Weekly
Report for Week Ending November 16, 2006
Past Weekly Reports
The LIGO Executive
Committee Agenda for Monday, November 20, 2006 will be:
(Meeting time: 10:30 am Pacific Time)
1.
Announcements
2.
Programmatic (Marx)
- Enhanced LIGO (Mike Zucker)
3.
Comments on weekly report
4. LSC
Issues (Saulson)
5. LIGO
Lab Operations
- Administration (Lindquist)
- Sites (Raab,
Zucker, Shoemaker)
- Commissioning (Fritschel)
- Optical and Mechanical (Coyne)
- Control and Data Systems (Bork)
- 40m (Weinstein)
- TNI (Libbrecht)
- LASTI (Ottaway)
- Lab computing ( Anderson )
- Science Group (Weinstein)
6. Enhancements
(Zucker)
7. Advanced
LIGO (Shoemaker)
8. Change
Control Board/Technical Review Board Session as needed
Site and other business issues:
Special Items:
Special
Announcements:
There will be no meeting
on 27 November (Fincance focus) due to people
traveling to the PAC meeting.
Weekly Report
Highlights
A meeting of the LSC Executive Committee was
held on Thurs 16 November. A new
version of the MOU with Virgo was discussed and approved for transmission to
Virgo, for meetings of the Virgo Steering Committee on 6 Dec and of the EGO
Council on 8 Dec. We are hopeful that we are converging on a final version,
which would then be submitted to the LSC Council (on our side) for final
approval.
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs
(Lloyd)
PROPERTY MANAGEMENT (Luna)
>
- Assisted LLO (A. Sibley) in requesting
disposition instructions for two GSA Vehicles.
- Provided data to Property Services to complete
the Federal Automotive Statistical Tool report requested by the NSF.
- Working in disposing one argon ion laser from
the 40M lab (S. Vass).
- Tagged and created Property records for one
Network Spectrum Analyzer (L. Cardenas CIT).
- Working in creating a Memorandum for the
donation of vacuum equipment (P. Willems) to Embry-Riddle Aeronautical University .
DOCUMENT CONTROL CENTER (Turner, Mak)
>From: Linda Turner -
turner@ligo.caltech.edu>
- Provided a schedule of remaining milestones
between now and deployment of the new document system. The key events for delivery,
review, and acceptance from both LIGO and FileHold
have been included. The
schedule takes into consideration the numerous holidays and vacations
planned during the coming weeks.
Worked up a proposed itinerary and schedule to provide training for
the sites and larger-group collaborators.
- Received first of two rebuilds from FileHold.
Preliminary testing of the fixed search engine was extremely
pleasing -- the return was instantaneous and the search build was not
slowed down for screen refreshes.
Both of these issues were of concern earlier and seem to have been
resolved. The second rebuild
is in process currently so all testing is again on hold until that has
been completed successfully.
- Finalized contract for catering of the LIGO
Christmas party, and RSVP's continue to come in for the party.
- With the return of shelves to my office, began
to do a bit of rearranging so that hopefully the floor will once again be
clear for foot traffic.
>From: Cleveland Mak
<mak_c@ligo.caltech.edu>
- Completed verifying, editing, transferring,
renaming all those scanned "T" category files that were
mentioned in my last report.
- In the course of processing another fairly large
DCN. Unlike that "Mega
DCN" that I had finally completed a couple of weeks ago, this one
appears to be problem free.
- Scanning Update - Progress continues on scanning of Travel
Expense Reports.
FINANCIAL SYSTEMS (Funaro,
Brambila, Kaufman)
>
1) For ACCOUNTS PAYABLE HISTORY Press Here.
>From: "Brambila,
Ruth" <Ruth.Brambila@caltech.edu>
- Completed change order #8 to Tyler for
FY2007.
- Transferred the funds on several orders to the
new fabrication accounts.
- Made the tax code correction on Galli and Morelli, as
requested.
- Completed the order for the housing rental and
coordinated the recurring payment.
- Working on completing additional information
requested for the auditors.
>From: Florence Kaufman <fkaufman>
- Looked into expenditures and encumbrances in the
LIGO.HSAS account per Dennis Coyne's request. As a result, discovered that
California Use Taxes totaling $10,666 had mistakenly been charged. These charges have now been
removed.
- Submitted an Intra Award Transfer to reclassify
expenditures for the pendulum wall that had mistakenly been charged to a
non fabrication account. This
resulted in a savings of Indirect Cost of $5,141 in the Outreach Award.
- Modifying monthly financial reports to include
the latest version of the FY07 budget, which provides a breakdown by
quarters. This will provide a comparison of actuals
to a time phased budget rather than the straight line budgets used previously.
- Financial reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone
<gsalone@ligo.caltech.edu>
>From: Ed Jasnow
<jasnow@ligo.caltech.edu>
- The kickoff meeting for the design of the HAM
single stage seismic isolation system for Advanced LIGO was held with HPD
on Wednesday, November 15.
- The contract with Galli
& Morelli for the HAM SAS is being reviewed
to determine the amount of additional funds required to complete delivery
of the system.
PROPOSALS and REPORTS (Lindquist)
Submitted the end of
October monthly report to the NSF. Next month we are going to be a bit more
formal in collecting data from a few key individuals.
CHANGE CONTROL/CONTINGENCY MANAGEMENT
(Lindquist)
- There are no open change requests.
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa
<cindy@ligo.caltech.edu>
- The next Staffing Committee meeting is scheduled
for Monday, December 11.
- A Staffing Committee meeting was held on Monday,
November 6. The minutes and
action items have been posted on the SC web page. All files for the Staffing
Committee are up-to-date and posted on the SC web page
- Prepared numerous
appointment and reappointment memos for various Visitors, Post Docs, or
Term Staff
Quality/Safety ( Tyler )
>From: Bill Tyler tyler@ligo.caltech.edu
Nothing significant to
report this week.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of S5 Activities at LIGO Hanford Observatory
(compiled by M. Landry)
Duty cycles on LHO machines were
impacted this week by many effects, including commissioning activities such as
the floating of the 4k antisymmetric port table
ISCT4, high microseism, high winds,
seemingly endless baling of tumbleweeds
delivered by high winds, and calibration studies. The result was lower
duty cycle on both machines, H1-61%, H2-57%.
Furthermore, bns ranges were reduced owing to
microseism and baling, ~10-14Mpc for H1 and 5-6.5Mpc on H2.
LHO has a new local run coordinator
in Greg Mendell, following on the meticulous efforts
of Keita Kawabe.
Some S5/commissioning highlights
from the LHO elog are bulleted below:
- summaries: range
& duty cycle weekly, Tuesday maintenance
summary, IFO maintenance
- floating the ISCT4 table reduced
displacement noise by more than a factor of 10 at 40Hz and
100Hz. The RMS velocity of the table is the same as before, as
expected given this had already been reduced with the previous use of
damped tripod table legs. The table is behaving despite the 50mph
winds observed on the weekend
- the raid upgrade on hanford1 did
not take and had to be repeated on the following
day
- in order to produce a final V3 calibration for the
first calendar year of S5, we need a last set of fiducial
measurements to assess the latest epoch. We're trying to understand
why some of the actuation
calibrations don't look as nice as earlier in the run. This may
require new compensation filters.
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Giaime)
S5 Run Report (Igor Yakushin)
Still high microseismic
noise and low range of about 11 Mpc most of the week.
The duty cycle for a week was 54 percent.
On Tuesday calibration
measurements were made by Brian, Gaby and others.
Also Evan and Brian made photon
calibrator measurements and in the process found and fixed problems
with channel hopping and photon calibrator excitation channel.
Yesterday fb1
had trouble writing frames. The problem was tracked down to a cluster user
reading too much raw data from /frames. The user was advised to use L1 frames
from /archive instead and /frames was removed from LDAS mount point to prevent createRDS and LSCdataFind using
it.
CDS Computing (Lisa Bogue)
- Worked
with ldas to resolve a problem with the filesystems not writing out quickly enough. This was
crashing the primary framebuilder. The backup
was unaffected.
- Working
on purchasing a vmetro pcm
bus analyzer.
- Continuing
work on ldap.
- Worked
with Gaby regarding some questions about code used in creating the calibrations.
- Did
troubleshooting on a network problem on my GC machine. I would randomly
lose my network connection for about 45 minutes. I believe I chased this
down to an IPv6 ICMP issue.
- Working
with CDW to RMA the monitors in the control room that are showing
"water spots."
Safety/Security (Rich Riesen)
Found no site nor
laser safety concerns this reporting period. I was very satisfied with my walk
thru of the SEC before the grand opening concerning safety items I had
identified early. My suggestions and recommendations were addressed in a very profesional manner and I would like to thank all who were
involved.
General Computing
(Dwayne Giardina)
( Shannon
Roddy)
LDAS maintenance (Dwayne Giardina)
LLO Outreach (John Thacker)
Held highly successful
LIGO SEC Opening Event on Monday, Nov 13th. [JG:
this is an understatement; the effort and dedication by the entire staff and LIGO Science
Education Center
collaborators resulted in a facility and opening event that our many visitors
won't soon
forget.]
Held Exhibit Training for new exhibits on
Nov 14th.... about 20 faculty and teachers attended. Conducted outreach for two High School
Physics classes (48 students) on Nov 16th.
Prepared programs for Nov
17th (5th grade) and Nov. 18th (SUBR Project MISE teacher Professional
Development).
Mechanical and Optical Systems (Coyne)
See Advanced
LIGO
Controls and Data Systems (Bork)
Jay finished review of the successful
testing of the revised LOS Bias Module. 10 units of the revised design will be
manufactured for distribution to the
sites.
See also Advanced
LIGO
40-Meter Interferometer (Weinstein)
Lots of good progress this week, on tuning
the PSL, MZ, and mode cleaner; lock acquisition of the dual-recycled Fabry-Perot michelson;
commissioning of the DC readout servos; and vacuum squeezing.
DC Detection
- Rob revamped the front end controls and the MEDM
screens for the DC readout system. He then deleted the old OMC channels
from the conlog database and the DAQ, and added
the new ones; and added an autoBurt.req file.
- Rob digitally locked the OMC length with a ugf of 200Hz and a dither
frequency of 12kHz. He then dithered a tip-tilt PZT at 9kHz
in pitch and 10kHz in yaw, saw reasonable error signals, implemented a
servo filter, and locked the two degrees of freedom. He easily got a UGF
of 80 Hz. The other tip-tilt PZT will come next.
- Rob got a camera onto the OMC transmitted beam
(it looks nice and round) and a thorlabs PD onto
the OMC reflected beam and thence into the digital control system.
Vacuum squeezing
- After several weeks of optimization work, Eugeniy, Shally, and Go
observed about 4.5 dB of squeezing and about 8.0 dB of anti-squeezing 900kHz before subtracting the electronic noise, and 6
dB after subtracting electronic noise. They also noise-locked the homodyne
angle while locking the OPO cavity manually.
- Go and Eugeniy tried
without success to use two different auxiliary lasers to generate a 610MHz
subcarrier subcarrier
to be used for locking the OPO cavity. They are now turning to an AOM to generate
it from the main beam.
IFO Commissioning, Electronics, Controls, Computers
- After all the good work on the PSL / MZ / MC
(described below), Bram, Kirk, Rana, and Sam
locked up the IFO (with the arms at half-resonance) with no problems.
Handoff to the double-demod signals and DARM-RF
was no problem. They swept the MICH,
PRC, SRC and CARM loops and optimized the gains. They successfully handed
off CARM from driving the differential ETMs to
driving the MC_L path. Next step is to get the common mode servo working
well and then start reducing the CARM offset to get back to full RSE.
- Kirk, Rana, and Sam
are configuring the common mode servo board to match the topology employed
at the sites. The input comes from POY_33_I, a digitized slow output goes
to MC_L, and an analog fast output drives the mode cleaner "additive
offset" for the frequency stabilization loop. They used this to lock
the y arm. They also implemented a servo script to offload MC_F values to
the ETMs to keep the VCO from railing.
- Kirk and Rana found
that the PSL FSS beam was only singly passed through the AOM instead of
double-passed, so they realigned the entire FSS/RefCav/AOM
path on the PSL table. This recovered a bunch of phase in the MCF servo
path, allowing them to increase the MC servo UGF to 50 kHz.
- Rana, Sam, Rob and Kirk reworked the Mach Zehnder servo board, allowing them to increase the
gain at DC by a factor 100.
- Bram replaced the ETMX oplev
diode laser with a HeNe laser and reduced the
number of bounces, as he did with ETMY before. He had to flip the sign of
the servo gain to get it to work.
- Steve designed the optical mounting hardware for
our new oplev He/Ne
lasers. This is an effort to reduce cost and improve performance with
optical levels. It will be ready in three weeks.
- Royal modified and re-installed the whitening
board on the ETMX to give it the same analog and digital filters that she
added to the ETMY, which significantly reduced the noise. She also
modified the digital filters by adding two new dewhitening
filters for each quadrant to deamplify the
signal.
- Rana wrote and employed scripts to optimize the the demod phase for POX and
POY with single arm lock. The optimized phases were very different from
what was there before!
- Rana turned off the MC2 oplev
and guided the beam transmitted through MC2 into the old MC2 oplev QPD.
- Rana locked the DRMI using single-demod REFL RF signals, then
tuned the double-demod phases. Now the handoff
from single-demod to double-demod
is smooth.
- Rana and Kirk locked the michelson and took a calibrated spectrum. The
noise is huge.
- Rana found evidence of excess noise in the OSEMs of several suspensions, probably electronic. To
be investigated.
- Kirk and Sam measured and tweaked the PSL/IOO
servos, increasing their UGFs to 580 kHz for the
FSS and 65 kHz for the MC. The crossover frequency from MCL to MCF is now
at 85 Hz. These servos are now working very well.
- Steve reinstalled beam tube guards on the PSL
table so that they do not clip the ISS pickoff.
- Steve noticed low beam centering on the second
mode matching lens into the MC. He and Rana
rebuilt the mount and the centering is good now. The pointing is recovered, however the MCT power went down a little
bit. This needs more fine tuning. The psl_pos_qpd
was set up again as preparation for this work. The psl_ang_qpd
does not work. The 35.5MHz EOM is glowing more than it should, requiring
better alignment.
- After this, Rob, Kirk, and Bram recentered the MCR beam on the WFSs
and the MC locked happily.
IFO Modeling
- Rana and Kirk assembled a Bench calculation of the expected
noise spectrum from the 40m PR-FPMI. They found and fixed a problem in the
calculation of the radiation pressure noise.
Lab Infrastructure, Bake Lab
- Steve noted that the leybold-secu
valve must have cracked o-ring seal (it is 30y old); Bob will take apart
and fix it.
- MIT's Spectra Physics argon ion laser was handed
over to Rod Luna. Model 2080-25S & 2580C, SN 298&629. D. Shoemaker
wanted the MIT property tag but Steve couldn't find it.
- Bob will tend to the
care and feeding of the 40m lab while Steve is on vacation for three
weeks.
Thermal Noise
Interferometer (Black)
Nothing significant to
report this week.
LASTI (Ottaway)
CIT
Science Group (Weinstein)
Kent Blackburn
TCLGLOBUS
Added Globus
assert to check for XIO operation index value whenever it gets modified. This
effort would be useful for solving LDAS managerAPI
core dumps.
OSG
Testing nano HIPE workflow with Pegasus job clustering feature. We need
to move "seqexec" executable binary to $APP
in order to use this feature at the remote execution site. The one installed
(from OSG 0.4.1 software stack) is fairly old and doesn't work. I've completed running nano HIPE at OSG_LIGO_PSU and it's
still running partition 2 at UCSD.
Current status of running HIPE with 24
partitions at 2 more OSG production sites:
STAR_BNL:
still running partition 2
FNAL_GPFARM:
still running partition 4
Had technical discussion with Kent
Blackburn, Stuart Anderson and David Meyers on adding LDG support into LIGO
Workflow planner. This is to
support running Condor jobs on LDG cluster through the planner.
OSG INTEGRATION TESTBED
Debugged segexec -
Pegasus executable required for clustering Pegasus DAG nodes.
Added voms proxy
support to osg-vtb.
Discovered problem
installing latest ITB client package from ITB cache on fc4. Created a trouble ticket at the
OSG GOC.
FERMILAB VISIT
On Friday of last week,
met with the WAN network group at Fermilab. Discussed the LIGO WAN and out increased involvement
with OSG sites and the need to efficiently move data from LDG onto OSG. Also heard about efforts underway at Fermilab
to provide WAN moniotoring. These are both
areas in common with both groups.
OSG RESOURCES MANAGER
Continued to work with the
statements of work for the 18 separate institutions involved in OSG.
Continued organizational
effort for OSG Executive Board meetings to be held at Caltech in December.
Met with Julie to provide
signature on Caltech DAF so that my name can appear on the Caltech SOW,
allowing the SRO to approve so that funds can flow. Still need PMA, Vice Provost and SRO officer
signatures before sending to UW Madision's Contracts
Office.
Data Analysis
_______________________
Vuk Mandic
I prepared a new draft of the S4 isotropic
stochastic paper, in response to the suggestions of the ApJ
referees. The new draft has been approved by the stochastic review committee
and by the stochastic group, except for a few minor modifications. The paper
should be resubmitted to ApJ next week.
I worked with Nick Fotopoulos and Joe Romano
on formulating veto parameters, based on PEM-coherence studies and on
time-shift studies, to be used in the H1H2 isotropic analysis.
I have restarted the pulsar hardware
injections on all interferometers.
I participated in the review of the Output
Mode Cleaner suspension design.
_______________________
Duncan Brown
- Working with Kip to complete LIGO-IMRI paper -
Looking at problems with constraint damping in numerical relativity
simulations
- Worked with Lisa to track down coincidence
problems in the S4 ringdown search
- Helped Igor track down a problem with segment
database replication - Updated glue install script as requested by DASWG
_______________________
Eirini Messaritaki
- Kept working on the S5 BBH search, rerunning the
stages of the search affected by the recent bug in the coincidence code,
and doing some sanity checks for the results.
- Worked with Vibha on
the issue of detection of spinning BBH waveforms with non-spinning
templates.
_______________________
Gregory Mendell
I am continuing to work with the pulsar
group on plans for the SFTs needed for the next stage
of the S5 Einstein@Home search. We may regenerate the
SFTs using the new S5 calibration due out soon. As I
said last week, I hope to start some coding tasks for the Einstein@Home
search this week. I have also been discussing with Pinkesh
Patel the distributed demodulated FFT algorithm he is working on, and which
looks promising to me.
_______________________
John Zweizig
This week I have been working on scanning L3
RDS frames for dataValid errors in the DARM_ERR
channel. When these occur during science mode it indicates that the a data acquisution error
occurred that could make the GW channel unreliable. In fact the glitch group
has noted loud glitches caused by these errors. I previously performed a
preliminary scan on LLO data and found several segments to within 256s (i.e.
within a L3 frame). I am now iterating this with a new program that uses the auxillary information within the frames to limit the times
to within a 62.5ms slice.
This has been performed on all IFOS over the
first year of S5 operation and will be published as data quality flags as soon
as possible after the lists are finalized.
_______________________
Rejean Dupuis
- Generated spectrograms for last month of data
for H1, H2, and L1.
- Also produced spectrograms for S5 data that E@H
intends to analyze in next run.
(www.ligo.caltech.edu/~rejean/S5/spectrograms)
Laboratory
Computing (Anderson)
LDAS Software Systems (Maros)
The version of the Sun Studio 11 compiler
suite was upgraded to the latest development version. This has not resolved any
of the outstanding issues with building LDAS for the Sun Opteron
platform. A new approach of building a minimal datacondAPI
has been adopted. With this approach it should be easier to resolve the
outstanding issues.
The cmonClient has
been modified to default to port 10000 when adding a new site. This is also the
port number given in the context sensitive help message for the form. Also removed deleted sites from list of sites immediately upon
deletion.
The cntlmonAPI now
traps out exceptions when loading tclglobus and
writes the error to the log files.
Tcl debugging information used to debug tcl 8.4 has been removed from the frameAPI.
The managerAPI has
been modified to have resource variables from the globus
location and LD_PRELOAD_64. Also, if tclglobus cannot
be loaded, the error is caught and written to the log files.
The runLDAS script
has been modified to read the additional managerAPI
resource variables for LD_PRELOAD_64 and the globus
library path.
System testing of LDAS was done using
version 1.8.369 of the software. All system tests passed successfully.
Modified the putStandAlone test to not remove ilwds
which were still needed. This was
first an issue on the linuxopteron box.
Efforts are underway to consolidate all of
the tests scripts used for system testing into a single directory hierarchy.
Once this is done, it will be put under CVS and be part of the standard build
of the LDAS software.
LDASJobH has been modified to conditionally load tclglobus. The SeqInsert program
on linuxopteron has been extended to support globus options for LJrun.
The createRDS
system tests are being run each night on sunopteron.
The standard LDAS loop scripts are running
nightly on ldasopteron.
LDAS System Administration (Anderson)
Caltech
(Phil Ehrens)
- Worked with Albert Lazzarini,
Dorothy Lloyd, and Linda Turner on MOU CGI interface. Wrote wiki-stylesheet.css for use on this project (though it
is generally useful for UseMod based wiki's.
- Replaced power supply in former llo-kickstart machine. Machine is now functional.
- Wrote DOE certificate locating and status
checking script and tested it against a number of machines. Found that
many hundreds of expired and unused certificates exist on our machines.
- Supported Igor Yakushin
in the maintenance of ldbd certificate based Websphere applications.
- Ongoing work migrating
the sgwb cvs
repository to a secure service.
- Began configuration of machine to be used as log_mon server.
(Erik Espinoza)
- Helped upgrade Condor at LHO/LLO including
starting E@H.
- Assisted Larry w/ GC Mail Scanning Server.
- Filed Condor problem report for DedicatedScheduler schedd
crash (condor-support #1739).
- Fixed issue w/ GSI OpenSSH
4.2 in new LDG.
- Configured and tested NFSv4 w/
node329/node500/dataserver-cit.
- Assisted Dan in tracking down bottleneck on
frames @ LLO.
- Renewed my cert.
- Notified user of quick terminating jobs.
- Contacted ASA for mobo/cpu
replacement.
- Notified ASA that mobo
replacement did not include brackets necessary for installation.
MIT
(Fred Donovan)
- node37 is down, confirmed mainboard
bad.
- Continued smartd
install on nodes.
- Compute nodes - no email ability (fixed for
node1 - testing) - needed for alerts.
- Heat/cooling is now stable, as 1/2 nodes off
condor.
Livingston
(Igor Yakushin)
- The segment database replication between sites
was broken for some time due to expired ssl
queue certificates. After the expired ssl
certificates were regenerated, the replication started running again.
Thanks to Duncan
for helping to diagnose this problem.
- fb1 had trouble writing to /frames yesterday. The
problem was tracked down to a cluster user overloading /frames by reading
huge amount of raw data from there. The user was advised to use L1 frames
from /archive instead. /frames was removed from
LDAS mount point so that createRDS jobs and LSCdataFind would use /archive.
- Replaced flaky disk 1 in dataserver.
This disk was responsible for mirror failure during the last power outage.
- Prepared the first version of "Proposed
changes to version handling in the segment database" document.
- Reconfigured LDAS 3511s and 3510 to disable the
auto global spare option that could lead to a data loss due to a firmware
bug. fb0's 3511s also need this configuration change
which require no downtime. 6) Opened a case (#65234696) with SUN
for the failed tape drive 2.
(Dwayne Giardina)
- Ejected tapes for shipment to CIT,
imported and labeled replacements.
- Tuesday's maintenance included condor, ldg, openssh,
httpd, and kernel upgrades. ldg upgrade was then backed out due to errors
discovered in testing.
- 8 nodes mysteriously rebooted after the upgrade,
and another power strip required reset.
- Our cluster is now running Einstein@Home
as backfill jobs.
- fb1 had issues writing to /frames filesystem yesterday. frame
files produced around the times in question passed FrCheck.
Hanford
(Greg Mendell)
- Beyond routine tasks to keep LDAS services
running, my main sys admin activity for the past week was testing the
install of the LSC Data Grid, version 4.3, and testing addition frame
compression options for use during RDS generation.
(Ben Johnson)
- Set up new workstation. So far it is leaps and
bounds faster than the old laptop. I have yet to try any Xen virtualization.
- Tuesday maintenance: Condor -> 6.8.2, SAM-FS
-> 4.5.33, E@H -> nodes.
- Peter Shawhan pointed
out an improper segment number in the segment database. This was due to my
FrSegmentFetcher code not being able to handle
the EPICS channels-are-grabbed-asyncronously
race condition. I have thought of the work-around, but have not coded it
up yet.
- The level 1 RDS -> nodes spray has been
stalled due to a couple of nodes' /usr1 filling up. I will take them out
of the spray map file and restart the process.
General Computing (Wallace)
MIT
(Fred)
- dovecot server on-line for testing, seems ok
- printer relocating, mail filter coding,
- travel web page cgi/html
coding,
- LASTI computers - with PS speced
out and quoted 2 stations emphasis floating point Livingston:
(Dwayne)
- Helped a user migrate from old desktop PC to new
laptop; additional software installs and configurations
- More SEC building setup/cleanup; removal of PCs
and projectors used for opening ceremonies is on my to-do list
- Printer installs on user PCs
- Setup trend graphs and reports for the SEC
building air handlers.
- Our GC backup system has been flaking out. We
decided to install a new 12TB raid disk array to work with recycled server
hardware running Solaris 10 and an upgrade to the latest arkeia software. We will be doing disk-to-disk-to-tape
backups. I am currently in the process of installing this.
- Continued training our spam filter
(Shannon)
- Finally successfully have the BGP session going
with LSU. The new subnet is now multi-homed. Time to seriously get a plan
together for moving certain machines.
- Working with Dwayne on the backup server
update/upgrade.
- Helped Rusyl move
outlook data to his new laptop.
- Planning transition of several machines to the
new subnet.
- Still looking into odd behavior on the router.
- Looking into pricing on updated Foundry core
switch. Will take some significant budgetary planning but may be necessary
for tying in the SEC building and some of the network changes taking
place.
Hanford
(Christine)
- The PO for the
new Cisco switch/router has gone out. The equipment should be delivered in
three weeks.
- PNNL is planning a network outage over the
Thanksgiving weekend. LHO primary network will be down Friday 11/24 all
day. I am working with ESnet to move over to the
backup network during this time.
- Still setting up new servers.
- Several users have had problems with badly
formatted spam email causing their mail tool software to freeze or to be
unable to finish processing their mail from the server. Using Pine or vi to delete the offending spam mail fixed the problem.
CIT
(Mike)
- Setup up VRVS in large conference room over in Millikan. This software is updated on the win 2000
partition only. The camera had some mechanical problems we were able to
fix this issue. I have also tested this software with Larry &
Christian using the café virtual testing room. We still have some
audio issues to work out.
- Testing SoldWorks PDMWorks server upgrade. I finished up testing on
upgrading from 2005 to 2007. It looks like this upgrade should run smooth.
I also loaded Solid Works 2007 too test connectivity to a 2007 test vault
using multiple logins making sure all security permissions came across
during the upgrade. The interface is much different in comparison to 2005.
- Worked on Access Points trouble shot a script
that stopped working. After adding additional users to our mac address filtering list the access points locked up
and would not reboot. I had to make some changes to the script we use to
get the access points working again.
- Took care of some networking issues over in
Wilson House, this was due to a power glitch.
- Other additional user support and daily sysadmin tasks.
(Christian)
- Created a backup of Ed Jasnow
and Gina Salone workstation.
- Computer move- Gina Salone
and Florence Kaufman switch offices.
- Minor tweaks on the unit in the display case.
- Called Dell support to have LCD screen replaced
on a loaner laptop.
- Re-imaged laptops that were returned to the
loaner pull this week.
- Configured SVRS on Mac OS X.
- Mike Larry and I relocated tape backup cabinet
to the synchrotron server room.
- Worked on the Spam Filters with Mike and Larry
- Other misc.: Continued onsite software/phone
support.
(Bruce Sears)
- iLog Maintenance: (0.5 days)
General iLog maintenance (user adds, keyword adds, systems
work, etc.)
(Larry)
- Worked a number of procurement issues. Ordered
another license of SolidWorks for the
engineering group. Tracked
down invoices and charges on a number of items, finishing up reconciliation
on the P-card.
- Worked with different people and assisted PMA on
the room/lab modifications that are taking place. So far most of the work
has dealt with the rooms in the sub-basement. Along the same lines we worked a
couple of office moves, mostly computer equipment. Assisted Christian and Mike in
moving the tape cabinet over to the LDAS cluster room.
- Spent time working different cabling issues in
the computer rooms. The kvm switch cables and a
number of the network connections needed to be reseated. Discovered some
issues with one of the kvm switched and will be
ordering new cables to take care of the problem with the converts for the
switch.
- Reworking Bruce Sears
machine so he will be able to use it from home. It is just about complete,
he should be able to take it today and start testing it out.
- The usual assistance to the users. However, one
printer problem on a SUN box I've still not resolved. I did get a
workaround for the user to where he can print the items he needs but why
those specific documents would not print normally is still a issue.
- Working on a couple of different items
concerning the mail services. Worked with Eric in getting up a new filter
server to test. We went through a number of issues but it is up and
running and testing has started. Building a new mail server machine for
the users to use. There are still some configurations that need to be
changed but it should be ready in a couple of days to start testing. Modified the existing mail servers
to help keep the spam filters from getting too clogged up with all the new
spam they are being hit with. We
are blocking well over 10K messages a day of spam and recently over 2K/day
of messages containing viruses.
- Worked with Mike and Christian on VRVS setup and
testing. Still some issues to workout.
- Spending more time on working out Apple related
issues/items. Work related to the apple machines will probably continue to
grow.
- Working disk space
issues. This will become a non-issue when the new drive farms are
installed. No date as of yet to when they will ship.
Advanced LIGO and
Supporting R&D (Shoemaker)
Advanced LIGO Systems
Modeling and Simulation (Hiro Yamamoto)
(Bruce Sears for Hiro Yamamoto)
-----------------------------------------------------------
AdvLIGO LSC/ASC design using FP arm model with quad
suspension (Osamu Miyakawa)
------------------------------------------------------------------------------------------------------------------
No E2E work
this week.
Fast simulation of Dual Recycled Michelson
Cavity (Keiko Kokeyama)
--------------------------------------------------------------------------------------------
The iteration number N(*)
is being validated. In static cases or some cases when the mirror has a
constant velocity, N~10000 is ok. In other cases that mirror tilt angle
oscillates (tilt angle=sin(wt)), N can be only 50. In
such cases, there must be some reasons that the approximation is broken. We
will unveil what term(s) in the expression breaks the approximation so that e2e
can stop using the approximation code when this expression is applied to e2e.
In parallel, we are investigating how tilt angles and mirror velocities affect
the result analytically.
(*)This number determines the time of the
next calculation point. For example, the code compute the field at the time
t=0, t= 2 N tau, t=4 N tau...
tau is an original time step which is determined by a
cavity length.
Modeler (Bruce Sears, Melody Araya)
---------------------------------------
Bruce - I/O interface implementation for
user defined primitives completed.
Now working on the merging FUNC_X code into UserDefinedPrimitive in order to have the modeler dynamically create the code and instantiate these
objects as needed, in the same manner as they are for FUNC_X
objects. (In fact, when completed, FUNC_X will be subclassed
from the more general UserDefinedPrimitive
class. (4.5 days)
Melody - Reacquainting myself with the
FUNC_X code to help with UserDefinedPrimitive
implementation. (1.0 day)
Mechanical Simulation for advanced LIGO (Sany Yoshida and SLU team)
-----------------------------------------------------------------------------------------
We continued modeling the AdvLIGO Input MC triple pendulum placed on HAM-SAS. Andrew and Jameson started to work on the
Input MC?s length
sensing control. At this point, they are learning the basics about length sensing control using the triple pendulum e2e
code we built. We still need to improve local
damping filter for the yaw degree of freedom.
We received a revised state-space matrix of
the HAM-SAS vertical model from Valerio Boschi. We confirmed that
this model is stable. Further analyses such as
comparisons of transfer functions from the base to optical table etc with
Valerio?s results, investigation on back
reaction from the triple pendulum to the HAM-SAS for the vertical degrees
of freedom (vertical translational, pitch and roll DOF) are under way.
ALFI : e2e front end (Bruce, Melody)
-------------------------------------------------
Bruce - No
work on Alfi this week.
Melody -Finishing up in the graphical implemention for the new User Defined Primitive.
Graphical icons can now be assigned to the UDPs.
(4.0 days)
Seismic
Isolation
No
report this week.
Suspension
From: Janeen Romie
<janeen@ligo-la.caltech.edu>
*LIGO SEC
Kinetic Art Project*
Finishing
up some invoice questions.
Advanced
LIGO
Preparing
for an internal SUS/ISC review of the OMC suspension for enhanced/advanced LIGO
tomorrow.
Participated
in an ear/prism bonding jig meeting today with Ian Wilmut
and Glasgow folks.
From: k mailand
kmailand@ligo.caltech.edu
The CES
shop is modifying the fixture rotator assembly X-axis plate to match the arm,
and the LASTI set up.
I have made
drawings for Mike Smith showing the SOS with a faraday isolator, and the cone
baffle with the new beam
locations, I'm also running a cavity beam
dump FEA, to see if additional bracing is required.
ALUK
held its latest Project Management Committee on 10th November 2006
(See LIGO-M060318-00-K). A brief
activity summary follows:
RAL: Currently focussed on getting parts
drawn and built for the noise prototype. All the contracts have been placed for
the noise prototype parts following DCN process and it was still planned to
complete the dirty assembly by the end of January. Sample welds are expected
shortly from the manufacturer of the structure. The long lead items for the
laser welding machine are on order. BS initial assembly procedure drafted and
design proposals now ready to be presented to the SUS community.
Glasgow :
Plans for CAC’s succession as follows. Dianne Masson will take over
financial control and reporting. RAJ will take over chasing manufacture of
optic components and the mechanical design aspects of the laser welding machine.
MB will take over the control/science aspects of the laser machine. KAS will
oversee and take steps to plug any gaps that appear. The new water chiller for the laser is delivered and the power
stabilisation issues are now understood.
Birmingham :
OSEM parts being made (problems with flexi-rigid circuit being ironed out) and
DCN awaiting approval; satellite box (PD signal amplifier) nearing completion.
Coil amplifier design work started. Contractors identified for satellite box
mass-production.
Overall: still aiming to have the noise
prototype at LASTI in early March.
Core Optics
From: Bill Kells
<kells@ligo.caltech.edu>
Last
week I was ensconced in the "Optics summit" meetings which were truly
a watershead status summary of outstanding issues (see
Ottoway's compilation to which I contributed).
This
week was involved in follow up issues to last week's meeting. For me
outstanding issues to pursue have been:
1.
(After intense discussions and even initial calculations with Vyatchanin) I have been developing a numerical code which
invokes his latest analytical description of PI for fully rcycled
interferometers. This I can (and have ) compared to my
own previous code (see T060159). Although we discussed enough to appreciate
that we agree on matters of principle and concept, our numerical results
significantly disagree. We parted ageeing to look
into this in detail and resolve.
2.
Last week the summary of more refined "as built" FFT simulations of Hiro Y. plus reiteration that the H1 recycling
gain appears "now" to be quite high (~55) combined
to make it appear that per HR TM scatter loss was not
so bad as I had previously
(c. '02-'03) been concluding (ie
perhaps only 15-25 ppm vs
my old 60-80ppm).
However just this week Rana tells me that he has
established that the H1 Rgain
of 55 is mileading. The
calibration has been off for some time. The gain is
more like 46-48).
3.
Therefore I have been reviewing the direct, scatterometer
determinations of scatter loss.
How good are the measurements? How big is the discrepancy with "As
built" FFT?
Factoring into this are the (all too quick) scatteometer
meausrements I made in 2/06.
These nominally showed a ~50% drop in HR loss compared to scatter measured on
the
same TMs in '03 ! Many possible systematic problems !
Input Optics
From: Dave Reitze <reitze@phys.ufl.edu>
Mechanical
Design (Luke Williams)
- finished the IO component
layout on the PSL table for the PDR
- working on second draft of the AdvLIGO cavity length document
- working on in-vac layout
MMT (Muzammil Arain)
- IO mode matching strategy is
being refined for adaptive control (aMMT). The
extent of interaction between TCS and IO is being investigated. Proposed
TCS dedicated sensors will be used as a diagnostic tool to determine mode
mismatch. Required adaptive heating at MMT2 and MMT3 for adaptive mode
matching control has been evaluated. Optical layout for both stable and
marginally stable recycling cavity has been finalized for the PDR.
- Revising draft of MMT section
for the PDD
Modulators
(Wan Wu, Volker Quetschke)
- Continue phase meter
measurement on the beat signals between two phase locked lasers. We have
seen clear correlation between the phase noise of the function generator
and the modulation index phase noise. Investigation on the source of the
modulation index amplitude noise continues.
- The MZ modulation experiment is
mostly finished at the level of the PDR, including DL displacement noise
characterization, amplitude modulation. Documentation for the PDR is
almost complete.
Faraday
Isolator (Luke Williams, Dave Reitze)
- Federal Express managed to
loose the magnet ring that was being shipped to Caltech for vacuum
testing. Another set of magnets is being assembled and sent from IAP
to Caltech.
Auxilliary Optics
SLC
I developed
a method for calculating the scattered light noise due to large motions of a
surface that causes fringe wrapping.
I am in the
process of determining the effect of fringe wrapping. Preliminary results
indicate that fringe wrapping is not a problem; however, in looking at this
possible problem, it appears that scattered light noise from the AS beam off
the Brewster's window between HAM 5 and HAM 6 may be problematic because of the
horizontal motion of the HAM chamber ( especially if it has a resonance between
10 to 30 Hz). In a similar vein, the motion of the cavity beam dump attached to
the BSC chamber walls may be problematic because of horizontal motion. I am
waiting for some data from Robert Schofield regarding the motion of the HAM and
BSC chambers at LHO.
From: Chris Echols
<cechols@ligo.caltech.edu>
Advanced
LIGO R&D (AOS optomechanical):
Analyzed Brewster Window Plate for natural frequencies
Analyzed Brewster Window Plate for vibration response
spectrum (in progress)
Analyzed HAM Chamber for natural frequencies
Illustrated new pick-off mirror suspension concept in SolidWorks
Pre-Stabilized Laser
From:
Peter King <pking@ligo.caltech.edu>
A telecon was held with Benno, Maik, Rick and myself to discuss
the requirements for the laser diode enclosure. It is intended that this
room be placed in the mechanical area.
Benno, Maik and I started developing a laser safety plan for the
200-W laser. We have a number of ideas that I have to combine with the
material outlined in the ANSI standard.
Basti Schulz has
completed the package design for the amplifier module. It is a nice
compact design that mounts to the optical table via mounting forks. The
particular unit I saw was to be delivered to Virgo. Some pictures are
available on request.
A
reference cavity identical to that used at the sites was suspended and placed
into a vacuum chamber at the AEI. The plan is to use the reference cavity
to develop the frequency stabilisation. A
current edition table-top frequency servo from LHO arrived at the AEI whilst I
was there and this unit will be fired up and tested out on either a 2-W Innolight NPRO or an 800-mW model.
Control and Data Systems
From: Rolf Bork
<rolf@ligo.caltech.edu>
- Mohana is working on thermal management and packaging
for the ISI Coil Driver. The prototype metal work has been submitted
to the sheet metal house, and they will build a prototype within the next
two weeks. In the meantime,
the PCBs and other items will be finalized in order to finish a prototype.
- (Mohana) Received
Satellite Amplifier boards from the stuffing house. Testing will
begin soon.
- (Jay) Sent 3 Anti-Aliasing chassis to the
outside testing facility for electrical test and subsequent shipment to
MIT.
- (Rich) Did measurements on ASC diodes as a
continuation of the down select process. One of the InGaAs diodes has been illuminated up to ~50mA without
obvious damage.
- (Rich) Laying out test boards for RFPD topology
comparisons.
- (Rich) Working on DC readout components for LIGO
upgrade. Trying to get together a plan for in vacuum electronics and
cables.
- Received I/O chassis and computer for HAM-SAS
controls at Lasti. Installation of HAM-SAS controls at Lasti scheduled to begin Nov. 28.
- (Rolf) Starting to
work out controls interface with Enhanced Ligo PSL,
in particular the interface to the PLC being provided by LHZ.
For
additional information about this report, contact Albert Lazzarini
or Phil Lindquist