Weekly Report for Week Ending November 30, 2006


LSC

Administration

Hanford Observatory

Livingston Observatory

Optical & Mechanical

Controls and Data Systems

40 Meter Facility

TNI

LASTI

CIT Science Group

Laboratory Computing

Adv. LIGO Development

Past Weekly Reports


Agenda:

(Meeting time: 10:30 am Pacific Time)

The LIGO Executive Committee Agenda for Monday, December 4, 2006 will be:

Announcements

Programmatic (Marx)

  • PAC meeting summary --- Albert (5 min)
  • PAP meeting summary --- David (10 min)

LSC Issues (Saulson)

  • Status of negotiations with Virgo on MOU

LIGO Lab Operations

  • Administration (Lindquist)
  • Sites (Raab, Zucker, Shoemaker)
  • Commissioning (Fritschel)
  • Optical and Mechanical (Coyne)
  • Control and Data Systems (Bork)
  • 40m (Weinstein)
  • TNI (Libbrecht)
  • LASTI (Ottaway)
  • Lab computing ( Anderson )
  • Science Group (Weinstein)

Enhancements (Adhakari, Zucker)

Advanced LIGO (Shoemaker)

Change Control Board/Technical Review Board Session as needed

  • No open change requests

Site and other Business Issues


Special Announcements:


Weekly Report Highlights


LSC Issues (Saulson)

The S4 Stochastic All-sky search paper was accepted by the Astrophysical Journal. The Editor also wrote, "I encourage you and the LSC to consider ApJ again for future LIGO papers!" [Exclamation mark his.]

LIGO Laboratory Administration (Lindquist)

PROPERTY MANAGEMENT (Luna)

>From: Rod Luna <rluna@ligo.caltech.edu>

  • Requested a one-year extension of the Temporary Import Bond for the Fused Silica Blanks that came from Germany
  • Provided assistance to Christian Cepeda in shipping a package to Dell.
  • Assisted the PWC auditors in showing them two pieces of equipment as part of the A-110 audit.
  • Cleared equipment disposal for LHO (B. Riviera), two sun computers.
  • Created property records for four UHV Gate Valves and one Data Storage unit at LLO.
  • Submitted the 2007 Replacement Vehicle Worksheet to GSA to replace one vehicle at LLO.
  • Tagged and created property records for one Pulse Generator at CIT (L. Cardenas CIT).
  • Attended a meeting with the Property Services Department to plan the FY07 Equipment Inventory.

DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner <turner@ligo.caltech.edu>

FileHold Status:

  • Worked with Mike Pedraza to ensure that all the links, downloads, and instructions were accurate for using the latest application. With the procedures working, released to the test group at large to do final checking against comments previously submitted to FileHold and ensuring that the bugs previously noted are resolved. Comments are due to me by Monday morning, December 4th. An accept/reject decision is due to FileHold on that day.
  • Met with Ian and George and went through a list of import issues that were flagged at the last upload/download of metadata and documents. All issues were resolved on LIGO's side but for two: provision of a list of acronyms to be used against the Title standardization; and a list of documents that are duplicates. These will be finalized in time for the upload/download for the "dry run" delivery. Additionally, a few items from the import issues were noted for resolution by FileHold.

Additional Activities:

  • As a board member, met with Document Magazine editorial team in laying out all the issues of the magazine for the first half of 2007. Additionally, was assigned responsibility for a weekly blog pertaining to archiving and imaging.

>From: Cleveland Mak <mak_c@ligo.caltech.edu>

  • Processed 4 sets of HAM drawings from Promec.

FINANCIAL SYSTEMS (Funaro, Brambila, Kaufman)

>From: "Funaro, Catherine" <Catherine.Funaro@caltech.edu>

>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

  • Orderedthe Vanguard analyzer which should be delivered in 2 weeks.

>From: Florence Kaufman <fkaufman@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Jasnow, Salone)

>From: Ed Jasnow <jasnow@ligo.caltech.edu>

  • An RFP is being prepared for the polishing and metrology of sample Advanced LIGO optics. It is anticipated that possibly two contracts may be awarded for this effort to select a contractor for the production of the 54 optics needed for LIGO 2.

CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)

  • There are no open change requests.

Summary of S5 Activities at LIGO Hanford Observatory  (compiled by M. Landry)

The machines have run quite well over the last week - 13-15Mpc on H1, 6-7Mpc on H2, with duty cycles of 90% on H1 and 85% on H2.  The high duty cycles are in part due to good running over the Thanksgiving holiday, and in part due to less wind over the last couple of days.

S5 highlights from the LHO elog are bulleted below:


LIGO Livingston Observatory (LLO) and Interferometer Operations (Giame)

S5 Run Coordination:

Most of the time the microseismic noise was still too high and the inspiral range was about 12 Mpc.

The duty cycle for a week was 67%. Sam, Phil and Valera are working on:

1) <a href="http://ilog.ligo-la.caltech.edu/ilog/pub/ilog.cgi? group=detector&date_to_view=11/27/2006&anchor_to_scroll_to=2006:11:27 :23 :48:24-waldman">upconversion noise injections</a>;
2) <a href="http://ilog.ligo-la.caltech.edu/ilog/pub/ilog.cgi? group=detector&date_to_view=11/29/2006&anchor_to_scroll_to=2006:11:29 :01 :19:11-waldman">thermal lensing measurements for ITM absorption</a>;
3) <a href="http://ilog.ligo-la.caltech.edu/ilog/pub/ilog.cgi?group=detector&date_to_view=11/30/2006&anchor_to_scroll_to=2006:11:30 :12 :09:54-waldman">tidal DARM servos</a>.

This work is expected to consume our whole 25 hour commissioning budget for a month. LDAS servers and fb1 had SAM-QFS/QFS patched. Next week it will be done on fb0 as well.

CDS Computing (Lisa Bogue)- More work on purchasing a Vmetro bus analyzer. The workorder is now complete and the vendor gave us an expected shipping date of 12/6.
- Worked with Dave and the ligo security team on a password policy
for CDS.

LIGO computing and network security (Roddy)

General computing and LDAS admin (Giardina)

Data analysis & computing (Yakushin)
---------------------------------------------------------------------
Storage/Condor/LDAS admin:
Reported under LDAS System Administration, see below
Data analysis:
Reported under Data Analysis activities, see below


Educational Outreach

(John Thacker)prepared four pre-visit packages and mailed outdeveloped visit programs for this weekDeveloped a new Design Challenge activity to be tested out this week.

(Janeen Romie) LIGO SEC Kinetic Art Project (aka Wave Wall)Working with Ed Jasnow and Allen on the final Superior Steel invoice.Wrote up procedure for locking the wave wall and put it on the LLO wiki.

Mechanical and Optical Systems (Coyne)

See Advanced LIGO


Controls and Data Systems (Bork)

See Advanced LIGO


40-Meter Interferometer (Weinstein)


  • DC detection:
    • Rob has commissioned the length and alignment control systems for the output mode cleaner. Using dithers in the kHz range, the OMC length control locks with UGF ~ 300 Hz. One by one, all 4 ASC loops lock and run with UGF ~ 25 Hz. However, there was considerable coupling between pitch and yaw. This seems to be due to the fact that the dither frequency is above the first resonance of the PZT mirror mounts (~ 600 Hz), so the whole thing is shaking. Rob then went down to several hundred Hz dither lines, and can now lock all 4 degrees of freedom simultaneously and robustly, with UGFs around 7 Hz. Rob used the reflected light to measure the visibility of the OMC. With no attempt at mode-matching (beyond what was done during the installation vent), he gets OMC visibility > 92.5%. Working with the main IFO at Michelson mid-fringe, Rob transfered MICH control from the RF signal to the DC signal; it worked the first time. With MICH under DC control, Rob measured noise spectrum and calibrated it using the technique Kirk and Rana used to calibrate the Michelson last month (the level is ~ 1e-11 m/rtHz at 100 Hz falling to ~ 1e-12 at a few kHz). The comparison of the measured noise spectrum shows that the DC control has far less dark (electronics) noise and 60 Hz harmonics, and is quieter than the RF readout above ~ 150 Hz (and about the same, below that). Although there's plenty more optimization and measurements to be done (including control of the PRFPMI), the above achievements meet our initial goals for this first DC readout prototype. This is a significant milestone! Rana swept the OMC length and measured the higher order mode structure transmitted through the OPD with poorly-aligned light from the PRFPMI. We can use the higher order mode peak locations and the distance between the TEM00 modes to determine the g-factor and the curved mirror's radius. Rob found that the DC photodiode whitening filters in the in-vac preamp are not quite right, and the digital compensation filters are not compensating. He modified the digital filters, but we need more whitening for low noise running with the full IFO. Rob is working with Ben to prepare a modified preamp to be installed at our next vent, along with a new preamp can / nipple to replace the one that is leaking due to mechanical stresses during assembly. We may vent in the next few weeks to replace the DC photodiode preamp / nipple and also Go's movable mirror for vacuum squeezing.
    • Rob is scriptifying the DC readout controls, to automate the locking and re-locking of the length and alignment servos.
  • Vacuum squeezing:
    • Go, Eugeniy and Shally re-established ~6 dB of squeezing after much optimization of the squeezer system. They noise-locked the OPO and got 3db of squeezing broadband. Go and Osamu measured the PSL laser noise to see if it was shot-noise limited, and determined that it will be difficult to see the effect of squeezing below ~ 10 kHz. Go's flipper mechanism for inserting a mirror to inject squeezed vacuum into the interferometer works well and is now ready for installation into the vacuum system. The ouptut optic chamber will most likely need rebalancing, so ballast is being prepared. Osamu tested a new photodiode for squeezing monitoring; it looks good. Go tried using an AOM to generate a 600 MHz single sideband for OPO locking, but it didn't work. He's going back to using an auxilliary laser, a Lightwave 120. The throughput is low and the control signal has an SNR of ~5, but the OPO cavity locks and for now he will live with it. It's less noisy than noise locking, anyway. Now he's working on locking the auxilliary laser to the PSL MOPA frequency. Go's next step is to set up the squeezing phase locking, and then he's just about ready to inject squeezed vacuum into the IFO. We will install his mirror in the coming weeks. Go plans to have a meeting of interested parties to plan this next phase of the squeezing experiment. Go gave a LIGO seminar last week on applications of servo-controlled optical cavities in biomedical imaging.
    • Kirk gave a CaJAGWR talk on Tuesday reviewing work on quantum squeezing for GW interferometry.
  • IFO commissioning, Electronics, controls, computers:
    • Kirk, Sam and Rana worked on the new common mode servo and tested it by locking the YARM, raising the UGF from 300 Hz to somewhere in the neighborhood of 6 kHz. They had some problems in the CM handoff, traced to a bad XYCOM board that was replaced. Kirk and Rana have been working on scripts for locking the PRFPMI smoothly. The scripts work and the PRFPMI can be locked smoothly and brought the arms to half fringe, the Michelson at half fringe, and the PRC fully resonant. A bit more work is needed to switch the arms over to RF signals, switch on the CM servo, and bring the PRFPMI to full power. Kirk and Rana locked the IFO in the FPMI configuration (without PR) and then made the transition from locking the arms at 1/2 fringe with the DC signal, to full resonance using RF signals. Bram has been designing slow alignment servo loops (Perl scripts interfacing with EPICS channels) to control the position of the beam on the ITMs and ETMs or the arm cavities (to minimize angle -> length couplings) and the launch positions/angles of the beam into the arms (to maximize coupling into the arms). He has a document and wiki page describing the system, and is commissioning his scripts.
    • Rana did some work on all the oplev servos, and got the UGF up to 5 Hz on all of them.
  • IFO modeling:
    • Osamu has released a new version of his loopnoise matlab package, which calculates the noise contribution from IFO control loops to the GW channel in AdLIGO. He concludes that the coupling from the SRC loop to DARM is rather large. Quantum noise due from the RF vacuum is important (especially at low frequencies) and he's been working on including it, but it is difficult. He's off to MIT next week for a summit on AdLIGO ISC issues.
    • Kirk found and fixed an error in the way the BENCH code implements non-100% quantum efficiency in the quantum noise. He will update the official BENCH code repository in the AdLIGO Wiki, soon.
  • Lab Infrastructure, Bake lab:
    • Luke Williams will be visiting from UFl and will be assembling big magnets in the Bake Lab clean room. Bob is preparing the lab (removing all magnetically susceptible materials). He has received the magnets; they are indeed quite powerful.
    • Bob continues to tend to the care and feeding of the 40m lab while Steve is on vacation.

Thermal Noise Interferometer (Black)

Not too much going on this week, due to the holiday. Akira has been measuring Q's of individual mirror modes, to see how much damping the monolithic rings provide. Greg ordered remote-control mirror mounts, to speed alignment when we change optics. The latest update from LMA and Benevento shows the mirrors with aperiodic coatings to be on schedule for an end-of-November delivery.


LASTI (Ottaway)

HAM SAS Preparation

Rolf and Rich Abbot were at LASTI this week installing the first installation of the HAM SAS electronics installation. Rolf gave the local LASTI staff a tutorial on the new “Auto Rolf” software. The clean ante-room has been completed and the additional vacuum viewports have been installed.

Rich Mittleman reports:

ISI Report

We have both stages of the ET freely hanging from the flexures (no inadvertent touching or rubbing). It turns out that the initially difficulties were a result of the large actuator installation procedure; we reworked the procedure and were then able to successfully install all of the actuators.

Over the last week or so we have been measuring the system transfer functions and compliance matrix.

Some data can be found in the LASTI ilog on November 28th.

ADE has repaired and returned the capacitive position sensors, so we now have a full set of working sensors.

LASTI Vacuum

Accu-Glass has successfully repaired two out of three of the vacuum feed thru flanges needed for the ET electronics and drives. The flanges have been cleaned and baked at Caltech and are being returned to us to be leak checked and hopefully installed. We will then remove the third flange and return it to Accu-Glass for repair.


CIT Science Group (Weinstein)

___________________
Patrick Sutton

Coherent burst analysis: I wrote an improved matlab function for predicting coherent likelihood sky maps for a general detector network using a simple GWB model (linearly polarized impulsive signal). Stephen Poprocki (U. Wooster) will be using this function as part of a method for estimating a GWB source position by comparingthe measured sky map to the predicted map. Also, I'm reviewing the updated LIGO-Virgo Project Ib paper,and I met with Tinto and Fairhurst to discuss tests of the usefulness of empirical mode decompositions in GW searches.

___________________

Eirini Messaritaki

I kept working on the S5 BBH search. I did some comparisons between the accidental coincidences and the playground triggers and saw some significant discrepancies. Further investigation revealed that it wasdue to incorrect rescaling of the background triggers to theplayground time. This has been fixed and the playground and background results are now consistent.___________________

John Zweizig

This week I have ported the DMT software to 64-bit architecture. This port requires 64-bit versions of framecpp and root, both of which exist in principle, but have not been packaged as rpms. All should be madeavailable for use on the LSC condor clusters soon. There is a small (5%?) increase in speed, but the main advantage of the 64-bit version is that multiple versions of DMT dependencies (fftw, framecpp,frameL) will not have to be maintained on the LSC clusters. I have also added a new monitor (dvTest) to the DMT. This monitor generates triggers when dataValid errors are found in a frame and has been upgraded to work on RDS frames as well as raw data frames. This will allow it to be run on L1 RDS frames over all of S5 to check the most important channels.
___________________

Igor Yakushin

1) Rerunning S5 analysis with the latest version of the coherent waveburst.2) Comparing software injection triggers obtained by coherent WB and incoherent WB+CP pipelines.3) Investigating why the incoherent WB+CP seems to have trouble estimating hrss of 70 Hz sine-gaussians while the coherent waveburst does not have such a problem.

___________________

Gregory Mendell

I have started some coding tasks for the hierarchical version of the Einstein@Home search. I have added these modules to LALapps under lalapps/src/pulsar/hough/src2: StackSlideFstat.c and StackSlideFstat.h, and will be adding in a StackSlide option to the hierarchical code over the next few weeks.
___________________

Rejean Dupuis

- spent much time re-installing OS on laptop due to failed hard disk- worked with Pinkesh on finding problems with his F-statistic implementation- reviving draft of paper on measuring properties of pulsar populations with GW observations
___________________

Duncan Brown

- Finished the AdvLIGO intermediate mass ratio inspiral paper and sent it for LSC review.- Worked with Lisa to understand strange filter output in the ringdown search. We now think we understand the observed SNR vs frequency plot for injections.- Worked with Diego on PTF search: he is currently writing up the PTF filter calculation with all the normalization in gory detail so he can track down normalization errors in the code.- Wrote letters of recommendation for 2 grad students and an undergrad.
___________________

Xavier Siemens

- Did S5 Einstein@Home analysis segment selection (have 53 segments of combined H1-L1 data with a total of 40 hours of coherent integration that span no more than 25 hours)
- Cleaned spectral lines of relevant S5 data set
- Worked on smaller sky grid for speeding up the coherent pulsar search, looks like we could get a factor O(10) speedup with acceptable SNR loss
- Worked a lot with Eiichi Hirose on time-domain calibration
- Started work to speed up LALDemod, working for a speed up by a factor of 30X.

___________________

Special note from Shourov Chatterji:

Suzanne and I are happy to announce the birth of our twin sons, Owen and Aidan! They were born on Friday November 24th at 5:10pm and 5:11pm. Owen is 19" tall and weighs 4 lbs 14 oz, and Aidan is 18" tall and weighs 5 lbs 12 oz. Despite the size difference, they look very similar and are probably identical twins. Suzanne,Owen, and Aidan are all doing well. I've posted some photographs at http://www.ligo.caltech.edu/~shourov/twins/.

Laboratory Computing (Anderson)

LDAS Software Systems (Maros)
-----------------------------

LDAS can now be built and run 64bit on Solaris Opteron. The final piece to the puzzle was to link tclsh with the g++ compiler rather than gcc so it would be able to handle C++ exceptions. Work has begun on supporting configuring I/O characteristics based on file system types. Most of the preliminary work is complete on ldas-suntest1 and is currently being bench marked using a single iteration of the nightly createRDS loop script. The latest version of TCL/TK (8.4.14) has been installed on ldas- dev. A combination of this and use of the non-threaded version of tclglobus is being used to verify if the managerAPI still coredumps inside of the globus 4.0.3 code. Test scripts continue to be modified to work from a common directory tree. Greg's createRDS scripts have been added this week. LDAS was system testing using version 1.8.385. The RDS Verification script was modified to properly report failure if data products generated could not be sent to the datacondAPI for comparison and verification (PR#3081). The permissions for the test script pr3076.tcl have been changed in CVS to allow for execution upon checkout. This will be officially verified next time LDAS is system tested.

LDAS System Administration (Anderson)

Caltech-------

(Dan Kozak)

  • Verified that sending mail now works from dataserver-cit.
  • Finished verifying that all files in CIT's /home filesystem are 'release_n' and online.
  • Got arogan and dietz to reduce their disk space usage on ldas- grid:/usr1.
  • Staged & pinned SFT data to disk at CIT.
  • Wrote a script to parse log_mon emails so that I get no duplicate messages and a by machine breakdown.
  • Wrote a tricky sed script for Shourov.
  • Updated the homedu stuff a bit.
  • Helped track down the slow down of LLO's /frames slowdown (itwas being swamped by a cluster user to the point where theframebuilder couldn't write out it's trend files).
  • Ejected S5 L1 tapes at LHO for shelf storage (that holds thedata Ben had copied into the cluster).
  • Turned off GEO RDS in lag plot.
  • Fixed LLO archiving after SAM-QFS patch (ground up restart).
  • Helped install new memory in cluster nodes.
  • Fixed the "duplicate" tape at CIT
  • Replaced 3510 disk at CIT.
  • Switched off "global spare enable" on 351x boxes.
  • Did big grep for scripts/programs referencing '/archive/home/': - dataserver-cit# wc -l /usr2/files.w.archive_home.in.them 2230823 /usr2/files.w.archive_home.in.them
  • Fixed stuck staging at CIT (during ingest, but it worked fine the following week so...?).
  • Kicked LDRSchedule at CIT a few times to get it to work again.

(Phil Ehrens)

* Completed debugging cycle of certcheck.sh - this tool can now be run from the command line or via cron to detect expiring certs inthe most thorough and efficient manner. When run from the commandline the results are dumped to a file and to the screen. When runfrom cron they are written to a file, logged, and sent via email to the defined address. The initial run of the program generates a persistent text file with the location of all detected certs. This file is regenerated at 3 month intervals.* Completed debugging and review cycle of visitor-application cgi suite for Alan Weinstein and Cindy Akutagawa. The suite of is to be deployed on a GC machine yet to be identified.* Added pwck, grpck, walk looptime reporting, and various default resource file enhancement to minimize false alarm emails in log_mon.* Helped with installation of new memory dimms in cluster.

(Erik Espinoza)

  • Looked into E@H not running.
  • Built/deployed kernel 2.6.18.3 on all nodes.
  • Removed two prior custom kernels from nodes.
  • Worked with Phil/Dan/Stuart to replace ram in 100 nodes.
  • Replaced ram in new mailscanner.
  • Replaced node327 w/ Kingston RMA node.
  • Discussed mail options w/ Larry & Stuart.

MIT
---

(Fred Donovan)

  • Just continuing to add smartd disk monitoring to cluster.
  • Matlab 2006b (and all previous revisions) license is now available; (Client license files need to have USE_SERVER added after theSERVER line; All lines from DAEMON (including INCREMENT) need to be deleted.)
Livingston
----------

(Igor Yakushin)

  • SAM-QFS/QFS patch was applied on dataserver, gateway and fb1.
  • svc-startd patch was applied to dataserver and gateway, both were rebooted to activate the changes.
  • Due to recent network problems at LHO, segment replication between LHO and other sites got stuck; restarted replication.

(Dwayne Giardina)

  • Ejected tapes for shipment to CIT, imported and labeled replacements.
  • Ejected tapes for shelf storage, imported and labeled replacements.
  • fb0-3511 configuration change to disable auto-config global spare.
  • A few nodes had network connection troubles after being powered down for Tuesday maintenance. We ended up with a few bad cablesand possibly a couple bad ports on the switch. Of the 8 cablesthat were disconnected from the switch, 4 tested bad.
  • With Lisa, applied SAM-QFS patch on fb1 coordinated along with additional patches on LDAS systems.
  • Restarted minute-trend disk2disk after failed start whenmaintenance completed.
Hanford-------

(Greg Mendell)

I have been working on FrDiff, a utility that checks for differences in the data between two frame files for comparing frames with and without compression options used during RDSgeneration. After adding a few more options to this, I will see if it can be added into ligotools. I also performed routine tasks to keep LDAS services running, and data archiving and RDS generation up-to-date.

(Ben Johnson)

  • The NoAuth dataFind server is being used by Igor at LLO and LHO, after setting it up at LHO. I am converging on a standard package (a.k.a. tarball) for running the LDRdataFindServer on the nodes.
  • The default LDRdataFindServer at LLO is now running on nodes 1-10.
  • About 80 RDS_R_L1 tapes were replaced last week. As of today,there is still about 20TB of blank tapes in the library.
  • Two T3 disks have been replaced this week, though we still have 22 spare disks left.
  • Fixed a bug in the FrStateFetcher code. It now reports the segment number's mode in a particular interval, not simply its value at the start of that interval

General Computing (Wallace)


MIT:

(Fred)-Dovecot imap in production now-Continuing to add gc machines to backup server tintagel-Setup for PAC meetings here this week-Installed matlab 2006b and new license for server-Some computer HW ordering for LATSI (3 opterons)-Local mit gc computing page (http://emvogil-3.mit.edu/~fjd)

Livingston:

(Dwayne)- Setup new fax/printer/scanner in Bonnie's office; driver installs on user PCs- Repaired our current GC backup system, manually ran full backups before Thanksgiving holiday.- Helped a user with some wiki and ilog entries- Gave the Einstein@Home PC in the SEC a network connection on a temporary switch, debugged other network issues in the SEC- Minor assists to Shannon on setting up the new raid unit in GC- Security server problems required restarting kantech software to repair a glitch with the front gate- Fixed a broken SAV install on a PC, uninstalled old SAV, installed new SAV, ran scan and removed virus on user PC. Thanks to Tom for doing most of the dirty work.- Continued training our spam filter- Other usual user requests and support

(Shannon)

-Investigating a problem with routing between our legacy and new networks. It appears to be local to the Cisco 3550. I am currently evaluating options with Foundry for a core switch upgrade since the FI-400 we have does not do BGP.-Working with LSU on permanent plans for BGP. We are currently in a temporary configuration while LSU sorts things out. May mean limited downtime on our WAN connection once they figure out what they want to do.-Benchmarking a ZFS filesystem. This is on our replacement backup server, which is not that critical for file access speed, but itis good information to have.-Still working on getting the CA up and running. I need to get a KVM in my office for this box.-Compiling historical expenditures to go over some budget items with Joe G.Hanford:

(Christine)

- Continuing set up of new servers and re-wiring of the server room.
- Tried to re-route network traffic from the primary circuit to the backup circuit for the Thanksgiving weekend because PNNL had a planned outage on the primary circuit. The backup circuit sort of worked,but only about 20% of the packets made it through and quite a few of them were corrupted. The ESnet engineer thinks it is caused by something Amerion is doing, the Amerion engineer thinks it is caused bysomething PNNL is doing and finally both engineers blamed it on the fiberbetween LHO and Amerion. The backup circuit has had nothing but problemsfrom the beginning, but it was working just fine in Aug.- The new Cisco 6504 switch/router is scheduled to be delivered in two weeks, so I will postpone any further network testing until the 6504 arrives. I'm going to have to take the network down repeatedly toget the new router working and to get BGP peering going with ESnet.- Other misc. user support.

CIT:

(Christian)-Created a backup of Dorothy Lloyd, Irene Baldon, Cindy Akutagawa and Ed Jasnow workstation.-Called dell support to replace cd/dvd burner on visitor system.-Worked on getting equipment together to be turned over to Caltech.-Restored files from ghost image for Ben Abbott.-Called HP support to replace fax modem on LaserJet 9050 MFP scanner/copier/fax machine.-Worked on the Spam Filters with Mike and Larry.-Other misc.: Continued onsite software/phone support.

(Mike)

  • Setup up Lee Cardenas workstation to connect via remote desktop to a Solid Works workstation.
  • Worked on mail server and home accounts with Larry.
  • Continued work on Spam Filters.
  • Helped Dot on an email problem. Eudora would crash when trying to launch this app. After uninstalling and reloading this applicationI was able to open up Eudora to see what the problem was. The culpritturned out to be a corrupted outgoing message.
  • Worked on a webpage for Linda Turner giving step by step instructions on how to connect to the FileHold server via http: plus installingthe windows FDA client application. These instructions are for thetesting group only.
  • Worked on Millikan's conference room pc by reloading the OS from win 2000 to XP. I'm setting up this computer for a VRVS conference forKent. I also was able to get the Polycom to work with this setup aswell. We still have some testing to do before this conference.
  • Ran some more test evaluating backup software for our NT servers. It looks like we are going with this software (Backup For Workgroups)they also offer an educational discount. The main purpose for thissoftware is being able to stop and start up services after backup iscompleted, which is needed for the pdmworks vault.
  • Tried loading a new Solid Works 2007 license using 2005 software which does not work with out a dongle. The new licenses do not require a dongle. I have a called GoEngineer's Support group and they aresending out a dongle to run 2005.
  • Other user support and sysadmin tasks.

(Bruce)

-iLog Maintenance: (0.5 days) General iLog maintenance (user adds, keyword adds, systems work,etc.)

(Veronica)- LIGO: Most time was spent doing web postings for the PAC/PAPmeetings at MIT. Ongoing work on the LAAC database scripts. Assisted Julie in the setup of Jay's homepage, other web-related user support. Updates of various webpages at LIGO and MIT. High- resolution images for ANU for the Amaldi07 poster. Updated the roster database.- LSC: Updates of the database of technical papers. Updates of the LSC-related mailing lists.- CaJAGWR: Taped/compressed for streaming the video of the last talk, burned it onto a DVD for LHO. Made a write-up of videotaping how- to for Michele Vallisneri so that he could do the taping on 11/14 when I was out of town. (Michele didn't make it to the taping due to a last- minute schedule conflict.) Updates of the CaJAGWR website.(Larry)-Continual work with procurement items. Ordered more Dell items to upgrade some of the existing workstations. Placing an order for more pocket drives as backup units for thosethat travel. Working on a purchase of some backup s/w for the PC servers.-Used the wireless modem over the holiday weekend. It works ok in a pinch. It is not as fast as DSL but is better than a regular modem. I was in a area that did not have any network connectivity but did have some temporary cell phone access and I was able to get to my e-mail a couple of times and take care of some minor problems remotely. I can recommend this tool only for those that travel a lot and will be in locations that don't have network connections but do have cell phone coverage.-Worked a number of e-mail issues. Most of the problems came from spam storms. Worked the spam filters with Mike and Christian. The amount of spam getting through the system has increased. The settings may need to be reset but hopefully we will have a newsystem in place before that happens.-Working with the DCC on a number of fronts. Presently, assisting in the testing of the new DCC software package.-Worked a number of requests by the users. Still have a number of items to take care of including setting up some more accounts.-Worked with Mike and Christian on the VRVS testing and setup.

Advanced LIGO and Supporting R&D (Shoemaker)


Advanced LIGO Systems

From: Hiroaki Yamamoto hiro@ligo.caltech.edu

Modeling and Simulation (Hiro Yamamoto)

modeling and simulation (Hiro Yamamoto)

-----------------------------------------------------------

e2e weekly meeting

----------------------------

Andrew of SLU (see report below) reported his study of the vertical mode of HAM-SAS using a statespace module provided by Virginio and Valerio.

Neither HAM-SAS model nor Mark Barton's quad suspension model does not have the suspension cage effect. Mark suggested that it is an easy and good enough implementation to place a stiff box on top of the HAM-SAS table. Valerio will modify the model to include the case effect.

Mark explained the difference of the test mass chain and reaction mass chain, and the effort to make ITM and ETM suspensions same (similar).

AdvLIGO LSC/ASC design using FP arm model with quad suspension (Osamu)

------------------------------------------------------------------------------------------------------------------

When the test mass is pushed by the length force only, pitch motion is excited due to force from the wire. In the experiment, the output matrix to OSEM should be adjusted to have no excitation in pitch motion. In the simulation, an extra force to pitch which is proportional to the length force is applied in order to avoid pitch motion. After some investigation with DC response, ratio from length force to pitch force to avoid the pitch motion for M1, M2 and M3 was determined to be 2e-3, 2e-3, 6e-3 respectively. As a result of applying these forces, cavity keeps lock longer than 100sec or more (previous ~10sec). However still lock acquisition is difficult once seismic motion is excited.

Static IFO simulation (Hiro)

-------------------------------------

A new base class is developed to that multiple configurations can be easily modeled. FP case is done and a couple cavity is being built to study the effect of the size of BS. Hiro helped John Mirror to simulate the Mexican hat cavity so that John can use a simulation to design WFS. All tools for the standard LIGO simulation worked, except that the aliasing effect seems to be more complicated that the normal FP cavity with well defined modes. For John's purpose, the uncertainty is small enough, but this is an interesting issue to be investigated in the future.

Modeler - e2e simulation engine (Hiro, Bruce, Melody)

---------------------------------------------------------------

Working to implement a new primitive, UserDefinePrimitive. This is an extension of FUNC_X, and allows a user to built a primitive with arbitrary inputs and outputs. Bruce is building the code by mirroring the code of FUNC_X with necessary modification. Melody is working on the modification of the shared library support routine so that UserDefinedPrimitive can be implemented with minimal deviation from the FUNC_X implementation.

Mechanical Simulation for advanced LIGO (Sany and SLU team)

-----------------------------------------------------------------------------------------

Andrew Kinchen reported on behalf of Sany who attended the PAC meeting at MIT to present his groups activity and work plan.

I ran simple models including the new mgas state space provided by V .Sannibale and V. Boschi, finding results equivalent to theirs. I have also begun the implementation of the mgas state space into a mgas and triple suspension feedback control loop, based on a previous inverted pendulum and triple suspension model. I have also continued my efforts in the construction of a rudimentary triple cavity model designed to determine the optimal feedback filter settings for an advanced mode cleaner.

Yesterday, 29 Nov, I spoke with the originators of the new mgas model, sharing my observations, and requesting port assignments details.

Future actions:

I. Finalization of the mgas triple suspension model, on the basis of specifications discussed yesterday.

II. Continuing development of the Advanced MC triple cavity in conjunction with J.Quave of S.L.U. who is working on a similar length sensing model.

ALFI : e2e front end (Melody)

-------------------------------------------------

Finished the graphical implemention for the new User Defined Primitive.

Seismic Isolation

From: Brian Lantz BLantz@stanford.edu

Agenda for the weekly SEI telecon
Friday, Nov 17, 2:00 pm Eastern, 1:00 pm Central, 11:00 am Pacific time

HAM Kickoff meeting summary
Kickoff meeting went well.

Preliminary Design Review
The PDR will at HPD in Boulder on Thursday Jan 4. It will be an all day meeting. Brian and Dennis plan to be in Boulder . We hope that Ken will be able to make it, also, otherwise he will join by phone.

The goal of the meeting is to sign off on a provisional approach. Between now and the PDR, HPD will do various trades, studies, and investigations. Not too deep but "several times around" the set of design issues. This should result in a formalization of what HPD proposed to design for LIGO, and an understanding of the what and why for a viable approach. This will not be a detailed design. This will include issues of the mass distribution and access.

Final Design Review
The first part of the FDR will be Monday, April 2. The second part of the FDR will be in the week on April 16-20.

For the first part:
This should be enough information about the design that the Stiff team can prepare a case which will allow the LIGO evaluation team to choose between approaches for the LIGO interim upgrade. It should include: solid model, and useful cross-sections, confidence that the system can be built, installation/ instrument access discussion, all relevant dimensions for performance analysis, bending modes, cost and schedule estimate for manufacturing. (Note, HPD needs to know how many will be built before they can say how long/ how expensive it will be). The manufacturing estimates are not binding; they are estimates. LIGO/ HPD will work together to generate a list of particular differences between this design and existing experience.

This review will not include dimensioned drawings or firm quotes on parts.

Brian (and others) will travel to HPD for this review.

The second part of the FDR will review the drawings, and make sure that we are ready to build.

The handoff of documentation, particularly detailed assembly instructions, may happen after the FDR.

Progress on the BSC
Capacitive sensors:
4 sensors for stage 1 are broken (we started with 7 = 6 + 1 spare)
2 are due back the week on Nov 20
2 will be back in 3 to 6 weeks
Rich will watch the supply voltages on startup/ shut down to see if spikes or drops are killing the sensors. Ben will be asked to try to get us 1 more spare for both the coarse and fine channels.

Geophones
We think that all the preamp boards for the GS13s and the L4C were damaged when the d-sub connectors were connected with the wrong number of vacuum feed-through pin reversals. The cables on the prototype are now correct. Rich and Brian O say that the lock on the GS13 is working, and that the GS13s are locked.

Brian O will send a new set of pre-amps to MIT, to replace all the broken ones.

After the complience measurements on stage 1 and stage 2 are done, the sensors will all be removed and the boards replaced.

The old boards need to be fixed.

We need a channel-checker to be sure this doesn't happen again. Ben has a conceptual design for this. time to build it. Brian O will coordinate with Ben on this.

Compliance Matrix
Rich has some preliminary measurements of the compliance matrix for stage 1. He will try to finalize these measurements today, and get the measurements for stage 2 in the week of Nov 20.

Stanford Progress
Feedforward
Matt has remeasured the stage 2 transfer functions for y and rx to correctly predict the stage 2 responce in the stage 1 basis (you need x, y, rx and ry for this). Using this information the feedforward supression of stage 2 x motion between 10 and 20 Hz still doesn't work.

Seismometer
Dan C has been working to re-calibrate the 4 temperature probes. The most recent set of data may be contaminated by a heat leak from the reference thermometer. A replacement reference has been found and the calibrations will be repeated.

We've started to build a pressure sensor, and are thinking about the best way to calibrate it.

Dan Clark is trying to get another 3-day run of the seismometer next week. Then we will take it apart to make some changes in the null point, add a mirror for the short interferometric readout. Dan DeBra reminds us to get enough data that we can measure changes in stiffness and bias points when we reassemble the device.

SPI
Parts for the optical sensor and the PZT drive are almost done. The PZT stack on the mirror has quite a bit of tilt when it translates. We think this is OK, but are suprised by the poor quality of the PZT stack. A new stack may be needed.

Ground Motion History
Shang has put together a nice history of the ground motion at the obseratories over the last 2 or 3 years (depending on which sensor you pick). The data can be seen in the SEI logbook, entry 731. He is working to create a report which will explain the methods and results. We see the motion at LLO is, if anything, smaller this year than last year.

From: Ben Abbott <abbott_b@ligo.caltech.edu>
Seismic:

HAM-SAS

All of the boards for the HAM-SAS electronics system have arrived, and are either stuffed, or being stuffed. There are some parts that are back-ordered, and should arrive shortly. Their front and back panels have arrived, and most of them are now in place on the boxes for the boards. The power supplies are installed in the boxes, and many of the boards are as well. I should have a good amount of hardware to bring with us next week to install in LASTI. Some of the other boards need some extensive testing, and will be shipped to LASTI in the coming weeks.

ISI

The new GS-13 boards have mounting holes that were spaced incorrectly. In the picture, it looked like they were on 1" centers, but they are actually supposed to be on 29/32" centers. The existing board has been modified by Joe Hanson, and I have changed the PCB to fix the problem. New boards will be ordered shortly.

From: Dennis Coyne <coyne@ligo.caltech.edu>
Subject: minutes HAM-SAS 22-Nov meeting

1) fabrication status


Dennis returned from his visit to G&M -- the cleaning and cleanroom facilities are very good -- the parts are all of high quality craftsmanship -- the clean assembly protocols/practices are good (comparable to LIGO's practices)
all 4 filters tuned at < 200 mHz with tuning screws & spring in parallel

Filter

Frequency [mHz]

Optimal Load [Kg]

Height [mm]

A

192

276.21

19.46

B

180

275.42

19.95

C

188

276.34

20.15

D

180

276.45

20.0


Preparing to attach 4 filters to base plate had failure of an eye bolt! -- void found at the root of the eye and caused failure at ~10% of rated load -- fortunately no one was seriously hurt and only a minor, localized dent to a part (drop was ~10cm) -- new eye bolts from a different manufacturer are being procured

Bolted bottom plate to the support weldment

Started mounting IPs to base

Going to bake all coils, except race track coils (which arrive tomorrow) -- washed in ultrasonic at 50C in alcohol -- will bake 200C overnight

Lifting carts are mostly disassembled -- parts will go into cleaning tomorrow

Stepper motors to be baked in the small oven -- PID controller has been installed

Vertical & horiz springs for 2 configurations have arrived -- receipt of some more springs (with slightly higher and lower stiffnesses) is pending, to deal with off-nominal spring stiffness if needed

Chiara will send an email to Ed and Dennis with a request for LIGO to cover some additional costs incurred at G&M (per discussions between Carlo, Chiara and Dennis on Monday)

2) LASTI test plan

Nothing new

Pending actions:
a) Dave O.: triple suspension to be installed on the HAM-SAS table initially, or after some testing of HAM-SAS by itself?
b) Dennis: prove that air bearings are not needed on the piers
c) Dennis & Dave: draft evaluation criteria for review by the group and to see if the test plan (and simulation plan?) are complete and timely for a decision in March

3) electronics

10 Modules are being stuffed in the Wilson house shop @CIT
Panels due in next week from panel express
Next week Rolf, Alex, Rich travel to LASTI to install CDS infrastructure for several projects including HAM-SAS
Week of 12/4 Jay and Ben travel to LASTI to install HAM-SAS specific electronics and continue where Rolf et. al. finished

Jay & Ben will discuss with Virginio what electronics/controls testing can be done at CIT to compliment tests being done in situ at LASTI

Next week (Wed 11/29 at the usual time, 8:00 am PT), Jay will go over an overview of the HAM-SAS controls. See the links to some HAM-SAS documents at the top of this page:
http://www.ligo.caltech.edu/%7Ejay/documents.htm

4) Simulation

Nothing new

Suspension

From: Janeen Romie <janeen@ligo-la.caltech.edu>

LIGO SEC Kinetic Art Project (aka Wave Wall)

Working with Ed Jasnow and Allen on the final Superior Steel invoice.
Wrote up procedure for locking the wave wall and put it on the LLO wiki.

Advanced LIGO

Working on actions from last Thursday's OMC meeting. Most of the SUS weekly last week centered on the OMC. Working with Carol, Florence , Jay, Rich and others on budget and fabrication account information. Working with Chris and Calum about detail design.

Provided to Justin a table of the count of hybrid and initial LIGO type osems for all suspensions. Worked with him to update his appendix. Updated the suspensions bonding matrix.

Phil Willems is here at LLO and I'm working with him on the design of the ring heater and it's interface to the ETM lower structure. Joe O'Dell provided helpful pdfs and a step file.

From: k mailand kmailand@ligo.caltech.edu

The CES shop is modifying the fixture rotator assembly rotating plate to match the arm, and the LASTI set up.

The final set up and machining of the arm is in progress at CES; all of the purchase parts for the LASTI 'conveyor'

tooling have been ordered. I have been working on the ESD mask , and with Navitar the coating company re.the tooling requirements for their process. I'm also running a cavity beam dump FEA, to see if additional bracing is required, algor has problems solving it, algor tech support can not determine the problem, and has sent me a cd with the latest v19.3 program version to try.

From: Chris Echols <cechols@ligo.caltech.edu>

Advanced LIGO Output Mode Cleaner

Mechanical design:

  • updated lower wire attachment buttons
  • added "tablecloth" osem coil holder and osems
  • updated intermediate mass assembly
  • added blade guard, added blade mounts to structure
  • updated structure design (.25" wall thickness on legs, 10cm increase in height overall, 2" wider)
  • Janeen will take over blade assemblies, while I have acquired "tablecloth" design

Drawings:

  • updated structure drawing

Other:

  • met with M. Gerfin to discuss cost and schedule--still on track to deliver structure mid-February

Advanced LIGO AOS

No update

Core Optics

From: Bill Kells kells@ligo.caltech.edu

From: GariLynn Billingsley <Billingsley_G@ligo.caltech.edu>

The Advanced LIGO polishing pathfinder request for proposal has been compiled and is ready to go to our vendors. We hope to have this accomplished by the end of the day December first. We are asking for responses by January 19 out of a realistic allowance for the Christmas holidays. We hope to have our review committee in place before the end of December so that we are ready to work quickly and place the desired contracts.

We now have a size for the compensation plate to be used in LASTI. I am gathering requirements in an attempt to expedite procurement of this piece in time for some testing at LASTI. I sincerely doubt that we will be able to make delivery by the time the noise prototype is installed.

The various core optics meetings have been condensed into one. Nominally Wednesday at 1pm pacific, unless we get another request to change the time. Please let GariLynn Billingsley know if you would like to be included in the meeting notice distribution and are not currently.

We have sent 1" coated and uncoated optics to CSIRO that have been measured on our scatter instrument. We will ask them to address the difference in microroughness between the two samples, then to evaporate a gold coating and repeat the measurements. The samples will then be measured again at Caltech, we hope to determine if the excess scatter seen at the observatories is due to the substrate or coating.

Auxiliary Optics

From: Michael Smith <smith@ligo.caltech.edu>

SLC

I refined the scattered light noise fringe-wrapping model by incorporating a Bessel function expansion to calculate the noise amplitude at the fringe-wrapping harmonics.

I finalized the concept for the errant beam baffles. Luke Williams is creating SW conceptual models of the baffles.

I developed a SW conceptual model for the suspended arm cavity baffle. The baffle will be suspended on the HR side of the ITM and ETM, similar to the elliptical baffle, either directly from the quad support frame or from the BSC optical table, with a positional reference to the quad structure. The baffle will be made of polished, oxidized stainless steel and the estimated weight is 4.5 kg. I will send the SW file to the SUS group for their help in mounting the baffle.

I developed a SW conceptual model for the parking beam dump, which provides a safe place to put the reflected beam when the PRM is intentionally misaligned to break the lock of the power recycling cavity.

I am in the process of writing the Conceptual Design and Requirements document for Stray Light Control.

Luke Williams is in the process of testing the oxidized stainless steel baffle material with a high power laser beam in vacuum, to determine the failure mode.

Control and Data Systems

From: Rolf Bork <rolf@ligo.caltech.edu>

- Primary work this week of the CDS group has been focused on the HAM SAS controls installation at MIT. Rich and Rolf are at MIT this week. The controls racks have been dropped into place and the controls computer, I/O chassis, and DC power distribution were installed. Jay and Ben have continued work on more SAS electronics chassis and will finish up installation, field cabling and system tests next week.

- Held a couple of class sessions with MIT staff and students on how to use the CDS Matlab code generator for new CDS systems at Lasti.


For additional information about this report, contact Albert Lazzarini or Phil Lindquist