(Meeting time: 10:30 am Pacific Time)
1. Announcements
2. Programmatic (Marx)
3. Comments on weekly report
4. LSC and Data Analysis (Saulson)
5. LIGO Lab Operations
6. Enhancements (Zucker)
7. Advanced LIGO (Shoemaker)
8. Change Control Board/Technical Review Board Session as needed
Site and other business issues (after 5 minute break)
LSC Council to discuss a motion to approve the agreement on closer
collaboration
with Virgo. Immediately after the meeting, the Council will vote by email
on the motion.
The Detection Committee continues its series of meetings to prepare a
proposal for a blind injection exercise in S5 data. This was proposed by
Patrick Brady for the Inspiral Group at the November LSC meeting. When the
Detection Committee completes its proposal, it will be discussed by
the LIGO Directorate and the LSC Executive Committee.
A meeting of the LSC Exec Comm will be held on Thur 18 Jan. The agenda
is still being prepared, but it will include discussions of the approval of
two papers, the Stochastic S4 Radiometer paper and the CW S3/S4 Time Domain
Pulsar Search paper.
>From: Rod Luna <rluna@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Document Management System (Lindquist)
Joe Giaime has agreed to chair a committee that will restart the DCC redesign effort. Please stay tuned.
George Stokes has been very busy assembling documentation on the current system as well as information on the attempted conversion to FileHold. We expect to have this phase largely completed by the end of this week. We are looking for guidance as to whom this information could/should be provided. Linda will be assembling a shelf full of hardcopy.
>From: "Funaro, Catherine" <Catherine.Funaro@caltech.edu>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
>From: Florence Kaufman <fkaufman>
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
We are assembling the end-of-December report for the National Science Foundation. The target is to deliver the report next week.
We are beginning to discuss the preparation of the proposal for Continuing LIGO Operations (FY 2009 – FY 2013). We will follow the usual process: propose an outline, assign responsibilities, and prepare a schedule. The target will be to have a complete draft by mid-July. Concurrent activity will include preparation of the Annual Report for FY 2007.
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
>From: Bill Tyler tyler@ligo.caltech.edu
No report this week.
This report covers the previous two weeks of S5 running, owing to
the holidays. Two-week duty cycles then were suprisingly good
despite the Christmas Day power outage (more below), with H1 logging
75% and H2 higher at 86%. Downtimes were offset by smooth and
quiet holiday running. Ranges were typical of times with sporadic
high microseism:
11-14Mpc
on H1, and 6-7Mpc on H2.
Moderate winds, and tumbleweed baling resumed Tuesday on site.
Some S5 highlights from the LHO elog are bulleted below:
S5 Run (Valera Frolov):
The science data taking uptime was 70% during the two week holiday break. The downtime was mostly due to the seasonally high micro-seismic activity. The problem with Y end station building temperature control caused the temperature change but the disruption of the data taking was minimal since the repair was done during the power outage at LHO. The BNS range was 12-13 Mpc most of the time. There were two interferometer related problems reported during this period: one was a new 45 Hz line and harmonics in the DARM spectrum, which was tracked to the RM optical lever laser, and the other was the low frequency 3-4 Hz intermittent noise in DARM, which is still under investigation. The replacement for the RM optical laser is planned on Friday.
[J.G.] Note on Y end temperature problem: There were strange multiple failures in the Y end HVAC equipment, discovered on Dec 22, that caused poor temperature control in the CDS highbay. The temperature in the Y VEA also changed, though not as much because the heat load there is so small. Repairs were complete Dec 28.
--------------------------------------------------------------------
Reported under General Computing, see below.
---------------------------------------------------------------------
Reported under LDAS System Administration, see below
---------------------------------------------------------------------
Storage/Condor/LDAS admin:
Reported under Data Analysis activities, see below
CDS Computing (Lisa Bogue):
- The holidays were reletively quiet. There was a small dmt problem
that was readily resolved by John Z.
- Working on re-writing the perl scripts that auto-generate some of the
S5 pages.
LIGO Science Education Center (Thacker)
Prepared programs for and conducted outreach to 3 groups this week: Livingston Parish Science Teachers, Pointe Coupee Parish AMPS Mentoring Group, and Tangi Home School Group. Prepared for Saturday Teacher Professional Development workshop (Tangi Schools MSP project)
Ordered materials for LA GEAR UP workshop next month.
Drafted Activity protocols for: Colored Shadows, Polish Portraits and Gravity Blanket
See Advanced LIGO
See Advanced LIGO
Some of the picomotor mirror mounts came in over the holidays, and Greg has started unpacking them and preparing for installation.
ISI pre-isolator hardware (R.Mittleman, F.Matichard)
The Compliance results for the apparatus were showing a difference from the model of about 28%. We brought one of our electronics crates and a set of sensors to the manufacturer (ADE) who is look to be checked. We found three different problems, 2 of which were ours and one of which was theirs. We fixed our problems and now the sensors should be good to 1% (the remaining ADE problem) and the compliance matrix diagonal terms now agree with the model. The off diagonal terms have been reduced, but the system is till slightly asymmetric.
We found an effect that we were previously identifying as friction between stages is dues to a DC drift, most likely due to the temperature of the laboratory.
We are now using a combination of higher harmonics and transfer function measurements to characterize the interference of the system. We think that we currently have a small interference.
HAM SAS (D. Ottaway, A. Stochino, M. MacInnes and B. LaLiberte)
Most of this weeks effort centered on getting various parts of the HAM SAS from the loading dock to the lab. The HAM SAS was de-crated and moved to the optics lab adjacent the highbay. We will vent start taking doors off tommorrow (Friday) and will begin installing the elevator fixturing
In addition to this measurements on clustered geophones show an order of magnitude separation between the geophone noise and ground motion in the highbay of around an order of magnitude in amplitude in the middle of the night at 0.1 Hz. This means that we should be able to measure the isolation at 0.1Hz using only geophones and will not have to resort to putting an STS-2 on the HAM SAS.
Cavity Locking Tests
Ken M has built up a solid works model of this experiment and we will begin to order parts for this soon.
TCLGLOBUS
Still investigating the issues arising in the LDAS software associated
with GSI socket buffering.
GRID APPLICATION DEVELOPMENT
Currently running full HIPE with local cache at UCSD for meeting
the first OSG milestone which is using 25 slots at UCSD continuously
in one week.
After running 4 days (Dec 20, 2006 - Dec 24, 2006), LIGO jobs were
limited to only 4 slots because CDF and CMS jobs had maxed out the
slots from Dec 25, 2006 to Jan 1, 2007. This was reported to the USCD
and a meeting is planned for this Friday.
Restarted the run on Jan 1, 2007 and it has been running continuously
since then.
Started testing nano HIPE with SRM/dcache at UCSD. Pushed input LIGO
GWFs to LIGO partition under the SRM server but experienced failures
which are being investigated.
Met with Kent Blackburn and David Meyers to discuss initial steps
for benchmarking full HIPE at CIT LDG cluster without having to moving
any data. This requires some Pegasus property changes. We are working
with Pegasus developers to enable recognition that the data is already
available locally.
Held weekly teleconference with Pegasus developers to discuss progress
on meeting first OSG milestone, dynamic data clean up, and a conference
paper on dynamic data clean up in workflows. Discussed LSC publication
policies with group.
OPEN SCIENCE GRID INTEGRATION TESTBED
Reported problem on the ITB site validation table caused by change
in certificate needed by GridScan and VORS submit host. This has now
been resolved by John Rosheck at Grid Operations Center (GOC).
Attended weekly Integration Testbed teleconference.
OPEN SCIENCE GRID VALIDATION TESTBED
Configured NFS and updated kernel to 2.6.17-1.2142-FC4 on worker
node1 and CE. Updated to 6.8.2 Condor release. Successfully ran
site_verify on VTB 1.6.0 cache.
Attended weekly Validation Testbed teleconference
OPEN SCIENCE GRID MANAGEMENT
Developed and discussed an OSG Change Control Process to be presented
at this weeks OSG Executive Team meeting.
Signed off on the FermiLab Statement of Work as OSG Resource Manager.
Reviewed OSG Security Plan with subset of OSG Executive Team.
Filed first monthly OSG excel spreadsheet capturing progress made on
WBS tasks specific to Caltech and the Pegasus developers at ISI.
______
Gregory Mendell
Since the last report I have worked with other members of the pulsar
group on the S4 PowerFlux, StackSlide, Hough paper, with the latest
draft sent to the reviewers yesterday. The paper is expected to go
through several more iterations before a final draft ready.
______
Igor Yakushin
LDAS admin:
1) ldas-grid froze 3 times during recent couple weeks at LLO and couple
times at LHO. At the moment the cause is not known. I am running 'top'
as a cron job each two minutes to catch an abusive process in action.
Since I started doing this 4 days ago, there were no more problems with
ldas-grid so far.
2) Ejected/imported tapes on Tuesday.
3) Installed Solaris 10 update 3 on the new dataserver.
4) Wrote a segment replication monitor:
http://ldas.ligo-la.caltech.edu/ldas_outgoing/archiver/Status_Pages/SEGMENT_
REPLICATION/index.html
Data analysis:
Working on Coherent WaveBust online infrastructure.
______
Xavier Siemens
- Worked on neutron star populations
- Written the final data selection c code for Einstein@Home (this one's
finished)
- Shifts at LLO (Jan 2 - Jan 8th)
Work is proceeding on preventing the diskcacheAPI from hanging when
scanning non responsive file systems due to NFS issues (PR#3015). During
this process, it has been discovered that the frameAPI will not come up
if an entry in the mount point table suffers from NFS issues. As a
result, the code originally developed for the diskcacheAPI has been
moved to the genericAPI so the frameAPI can benefit from the solution.
To reduce the number of new processes created at the TCL layer, a touch
procedure was written (PR#3103). This replaces the need for calling the
system utility touch. It has been incorporated into cmonClient,
cntmonPI, ligolwAPI, and the genericAPI.
The manager now rejects jobs for which an API required by a command
macro is not available (PR#3087).
System tests for LDAS were done using version 1.8.408 of the software.
Some of the regression tests failed in FrDump and FrVerify. These are
being investigated.
A solid week of testing on four systems: ldas-dev, ldas-test,
ldas-suntest1, and ldasbox1. Most of the errors were timing issues which
resulted in the datacondAPI terminating the job. "Bad Symbol" (meaning
some data did not arrive at the datacondAPI in a timely manner and hence
was not available to the algorithm section) was the reason for the
datacondAPI's action. On lasbox1, the frameAPI was rebooted twice by the
manager due to memory limit issues. This was expected due to the small
amount of resources available.
Caltech
-------
(Dan Kozak)
* Fixed stuck staging (reported by David Meyers).
* Ejected tapes for shelf storage at both sites & CIT.
* Helped Mike with globus-rls-cli, pools and some info about the difference between /data and /archive.
* Fixed tapes marked as 'tp' (generic tape) at LLO.
* Helped Larry identify and work around the talitha newfs problem (newfs ignores the -i for filesystems over 1TB).
* Replaced a 3510 disk (first in a long time).
* Set up 6140 RAIDs on IP, other config ongoing as I'm dealing with Sun on a couple of issues.
* Fixed stuck tape robot daemons at CIT.
* FrChecking all frame files on node 304 for Erik (ongoing).
(Phil Ehrens)
* Coordinated with Larry, Veronica, Cindy, and Albert to install the Visitor Appointment Application online form on an appropriate machine.
* Investigated RAID failure on node304. Replaced a single bad drive in port 1, and ran rebuild with the ignoreECC option to rebuild the array.
* Investigated a problem identified by Mary Lei with LDAS on the dev system. Some log file links were stale. I created a patch for the genericAPI log.tcl library that is being tested by Mary. It seems that Tcl reports a dead link as a file that doesn't exist, which is inconsistent with existing file existence checks.
* Ongoing cleanup of expired certificates throughout the LDAS computing systems.
* General certificate related support.
(Erik Espinoza)
* Built various "LIGO" FC4 distributions to support new Sun hardware.
* Shipped 420 sticks of ram to ASA Computers.
* Further training of spam filters on GC Spam Gateway.
* Testing kickstart w/ Latest LIGO FC4 x86_64 Distro.
* Requested DVD Burner for D610 Laptop.
* Rebuilt RAID, ran fsck on /usr1 on node304.
(Stuart Anderson)
* Stress tested the 5 new X4600M2 machines at Caltech under Solaris 10 Update 3.
* Built a newer Linux kernel for the X4600M2 machines that appears to have
solved a kernel panic problem with the latest FC4 kernel.
* Ordered UPS and rack mount equipment to install the new Sun RAID systems
and servers for the LDAS-CIT cluster.
MIT
---
(Fred Donovan)
* All quiet, replacement power strips (2) ordered.
Livingston
----------
(Igor Yakushin)
* ldas-grid froze 3 times during recent couple weeks at LLO and couple times at LHO. At the moment the cause is not known. I am running 'top' as a cron job each two minutes to catch an abusive process in action. Since I started doing this 4 days ago, there were no more problems with ldas-grid so far.
* Ejected/imported tapes on Tuesday.
* Installed Solaris 10 update 3 on the new dataserver.
* Wrote a segment replication monitor: http://ldas.ligo-la.caltech.edu/ldas_outgoing/archiver/Status_Pages/SEGMENT_REPLICATION/index.html
(Dwayne Giardina)
* Noticed connection problems to ldas-gridmon from LLO GC DHCP addresses. eth1 on gridmon had no network connection. It does now, and connections are fine.
* Rack-mounted new 3511s and new x4600 with Bernie and Igor.
* Packaged tapes for shipment to CIT.
Hanford
-------
(Greg Mendell)
* The main sys admin activity since the last report, besides routine tasks, was to make sure the LDAS systems and services recovered completely from the power failure at LHO on Dec. 25, 2006. I am also making sure that archiving and RDS generation at the sites and the transfer of this data to CIT is up-to-date.
(Ben Johnson)
* Replaced bad T3 disk drive.
* Put new x4600M2 into a rack with a dedicated 2200 KVA UPS; installed Sol10 U3; currently burntesting the unit. The current location for the server is temporary pending more thought.
MIT:
(Fred)
-Ram tests tintagel, crashing, 1 bad ram stick RMA Genstor
-Replacement for thinkmate cpu's arrived
-Building horde, for webmail IMP interface
-More hosts added to nagios, more testing done
-Resolved some misc printer xp issues
-Built pellinore (sunblade 1500) powered on, virtual machine
(zone) "ligo" created for backup mail server; plan to create other
virtual machine (emvogil-2, oyster, + more) as my global backup machine.
Livingston:
(Dwayne)
- spam filter cleanup
- other usual user requests and support
LLO mail summary for 21 December 2006 - 4 January 2007:
Rejected: 42,091 (107 containing virus)
Accepted: 2,926
Total: 45,017
(Shannon)
-Laying out new VLANs for the switch gear. Previously, almost
everything was in one VLAN, now we need to segregate ports as the new
allocation comes online in places other than the computer users room.
-Upgraded the new fileserver to Solaris 10 U3. Added in ZFS hotspare
functionality.
-Contacted Arkeia on a support issue concerning ZFS. Issue resolved.
-Contacted Arkeia on a library support issue. Issue unresolved at the
present.
Hanford:
(Christine)
- I was sick last week, so I postponed rack mounting all the new
equipment until this weekend, 1/6-7.
- Postponing the rack mounting turned out to be a good thing because
Richard had his electrician in this week to install connections to the
new UPS for the server room. Richard bought some rack mountable power
strips that have network connections and on board computers to report
power statistics for the strips. I'm borrowing two of those for my
server room racks.
- I also received the Veritas backup software to be used with the new
raided disk arrays and tape drive.
- Purchased more wireless keyboards, mice, and USB drives. Everyone
with a laptop wants a wireless keyboard and mouse and many are using the
120 GB USB drives as portable backup for their laptops.
- Helped a couple of users get acquainted with their new laptops.
- Ordered a new laptop for another Operator.
CIT:
(Mike)
-Finish up working on Primavera/Prism servers. All software is now
updated and running correctly.
-Worked on our VPN server establishing a new connection for a new user
in LHO. This user now has a VPN connection as well. I'm also looking
into the IP database to free up some more IP numbers to accommodate
additional advance LIGO users that will need an offsite connection to
our Primavera/Prism server located here on campus.
-Moved backup server Repository and backup software to another server.
This new server will be our permanent storage for all NT servers with
plenty of room for growth. I now have all client servers backing up to
the new server.
-Bridge Annex server rooms: Larry and I installed and fired up SunFire
X4600. We had to moved another server out of RM:19 to RM:18 to free up
some power consumption in RM:19 to run the X4600.
-Ran end of month ghost backups on all NTSRV's.
-Continued work over the Holiday's on Spam Filters and working the mail
servers.
-Additional user support plus other sysadmin tasks.
(Veronica)
- LIGO: Homepage redo. Various web updates.
- LSC: Updates of the databases of publications and technical
papers. Addressed an issue with the discrepancy of LSC-related
mailing lists (lsc-all is an alias, and the actual list is generated by
merging 2 separate lists). I got a complaint of someone not getting
messages even though the person was in the lsc-all.
- CaJAGWR: Web updates/ user support.
(Christian)-Osamu Miyakawa- Configured new system with the engineering
Ligo image for Osamu.
-Lloyd, Dorothy- replaced Dot's old CRT monitor with a new LCD monitor.
Irene Baldon- replaced Irene's old CRT monitor with a new LCD monitor.
-Shourov Chatterji-- Hard drive failure on laptop. Rebuilt new hard-drive
with our standard ligo image.
-Rod Luna- - Upgraded Rod?s workstation from Windows 2000 to Windows XP.
-Finished upgrading Flexml license server from windows 2000 to 2003.
-Worked on the Spam Filters with Mike and Larry.
-Other misc.: Continued onsite software/phone support.
(Larry)
-Worked a number of purchases. A number of new notebooks systems have
arrived and Christian is getting them ready for distribution. We should
also receive more related items over the next few weeks.
The wireless modem card for the PC so far has tested out positive. We've
purchased another one and will probably purchase one more in the near
future.
Checking on some licenses supplied by campus that are due to expire.
-Did the monthly backups. Presently, in the process of redoing some of
them. After checking some of the tapes it was discovered some items did
not get backed up completely so I am doing a little more checking but
things appear to be OK now.
-Working on moving home accounts to the new server. So far so good. I
should start moving over a number of people in the next few days, after
I get rid of some of the dead accounts.
-Installed some new h/w and reworked some of the cabling in the computer
rooms.
-Setup a few new accounts and modified a number of mail alias lists.
Presently, going over the lsc mailing lists with Veronica. Also, going
through the whitelist for the new mail server.
-Working with PMA and others on some of the room modifications that are
taking place.
-Misc. e-mail work. Spam filter cleaning and related items. We are still
blocking over 10K/messages a day on the main mail server.
Also, took care of a couple of mailman issues. Still need to process a
number of requests for new mailman lists.
-Did some testing on a couple of lowend Gige switches. They are OK for
offices or small labs but not for the core network system.
From: Ken Mason kmason@ligo.mit.edu
From: Brian Lantz <BLantz@stanford.edu>
HPD continues with the preliminary design of the single stage HAM isolation and alignment system. The Preliminary design review will be held on Jan 11 at the HPD facility in Boulder, CO.
BSC ISI
The LASTI team continues the air testing of the ISI system for the BSC. A number of issues with the displacement sensors have been identified and corrected, the foremost of these being low voltage levels in the power supplies. This supply voltage error caused the internal voltage reference in the devices to misbehave, affecting the scale factor of the devices. Now that this has been corrected, the compliance matricies of the system are being remeasured.
In addition, we are reviewing the procedure for trimming the springs to achieve the low cross-coupling we would like to see in the compliance matrices. We have been in contact with Ken Smith at ASI to help us better understand and implement this procedure.
Tech Demo at the Stanford ETF
The Tech Demo is being preped for another data run.
Advanced Vertical Seismometer
The Vertical seismometer has been disassembled and a variety of mechanical modifications are underway to improve the sensing and mechanical performance. These include the replacement of the old capacitive sensors with optical sensors, the addition of a mirror for the new interferometric sensor, addition of mounts for the temp sensor suite, remounting of the actuator coil to improve the stiffness, and installation of a setup jig to correctly pre-buckle the offload springs.
From: Riccardo DeSalvo desalvo@ligo.caltech.edu
HAM SAS has arrived at LASTI
http://www.ligo.caltech.edu/~desalvo/HAMSAS/arrival@LASTI/HAM-SAS@MIT3.jpg
http://www.ligo.caltech.edu/~desalvo/HAMSAS/arrival@LASTI/HAM-SAS-in-LASTI.jpg
From: Ben Abbott abbott_b@ligo.caltech.edu
All new activity since last weekly is written in red.
HAM-SAS:
Custom Electronics chassis: (# needed + #spares)
-LVDT Driver (2 + 1) -1 being tested, 1 ready for test, one stuffed, but needs boxing and testing
-LVDT Interface (2) Installed
-Stepper Motor Interface (2 + 1) - Installed
-Coil Driver Interface (1) - Installed
-QPD Whitening (2 + 1) - 2 Installed, 1 here, needs testing and boxing.
-QPDs (4 + 1) - 5 in hand, need testing.
-Guralps Interface (1 + 1) - 1 tested, 1 built but untested.
-AA Interface Rev 4 (1) - Installed
-AA Interface Rev B5 (1) - Installed
-AI Interface Rev 3 (1) - Installed
-Coil Driver (4 + 1) - 3 modified and Installed, 2 Modified and being sent from
-In-Vac Breakout boards (2) Arriving 1st week in January, Connectors ordered, due in 30 days, but I may score some samples on short turn-around. Last piece of in-vac machining-work finished. All screws and hardware should be here tomorrow.
Commercial Electronics:
-Opteron Processor (1) - Installed
-Stepper Motor Driver (4) - All due to ship here 1st week of January.
-I/O Chassis (1) - Installed
-Power Supplies (2) - Installed
Miscellaneous:
-In-Vac Accuglass cables- All 13 were due to ship Thursday, but they are saying that there might be a problem with the 9-pin cables. They may not ship until next week. I'll find out more tomorrow.
-Stepper Motor Drivers - All 4 due 1st week in January
-Guralps cables - Specialty cables from Guralps Instruments Ordered 12/21 quoted a 30 day lead, but they'll "see what they can do".
-Special cable connecting the LVDT 25-pin Witness board connector to the 9-pin ADC connector is finished, and ready to send.
ISI:
-ISI Interface - (3 + 1) I've started to draw a schematic. I'll send it out for review when it's ready.
-GS-13 Boards - (many) 15 boards came back from PCB Express. They'll get stuffed sometime soon, and delivered sometime thereafter.
-Coil Driver - (3 + 1) (Mohana) - The Coil Driver board has been stuffed and is in test. The interface board is stuffed and ready. The metalwork is finished and looks fine.
From: Janeen Romie <janeen@ligo-la.caltech.edu>
From: k mailand kmailand@ligo.caltech.edu
The CES shop is continuing work on the arm style, and LASTI conveyor style, installation tooling,
also the elevator mechanism for the lower quad, and the fixture modifications for the tooling interface.
Most of the final shop drawing details for the initial assemblies will be complete 1-10.
ken
From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>
Mesa Beam interferometer, John Miller back from vacation, restarting the sideband locking tests and designing the power recycling cavity structure
From: Dave Reitze <reitze@phys.ufl.edu>
ELIGO and AdvLIGO Faraday isolators
- A reworked version of the Faraday rotator went through the LIGO bake out
and RGA analysis in December. It passed as far as ELIGO is concerned, and
a long term contamination test is planned soon. Luke Williams and Evgeny
Kamenitsky went to Caltech to assemble the rotator; the housing was
assembled, and lessons were learned that should make it easier in the
future
- We've found fused silica thin film polarizers from CVI Laser that
deliver 39 dB isolation up to 100 W in the Enhanced/Advanced LIGO
FIs. We're rethinking whether we want to use calcite polarizers for
Enhanced LIGO (but will keep them for Advanced LIGO
Enhanced LIGO EOM
Due to a snafu with purchasing agents, we have not yet received the 40 mm
long RTP EOM crystal. Hopefully it will arrive in about a
week. Meanwhile, working on finalizing housing design.
IO PDR
- tentatively scheduled for sometime in February. Docs in preparation.
From: Michael Smith smith@ligo.caltech.edu
SLC
I am in the process of comparing Peter Fritschel's scattered light analysis in the AS port with my analysis. I underestimated the scattered light from the OMC by neglecting the build-up of scattered light inside the OMC resonant cavity; however, with the suspended OMC, it is still negligible. The biggest difference between the magnitudes of our scattered light calculations is the value used for the BRDF of the Brewster's window surface. This discrepancy needs to be resolved.
PHOTON CALIBRATOR
I made a ZEMAX conceptual layout of the non-folded ETMX photon calibrator beams. Phil Willems' concept is for two photon calibrator beams to hit the ETM HR surface symmetrically across the diameter to eliminate torque on the mirror. In-vacuum periscope mirrors are required to direct the reflected beams out through separate viewports in the A-7A spool piece flange--one periscope will be suspended from the BSC optical table near the ETM quad suspension; the second periscope will be mounted to the chamber walls near the viewport on the A-7A flange
INITIAL ALIGNMENT
I am in the process of writing the Initial Alignment Conceptual Design Requirements document.
From: Phil Willems <willems@ligo.caltech.edu>
Photon Calibrator Conceptual Design:
------------------------------------
I have been composing the AdLIGO Photon Calibrator Design Requirements and
Conceptual Design Documents, using advice gathered from Rick Savage, Daniel
Sigg, and others. One thing learned by this is that we need to firm up the
vacuum and viewport layout for the folded interferometer at
can progress on a preliminary design for this and many other subsystems.
The photon calibrator produces both a recoil and an elastic deformation of the
test mass. These are 90 degrees out of phase (below the test mass resonances,
at least), and have different frequency dependence, the elastic deformation
being flat with frequency and the recoil rolling off with frequency squared. If
the photn calibrator illuminates the center of the test mass face the elastic
deformation equals 1% of the recoil at about 200 Hz. This only weakly depends
on photon calibrator spot size. The next step is to account for the test mass
resonances. Going off center could make this effect largely go away.
From: Peter King <pking@ligo.caltech.edu>
AdLIGO PSL
==========
Dark noise measurements of Ge, InGaAs and Si photodiodes have been
completed with the Ge photodiodes being the most quiet from 0.3 Hz to 100
kHz. Below 0.3 Hz all the photodiodes are about the same and below 0.1 Hz
it is hard to tell from the noise floor of the SR785 used.
I will be incorporating one of the Ge photodiodes tested into a general
purpose photodetector board to see how it behaves under exposure to high
power.
For additional information about this report, contact Albert Lazzarini or Phil Lindquist