Weekly Report for
Week Ending September 14, 2006
Past Weekly Reports
The
LIGO Executive Committee Agenda for Monday, September
18, 2006 will be:
(Meeting time: 10:30 am Pacific Time)
1. Announcements
2. Programmatic
(Marx)
- Executive
Committee Meeting Format and Schedule
- Site
Teleconference Format and Schedule
- Weekly
Status Report
3. Comments
on weekly report
4. LSC
Issures (Saulson)
5. LIGO
Lab Operations
- Administration
(Lindquist)
- Sites
(Raab, Zucker,
Shoemaker)
- Commissioning
(Fritschel)
- Optics
and Mechanics (Coyne)
- Control
and Data Systems (Bork)
- 40m
(Weinstein)
- TNI
(Libbrecht)
- LASTI
(Ottaway)
- Lab
computing (Anderson)
- Science
Group (Lazzarini)
6. Enhancements
(Adhakari)
7. Advanced
LIGO (Shoemaker)
8. Change
Control Board/Technical Review Board Session as needed
Special Items:
Special Announcements:
Weekly Report Highlights
No report.
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
SITE TELECONFERENCE (Lindquist)
- A site
teleconference was scheduled for Thursday, September 14, 2006. The following issues were among those
discussed:
- FY
2007 Budgets – draft budgets have been distributed for FY 2007,
and Florence
has issued a set of reports comparing the proposed budget model with
actual costs through August FY 2006.
These budgets will be the subject of discussion during the meeting
of the executive committee on Monday (September 18, 2006). The current projection for FY 2006
actual costs is $32.2 million.
- Livingston Science Education
Center –
As far as the contractor is concerned, LIGO has beneficial occupancy of
the building. There is a continuing
deficiency regarding the water supply for the fire suppression system and
we may need to request a temporary permit to proceed pending final
resolution.
- There
are currently no open action items.
PROPERTY MANAGEMENT (Luna)
>
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
- Received
the LIGO-customized version of the FDA.
Though it had the functions, it was a scrubbed program. So, created all the schemas, drop-down
menus, and file structure. These
were needed to begin testing the functionality of the program.
- After
conferring with FileHold, had about 3,000
records that did not have sufficient destination information for the
migration. These are in the process
of being addressed.
- Identified
four large pockets of records that will be isolated and allocated to their
new destinations in FileHold.
- Continued
to work with G. Stokes in responding to issues and questions raised by FileHold as they create scripts for migrating metadata
from our system into the new.
- Continued
to plan the training aspects necessary upon rollout of the new system.
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- Processed
another two sets of revised/new HAM drawings from Promec.
- Finally
completed printing out all the necessary PSI as-built drawings from the cd rom.
- Assisted
in the process of conversion/allocation of current data to the new
database.
- Scanning
- Progress continues on scanning of non-electronic "T" category
documents.
- Activity:
|
Week Ending
09/14/2006
|
In
|
Out
|
|
Packages
|
26
|
7
|
|
Faxes
|
22
|
20
|
FINANCIAL SYSTEMS (Cronin, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Working
on the change orders for Raytheon and Northrop.
- Prepared
the draft of the Triad agreement for support services.
- Completed
change order #15 to U.S. Civilian R & D and submitted to the vendor.
- Completed
change order #2 to Filehold and submitted to the
vendor.
- Placed
the order for the spare parts for the equipment at LLO.
- Completed
change order 1 to Custom Metal Works and submitted to the vendor.
- Submitted
the list of the soon to be expired subcontracts and blankets for the
extensions to be generated so that they can be renewed. There are 44 subcontracts and 7 blankets up
for renewal by October 11, 2006.
- Fiscal
year 2006 is coming to an end. The
deadline for submitting requisitions to be entered for FY2006 is
9/15/06. The deadline for
submitting FY2006 purchase requisitions is 9/15/06. Refer to the attached
link for other FY2006 deadlines.
>From: Florence Kaufman <fkaufman>
- Worked
on spreadsheets showing the FY07 budget amounts alongside the FY06
expenditures and commitments through August 06.
- Met
with Tom Currier, Ruth Brambila, Gina Salone and Ed Jasnow to work
out a process for adding funds to purchase orders for subcontracted labor
services. The meeting was to
discuss the appropriate way to handle unexpended balances in the contract
when the contract was being modified for the new period of performance.
- Met
with the representative from Northrup along with
Ed Jasnow and Gina Salone
to try to resolve issues related to invoicing and to discuss the proposals
for for extension of services for various contractors
provided by Northrup.
- Completed
and sent out reports for the Visitor Award, Outreach Award, the Conference account at Hanford,
the Hanford and Livingston
discretionary accounts, the Director's discretionary account, the I2U2
Award, the Low Noise Award and the MIT Grid Award.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone <gsalone@ligo.caltech.edu>
- A
modification in the amount of $25,000 was issued to HPD to cover
additional support required because the responsibility for the exterior
wall exhibit for the LLO SEC was moved in-house.
- Change
orders are being initiated to assure the renewal of appropriate contractor
personnel.
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- Beneficial
occupancy of the LLO SEC is now awaiting resolution of the fire marshal's
issues regarding water connections.
The original architect's drawings showed LLO as being hooked to Livingston city water, which is not the case. The revision is being made, and the
correction will be presented to the fire marshal shortly. Meanwhile, the exhibits will be moved into
the new building on schedule.
- Ed
Jasnow is working with Ann Bussone,
of the Office of General Counsel, to resolve ITAR issues in two separate
areas. ITAR is the set of
regulations governing the import and export of sensitive technology. The first area concerns the laser
control system being procure for Germany, and the second
concerns the international collaborators on Advanced LIGO.
- The
new form for the processing of volunteers has been agreed upon between
LIGO and PMA, and is now awaiting approval by OGC.
Administration (Hiroto)
- Travel
for Jay, Barry and Albert.
- Arrangements
for GDE-ILC meeting (Oct 9-10).
- Arrangements
for NSF Review- LHO (Oct. 23-25).
- Moving
arrangements for offices of Deputy Director and Director.
PROPOSALS and REPORTS (Lindquist)
- Completed
the monthly report for the NSF. It
should be more or less ready to send.
- Draft
budgets are being prepared for FY 2007 for review during the meeting of the of the executive committee on Monday (September 18,
2006).
- Have
received notification from the NSF concerning due date for submittal of
“GPRA” reports (annual measurement of accomplishment).
- Have
received notification from the NSF that they want us to submit a final
report for the 1996 Visitor’s Program.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
- There
are no open change requests.
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
Nothing significant to report this week.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of S5 Activities at LIGO Hanford
Observatory (compiled by M. Landry)
The week was a relatively quiet one, with good science
mode running, typical ranges, and duty cycles for the week just at our S5
single-IFO goal: H1 - 86%, H2 - 85%, despite a 7h calibration run on Sunday.
S5 highlights from the LHO elog
are bulleted below:
- current
problem spectral
lines were listed in the elog; one of the
main commissioning tasks for our next break will be to try and mitigate
some of the offensive lines in our pulsar searches (see maintenance link
below)
- the Sunday a.m. calibration
had very mixed results, so that we will have to request additional time to
finish/redo these measurements. We had some structure in simple michelson/AS_Q transfer functions that had not been
observed in previous runs, plus there were some delays owing to a
misbehaving awg processor on h1
- our
standard suite of weekly summaries: range
& duty cycle, IFO
maintenance, including plans for an upcoming commissioning run,
expected some time between Oct 25 and Thanksgiving, possibly lasting two
weeks, and lastly, CDS work summarized for the maintenance period last Tuesday
- the
Tuesday maintenance itself went long (8h instead of 4h), as roofers
continued working
- the
TCS laser failed
on the 4k; later, followup and a prescription for running was posted
to the elog
- mis-centering of the photon calibrator and IFO
beam was better understood; this does not however significantly impact the
offset obsesrved between the two calibration
methods, official and photon
- a comparison
of 4k and 2k spectra show the 6Hz peak in the 4k could use attention
- long
spectra on the 2k allow for the investigation of low frequency resonances
- DMT glitches
showed up steadily late last week
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
L1 in S5 (MZ for O'Reilly)
Mostly a quiet week.
We are still impaired in daytime by some nearby logging activity, apparently
inside the acute angle of the arms. Scout teams are scouring the logging roads but
have not yet made definitive contact.
The microseism has come up above the 50th historical percentile due to
Atlantic storms. This made operation at
high power prone to glitching and poor statistics. For several nights this week we stayed at our
lower "daytime" laser power to maintain higher dynamic reserve (at a
slight loss of peak inspiral range).
LLO Outreach (Thacker)
Subtantial efforts on Opening Event work list:
invitations copy work reviewed & edited, media kit
contents organized; late additions to guest list; Scheduled Exhibit pickup from
Southern University on Sept 26th; Arranged Group C exhibit delivery details for
Oct 11th. Met w/ Reps
from LSU physics department to discuss partnering in teacher Professional
Development. Discussed
procedure for developing the by-laws and work mechanisms/procedures for
potential partners to join the SEC Partnership. Significant progress made on developing
outreach material to be posted on our SEC website.
Comments from Partnership w/ Southeastern Louisiana University (SLU). This partnership, not yet formalized with an
MOA, is proceeding with grant funding from LA GEAR UP. These agreed upon outreach items consist
of: (1) High School student research,
mentored by former LLO RET and (2) an SLU Elementary Physics course for
Education Majors that uses LIGO exhibits and derivative tabletop demonstrators
("snacks") to uncover basic physical science themes.
(Gersch/Perez/Wagner, Holden High School
Science Teacher/HS Senior/HS Senior) This
week we used Scott's JVC camcorder and inserted the movie into LoggerPro 3.3. The
camera was able to record 30 fps; this allowed ten to eleven points to be
clearly visible in the projection. With
additional points the slope of the line for y velocity plotted against time was
close to gravity. It appeared that
terminal velocity may have been reached as it entered the trough (a distance
of about .5 m), but we need to do more analysis and experimentation to be
sure. The x velocity was fairly constant
throughout the trajectory slowing slightly at the end. (They continued their analysis on the
projectile motion using the Gravity rainbow exhibit. Added by Yoshida)
(Norwood,
SLU Physics) Snacks related to the first
LIGO visit of PHYS 142 students were constructed and introduced to
students. All site visit reports (from
students) for the first LIGO site visit have been received. One student has been recruited to help Naomi
with snack construction, as well as prepare a short guide to the construction
of the snacks (parts list with estimated costs, guide to the construction).
LLO Mech Engineering (Romie)
LIGO SEC Kinetic Art Project Continuing to status orders to assure delivery.
Received a call from the bearing distributor on Thursday saying bearings were
still 7 weeks out. Worked with HPD to
find a replacement and placed a replacement order (after Allen cancelled the
previous PO) today for bearings with a 3 week
lead time. Hope to receive them on Oct
3rd. Allen is statusing with SAPA on pendulum freight
delivery. Working with
Bill Hollander, Mike and Ed Jasnow on contract
extension while I'm here at Caltech.
Advanced LIGO Suspensions Working here at Caltech on AOS
pick off suspension and ETM telescope suspension. Dennis, Calum & I had an extensive discussion about the OMC
yesterday. Dennis will be sending a long
memo about this today. We covered the
labor available, the tasks, the best division of tasks, the schedule for the
tasks and a few technical items. Calum talked to Norna this morning to fill her in. I will attend the OMC
meeting tomorrow, if my flight permits, during my layover at DFW airport. Working with Justin and Ian
on blade material for them to use for a fabrication study. Working with
them to determine what more information they need from the AOS group to finish
up the ITM/CP and ETM suspensions. We
hope to schedule a meeting in the coming week to address these outstanding
issues. Working with Caroline Cantley and Helena on ear and bonding issues.
Misc Bob Taylor hopes to ship out short initial
LIGO osems to Conor
Mow-Lowry tomorrow.
L1 CDS (MZ for Bogue)
- Ongoing
support of S5.
- All
three LLO weather stations are *still* reporting to CDS
- Worked
with Alex on new ETM front end code install
- Worked
issue of communication loss with LDAS jamming certain control room FOM
tools
LIGO Computing and Network Security (Roddy)
- Tuesday
we took the first steps in getting the WAN connection between LLO/LSU/LONI
reconfigured. We now have two
logical pipes running over one physical pipe which will allow us to run
with our legacy LSU allocated IPs and also our
new ARIN allocated, multi-homed IPs. The next step will be initiating a BGP
session with LONI (or LSU, the details are still being worked out) and
advertising the IPs over that link.
- Made
some progress in getting SoA for the ligo-la subdomain, in large
part thanks to Larry speaking in person to folks on campus. I need to get a server in place now to
accommodate our having SoA. After that, we will work to get control
of the subdomain to make our transition to new IPs easier.
- Working
on ordering some fiber to install between the Communications room,
computer users room, and the MSR.
This will provide us with the ability of installing a jumper rather
than crawling under the floor anytime a change is made. I am also installing 10 gig capable fiber so that when the time comes, we are ready.
- More
planning issues with LSU. There was
a meeting on site Wednesday to discuss the timing of our move off of LSU's IP addresses.
I think LSU understands the situation at this time and some of the
pressure will ease up. Lots of
discussion over the last two weeks concerning this...
- Working
on more long term network planning with the new allocation. Laying out the IP subnets, etc. Have to start dividing up the space now
that it is live and I need to start allocating it.
- Received
a catalog for fiber video equipment for the grand opening of the outreach
center. Evaluating and selecting
the needed equipment.
General Computing and LDAS Admin (Giardina)
- ordered a couple wireless mouse(s)/mice?? for laptop
users
- FC5
install with MySQL server for Shannon
to use. Finally sorted this out
after numerous hardware issues.
- user had video problems when trying to use monitor our
projector with her laptop. still trying to
straighten this out.
- another email flood released by LDAS due to scripts
started by cron being terminated before the cronjob itself on nodes. I found a possible solution for this,
but have not yet implemented it 100%.
Still looking at consequences and other possibilities.
- installed
printer for a couple users
- continued
training our spam filter
- more housekeeping, roundup of old PCs and various
parts, etc.
- other
usual user requests and support
- rode shotgun with operator in search of logging
activity in the woods between beam tubes.
- ejected
tapes for shipment to CIT, imported and labeled replacements
- worked
with Dan to resolve another duplicate tape being reported by sam
- another email flood released by LDAS due to scripts
started by cron being terminated before the cronjob itself on nodes. I found a possible solution for this,
but have not yet implemented it 100%.
Still looking at consequences and other possibilities.
- changed
symlink for ldg to
complete the upgrade from 4.0 to 4.1.0
- verified FQDN in /etc/hosts for ldas(gateway)
with the internal IP on nodes. node1 had different entry than nodes 2-210, I presume
from someone's testing?, so I have not changed it back.
- changes to cluster_mon app so
that only one instance can run.
- uninstall
of dovecot on ldas-pcdev1 to eliminate a cert-check error email
Data Analysis (Yakushin)
Storage/Condor/LDAS admin
- Configured
automount of node's /usr1 and ntp on the test segment database server;
- Using
L3 frames on the nodes, published the corresponding segments on the test
segment database;
- Tracked
down a problem with clearwater not being able to
insert segments into ldas' segment database;
quite unexpectedly to everybody it turned out that clearwater
is visible on GC network with its CDS 10.100.0.155 address; the same
problem prevented lloscript from accessing data
in /archive/frames; firewall rules have been modified to fix that;
- On
Sunday segment replication to LLO (but not from LLO) stopped; restarting
segment replication at LHO fixed LLO's problem;
most likely replication was broken during Sunday's network outages
(although typically it is robust against such events and restarts
automatically);
- The
tape cabinet arrived.
Data analysis
- Running
the latest version of the coherent waveburst on
LIGO and LIGO-GEO S4 data to generate the final set of triggers for the
paper comparing incoherent and coherent waveburst
pipelines on S4 LIGO-GEO and LIGO data.
- Preparing a presentation about LDAS for tomorrow's
visit of a group of CCT LSU students.
Mechanical
and Optical Systems (Coyne)
See Advanced LIGO
Controls and Data Systems (Bork)
See Advanced
LIGO
40-Meter Interferometer (Weinstein)
IFO Commissioning, Electronics, Controls, Computers
- Last
week, Rana again noticed that the RFAM coming
out of the Mach-Zender was very large, and very
sensitive to poking with his finger. He found the EOM mounts to be less
than stury, and thermally not stable. He
tightened screws and did a few more tweaks. Osamu checked the alignment of
all the EOMs and the input beam to the MC. We should plan on replacing the
EOM mounts, re-laying out the MZ, and re-aligning the whole IO path,
sometime after the vent.
- Osamu
and Rana will do a final round of IFO locking,
taking baseline readings of all power levels and beam positions, in
preparation for our upcoming vent.
- Steve
set up the MC2 oplev QPD to instead monitor the
MC2 main laser transmitted light. However, we changed our mind, judging
the oplev to be a more useful monitor during the
vent. Rana will re-setup the MC2 oplev. Then we'll switch back to transmitted light,
after the vent, since the MC2 oplev has never
been very useful.
- Steve
noted that the beam path to the IOO POS and ANG QPDs
was clipping, so he re-routed the path around the persicope.
He then re-established good signals on all the reference QPDs (IOO POS and ANG, IP POS and ANG, all oplevs).
- The
lenses that mode match the PSL beam into the MC were not AR coated. Osamu
and Steve replaced them with new AR coated lenses, and re-established the
beam pointing into the MC. The visibility was measured to be 92% (somewhat
lower than Osamu remembered from years ago). However, we now have 14% more
light into the MC.
- Rana plans to measure the offset of the beam spot on
the ITMs. If ITMX is offset in x (horizontal,
transverse to beam), we will move it a bit. Dan moved the ITMX
horizontally by 6 mm last summer, and the beam spot as seen on the CCD
monitor appeared better centered. This time, Rana
is measuring more accurately by dithering the ITMs in pitch and yaw with the arms locked, and
observing any angle-to-length coupling.
- Osamu
is writing up a detailed procedure for optimizing the OSEM positions on
the suspensions, in preparation for adjustments to the OSEMs
on the MC2, BS, PRM, SRM suspensions during the upcoming vent.
- Rana has proposed that we replace our cheap, noisy oplev diodes with HeNe
lasers. Dan measured the RIN of the HeNe laser,
getting ~ 1e-6 V/rtHz baseline with some large spikes
in the 100-500 Hz region.
DC Detection and Vacuum Squeezing Development
- Bob
has prepared all the in-vac cabling for the DC
readout beamline.
- Osamu
checked that the DC response of the two TT PZT mirrors behaved as
expected; all the axes moved as expected (pitch for pitch and yaw for yaw)
with ~ few mrad/100V.
- Rob
has completed the assembly of the in-vac beamline, on the flow-bench. He's wired everything up
and done lowest-order testing. He has dither-locked the OMC using analog
electronics, using both forward-propagating laser light and
backward-propagating (from the DC PD back towards the main IFO). Handles
have been installed on the breadboard so that it can be lifted up and
placed in the vacuum chamber. Rob has written down a fairly detailed
installation procedure in the 40m Wiki. Aside
from the DC PD problem (below), he's ready for installation.
- Ben,
Bob and Rob assembled the DC PDs and in-vac resistors, and wired it all up. Rob discovered
that one of the DC PDs was broke (no signal). It
turned out that one of the PDs had been damaged
either in the de-canning, or the cleaning phase. Ben brought over
replacements, de-canned them, they were cleaned by Bob and installed by
Rob, who verified signals.
- However,
Rob and Rana measured the noise and found it to
be very large (~ 5x Johnson noise), with lots of HF spikes. Rana and Ben are working on mods
to the in-vac amplifier electronics to filter
out the spikes. Because of this, the vent was delayed from this Thursday
to next Monday.
- Rob
and Rana are compiling a list of "lessons
learned" from the DC readout assembly (even before we commission it!)
on the 40m Wiki. Alan is assembling lots of
related info on the DC readout experiment, on the Wiki.
- Rolf
has begun installation of the DC readout digital controls in rack 1X5: the
Sun computer, IO chassis containing ADCs and DACs,
AA chassis, master and slave timing modules. We hope to get in enough
equipment this week to start running the I/O and software. Once the
computer is up, we need to start testing the new Framebuilder
code to verify it can accept data from both the existing reflected memory
network and the new Myrinet network.
- Bob,
Ben, Rolf, and Riccardo are working on the
cabling, ethernet, and fiber optic runs required
for the DC readout digital controls in rack 1X5.
- Rich
has made significant progress on the Piezo
Driver unit for the DC readout experiment. He anticipates being mostly
finished with the PCB layout by tomorrow. The bill of materials is
complete, and all the parts can be obtained on short turn around
(overnight) from Digikey.
- Bob
has been ordering and collecting the supplies that we need for venting.
- Go
used the video output of the existing spectrum analyzer HP8591E to
noise-lock the squeeze angle. About 2.5dB - 3dB of squeezing was observed
at 900kHz.
- Go
is working on realignment of his squeezer optics and optimizing the OPO
temperature. He also replaced the PPKTP crystal with a new one coated by Tafelmaier. After some effort, he got back to a
parametric gain of 3.
Lab Infrastructure, Bake Lab
- Although
the RGA display did not survive the power glitch of Sept 1st, both the RGA
and its logger did survive. Thus we continue to have RGA spectra logged to
disk. We'll continue in this way until after the vent, then
decide on whether to replace the RGA with the SRS one.
- Steve mopped the IFO hall with Dursban
ant poison in preparation for the vent.
Thermal Noise Interferometer (Black)
Significant progress has been made on the ring-damping
project. Greg has completed the circuit to drive the inductive heater, and with
no mirror in place, it heats up the copper rings nicely.
Greg and Akira are opening the chamber to
remove SAC's output mirror, in preparation for
installing the monolithic rings on it.
No report.
CIT Science Group (Lazzarini)
Data Analysis
Mendell:
The final review of the StackSlide S4 results
presented at the August 2006 LSC meeting is scheduled for tomorrow. One issue
mentioned last week was the jog seen in the S4 L1 noise spectrum above the
second harmonic of the violin modes. This was resolved by Mike Landry as a
feature of V3 calibration curve, which does not occur in the final V4
calibration used by StackSlide. Also, a bi-weekly telecon with the Australian National University LSC members
working with the pulsar group (during a time that is not the middle of the
night in Australia)
on searches targeted at isolated neutron stars seen only in x-rays was started
this week.
Yakushin:
1) Running the latest version of the coherent waveburst
on LIGO and LIGO-GEO S4 data to generate the final set of triggers for the
paper comparing incoherent and coherent waveburst
pipelines on S4 LIGO-GEO and LIGO data.
2) Preparing a presentation about LDAS for tomorrow's visit of a group of
CCT LSU students.
Grid research (Blackburn)
TCLGLOBUS
Collaborating with Mary Lei to resolve the issue with LDAS managerAPI
using 45% CPU when using Globus socket. I've been using GDB to
step through each Globus call using TclGlobus unit test.
We're still comparing systems calls when using Globus and
non-Globus within LDAS managerAPI.
Creating matrix for running TclGlobus unit tests
with the following
platforms:
- GT-3.2.1,
GT-4.0.1 and GT-4.0.2
- 32-bit
Linux and Solaris
- 64-bit
Linux and Solaris
OPENSCIENCEGRID:
Worked with David Meyers to try running hipe workflow on one OSG site, OSG_LIGO_PSU.
- Completed
the 1st partition after cleaning bad segments.
- Still
at the 2nd partition and it has been failing 3 times over the past few
days because of data transfer error.
Switching to chain mode from bundle mode to isolate the problem.
Per Kent
and David's suggestions, I'm breaking down the original segment list into 8 sub-segments and
will run 8 separate workflows at OSG
production sites in parallel mode to clean up bad segments from HIPE workflow and to complete HIPE
workflow
OSG - ITB Test bed maintenance: Applied revision to security patch to Globus 4.0.2 released by the VDT to fix the restore script
broken in the intial
release of the security patch which was applied to LIGO-CIT-ITB.
Configured a validation test node for a validation test bed and installed host
certificate for use as an OSG resource.
Development: Worked with Terrence Martin at UCSD on a wrapper script method to support NFS-Lite and the use of RemoteInitialDir in Condor-G.
Determined that the security patch applied to LIGO-CIT-ITB damaged the $OSG env vars.
Provided documtation to Michael Samidi on configuring chain workflows in VDS and executing LIGO
jobs on OSG ATLAS sites.
Attended VDT, ITB and VDS telecoms. Attended a
first telecom of the
Validation Test Bed working group on scope, methodology and resources for project.
xecuted 928 of 946 DAG
nodes on NERSC production resource for
the first time.
Laboratory Computing (Stuart)
LDAS Software Systems (Maros)
All code has been compiled for both Solaris 10 and Fedora Core 4 running on
the 64-bit Opteron platforms. Not all of the unit
tests are passing.
Testing has revealed that it is the result of using gcc
4.1.1 instead of gcc 4.0.3. As part of getting the
code compiled for Solaris 10 on the Opteron, DB2 was
installed on the system. The documentation for installing DB2 has been extended
to include installation instructions for both Solaris 10 and Fedora Core 4
running on Opteron hardware.
System testing of LDAS was done using version 1.8.298. Some of the
regression tests continue to fail as well as lsync.
The regression tests are being modified to use username/password authentication
as the install user does not have a globus
certificate.
Examination of excessive CPU utilization in the manager indicates the
possibility that the change in behavior is the result of recent TCL changes.
These changes are being reverted.
LDAS System Administration (Anderson)
Caltech
(Dan Kozak)
- Released
some of Duncan's
files in CIT /home.
- Moved
Vladmir's SFTs
(sft-1800_v1_C02_Hann) to /archive/frames, freeing up ~700GB in /home.
- Sent
the test 3510 with 15k drives back to Sun.
- Worked
on eliminating the last "duplicate" tape at LLO, LL1163 (rearchived all it's files and
relabeled it).
- Got
my dual monitor configuration set up.
- Fixed
stuck staging at LLO (was preventing LLO->LHO LDR transfers).
- Assisted
with ldas-cit NFS problem.
- More
work on /home disk usage plots...still not fully automated, but getting
there.
- Identified
LHO tapes for shelf storage.
- Restarted
RLS after Murali's big query crashed it.
(Phil Ehrens)
- Attempted
to upgrade two SunBlade 1500 machines, deimos and sadan, from Solaris 9 to Solaris 10u2. Upgrade path failed in both cases after
disk partitioning step. I failed to ask whether there was local data on sadan and accidentally destroyed data on the local
/usr1 partition. Fortunately there
was a backup copy of this data on another machine and Larry Wallace was able
to restore the data.
- Updated
Solaris 10 Apache documentation to include perl
one-liners for updating the log and config file
locations, and for semi-automated addition of the required LoadModule lines. This was done as part of the
preparation for switching to the Solaris bundled Apache on ldas-sw. The Apache setup on ldas-sw
is now ready for testing and final debug.
- Documented
procedure for creating a cvs repository with
local group access control and remote ssh access both simultaneously supported. The
critical step in doing this is to understand that the login shell used to
setup the cvs environment will not have the
proper group permissions for testing the setup, so calls to cvs made locally from the setup login shell will need
to be run under "sg" to set the
primary group to cvs. This primary group
requirement does not pertain to subsequent logins locally or via ssh.
- Provided
Larry Wallace with a copy of shasumcheck.tcl to
be shown to campus ITS for review as a possible campus-wide lightweight
replacement/supplement for tripwire.
The version as provided is not highly secure, but is easy to
understand. The script can be made highly secure via chroot,
and can be hardened somewhat by running it as a daemon instead of via cron. The modifications required for hardening are
trivial.
- Extended
view of log_mon server on ldas-kickstart
to include all LDAS "tandem" development systems. This exposed a
bug when a machine does not see the 3ware cli
tool, which I have patched.
- Decommissioned
4 unneeded crt type
monitors.
- Installed
power strips in graduate student offices to make better use of available
circuits. Formerly all cubicle load was on a
single 20 amp circuit, and this was described by a campus electrician as a
potential fire hazard. The redistribution
of load was done according to the instructions of the campus electrician.
(Erik Espinoza)
- Enabled
irqbalance on cluster.
- Sent
dagman logs from a duplicate dagman
instance to condor team.
- Assisted
Eirini w/ ssh
X forwarding issue on FC5.
- Submitted
RMA for CPU of node that was returned from SuperMicro.
- Reported
issue w/ 'condor_history -backwards' w/ quill.
- Contacted
Sean RE: 6 WD2500 HD's.
- Fixed
minor bug in sendmail config
@ ldas-cit.
- Showed
Mike Pedraza our FC4 x86_64 configuration on Hiro's machine.
- Made
Condor Changes:
-
Started 2nd schedd on
ldas-pcdev1 for Dedicated Scheduler Jobs
-
Configured nodes to use ldas-pcdev1 for Dedicated
Scheduler jobs
-
Enabled D_FULLDEBUG on schedd
for Condor troubleshooting
-
Raised PID Collision Retry to 1000
- Replaced
Memory w/ Dual Rank Kingston/Micron:
-
node38
-
node132
-
node181
-
node328
- Moved
non-MCE memory to diff nodes:
-
node38/CPU2
-> node10/CPU2
-
node132/CPU0
-> node232/CPU0
-
node181/CPU2
-> node256/CPU2
-
RMA
Ram -> node293/CPU0
- Moved
Possible Good from high MCE nodes (prior to replacement w/ Single Rank
Samsung install)
-
node159/CPU0 -> node299/CPU0
-
node53/CPU2 & node68/CPU2 -> node159 (removed
Single Rank)
-
node133/CPU2 & node159/CPU0 -> node271 (removed
Single Rank)
- node128 crash on Sept 13, 2006.
(Stuart Anderson)
- Re-installed
LDG at CIT and mirrored to other clusters to pick up:
-
latest GT security patches.
-
LSC certificate script updates.
-
New UK
e-Science Certificate Authority certificate so our UK colleagues can login to the
clusters.
- Working
with Condor development team on several Condor stability issues.
- Identified
problem with user code crashing ldas-grid@CIT by
using all available memory and the author fixed the code.
- Tracked
down problem with new user code saturating NFS services from ldas-cit and solved by increasing the number of NFSD
threads.
- Received
evaluation temperature probes from ServerTechnologies
to attach to rack PDU's.
- Worked
out a memory swap plan with Erik to further reduce the number of corrected
ECC MCE events.
Livingston
(Igor Yakushin)
- Configured
automount of node's /usr1 and ntp on the test segment database server;
- Using
L3 frames on the nodes, published the corresponding segments on the test
segment database;
- Tracked
down a problem with clearwater not being able to
insert segments into ldas' segment database;
quite unexpectedly to everybody it turned out that clearwater
is visible on GC network with its CDS 10.100.0.155 address; the same
problem prevented lloscript from accessing data
in /archive/frames; firewall rules have been modified to fix that;
- On
Sunday segment replication to LLO (but not from LLO) stopped; restarting
segment replication at LHO fixed LLO's problem;
most likely replication was broken during Sunday's network outages
(although typically it is robust against such events and restarts automatically);
- The
tape cabinet arrived.
(Dwayne Giardina)
- Ejected
tapes for shipment to CIT, imported and labeled
replacements.
- Worked
with Dan to resolve another duplicate tape being reported by SAM-QFS.
- Another
email flood released by LDAS due to scripts started by cron
being terminated before the cronjob itself on
nodes. I found a possible solution
for this, but have not yet implemented it 100%. Still looking at consequences and other
possibilities.
- Changed
symlink for ldg to
complete the upgrade from 4.0 to 4.1.0.
- Verified
FQDN in /etc/hosts for ldas(gateway) with the internal IP on nodes. node1 had
different entry than nodes 2-210, I presume from someone's testing?, so I
have not changed it back.
- Changes
to cluster mon app so
that only one instance can run.
- Uninstall
of dovecot on ldas-pcdev1 to eliminate a cert-check error email.
Hanford
(Greg Mendell)
- A
local HVAC contractor performed routine maintenance on the LDAS Liebert air conditioners at LHO on Tuesday. This
included changing the belts and filters, recharging refrigerant as needed,
checking the electrical systems, and cleaning the coils. The 3-pole
contractors for the humidifier were burned out on the 10 ton unit and
looked ready to fail on the 22 ton unit, and were replaced on both.
(Ben Johnson)
- Partial
cluster shutdown, reboot on Tuesday due to periodic maintenance both AC
units.
- Copied
vast majority of L3 and L4 data to the node disks. ~4TB freed on /archive
when L3 data was released from disks (L4 was not marked release -n to
begin with).
- Get
data flowing from LLO->LHO again. Problem was
an acl entry in the RLS server's config file (due to LLO host cert update the previous
week).
- Created
and pass on base IPF config to CIT admins.
- Fixed
/etc/hosts at LHO and MIT to map ldas.[GC domain] to gateway's internal IP address.
- Republished
more h(t) data due to bad md5sums.
- Assisted
Igor with IPF setup at LLO.
General Computing (Wallace)
MIT
(Fred)
- Getting
acquainted with environment, poking around.
- Met
with MIT Facilities etal. re:
new LIGO offices. Some items: offices in NW22 on same subnet as basement ( cluster ) NW17? 1 Gb
backbone & uplink for new offices ?Upgrade
NW17 uplink to 1G? Data transfer
issues between NW22 and NW17; our IS&T provide vlan
or circuit? Possible sign-off on plans next week.
- Backups.
Activated 2 cpu opteron
with 1Tb ( 4 X500 ) sata
( 2 80GB raid 0 scsi for OS) as GC backup server
(Fedora 4).
- Looking
at aoe (ata over
Ethernet) as part of backup backing store for GC. Tested using above box. Mounted from
Fedora to a solaris 9 box. Speed
seem very good so far.
- GC
AIT tape backups;
resurrected Ultra 10 for crash/burn.
- Compiled
Dovecot, testing on above crash/burn. Will be offering IMAP.
- Met
with Erik Katsavounidis & LDAS people here.
Gravity & Lancelot disks full; one pc raid in cluster is offline. Need
additional storage for L2 data; will provide 500GB until pc raid issue
resolved. Backing up some ½ TB right now.
- Some
miscellaneous pc/linux tasks: additional ram,
set up fedora, tweak xp laptop.
Livingston
(Dwayne)
- ordered a couple wireless mouse(s)/mice?? for laptop
users
- FC5
install with MySQL server for Shannon
to use. Finally sorted this out
after numerous hardware issues.
- user had video problems when trying to use monitor our
projector with her laptop. still trying to
straighten this out.
- another email flood released by LDAS due to scripts
started by cron being terminated before the cronjob itself on nodes. I found a possible solution for this,
but have not yet implemented it 100%.
Still looking at consequences and other possibilities.
- -
installed printer for a couple users
- continued
training our spam filter
- more housekeeping, roundup of old PCs and various
parts, etc.
- other
usual user requests and support
- rode shotgun with operator in search of logging
activity in the woods between beam tubes.
(Shannon)
- Tuesday
we took the first steps in getting the WAN connection between LLO/LSU/LONI
reconfigured. We now have two
logical pipes running over one physical pipe which will allow us to run
with our legacy LSU allocated IPs and also our
new ARIN allocated, multi-homed IPs. The next step will be initiating a BGP
session with LONI (or LSU, the details are still being worked out) and
advertising the IPs over that link.
- Made
some progress in getting SoA for the ligo-la subdomain, in large
part thanks to Larry speaking in person to folks on campus. I need to get a server in place now to
accommodate our having SoA. After that, we will work to get control
of the subdomain to make our transition to new IPs easier.
- Working
on ordering some fiber to install between the Communications room,
computer users room, and the MSR.
This will provide us with the ability of installing a jumper rather
than crawling under the floor anytime a change is made. I am also installing 10 gig capable fiber so that when the time comes, we are ready.
- More
planning issues with LSU. There was
a meeting on site Wednesday to discuss the timing of our move off of LSU's IP addresses.
I think LSU understands the situation at this time and some of the
pressure will ease up. Lots of
discussion over the last two weeks concerning this...
- Working
on more long term network planning with the new allocation. Laying out the IP subnets, etc. Have to start dividing up the space now
that it is live and I need to start allocating it.
- Received
a catalog for fiber video equipment for the grand opening of the outreach
center. Evaluating and selecting
the needed equipment.
Hanford
(Christine)
- Finally
was able to update glibc and nscd
to the correct version to work with NIS+. The Fedora C4 box is now a NIS+ client and has
all the appropriate ldas and GC filesystems mounted.
The only thing that didn't work was the lscsoft
update. Ben is helping me with
that. I now have to work with Dave
and the Operators to find a good location for the box in the Control
Room. This box will be used by the
Operators and SciMon for Qscans,
gridSSH and other data analysis tools.
- I
requested comments from PNNL, ESnet and Amerion on the requests Fred has received for LIGO to
provide network access to two other science groups on Rattlesnake mountain. ESnet and Amerion have no
objections, except that LIGO will be solely responsible for all traffic
and any problems that may occur.
PNNL is planning a node of the NorthWest GigaPop (NWGP) in Richland that would allow education,
science, medical, etc. institutions in the Tri-Cities to peer over this
node. PNNL is going to write up a
proposal detailing how LIGO and the Rattlesnake mountain groups would be
able to use the NWGP node. PNNL has
asked that LIGO hold off for now on connecting these groups to our
network.
- Worked
with the Cisco engineer to configure the new router I need to do BGP
peering and GigE bandwidth. I should have the first quotes by the
end of next week.
- Finished
the LHO GC Cybersecurity Vulnerability
report. Sent encrypted to Larry.
- I
updated my PGP key as my old one didn't work anymore.
- Set
up a computer for a new hire. Set
up user/email accounts for her.
- Purchased
a new laptop for another full time Advanced LIGO contractor.
CIT
(Veronica)
- LIGO: Continued work on processing of the SciMon bootcamp videos. This turned into a more involved project
than appeared at the start; the compressing s/w timeline was off by 50% so
that the playback was distorted. I
reloaded the s/w but it didn't fix the problem. I then installed patches and the
compression was back to normal.
There was also a server issue when the files would play back in
situ but a connection call using a ram file and rtsp
would be refused by the server. The
streaming of earlier files was not affected; still something to look
into. After some troubleshooting, I
set it up without a ram file and over http, which resolved the issue. Working on a page for the upcoming NSF
review. This is now the high priority item. Work on the new LIGO web page
will continue when this is done.
Continuing work on the LAAC website, installed/configured a hit
counter, working on the database updates.
LIGO website updates. User
support (Julie, Jay). Prepared a
high-resolution image for an NSF publication.
- LSC: Updates of the database of the technical
papers, website updates.
- Project
Science: Website updates.
(Mike)
- Working
with File Hold engineers and tech support on finishing up the most recent
revision of their software for the LIGO project. We are now testing this
software on our servers here at Caltech. This is an on going project.
- Did
some research on upgrading Primavera software from 3.1 to 5.0. It looks like I will be able to run both versions
of this software on the same server.
- (node1)
Loaded a new NIS+
fedora 32bit core 4 workstation for Hiro. The
32bit did not work for him. I'm re-loading this as a 64bit OS.
- (node2)
Tried loading Fedora core 5 64bit version but came up with multiple hard-
ware errors. I ended up having to load core 4. This has been completed and
I have swapped out Hiro with this unit. Eric
Espinoza pointed me where the updated software is for these types of
builds. Plus he took care of some configuration issues I was having.
- Continued
work on Spam Filters.
- Other
misc. user support, sysadmin tasks, plus
additional work in B/A server room.
(Christian)
- Setup
HP printer/scanner on the 3flr W/B and Wilson House with scan to email options.
- Re-imaged
two laptops that were returned to the loaner pull this week.
- 3flr
W/B - Replaced toner cartridges on HP 5500 printer.
- Called
Dell support to have my laptop replaced after the motherboard died for the third time.
- Worked
on the Spam Filters with Mike and Larry.
- Worked
with Veronica a little on troubleshooting a problem with the video tape
conversion.
- Minor
tweaks on the unit in the display case.
- Other
misc.: Continued onsite software/phone support
(Bruce)
-Ilog maintenance
(Larry)
- Still
working procurement items. Mostly a number of small items that need to be
cleared up before the end of the fiscal year. Made a number of quick purchases for
different people needing things ASAP.
Resolving some of the P-card issues that have come up. Mostly,
getting corrected documentation.
- Spent
a good deal of time restoring files for different people. On one case the tape(s) will not restore
on anything other than solaris8. Tried a number of workarounds some of
which partially worked but finally wound up installing the tape drive on a
solaris8 unit to get the files extracted.
- Worked
a lot with the DCC setting up the new DCC program. We are now in the
preliminary testing of the s/w installation on the local servers.
- Assisted
Mike with a couple of setups for the E2E group. Moved one of their servers, people kept
shutting it off without checking first.
Also, spent time tracking down why one of their sandboxes had been
shutdown. Discovered, it was accidentally shutdown.
- Assisted
in a number of equipment moves.
- Made
some changes in hardware and setup of the network in the backhouse at WH.
- Tested
the new projector. It does work well and ordered a couple more. It is quieter and will work well for
meetings.
- Continual
work with user requests. Still
doing the checkout for students and visitors.
- Work
with the mail services continue. Some of the services had to be restarted
because of a spam storm and DOS attack on the unit over the weekend. A number of misc. items such as tracking
down messages for people also took place.
Worked the spam filters along with others in the group.
Mail Statistics for Sep 07-13, 06
|
Mail Statistics
|
09/14/2006
|
|
Rejected Messages
|
37,330
|
|
Virus Messages
|
1,269
|
|
Accepted Messages
|
24,423
|
|
Total Messages
|
61,753
|
Advanced
LIGO and Supporting R&D (Shoemaker)
Modeling and Simulation (Hiro Yamamoto)
e2e weekly meeting
On September 13, the discussion about the triple suspension model with
reaction force output continued. Mark
explained the upgrade of his model and showed some results of the transfer
function from suspension point motion to back reaction force. Sany showed his
result - Mark's model implemented in e2e - which is consistent with Mark's
original calculation using Mathematica. Sany also showed the
transfer function of HAM-SAS model calculated using e2e setup, and it was
confirmed to be correct by Valerio. Valerio will
send the latest version of HAS-SAS model (v5) to Sany,
and Sany will be ready to simulate the compound
system, HAM-SAS and triple suspension with back reaction effect. After that, Sany and
HAM-SAS team will develop control systems around the e2e setup to study the
effect of the back reaction. The
materials discussed in this meeting are available in www.ligo.caltech.edu/~e2e/ME2ET/060913/.
AdvLIGO LSC/ASC design using FP arm model with
quad suspension (Osamu, Hiro)
AdLIGO will chose the g1 = g2 = -.926 (ROC =
2076m) configuration based on Daniel's (static) model, which showed that this
was more stable than a positive g solution. We started investigating that it
this really true when the dynamics are included? We changed the ITM/ETM ROCs to make the positive g solution (ROC = 54.4km). As a
result of simulation positive g-factor seems less stable. Essentially, less
stability with positive g-factor comes from less phase margin at UGF.
Opt-mechanical (suspension) TF has changed into what has additional slope and
additional phase delay because of a sign flipped spring constant. Therefore we
recommend to use default negative g-factor.
Static IFO simulation (Hiro)
As per request / concern by Bill, more systematic study of the surface noise
effect started.
Fast simulation of Dual Recycled Michelson Cavity (Hiro,
Keiko)
For the FP field calculation, Ecav (intra cavity
field leaving ITM) can be written as
Ecav(
t_now ) = R(t_now) * Ecav (t_now - 2 tau ) + t_ITM E0(t_now)
where R(t_now) is a round
trip operator, including the mirror displacement and rotation, and t_ITM is the transmittance of ITM, and E0 is the input
field coming into ITM, and tau is cavity length /
speed of light.
Using this formula recursively,
Ecav( t_now ) = Rprod( t_now, N ) * Ecav( t_now -2 N tau ) + t_ITM ( sum(n=1~n) Rpod(t_now, n) E0(t_now-2 n tau ) + Eo(t_now)
Ecav and E0 are vectors represented by modal model
base and R and Rprod are matrxies.
This way, the field at t_now can be calculated using the field value at t_now - 2 tau N and summation of
external inputs. The calculation can be
sped up by replacing N folder products and summations of matrixes by a simple
form. This can be done by assuming all
field quantities are changing linear, like mirror motion = x0 + v0 * t or thetaX = thetaX0 + thetaV0 * t.
By expressing a mirror reflection matrix X as U^-1 X0 U where X0 is a
diagonal matrix, it is shown that Rprod(t_now, n) can be expressed in an
explicit form.
Next is the summation of Rprod(t_now -2 tau
n) * E0(t_now - 2 tau n),
which cannot be explicit carried out. This approximation formula is dependent
of the linear and angular velocity.
Mechanical Simulation for advanced LIGO (Sany and
SLU team)
(Yoshida)
Continued e2e modeling of AdvLIGO
Input MC triple suspension and HAM-SAS seismic isolation. Using Mark Barton?s most recent version of
the state space matrix, we recomputed the back reaction exerted by the triple pendulum
on the structure. The resultant reaction force in the direction normal to the
mirror surface (X direction) seems reasonable. (See below for more details.) At this point, the triple pendulum is freely
hanging. These reaction force/torque outputs will be fed back to our HAM-SAS
model (based on Valerio Boshci’s
Simlink model) to simulate the effect of back
reaction to the HAM table by the triple suspension.
By including the state space matrix generated by Valerio
Boschi, we made an e2e model of HAM-SAS horizontal
dynamics (Inverted Pendulum model). By injecting white noise as ground X and
Yaw inputs, we computed the ground to Optical table/Spring Box X/Yaw
transmissibility. The resultant power spectra seem to agree with Valerio?s results based on his Simlink model. We are currently working on the vertical
model of HAM-SAS.
(Kinchen)
I used the E2E modeler to simulate back reactions (by the triple suspension
to HAM table) by injecting white noise to suspension point position
inputs. The white noise was used to create disturbance on and about each
DOF one at a time. Each disturbance generated a set of six force and
torque reactions simultaneously. The Fx (Force in x direction or normal to the mirror
surface) reaction to disturbance to suspension x-axis was graphed and compared
with a plot produced by Mark Barton. The purpose of this comparison was
to ensure accurate conversion of the Mark Barton's latest state space matrix
from its native Mathematica format to that of
E2E. The comparisons verified that our conversion is correct
ALFI : e2e front end (Melody)
Started implementing the dialog for the new User Defined
Primitive.
Refactoring ALFI code to replace deprecated java 1.4 methods.
Seismic Isolation
BSC Seismic Isolation Assembly and Test
While assembling the actuators we had two large actuators and 1 small
actuator fail. We were able to use the large actuator prototype found at
Caltech to replace one. The other large actuator we found a screw had contacted
the winding and was easily repaired. The small actuator had a break in the
connection to the winding. Myron removed the potting epoxy and resoldered the joint. We are now waiting for epoxy to fill
back in.
Brian Lantz and I have been rewriting the HAM single stage design
requirements. A package is being prepared to send to design firms to quote the
completion of the design.
From: "Joseph A.
Giaime" jgiaime@ligo.phys.lsu.edu
Agenda for the weekly SEI telecom
Friday, Sept 1, 2:00 pm Eastern, 1:00 pm Central,
11:00 am Pacific time
HAM status (Joe summarizing)
- Corwin told to write up the design work as is by
mid next week. Then we can discuss the issue of improvements to the
GS-13 mount.
BSC SEI status
- New
STS-2 can received from Nor-Cal, will be used to test fit.
- Two
corners of actuators installed (i.e., 8 actuators). Tooling not
setting the distance very well in the gap direction, but very well in the
other two directions. 0.03 gap (minimum) remains, which is OK.
- Stage
2 released; on of its locators now jammed for unknown reason.
- Three
damaged actuators (two large, one small). The potting material is
used to strain relieve the wire, and this material does not stick to teflon. We are in touch
with the vender to make a new batch with in a lug to relieve strain.
- Also,
one of the damaged actuators has a short between the coil and bobbin.
- Some
of the damage resulted from rough shipping/handling between two LIGO labs,
and some was due to poor design.
- Pod
assembly underway; some fasteners were the wrong size and new ones are
ordered.
- We
need to line up the cleaning company well in advance of shipping to them.
From: Ben Abbott
abbott_b@ligo.caltech.edu
I just finished changing the schematics for the HAM-SAS system to
accommodate the test electronics. Jay is using the new drawings to order
the cables that will be needed for installation.
I've started working on the Guralp Interface
Chassis.
I've been tasked with re-doing the GS-13 cable for ISI. I await a pinout drawing, and I will start.
From: Dennis Coyne coyne@ligo.caltech.edu
Minutes 13 Sep 2006
HAM-SAS Weekly Meeting
Virginio, Dave O., Ric, Dennis, Chiara, Valerio, Ben
Fabrication
at G&M
starting to load temporary
optical bench with 1 metric ton today (1042kg by adding vertical GAS filter
loads) -- needs to be balanced -- this is the spring box without the IPs -- will pull sideways & let oscillate to measure
the lateral GAS filter
Ric leaves in 2 days
Gianini & Ric reviewed drawings
for LVDT monitor posts
tomorrow (a Lucca city holiday) will try
vertical IP length adjustment mechanism & try horizontal LVDT assembly
vertical LVDT assembly to be completed next week by Chiara & Alberto
Ric needs to define horizontal springs from table to
stepper motor -- need about 1 N at each of the 4 points to balance the IPs
At 125 mHz
IPs seems to become unstable -- IP lengths were
measured and found to be as much as ~0.5 mm different -- cause was improper
machining (set tight tolerance on wrong dimension; revised drawing makes
relevant/tight dimension clear) of the IP leg feet -- new parts machined --
with better IP length control, expect that instability will disappear
re-welded shelves on columns around IPs
due to cleanliness (vacuum compatibility) concerns
estimate disassembly by end of next week & then into
cleaning
almost all oven parts are here, except sheet metal expected
this week -- should be completed next week
G&M plans to spend a lot
of time watching and QA'ing Soldi's work on cleaning
the parts
duration of the cleaning is a bit unknown -- hoping for a
month, plus a month for re-assembly and shipping (or arrival at LASTI mid-Nov)
-- there is some concern that cleaning/baking could take 2 months
Electronics
Valerio measures LVDT driver bds
have 10x higher noise -- to be investigated further
Ben has sent out a system
schematic for review
Ben concerned that we need
more LVDT drivers and 4 + 1 spare actuator coil drivers and we may not have
this quantity on hand - Virginio will contact Francesconi to obtain more actuator coil drivers
Simulation
Valerio is working with Sany &
E2E group to create a coupled state-space model (Valerio's
& Virginio's HAM-SAS Maple model exported as a
state-space model coupled to Mark Barton's Mathematica
model triple model exported as a state-space model)
Cassi has not yet succeeded in getting the finite element
model of the triple to match experimental results -- Dennis has suggested a few
corrections to parameters in her model which have not yet been tried (the
intent is to couple this triple model to Dennis' HAM-SAS finite element model
and then export as a state-space model for controls analysis in Matlab)
LASTI
good news: Laurent intends to stay at LASTI for another 6
months
long term stays at LASTI -- there may be an apartment
available (~$1K/month)
should coordinate
accommodation needs to Marie Woods -- Dave will ask Marie Woods to investigate
options, such as committing to one apartment for Alberto for the duration of
the HAM-SAS testing plus another for transient visitors
LASTI staff are attempting to
install the scissors tables, but they are in 'tough shape' -- some spring cups
have galled, difficult to adjust height -- not clear how to lock into a
position -- will contact the InL SEI experts at LHO
&/or LLO
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
Working here at Caltech on AOS pick off suspension and ETM
telescope suspension. Dennis, Calum & I
had an extensive discussion about the OMC yesterday. Dennis will be sending a
long memo about this today. We covered the labor available, the tasks, the best
division of tasks, the schedule for the tasks and a few technical items. Calum talked to Norna this
morning to fill her in. I will attend the OMC meeting tomorrow, if my flight
permits, during my layover at DFW airport.
Working
with Justin and Ian on blade material for them to use for a fabrication study. Working with them to determine what more information
they need from the AOS group to finish up the ITM/CP and ETM suspensions. We
hope to schedule a meeting in the coming week to address these outstanding
issues. Working with Caroline Cantley and Helena on
ear and bonding issues.
Bob Taylor hopes to ship out short initial LIGO osems
to Conor Mow-Lowry tomorrow.
From: Ken Mailand kmailand@ligo.caltech.edu
I'm using information from Ian, and working on a lower quad installation arm
shop drawings. The CES shop has completed more than half the parts for the
basic arm.
I'm have completed the cavity beam dumps and other
parts for Mike Smith. The fixture lift table for LASTI has returned from chrome
plate, and is at CES for re-assembly.
Core Optics
From: Bill Kells kells@ligo.caltech.edu
I've finished my full review and commentary on the AdL
polishing specifications. Transmitted to Garilynn.
We have new OTF measurements of superpolished
mirror scatter (loss). These are some
interesting new results on the same surface scanned with different dirameter probe beams. This is important for properly
hunting for and interpreting sporatic
"point" scattering defects. There seem now (preliminarily) to be some
puzzling systematics (which may impact previous
conclusions). More to come!
I continue to study the PI phenomenon. The basic existent theory has several
imporant (and not obviously valid) approximations. I
am trying to conclusively fathom these. One
Approx. is that the acoustic mode frequency is
absolutely stable. Of course, this is hardly so (the reason it is so hard to
measure a TM internal reso. Q by simple SA observation !). These resonances wander around (Thermal,
stress, etc) by many line widths. How does this effect the PI
? Does it merely "follow" the wandering and continue to grow
(at the ideal non-wandering) rate?
Another question: now "answered" is whether PI acousto
resonances in different TMs (say ITM and ETM pairs) conspire to reduce the PI
threshold (from what it would be for just one TM active: the original simple
case analyzed)? The answer is no, unless the two mode frequencies are closer
than ~the acousto line width (very unlikely
!~).
From: GariLynn Billingsley
<Billingsley_G@ligo.caltech.edu>
From: Helena Armandula ahelena@ligo.caltech.edu
Advanced LIGO Coatings
I was contacted, at one time or another, by the coating vendors in reference
to the RFI. Received and evaluated their
responses.
Ordered 3" dia x
0.100" thick substrates to support coating development.
First Contact test –
First Contact was applied to the surface of a 1"dia. mirror; the film
was removed one week later. Scattering measurements were taken before and after
the procedure.
From Liyuan Zhang's report:
The scattering test of First Contact on an 1"
mirror is finished. The result is very promising, not only there was no
evidence of scattering increase, but, some decrease was observed, probably due
to less high scattering (saturated) points; the film could have removed some
dust (or contamination) stuck on the surface. To make a solid conclusion, more
tests will be needed.
Advanced LIGO SUS
Researched some bonding agents to have a second option to Vacseal, however, Vacseal, having
been tested and deemed acceptable, remains the adhesive of choice for Advanced
LIGO SUS.
As a second option, Norland Optical Adhesive 88
will be tested. Is a low outgassing, Collected
Volatile Condensable Material (CVCM) <0.01% adhesive. It cures by UV light
and it is used on parts destined for space exploration, bonding of high tech
computer components and very sensitive instruments.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
A set of viewports and a heater jacket was shipped
to AEI (thanks to Rod Luna for organising the packing
and shipping) as they are assembling a reference cavity identical to that used
at the observatories. The vacuum chamber and ancillary equipment should
be fabricated by the end of the month.
Controls, Data systems
From: Rolf Bork rolf@ligo.caltech.edu
AdvLigo/LASTI
- Mohana and Rich have been working on the high current
coil driver for the ISI system. The prototype is able to supply the
current requirements for the coarse and fine actuator. We are
working on noise issues now.
- (Rich)
Received prototype boards that I designed for evaluation of the ASC
photo-diodes. Need to put together the test laser system. I am
evaluating a prototype system for mounting the diodes in a vacuum environment.
The prototype was supplied by Accuglass Inc.
- Seismic
(Ben)
-
I just finished changing the schematics for the HAM-SAS
system to accommodate the test electronics. Jay is using the new drawings
to order the cables that will be needed for installation.
-
I've started working on the Guralp
Interface Chassis.
-
I've been tasked with re-doing the GS-13 cable for
ISI. I await a pinout drawing, and I will
start.
- Ponderomotive Experiment: We will begin the controls
equipment installation the week of Sept. 25, with Alex and I installing
the rack mount equipment and getting the computer system on line. Jay will
follow up the next week to finish up and get the field cabling installed.
Other Laboratory R&D
From: John Miller <miller_j@ligo.caltech.edu>
John
Attempts to measure mirror tilts using an optical lever have been hampered
by electronic noise and beam jitter. We hope that by setting up an experiment
to measure tilts using lock in detection and triggered beam capture we can
mitigate these effects.
Yumei
continue simulating the leg and finding the Modes
we need.(flex joint s-shape and leg c-shape)
For additional information about this report, contact Stan Whitcomb or Phil Lindquist