Weekly Report for Week Ending February
22, 2007
Past Weekly Reports
There
will be no LIGO Executive Committee scheduled Monday, January 26, 2007 due to the
Staffing Committee Meeting scheduled for that time.
Special
Announcements:
Weekly Report Highlights: LIGO & Virgo hold first joint Data Analysis Council Meeting; LIGO and Virgo issue press release on MOU that heralds an era of joint analysis!
Last Tuesday, the joint Virgo/LIGO Data
Analysis Council held its first meeting.
Co-chaired by Andrea Vicere
and Maria Alessandra Papa, the group
will initially focus on discussions of when to recommend the start of data sharing.
Responding to a press release issued jointly
by LIGO and Virgo, news of the agreement
between our two projects has started to spread. A nice piece appeared on the New Scientist web site: http://space.newscientist.com/article/dn11194-gravitational-wave-observatories-to-join-forces.html
Look for a short piece in an upcoming issue of Physics Today.
LIGO Laboratory Administration (Lindquist)
PROPERTY MANAGEMENT (Luna)
>From: Rod Luna
<rluna@ligo.caltech.edu>
- Worked with our broker in making shipping
arrangements for the Noise Prototype Reaction Mass from the UK to
LASTI.
- Provided assistance to Christian Cepeda in shipping a package to Dell Computers.
- Continued working on LIGO's
Equipment Inventory @ CIT.
DOCUMENT CONTROL CENTER (Turner, Mak)
>From: Cleveland Mak
<mak_c@ligo.caltech.edu>
- Most efforts were focused on packaging and transporting
documentation for the sub-basement storage move.
- Began processing 2006 Travel Expense Report
Files.
- Scanning Update - Progress continues on scanning
of miscellaneous large/bulky "C" documents on file.
FINANCIAL SYSTEMS (Funaro,
Brambila, Kaufman)
>From: "Funaro,
Catherine" <Catherine.Funaro@caltech.edu>
>From: Florence Kaufman <fkaufman>
- Submitted 10 Fabrication Equipment Requests
mainly for the ISC and SUS efforts.
- Prepared and submitted funding realignment
authorizations requested by Project Accounting. These realignments
are required to enable billing to NSF whenever the expenditures for a
particular project exceed the budget in ORACLE for that project.
- Notified Cindy that an incorrect expenditure
type had been used for a Visitor charged to LIGO Operations.
Correction is required to change it to an expenditure type for Participant
Support.
- Financial reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence.)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Ed Jasnow
<jasnow@ligo.caltech.edu>
- Both Pathfinder optics polishing contracts have
been signed by the contractors, CSIRO and QED, with the QED contract
received and about to be signed by Caltech. The kick-off meetings
have been scheduled for March 9 with CSIRO in Sydney,
Australia, and March 27
with QED in Rochester,
N.Y.
- Rod Luna, Ed Jasnow,
and Carol Wilkinson finalized the letter which will accompany all of the
material for Advanced LIGO which will come from outside the United States.
This includes material contributed by collaborators, as well as items
purchased directly by LIGO from foreign companies. The letter is now
being reviewed by Ann Bussone of the Office of
General Counsel.
PROPOSALS and REPORTS (Lindquist)
Nothing new to report. I will distribute a "straw man" outline for the 2009-2013 LIGO Operations proposal this week.
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa
<cindy@ligo.caltech.edu>
- The next Staffing Committee meeting is scheduled
for Monday, February 26. All files are posted and up-to-date on the
web page.
Quality/Safety (Tyler)
There will be kick-off meeting of the LIGO Scafety Committee with the Adv. LIGO management team at CIT next week.
LIGO
Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of S5 Activities at LIGO Hanford Observatory
(compiled by K. Kawabe)
High wind (up to 54 MPH) and
subsequent tumbleweed bailing, together with high microseism made this week a
rough one. Duty cycle (Thu Feb/15
to Wed Feb/21 2007) of H1 was 79.4 percent with 14 - 15 Mpc
inspiral binary range. For H2 it was 72.1 percent
with 6 - 7 Mpc range.
Summaries: Range
and Duty Cycle update. Tuesday maintenance summary.
Highlights from the LHO elog
are listed below:
- Mitigating
the impact of TCS glitch on H1 by merely reprogramming polarizer rotator
was suggested (but not yet implemented).
- 2000
Hz peak in H1 was found to be gone after an attenuator was installed
to mitigate IRIG-B-related lines.
- h1awg0 became unstable again (see for example this,
this,
this,
this),
causing pulsar injection to drop. Frontpanel-resets
were performed many times, and a full power cycling was done once on
Tuesday. However, it seems that the problem was not fixed, and we still
have to reboot awg once in a while.
- This was the third week of online
inspiral binary monitor problem. Real remedy
was delivered when, finally, they
tracked the last problem down to kernel of LDAS grid machines. After
they fixed this, it started to catch up, and as of this writing it is
working nicely.
- Hardware
injections were updated.
- One
of the injections was so loud it knocked H2 out of lock, while H1
AS-triggered into AS5 and managed to keep locked (but out of science
mode).
- DST
patching of all of the workstations started on Tuesday and is still continuing.
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Giaime)
The S5 run is
proceeding well, with 75 percent uptime this past week.
CDS
Computing (Lisa Bogue)
- Worked on a solaris 10
sendmail configuration for CDS machines. This is so CDS machines can route status
messages through the main ligo-la mailserver.
- Continuing DST patching.
Enhanced/Advanced
LIGO (Janeen Romie)
Reported
in Advanced LIGO Section below.
LLO
Outreach (John Thacker)
Began
development of new activity on UV for High School students. Prepared for and conducted two Group Visits:
High School Physics and Ninth Grade Physical Science. Prepared pre/post visit packets for each group. Prepared and presented program for middle
school Family Math Night. Prepared for Docent training on three exhibits. Routine exhibit maintenance
Data Analysis & Computing (Yakushin)
Storage/Condor/LDAS
Administration
Reported under LDAS System Administration, see below.
Mechanical and Optical Systems (Coyne)
See Advanced
LIGO
Controls and Data Systems (Bork)
See Advanced LIGO
40-Meter Interferometer (Weinstein)
Mike Zucker livened up the lab for a couple of days this week.
IFO Commissioning,
DC Readout, Electronics, Controls, Computers
- Rana, Kirk and Rob continue to work on improving the
locking of the PRFPMI, finding and fixing problems and noise sources.
- Rob has been working on reducing the noise in
the DC readout of the PRFPMI, by changing loop gains, etc. He worked on
diagnosing the origin of the large noise peaks in the 1-2 kHz region of
the DC readout noise spectrum taken last week. His theory that it was due to DAC noise
on the PZT steering mirrors turned out to be wrong.
- Royal installed the whitening board she built
for the ITM optical lever signals, with improved filtering. Signals are now seen above the ADC
electronic noise floor in the 10-1000 Hz frequency range. She also built
and installed new cables.
- Tobin, Kirk, and Rana
changed the main drive resistors on all the TMs from 100 to 400 Ohms and
saw the expected noise improvement of 4 at frequencies below ~ 300 Hz. (in
the PRFPMI configuration with DC readout). They tried many things to reduce the
noise in the 300-3000 Hz band, without success.
- Tobin ran Rana's
scripts to repeatedly measure the DC power with the arms in the locked and
unlocked state, in order to get an estimate of the losses in the arms. Data are being analyzed.
- There's something very wrong with the side
damping on ITMX, which might be a mis-mapping of
the OSEM cables. Osamu is
investigating.
- Steve will install a HeNe
laser for the BS/PRM/SRM oplevs, in the next
week. The HeNe
lasers on the ETMs are much less noisy than the
diode lasers we have been using. Steve will procure parts to replace the
remaining diode lasers, on the ITMs.
- There have been a fair number of problems
associated with the controls computers, but Larry's group has been helpful
in resolving them.
Vacuum
Squeezing
- Osamu and Go improved the alignment of the
squeezed vacuum injection optics, and obtained much better mode matching
into the interferometer. This in turn resulted in a much higher level of
squeezing; they measured 3.5 dB of squeezing at 4 MHz.
- Osamu and Go noise-locked the injected squeezed
vacuum with the interferometer in the signal-recycled Michelson (SRMI)
configuration. They observed a squeezing-enhanced noise spectrum at
frequencies down to 4.5KHz, with about 2dB of
broadband noise reduction. They excited the BS to simulate a GW signal at 7kHz and will use that to calibrate the spectrum. It is
not certain that the noise is quantum-limited shot noise (for one thing,
the spectrum isn't flat). Under investigation.
Lab
Infrastructure, Bake Lab
- Rana ordered, received, and configured two new
laptops for EPICS controls in the laboratory.
- Valera supplied us with a new IR viewer that turns off
automatically.
- Steve is following up on all the action items
identified at last week's safety audit. He has also compiled a detailed
inventory of all lasers in the lab.
- Steve obtained five more laser safety glasses
with appropriate protection for both IR and green light (from the squeezer
SHG). He is researching dual-wavelength glasses which have better
visibility.
- Bob's on vacation
this week.
Thermal Noise Interferometer (Black)
Greg is working
on the spot- size measurement, and Eric is at Hanford for a scimon
shift.
LASTI (Ottaway)
ISI
- Laurent worked on
the temporary pusher to load the blades with the new shims as well as on
the future pusher (2 screws) for stage 0-1 blades. Work on the ISI stage
1-2 matlab model and added the riser stiffness,
results match Ken's calculations well.
- Fabrice is working on the calculations and measurements
that enable us to compute with more accuracy the shims as a function of
the change of load. He's currently checking the calculations by
measurements of the tip angle of the blade against the load
using an optical lever
- Rich checked the actuator drive circuit to try
to understand why the compliance seems to be a function of the drive
amplitude
Quad-Triple
Cavity
- The triple that will be mounted on the HAM SAS
platform was extracted from the Xend a located
ready to be installed in the Yend. We mounted
the full triple on its spacer block and coarsely positioned it in Yend HAM chamber. Fine alignment between the quad and
the triple will occur on Friday and Monday.
HAM
SAS
- A source of rubbing was found between the magnet
and the coil of one of the actuators. This was in all likelihood caused
when this particular corner of HAM SAS was somehow mis-matched
with the ball and socket joint possibly occuring
during shipping. When this was fixed the modal spectrum looked a lot
cleaner although still clearly not a long cartesian lines. Riccardo,
Dennis and Alberto diagnosed the non-working stepper motors and found a mis-wiring had occurred.
This was fixed and the stepper motors now work.
CIT Science Group (Weinstein)
_________________________
Xavier Siemens
This update is for the last three weeks. In
no particular order:
- Visited Case Western in Cleveland recently for a few days. Gave
seminar.
- Found and re-made some h(t)
for Drew (for the S5 inspiral search) &
dealt with lots of h(t) unpleasantness.
- Worked with some folks (Irit
Maor and Tanmay Vachaspati) at Case on cosmic string microlensing. Work in
progress.
- Worked some more on GW SB from preheating. Turns
out some people at Case were also
interested in this problem and so now we are collaborating on this as well. Work in progress.
- Worked on Einstein@home
data set
- Spent time with Pinkesh
and Rejean working on re-sampling technique
for pulsar searches.
- Spent time on h(t)
review. Started on creating DQ flags based on fractional differences between h(t) and h(f) for S4 h(t) data.
- Read Joe Polchinski's
latest paper on cosmic string small scale structure in detail.
Eirini Messaritaki
- Worked on the null-stream veto; trying to get
null-stream results from the accidental coincidences of the first epoch
of S5.
- Worked with Vibha on
the detection of spinning waveforms with
non-spinning templates.
Rejean Dupuis
- generated time-frequency spectrograms for all of
2006 and looking for interesting features
(www.ligo.caltech.edu/~rejean/S5/spectrograms/2006)
- working with Pinkesh
to set up long FT F-statistic code
Laboratory Computing (Anderson)
LDAS Software (Maros)
- Efforts to solve PR#2946 which deals with the diskcacheAPI falsely reporting gaps at either end of
the frame query have been slow. A solution that was under testing consistently
cased core dumps due to an introduction of a race condition. The code has
been reverted to gain insight into the problem.
- The C++ version of kill is being incorporated
into the TCL layer. When completed, it will remove another instance where
the TCL layer was doing system calls via a forked process.
- System testing for LDAS was done using version
1.8.460. The single regression test pr2121.tcl failed due to file
permission problems by user install in removing the frame directory before
running test case 5 as the directory and files were output by user ldas. Fixed by just removing the frame files in
the directory instead of entire directory.
- System testing on the Opteron
platforms continues using ldasbox1 and ldas-suntest1 without globus. ldas-suntest1 DB2 9.1 insertions worked
initially but soon jobs were stuck in metadataAPI
and built up a huge queue as well as rejecting jobs. DB2 had to be
restarted.
- Jobs ran fine on ldas-test
running ldas 1.8.0 with the usual bad symbol
error from datacond
and the job timed out reading from tcl socket
which was fixed in higher versions.
- The dcmangle related
scripts were modified to run under various environments: opterondata-dev, ldas-test
with ldas 1.8.0, and linux.
All the changes have been committed to cvs.
- After OS upgrades for DST issues, ldas on ldas-cit was
restarted and some test jobs were run. The dataPipeline
jobs had to be aborted as it hangs in the eventmon
waiting for wrapper to send data over if there is a wrapper. The other
commands (createRDS, putMetaData
and getMetaData, getFrameElements,
conditionData) all worked fine.
- The script which generated the system status
page reporting on the nightly builds has been updated to properly report
the word size (PR#3071).
LDAS
System Administration (Anderson)
Caltech
(Dan Kozak)
- Republished h(t) files
at LHO (ongoing).
- Finished relabeling
2nd CIT copy of A4 L1 data tapes.
- More tapes for shelf storage at LHO.
- Did shutdown/restart of SAM/segfind/LDR/rls/mysql
on ldas-cit and dataserver-cit
so they could be updated to Sol10U3.
- Did regular tape ingest, plus ingest of data
that had been mailed/put in silo but never ingested here at CIT (caught by
Greg's GapCheck).
- Updated PDFs of home
directory usage so users could find out where the disk space had gone.
- Did a throttled rm of
several million files for user lindy.
- Called in a bunch of parts to sun (3510 PS, 3510
disk, 880 disk).
(Phil Ehrens)
- Test modifications to TAR form requested by Albert Lazzarini.
- Various grid certificate related tasks.
- System upgrade support.
(Erik Espinoza)
- Replaced disk in node118 (p0).
- Moved Condor negotiator, collector & postgresql from ldas-grid to
ldas-condor.
- Installed/Configured new ldas-grid
(x4600m2).
- Installed/Configured new ldas-pcdev1 (x4600m2).
- Updated Condor config
files to match new hardware configuration.
- Upgraded cluster to Condor 6.8.4.
- Updated all nodes for DST changes.
- Tested speed of software raid, hardware raid and
single disk configuration on x4600m2.
- Sent logs to Condor team regarding failing jobs.
- Testing and configuring trunking
on Solaris/Cisco.
MIT
(Fred Donovan)
- More ganglia.
- Cfg smartmon for 3ware on
data1, with sendmail cfg.
- Data1-11 will be primary data stores (not
nodes).
Livingston
(Igor Yakushin)
- Inserted the missing segment number (for a few
science segments) into the database.
- Working on implementing segment database
changes.
- Weekly tape export/import/shipment.
Hanford
(Greg Mendell)
- As a part of routine sys admin work, I fixed a
few gaps in the transfer of RDS and trend data to CIT. These are now
up-to-date. I am still working on the LDG 4.4 release.
(Ben Johnson)
- Working on Matlab NDS
client. So far, I have a beta client that works under 64-bit Linux.
Cleanups still need to be made so that it can be used in multi-hour Matlab sessions under Linux, Solaris, and Mac. A
windows client is still on the drawing board.
- I put an FrCheck test
into the publication script, and turned it on for H1 and H2 h(t). L1 h(t) FrCheck will be activated today.
- Changed ldas-grid's
kernel back to 2.6.17-1.2143_FC4 from the custom 2.6.19.2. This increased
disk I/O bandwidth by an order of magnitude. Unfortunately this is
only a UP kernel; it will need to be switched next Tuesday.
- Put the ldbdd servers
under SMF at LHO. The setup is not ideal, my original plan was to have the
servers dependant upon a "DB2" service;
now the ldbdd services are only dependant upon
the ligo-server milestone. Hopefully this will
not cause too much trouble in practice.
General Computing (Wallace)
MIT
(Fred)
- gar file server erratic: decommissioned and
moved to nova as new fs with firewalling
- testing 4 scsi hdd (2X181, 2X140) on pellinore
for tubera additions (2X140 reports errors)
- local matlab installs
on gc computers (from prev
client/server (gar))
- DST patches downloaded (Friday pm or Sunday am
install planned)
- Housecleaning (old equipment -> deactivated)
- NSF conference Thursday/Friday
Hanford
(Christine)
- Continuing to install the DST patches.
Decided to install the complete
Security and Recommended patch clusters on as many Solaris computers as possible. Installed the
cluster on the file server on Monday.
Didn't get to all the servers last Tues. so I will install the cluster on the mail server and the LSC sandbox computer
next Tuesday. Will install the
cluster on the DHCP server this weekend. Had to upgrade two loaner laptops to WinXP because there is no DST patch for Win2k. They needed to be upgraded anyway.
- Getting quotes to renew and upgrade the service
contract for the Cisco equipment.
Currently have two contracts that will be combined and extended for three years at 24x7x4 hours
on-site.
- Renewed the maintenance contract for the Mathematica network license.
- Continuing work on building the new router,
servers and disk systems.
Caltech
(Mike)
- Continued work on updating servers with DST
patches.
- Worked on a Sun box over in 40Meter. This had a
corrupted library that was
preventing this system from booting. I ended up upgrading this unit
which corrected this issue.
- Working on DCC nightly-process computer.
I’m working on putting together
another computer just in case the current system has some hardware/system issues. Larry has requested
this.
- Configured a new wireless access point for Wilson
House.
- Other user support plus sysadmin
tasks
(Christian)
- Installed monthly Microsoft security patches on
all Windows 2000 and 2003 servers.
- Calum Torrie- returned
laptop back to LIGO. I created a backup and re-imaged it with our standard image.
- Irene Baldon- Needed a
loaner laptop to be configured so she can login remotely and work from home.
- 3flr W/B- Replaced broken DVD burner on the
scanner/ CD burner system.
- Toner cartridge replacements- 40 Meter, Irene Baldon and Albert Lazzarini
- Re-imaged laptops that were returned to the
loaner pull this week.
- Worked on the Spam Filters with Mike and Larry.
- Other misc.: Continued onsite software/phone
support.
(Veronica)
- LSC: Updates of the databases of
publications and technical papers. Various
web updates. Assisted Dorothy with postings of the MOUs. Updates
of LSC-related mailing lists. Ongoing support of the March meeting.
- LIGO: Website updates. Set up a
mailing list for CDS. Assisted Sydney with file transfer from his laptop for web
posting. High-res images for two popular science magazines.
- CaJAGWR: Website updates/ user support.
Advanced LIGO and
Supporting R&D (Shoemaker)
Advanced
LIGO Systems
Static IFO simulation (Hiro)
- The diffractive loss due to the thermal
deformation has been studied. For the symmetric cavity (2076-2076), the
loss is small, ~ a few ppm. The mode matching loss
can increase to 15ppm x Finess level when the
same input beam is used for a cold and a hot cavity. A small tilt, ~10 nano radian, does not induce any observable
diffractive loss.
Mechanical Simulation for advanced LIGO (Sany and SLU team)
- Continued e2e modeling of AdvLIGO triple suspensions modal control for the Yaw DOF. Found a bug in the e2e code that I previously made and fixed it. Consequently, with the same impulse input to the suspension point and the same estimator/control filter settings, the time series of the three masses' yaw motions are identical to the corresponding time series obtained with the Simulink model developed by Laurent Ruet.
modeler (simulation engine) and ALFI (GUI front-end)
(Melody, Bruce, Hiro)
[ UserDefinedPrimitive is an e2e equivalent of MATLAB MEX-file extension,
i.e., adding new functionality to the engine program without modifying the
engine code. ]
- The implementation of the UserDefinedPrimitive
has been revisited.
- A better implementation has been chosen to
implement which makes the customized UsefDefinedPrimitive
more easier to develop and use. This can be implemented along the line of the
development plan of current alfi (e2e GUI
front-end) and no modification of modeler (e2e simulation engine) is
needed.
- Melody has been working on improving the UserDefinePrimitive editor, and Bruce has been working
with Hiro to implementing the UserDefinedPrimitive in modeler.
- As the highest priority, they will work together
to upgrade alfi to support the new design of UserDefinedPrimitive.
CDS
From: Rolf Bork rolf@ligo.caltech.edu
ISI
- STS2 Test box design in progress.
- One ISI course/fine driver chassis is complete; Fab of additional units in progress.
- Guralps cables have shipped from Europe
and should arrive soon.
- GS-13/L4C Emulation module: (Ben) I thought that
I had finished the schematic, but there was a part that I was going to use
that is only available in batches of 2500. I have redesigned for a more
common part, and will alter the PCB tomorrow. I'll send it off for fab soon.
- GS-13/L4C Control Module - The schematic is
about done, I just want to look it over one last time before making a
PCB. It should be done tomorrow.
SUS
- Seven satellite amp. modules
in fab.
- Electronics design review comments sent to UK.
HAM
SAS
- Stepper motor control hardware/software
assembled and undergoing tests at CIT; Alex will travel to MIT for
installation at Lasti next week.
CDS
Infrastructure
- Travelled to LHO for AdvLigo
CDS design requirements meetings with site staff last week; in progress of
adding discussion items to requirements
document.
- As a follow on to last weeks discussions at LHO,
plan to meet with S. Anderson next
Tuesday to discuss data retrieval in support of ops and commissioning
activities.
Prestabilized Laser
From: Peter King
<pking@ligo.caltech.edu>
- I am still working ym
way through the pages of documentation for programming the Beckhoff Automation interface.
- In checking my numbers in the draft PSL laser
safety plan, I discovered I made a mistake (over estimate) and that the
optical density I required was too high - not that that's a bad
thing. Checking over the latest ANSI Z136.1-2000 standard I was
surprised to find that the requirements were relaxed over the 1993
standard. I hope to check this out next week. Otherwise my numbers
are consistent with a commercial program.
- In working on the draft safety plan I have also
begun a sample SOP for the Advanced LIGO Laser.
Seismic
Isolation
From: Ken Mason kmason@ligo.mit.edu
BSC
Seismic Isolation Testing
- We have recieved
quotes for the UHV cleaning of the large parts from Galli
& Morelli. The cost is in line with our
other quotes and the delivery time having them process our parts is 8
weeks compared to 12 weeks for the other options.
- The second set of shims will be installed next
week which adjust for the full payload and to reduce cross coupling. Our
target date for starting the disassembly and sending it out for cleaning
is the week of march 5th. The crates have been recieved for shipping all parts.
- Additional high vacuum cabling and connectors
have been ordered for installation into the BSC chamber.
HAM
single stage isolation system
- We have accepted the design and performance
parameters submitted by HPD on 2/20 and requested they complete the design
details.
From: Dennis Coyne coyne@ligo.caltech.edu
Subject: HAM-SAS weekly report
- We have mounted new stiffer anti-tilt springs
and have found improved angular stability. We discovered that the cause of
the abnormal behavior of one of the vertical Geometric Anti-Spring (GAS)
filter stages was due to contact/rubbing of the LVDT coil. This contact
occurred at the stage with the ball-and-socket interface where we know
there is a high lateral force due to the interface plate bending. By
re-positioning the magnet ring structure we were able to get reasonable
clearance. The optics table with payload now appears to float normally and
has been leveled.
- The stepper motor wiring has been corrected and
all stepper motors now function properly.
- We are in the process of taking transfer
function measurements.
From: Ben Abbott abbott_b@ligo.caltech.edu
All new activity since last weekly is
written in red.
40m
DC PhotoDiode
- Have finished the new DCPD schematic and pcb layout. I await
feedback on the schematic that was sent out to interested 40m people.
HAM-SAS
Custom
Electronics chassis: (# needed + #spares)
- LVDT Driver (2 + 1) -2 Installed the spare is stuffed,
but needs boxing and testing
- LVDT Interface (2) Installed
- Stepper Motor Interface (2 + 1) - Installed
- Coil Driver Interface (1) - Installed
- QPD Whitening (2 + 1) - 2 Installed, 1 spare here, needs
testing and boxing.
- QPDs (4 + 1) - 4 in electronics lab, 1 is just a
bare board and I'll keep it for a spare board.
- Guralps Interface (1 + 1) - 1 installed, 1 built but untested.
- AA Interface Rev 4 (1) - Installed
- AA Interface Rev B5 (1) - Installed
- AI Interface Rev 3 (1) - Installed
- Coil Driver (4 + 1) - Installed
- In-Vac Breakout boards
(2) Installed
Commercial Electronics
- Opteron Processor (1) - Installed
- Stepper Motor Driver (4) - Installed
- I/O Chassis (1) - Installed
- Power Supplies (2) - Installed
Miscellaneous
- In-Vac Accuglass cables (13) - Installed
- Guralps cables - Specialty cables from Guralps Instruments Ordered 12/21 quoted a 30 day
lead, but they now say that they have been shipped
from Europe, and should arrive here very
soon.
- Special cable connecting the LVDT 25-pin Witness
board connector to the 9-pin ADC connector - Installed
- The 5 L-COM cables that were short were
delivered to Alberto last week. Marie told me that Riccardo came and picked them up after Alberto had
left for the day. I assume that Riccardo
installed them.
- The decision has been made to read back the
stepper motor steps so we can keep track of the actuator position when we
move the steppers. The first stage of this effort will be to move
the motors manually via the front panel, and read back the RS232 signal
that records the # of steps through the PCIX adapter module to a terminal
window. We have jumped ahead to stage three
which involves actually controlling the motors from epics, and reading
them back there also. This came to pass because of great efforts on
the part of Alex, and because we were sent a spare to use for the test bed
for the controller and a spare stepper motor. It will be shipped out on
Friday, and Alex will be there next week to install it.
- The RS232 to PCIX adapter board has
arrived. Alex has been using it to control the stepper motors.
- Of the five coil drivers sent from Italy, two
do not work. David and Alberto have installed one of the remaining
unmodified coil drivers instead. Riccardo has
shipped the broken boards to me to diagnose and repair I will diagnose
them as I get time.
- I have finalized the system schematic,
and it now agrees with the observed controls pinouts.
ISI
- ISI Interface - (3 + 1) I
continue to work on the schematic.
- GS-13/L4C Emulation Module - I've thought that I had finished the schematic, but
there was a part that I was going to use that is only available in batches
of 2500. I have redesigned for a more common part, and will alter
the PCB tomorrow. I'll send it off for fab
soon.
- GS-13/L4C Control Module - The
schematic is about done, I just want to look it over one last time before
making a PCB. It should be done tomorrow.
- GS-13 Boards - (many) 15 boards came back from
PCB Express. They'll get stuffed sometime soon, and delivered
sometime thereafter.
- Coil Driver - (3 + 1) (Mohana)
- The Coil Driver board has been stuffed and in test. The new
interface board has arrived and been stuffed
Testing of the entire chassis will occur soon. The metalwork
has been sent out to Front Panel Express.
- STS-2 Emulation Module - Mohana is looking
at requirements for this board.
- STS-2 Control Module - Mohana will start thinking about this module after she
gathers requirements for the Emulation Module.
Suspensions
From: Norna
Robertson <nroberts@ligo.caltech.edu>
- LASTI TAC report on the long term research plan
at LASTI was completed, circulated and sent to the DCC (T070031-00-R)
- Thermal noise modelling
for beamsplitter has been carried out by M
Barton to see if a wire suspension could meet noise requirements, thus
avoiding the optical loss from the flats needed for silicate bonding, and
simplifying the construction. Estimate depends on how much coupling
from vertical to longitudinal (will vary with wedge angle), but could just
meet target at 10 Hz. However highest vertical mode falls above 10 Hz (~16
Hz in current model).
- Estimate of required person-months for quad
suspension assembly (clean, metal-only) carried out with J Romie and C Torrie, for use
in comparison to costbook number. Triple
assembly estimate underway.
- Quad noise prototype test plan outlined with
input from J Greenhalgh and K Strain.
From: Janeen
Romie <janeen@ligo-la.caltech.edu>
- Working on OMC design. Safety stop design OKed; moving forward on bracket details. Last week,
facilitated daily meetings with the engineers. Checked some drawings.
Provided structure hole dimensions to Mike Gerfen. Answered some questions of his and Ric Paniaguas yesterday. I
am the point of contact and procurement person for packages to Valley
Precision from Calum and Chris. Facilitated DCN
for initial release of some of Chris's drawings.
- Answered some questions of Bram's for tip-tilt
suspensions.
- Still working with Carol and Florence on opening the 8 fabrication
accounts pertaining to Advanced and Enhanced LIGO. Working with Justin on
the Birmingham
and initial LIGO osem count for prototypes and
production.
- Provided labor estimates for quad and triple
assembly tasks.
From: k mailand
kmailand@ligo.caltech.edu
- The CES shop is continuing work on the LASTI tooling assemblies.
- Ian will deliver his outer support frame to CIT
the first week in March, we will use it to test
our assembly.
From:
Helena Armandula ahelena@ligo.caltech.edu
Advanced LIGO - SUS
- Received the new mask for the electrostatic
drive. We'll have a trial coating run (at no charge) at Navitar to see how it works.
- The modifications to the ERGO arm will be
finished next week and the arm will be shipped to LASTI
- The shipping box for the arm is almost ready, Ken Mailand supported
this effort by overseeing the construction of the shipping container.
Core Optics
From:
Helena Armandula ahelena@ligo.caltech.edu
Advanced LIGO - Coatings
- We expect some 2"dia. mirrors from Lyon. The scatter measured in Lyon
is very low, we'll be testing them at Caltech to
compare results.
Advanced LIGO - Contamination Control
- I am performing some tests to evaluate possible
contamination caused by the UHV foil used for wrapping cleaned parts.
Contrary to my expectations, I can not see (under a microscope) particles
generated by crumpling or tearing the foil on top of a clean substrate.
Next, I will repeat the tests while running a particle counter.
Auxiliary
Optics
From: Michael Smith smith@ligo.caltech.edu
OPTICAL LAYOUT
- I revised the stable RC optical layout based on
the criteria of achieving minimum wedge angles for the BS (1.66 deg) and
choosing the ITM wedge (1.45 deg) plus CP wedge (0.61 deg) so that the PRM
wedge was eliminated. I am in the process of revising the cost comparison
between the stable recycling cavity and the unstable RC cavity.
From: Phil Willems
<willems@ligo.caltech.edu>
- Mike Landry, Sam Waldman and I performed
measurements of the test mass drumhead mode frequencies as H2's laser
power was modulated. We also tried to collect data with the TCS
power modulated but lock losses severely limited what we could do.
Analysis of the data has only just begun.
Input Optics
For additional information about this
report, contact Albert Lazzarini or Phil Lindquist