Weekly Report for
Week Ending August 31, 2006
Past Weekly Reports
There
will be no LIGO Executive Committee meeting scheduled Monday, September 4, 2006 due to the
holiday. The next Executive Committee
Meeting will be scheduled Monday, September 11, 2006.
Special Announcements:
Weekly Report Highlights
There has been a lot of activity this week on preparing institutional
pre-proposals for NSF's program called Partnerships for International Research
and Education (PIRE.) Within the Directorate there was some discussion of
pulling together an all-LSC data analysis proposal to support integration with
Virgo, and several LSC institutions expressed interest in such a plan. In parallel, though, there are several
independent efforts to submit PIRE proposals.
After much discussion, it looks like the best way forward is to see
which of the independent proposals make it through the institutional selection
procedure (no institution can submit more than three PIRE proposals, and at
some institutions the competition is fierce.)
After that step, we will attempt to harmonize competing proposals to
best serve the needs of the LSC.
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
SITE TELECONFERENCE (Lindquist)
- A
site teleconference was scheduled Thursday, August 31, 2006. Issues discussed are covered below.
- There
are currently no open action items.
PROPERTY MANAGEMENT (Luna)
>
- Provided
assistance to the Detector Group (H. Armandula)
with shipping and the preparation of a Commercial Invoice for US Customs
Clearance of one 3"dia x 1/2" thick glass substrate to the
University of Western Australia (L. Ju). Account Number LIGO.OPT - 5.4 -
NSFLIGO.FY02ON.
- Reported
to NSF the projected Vehicle Cost Data on Government-Owned vehicles for
2006, 2007 and 2008.
- Assisted
the CDS group (R. Abbott) with shipping and the preparation of a loan
document for a Dynamic Signal Analyzer to Logic Plus Inc. in San Luis Obispo,
Ca. Account Number
LIGO.TEC-1.3-NSFLIGOFY02ON.
- Created
Property records for the Audio Precision Analyzer @ LHO.
- Provided
assistance to Mike Pedraza in shipping a package
to ASA computers. Account Number
LIGO.DAT-1.5.3-NSFLIGO.FY2ON.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
- Spent
most of the past week involved in review of the functionality requirements
for the new DCC document system from FileHold. Several "fix-its" were
identified and are in the process of being fixed by the development team
at FileHold.
- Spent
time working with Dennis, Rich and Todd on the Engineering needs with the
new system, identifying possible work flows and working current processes
into the new paradigm.
- Had
3 teleconferences with Ian at FileHold securing
answers raised during the review as well as getting input as to possible
solutions for issues arising.
- Began
to flesh out a deployment and training strategy for the new system.
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
FINANCIAL SYSTEMS (Funaro, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Issued
the order for the lasers for Hanford.
- Issued
the purchase order for Custom Metal works for the LIGO Livingston
Observatory.
- Working
on finishing up the change order for Kaufman.
- Made
arrangements for the return of equipment to Newark which will be upgraded to a
better system.
- Completed
change order #14 to Southern Enterprises and submitted to the vendor.
- Placed
purchase orders for goods to be delivered to Caltech and the sites. Issued
the order for the pulse generator and the spectrum analyzer.
- Completed
change order #3 to Eskew Dumez Ripple and submitted
to the vendor. Received the current Certificate of Insurance.
- Completed
change order #17 to Promec and submitted to the
vendor.
- Trained
a new user on placing orders and requisitions in TechMart.
- Researched
the status of purchase orders over 90 days and took care of changes on the
status. Closed out purchase orders.
- Placed
the purchase order for the print and website for teachers
resource.
>From: Florence Kaufman <fkaufman>
- Updated
the report for the Outreach Award to account for revised data on estimate
to complete.
- Assisted
Gina Salone with the analysis of Northrup invoices.
- Requested
correction of expenditure types for several purchases charged to
fabrication accounts that used the equipment expenditure type in error.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- The
inspection of the LLO SEC went well, with a very minor punch list
resulting. The only major item
regards the certification of the water pumps for the fire system to
accommodate the fact that LLO is not hooked up to city water.
- A
new drawing for the front lettering for the LLO SEC has been received from
the architect, and will be installed by a subcontractor for Cangelosi-Ward.
Determination of who pays for this additional work is pending.
- Deliveries
are beginning for the parts for the LLO SEC outdoor wall exhibit. The schedule shows five weeks for the
assembly and installation of this exhibit.
PROPOSALS and REPORTS (Lindquist)
The NSF has approv4ed our Annual Report for LIGO Operations. This clears the way for funding come October
1 as soon as the NSF gets the funds. Currently working on the budgets for FY 2007.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
- There
are no open change requests.
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- The
next Staffing Committee meeting is scheduled for October.
- The
minutes and action items from the August Staffing Committee meeting have
been posted on the SC web page.
- All
files for the Staffing Committee are up-to-date and posted on the SC web
page.
- Prepared
numerous appointment and reappointment memos for various Visitors, Post
Docs, and Term Staff.
- Processed time sheets and submitted to payroll.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
No report.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of S5 Activities at LIGO Hanford
Observatory (compiled by M. Landry)
Duty cycles for the last week were: H1
81 percent, H2 90 percent,
and ranges were typically ~14Mpc on H1 and ~7+Mpc on H2. However there
were notable problems with H1, due to glitching in
the PZTs associated with the input beam. Ranges
and duty cycle suffered from the glitching. The
problem was traced and then the PZT board was swapped
(more links on this investigation below). The glitches appear to have
vanished but we're watching to see if this holds long term.
Some highlights from the LHO elog are bulleted
below:
- There
were no
lock losses despite 250 people on site for a public event with the TriCity Astronomy Club. Weekend sensitivity to seismicity was likely due to the transport
of a sub reactor.
- links
to standard summaries: Tuesday
maintenance, range
& duty cycle, IFO maintenance
- H1
suffered mystery
lock losses, leading to the observation of twitching
of the MC as of over a week ago. This was later tracked to the PZT.
- truck
events were studied, including the effect at 6Hz on H1 and associated upconversion into the gravity wave band
- violin
RMS was tracked
over Jun/Aug: we still have the ~factor of two smaller lines than
expected, and there is variation from line to line, but given lines are
stable over this time-frame
- PulsarMon showed occasional
jumps in the the time-to-reach the Crab spindown; this was seemingly shown
to be a wandering line, source unidentified, although similar events have
been previously attributed to pumps/chillers.
LIGO Livingston Observatory
(LLO) and Interferometer Operations (Zucker)
No report.
Optical and Mechanical Systems
(Coyne)
See Advanced LIGO
Most of the group’s efforts are reported under the Advanced LIGO
project.
Dennis Coyne and Rich Abbott have continued to help evaluate the new DCC FileHold application customized for LIGO.
- The
most significant remaining issue to be resolved with FileHold
is the generation of an appropriate URL to a document. There may be some
fundamental limitations to the FileHold
application (based on security concerns we’re told) that make the
URL link awkward. With the URL and
some other fixes/issues identified the balance of the application meets
functional requirements.
- We
are currently revising the file hierarchy, defining supporting source file
format/types, revising the technical & engineering document types.
- Next we’ll (1) think through some work flow
process scenarios (for possible implementation after the transition to the
new DCC application) and (2) develop a manual for engineering use of the
new DCC (i.e. guidelines, rules, good use/practice, policies).
Controls and Data Systems (Bork)
See Advanced
LIGO
40-Meter Interferometer (Weinstein)
IFO Commissioning, Electronics, Controls, Computers
- The
EPICS database for the new MC board had some problems; Ben fixed it, and
Sam checked out that all controls and readbacks
seem to work correctly.
IFO Modeling
- Monica
presented the status of her work on e2e and at the 40m, in a meeting with
her Virgo colleagues Patrice Hello and Fabien
Cavalier, who were visiting earlier this week. Her talk is here.
She is working on LIGO reports on her mirror velocity measurements and her
work on the MC WFS Guoy telescope and servo diagonalization. She returns to France
next week.
- Osamu
has been working with Kentaro on modeling of new
RF control schemes for AdLIGO, validating with Optickle, Finesse, Corbitt-code. He also did a study comparing
different arm cavity g-factors to reduce the severity of alignment
instabilities.
DC Detection and Vacuum Squeezing Development
- We
planned to vent for installation next Tuesday, but we're not ready with
the 2nd TT PZT. We got a spare one from LLO, but they want it back. We
await delivery of two TT PZTs from Piezo Jena. Word is, we'll
get one (the repaired one) sometime next week; so we'll postpone venting
until that is received and checked out.
- Rob
and Sam are assembling and aligning the in-vac
optical beamline on the clean bench. the only hitch was a missing mirror clip. Ben made one,
and Bob cleaned it (twice). They're now starting on the OMC assembly,
electronics, alignment.
- Status
of controls electronics for DC readout: Ben has completed an updated draft
of the system
wiring diagram. Computer, PCIX IO chassis, ADCs, DACs
and REFMEM are all in hand and under test by Rolf & Alex. AA and AI
boards are assembled and under test. QPD whitening board is stuffed and
Ben will test it soon; he'll use a new LIGO Rack Mount Chassis which will
be ordered soon. DC satellite box and in-vac
DCPD amp are in hand and in use. Rich is still working on the PZT driver
boards.
- Ben
changed to different opamps on the DCPD
amplifier board to get lower overall noise, did a functional test, and
updated the schematic.
- Ben
and Steve installed the DCPD amplifier board into the vacuum nipple,
filled it with krypton, and sealed it up. Rob will test it on the clean
bench in preparation for installation.
- The
new rev of the QPD Whitening board is stuffed now, and ready for testing.
Ben will write a test procedure, then it can be
tested in the back shop.
- Ben
cut the cans off two GAP2000 PDs that we can use
in the vacuum DCPD.
- Rich
chose, and ordered, some Kepco high voltage DC
power supplies for the PZT drivers for the OMC and TT mirrors.
- Steve
is preparing the lab for DC readout installation. He has cleaned out two
small electronics racks and cleared out the cabling; the racks are ready.
- Riccardo continues working on balanced PDs for the squeezing experiment. He assembled his
circuit on a breadboard and set up an optical system. He then measured the
relative QE of 12 PDs, (ranging from 82-87%, in
good agreement with expectations), and estimated the errors. He also
measured the angular dependence of the result, and found it to be roughly
flat out to 60degrees. His PCB design has gone an
iteration with Chris Wipf, and is ready
to be sent out to PCB express for fab. Ben will
help with that.
- Go
and Shally designed and built a spectrum
analyzer for the squeezing experiment. It is now completed and tested, now
being integrated into system, with help from Riccardo.
- Go
is now realigning the squeezer optics to reestablish squeezing with the
new spectrum analyzer.
- Go
is working on two papers describing the squeezing experiment.
Lab Infrastructure, Bake Lab
- Steve
checked that particle counts in the back clean room (where the DC readout beamline is being assembled) are near zero.
- Steve plans to add more fore-pump power behind the
main TP1 maglev turbopump to avoid overheating
during pumpdown. He received some vacuum hoses
to make these mods.
Thermal Noise Interferometer (Black)
No report.
LASTI (Ottaway)
HAM SAS
The first draft of the LASTI test plan was completed and will be circulated
on Monday for general comment from anyone who is interested. The test plan will
be circulated to those on AdvLIGO SUS and SEI email
lists. If anyone else is interested please contact Dave Ottaway
for a copy.
Quad Report
We have finished up working in the chamber and Lasti
is now under vacuum. The resistors and thermistors
for doing the thermal loading test of the suspension have been installed. There
are pictures and descriptions on the Lasti ilog, 8/30/06.
The "interference issue that we were experiencing on the reaction chain
has been cleared up, the cabling for the electro-static drive
were under tension. They have
been disconnected for the time being.
The main eddy-current damping has been reinstalled on the reaction chain.
The blade eddy-current damping on the upper intermediate mass has been
removed so that a comparison between the two chains (with and without blade
ECD) can be made.
ISI
We ran into some problems with the tooling that is designed to position the
actuator coil relative to the actuator magnet/body. It was only correctly
positioning the coil in 2 out of 3 dimensions.
Once we figured out a better procedure we proceeded and have installed 2
corners (8 actuators). We have released and rebalanced stage 2 and started the
modal testing.
We have found a design problem in the actuators that has resulted in 3
damaged actuators (2 large, 1 small) that is currently being evaluated. This involves how the actuator leads attach
to the coil windings.
CIT Science Group
(Lazzarini)
Data Analysis
Brown:
- Worked
on LIGO EMRI parameter estimation project
- Writing
and editing LIGO EMRI project paper
- Worked
on numerical relativity simulations
- Worked
on LISA supermassive black hole data challenge
- Helped
Lisa with some ringdown search issues
- Provided
segment database support for Igor
Chatterji:
- Prepared
glitch group report for 2006 Aug 24 - 27
http://ldas-jobs.ligo.caltech.edu/~shourov/reports/glitch/glitch_report-20060824-20060827/
- Prepared
glitch group summary for weekly S5 run call
http://ldas-jobs.ligo.caltech.edu/~shourov/reports/glitch/WeeklyDC_20060820-20060827/
- Continued
preparation for S5 Q Pipeline analysis.
Updating condor submission scripts to handle new Q Pipeline layout.
Dupuis:
- analyzing
data in a narrow frequency band around Crab pulsar with first 9 months of
S5 data
- investigating
distributed FFT algorithms for long data sets
- writing
code to calculate F-statistic using intermediate heterodyned time series
from the time-domain search
Mendell:
My data analysis work for the past week was to do a few calculations for the
pulsar group, comparing times Einstein@Home analyzed
the S4 data with the times hardware injections were running, and checking a few
equations. Once this is finished, I will return to work on the final draft of
the S4 PowerFlux, StackSlide,
and Hough paper.
Yakushin:
- Generated
S5 waveburst triggers with 5 second time step
for time shifts between LLO and LHO to be used for the final background extimate in the analysis of the first few months of S5
(up to April 2). The tuning of the thresholds is currently done using
3.125 second time step.
- Making
plots that show daily background rate for waveburst
triggers.
- Investigating
why some injections for SG70Q9 are not found.
- Presented
an LLO lunch talk about triggered and untriggered
burst search last Friday.
Grid Research (Blackburn)
Integration Testbed Activity
Determined that NFS-Lite configured at CIT_ITB_1
moves the startup directory specified in the Condor submit script from the InitialDir specified by the VDS planner to an unspecified
place in a subdirectory of /tmp. So NFS-Lite breaks
the locations specified by metadata locations specified by VORS (and GridCat). NFS-Lite is only installed at a few OSG sites at present.
Determined that site BNL's ITB site has $OSG_GRID mis-configured. Am working with the site administration on reconfiguration.
Assembled IP address, additional rack server, and ethernet
switch as components for a future validation test bed (VTB).
Validated two ITB pre-release installations of OSG 0.5.0.
with the 940 DAG node LIGO Workflow test.
Workflow Development Activities
With Michael Samidi's assistance, determined that
a small partitioned HIPE job can cleanup storage in the N - 2 partition, when
the Nth partition is executing. The latest hurdle is
there are 4 bad GW files which prevent the completion of partitioning workflow.
Tested VORS with vds-get-sites and determined more
testing will be needed.
Met with the VDS team in a weekly telecom and worked toward a plan for
generalizing partitioned HIPE cleanup.
TclGlobus
Resolved TclGlobus unit test failure on 64-bit
platform related to the callback script never gets evaluated inside Tcl interpreter. The
problem description as follows: Tcl_GetByteArrayObj() is taking int as one of the
parameters and TclGlobus is passing long to specify
the length of the actual buffer.
Encountered another problem when running TclGlobus FTP client unit test on 64-bit Solaris platform (sparc). There
is a race condition between two channel functions, control and data channel.
This issue is still under investigation.
This issue doesn't show up on 64-bit linux opteron.
Laboratory Computing (Anderson)
LDAS Software Systems (Maros)
Efforts continued with getting LDAS compiled 64bit
for Solaris 10 opteron and Fedora Core 4 opteron. The DB2 software for Fedora Core 4 opteron has been installed. All but one of the unit tests
have passed for Fedora Core 4 opteron. The one
failure is being investigated with the current speculation that it is a
rounding issue. For Solaris 10 opteron, all unit
tests have passed for the lib subdirectory. Build rules are still needed for tcl and tk as the configuration
macros supplied by the software authors claim it to be an unsupported platform.
To fix the LDAS account management software, the cntlmonAPI
ignores trailing garbage from the account management cgi
script. The source of the extra characters is still under investigation.
The diskcacheAPI now informs the manager of the diskcache's cache file name.
The ligolwAPI no longer generates a background
error of not finding cid var when an object arrives
after job cleanup.
The LDAS system tests were done using version 1.8.284 of the software. New failures this week are several regression
tests that complain about corrupted frames. The lsync
test continues to fail.
LDAS System Administration (Anderson)
Caltech
(Dan Kozak)
- Continued
to repack tapes at LLO.
- Moved
the first batch of tapes from the CIT silo into shelf storage. The data on the tapes is all from
engineering runs. Scanned the
barcodes of the tapes, but haven't yet worked with Ben's catalog script.
- Finished
checking the provenance of Xavi's h(t) frames.
- Had
Ben start writing .md5 files to /archive/meta at
LLO. This is now complete at all
locations.
- Ejected
L1 tapes at LHO for data that had been dual copied into the cluster. Used the /var/sam/tapeusage
(such as it is) script, which will eventually help sort out the Venn
diagram of what data is on what tapes.
- Copied
Keith Thorne's latest Burst-MDC files from the CIT cluster into
/archive/frames and made sure they were on tape.
- Sorted
out the RLS cert problem that caused LDR to stop scheduling files for
transfer from LHO to CIT.
(Phil Ehrens)
- Upgraded
Solaris to 10u2 on sunbuild, ldas-test,
dataserver-test, and ldas-dev.
All upgrades went without incident. Note that it is not necessary to
configure networking when doing an upgrade unless the upgrade script
specifically prompts for it, and in that case it will have the values
filled in auto-magically anyway.
- Ongoing
x509 certificate related tasks. Lots of host and service certs are expiring at this time, and I'm trying to get
a better understanding of the whys and wherefores of cert install
locations in the interest of reducing the number of known locations (just
down from 54 to 53!) to a tractable number.
- Converted
all apache servers on Solaris to used the bundled
Solaris version of Apache and the Solaris service management
facilities. The only problem has
been with ldas-cit, where the configuration of
the server is unusual. Work on ldas-cit is
ongoing.
- Further
development of rulesets and features for log_mon.tcl, which currently lacks only a robust
startup method before it can be distributed. Use of this tool at CIT has
been extended to cover all machines in the ldas-cit,
ldas-dev, and ldas-test
systems as well as the desktops on the 6th floor of Millkan
and a few machines that are not integrated into groups. The reports generated for the nearly 400
machines visible to the script have been reduced to a reasonably benign
flow without sacrificing visibility into any issues.
- Applied
for and received blessing from the DOE certificate management authority to
issue host and service certs for all domains
which have heretofore required the issuance of certs
related to LIGO data flow and analysis.
(Erik Espinoza)
- Configured
MRTG to track temperature of CIT
Data Center.
- Tested
returned node from SuperMicro with 6 diff ram
stick configurations.
- E-mail'd Christine Barker instructions for NIS+ on FC4.
- Testing
"expect" script to re-index tables in PostgreSQL
db for Quill.
- Responded
to Condor Crash @ CIT 8/29/2006 & 8/30/2006:
-
Cleaned up duplicate Rescue Dags.
-
Notified users via daswg.
- Sent
details of node329's mobo to ASA, requested RMA
for mobo.
- Spoke
with Sean@ASA about outstanding RMA's:
-
16 Sticks of Ram
-
6 HD's
- Spoke
with Bruce Allen about Einstein@Home
configuration, will be tweaking in the near term.
- Submitted
CDS/LDAS Security doc to Stuart.
- Crashed
nodes:
-
node329 - Sun Aug 27, 2006 - Considered marginal board
-
node264 - Thu Aug 31, 2006 - Rebooted via IPMI
Livingston
(Igor Yakushin)
- Diagnostic
boot on the old dataserver revealed bad memory
DIMM. Since this machine is no longer under service contract and since one
has to insert/remove 4 DIMMs at a time, I
removed 4 DIMMs reducing the total memory from 4
to 3 Gb.
- Showed
Dwayne how to do diagnostic boot and use minicom
to capture the results.
- Configured
a test segment database on the old dataserver.
- Experimenting
with the test segment database to figure out how to make the changes
requested by Keith Riles.
- Node37
got frozen today. Rebooting fixed the problem for now.
- Enabled
firewall on gateway.
(Dwayne Giardina)
- Ejected
tapes for shipment to CIT, imported and labeled
new.
- Ejected
116 tapes for shelf storage, imported and labeled
new.
- Switched
instances of apache2 installs to the one packaged with Solaris 10.
- Restarted
createRDS scripts Tuesday during maintenance,
possibly unnecessary.
- Housekeeping,
organizing LDAS parts, manuals, etc.
Hanford
(Greg Mendell)
- The
work for the past week has focused on keeping LDAS services running at
LHO, while we fix problems with RAID boxes, publishing meta
data, and the web server. The problems have been minor and not caused any
loss of data. Overall LDAS services continue to run smoothly at LHO, as
they have throughout S5.
(Ben Johnson)
- Ejected
first 95 directories worth of Level 1 RDS data (or about 60 tapes).
- Put
IPFilter firewall in place at LLO.
- gateway@LHO is now running Solaris 10 release version
of apache.
- t3-23 shut itself down for an unknown reason. The unit
came back up after a powercycle, and missing raw
frames were copied from backup framebuilder.
- Continuing
to investigate testpoint manager + framebuilder corruption.
General Computing (Wallace)
MIT
Nothing to report
Livingston
(Shannon)
- Trouble
shooting a Solaris 10 x86_64 system.
Sun has not been much help.
The initial suspicions have proved to be incorrect, so I am still
trying to diagnose the exact cause of the system lockups.
- Looked
into an issue with the IDS at LHO.
Turned out that a misconfigured sendmail daemon had been filling up the log partition
on the loghost.
This in turn caused issues with several other things, including the
IDS.
- Putting
together a system for a MySQL server. Will have Dwayne install the OS/software
once I get it built. Several issues
with it so far. Had to order an
adapter cable, etc.
- Set
up a global directory for "lscsoft". John Zweizig
has ownership and has agreed to maintain the software for now.
- More
pouring through IDS logs...
- Reading
more documentation on BGP, which will need to be set up
in the next couple of days for initial testing with Charter.
- Set
up auditing on a Solaris 9 GC host.
The plan is to roll out auditing across all of LLO GC, but initial
testing is needed to determine disk usage, configuration details,
etc. Will also document and pass on
to Dave as we are planning on this for CDS also.
Hanford
(Christine)
- Tried
again to get the Fedora C4 NIS+ client working. Re-installed the OS again, followed all
the instructions from Erik, still won't
work. I can run all the niscat commands on all of the databases, everything
looks good, but I can't login with a NIS+
username.
- Hope
to finish the cybersecurity vulnerability spread
sheets this week. I've spent most
of the week working on it.
- Helped
a new long term visitor get settled in.
He brought his own laptop and desktop, both Linux.
- Helped
another visitor get the printers set up on his laptop.
- Started
budget planning for next FY.
- Requested
quotes for a new router from several sources.
CIT
(Mike)
- Finished
up loading our new SQL server. After working out many hardware issues I
was able to get this server up and running. I now have the SQL server
software for DCC running on the new server.
- Worked
the third floor network closet, mounting network switches, and re-cabling
all network cables. Christian gave
me a hand with this.
- Ghosted
all NTSRV's EOF backups. Christian gave me a
hand with this to get him familiar with backups.
- Working
on loading a new Linux server.
- Continued
work on Spam Filters.
- Other
misc. user support, work in B/A server room, plus other sysadmin tasks.
(Veronica)
- LSC: Updates of the database of technical
publications. Updates of LSC-related mailing lists. Posted belated
presentations from last meeting.
- LIGO: Video editing for Vladimir Braginsky. Image editing permissions for NSF and other
publishers. Updates of the website.
User support for AdvLIGO Project office.
Tracking down a shipment of videotapes of SciMon
from last meeting, it's supposed to arrive today.
- CaJAGWR:
Website updates.
- Project
Science: Website updates/user support.
(Christian)
- Mike
and I relocated and organized two network switches on the 3rd W/B.
- Ran
monthly ghost backups on all NTSRV's
- Stocked
printer cartridges that were delivered to LIGO this week.
- Working
with HP support to configure new printer/scanner that is going to be
station at 3rd W/B.
- Continue
working on the system that is going into the display case.
- Worked
on the Spam Filters with Mike and Larry.
Other misc.: Continued onsite software/phone support.
(Bruce Sears)
-iLog Maintenance: (0.5 days)
General iLog
maintenance (user adds, keyword adds, systems work, etc.)
(Larry)
- The
procurement cycle continues. Still making a number of procurements for new
arrivals and projects. Wrapping up
the SUN maint. contract
and checking on a couple of the s/w contracts that are due to expire. Still working on getting more disk space
for the home accounts.
- Getting
the broken quad dual core cpu
unit ready to be shipped back. The
system is to be upgraded and repaired. Hopefully, when it returns we will
have a viable system to use.
- Assisted
Mike with a number of different projects he has been working on. Mostly,
helping him trouble-shoot some of the problems he has encountered.
- Working
with the group on the system going into the display case. We have the h/w
working and now we are down to the s/w installation.
- Still
signing out SURF students. Also, signing new people in.
- Setup
a new mailman account and have received requests for a couple more.
- Working
multiple calendar manager issues. We will start testing a product that may
be used as a replacement for the existing calendar system. However, we
will be upgrading the existing system to the latest version so we can get
a good comparison of the products.
- Assisted
a number of students in trouble-shooting different items. Still working on a matlab
environment problem with one of the students.
- Started
the monthly backups.
- Worked
with Mike and Christian in rearranging some of the equipment in the
computer room. This is being done in preparation to re-cable a number of
machines.
- Worked
a number of e-mail and spam issues.
Mail Statistics for Aug 24-30, 06
|
Mail Statistics
|
8/31/2006
|
|
Rejected Messages
|
33,248
|
|
Virus Messages
|
1,090
|
|
Accepted Messages
|
30,198
|
|
Total Messages
|
63,446
|
Advanced
LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Systems
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Systems, Management
from Dennis
Coyne
Systems
See also:
AdL Systems wiki web page
AdL
Systems email archives
Records
Of Decisions or Agreements (RODA) status web page
Nothing significant to report
Vacuum Compatibility
Vacuum
Preparation & Residual Gas Assay (RGA)
See also the Vacuum Bake Lab
Bob Taylor
No report (out sick)
High-Irradiance,
Contamination-Exposure Cavities
Lee Cardenas, Liyuan Zhang
Cavity # 1: OTF Lab. at W. Bridge: No Change.
[Still measuring absorption & total
loss on wire sample daily. Ready for new sample.]
Cavity #2: No change
Cavity #3: OTF Lab at Lauritsen
Room 38:
We have encountered with a situation such as the output signal was not as
stable as before. As we have pursued to
find the cause, we have lost the cavity lock, then we went through a complete
new re-alignment BUT that did not solve.
As we suspect of the malfunction of one of the equipment, we found that the this "old" function generator was the cause.
We brought another function generator and finally we were able to lock the
cavity again and we are now optimizing its power output with a good gaussian (TEMo,o)
mode. Now, The
new sample, stepper motor is in the cavity. The cavity is locked. We were
taking measurements and we'll continue taking every day for absorption and ring
down.
Scatter/Absorption Test Measurement:
We have started the scatter measurement for a witness 1.00" mirror. Later, this same mirror will be covered with a
protective film (“First Contact”) by Helena. After 1 week of exposure, we’ll
remove the film and then take new measurements and compare with the previous
measurements.
Modeling and Simulation (Hiro Yamamoto)
e2e weekly meeting (Mark Barton + X)
On August 30th, 10am, the first e2e meeting organized by Sany
and Osamu started. Mark Barton gave a
talk summering the update of his suspension modeling work. This time, the main focus was the update of
the triple suspension model, comparison of quad blade vs
double blade performance with different wire spacing. The talk is G060490. Mark's work is available now in www.ligo.caltech.edu/~e2e/SUSmodels/
AdvLIGO LSC/ASC design using FP arm model with
quad suspension (Osamu, Hiro)
Peter asked me to check positive g-factor case which has 54.4km of ROC for
both ITM/ETM instead of 2076m for negative g-factor. As a result of simulation,
it appears that the positive g-factor is less stable due to additional slope(equivalently less phase margin) around unity gain frequency.
And furthermore, yaw differential mode has a dip around 2Hz, so that design of
feedback filter might be more complex.
Static IFO simulation (Hiro)
It was found that the calculation of a stationary field fails due to some
degeneracy. This was solved by reducing
DOF, which also accelerated the convergence of estimation. Locking code was generalized to handle generic
case.
Modeler Hiro, Bruce, Melody
A new module is being developed, which can accept any kind of inputs
and can generate any kind of outputs using C++ code as the setting. This one is an
enhanced version of FUNC_X, combined with the template based primitive
architecture. Now is a design state, both modeler and alfi.
Fast simulation of Dual Recycled Michelson module with modes (Hiro, Keiko)
The formulation to calculate time evolution of fields with spatial mode in a
composite optical system is very complicated.
The goal is to calculate fields in DRM keeping the linear term of
various quantities, like position of masses and phase of fields. In order to find a good strategy, a FP system
is used at first.
Last week we develop the formulae of the modal model approximation. In this
model, the values such as the light fields or the mirror reflectivities
must be expressed as the matrix forms due to the multiple modes. In order to
calculate the light field in the time domain, some matrix products which has
the n times summation should be dealed with. It makes
the calculation very long. We expanded this n times summation using
Taylor-expansion. If we take only higher order, the calculation time can be
shortened. We are going to validate this expression numerically by comparing
with the formulae without any approximations.
Mechanical Simulation for advanced LIGO (Sany and
SLU team)
(1) E2e modeling
(Yoshida)
Continued e2e modeling of Modal Damping AdvLIGO MC Triple suspension. The test results on
the plant SS matrix in the e2e format (i.e., free hanging triple sus) has been confirmed to be reasonable by Laurent Ruet (our e2e model is based on Ruet?s
simlink model). Constructed e2e models of estimator
and control loops and tested with the above plant model. The test run indicates
that the system is unstable. The problem is currently being investigated.
We had an e2e telecon. Mark Barton presented
updates on his e2e AdvLIGO triple suspensions.
Andrew Kinchen (Southeastern e2e group?s new member) set up a new
account under our on-campus unix machine
(specifically used for e2e modeling). He encountered some configuration
problems, which will be solved soon. He started to learn basics of alfi and modeler.
(Quave)
Problems concerning compatibility issues with Virginio's
matlab and statespace syntax
were solved and the SS is now being integrated into an e2e box. Apparently the binary matlab
files can only be run on Matlab version r2006a using
an x86 processor. We are currently having trouble getting modeler to use the statespace generated, but upon further investigation I
expect it to be useable and integrated with our current table model soon. The notebook file sent by Mark Barton to
generate the back reaction force for the triple sus mathematica model was used to generate a new statespace including this parameter, but currently the
E2EExport.nb is not working properly. The reason for our problems is assumed to
be caused by problems running mathematica remotely. Sany will run the mathematica
model on LIGO computers with direct mathematica
installations, and if this not not
solve the problem I will modify E2EExport.nb soon to correctly output
e2e usable statespace.
(2) Outreach
(Sutton)
I have completed editing the procedure manuals for the Giant Slinky, Standing
Waves, Hot Light Exhibit, Pipes of Pan, and Variable Length Pendulum. They have been sent to Dr. Norwood for final
review.
(Norwood)
The pilot program to bring pre-service teachers from Southeastern to the
LIGO Outreach Center begins this semester, with three trips planned to expose
the teachers to seven (7) of the displays. These pre-service teachers are
Elementary Education majors enrolled in the physics
departments PHYS 142 class, Elementary Physics. Thirteen students are enrolled,
and are scheduled to visit the Center. Six (6) manuals written to guide
the pre service teachers through the displays have been vetted by a team of
three Southeastern professors, two in-service high school teachers, one
pre-service teacher and one talented high school
student. After these visits, the pre-service teachers will critique those
manuals and critically assess the utility of the LIGO Outreach
Center as a resource for
elementary school teachers.
(Gersch/Perez, Holden High School
Science Teacher/Senior)
We have made several videos of Gravity's Rainbow and were successful in
loading them into the software program. Only three points were able to be
made with the digital camera because it only has about 15 fps and the ball is
in the air only about .4 s. Some of the results are close to the
experimental data we have.
(Anderson, St. Thomas
Aquinas High
School Science Teacher)
Edited the lab manual for the Interference in soap bubbles
exhibit. Worked on a "snack" version of the
"Snake pendulum" for the classroom use.
AdvVirgo Model (Monica)
The AdVirgoFP
package has been tested and ready to be delivered. It allows to acquire the
lock of a Virgo-like arm cavity using a laser power of 150W and the control on
the reflected signal of the cavity; the transmissivity
for the input mirror is T_itm=0.005 while for the end
mirror is T_etm=10-7.
[ Hiro : Monica
uses a simplified model for the Virgo arm, 7m single suspension for SUS, no
limit of the actuation force and only linear DOF. This conclusion that advVirgo arm can be locked with 150W input needs to be
examined more carefully to understand how practical it is.]
Seismic Isolation
BSC Sesimic Isolation Assembly and Test
We have found problems in the coils with two of the large actuators and one
of the small actuators. The large actuators contain shorts between the windings
and the case and the small actuator has had the wire to the coil winding break
off. We are looking into the cause of the problems with PSI and at different
options which will allow us to continue our testing.
Considerable time is being spent writing assembly and installation procedures.
From: Ben Abbott abbott_b@ligo.caltech.edu
I have made changes to the schematics for, and re-layed
out the PCB for the ADC Interface Chassis to accommodate a recent addition of 3
witness LVDTs.
The HAM-SAS Test plan came out on Wednesday, and in it, significant
additions to the electronics system are listed. I have begun to change my
drawings to reflect the additions, and am starting to look at procuring, or
making the additional electronics modules.
I've finished the HAM-SAS in-vacuum breakout board. Some research on
in-vacuum circuit boards is still needed, I'll make
some calls soon.
From: Dennis Coyne coyne@ligo.caltech.edu
Minutes
of the 30 Aug 2006 Meeting
see also:
HAM-SAS
Home Page
HAM
SAS Development Web Page
Riccardo's plan for the next 2 weeks at Galli & Morelli:
Tasks
for the next 2 weeks:
1) try IP table as is (smaller Flex joints, reduced load),
equalize load, tune to low frequency.
2) Test
mount Horizontal LVDT/actuator units and tuneable
springs
3) Tune
up the remaining 3 GAS filters to <300 mHz (only
one tuned so far), check positioning and spacer of vertical LVDT/actuator units
4) Change
IP flex joints with the new nominal load ones, reassemble
5) Load
temp plate on filters and tune both filters and IP to low frequency
6) Assemble
elevator/translator carts. Load with the HAM SAS unit, try the movements
7) Disassemble
for UHV cleaning
8) Calibrate
IP CW
9) Organize
FT-IR measurements
10) Organize
cleaning process
11) Finalize
clean room
12) Calibrate
magic wand tuning
Clean room is being completed this week.
Cart parts are on-hand except commercial rails.
a company representative for the FTIR instrument
has arrived at G&M to set it up and give instruction on its use found local
chemical company for the cleaning & FTIR solvent. G&M now has permission to retain chemicals
in "small" quantities (much more than we will need)
Dave O. has asked for the addition of 3 LVDT witness sensors on a column in
the center of the system
Ben is looking into accommodating these additional 3 LVDT channels with
their drivers
We need to tests the vertical LVDT and the actuators
whcih have been already done. They should be sitting
somewhere there in Lucca
and must be shipped to caltech ASAP. Ric will look for
& ship
Difficulties with LVDT electronics, being addressed
Availability of the Guralps
(CMG40T? ) confirmed, and no additional Seismometers are called out in
the test plan
Availability of a triple pendulum to place as a payload on
the optical table to be placed from the beginning is confirmed; electronics in
preparation.
Test plan drafted by Dave Ottaway.
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
Held a meeting on Monday about bonding and wire break off
approaches for all optics. A number of actions were assigned and research
is ongoing.
Held an AOS suspensions meeting with SUS folks, Mike Smith
and Chris Echolls. Actions were assigned in
preparation for a full-day work session at Caltech on 11 Sept.
Putting some Solidworks files on the vault and
generally cleaning out my Solidworks directory.
From: Ken Mailand kmailand@ligo.caltech.edu
I'm using information from Ian, and working on a lower quad installation arm
shop drawings, also a 'conveyor' version to be used at the LASTI site. The
majority of the installation arm parts are in the CES shop, several have been
completed, I'm working on the and cavity beam dumps
for Mike Smith.
Core Optics
From: Bill Kells kells@ligo.caltech.edu
This was a half week for me: was in NY last week. However it has been overdrive/crunch time to
finish up the SURF project I comment on previously. This has been successfully
wrapped up (with an initial report in draft and to
be offically submitted within ~ 2 weeks). This has
been about a full cavity field PI simulation covering every single acoustic
mode relevant for AdLIGO (some 9200 modes to 90 kHz).
The massive survey entailed gives an informative overview of the issues (e.g.
that only a few modes would be potentially unstable for any instantaneous config. "snapshot"). On the other hand it gives a nominal answer
to the question K. Thorne possed on whether there
could be significant non-cavity resonance constributions.
Of course, as with any such "big"
simulation there is much more obvious to do "next", and several
limitations and caveats.
Its been a very nice piece of work (much thanks to
the super hard working student, Hans Bantilahn, whom
I had). He intends to continue working on this during the coming year (as a Senior at Carlton Coll.).
From: Helena Armandula ahelena@ligo.caltech.edu
Advanced LIGO Coatings – CSIRO
Last Thursday we had a telecon with CSIRO; future
coating runs were discussed. We agreed
that the next runs will be: a Ti doped Ta coating following the guidelines on
the paper soon to be published and a single layer of fused silica on which to
measure the fused-silica mechanical loss.
LMA
The next coating with LMA, due in about 3 weeks, will be applied to a
3" dia. substrate. The coating formula that gave
the best mechanical loss will be tested for absorption to see if the Adv. LIGO
requirements can be met.
Testing of First Contact continues. A 1" fused silica mirror will be
tested for scatter after the film is pulled from the mirror's surface a week
after the application.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
For a mixture of input polarisations, the polarisation filtering provided by a pre-modecleaner was measured. When operated in the low-finesse mode, the low signal levels proved to be
troublesome despite plenty of pre-amplification and the use of a lock-in
amplifier. The best power attenuation measured was 45 dB. When
operated in the high-finesse mode, the cavity losses were such that the
throughput was rather poor.
Work on the digital filters
with the DSP came across a limit with the fixed floating point representation
used, so that a copy of a Simulink model could not be
used. This is only a problem with filters that involve low frequencies,
which the intensity stabilisation does.
Electronics, Controls, Data systems
From: Rolf Bork rolf@ligo.caltech.edu
AdvLigo
/CDS Infrastructure/
- (Rolf)
With two experimental systems (Ponderomotive and
Hannover PSL test bench) now having control
cycle requirements of 128KHz, I started more
timing tests with our new controls architecture. The code for both can easily run in the
time allotted for this rate, but I needed to further test the ADC input to
DAC output times. The test is run by feeding a square wave into the ADC,
have the computer read that data, then send the signal back out to the
DAC. The ADC input and DAC output signals are then compared on a scope.
The minimum time I was able to achieve with our standard 200KS/sec ADC and
DAC was about 12usec. Without
introducing a lot of phase delay, this is only suitable for a system
running at 64KS/sec max, more comfortably 32KS/sec. We also have a 2MS/sec
combination ADC/DAC module available, that I have now begun testing. A
quick measurement indicates a time of about 8usec. I want to do some I/O
code optimization, similar to what was done for the 200KS/sec ADC, which
could buy me another 3-4usec, which would allow this module to be used in
a 128KS/sec controller. These tests were all run with the ADC/DAC modules
in our PCI-X and PCI Express I/O expander units. I discovered during the
testing that individual I/O read/writes took almost 3 times longer using
the PCI-X version than using the PCI Express version. I plan to run the
tests again with the ADC/DAC directly in the computer (no expander) in the
next few days.
- (Alex)
Now that we are running on multi-core processors, working on our software
that generates code from Simulink files to produce
multiple threads that run across the available processors.
- (Rich)
Received the second prototype LIGO Rack Mount Chassis from the metal
shop. It looks great. I am doing one more set of design changes
to simplify manufacturing and assembly. The first order for 20 or so
units will go out soon. Worked with Jay to design a "standard" LIGO
power regulator board for use in the new chassis
/Seismic/
- (Ben)
I have made changes to the schematics for, and re-layed
out the PCB for the ADC Interface Chassis to accommodate a recent addition
of 3 witness LVDTs.
- (Ben)
The HAM-SAS Test plan came out on Wednesday, and in it, significant
additions to the electronics system are listed. I have begun to change my
drawings to reflect the additions, and am starting to look at procuring,
or making the additional electronics modules.
- (Ben)
I've finished the HAM-SAS in-vacuum breakout board. Some research on in-vacuum circuit boards
is still needed, I'll make some calls soon.
- (Jay)
Additional boards and chassis for 8 more capacitive position sensors are
being assembled.
- (Jay)
Ordered 3 more racks and replacement rails for LASTI HAM SAS and DC power
systems.
- (Jay):
Designed replacement coil driver chassis to be used for Triple SUS to be
tested with HAM SAS. It coul also be used for
the Squeezing Experiment.
- (Mohanna): I have sent the prototype version of the Adl SEI Coil Driver Board to the PCB express. It is
using the 10A, LM12 operational amplifier. The spice does not exist to do
the simulation. During my test I will measure the transfer function and
other characteristics to determining whether it would be an ideal high
current op amp to consider in the seismic fine, coarse actuators.
/ISC/ (Rich)
- Received
the parts I ordered for a modulated laser to use in the test and
evaluation of ASC photo-detector elements. Received additional
diodes from the manufacturer, so we now have duplicates to test.
- Started
research into in-vacuum sockets for mounting photo-diodes on standard
vacuum conflat flanges. Accu-glass is looking into this for me.
40m Lab
- (Rich)
Chose (and ordered) some Kepco high voltage DC
power supplies for the DC readout experiment.
- (Ben)
The new rev of the QPD Whitening board is stuffed now, and ready for
testing. I have to write a test procedure, then
it can be tested in the back shop.
- (Ben)We
put the electronics into the clean vacuum nipple, and filled it with
krypton. I then sealed the nipple, and it is now ready for
installation.
- (Ben)
I cut the cans off two GAP2000 PDs that we can
use in the vacuum DCPD.
Other Laboratory R&D
From: John Miller
<miller_j@ligo.caltech.edu>
Livia and John
We have constructed an optical lever and written a data acquisition program
to retrieve the data. We are now able to measure tilts and record mode shapes
simultaneously rather than using a calibration. We are working with Juri Agresti on simulations to
verify our new results.
Yumei
Writing report of all of my work in Caltech.
For additional information about this report, contact Stan Whitcomb or Phil Lindquist