Weekly Report for
Week Ending September 21, 2006
Past Weekly Reports
The LIGO Executive
Committee Agenda for Monday, September 25, 2006
will be:
(Meeting time: 10:30 am Pacific Time)
1. Announcements
2. Programmatic
(Marx)
- Preparation for the
NSF Annual Review
- Budget
discussion---Advanced LIGO and other R&D/development
3. Comments
on weekly report
4. LSC
Issures (Saulson)
5. LIGO
Lab Operations
- Administration
(Lindquist)
- Sites
(Raab, Zucker, Shoemaker)
- Commissioning
(Fritschel)
- Optics
and Mechanics (Coyne)
- Control
and Data Systems (Bork)
- 40m (Weinstein)
- TNI (Libbrecht)
- LASTI
(Ottaway)
- Lab
computing (Anderson)
- Science
Group (Lazzarini)
6. Enhancements
(Adhakari)
7. Advanced
LIGO (Shoemaker)
8. Change
Control Board/Technical Review Board Session as needed
Site and other business issues:
Special Items:
Special Announcements:
Weekly Report Highlights
Work continues on the MOU (and Attachment) for joint research between
LIGO/LSC and Virgo. Marialessandra Papa
from the LSC and Andrea Vicere from Virgo have led discussions among the data
analysis group leaders, proposing some revisions to the MOU and many features
to add to the Attachment. The two of
them will join the meeting between Virgo Spokesperson Benoit Mours and the LIGO
Directorate on Friday 22 Sept.
A meeting of the LSC Executive Committee was held on Thursday 21
September. The updates on S3 results for
the Einstein@Home web page were approved.
Most of the rest of the meeting was devoted to discussion of LIGO/Virgo
issues, including a proposed joint collaboration meeting schedule. Comments
from members of the LSC Executive Committee will help to guide the ongoing
discussions with Virgo.
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
Listed below are complete August 2006 MOUs and attachments. They were
accepted by the review panel as submitted, and will be routed for signature and
submitted to the DCC for posting shortly.
|
MOU
|
Attachments
|
|
CaRT
|
ACF, DAT, OPT, Z
|
|
GEO
|
ACF, DAT,
LAS, OPT, SUS, Z
|
|
Hobart
|
OPS, OPT, OUT, SUS, Z
|
|
IUCAA
|
DAT, Z
|
|
Loyola
|
DAT, OPS, Z
|
|
Michigan
|
DAT, OPS, OUT, Z
|
|
Oregon
|
DAT, OPS, Z
|
|
Southern
|
OPT, OUT, Z
|
|
Syracuse
|
DAT, OPS, OUT, Z
|
|
TexasB
|
DAT, OPS, OUT, Z
|
|
WashState
|
DAT, OPS, Z
|
|
Wisconsin
|
DAT, Z
|
Embry-Riddle, LaTech and SLU have been received complete with changes and/or
additions requested by the panel. These will be processed and routed for
signature in the next week or so.
Other MOUs are on hold pending
various changes/additions requested by the panel of reviewers, and will be
processed as they are received.
SITE TELECONFERENCE (Lindquist)
- A
site teleconference was scheduled Thursday, September 21, 2006. There will be one more site
teleconference scheduled Thursday next week. Starting in October this meeting will be
appended to the Executive Committee meeting scheduled Monday
mornings. A proposed schedule has
been provided. The following issues
were among those discussed this week:
- FY
2007 Budget – in
process. Information has been
received from the sites that will be incorporated before the meeting next
Monday.
- Livingston
Forklift Procurement – has been signed off.
- Paving
of the Parking Lot for the Science Education Center – An IFB is
being assembled.
- There
are currently no open action items.
PROPERTY MANAGEMENT (Luna)
>
- Attended
the Federal Acquisition Regulations (FAR part 45) training at Stanford
University.
- Created
a document about Export Administration Regulations (EAR) and International
Traffic in Arms Regulations (ITAR).
- Provided
assistance to Christian Cepeda in shipping a package to Dell.
- Coordinated
the disposal of old computer equipment from the Wilson House. Account Number
LIGO.TEC-1.3-NSFLIGO.FY02ON.
- Screened
for three pieces of equipment for LLO (Forklift, Fusion Splicer, and
Spectrum Analyzer)
- Working
with Property Services on year end reports for Government-Owned property
and leased GSA vehicles.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- In
the process of entering into the database that large batch of PSI As-Built
drawings recently printed.
- Made
some changes on the current Document Log Table in an effort to clean
things up for the document conversion.
- Scanning
- Progress continues on scanning of non-electronic "T" category
documents.
- Activity:
|
Week Ending
09/21/2006
|
In
|
Out
|
|
Packages
|
32
|
6
|
|
Faxes
|
30
|
38
|
FINANCIAL SYSTEMS (Cronin, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Placed
the order for the speed buffers for delivery to Caltech.
- Placed
the order for the forklift for LLO.
- Placed
the order for the furniture for LLO.
- Completed
change order #17 to U.S. DOE and submitted to the vendor.
- Working
on change order #3 to HPD. The Lobbying Cert is pending.
- Completed
change order #3 to Filehold and submitted to the vendor.
- Placed
the order for the Spectralon sphere.
- Completed
the invoice-attached orders for payment of LIGO Livingston Observatory
invoices.
- Placed
the order for Riccardo for the gaussmeter.
- Placed
the order for the mephisto laser.
The vendor will import from Germany. It has a 5 to 6 week
lead-time.
- Placed
the order for the prototype boards.
- Assisted
various individuals with preparing orders in TechMart, adding additional
requisition approvers, and resolving issues with TechMart.
- Placed
the order with Varian Inc for the spare parts for the LIGO Livingston
Observatory.
- Placed
the order for the Spectrum Analyzer for LIGO Hanford Observatory.
>From: Florence Kaufman <fkaufman>
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone <gsalone@ligo.caltech.edu>
- The
furniture for the LLO SEC has been ordered, and will be delivered prior to
the opening ceremony scheduled for November 13.
- An
order is being placed for a new fork lift for LLO. This forklift will be capable of
handling the delicate exhibits in the SEC.
- An
invitation for bid (IFB) is being prepared for the paving of the east
parking lot at LLO. Bids will be
due on September 29.
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- A
special account was created by Caltech to allow for the procurement of
items necessary to provide the laser controller for the Max Planck
Institute at Hannover, Germany.
Those procurements are now under way.
- Parts
are being received at LLO for the outdoor wall exhibit for the SEC. Discussions are being held with the
installer regarding the schedule.
PROPOSALS and REPORTS (Lindquist)
Monthly Report for LIGO Operations sent to the NSF.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
- There
are no open change requests.
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
No report.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of S5 Activities at LIGO Hanford
Observatory (compiled by M. Landry)
A comparison of H1 and H2 noise indicated the 6Hz stack mode to be a problem
on H1. This led to the modification
of ASC and SUSPOS filters which improved the H1 IFO range out to 15Mpc as
claimed by Sensemon (Autocal
range estimates suggest
we should update the H1 calibration, we may get a bit more range in a new
cal). The darm spectrum
with and without the filter bank clearly shows the 6Hz suppression. WFS
filtering mods were contemplated too.
Single IFO duty cycles for the last week were: H1- 86%, and H2 - 87%.
S5 highlights from the LHO elog are bulleted
below:
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
No report.
Mechanical
and Optical Systems (Coyne)
See Advanced LIGO
Nothing significant to report.
Controls and Data Systems (Bork)
See Advanced
LIGO
40-Meter Interferometer (Weinstein)
DC Detection and Vacuum Squeezing Development
- The
broadband noise on the DC PD was mis-estimated;
it's actually lower than we thought, and is acceptable. There is still a lot of spikes in the noise, presumably
associated with grounding problems, and the LP filter added to the preamp
doesn't help much. But it's good enough for now. The preamp has been
returned to the vacuum nipple, refilled with krypton, and the nipple
sealed up.
- Rob
installed a laser and some optics on the AS table in preparation for
aligning the DC readout optical train through to the SRM.
- Steve
and Dan began the vent on Tuesday at 11, and by late afternoon they
started opening doors and removing the access connector between the BS and
ITMY chambers.
- The
pumpdown caused the oplev
signals to shift, and they are being carefully watched.
- Rolf
and Alex have begun the installation of the DC readout controls. More work
will continue next week. They were able to bring the controls computer on
line to test with the Framebuilder. The Framebuilder can now accept data from both the
reflected memory network and the Myrinet
network.
- Bob
is building cables for the DC readout controls, and temportary
cables for the in-vac alignment work.
- Go
realigned the SHG beams and increased the green light power by a factor of
2. He then realigned the pump beam into the OPO and lowered the crystal
temperature, getting the parametric gain up to 30.
- Go
measured the beam profile of the seed output and LO at the homodyne photodetectors in order to improve the homodyne
visibility.
- Riccardo is stuffing his balanced PD PCB boards and
beginning tests. He's also frantically writing his paper and a talk for
next week. He looks a little tired!
IFO Commissioning, Electronics, Controls, Computers
- Steve
and Osamu opened up the MC2 chamber to improve the OSEM positioning on the
suspension. Steve set up the oplev with MC2
exposed, do use as a reference diagnostic. Osamu spent some time fiddling
with the MC2 OSEMs. The UR OSEM had a lower
voltage than the others. They swapped the satellite amplifier with a
spare, then the UR sensitivity became the same as the
other OSEMs. The UR was also noiser
than others. They swapped some cables and the noise got better. We need
new, well-made 4-pin LEMO cables. Some of the in-vac
OSEM pigtail cables were potentially close to the beam, so the OSEMs were rotated and the cables tied down. They
adjusted all the OSEMs to give readings in the
middle of their range (~0.8 V). Finally, they tried to decouple the back OSEMs from bounce and roll modes, and also decouple
the side from POS motion; they didn't see much improvement, but it's good
enough for now. ON to the other suspensions!
- Dan
replaced all the opamps on the LSC PD Interface
Board in the MC rack with less noisy ones, to get better signals for the
MC REFLPD and the MC RFAM PDs.
- Dan
replaced the ETMY Oplev laser diode with a small
HeNe laser, and Rana
measured the uncalibrated noise spectrum.
- Alex put in a new martian network switch to handle the new
controls computers.
Thermal Noise Interferometer (Black)
No report.
Quadruple Pendulum Noise Prototype
We have identified and measured the first modes of the blades on the upper
intermediate mass. We have also observed the effects of the eddy current damper
on these modes. There are entries on these measurements on the Lasti ilog on September 18 and
20. LASTI was vented this week and is
now in the process of being resealed. We realigned the main eddy current
dampers, reinstalled the resistors for the thermal test, and reinstalled the
blade eddy current dampers. The problem with the resistors appears to have been
a bad solder joint. While reinstalling the blade ECDs
one of the magnets came unglued so we are running without it for the time
being.
Internal Seismic Isolation
The broken actuators have been repaired. We should have all of the position
sensor electronics by Monday, so we will finish the actuator installation next
week.
HAM SAS Preparation
The new cleanroom was installed and the scissor
tables have been installed to support and adjust the gullwing
height.
CIT Science Group (Weinstein)
Shourov Chatterji
- Travelled to MIT to work with Leo Stein, Lindy Blackburn, and Erik Katsavounidis
on the S5 Q Pipeline search and code review.
- Finallized collocated H1H2 consistency test for the S5
Q Pipeline search
- Added
Q Pipeline executable to QSCan installations.
- Initiated
weekly teleconferences for the S5 Q Pipeline search and code review on
Thursdays at 10am pacific time.
- Implemented
automated updating of QScan frame cache and
segment information on LHO, LLO, CIT, MIT, PSU, and UWM computing clusters
and LHO, LLO, CIT, and MIT general computing systems.
- Discussed
whitening algorithms with John Cannizzo (NASA
Goddard), which may lead to improvements in Q Pipeline data conditioning.
- Gave
weekly glitch report update on S5 run call. http://ldas-jobs.ligo.caltech.edu/~shourov/reports/glitch/WeeklyDC_20060910-20060917/
- Met
with Hannes Helgasson
to discuss chirplet based approaches for burst
searches and a related work done by him and Phillip Charlton
Stephen Fairhurst
- Worked
on automating the procedure for obtaining the upper limit from inspiral searches. This is being applied to all
S3/S4 searches. Also, continued writing up a paper describing
the details of the method.
- Gave
a presentation to the tapir group on black hole horizons and discussed
possible applications in numerical relativity.
Duncan Brown
- Visited
Jon Gair in Cambridge to learn about 'kludge' code
for generating EMRI waveforms
- Attended
workshop on spinning binaries in Cardiff.
Gave a talk about the implementation of the physical template family.
- Met
with Diego to discuss his progress implementing the PTF code
- Re-interpolated
the domains on several of my numerical relativity simulations
- Helped
Lisa prepare for her candidacy exam
Patrick Sutton
I've been studying GRB060813 using the Xpipeline
coherent analysis package. I presented a preliminary report http://www.ligo.caltech.edu/~psutton/protected/xpipeline/GRB060813/report.html
on the background statistics at this past week's ExtTrig
and Burst telecons. Currently I'm analysing data with injections. I've also been doing
some code development work: testing clustering codes for post-processing of the
likelihood maps produced by Xpipeline, and computing
significances of constraint likelihoods (used in comparing likelihoods for
different sky positions). I met with Tinto and
Searle to discuss our "Bayesian glitch" project. Finally, I've
been helping Stephen Poprocki as he drafts his final
SURF report.
Gregory Mendell
I am giving a seminar at Washington
State University
on Sept 21, 2006. Title: The Search For Periodic
Gravitational Waves Abstract: I will survey the LIGO Scientific Collaboration
Periodic Search Group's methods and results. DCC number: LIGO-G060499-00-W.
Rejean Dupuis
This week I've been doing SciMon shifts at
LHO. I generated some nice looking high resolution spectrograms of recent
S5 data. They are available at http://www.ligo.caltech.edu/~rejean/S5/spectrograms.
I also prepared and I gave a presentation on Tuesday to some RXTE folks on
our targeted periodic searches.
Weinstein
- Continuing
review of S3/S4 inspiral analyses
- Helped
Lisa prepare for her candidacy exam
- Recruiting Caltech undergrads to work on LIGO data
analysis.
Laboratory Computing (Stuart)
LDAS Software Systems (Maros)
System testing of LDAS was done using version 1.8.305 of the software. Both
the lsync and the single regression test (pr2221.tcl)
continue to fail. Investigation this week revealed that the failure of the
regression test pr2221.tcl is due to improper copying of an output file from
the remote system to the local system. The LJcopy in
the LDAS Job package is being investigated as the cause of the failed copy.
Testing of PR3023 for timeout resulted in the generation of a problem report
for tclglobus requested the returned error message
read "Operation timed out" instead of "Operation was
canceled".
To facilitate submitting jobs through a regular tcl
socket, the test scripts for qalib.tcl (RDSVerify), datacondMDC (.datacondAPI.rc) , complex_data, geotest, compression test, dc2frame test were updated to
include a -globus $::USE_GLOBUS_CHANNEL option for LJrun.
LDAS currently is unable to use the tclglobus
socket interface for 64-bit Solaris as it causes a tight spin loop even when no
jobs are sent though the tclglobus socket. A proposed
solution of changing some system configuration is currently being tested.
LDAS System Administration (Anderson)
Caltech
(Dan Kozak)
- More
work on /home disk usage plots...still not fully automated, but getting
there.
- Encouraged
Thomas Cokelaer to use LSCdataFind
to find his data in the cluster as opposed to staging it back from tape.
- Worked
with Erik on the ldas-cit NFS server problem
(fixed by upping the number of NFSDs
ultimately).
- rm'd all /home/dwoods (~400GB).
- Cleaned
up old gridftp-server processes on ldas-cit (discovered as part of getting data moving to
MIT again).
- Attempted
to recover deleted file for Shourov, but it
hadn't been around long enough to get on tape.
- Discovered
that archiving for /home had gotten stuck and so files that should have
been going to tape weren't...:arstop/:arstart
got it going again, but I'll have to keep a close eye on it.
- Did
some poking around on Keith Thorne's LSCdataFind
problem.
- Got
GEO RDS frames moving to CIT.
(Phil Ehrens)
- Wrote
wrapper scripts using the VDT CertScripts
extensions to issue host and service certs.
- Modified
the grid-adduser.sh script to modify
/etc/aliases on ldas-cit and to propagate the
modified file and run makealiases on ldas-jobs.
- Installed
qonline analysis support for CIT grid
resources. This allows qonline investigators to execute long running jobs and
cron tasks as user qonline.
- Developed
frontend and backend cgi
scripts for Albert to handle Travel Applications.
(Erik Espinoza)
- Node
Crash: Sun 9/17 node52 kernel panic.
- Tested
Condor 6.8.1 release on Frog.
- Tested
kernel (based on nemo config)
on node321-329.
- Installed
cpu on node329.
- Replaced
cpu 2 on node500
(Larry's node).
- Shipped
42 Dual Rank Samsung Memory & 12 Single Rank Samsung memory to ASA.
- Conducted
bonnie++ tests on 3 kernels (optimize space, default, fedora).
(Stuart Anderson)
- Working
with Condor development team on recent LDAS-CIT crashes.
- Successfully
tested an initial 16 dual-rank replacement memory and requested another
identical 54 replacements.
- Requested
a quote from Sun to upgrade the cluster home directory and frame archive
storage at Caltech and replace the remaining T3 filesystems
at the Observatories, as well as replacing the Sun V880 servers at CIT
with newer Opteron based systems.
MIT
(Fred Donovan)
- Power
outage NW17 - straighten up nfs moutns, etc.
- ldas-pcdev1 ssh issues : automounter not mounting, probably left over from
power issue NW17.
- Spoke
with (you) Stuart, about an hour going over the LDAS setup, etc.
- Checked
mainboard serial number for LDAS cluster with
ASA computers, some software quotes ( matlab for Michele Z, sata
drives for nova ( 2 X 750GB), started spare parts inventory.
Hanford
(Ben Johnson)
- Worked
on improved LDRdataFindServer to be able to
serve at better than 0.5 Hz.
- Helping
track down some data glitches at LLO. Some seem due to data mismatches
between the front-ends and the framebuilder(s).
- Attempting
to find replacement motherboards for the nodes here. ASA claims they may
be able to find our X5DPR-IG2+ models.
- Helped
Christine grid-ify the new Linux GC box in the
control room.
General Computing (Wallace)
MIT
(Fred)
- Replaced
bad disk for lc; dual monitor nvidia / linux setup for pf
- Checked
Marie's auto updates and firewall
- Power
outage NW17 - straighten up nfs mounts, etc
- Started
backups from lancelot/raid to gravity
- Set
up new node (nova, nee oscar)
as second compute node for Erik's group. Added extra disks, integrated
into LDAP, restarted slapd on needle, Poked
around LDAP setup, did some tracing in order to get nova / ldap stuff working (TLS certificates)
- Worked
with Marie a bit to fix some broken web links, set up Dreamweaver
site for her so she could maintain the site.
Livingston
Hanford
(Christine)
- Helped
a new staff member get set up with accounts and a computer.
- Started
building a web server for Einsteins' Messengers
web site.
CIT
(Mike)
- Working
on upgrading Primavera/Prism server. This software is currently running on
server 2000. After loading Primavera's updated software I noticed degrade in performance, plus a few OS issues. I have loaded an image of this server to
a temporary server while I reload the old server with server 2003. This
server may have been having issues before the upgrade. This is an on going
project.
- This
week was a lot of work in W/B server room mounting servers in racks,
trouble shot tape robot with Larry, and running some additional network
cables, plus KVM cables to hook up new servers. Some clean up work as well.
- Loaded
another LINUX box for Hiro. Erik looked into
some yum update issues I was having with this installation. We ended up
using the ldas updated kernel instead of loading
off the downloaded cd's. From hear on out I will be using the ldas load for Fedora. Added additional remote mount
points for this build as well.
- Continued
work on Spam Filters searching for false positives.
- Additional
misc. user support, plus other daily sysadmin
tasks that include working on mail servers, dhcp
server, and work on dcc servers.
(Christian)
- Installed
and tested the latest Microsoft security patches on all windows server.
- Rod
Luna- Upgraded Microsoft Office from 2000 to 2003.
- Patrick
Sutton- Configured new Macbook Pro and installed
parallels software for Patrick.
- John
Miller- computer keeps crashing after running simulations. Transferred all
of john's files and settings to a faster system.
- Installed
new 20 inch LCD monitor for Todd Etzel and Paul
Russell.
- Minor
tweaks on the unit in the display case.
- Worked
on the Spam Filters with Mike and Larry.
- Other
misc.: Continued onsite software/phone support.
(Bruce)
- iLog Maintenance: (0.5 days)
- General
iLog maintenance (user
adds, keyword adds, systems work, etc.)
(Veronica)
- LIGO: Continued working on the NSF
website. This required sorting out
the issues of restricted-access information, as well as restructuring the
public access contents. Worked with
the AdvLIGO team on archiving the information as
public vs private. Posted the information for the upcoming
review meeting. Working on the
online registration tool. Continued
working on the PAC meeting website.
Here, too, an issue of access restrictions came up; even though we
restricted access on our side, some authors put their files in docspublic, which then made it into Google search database. We've asked the PAC20 speakers to
archive sensitive files in the restricted-access area of the DCC, or give
the DCC clearly stated instructions to do it. Working with the speakers and the DCC
to reorganize the presentations.
Working on the updates of the LAAC website. Updates of the LIGO website.
- LSC: Most of the time was spent working on the
website for the upcoming LSC meeting at MIT. Installed the website, posted the static
information. Working on the online
registration database application.
Working with the MIT e-commerce and Marie on the integration of the
online credit card payment application into the website that we'll be
hosting. Updates of the database of
technical papers under review.
Updates of the author list pointers.
- Project
Science: Website updates/ user
support.
(Larry)
- Worked
a number of procurement items. Mostly supply items. Procured a couple of systems for
different people. Reconciled Pcard for the month.
Working on a couple of server and storage procurements. Tracking down items to install new
projectors in the conference rooms.
The new units are quieter.
- Assisted
in the setup of the new E2E machines. Worked on a couple of the E2E
servers. One unit just need a few more s/w settings changed and the other
needed to be rebooted, still watching it to see if it is starting to have
h/w problems.
- Worked
with Mike and others on things in the computer rooms.
- Cleaned
out LIGO items in room 054 with Rod and Christian. Also, started getting
things ready to move to another storage area in the sub-basement.
- Started
working on the tape robot. After a good cleaning (it had been on the shelf
too long) it is now able to communicate with itself. Now I hope to get it
to work with the SUN boxes, there are number of
issues to still be worked out.
- Assisted
with the DCC with a number of different items. The one taking the most
time is the testing of the new s/w.
- Assisted
a number of users with account modifications. Checked out a couple of the
SURF students and setup a couple of new accounts.
- Worked
out some minor problems at WH.
- Started
on a new setup for the 40M.
- Assisted
Veronica in working out some logistical issues with the different web
projects now going on.
- The
display case is now up and running. Thanks to all that helped out,
especially Christian and John Z., there is some tweaking that needs to
take place to make things a little more stable but it is looking good.
- Continual
work with the different user requests and checking out the spam filters.
Advanced
LIGO and Supporting R&D (Shoemaker)
e2e weekly meeting
The meeting was held on 21st, attendees were Sany,
Valerio and Mark, discussing about the modeling of a
triple suspension sitting on HAM-SAS.
The effect of the back reaction from the triple suspension to HAM-SAS is
studied now. There is some discrepancy between Virginio-Valerio
model based on Maple and the e2e model using Mark's triple pendulum sitting on
HAM-SAS. It was concluded that, for now, the e2e setup with Mark's triple will
be used to study control systems. Later, Virginio
suggested that the difference may come from the placement of the suspension
cage which could induce torque.
After this discrepancy is understood, the major milestone of this study is
- short
term goal (1 week): transmissibility from the suspension point motion
to back reaction force without any control
- medium
term goal (a few months) : same quantity with triple pendulum local
controls
- long term study is the study of the HAM-SAS with
suspension forming a cavity where the radiation pressure can push the
system in different way than forces by control systems.
Sany has a simple version of the local dumping
code. After discussing with Osamu, this code will be passed to Valerio and Valierio will
complete the triple pendulum local dumpling code. Sany
will work with Laurent Ruet of MIT to implement the
modal control in the triple pendulum setup in the e2e simulation setup.
Static IFO simulation (Hiro)
A more systematic study of surface noise was done. In short, if you specify
the rms of the mirror surface up to 10cm for Adv.LIGO arm, the loss changes less than 1ppm even when the
rms outside is worse by factor 3. If you specify the rms in a smaller region, the actual loss could get
appreciably larger than the estimation.
A couple cavity modeling is going to study the clipping effect by BS.
Fast simulation of Dual Recycled Michelson Cavity (Hiro,
Keiko)
Formulation of an approximation field calculation in a FP using linear
approximation is still going. Keeping up
to the linear term in velocity and angular motion of mirrors, an explicit
expression has been derived to calculate the field evolution over a long term
(many bounces all at once, not single bounce, in a cavity). Next is to validate
this formula numerically. Once this validation is done, this approach
will be applied to the dual recycled Michelson cavity, which is the final goal.
Modeler (Hiro, Bruce)
Bruce is developing the C++ code of the UserDefinedPrimitive
(FUNC_X based user-configurable universal primitive), built in the simulation
engine, modeler. We have new machines, rigel1 and nunki, dual
core dual CPU machine running at 2.6GHz, using FC4. Hiro and Melody
studied the performance. The same issue as saiph is
found, i.e., glibc's bug makes the code run slower
and we have to use older version of libm.so. Melody
is now testing the latest gnu version, 2.4, to see if the issue is solved.
Mechanical Simulation for Advanced LIGO (Sany and
SLU team)
Kept working on the modeling of the mechanical system using Mark Barton's
triple pendulum and HAM-SAS by Valerio. See about about the
e2e weekly meeting.
ALFI : e2e front end (Bruce, Melody, Hiro)
Melody is developing the interface of the UserDefinedPrimitive
(FUNC_X based user-configurable universal primitive), in alfi.
Now JAVA 1.5 or even 1.6 is out, Melody
modified alfi so that alfi
can be compiled and run using JAVA 1.5. Hiro sent mails to alfi uses if
the transition to JAVA 1.5 is OK, and so far no complaint is returned. We
hope to switch to JAVA 1.5 version of alfi by the end
of the year.
Seismic Isolation
Single Stage HAM SEI Procurement
The Request for Proposal, Design Requirements document, and reference CD is
nearly completed for the design and fabrication of the Advanced LIGO Single
Stage HAM Seismic Isolation System. We are waiting for a conceptual
design report to complete the bid package. The bid package is scheduled to be
sent to potential bidders next week.
From:
"Joseph A. Giaime" jgiaime@ligo.phys.lsu.edu
Agenda for the weekly SEI telecom
Friday, Sept 15, 2:00 pm
Eastern, 1:00 pm Central, 11:00 am Pacific time
- Locks
unstuck at BSC prototype; threads had gotten a bit dirty and barrel was
slightly scuffed. We need to find a surface treatment to make both
the threads and the barrel slip better when UHV clean. Perhaps the
same surface treatment used in the LIGO-1 seismic knuckles.
- First
transfer functions take from stage 2 horizontal sensor to nearest
L-4C. Also, Rich ran Brian's model and compared with the data.
- Two
damaged actuators have been repaired and await
re-potting with approved epoxy. The correct epoxy is on order.
We are still missing the prototype small actuator. Kyle, Jay and Bob
Taylor ought to search their stuff.
- Brian
has received some pages from Corwin as a start on the conceptual design
report.
- Brian
and Ken have assembled a draft for the single stage HAM requirements
document. The draft and Brian's summary of the changes since our
last seismic RFQ appear in seismic log entry 691.
From: Dennis
Coyne coyne@ligo.caltech.edu
HAM-SAS weekly meeting minutes 20 Sep 2006
Ric, Dennis, Chiara
(Dave O. & Virginio briefly)
agenda:
1) fabrication status
finished loading table this morning-- 158 mHz,
stopped trying to get the resonance lower -- should allow another ~50 kg to get
to collapse point -- used about 1485 kg (1545 kg at collapse point) -- Ric will put together a note on the loading for the IPs and the GAS filters
no longer a preference for rotation about 1
(preferred) leg -- previously this observed & found to be due to one leg
being macroscopically longer than the others
will test fit LVDTs &
motorized springs this week, central post for monitoring LVDTs
to be ready next week, then will get ready for disassembly & cleaning
received optical bench cart from Soldi -- will re-assemble & then ship to LASTI along
with drill templates to create holes required on bottom on HAM table, 2nd
transfer cart to be sent to Soldi soon for cleaning
elevator carts: moved 2 tons easily with no problems horizontally (note:
wheel/track guard has not yet been installed) -- found a problem with the
vertical lift mechanism -- making change to sliding spring loaded clamp &
non-reversing mechanism (negligible cost change) -- also changed gearing (still
have sub-millimeter positioning capability)
cleanroom has lights now
oven: received final sheet metal -- beginning
welding -- expect that it will be delivered on time
Ric returning to G&M 10/9 (will be at thermal
noise summit meeting 10/7)
cleanroom supplies: plan
for LIGO to purchase in US & ship to G&M
base plate welding: constrained welding -- reduce
warping
lateral mode of the spring box: RIc
measured 6 Hz, not 1.5 Hz as predicted: see (3.7 MB word file), http://www.ligo.caltech.edu/~desalvo/HAMSAS/spring-box-tuning-report/Test-of-the-Spring-box.doc
tilt instability before lateral instability observed (22MB movie): http://www.ligo.caltech.edu/~desalvo/HAMSAS/spring-box-tuning-report/tilt-instability.MOV,
this should be expected given high center of mass relative to the support
points -- not observed in simulation?
2) LASTI test plan
Dave has not received many comments as yet -- please read & comment
3) electronics
Valerio observed overheating of the modified LVDT driver
circuit, but higher range, better sensitivity: http://www.ligo.caltech.edu/~citsas/HAM-SAS/Presentations/HAMSASWeekly20060920.pdf,
noise is a little higher at 2 Hz but likely can be reduced some -- will work
with Ben to resolve problems
need to review/comment on Ben's system
interconnection diagram distributed last week
4) simulation
no comments during meeting -- Yumei
has calculated the shift in 's' mode frequency with change in IP leg load
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
Attended most of the OMC meeting last thursday
before my flight at DFW airport. Working with Calum on design details. Met with
Caroline and Helena this morning about preparing for the quad noise prototype
delivery to LASTI. Helena
will schedule another meeting. Working on Advanced LIGO suspension budget estimates. Reviewing Justin's UK Milestone schedule in preparation for a
detailed discussion on Tuesday. Reviewed and commented on some paperwork
for Joe G today.
From: Ken Mailand kmailand@ligo.caltech.edu
I'm using information from Ian, and working on a lower quad installation arm
shop drawings. The CES shop has completed more than half the parts for the
basic arm.
The fixture lift table for LASTI has returned from chrome plate,
and is at CES for re-assembly. I'm working on the lift assembly for the suspension.
Core Optics
From: Bill Kells kells@ligo.caltech.edu
We had an additional TCS review committee meeting this AM, which has
required a lot of study for (as well as dicsussion/analysis
with Phil W on).
Finished off SURF project paper (now submitted) with H. Bantilan. Actually
the process has launched also an ongoing analysis and further studies which he
is still participating in.
I have essentially finished my analysis of how "drifting" acoustic
resonance lines affect the PI instability thresholds. This will be reported in
tomorrow's OWG meeting.
From: Helena Armandula ahelena@ligo.caltech.edu
CSIRO
Just received the selection of small targets that they
ordered for doping during the up-coming runs. They are drilling them so
they can suspend them in front of the main targets. They have: Ti, Ta, Nb and Al. The Ti
doped Ta coating run will be done first. They have also completed the fixtures to hold the Glasgow
diving boards and they are ready to
proceed with those.
Advanced LIGO SUS
Working with Janeen and Caroline on how to pursue
the installation and commissioning of equipment needed for ribbon pulling,
welding and characterization at LASTI.
Auxiliary Optics
PO TEL
Chris and Calum have decided that the conceptual
design for the ETM PO TEL suspension assembly, including a suspended output
detection bench will be similar to the PO Mirror SUS. Chris will make a
conceptual SW drawing. The baseline concept for the earthquake stops/catcher
for the lower mass is to mount it to the chamber walls.
LAYOUT
I calculated new positions for the PRM, SRM, ITMx,
and ITMy; which are compatible with a free spectral
range of 9 Mhz for the PR
cavity, 180 MHz for the SR cavity, and a Schnoop assymetry of 200mm. The average PRC optical length is
8327.6 mm, and the average SRC optical length is 8340.8 mm with a detuning of
0.1. I used the formalism given on p.3 of T010076-01. The ITMy
mirror was placed at the closest position to the BS--this position may change
when Chris updates the layout with the PO Mirror SUS design. The global
coordinates of the optics are as follows:
|
optic
|
X
|
Y
|
Z
|
|
PRM HR
|
-3526.7
|
219.0
|
157
|
|
SRM HR
|
-180.6
|
-3087.3
|
159.3
|
|
ITMX HR
|
4847.4
|
200
|
80
|
|
ITMY HR
|
-200
|
4900
|
86
|
OPTLEV
I am writing the conceptual
design requirements document for the AOS OPTLEV subsystem
SLC
Luke has a conceptual SW layout of the HAM2 and HAM3 baffles
in the vault.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
I have been characterising the performance of a differential photodetector to see if it performs any better at low
frequencies. The low-frequency measurements keep getting reset whenever
machinery is operated from either the machine shop below or next door to the
lab. This is a tad inconvenient. I have not analysed
the data taken thus far but certainly the dark noise is no worse than is the
case for a normal photodetector – as it should
be.
Controls, Data systems
From: Rolf Bork rolf@ligo.caltech.edu
Lasti ISI
(Mohana) I was testing the Coil Driver Prototype.
The circuit meets the current requirements as per the spec for the Coarse actuator 3.5 Amp, and for the Fine Actuator when I
measured the noise requirements between the frequency 10 - 30 Hz it is higher
by a factor of 2. I am doing the model to to see how
much input noise is contributing by the LM12, and it is 318nV/rtHz at 10 Hz. I
also found out the OPA549 is a good High Current
op Amp. I will do more research on it.
(Jay) Two more capacitive position sensor chassis have been assembled and
tested. They should arrive at MIT next Monday.
Lasti
Squeezing Exp.
(Jay)
- SUS coil driver boards received and are being
stuffed and tested. Chassis front panels have been sent out for fab. Sat amps are tested and ready for shipment.
- AA and AI chassis are assembled and tested. They
will be shipped this week.
- Field and rack cables have been ordered and are
scheduled for delivery next week.
- Installation and test of components at MIT will
begin next week and continue through 10/6.
- Preliminary wiring diagrams and rack drawings are
ready for installation.
(Rolf/Alex)
- Completed
software testing and cleanup for installation/test at Lasti
next week.
For additional information about this report, contact Stan Whitcomb or Phil Lindquist