Annonucements: There will be no LIGO Executive Committee for the NEXT TWO WEEKS:
- Meeting on Monday, January 19, 2007 cancelled due to the holiday.
- Meeting on Monday, January 26, 2007 cancelled due to the monthly Staffing Committee Meeting.
Weekly Report Highlights
Dave Reitze has been elected the next Spokesperson of the LSC. He was chosen from an outstanding list of candidates. We all wish Dave the very best in his new role, which will begin at the end of the March Collaboration meeting.
At its meeting on Thursday 15 Feb, the LSC Executive Committee approved three observational papers for publication: papers on the S4 untriggered burst search, on quasi-periodic oscillations in SGR 1806-20, and on the S4 stochastic search using LLO and ALLEGRO data.
LIGO Laboratory Administration (Lindquist)
DOCUMENT
CONTROL
CENTER
(Turner, Mak)
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- Continued to process MOU's.
- Began to package and transfer documentation for the sub-basement storage move.
- Assisted in clearing out all documentation in room 251 W. Bridge.
- Scanning Update - Scanning of all non-electronic "P" files is complete. Scanning has begun on miscellaneous large/bulky "C" documents on file. Made preparations for next scanning project.
Update to Current Document Management System (Lindquist)
We are currently looking t three possibilities:
-
- DocDB
- DocuShare
- What it would take to enhance our own current DCC System
We are attempting to see if we can get accounts on working systems in organizations of similar size. We have distributed the results from the last attempt to evaluate these systems for review and as a starting point to see if some of the issues have been resolved.
FINANCIAL SYSTEMS (Funaro, Brambila, Kaufman)
>
>From: Florence Kaufman <fkaufman>
PROPOSALS and REPORTS (Lindquist)
A proposal for Continuing Operations (2009-2013) is due to the NSF this summer. We met with the NSF this week to discuss what this proposal should contain. I will be publishing a proposed outline and assignments based on the information provided.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
- There are no open change requests.
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- The next Staffing Committee meeting is scheduled for Monday, February 26.
- All files for the Staffing Committee are up-to-date and posted on the Staffing Committee web page
- Prepared numerous appointment and reappointment memos for various Visitors, Post Docs, and Term Staff.
Quality/Safety (
Tyler
)
>From: Bill Tyler tyler@ligo.caltech.edu
Completed the safety audits of the Caltech campus facilities. The 40M lab was the last to be audited, no significant safety issues were identified. However, one safety concern was noted regarding the new bake-out oven. The door latching mechanism has no provision to unlatch the door from inside the oven. Also, the 40M lab office area needs some extra house cleaning effort.
The consultant
PO
for safety support, should be in-place by next week.
The selection of members for the LIGO Safety Committee was completed and the committee members will be notified in a few days. It is planned to have the initial meeting of this committee to discuss goals, objectives, LIGO and Advanced LIGO need dates for safety related issues during the last week of February.
LIGO
Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of S5 Activities at LIGO Hanford Observatory (compiled by K. Kawabe)
Duty cycle (Thu Feb/8 to Wed Feb/14) of H1 was been 88.7 percent with 14 - 15.5 Mpc inspiral binary range. For H2 it was 87.7 percent with 6 - 7 Mpc range.
Summaries: Range and Duty Cycle update. Tuesday maintenance summary.
Highlights from the LHO elog are listed below:
Outreach:
- LHO outreach visited Tonasket Middle School/High School in north central WA on 2/12 and 2/13 for two days of LIGO-flavored hands-on science with ~300 middle and high school students. Central WA University GEAR UP coordinated the visit.
LIGO
Livingston
Observatory (LLO) and Interferometer Operations (Giaime)
S5 run (Igor Yakushin)
- Most of the week the microseismic was low and the range was between 14-15 Mpc with daily duty cycle around 90%.
- On Tuesday the microseismic went up and the range dropped to about 12 Mpc.
- Most of Wednesday and Thursday L1 was down during the day due to the air pump repair work near LVEA.
- The duty cycle for a week is 72%.
(Valera Frolov)
We continued the dark port beam characterization using the output mode cleaner cavity:
- The mode scan of the dark port beam was repeated this week. It was found that due to the nonlinear response of the PZT to the applied voltage a nonlinear correction has to be applied to the frequency of the observed transmission peaks to identified the higher order modes. An additional data were taken with interferometer in cold and hot state with 7 W of input power. The dominant higher modes were identified using the CCD camera to facilitate the fitting of the data.
- The output mode cleaner cavity (a spare PSL pre-mode cleaner cavity) was dither locked to the carrier light at the dark port. The TEM00 carrier light was induced by introducing the offset into the DARM loop. After verifying that the transfer function was flat between the RF (ASPD5) and DC (OMC transmitted) paths, an attempt was made to hand off the control of the interferometer DARM dof to the DC readout. The attempt was not successful possibly due to the unstable lock point of the OMC. The instability of the lock point was not understood due to limited investigation time.
- The newly repaired clean air compressor is running and will be shut down this evening.
CDS Computing (Lisa Bogue)
- wrote a script for securing cds sol10 machines.
- began running dst patches.
Advanced & Enhanced LIGO (Janeen Romie)
- Working on OMC design. Met with Sam yesterday to review the new safety stop design. He preliminarily OKed the stop layout with respect to the optical beam layout as it is, and as it might be if changes are made. Facilitated daily meetings with the engineers. Calum has headed back to Glasgow. We very much appreciate that he could be at Caltech for so long. His presence, knowledge and support is greatly appreciated.
- Working with Carol and Florence on opening the 8 fabrication accounts pertaining to Advanced and Enhanced LIGO.
- Worked with Norna on the Birmingham osem count for prototypes.
- Working with Bob Taylor on initial LIGO osem count needed for site spares, R&D spares and Advanced LIGO prototypes.
- Provided a list items that need to be addressed for the recycling mirror and input mode cleaner suspensions, in preparation for the HAM Cavity design review, scheduled for May. This list is in support of schedule and budget analysis as well.
LLO Outreach (John Thacker)
- Developed activity for High School Physics classes on Suspensions using test mass mockup
- Developed IR camera acitivty (prototype for exhibit)
- Prepared and delivered 2 elementary school programs
- Prepared and delivered 2 HS physics programs
- Exhibit maintenance: Satellite Orbit Simulator, Hot Spot, Doppler Effect, Fading Motion, Soap Film Painting
- Monitored local Math/Science Partnership project teacher's workshop held at LIGOSEC
Note: Friday, 2/09/07, was noteworthy in that we had our first school group from out-of-state visit us. This was a group of HS physics students (all had passed their AP physics course; some had passed their AP Calculus course as well) from Little Rock, AR. This group arrived at about 15:00 and departed at around 20:00 en route Baton Rouge to spend the night.
LIGO computing and network security (Roddy)
-------------------------------------------------------------------- Reported under General Computing, see below.
General computing and LDAS admin (Giardina)
---------------------------------------------------------------------
Reported under General Computing, see belowReported under LDAS System Administration, see below Data analysis & computing (Yakushin)
---------------------------------------------------------------------
Storage/Condor/LDAS admin:
Reported under LDAS System Administration, see below Data analysis:
Reported under Data Analysis activities, see below
Mechanical and Optical Systems (Coyne)
See Advanced LIGO
Controls and Data Systems (Bork)
See Advanced LIGO
40-Meter Interferometer (Weinstein)
- There was a 40m Technical Advisory Committee (TAC) meeting on Feb 8th 8:30 Pacific. Rana showed these slides. The (draft) minutes from Ken Strain are here.
- There was a safety audit of the 40m lab on Feb 9, hosted by Rana, Steve and Bob. Several action items were identified and are being followed up on by Steve and Bob.
- IFO commissioning, Electronics, controls, computers:
- Rob and Kirk have been working on getting the common mode servo working in the PRFPMI case with REFL 166 (ie, non-resonant sideband) signals. It's now commissioned & scripted, including the CM Boost stage.
- Rob and Kirk have been working on improving the lock acquisition and control of the PRFPMI. It now locks reliably and robustly, and is fully scripted and (almost) fully automated.
- Alex, Rob, Sam, Tobin and Valera began commissioning the new IFO dither-alignment system, using a new control computer (c1ass), front-end code from Rolf and Alex, and EPICS controls set up by Rob, Tobin and Valera. Valera returned to LLO and Tobin continues the commissioning work.
- Rana set up some measurement scripts to measure the losses in the arms. He estimates a round-trip loss of 175 ppm (!) in the Y arm.
- Rana asked Gari, Helena, and Bill Kells to help reduce the mirror losses by drag-wiping the test masses. We plan to do this some time in the spring.
- Rana has been diagnosing problems in the dewhitening boards and coil drivers that are limiting our noise spectrum in the 100-1000 Hz regime, and is making plans to change the boards to reduce the noise.
- Royal has been modifying the oplev whitening boards to reduce oplev servo noise at low frequencies.
- We have HeNe oplev lasers on the ETMs, and they perform much better than the cheap diode lasers we were using before. Steve has a new layout of our BS oplev table (which sends oplev beams to the BS, PRM, and SRM) using a single new HeNe laser with his stable mounts, and will install it in the next week.
- IFO modeling:
- Kirk has been running Optickle models of various MICH and PRC signals, with varying CARM offset, for undercoupled and overcoupled PRCs. Our PRC is currently quite lossy and undercoupled. Kirk is identifying useful MICH signals for different CARM offsets.
- Kirk ran Bench sensitivity spectra for the 40m in PRFPMI configuration, with estimates of the (anomalously) large mirror loss. The shot noise limit should be a few times 1e-19 m/rtHz.
- DC detection:
- According to the High Level Schedule in the wiki, DC Readout Phase A concludes on Valentine's Day, 2007. To celebrate, Rob took a valentine-themed DC readout-controlled DARM noise spectrum in the PRFPMI configuration, bottoming-out at 1e-18 m/rtHz in the 1-2kHz region.
- Vacuum squeezing:
- Go and Osamu injected squeezed vacuum into the 40m in the signal-recycled-michelson (SRMI) configuration, scanned the sqeezing angle with a PZT mirror in the injection optics, and observed a -1.5 dB squeezed-vacuum-induced reduction in the noise at MHz frequencies (after subtracting electronics noise). This is a great achievement and a real milestone.
- Go and Osamu have been working on noise-locking the squeeze angle of the injected squeezed vacuum, so that they can observe broadband squeezing at lower frequencies. The DC power level of the AS port beam in the SRMI configuration was too unstable and they couldn't noise lock. So Osamu fed the DC level to the Michelson offset to compensate for the fluctuation. This worked pretty well, and then they were able to noise-lock it. Its stability is not so good yet and is being optimized.
Thermal Noise Interferometer (Black)
- Greg continues to make progress on his spot-size measurement, and Eric is at Hanford for a scimon shift.
LASTI (Ottaway)
ISI
- The ISI is now fully loaded with the complete final payload and system characterization has resumed. In addition to this the blade tip angles have been measured. The new actuator mount brackets for the stage 1-2 actuators have been ordered. The long lead time on these (~ 6 weeks) means that we plan to install them on the clean system. It is hoped that we will be in a position to start dismantling the system for cleaning in about 2-3 weeks.
HAM SAS
- Initial control characterization has begun. An initial look at the modes in the vertical direction tend to indicate that the modes are not aligned along cartesian lines. In addition to this we observed bi-stability again. New calculations by Riccardo and Valerio suggest that this may have been expected. We plan to install new stiffer tilt control springs next week. In addition to this the stepper motors do not appear to be working.
Pondermotive
- Final alignment is nearing completion and the chamber should be ready for sealing up next week.
Test Cavity
- The quad suspension was examined and new measurements of the wire break-off dimensions were recorded. The new mirror needed for the cavity was installed. The test layout for the HAM chamber has been completed and the injection bench has been installed. Both triple pendulums have been locked down awaiting re-deployment.
Infrastructure
- The ceiling in the high bay sprung a leak due to the delightful snow/ice rain mix we had in Massachusetts yesterday. It may be necessary to shut the lab down for the weekend to ensure that any potential flooding due to the weekends thaw out does not cause a problem.
CIT Science Group (Weinstein)
Patrick Sutton
Coherent burst searches:
- I spent Friday with Massimo Tinto at JPL. We discussed ideas for the application of coherent methods to the various LIGO searches.
- I've been reviewing Stephen Poprocki's senior thesis on source position estimation in coherent burst searches.
- I had a telecon with Sharmila Karmat (Columbia U.) to discus how the XPipeline package may be used for supernova triggered searches, and sent her sample input and output files.
- Further debugging of the XPipeline package.
Other duties:
- The scimon shift schedules for March-July were released on Saturday. I prepared a web page listing the LIGO-CIT shifts and started recruiting scimons. I have been processing requests as they come in. To date 12 of our 17 shift sets have been filled.
- LSC-PP: I've spent quite a bit of time this week in email and telecon discussions trying to sort out the author lists for the S2-S4 papers. Jolien Creighton is preparing the author lists, and I am going to contact all the authors who are not currently in the collaboration to alert them about the papers.
- I've been editing my portions of the Cardiff group's PPARC grant proposal.
_______________
Kent Blackburn
TCLGLOBUS
- Mary Lei and Michael Samidi are still working on ldasbox1 (64- bit machine) instead of ldasbox4 (32-bit machine) for running valgrind to investigate LDAS managerAPI coredumps using Globus threaded libraries.
- Resolved GSI authentication failure on Opteron systems. After running strace and openssl from command line, it turned out that the machine didn't have DOE certificates installed under /etc/grid-security.
- OpenSSL memory leaks within Globus Toolkit 4.0.3 has been addressed in Bug #4743: (http://bugzilla.globus.org/globus/show_bug.cgi?id=4743). Downloaded GT4.0.x development branch from CVS repository and they all use OpenSSL 0.9.7d dated on 17 Mar 2004 (old version containing memory leaks).
GRID APPLICATION DEVELOPMENT
- In a few hours, 2nd OSG milestone will be completed: Running LIGO workflow on OSG with 100 CPU slots continuously for one week.
- Discovered that Condor-G enable_grid_monitor variable is turned off by default (Condor 6.8.2) on osg-itb-se.ligo.caltech.edu. This is the cause of high overload on ldas-grid gatekeeper when running a large number of Globus jobs. Michael Samidi will use tclproxy as a second submit host to test this variable.
- Still working on SRM problem at UCSD with Karan Vahi. The problems are submitting srmcp jobs using Condor-G fails and missing a single quote surrounding SRM URL in the submit script.
OPEN SCIENCE GRID VALIDATION TESTBED:
- Installed latest VTB:ce-1.6.1a release and tested.
- Patched system for Daylight Saving Time change for 2007.
- Attended VTB telecom related to outstanding issues of OSG 0.5.2
OPEN SCIENCE GRID INTEGRATION TESTBED
- Tested pacman -update with OSG 0.5.2 pre-release. Reported PR related to site_verify script and MonaLisa.
- Worked with Michael Samidi and Kent Blackurn, successfully completed OSG milestone of running 100 Inspiral HIPE jobs continuously for one week as documented in MonaLisa.
- Upgraded tclproxy as a submit host by installing Condor 6.8.4. and OSG 0.4.1.
- Patched system for Daylight Saving Time change for 2007.
- Attended weekly DASWG, ITB and Pegasus telecoms.
OPEN SCIENCE GRID MANAGEMENT
- Drafted presentation on "OSG Status and Accomplishments" for the Joint Oversight Meeting next week in Washington, DC.
- Provided data and networking slides for a second presentation at the Joint Oversight Meeting next week.
- Attended first OSG Executive Board Meeting of the year.
- Submitted top level OSG policies and agreements document to the OSG Executive Team and added to OSG DOCDB.
- Work on job descriptions and postings at CERN and SPIRES for OSG positions at Caltech.
________________
Gregory Mendell
- This week's report is the same as last week's, expect with a new elog entry. I have generated more "fscan" spectrograms and spectra of channels during times from last month's commissioning period when Robert Schofield connected ripple boards to various power supplies. The latest elog is here: http://ilog.ligo-wa.caltech.edu/ilog/pub/ilog.cgi?group=detector&date_to_vie w=02/09/2007&anchor_to_scroll_to=2007:02:09:21:22:29-gmendell
Laboratory Computing (Anderson)
LDAS Software (Maros)
- Work has started on tracking down an issue with the diskcacheAPI not finding files for createRDS when there are many irregularities with the duration of the source files (PR#2946).
- The tcl code is being modified to make use of c++ implementation of the kill command.
- Nightly builds of LDAS for Solaris 10 opteron started this week.
- DB2 9.1 has been installed on a Solaris 10 opteron box. This version is currently under evaluation. It has been working successfully since version 1.8.457 of LDAS.
- The ldas-test system was used in verifying OS patches to deal with the upcoming changes of the daylight savings time rules. No issues for LDAS were discovered.
- Attempts continue to bring up Solaris 10 opteron and Linux FC4 opteron with globus but the errors are still there despite Mike's work with the certificates:
- A. linuxopteron
- cmonClient connects ok to cntlmon but manager hangs on opening the globus listening socket error from manager log manager host per system info: 'linuxopteron' *** glibc detected *** /ldcg/bin64/tclsh: malloc(): memory corruption: 0x0000000000837ea0 ***
- B. sunopteron
- cntlmon and manager open their globus socket ok but cmonClient received sec-context failed when connecting to cntlmonAPI
- globus_error_put(): globus_i_gsi_gss_utils.c:globus_i_gsi_gss_handshake:862: SSLv3 handshake problems: Couldn't do ssl handshake
- OpenSSL Error: s3_srvr.c:2010: in library: SSL routines, function
- SSL3_GET_CLIENT_CERTIFICATE: no certificate returned
- System testing was done using version 1.8.453 of LDAS. The system tests results were as expected.
- The new Solaris 10 opteron box was installed into the ldas-dev system.
- There was a 50% increase with disckcache jobs and a 70% increase in frameAPI jobs. Other bottlenecks in the system prevented an over all increase in job rate.
LDAS System Administration (Anderson)
Caltech
(Dan Kozak)
- Got new filesystem created on 6140 RAID arrays mounted to new opteron dataserver-cit (Phil installed the HBAs).
- Got /scratch mounted on opterondata-dev (QFS shared mode between Sparc & Opteron servers).
- Worked with Sun on the ldas-cit hardware (swapped in two CPU boards with dataserver-dev then did the memory and CPU replacements there to minimize downtime).
- Gave Ben another list of bad md5sums on h(t) data to republish.
- Computed list of tapes for LHO shelf storage.
- Did _lots_ of tape work at CIT after we ran out of free tape space due to lots of the tapes we got from CACR tapes turning up unusable. Freed up tape space by getting rid of the 2nd CIT copy of A4 L1 data. Collected data from the filesystem to allow the repack of old /home tapes.
(Phil Ehrens)
- Helped Dan Kozak with network fiber route tracing in Millikan and Booth.
- Helped Pinkesh Patel with an email problem.
- Took failed UPS down to Bridge basement for disposal.
- Fixed broken /etc/aliases files on m8, couch, boo, and garrak. Somehow these had reverted to the install defaults. Will need to watch for this reversion on other machines.
- Issued new certs for lscsegfind for LLO, LHO, and CIT.
- Added 6 new grid user credentials to the cluster.
- Installed authoritative DOE certs on ldasbox1 and ldas-suntest1 and linked them into the default locations to support the use of openssl verify by globus.* Installed authoritative DOE certs on ldasbox1 and ldas-suntest1 and linked them into the default locations to support the use of openssl verify by globus.
- Met with Albert Lazzarini to discuss additions to the Travel Authorization Request form.* Met with Albert Lazzarini to discuss additions to the Travel Authorization Request form.
- Discussed implementation and disposition of the Travel Authorization request form with Fred Donovan at MIT. Fred maintains a parallel implementation of the form specific to the MIT site.
- Discussion with Cindy Akutagawa regarding an addition to the LIGO Visitor Appointment Form of a notice to nonresident alien applicants advising them of the requirement to include a Caltech FNIF form. Implemented the notice and a link to the form.
- Upgraded Linux on the ldas-test datacon and metaserver machines for LDAS compatibility testing. The update kernel did not have the sk98lin module built, so I built a kernel with sk98lin and installed it on both machines.
- Swapped disk 3 in dataserver-dev for disk 1, which would no longer "light up". Rebuilt raid sets.
(Erik Espinoza)
- Re-build lastest FC4 kernel rpm w/ SysKonnect driver.
- Moved node321-node329 to LinkSys switch.
- Put internal interface on ldas-condor.
- Submitted vulnerability info re: postgresql to Greg Thain.
- Contacted Liebert about support for DC Air Conditioning.
- Dug up details about RHEL 5.
- Wrote wiki page for kernel rpm rebuild.
- Updated node321-node329 for Condor 6.8.4 & latest FC4 patchset.
- Configured ldas-condor for latest FC4 patchset.
- Configured pgsql on ldas-condor.
MIT
(Fred Donovan)
- Ganglia, yum update ldas-gridmon, yum confs updated nodes, installing Ganglia now.
- Data11 is ok, needed to build kernel 2.6.20 to get sata operational.
- Data1 has bad 3ware disk (port 4). Trying to get smartd to work with 3ware.
Livingston
(Dwayne Giardina)
- Had various errors while updating ldas-gridmon. Thanks to Stuart's help gridmon is now patched with the latest updates. All nodes and gridmon are running the new ganglia and are reporting correctly.
- Tape eject and shipment.
Hanford
(Greg Mendell)
- As a part of routine sys admin work, I am working to fix a few gaps in the transfer of data to CIT, and checking with others on a few corrupt h(t) files.
(Ben Johnson)
- Got simple command line NDS clients working on Mac OSX, Cygwin on Windows 2000, gentoo linux (32 and 64 bit compiles), debian "etch" linux, and solaris 9 (haven't tried 10 yet). Currently working on server.
- Submitted the sharedmemory C-based datafind "back-end" to LDR CVS. http://www.lsc-group.phys.uwm.edu/cgi-bin/cvs/viewcvs.cgi/tools/SharedMemServer/?cvsroot=ldr
- Attended Rolf's Advanced LIGO CDS discussions this week. My main contribution was the suggestion that there be an NDS protocol agreed upon and documented (and maintained) that would allow others to write NDS clients in their favorite language and OS.
- ldas-grid@LHO hung again, despite the new kernel. The next plan of action is to swap out HDDs with ldas-pcdev1 at next hang, or Tuesday morning whichever comes first (and also run yum update a la ldas-gridmon at that time).
General Computing (Wallace)
MIT
(Fred)
- Solidworks machine now ok, quadro fx 1500 works well
- Rebuilding tintagle; new machine for KM's new hire
- Misc. user accounts/desktop xp troubleshooting; got parallel/serial for FM soldworks.
Livingston
(Dwayne)
- SolidWorks 2007 install on a new PC, then troubleshooting licensing issues. Thanks Mike and Larry.
- kantech server reboot to clear random communication errors with controllers
- spam filter cleanup
- other usual user requests and support
(Shannon)
- More work on risk assessments...
- Planning DST patch. Non-issue mostly for GC except for interdependencies between GC & CDS, LDAS.
- Working with Bell South and LSU to find out about possible T1 service for the LSC meeting.
- Ordered backup hardware for Rusyl's laptop.
- Ordered various other bits & pieces.
- Investigated the Gentoo DST patch. Will need to do more research into this before the 3/6 when I plan on applying the patch.
- Sunday/Monday Responded to a vulnerability with Solaris 10. More details about this elsewhere. It was a *serious* security vulnerability that affected us, and I consider us lucky it didn't get nasty. We closed the holes ~24 hours from public exploit announcement.
- Other usual stuff.
Hanford
(Christine)
- Spent many hours trying to get SSH tunneling and NFS automount working on a MAC laptop. NFS automounting requires root access, the user and group names and id numbers must match on the MAC and on the NFS server, the client and server have to be in each other's hosts tables, etc. None of this is easy on a MAC. After many attempts I was unable to even get the user and group id numbers changed. Shannon didn't want MAC laptops to use NFS mounting of home directories anyway; he recommended SFTP or SCP. After much frustration I finally found a free software package that provides a GUI to do SFTP, SCP and SSH tunneling. Two other such software packages did not work, this one finally worked. It is http://rsug.itd.umich.edu/software/fugu.
- Continued work on configuring the new Cisco router. Put in the work around for the 2007 DST changes.
- Tues. 2/20, in coordination with Dave, I'll be rebooting all the GC Solaris servers, fortress, the Control Room GC Linux, and the GC DMT AMD Solaris computers to install the 2007 DST patches.
Caltech
(Mike)
- Continued work on moving over users to our new Home account server. This is an on going project. I still have many users to move over.
- Larry and I moved all GC computer equipment from our old storage room to our new assigned room over on the East Bridge sub-basement area.
- DCC: Worked with Larry on trouble shooting the nightly process function that updates the public search for off-site users to access docs from the Homepage www.ligo.caltech.edu <http://www.ligo.caltech.edu/> (Document Search link). We now have the public search working.
- Tested Microsoft’s monthly patches with GC and engineering software.
- Worked on a SolidWorks issue with Mike Smith. This is an on going issue, it looks like I have to reinstall SolidWorks due to some others issues I came across when trying install the latest service packs.
- Working the Spam Filters with Larry & Christian.
- Other miscellaneous user support plus sysadmin tasks.
(Bruce Sears)
- iLog Maintenance and Planning: (0.5 days)
- General iLog maintenance (user adds, keyword adds, systems work, etc.)
- Discussion of iLog issues and future development.
(Veronica)
- LSC: Ongoing support of the March meeting. Updates of the databases/webpages of technical and observational papers. Updates of mailing lists.
- LIGO: Working on the homepage. Miscellaneous web updates. High-resolution images for a publisher. Updates of the PAC website. File transfers for Sydney.
- CaJAGWR: Taped and compressed for streaming the video of the last seminar. Website updates /user support.
(Christian)
- Worked on the Spam Filters with Mike and Larry.
- Other misc.: Continued onsite software/phone support.
- Out sick most of the week.
(Larry)
- Spent a deal of time working on different DCC issues. We are now repairing some of the items that had been band-aided in the past. Most of the files have now been centralized, this has taken some serious time. We also discovered a bug in the s/w for the updating of the public search documents and found a work around until that issue can be addressed. The problem has been sent to the programmer of the s/w.
- Working/worked a number of license issues for applications being used by different groups.
- Started installing patches for the DST change and acquired a patch for one of the older servers. Also, working on the logistics for updating the various servers and related equipment.
- Working on documentation for risk assessment.
- Working with Mike on home account transfers to the new server.
- Assisted in resolving various web issues.
- Worked the spam filters with Mike and Christian.
- Worked with PMA in various room modification projects.
- Moved computers with Christian from the second floor and then worked with Mike in moving computers from different locations to EastBridge.
- Made a number of modifications to e-mail aliases with quite a few still to go. This has been on the increase lately.
- Worked on resolving an issue with a Solaris 10 vulnerability.
Advanced LIGO and Supporting R&D (Shoemaker)
ELI (Adhikari/Zucker)
=====================
PSL: Rick and Annamaria circulated a draft optics BOM for upgrade of the PSL tables. Meeting
w/Benno to finalize facility requirements for AdL lasers is planned for March LSC meeting.
TCS: Tobin, Phil and Rana posted a revised TCS laser table layout
(http://lhocds.ligo-wa.caltech.edu:8000/mLIGO/Thermal_Compensation_System)
SEI: Both ISI and SAS programs had a good week, see respective AdL reports
ISC: OMC substrate design is now ready for circulation to prospective vendors, RFQ cycle expected to
begin next week. See Garilynn's report and this URL.
http://ilog.ligo-wa.caltech.edu:7285/advligo/Output_Mode_Cleaner.
Vendor has been selected and design finalized for the hermetic sealing of in-vacuum DC PD preamplifiers.
SUS: Welding issues on the OMC SUS structure are believed resolved. Production schedule predicts all components
in house around 4/1. See Janeen's AdL report. LOS EQ stop retrofit outsourced to vendor
for engineering and prototype fab. Initial vendor design submittal is under LIGO review.
VE/AOS: HAM6 septum layout on hold pending AdL output beam layout (in process). See this URL
http://ilog.ligo-wa.caltech.edu:7285/advligo/NextMeetingAgenda?action=AttachFile&do=get&target=G070025-00.pdf
G&A: RA/MZ request all those contemplating upgrades, retrofits or experiments associated with or
parasitic to the ELI vents (but not currently baselined) to please contact us now to discuss their
proposals
Advanced LIGO Systems
From: Hiroaki Yamamoto hiro@ligo.caltech.edu
Modeling and Simulation (Hiro Yamamoto)
e2e weekly meeting
- Valerio Boschi explained a new mechanical system modeling tool, MBDyn (MultiBody Dynamics).This is used by the HAM-SAS group to model their system.
- Sany and his group are using state space models developed before developed using Maple. For now, Valerio will update this Maple based model, but will transit to the MBDyn model as soon as possible.
- The integration of the MBDyn model with e2e framework should be possible as a new e2e primitive, because MBDyn is an open source program.
Static IFO simulation (Hiro)
- The diffractive loss of FP systems with the surface deformation due to thermal heating has been calculated.
- For a symmetric cavity with nominal curvature of 2076m, the diffractive loss is ~1ppm. The loss due to the mode matching ( prepare an input beam for a cold state FP cavity and heat the FP mirrors with the same input beam ) is ~0.1%. (1 W TEM00 goes to FP, 0.999W TEM00 mode reflected back ).
- For an asymmetric cavity proposed by Peter, beam size being 5.5cm on ITM and 6.2cm on ETM, the thermal deformation makes the diffractive loss to be ~13ppm. A smaller beam size on ETM will help to reduce the loss. This should be compromised with the increase of the thermal noise.
Modeler - e2e simulation engine (Hiro, Bruce, Melody)
Melody:
- Currently working on user documentation for the UserDefiniedPrimitive.
Bruce:
- Completed modeler branch version 3.2.2 which contains all non User Defined Primitive related code added to the modeler since the last release. This is now a stable version which could be released. All these changes are also in the main trunk version in which ongoing UDP feature development is occuring (version 3.3).
- Continuing the organization and documentation of all code changes related to User Defined Primitives in the modeler since the last release.
Mechanical Simulation for advanced LIGO (Sany and SLU team)
- This week Douglas Carpenter (a physics major freshman) joined our LIGO research group officially. He is now learning how to use Matlab. Andrew continued optimization of triple pendulum?s damping control filter for the yaw DOF in our e2e modeling. He made an e2e code to compute the open loop transfer function, and is currently analyzing the results of computation. Sany continued his project on e2e modeling of AdvLIGO triple suspension?s modal control. Although the e2e model can damp the triple suspension reasonably, its damping performance seems to be somewhat different from the original simulink model developed by Laurent Ruet. He is now comparing the two models part by part by computing various transfer functions with the respective models. Mark Barton, Valerio Boschi and Jameson Quave helped him learn how to use simulink for linear analysis.
ALFI : e2e front end (Melody, Bruce)
Melody:
- Fixing a few quirks in the dialog and in the UserDefinedPrimitive feature.
CDS Prestabilized Laser
From: Peter King <pking@ligo.caltech.edu>
The Beckhoff Automation control panel arrived. Only four more components to go before we can actually do some software testing. In the meanwhile I have been going through the pages (and pages) of documentation on TwinCAT. It looks straightforward enough, only time will tell. At least it's not a hard language to read.
I have been thinking of additions to the PSL safety plan and am currently drafting out a sample standard operating procedure (SOP). I have subsequently found a pair of laser safety goggles that have the desired optical density at both 808 nm and 1064 nm plus a nice high transmission in the visible (75%).
Seismic Isolation
From: Ken Mason kmason@ligo.mit.edu
BSC Seismic Isolation Assembly and Test
- The new H3 shims to balance the isolation stages at full load have been installed and the stages have been leveled. Two leg element masses from the old BSC stack were added to stage 2. Rich Mittleman is retesting the system.
- Next week we will remove the stage 0-1 shims and replace them with new shims which are designed for full load and to reduce cross coupling.
- LLO is concerned that we cannot get the air bake oven installed in time to meet our schedule. We have asked Galli & Morelli to quote doing the cleaning at their facility.
- A new schedule has been created and posted in the seismic ILOG.
http://ligo.phys.lsu.edu:8080/SEI/801
Single Stage HAM Design
- We have reviewed with HPD several design changes which came up at the preliminary design review. HPD is now 55% complete with the design and are projecting a 16% increase in the cost.
From: Brian Lantz <BLantz@stanford.edu>
SEI telecon notes for Friday, Feb 9 2007
Announcements
- LLO outreach center on the cover of the Livingston phonebook
HAM contract status
- HPD is working on system installation and stage 0 deflection.
- Design estimate cost is about 112% of original
- Any news from PSI on the actuator feasibility not yet, Ken will ping them.
- No complaints on schedule, yet.
Progress on the BSC
- shims, trying to get system together, tooling works, but the tolerances are very tight. The tooling
will have to be redone for Advanced LIGO. It will work for the full-load shims at LASTI, but it will
not worth with full-load and less cross-coupling shims for at LASTI.
- Laurent has a sketch posted of one solution, MZ also suggests a telescoping main screw.
- stage 2 actuators in the wrong place, Calculations and redesign are done. Calculations by Laurent
and Ken Smith seem to be lining up. Calculations continue.
- additional cap sensors? Cap sensors are ordered, should arrive on or before April 6. Rich M will
check on the location of the testing units.
- mock pod electronics: GS13/ L4C emulation board has been laid out, should be sent out next
week for fabrication.
- GS13 tester design should be sent out next week.
- coil driver looks pretty much done, looks nice.
- Mohana has started to look at the STS2 emulator board
- control module probably good enough with +12 and gnd, since the neither of the two wires to the
motor are attached to anything else (like case ground).
- real pods at LLO - locker code, clean assembly, STS-2s? Joe Hanson to look at better ways to
hold the gear to the motor. several suggestions made - bigger set screw, epoxy, off-center pin,
keyed shaft. Brian O will confer with Joe H and decide. Epoxy is leading candidate right now.
- Still working on getting together an assembly procedure for the pods.
- Brian L to send Joe an email about the 2 broken STS-2s.
- Ben A. has info on locking modules in the ISI interface from Brian O & Shyang.
- Joe G recommends that the locker/ unlocker should stay separate from interface board because it
would be less complicated. This will be the way it is done .Since there are 2 GS-13s controlle
from each ISI interface board, we will try to put 2 locker controllers per locker chassis.
- cleaning: Rob Luna got the shipping quote. Ken will write a description as a scientific instrument.
Allen Sibley is in charge of the clean room
- Aluminum in the BSC ISI: many plates are made from 7075. one should not use 7075 in UHV.
Dennis has guess that it's only a problem at elevated temp so it might be OK with just a acid
etch, and not a bake.
can we test a small part?
- risk damaging an oven
- asking John
- alloy should make it not a problem
- ALS, SLAC bans zinc
We should try to find someone with experience in a non-baked syste. Mike to call Fred Dylla at
Jefferson Lab. Brian L to ask Dan D, and look for somebody at SLAC.
For advanced LIGO, we should replace most of the 7075 with 6000 series, because the parts are
stiffness limited, not strength limited. 6000 series is just as stiff, more vacuum compatible, and cheaper.
For the LASTI prototype, we need to figure out how to clean the parts, because the high temp vacuum
bake is probably no good.
Seismometry and Corner station SPI
- 20 hour run last week. Looked at the data from that to try to figure out what is important?
Least squares model captures the drive pretty well. We had 3 temp probes working, the most
important term is a temp gradient. We would like to 1) have more temperature isolation, 2) temp
compensate the system 3) better design to minimize gradients will probably put in a pit to help
with diagnostics
- Also making a way to calibrate the pressure.
From: Dennis Coyne coyne@ligo.caltech.edu HAM SAS
Yoichi, Ben, Virginio, Riccardo, Dennis, Alberto, Dave
- Alberto shipping 1 AML driver to Ben (CDS) so that software can be developed; also shipping 2 coil driver bds, 1 alu box to Ben for repair
- Virginio to post elog entry this afternoon. Table was in contact somewhere -- had to re-balancemeasured transfer functions to LVDTs (1.5 hr each). 1st attempt at DC control foiled by photon bug (doesn't save all filters?). Implemented viscous damping on 4 vertical -- 3 loops have high freq noise injection
- Wasn't floating yesterday -- tried to float but didn't succeed. Should see 3 large peaks on all 4 channels if the table is truly floating. The table floats for a day or so before temperature changes (likely) cause it to drift to the stops. Dave intends to implement stepper motor controls to enable faster re-floating of the table -- will test stepper motors & drive manually for now
- 1 vertical and 2 horizontal geophones currently on the table -- witness LVDTs are running (wethink) -- but have not been calibrated
- Virginio will try one by one local loop closures, re-measuring transfer functions after each loop is closed. Alberto & Dave will pursue modal approach
- Dave to ask Rich (?) to help with script for unattended transfer function measurements. Dave or Alberto will initiate the automated script before leaving for the night (not a good idea for someone to initiate the script remotely)
Suspensions
From: Norna Robertson <nroberts@ligo.caltech.edu>
- I have been working on several items ( e.g BS thermal modeling with Mark, quad assembly estimate of required person-months with Calum and Janeen) which are not quite complete - so will aim to report next week.
From: Janeen Romie <janeen@ligo-la.caltech.edu>
*Enhanced/Advanced LIGO *
- Working on OMC design. Met with Sam yesterday to review the new safety stop design. He preliminarily OKed the stop layout with respect to the optical beam layout as it is, and as it might be if changes are made. Facilitated daily meetings with the engineers.
- Calum has headed back to Glasgow. We very much appreciate that he could be at Caltech for so long. His presence, knowledge and support is greatly appreciated.
- Working with Carol and Florence on opening the 8 fabrication accounts pertaining to Advanced and Enhanced LIGO.
- Worked with Norna on the Birmingham osem count for prototypes. Working with Bob Taylor on initial LIGO osem count needed for site spares, R&D spares and Advanced LIGO prototypes.
- Provided a list items that need to be addressed for the recycling mirror and input mode cleaner suspensions, in preparation for the HAM Cavity design review, scheduled for May. This list is in support of schedule and budget analysis as well.
From: k mailand kmailand@ligo.caltech.edu
Adv. LIGO
- The CES shop is continuing work on the LASTI tooling assemblies. I have e-mailed Ian re. delivery time for his outer support frame, we will use it to test our assembly.
- I'm making an assembly of a suspended cavity beam dump concept for Mike S. I have a sample piece of kapton wire for a test of this concept.
- I have revised a sketch of a high resolution 3 axis positioning mechanism for Peter King for his laser assembly task.
From: Chris Echols cechols@ligo.caltech.edu
Advanced/Enhanced LIGO Output Mode Cleaner
- Submitted following mechanical drawings to Valley Precision Metal Products in Valencia, CA for quotation:
D020482, REV A UPPER MASS SCREW DRIVE SYSTEM QTY: 4
D060491, REV A MAIN SECTION, UPPER MASS, OMC QTY: 1
D070020, REV A MAGNET HOLDER, OMC QTY: 8
D070032, REV A T-SECTION, UPPER MASS, OMC QTY: 1
D070045, REV A LOWER BLADE COVER, OMC QTY: 2
These are for the remaining parts required for the Output Mode Cleaner prototype Upper Mass stage.
Core Optics
From: GariLynn Billingsley <Billingsley_G@ligo.caltech.edu>
- The 40 meter IFO is impacted by scatter. We plan to coordinate with them to measure the existing scatter in-situ, then assist in cleaning the optics in-situ, then re-measure. We have spares of the 40M optics that we believe will serve as good representative samples for lab measurement.
- We are placing an order with Insaco for fabrication of the compensation plate for LASTI. Ed Jasnow advises not to create a Fab account for this since the total cost is 21K. Insaco is providing the material.
- The LASTI TM is still on schedule for delivery Feb. 28th. It will go to Lyon immediately after a cursory inspection here at Caltech. Schedules have been updated.
- The budget for COC substrates for Advanced LIGO has been updated to include Suprasil 3001 (ne 311SV) for the beamsplitters and the thicker size of the compensation plates. The vendor provided a complete estimate for all substrates so the rest of the optics were updated for current pricing.
From: Liyuan Zhang <zhang_l@ligo.caltech.edu>
- We got some preliminary results with our new integrating sphere, which increases the collecting angle (theta) range from the 14-69 degrees of the old integrating sphere to current 1.5-78 degrees. While the 1" mirror shows a consistent result, the LIGO-I mirror 4ITM04 shows about half of the averaged scatter measured with the old sphere. Although the system and the measurement condition are quiet different as before, the discrepancy is still too large to understand. We are scanning other ITMs (4ITM08 and 07) to get more information and will keep eyes open on this issue.
Auxiliary Optics
From: Michael Smith smith@ligo.caltech.edu
OPTICAL LAYOUT
I revised the non-stable RC optical layout and the stable RC optical layout based on the criteria of achieving minimum wedge angles for the BS (1.66 deg) and the ITM (1.5 deg). Clearance of the BS PO mirror from the main beam determines the BS wedge, and clearance of the ITM ghost beam dump in the vicinity of the BS determines the ITM wedge. I gave a power-point presentation describing the layouts at the ADLIGO Systems meeting. The stable recycling cavity reduces the fabrication cost by approximately $140,000 per IFO.
From: Phil Willems <willems@ligo.caltech.edu>
TCS Noise on initial LIGO
Patrick Sutton and Cheryl Vorvick described in a Hanford elog on January 22 how glitches were observed in the PD1AC channels on TCS every 10 seconds, correlated with the updates to the polarizer orientations. Patrick analyzed the effect of such glitches on AS_Q by statistically correlating the glitch rates between the two channels and concluded that TCS glitches were not influencing AS_Q at a significant rate. More recently, Shantanu Desai used KleineWelle to conclude that about one large TCS glitch was getting into AS_Q per week. Cheryl and I have been using the known coupling transfer function of TCS to AS_Q to determine how real TCS glitches would appear in AS_Q. So far we think the typical TCS glitch in AS_Q has amplitude ~6e-18 m and has most of its bandwidth at 10 Hz, where it is buried in noise and not visible, supporting Patrick's conclusion. However, occasional glitches of larger amplitude or higher frequency could get through and be seen.
Cheryl and I suspect the cause of the glitch is vibration of the polarizer induced by step changes in its orientation. We suspect this because the glitch always follows the orientation change by ~0.1s, and because 10 Hz is a plausible vibration frequency. We also think this could cause visible glitches inEnhanced LIGO. We propose that the problem can be significantly reduced by programming the rotation stage controller to slow down the step changes and make them less impulsive- currently they happen faster than we can resolve using a 16 Hz encoder data channel.
Absorption in LIGO Test Masses
Analysis of the TM acoustic frequency shift data collected by Sam Waldman and Valera Frolov suggests the following absorption levels in L1: 2 ppm in ITMX, 6 ppm in ITMY, 3 ppm in ETMX, and 3 ppm in ETMY. Mike Landry and I have performed experiments at H2 to measure the absorption in the TMs there but have not yet analyzed the data.
For additional information about this report, contact Albert Lazzarini or Phil Lindquist