Brambila, Kaufman)
>
>From: "Brambila,
Ruth" <Ruth.Brambila@caltech.edu>
- Completed the purchase of the vehicle for LLO.
- Transferred funds on the MIT subcontract as
required for payment.
- Working on the change order to Galli and Morelli.
- Followed up on the status of the equipment
maintenance orders for LLO and LHO to be issued to Dynamic Systems, due on
4/1/07.
>From: Florence Kaufman <fkaufman>
- Posted Updated Account Number List on the LIGO
Internal Bulletin Board.
- Prepared and posted on the network a new report
for AdLIGO accounts which provides more detailed
information than that provided in the monthly financial report.
- Submitted two New Fabrication Requests and PTA
Set Up Forms for AdLIGO
AOS Systems.
- Submitted new Award Set Up
Form for the I2U2 Award.
- Financial reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone
<gsalone@ligo.caltech.edu>
- Completed the purchase of a 2007 Ford 500 sedan
for LLO. This replaces the
Chevrolet Impala, which was returned to the GSA.
- Finalized an agreement regarding the invoice
amount owed to Ezus-Lyon. There had been some confusion because
of a credit erroneously charged to the contract. The finalized amount owed is e16, 977,
or $22,579.
>From: Ed Jasnow
<jasnow@ligo.caltech.edu>
- Ed Jasnow, Stan
Whitcomb, and GariLynn Billingsley attended the
successful kickoff meeting for the Advanced LIGO Pathfinder optics
polishing contract with CSIRO in Sydney,
Australia. CSIRO had already received the substrate
for polishing, and provided a tour of the facilities to be used in the
polishing effort. A briefing was
also given concerning CSIRO efforts to privatize by being acquired by a
larger company. The Australian
Government has set a deadline of September 30, 2007 for the completion of
this effort.
PROPOSALS and REPORTS (Lindquist)
LIGO is preparing a proposal to the NSF for
Continuing Operations for FY 2009 through FY 2013. Activity this week
focused on a straw man budget projection and an analysis of the effect of
changing the indirect rate structure as defined by OSR.
The Large Facilities Monthly Report for the
end of February has been prepared and sent to the NSF.
CHANGE CONTROL/CONTINGENCY MANAGEMENT
(Lindquist)
- There are no open change requests.
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa
<cindy@ligo.caltech.edu>
- The next Staffing
Committee meeting is scheduled for Tuesday, March 27th, and the
minutes and action items for the last meeting have been posted on the SC
web page.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
- Working action items from LIGO Safety Committee
(first meeting).
- Working with L. Turner to gather LIGO Safety
document comments/revisions from reviewers.
- Started
preparations (agenda) for next Safety Committee meeting, 20 March 2007.
LIGO Hanford Observatory (LHO) and Interferometer
Operations (Raab)
Summary of S5 Activities at LIGO Hanford
Observatory (compiled by K. Kawabe)
The duty cycle (Thu Mar/8 to Wed Mar/14
2007) of H1 was 85.1 percent with typically 15 Mpc inspiral binary range. The
duty cycle of H2 was 74.6 percent with 6 - 7 Mpc range.
Summaries: Range
and Duty Cycle update. Tuesday
maintenance summary.
Highlights from the LHO elog:
- Good Scimons found
2 hour periodicity for H2 excess noise. During noisy time, 1.2
Hz stack resonance was found to increase quite a bit for H2, and this
apparently started after the change related to DARM -> PZT feedback
path.
- Later above mentioned 1.2 Hz noise was
identified to be an
aliasing of elevated 0.2 Hz noise in tidal feedback path that has 1 Hz
updating rate. It's not clear where this 0.2Hz is coming from with 2
hours period, but it was clear that the change in PEPI hardware LPF (from
0.1Hz single pole LPF to double (1 +- i) Hz pole pair) made the aliasing
problem worse. Tidal feedback gain for H2 was reduced and the problem seems
to be gone, though the real fix of making the tidal sequencer update
faster is yet to be done.
- Following a series of measurements done to L1
and H2, test
mass absorption measurement was performed for H1.
- After the Tuesday maintenance, 12
Hz bounce mode peak in H2 became much larger than normal, which later
was tracked
down to the fan in Mid Y station. Though it was not clear how 12 Hz
was excited, we are running
with another fan at the moment.
- Scimons have been reporting many times that corner
station roof radio channels are broken and Z accelerometer on ISCT10 is
higher than PEM reference (e.g. this
elog entry). Robert Schofield looked at both, radiometer was fixed,
and he concluded that ISCT10 table and the Z accelerometer were not
behaving bad.
- Robert also revisited the LVEA radio coupling. It
seems as if the gain of all of the channels were increased by a factor of
10.
- Scattering
as a possible source of H1-H2 correlation is being investigated.
- Recap
of H1 TCS rotator code change was posted.
Other things:
- Fortunately we didn't have any problem related
to earlier-than-usual DST change, which happened on Sunday.
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Giaime)
No report.
Mechanical
and Optical Systems (Coyne)
See Advanced LIGO
Controls and Data Systems (Bork)
See Advanced
LIGO
40-Meter Interferometer (Weinstein)
IFO
Commissioning, DC Readout, Electronics, Controls, Computers
- Last
week, our NPRO power dropped by 30% (which we believe is due to the pump
diode), and it hasn't recovered (but it hasn't gotten worse). The MOPA is
now only putting out ~ 3 watts. Steve opened up the MOPA to visually
inspect the NPRO, and didn't see anything suspicious. We need more power!
We are looking for a spare NPRO.
- Steve
redistributed the remaining power so that a sufficient amount goes into
the main interferometer, leaving the squeezer optics with almost nothing.
- Ben built
a latching relay box so that when the PSL enclosure interlock is broken
(by the enclosure door being opened without deliberately bypassing the
interlock), it stays broken until it is manually
reset. There's a problem with the bypass function, which Ben hopes to fix
soon.
- Tobin,
Rob, and Sam exercised the "pringle"
code that Alex installed here last week. They excited the pringle mode of the test masses and adjusted the gains
to minimize the coupling to POS.
- Sam and
Tobin continued their commissioning of the new dither-alignment system.
They turned up the dithers till they got coherence; adjusted the
demodulation phases for the YAW half of the system, and automated the process.
They measured the ITMX, ETMX, and PZT sensing matrices, and inverted to
get the control matrix. However, the resulting system wasn't able to
improve the alignment. More work is required.
- Rob
returned to PRFPMI locking, which went pretty smoothly. Started measuring
some frequency noise TFs, but was stymied by
test point/syncing problems in the c1omc.
- Rob
struggled with a slew of test point problems in the controls,
necessitating some front-end CPU reboots. Not sure what is causing these
instabilities. He also struggled with some flakiness in the communication
between the EPICS slow controls and the front-end servos, necessitating a
reboot of c1losepics. He will consult with Alex and Rolf.
- Rob
switched around some cables and RF photodiodes, so AS166 became AS33 and
POX33 became POX166. He thinks this PD setup is more useful for us in the
near term. We'll probably want an AS166 back when we go for RF-DC
comparisons with the full DRFPMI.
- Mike
installed DST patches on our Solaris machines, and Tobin took care of the linux machines.
Vacuum
Squeezing
- Go is in Japan. At NAOJ/TAMA, he gave a talk on progress
with vacuum squeezing at the 40m.
He'll give a version of this talk at the LSC meeting, and we plan
on having a get-together there to talk about the recent results and the
next steps.
- As noted above, our
dying laser leaves almost no beam for the squeezing setup.
Thermal Noise
Interferometer (Black)
- Greg has finished the spot-size measurement and
found it to be equal to our spec within his measurement uncertainty. We had assumed 160 microns for the spot
radius, and he finds 163 p/m 10 microns.
We also found that the coating thickness we had been using in our
analysis was for undoped coatings.
Laurent Pinard of LMA sent us the doped-
coating thickness, and it is about 6% larger than that of the
undoped. This correction would change our noise floor by about 3%.
- Akira is at Hanford, and he has been working on a
refinement of our model for H, the servo filter transfer function. He now has a model
that is more accurate than the old one by a few percent, and we are
in the process of incorporating that into our analysis.
- The big news is that Akira discovered that our
cavity length is about twenty percent longer than what we thought it
was. At the edges, the mirrors are
very close to being a centimeter apart (our design spec), but we neglected
to take into account the radius of curvature of the mirrors, which is one
meter. It turns out that the concavities add about 1.3mm at each mirror to
the cavity length. Taking into
account the center of mass shift and the measured separation at the mirror
edges, our cavity length is actually closer to 1.21cm than to the spec of
1.0cm. This brings our measured
noise floor for the doped- tantala coatings closer to the prediction from
the Q measurements, but it does not account for all of the discrepancy.
No report.
CIT Science Group (Weinstein)
Eirini Messaritaki
- I worked on the null stream implementation for
the S5 inspiral searches.
- I tried to apply the null stream test on the S3
SBBH candidate events and on some known glitches. SBBH application proved
a bit challenging due to the fact that the code currently does not handle
BCV-Spin templates; more work required on this.
- I worked with Vibha on producing the chisq
vs snr plots for
spinning injections recovered with SPA templates.
Kent
Blackburn
OPEN
SCIENCE GRID VALIDATION TESTBED
- No VTB activity this week.
OPEN
SCIENCE GRID INTEGRATION TESTBED
- Setup new catalog, scripts and pegasus components for
testing new algorithm for producing and supporting data cleanup dags.
- Validated new 0.6.0 installation on OSG_LIGO_PSU
with nanoHIPE.
- Fixed OSG Twiki
documentation on Locating Storage Elements so that examples are valid with
Glue 1.2 schema in the case of Storage URLs.
- Documented on OSG Twiki
how to set site specific attributes to overwrite incorrectly configured
attributes.
- Attended weekly DASWG, ITB, Pegasus, VTB and
telecoms.
OSG
DEVELOPMENT ACTIVITIES
- Submitted title, author list, abstract and
acknowledgment to LIGO directorate for an advanced workflow technical
paper.
- Worked with PSU on issue associated with being
able to test advanced workflow tools off their OSG head node.
- Interviewed OSG applications support person. Meet with Cindy and Florence regarding HR and account
aspects of new hire.
OSG
MANAGEMENT ACTIVITIES
- Reviewed and commented on proposal to allow
commercial entities into the OSG to the Executive Team
- Reviewed and approved agreement between OSG/Fermilab and EGEE/CERN to support a full time editor
for the iSGTW newsletter.
- Continued work on Statements of Work. Continued working on Change Control
Requests associated with OSG's WBS.
- Tracked down Caltech's OSG subaward
contract location with help from Gayle Lund.
- Attended weekly OSG
Executive Team Meeting.
Patrick
Sutton
Coherent
Network Analysis
- Added ability to perform GWB simulations to the
X-Pipeline GRB triggered search package.
- With Michal Was,
studying results of running the X-Pipeline GRB package on the LIGO-Virgo
WSR1 exchange data, for presentation at the burst face-to-face meeting.
- Met with Tinto, Messaritaki to discuss null
stream use in inspiral searches as a veto/consistency test, particularly
for high-mass BBH searches which are troubled by low-frequency H1-H2
glitches.
- Reading Poprocki's
undergraduate thesis (College
of Wooster) on
"Bayesian source direction determination for GWBs".
Reviewing results and compiling comments on the thesis.
Other
- Discussed
heterodyning for pulsar searches with Patel.
Xavier
Siemens
- Finished h(t) frame writing code (that took most of the week).
- Prepared presentation for the Pacific Coast Gravity
Meeting
Laboratory
Computing (Anderson)
LDAS Software Systems (Maros)
- The core dumps observed when running the beta
release of LDAS have been identified and code corrections to address each
of them are currently being tested on tandem systems.
- Under heavy createRDS
production, it has been observed that some jobs are not returning. This is
under investigation.
- The flushing of jobs from cmonClient
still fails under some circumstances. Suppression of the NoOp ping to servers which do not have the NoOp command has been implemented.
- The cntmonAPI is being
modified to support outputting the nightly test results.
- LDAS was tested using version 1.8.483 of the
software. All of the system tests passed.
- The createRDS tests
scripts have been modified to support S5 data sets and generate L1, L3 and
L4 RDS for this data set.
- The function snedCmd
in pipeloop.tcl has been modified to prevent an
infinite loop. The allows dcmean
test to run without terminating prematurely. The memTest
function has also been modified in an attempt to prevent a similar
infinite loop.
- A new loop test is being developed which will
continuously test the getFrameData command. The
command is based on the usage model seen on ldas-cit.
- The LDASJobH now supports
an environment variable to specify the timeout value for a job as some of
the test jobs now run for a longer time than previous allowed.
LDAS System Administration (Anderson)
Caltech
(Dan Kozak)
- Working on crashing Solaris servers at CIT.
Currently testing a patch from Sun.
(Phil Ehrens)
- Upgraded/patched 5 computers used by the e2e
group.
- Supported Dan Kozak
with ldas-cit server issues.
- Maintenance and bug fixing of log_mon.tcl to reduce amount of email sent when large
numbers of machines are affected by server failure.
- Patched travel auth form and visitor application
form to support lowercase hexadecimal alphabetic escape sequences as
generated by the lynx browser.
(Erik Espinoza)
- Worked with Larry on acrux
ClamAV issue.
- Assisted with crashes on the Condor side.
- Rebooted nodes that were hung after nfs issues.
- Worked w/ Condor team on X509 forwarding.
- Investigating trunks + solaris.
- Rebuilt node219 after double disk failure.
- Working w/ Larry on DNS Replacement.
MIT
(Fred Donovan)
- Expired certificates affected logins.
- pcraid 4 swapped out 3Ware; needs 2 new disk.
Livingston
(Igor Yakushin)
- Gateway crashed twice this week: the first time
the error messages indicated a problem with the mirror on which / file
system lives. However, the system rebooted cleanly without problems
and there was no indication in the logs or output from metadb, metastat
what disk had problems. There was no orange light on any of the disks
either. Log messages on gateway and 3510 indicated a possible problem with
one of the 3510 disks but the disk has not failed yet and it is unlikely
that it could cause gateway to crash even if it did fail. The replacement
disk from SUN arrived. About 3 hours after the second crash gateway
came up by itself, again nothing in the logs showed what the problem was
and there were no 3510-1 error messages during that day. Considering that
dataserver and gateway started crashing recently at CIT, it all might be
related to the recent upgrade to Solaris 10 Update 3.
- One of the power strips for the nodes shut down
twice this week. Ordering replacements.
- Due to nodes problems there were several
diskcacheAPI crashes this week.
(Dwayne Giardina)
- Replaced memory in nodes 158 and 159, node159 is
now reporting problems with /usr1 filesystem.
- Replaced hda in nodes 95 and 190, node190 has
died again.
- Need to check sendmail config on all LDAS
machines, clear mail queues and restart sendmail service.
- Moved beowulf to an unused node machine, the old
beowulf machine is now ready to become ldas-condor.
- Gateway crashed twice, the first time was
sometime Monday morning, rebooted machine and was OK for a while.
crashed again Wednesday night, but apparently restarted itself after a few
hours.
- Restarted condor on 68 nodes after condor died
for yet to be determined reasons, but most likely related to gateway
crash.
- Tape storage eject.
- Tape eject and shipment.
Hanford
(Ben Johnson)
- Archiving was stalled from the 8th to the 13th
of this month due to my forgetting to copy over /var/opt/SUNWsamfs/catalog
from the original dataserver disk.
- Staging was also in a bad state this week (i.e.,
not work). The cluster is still severly slown down, most likely due to NFS
waiting forever for data it will never get.
- Have a stable NDS client for Windows 2000/XP and
Matlab 2006b and 2007a. It only works with non-trend data at the moment.
The client also works on Mac, Linux, and Solaris.
General Computing (Wallace)
MIT
(Fred)
- Setup web page /cgi for conference registration
GH desktop gnome issues; pc laptop issues;
- Reconfiguration ldap/nis automount tables to
accommodate some home dirs move from gar to nova
- Set up docushare (window and unix) for
conference -More issues with catfish email firewall; will add 2nd nic to
ligo -Last of dst fixes over (this last) weekend
Livingston
(Dwayne)
- Continued preparations for the LSC meeting
- Network issues appear to have been related to
DNS and possibly DST patches. NS1and NS2 had incorrect time, we
reset via ntpdate. built a replacement for bartholomew, which went
live today. building a replacement for NS2 this afternoon.
- Users reported problems running qscan on
chestnut. The cause was /archive which is served by ldas-gateway
that has crashed twice in the last
week.
- The projector in the SEC classroom has
died. The manual says the solution for the particular combination of
blinking lights is "contact your vendor". Installed a
temporary replacement.
- Spam filter cleanup
- Other usual user requests and support
LLO mail summary for 22 February - 1 March
2007:
Rejected:
9,758 (127 containing virus)
Accepted:
4,453
Total:
14,211
(Shannon)
- LSC meeting prep has taken most of my time for
the last week.
- set up NAT router, DHCP server, DNS proxy, etc.
for the meeting.
- received loaner/eval WAPs from Foundry. Testing
is ongoing for these. If it works well for the LSC meeting, I
will consider using these on my network at LLO on GC.
- ordered various bits and pieces of needed items
for the LSC meeting.
- working with Cox Comm. on the network
connectivity for the meeting.
- had to work with the telecom guy at the hotel
to track down various interconnections between the conference area,
network closet, etc. at the hotel.
- Helped Dwayne in replacing our 130.39.245 DNS
server.
- Investigated what looks like was a DNS zone
transfer failure. This had fallout for CDS/DMT at LLO. DMT
evidently cannot handle a timeout of a primary nameserver. Most services
just roll over to the secondary, but something in DMT prevents this.
- Went over IDS logs, etc. Still need to
eliminate many false positives. *really* need a management solution
for snort configs.
Hanford
(Christine)
- Returned to configuring the new
router/switch. As this is a switch that does routing, it has taken a
while to figure out how to tell it to route not switch. There are a
lot of configuration items that are set as defaults that I have never seen
before. I'm having to search the Cisco web pages for documentation
on each unknown configuration to figure out what it does. I will be
testing the new router on Tues. 3/20.
- Set up another MAC laptop for a user. I'm
using the CIS guidelines as the base security configuration.
Couldn't get Matlab 7.3 or 7.4 to work on the MAC. Investigating a
rumor that 7.2 was the last version to work on the Intel MACs.
- Vern discovered a new ssh/sftp/scp GUI for
Windows that works with PuTTY. Looks pretty good, does more than the
SSHWin3.2.9 software.
CIT
(Mike)
- Finished up the DST patches on a number of
machines.
- Reset some of configuration files our Solaris 8
boxes. After installing the patch_cluster to get the DST patches
installed, sendmail and a few other services were turned on. After this I went
around checking to see what other services were turned on, with all of our
Solaris servers 6, 7, 8, 9, & 10. Larry found some issues with Solaris
10, we almost lost a mail server behind the patches.
- Setup GDE conference for Barry Barish over in
East Bridge.
- Added multiple users to the wireless access
points.
- Spent more time looking into the Primavera
licensing. I think things are now worked out. I am also working on a
backup scheme for the Primavera database. For now I'm doing manual weekly
backups.
- Additional user support and other sysadmin
tasks.
(Christian)
- Installed monthly Microsoft security patches to
all Windows 2000 and 2003 servers.
- Paul Russell- Installed and configured new
system for Paul.
- Gina Salone- Needed loaner laptop to be
configured so she can login remotely and work from home.
- Updated display case system with the latest
security patches.
- Setup laptop and wireless router for the GDE/EC
meeting.
- Other misc.: Continued onsite software/phone
support.
(Veronica)
- LSC: Ongoing support of the March
meeting: Improvements of the database of participants to make it
more user-friendly; an application to generate a payment report; helped
Bonnie with access to/working with the database. Updates of the LSC
mailing lists. Working on converting the roster data into a portable
format for a new roster utility. Updates of the database of
technical papers, publications for review, other miscellaneous web
updates.
- LIGO: Continued work on the homepage redo;
the changes have been ok'd by Jay, continuing work on the layout and
content generation. PAC website update, other various web updates.
- CaJAGWR: Website update /user support.
(Larry)
- Worked a number of licensing issues. Some time
spent with Mike and others working on the Primavera contract. Made
some minor purchases of computer items for different people. All of the
items received have been delivered. Still waiting on a couple of small
items. Working on the purchase of a couple of laptop units.
- Worked with Mike in finishing up the DST
patches. Only one machine came up with the incorrect time but it did not
affect anything and reloading the patch solved the problem. The
latest set of microsoft patches has caused some problems with a couple of
notebook units. They would get the blue-screen, backing out the patches
solved the problem. Still need to check out why the patch is causing the
problem. The issue has been sent to Microsoft.
- Installed a new OS on a couple of different
boxes.
- Worked a variety of mail alias items.
- Setup a new account and modified a couple of
others.
- Worked some air-conditioning issues.
- Assisted with some h/w installations in room 19.
- Assisted Mike, Christian and Julie with the
GDE/EC meeting.
- Worked with a number of people on the LSC
meeting taking place next week.
- The usual end-user assistance.
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Systems
Modeling and Simulation
From: Hiroaki Yamamoto hiro@ligo.caltech.edu
e2e weekly meeting
SLU group explained their analysis of the
frequency noise induced by the advLIGO MC. They are improving the
analysis, like a realistic seismic correlations among two HAMs by using
measured seismic motions.
Static IFO simulation (Hiro)
- The analysis of various measured losses due to
scattering (large cavity, small cavity and integrating sphere) are
underway to understand their implications.
- The studied of the effect of the aperture size and
thickness of the BS and the physics thermal deformation on the ITM and ETM
test masses are summarized in T070052 and it will be released soon.
- The code is cleaned and is installed on linux
platform for public use. This simulates three optical systems, (1)
BS, (2) FP and (3) FP with BS inside (part of a Michelson cavity).
Mechanical Simulation for advanced LIGO
(Sany and SLU team)
We continued e2e modeling of AdvLIGO Input
Optics. Jameson improved the performance of the Input Mode Cleaner’s
length sensing and frequency controls by adjusting the dc gains of the
respective control filters. Consequently, the Mode Cleaner is now locked much
more steadily. We placed this Mode Cleaner model (consisting of three triple
suspensions based on Mark Barton’s state space model) on a HAM-SAS model
(based on Valerio Boschi’s state space model), and simulated the
frequency noise on the Mode Cleaner’s transmitted light due to Mode
Cleaner’s length fluctuation. For this simulation, a floor displacement
model of the Hanford site (the standard ground motion used by SimLIGO) was fed
into the base of the HAM-SAS model. (Currently, only translational displacement
is used for the simulation.) The result of this simulation indicates that the
frequency fluctuation is on the order of 1e-3 Hz/rtHz at 0.1 Hz, 1e-5 Hz/rtHz
at 1 Hz, and 1e-9 Hz/rtHz for >100 Hz. The frequency fluctuation in the 100
Hz – 200 Hz range is four orders of magnitude better than the equivalent
calculation we performed previously for the Initial LIGO mode cleaner (single
suspended optics on the Initial LIGO HAM seismic isolation model).
ALFI : e2e front end (Melody)
Continue working on ALFI enhancements for
the UserDefinedPrimitive support: fixing dialog to display the default
MemberDecl settings correctly and allowing port placements for UDPs.
Seismic
Isolation
From: Ken Mason kmason@ligo.mit.edu
BSC Seismic Isolation Assembly and Test
We started the disassembly of the structure
on Monday. The actuators, instruments, springs, and all masses have been
removed. We are on schedule to finish the disassembly by 3/26.
Laurent has completed the design of new
tooling for installing the stage 0-1 springs. This design is flexible enough to
allow a wide range of shims to be installed.
The SEI procurement list for the HEPI
system, BSC seismic isolation system, and HAM seismic isolation system has been
completed with Carol W.
HAM Single Stage Isolation System Design
HPD has been making good progress with the
part details. They are 87% complete for the FDR scheduled for 4/2 and 68%
complete for the completed design which includes fabrication drawings and
assembly procedures. They anticipate they will be 27% over the estimated cost,
the majority of which is due to changes in scope.
From: Dennis Coyne coyne@ligo.caltech.edu
Subject: HAM-SAS 3/14 meeting notes
Achieved DC and damping controls on the
horizontal and vertical stages (separately) last week
Tried the electronic anti-spring control for
the vertical -- only managed to increase the frequency, more work to be done
Changed the tilt stabilization springs to
more compliant springs in order to reduce the tip & tilt mode frequencies
from ~400 mHz to 211 mHz and 244 mHz
Adjusted the GAS blade springs to reduce the
vertical bounce mode frequency from 377 mHz to 315 mHz
Plan to address mechanical issues before
pumping down:
- separate large masses into smaller masses to
permit tuning & allow for bouncy mass removal (350 gm)
- mechanically adjust vertical frequencies down:
- start with position scan to make sure we're at
the minimum (working point) and not bistable
- adjust cantilevered blades to reduce frequency
- if needed adjust tilt-stabilization springs
- 3) mechanically adjust horizontal stage (if
needed) after the vertical stage is completed
- 4) replace stepper motor cables (if available)
- 5) re-tap stepper motor nut to prevent seizing
- 6) keep the triple locked for this 1st pump down
- 7) pump down with controls on and adjust pier
scissor tables to compensate for floor tilt
Guralps working OK now
DTT readback for geophones does not
work properly -- Jay referred problem to Rolf, Alex
Simulation -- ongoing
Control objectives in the near term:
- DC control to level table and keep IP vertical,
and then offload to stepper motors after pumpdown
- system identification: transfer functions and
diagonalization
- electronic anti-spring for the vertical stage to
tune down the vertical bounce
Suspension
From: Norna Robertson
<nroberts@ligo.caltech.edu>
Scimon shifts at LHO
Preparing LSC presentation on OMC suspension
design
From: Janeen Romie
<janeen@ligo-la.caltech.edu>
Enhanced/Advanced LIGO
Overseeing fabrication of OMC parts. Meeting
with Chris & Calum about two remaining OMC designs. Working with Sam
and Calum on interface of OMC wires to optical bench. Sent two DCNs of
OMC drawings to Dennis for review. Coordinating deliveries and visits for
assembly and test of OMC.
Provided an update to the thermal
compensator plate drawing for Gari. Have DCN ready.
Working with Russell on the compensator
plate wire break-off prism.
Coordinating input for various LSC
presentations.
Working on initial LIGO count.
From: k mailand kmailand@ligo.caltech.edu
Advanced LIGO
The CES shop is continuing work on the LASTI
tooling assemblies the elevator mechanism, should be ready to test tomorrow.
We are waiting for Ian's outer support frame
for the lower SUS, we will use this for a dimensional fit check.
From: Bill Kells kells@ligo.caltech.edu
Actually quite a lot has been considered
(plans) this week concerning LIGO I [scatter] loss. See T070051-00 for
the "summary"
Also: PI discussions with D. Ottaway. We are
at the point where we ~fully understand each other, and there appears to be no
discrepancy.
From: GariLynn Billingsley
<Billingsley_G@ligo.caltech.edu>
Met with David Gritz of Heraeus to discuss
homogeneity of 3001 material for possible use in the beamsplitter for Advanced
LIGO.
Met with the team at ACPO(CSIRO) for the
polishing pathfinder kickoff meeting. We will need to revise our drawing to
include a reference mark for metrology purposes. We have no new news on
the privatization process, we hope to know more in September. Our
specifications, while challenging, appear to be achievable, ACPO is aware of
the contributions to loss from different types of surface error and so, is
prepared to feed back their experience into the design process.
There is a new chamber door for the coating
chamber at ACPO, it can hold two blanks of up to 400 mm diameter each.
This has been developed for another customer. There are also several new
large laps in place, presumably in support of the same project.
The LASTI ETM is ready to ship to LMA
From: Michael Smith smith@ligo.caltech.edu
SLC
I am in the process of revising the SLC
conceptual design requirements doc into two separate documents: Design
Requirements and Conceptual Design.
ETM Telescope
I am in the process of extracting the ETM
Telescope component from the PO Mirror and Tel conceptual design requirements
doc. and creating two separate documents: Design Requirements and Conceptual
Design for only the ETM Telescope.
Pre-Stabilized Laser
From: Peter King
<pking@ligo.caltech.edu>
I have been trying to communicate with the
Beckhoff Automation hardware down in the lab. The documentation on
setting this aspect up is practically non-existant.
Went through and made some comments about
the existing project laser safety plan. Bits of it need to be updated and
at the moment comments are being gathered.
The draft PSL Laser Safety plan is probably
at a stage now where it can be circulated for comments. I haven't done
this yet. From glancing at the proposed ANSI Z136.1-2007 standard there
are no changes from the 2000 edition that affect the PSL in terms of MPEs and
so forth.
I have requested datasheets from the
manufacturer of the chiller to be used in the functional prototype.
Unfortunately their website doesn't have any useful information in this
regard. The electrical requirements for the power supplies have been
obtained.
Control and Data Systems
From: Rolf Bork rolf@ligo.caltech.edu
LASTI (Jay)
- Installed remaining controls for the HAMX triple
suspension. Several of the osems on L1 and L2 need to be realigned.
- Working with Brett on new Quad suspension
control algorithms.
CDS Designs
- 4 docs in progress for conceptual design; sent
out for limited, informal review.
For additional information about this
report, contact Albert Lazzarini or Phil Lindquist