There will be no LIGO Executive Committee scheduled Monday, January 15, 2006 due to the holiday. There will be no LIGO Executive Committee scheduled Monday, January 22, 2006 due to the Staffing Committee Meeting scheduled for that time
MOU |
Attachments |
Balearic |
DAT, Z |
Carleton |
DAT, OPS, OUT, Z |
Embry-Riddle |
OPS, OPT, Z |
Florida |
ACF, DAT, OPS, OPT, OUT, Z |
LA Tech |
OPS, OUT, Z |
Northwestern |
DAT, OPS, Z |
SLU |
OPS, OUT, Z |
>From: Rod Luna <rluna@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
>From: Phil Lindquist – Lindquist_p@ligo.caltech.edu>
>From: "Funaro, Catherine" <Catherine.Funaro@caltech.edu>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
>From: Florence Kaufman <fkaufman>
>From: Gina Salone <gsalone@ligo.caltech.edu>
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
We are assembling the end-of-December report for the National Science Foundation.
As reported last week, we are beginning to discuss the preparation of the proposal for Continuing LIGO Operations (FY 2009 – FY 2013). We will follow the usual process: propose an outline, assign responsibilities, and prepare a schedule. The target will be to have a complete draft by mid-July. Concurrent activity will include preparation of the Annual Report for FY 2007.
The NSF notified us today that they are scheduling a Total Business Systems Review (TBSR) of LIGO and associated Caltech business systems at Caltech February 27 through March 2. The NSF team will be looking at our LIGO reporting and budgeting systems as well as Caltech’s procurement, payables, financial reporting, property, and human resources processes. We are not sure yet how many of staff will be affected.
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
>From: Bill Tyler tyler@ligo.caltech.edu
A schedule for LIGO campus facilities safety audits has been distributed to both the audit team members and the facility "lead personnel". The audits are scheduled to start on the 18th of January 2007.
Summary of S5 Activities at LIGO Hanford Observatory (compiled by M. Landry)
Extended periods of forty to sixty mph winds last weekend kept both IFOs from locking for long period. Duty factors were down, particularly on H2, with H1 up 71% of the time, H2 65% for the week. Ranges varied broadly as has been the case over much of the last two months, 10-15Mpc on H1 and 5-7+Mpc on H2.
We're gearing up for a ~1 week commissioning break starting on Jan 22. Key tasks are H1 PEPI, H1 higher power/WFS bandwidth increases, and line mitigation on both machines. We'll endeavor to resume science-mode or near-science-mode running in the late evenings after the commissioning day ends.
Some S5 highlights from the LHO elog are bulleted below:
Outreach (D. Ingram)
Outreach recognizes LHO's Josh Myers for coaching a LEGO robotics team at Christ the King School this winter. Josh worked with a handful of students weekly over a couple of months. Remember, LIGO is not LEGO.
Enhanced/Advanced LIGO (Janeen Romie):
--------------------------------------------------------------------
Reported under General Computing, see below.
---------------------------------------------------------------------
Reported under LDAS System Administration, see below
---------------------------------------------------------------------
Storage/Condor/LDAS admin:
Reported under Data Analysis activities, see below
See Advanced LIGO
LIGO Activities:*
- In the process of building the Test Point manager (TPM) code for later
OS revisions, Alex found a memory leak problem, which may or may not
have been the cause of TPM problems noted at LHO a while back. The code
has been fixed and loaded at LHO. At some point, a decision needs to be
made if and when the new code should be loaded at LLO.
40m Lab Activities:*
- The equipment and software for the new alignment system is ready and
will be installed over the next few days.
Enhanced LIGO:*
- Jay has put together an integrated controls drawing (DC readout,
suspensions, seismic) for the OMC. We are working off of this toward
verifying a cost estimate. We will also have to take into account some
CDS infrastructure pieces that will be needed to support this, including
reflected memory network connections, timing system, etc.
See also Advanced LIGO
IFO commissioning, Electronics, controls, computers:
Vacuum squeezing:
Lab Infrastructure, Bake lab:
Initial LIGO Suspension Thermal Noise Testing (Contributed by Gregg Harry)
Visitor Steve Penn and I got the initial LIGO suspension thermal noise experiment operating again. This time a clamp inspired by Virgo is being used. This clamp system uses harder tool steel to clamp the wire, and larger screws to allow for higher torques. It performed well in single wire tests at Hobart and William Smith.
The clamp was installed and the experiment pumped down to vacuum. Finding and measuring Q's on wire modes is the next step.
HAM SAS Installation
This week we used the HAM SAS elevator to succesfully extract the optics table and the old support table from the Yend HAM. The HAS SAS unit minus the optics table is now positioned on the elevator and ready for installation into the HAM chamber. Virginnio and Alberto are currently testing and calibrating the LVTDs and actuators. In addition to this the in-vacuum HAM SAS wiring is being installed.
Over the weekend we are hoping to do a fit check of the HAM SAS in the Yend Chamber
ISI
We have installed an optical lever to independent check the off- diagonal terms of the stiffness matrix. Stay tuned for the results.
Pondermotive
Build up on in-vacuum hardware has occupied the majority of this groups time
_______________
John Zweizig
This week I have been generating several lists of Data Quality segments through the first year of S5 running, including
_______________
Kent Blackburn
TCLGLOBUS
GRID APPLICATION DEVELOPMENT:
OPEN SCIENCE GRID VALIDATION TESTBED
OPEN SCIENCE GRID INTEGRATION TESTBED
OPEN SCIENCE GRID MANAGEMENT
Igor Yakushin
_______________
Gregory Mendell
_______________
Patrick Sutton
LDAS Software (Maros)
-With modifications to the diskcacheAPI and frameAPI, LDAS is under
system testing to ensure that it no longer hangs when trying to access
file systems that are unavailable due to NFS issues (PR#3015).
-CntmonAPI can now handle resources that span multiple lines (PR#3098).
-System testing for LDAS was done using version 1.8.422 of the software.
Some regression tests failed in FrDump and FrVerify. These errors are
under investigation.
-The failures over the weekend were the result of data not arriving to
the datacond machine. This results in the datacondAPI failing the job
with 'Bad Symbol' errors.
-The dcmangle.tcl script has been modified to properly write out the
variable MOUNT_POINT with multiple lines.
LDAS System Administration (Anderson)
MIT:
(Fred)
-All quiet.
LLO:
(Igor)
-Running tests on the new X4600 dataserver machine. So far no hardware
problems found.
-Improving replication monitor:
http://ldas.ligo-la.caltech.edu/ldas_outgoing/archiver/Status_Pages/SEGMENT_REPLICATION/index.html
-In particular, a) it is now looking at the segments covered by raw
frames from /frames and /fb0_frames so that one can determine
if all the frames were published and up to what time the segment
database can be trusted; b) the data about published and raw
frames is now collected not only for the last 2 days but for
the whole run.
-Disk 4 from 3510 failed.
LLO:
(Dwayne)
-Reset 3 ports on the switch to correct node connectivity problems
-Placed property tags on the new 3511s and x4600
-Received replacement disk for failed disk id4 in 3510, will
install this afternoon
-cluster_mon changes to the pie chart, how it displays node status
-Tape eject and shipment
LHO:
(Greg)
-I have reported to Keith Riles, for the purpose of generating
data quality flags, the GPS segments of data that are missing due
to the power failure at LHO on Dec. 25, 2006. I also just fixed
a minor problem with publishing from yesterday, which will bring
archiving and RDS generation at the sites and the transfer of raw,
trend, and RDS data to CIT up-to-date, later this afternoon.
(Ben)
-Most of my time is being spent on making a frame cache sync
daemon, in C. I'm currently working on getting it to do some of
the heavy lifting for queries so the LDRdataFindServer can be
moved back onto gateway.
-Assisted David Barker in setting up a zone on the site's Wiki
machine.
-Published some LLO h(t) data from Sep. 10 2006 that the original
h(t) generation pipeline missed (per Xavi's request).
-ldas-grid froze earlier this week. It is currently being
monitored for abusive processes, by logging "top" every 30s
(this is currently LLO's method as well).
CIT:
(Erik)
-Worked with Dan & Phil to mitigate issues revolving around power
outage and chilled water outage
-Monitored environmentals for Millikan, LarryLand, & Synchrotron
-Turned off condor, powered down the nodes
-Worked with Ed Maros to test "hung nfs" issues
(Phil)
-Performed various certificate related duties and actions.
-Damage control associated with the loss of power and subsequent
cooling problems at CIT.
-Began configuring marfik as the single point log_mon server for
desktop machines and servers.
(Dan)
-Finished FrChecking all frame files on node 304 for Erik
-Fixed phantom slot/tape in catalog at LHO
-Continued to work on setting up 6140 RAID units. Turns out
2TB limit on volumes is a known bug. Still working with Sun
on getting command line interface to work (which hopefully will
allow us to create volumes on all of the disk we have).
-Made arrangements for ldas-cit downtime to replace memory
(overtaken by events, will be rescheduled).
-Consulted with LLO on 3510 rebuild and global-spare situation
-Filled in all remaining gaps in raw data (tapes that had been
labeled 'tp' arrived at CIT)
-Suggested testing new diskcacheAPI with Ben's LSCdataFindServer
-Relabeled tapes at LLO
-With Erik, Phil, Larry & company, worked on fallout from power
outage and chilled water outage
-Did shelf storage tape inventory at CIT. Working on incorporating
this information into the SAM historian.
General Computing (Wallace)
MIT:
(Fred)
-Setting up test of webmail: squirrelmail, IloahMail, Horde IMP for ligo
-Continuing work on pellinore (multi zoned SUN backup machine) -
Ie: Apache, dovecot, mail; added zones to nis+, installing php eetal.
-Some printer isssues; new accounts, more software builds
-Few more additions to nagios
-ILOG additions for MIT LATSI
Livingston:
(Dwayne)
- installed FC5 x86-64 on natalia, running updates now
- with Shannon, moved GC network connections in old "new" building to a
new switch, replaced temporary switch in the SEC building with one of
the switches from previous step.
- installed Solidworks 2007 on laptop and desktop for a user
- setup a couple of streams in canit for a few users that wanted to
opt-out of spam scanning
- spam filter cleanup
- other usual user requests and support
LLO mail summary for 4 January - 11 January 2007:
Rejected: 19,212 (42 containing virus)
Accepted: 3,958
Total: 23,170
Hanford:
(Christine)
- Spent the weekend rack mounting all the new equipment in the server
room. In the end I was unable to power up most of the new equipment
because the new CDS UPS is not functioning yet and until that is working
I can't use the old CDS UPS.
- Set up two more laptops for Operators, a MAC and a WinXP.
- Finished some paper work from past purchases for Ruth for an audit.
- I've received two checks from a class action settlement against Dell
for over charging on taxes. Ruth told me how to send the checks to the
Caltech cashier for deposit to the Hanford Data/Computing account.
Spent time filling out paper work for that.
- Helped a user with a quarantined inbox. Helped another user whose
mapped network drive was no longer visible.
- Re-mounted the ldas and application server file systems to several
Solaris machines and to the Control Room Linux machine. After the power
outage on Christmas night these file systems were not re-mounted. These
machines are not used frequently so the problem was only recently
discovered.
CIT:
(Mike)
-Christian and I worked on updating all SolidWorks workstations from
2005 to 2007.
I also updated the PDMWorks Vault to 2007 as well. We are currently at
SP1.1 and will be upgrading to SP2.2 next month.
-Swapped out a wireless access point over in 40 meter. Christian gave me
a hand with this. We also ran an additional network cable to move the
access point into the Interferometer area, which gave us a better
wireless range.
-Larry and I worked in the server room rack mounting new Sun servers,
plus running additional network cables and some clean up work as well.
-Regular work on the mail server and working the Spam Filters with Larry
and Christian.
-Tested windows critical updates with GC and Engineering software.
-Spent some time dealing with the power outage. We had a UPS that went
down; Sun servers connected to this UPS had file system errors when they
came back on-line, ran (fsck) to fix these issues. One sun box in my
office has to be reloaded. Cooling system will be down a few more days,
we only have critical servers running for now until we get
our air conditioning back on-line. A lot of monitoring the server room
making sure things stay somewhat cool.
-Other additional user support plus sysadmin tasks.
(Christian)
-Gary McIntyre- Configured new laptop with the standard Ligo image for
Gary.
-Helena Armandula- Reinstalled Office 2003 and installed the latest
security patches from Microsoft.
-Mike and I upgraded Solidwork users from 2005 to 2007.
-Larry and I picked-up 2 portable air conditioner to use in the server
room after the campus blackout.
-Replaced toner cartridges for Irene Baldon and finished inventory on
printing supplies.
-Working on upgrading Web server (Amaldi) from Windows 2000 to 20003.
-Worked on the Spam Filters with Mike and Larry.
-Other misc.: Continued onsite software/phone support.
(Veronica)
- LIGO: Homepage redo. Various updates of CIT/MIT pages.
- LSC: Addressed an issue of e-mail lists, checked several lists for
inconsistencies. Updates of the database of technical papers. Updates
of the publications webpage.
(Larry)
-Continual work on procurement and licensing issues.
Tracked down some problems with the Dell orders and have resolved them.
Still working the the mathematica license renewal with campus.
Distributed a few more matlab licenses.
Procured a number of items to help keep some of the computers running
during the air-conditioning problem.
Procured misc. items for different groups.
-Assisted PMA in working out issues on the different moves for offices
and labs.
Worked on some of the physical moving of equipment in preparation for
the office changes.
-Worked a number of cabling items at different locations.
-Spent time keeping things going during the power outage and the
air-conditioning problem. The air-conditioning issue will continue for
another week. We do have the core items on the GC server room running.
Thanks to all those that have helped and are helping monitor things
(Mike, Christian, Veronica, Erik, Dan and Phil). With the cooler weather
and some chilled water to our local unit we are now able to keep things
physically secure without someone being here all the time to watch over
the equipment. We still have to extend the schedule for people but it is
working out.
-Working on the 40M computer replacement. I will probably move the unit
over to the 40M and finish working on it over there.
-Assisted the DCC with a number of small issues.
-Working on the new mail server and home account system. I've discovered
a few gotchas and should have them worked out pretty soon(depending on
jury duty).
The samba system will have to be changed but the testing of the new
system has shown a good improvement in performance.
Still have a number of tests to run on the mail servers but it appears
all of the show stoppers have been taken care of.
-Installed a number of h/w items, with Mike, into the racks. The
shuffling of equipment has started.
-Added a number of new accounts and cleaned out a couple of old accounts.
-Worked a couple of backup issues. Still need to do some testing to make
sure things are working properly.
-Worked the spam filters with Mike and Christian.
We are still filtering out over 10K messages/day on the main mail server.
-Regular assistance with minor items such as printer jams, restarting
processes on end user boxes and clearing out tables.
(Bruce)
-iLog Upgrade: (4.0 days)
Implementing restricted/unrestricted iLog entry viewing access on user
by user basis.
CDS Infrastructure:
From: Rolf Bork rolf@ligo.caltech.edu
Seismic:
ISC:
Work has progressed on the development of an in-vacuum DC Readout Diode and a Thermal Actuator to be used in the mLIGO Output Modecleaner System. A schematic for the prototype detector has been prepared and the associated PCB is being designed. Due to size and weight constraints, the DC detector circuit board is being made as small as possible. The DC diode is to live in a small laser welded vacuum tight enclosure containing a trace gas for leak detection. The diode electronics enclosure also serves as a mount for the diode element as well as providing a beam dump and stray light baffle.The thermal actuator consists of a custom designed vacuum compatible aluminum nitride heater element that provides about 2 watts of heating capability. The heat flows uniformly and symmetrically into an aluminum optic holder to accomplish the length actuation.It is a desire for the system components to maximize radiative cooling to avoid thermal distortion in other system components. With this in mind, a company has been selected to try some experimental vacuum-compatible coatings to the aluminum surfaces of devices to be cooled. The emissivity of the surfaces can be increased by a factor of ~8 beyond bare aluminum. A small vacuum test chamber will be used to verify the effectiveness of the coatings prior to design completion. Estimates for heating and cooling times have been made as well as conductive heat transfer modes into the output modecleaner bread-board.Another new aspect to this development is the use of "disposable" electronics modules to enhance modularity and vacuum compatibility. The laser welding, coatings, and leak checking will be done by a list of outside vendors that have been selected based on their expertise in these areas. It is believed this will help reduce cost and increase reliability overall. The same techniques can be used for other in-vacuum electronics in the ISC system and other applications.
From: Peter King <pking@ligo.caltech.edu>
I spoke with Benno about the interface that will be provided with the front-end laser. The laser will be under control using the Beckhoff automation interface. I have obtained the Beckhoff hardware and software information from Christian and have a call into Beckhoff HQ for pricing and other information. Then the aim will be to test communications between EPICS and the Beckhoff software.A Ge photodiode was installed in a general purpose photodetector board and the circuit is being debugged.
From: Brian Lantz <BLantz@stanford.edu>
SEI telecon notes
Friday, Jan 5, at 2 pm eastern, 1pm central, 11 am pacific, etc.
Announcements HAM contract status
Ken is inclined to keep the table flatness at .010" , and will email HPD as such. He will include info from Arland tool that tolerance for a machine cut for BSC table (front and back) is not too hard. Dennis will see if specs from Initial LIGO shed light on req's.
Progress on the BSC
Rich will do a few more test, and then remove 2 actuators from interfering corner and inspect them. Maybe use a sticky thing to remove contaminants from inner gaps? Suggestions for changes to the actuators for Advanced LIGO and single stage HAM:
Brian will send email to Ben Abbott and also ask for a few more 1m cables
Brian O will check up with Joe Hanson, the new clamps should be done soon. Not sure about status of the locker/ unlocker program which Shyang is working on.Rich M to check the boards and cables for the GS13 to be sure that LASTI has all the parts needed to fix the GS-13s when they come off at the clamp replacement
Ken got quotes back and is talking with Dennis about options (this is contract sensitive)Feedforward at Stanford
Seismometry and Corner station SPI
From: Dennis Coyne <coyne@ligo.caltech.edu>
Subject: minutes of the HAM-SAS weekly meeting, 1/10/2007
minutes of the HAM-SAS weekly meeting, 1/10/2007
David S., Ben, Dave O., Ric, Alberto, Virginio, Dennis
1) LASTI
Cables out of the bake oven in two batches (Fri & Mon) -- slip of ~3 days
Missing (class B) bracket being remanufactured & cleaned & air-baked by G&M
2) Electronics
Virginio mounted LVDT boards into rack -- will make a special cable for vacuum feedthru pin flip & will then test -- EPICs channels seem to give correct results -- need more D25 cables
3 coil drivers are in the NIM crate -- 2 more coil drivers modules have been(?) shipped from Italy (Marwan); these units need to be put into a NIM module (need 4 plus 1 spare) triple: will only use M1 stage (issue with supporting the lower stages with the current infrastructure) -- this is deemed acceptable
From: Janeen Romie <janeen@ligo-la.caltech.edu>Enhanced/Advanced LIGO
From: k mailand kmailand@ligo.caltech.edu
From: GariLynn Billingsley <Billingsley_G@ligo.caltech.edu>
We have received two quotes out of 9 RFQs for the LASTI compensation plate. Looking into acquiring inexpensive but suitable glass for this effort.
We are answering some questions about the pathfinder procurement, nothing surprising yet.
Ed Jasnow and GariLynn Billingsley visited General Optics on the 9th, to check up on the progress of the polishing of the LASTI TM. GO estimates an end of February delivery, putting the TM (with ears bonded) at MIT around the beginning of May, ready to hang by the end of June, after the bonds cure. Helena is working to be sure that LMA is ready to receive and coat the LASTI TM as soon as possible upon receipt. We will modify the contract with GO to reflect the new promised delivery date.
From: Helena Armandula ahelena@ligo.caltech.edu
Advanced LIGO Coatings - First ContactStarted testing methods to apply and remove First Contact on a large mirror. I am using an old pathfinder LIGO I substrate. The results are good but not perfect; the techniques and the tools I am using need to be refined.
From: Michael Smith smith@ligo.caltech.edu
SLCI compared Peter Fritschel's scattered light analysis in the AS port with my analysis (see http://www.ligo.caltech.edu/~smith/AOS/SLC/T070003-00_AOS-P.F.-comparison.pdf . The two different approaches are equivalent. The biggest difference between the magnitudes of our scattered light calculations is the value used for the BRDF of the Brewster's window surface. I have contacted Newport Corp and TMA Technologies; they will try to give me some information on the back-scattered BRDF of uncoated superpolished windows.
INITIAL ALIGNMENT
I am in the process of writing the Initial Alignment Conceptual Design Requirements document.
COST UPDATE
I am in the process of updating the cost estimates for ADLIGO AOS.
Enhanced LIGO
I made a layout of the OMC in ZEMAX for Sam Waldman.
For additional information about this report, contact Albert Lazzarini or Phil Lindquist