The LIGO Executive
Committee Agenda for Monday, August 28, 2006
will be:
(Meeting time: 10:30 am Pacific Time)
1. Announcements
2. Comments on weekly report
3. LSC Issures (Saulson)
4. LIGO Lab Operations
5. Enhancements (Adhakari)
6. Advanced LIGO (Shoemaker)
7. Change Control Board/Technical Review Board Session as needed
Special Items:
PI's are now receiving feedback from the MOU Review Panel. Most cases were straightforward. A few have involved discussions involving not only the PI's Liaison from the MOU Review Panel but also the Spokesperson. Most of those discussions have now taken place; they have been very fruitful.
The next steps are to sign those MOU's that are ready for signature, and to collect and process the ones that need revision.
>From: Rod Luna <rluna@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
|
Week Ending 08/24/2006 |
In |
Out |
|
Packages |
25 |
3 |
|
Faxes |
25 |
20 |
>From: "Funaro,
Catherine" <Catherine.Funaro@caltech.edu>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
>From: Florence Kaufman <fkaufman>
>From: Gina Salone <gsalone@ligo.caltech.edu>
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
The time has come to work on the budgets for next year.
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
>From: Bill Tyler tyler@ligo.caltech.edu
During this reporting period, a LIGO audit team completed a safety audit of the Hanford Observatory. The audit team found that the staff at LHO had completed closure of all of the 2005 safety audit action items assigned to them. The audit team noted that LHO staff has achieved significant improvement in their "housekeeping" and the overall "appearance" of the site is quite good and should make a good impression on visitors. The challenge to the LHO staff will be to maintain and/or improve on this achievement. The LHO staff continues to maintain good safety practices and is already starting to "think-ahead" about safety issues/concerns involved with both Enhanced and Advanced LIGO. Overall, the results of the LHO safety audit were very positive, there were only two new action items assigned to LHO involving some incomplete Incident Reports.
The list of action items and recommendations will be distributed next week.
Duty cycle of H1 this week (Thu Aug/17 to Wed Aug/23) was 83.3 percent. Despite the problem of REFL/CM/MC path (see
below); H2's duty cycle was respectable 90.9 percent.
Out of the down time of H1 of 28.1 hr (i.e. 16.7 percent), 8.9 hr (or 5.3
percent) was attributed to the IFO-centric commissioning/measurement
activities. These activities were done
in coincidence with
The binary range was 13 - 14+ Mpc for H1, and 6.5 - 7+ for H2.
S5 highlights from the LHO elog are bulleted
below:
Other things: This week we had a safety audit.
All of the major procurement is in process. Allen and I have met with the company doing the machine shop work last week and are meeting with the welding shop this morning. We will meet with HPD this afternoon to tie up any loose ends and continue work on assembly and installation procedures. Parts are already coming in so space allocation is becoming important. Working on a spreadsheet of costs and delivery information this morning
from Dennis Coyne
Last week was the last for 40m SURF students Jenne
Driggers, Darcy Barron, David Malling
and Royal Reinecke. They all did terrific jobs and
will have impressive final papers. It was a pleasure having them all and we
wish them the best. Also, this is Shally's last week
before returning to
Rob presented the status of work at the 40m at the LSC meeting.
Since our last report, Akira, Matt, and Cacey finished installing the SAC output mirror, aligned
the interferometer, locked the instrument, and took data.
Preliminary indications are that Q reduction
is as good as with buna. There are no mechanical modes that we can
excite with the OSEMS. All of the Qs are now smaller than we can measure by
excitation. We have not yet looked at the width of the thermally-excited modes.
Unfortunately, the noise floor has been
disturbed. Our calculated lowest mechanical mode for copper rings was in excess
of 100kHz, but we see at least three clear modes around 1-2kHz, and we observe
some broadband noise above coating thermal noise below a few kilohertz. Neither of these effects is, as yet, understood,
but we are working with Dennis Coyne on modeling two possible scenarios.
One hypothesis is that the spring is not
providing enough tension for the rings to make good contact all around the
barrel of the optic, leading to a "bending" mode where the ring is
free. Greg is moving ahead with the heater for the monolithic rings, and he is
now in the process of winding the induction coil.
Attached is a plot of the total noise in SAC
with the copper ring dampers installed (blue curve) and without any ring dampers
(red curve).

The locator / lock subassemblies have been installed, properly gapped, and
work in both the locked and unlocked position.
We have installed two sets of course and fine actuators on the seismic
structure. We are waiting for electronics and sensors from the CDS group to
install the final set. This completes the "dirty assembly." Modal testing will
begin next week using the installed actuators to shake the structure!
We have aligned all of the stage lockers with a maximum error of <=
3/1000 inches. We have now transferred
the reference from the pins to the locators. This lets us account for the small horizontal
motion that we get when the system is released. One set of actuators (two fine and two coarse) have been installed, with the position
sensors zeroed. We do not yet have the
electronics to run the other 2 corners so we will hold of on those.
A procurement plan with new specifications has been written for the single
stage HAM project. Brian Lantz is checking the specifications and providing
additional input.
We have brought Lasti up to air so that the Quad
can be worked on. There was an interference in the
reaction chain that was attributed to the newly installed eddy current damper.
It turns out that the problem was not in the ECD so we are now hunting for the
cause. We will also install the power resistors (which passed the RGA test) for
the thermal load test of the structure.
Next week we will start to install the scissor tables and clean room over the Y-end HAM. The LASTI test plan is currently being written and should be ready for comment by SEI and SUS groups by the start of next week. Cassie continues to troubleshoot her ideas model of the triple.
Brown (2 weeks' worth):
Chatterji:
Mendell:
Work continues towards producing a final draft of the S4 PowerFlux, StackSlide, and Hough paper. An updated draft was presented at the August LSC meeting at LSU and my presentation has been submitted to the DCC as LIGO-G060388-00-W.
Sutton (2 weeks' worth):
Last week I attended SciMon Camp at LLO, where I gave a brief presentation on RayleighMonitor. This week I've been studying Bayesian approaches to GWB detection, writing a paper with Stephen Poprocki comparing various coherent statistics for black-hole merger detection, and helping Stephen draft a proposal for his B.Sc. thesis project.
I've spent the past week at the bursts face-to-face meeting and the LSC meeting. I presented the results of Stephen Poprocki's SURF project, comparing different coherent statistics for detecting black- hole mergers. I also took a scimon shift at LLO.
Resolved Globus socket (Tcl channel) memory segmentation issue on 64-bit platform:
Calling timestamp() is the cause of memory segmentation. The solution is to remove the timestamp() and put the functionality inside macro.
Fixed type mismatch when reading the data from Globus buffer and pass it to Tcl layer. Globus is using globus_size_t * which is long * to store the number of bytes read and Tcl is using int to store and pass the value to the application.
Still working on the following 64-bit issue:
TclGlobus asynchronous unit tests failed on 64-bit platform. The problem is the callback script never gets evaluated inside Tcl interpreter and this causes the program to get stuck.
Working on cleaning up N-2 data partition manually using small partition DAX. Modifying the workflow code to handle this new functionality.
Working on the following PR:
New functionality needed for specifying the Stage-out Host & Directory
Fixed the following PR:
GUI needs to support both partition and non-partition workflow
Attended a meeting with Kent Blackburn at the OSG consortium meeting regarding potential reorganization of the ITB activity. Agreed to chair the ITB meeting to provided relief for OSG staff during vacation or travel of current chairs.
Discussed proposal on a Virtual Testbed (VTB) which would require reorganizing hardware from the single ITB cluster to a smaller ITB cluster and a new VTB cluster with its own CE and 4 worker nodes. Possibly one new PC would be needed for a VTB GUMS server. A new 100-Base-T ethernet switch would be needed for interconnecting the VTB nodes.
One new IP address would be needed for the VTB CE node.
Working with Michael Samidi, completed rudimentary support for partitioned DAX workflow planning and execution in the LIGO Workflow planner. Demonstrated the Workflow planner running the partitioned DAX of the Inspiral HIPE analysis at the Consortium meeting. Workflow executed at Brookhaven National Labs OSG production site.
Attended three days of meetings at the OSG Consortium meeting related to storage management, OSG release planning, documentation and information services. Fermi Labs manager Keith Chadwick offered to assist with analysis of suspected GUMS memory error that appears to be related to 15,000 DAG node jobs causing GUMS failures.
Previous week
We discovered 64-bit issue with TclGlobus. This issue was discovered when using Globus socket. When passing data from Tcl layer down to C layer, the function call uses the information about the size of the buffer. Then, this information will be sent over to the other side before sending the actual data. However, the information becomes incorrect causing segmentation fault. I'm working with Ed Maros to solve this issue
Added partitioning functionality into LIGO Workflow Planner GUI.
Discovered a problem when aborting partitioning DAG from submit host, osg-itb-se. Removing top level Condor job doesn't remove the sub- partition Condor jobs. Discussed this with Karan Vahi from ISI and he suggested to upgrade Condor to the latest version, 6.8.0
Successfully partitioned the full S5 HIPE DAX into six partitions. Java had to be upgraded to Java 5 to prevent heap memory errors when running the VDS utility partitiondax.
Created a small set of six partitions for testing and integration with the LIGO workflow planner. Tested execution of the full six partitions on the OSG site PSU. Completed 16000 DAG nodes before exception threw a rescue DAG. Analysis indicates that four gravity wave files apparently having bad data, were the cause of the lalapps_tmpltbank code failing. A science analysis of these bad data segments by the appropriate experts will be required. Correct execution of partitions 2-6 depends on cleanup of these partition one failures.
Determined that the GUMS server at PSU [and probably at all other OSG sites due to a memory leak that occurs on a per job basis - JKB] is not robust when running the 16000 DAG nodes in HIPE partition number one. Two execution runs of the partition number one of HIPE both failed at around 15000 - 16000 DAG nodes. PSU has installed a grid mapfile to improve reliability.
Configured a laptop PC with fedora 5 and TclGlobus for the OSG consortium meeting.
Kent Blackburn was confirmed by the OSG Council as the new Co-Resource
Manager and member of the OSG Executive Board. Warren Anderson of UWM will
replace
Currently 64bit LDAS cannot accept certificates due to limitations with TclGlobus. The issue is being addressed by the TclGlobus team.
Compiling 3rd party software needed by LDAS for Solaris 10 running on an Opteron box continues. Tcl/Tk is the only package not yet ported. On linuxopteron, porting of the LDAS software has started. The first issue that has been discovered is the 32 compilation of ObjectSpace. This error will be corrected by the end of the day
The cmonClient had several problem reports closed. The first affects the cancellation of the "All User Test". It now reenables all other test tabs upon cancellation (PR#3020). Also, the user's preference of showing info and warning dialogs is now saved (PR#3049).
System tests for LDAS were done using version 1.8.277. All test passed as before except for lsync which is still unable to see RDSVerify and some /scratch directories in the lsync cache and dataStandAlone grid due to no /ldas/bin/wrapperAPI on sun box.
A communication error when renewing or adding user accounts to ldas-dev has been discovered. This critical problem will be corrected by next week.
(Dan Kozak)
(Phil Ehrens)
(Erik Espinoza)
(Stuart Anderson)
(Dwayne Giardina)
(Greg Mendell)
(Ben Johnson)
(Larry)
(Dwayne)
(
(Christine)
(Veronica)
(Mike)
(Christian)
(Bruce Sears)
General iLog maintenance (user adds, keyword adds, systems work, etc.)
(Larry)
Mail Statistics for Aug 17-23, 06
|
Mail Statistics |
08/27/2006 |
|
Rejected Messages |
41,228 |
|
Virus Messages |
1,615 |
|
Accepted Messages |
22,144 |
|
Total Messages |
63,372 |
from Dennis Coyne
See also:
Records
Of Decisions or Agreements (RODA) status web page
Vacuum
Preparation & Residual Gas Assay (RGA)
See also the Vacuum Bake Lab
Bob Taylor
High-Irradiance, Coamination-Exposure
Cavities
Lee Cardenas, Liyuan Zhang
Cavity # 1: OTF Lab. at W. Bridge: No Change.
[Still measuring absorption & total loss on wire sample daily. Ready for new sample.]
Cavity #2: No change
Cavity #3: OTF Lab at Lauritsen Room 38: No Change.
Still measuring absorption & total loss on stepper motor sample daily. We will continue taking measurements until the test is completed.
Scatter/Absorption Test Measurement:
We started the scanning of a ITM04 mirror for the scatter measurement. In the setting of the RTS, we found some noise coming from one of the photodiode. We have built a new mount and re-mounted the photodiode in a xyz mount and be able to find a position which will decrease the noise. The noise measurements on new He-Ne (one watt of power ) has been completed and Dr. Zhang is working on the analysis of the data.
>From: Hiroaki Yamamoto hiro@ligo.caltech.edu
Weekly e2e meeting was
stopped because I (Hiro) was too busy to
organize. Now, Sany
and Osamu volunteered to organize the meeting and start the meeting again. Thank you very much.
Osamu gave a talk about his work at the LSC meeting at LSU (G060396)
We implemented electronic noise at the photodetector, and control signal was over the dynamic range of OSEM of penultimate mass when lock is acquired with very low power. There are several ideas to avoid the problem, and we put 30Hz 2-pole into the filter, which is the simplest way, then control signal has been enough small.
Gave a talk at the LSC meeting about this model and the implication of the surface roughness on the loss (G060386). Finished v1 of FP simulation setup.
Many changes needed for the full Advanced LIGO simulation. Michelson cavity setup being constructed.
Keiko Kokeyama has joined the e2e team. She is going to stay at Caltech until the end of this year. Her task is to formulate an approximate calculate of the dual recycled Michelson cavity (DRM) to accelerate the simulation of the DRM using modal model. The formulation is an extension of the work done by Hiro to implement the fast simulation of DRM using plane wave approximation.
(Keiko)
I read and followed the calculations of the scalar model approximation which is already solved, in an attempt to understand and start to develop the modal model approximation for the e2e fast module. I also started the calculation of the very first part of the modal model formulae. For the modal model calculation, we have to take into account matrix values as the reflectivities, propagators, etc. because of their multiple modes.
(Bruce, Melody, Hiro)
FUNC_XX work started. See below section of Afli.
(1) E2e modeling
With a great help by Laurent Ruet, started e2e modeling of Modal Damping for Advanced LIGO MC triple suspension. By running a matlab code written by Laurent for one DOF model, created a state space matrix for Yaw DOF and converted it to the e2e format. This SS model (the plant model) takes suspension point yaw motion and actuation forces (torques) to three masses as input and computes yaw motions of all three masses as output. The plant SS matrix in the e2e format is currently being tested with a simple e2e code using white noise input to the suspension point (without actuation forces). The estimator loop model, associated filters and control loop will be constructed after the test.
Jameson Quave continued working on modeling the SAS HAM seismic isolation based on a state space matrix created by Virginio S. It seems that the SS matrix has a syntax error and the original matlab binary file does not run properly on our machine (possibly caused by the difference in version of the matlab or processor architecture). The problems are currently being investigated.
Andrew Kinchen (Southeastern Undergrad Physics major) joined our e2e team. Previously he helped us installing a Linux OS into our on-campus computer. He will work on e2e modeling of Advanced LIGO Input Mode Cleaner, mostly on the campus.
(2) Outreach
We completed reviewing the lab manual that Naomi Sutton and Shahla Anderson drafted for several LIGO SEC exhibits
(Giant Slinky, Standing Wave, Variable Length Pendulum, Pipes of Pan, Hot Light
Exhibit and Soap Bubble Interference).
Naomi is now editing the final version. The manual will be tested in a
physics course offered by
Kay Gersch (A Holden High School science teacher)
and Scott Perez (a
The control system of the
40mInLockstate model has been tested running a simulation of 6s: the seismic
noise has been injected at 1s and the DARM and CARM loops have been opened at
1.5s and closed at 1.505s. Under these conditions the lock is stable and it
becomes stable again after opening and closing the loops. Nevertheless there is
a kind of instability simulating the optical response at dark port with modeler_freq: the lock is not broken but there is some
frequency disturbing the correct answer
of the transfer function. Under investigation.
Melody finished implementing new features, grouping and GUI commenting. Bruce worked on the modeler code to implement primitives based on primitive templates. The architecture of his work using primitive template is the foundation of the new primitive FUNC_XX.
Bruce, Melody and Hiro discussed about the implementation of a generic FUNC_X, called FUNC_XX. This is a primitive that can have arbitrary data type inputs and outputs. Both modeler and Alfi need to be modified. Once this is implemented, essentially all other primitives can be replaced by modules based on FUNC_XX. Bruce and Melody will focus on this task. It is estimated to take about 6 months to complete, including validations.
From: Ken Mason <kmason@ligo.mit.edu>
The locator / lock subassemblies have been installed, properly gapped, and work in both the locked and unlocked position. We have installed two sets of course and fine actuators on the seismic structure. We are waiting for electronics and sensors from the CDS group to install the final set. This completes the "dirty assembly", Modal testing will begin next week using the installed actuators to shake the structure!
A procurement plan with new specifications has been written for the single stage HAM project. Brian Lantz is checking the specifications and providing additional input.
From: Dennis Coyne
<coyne@ligo.caltech.edu>
Mechanics
G&M are now back from the summer break
A-frame design done will start oven welding beginning of the Sept-- delivery end of month
Acquisition of the still for evaporating the isopropyl alcohol is in process
FTIR cell received -- all FTIR parts are in hand, except computer
G&M to buy computer for FTIR in
Dennis visually inspected cleaned sample welds that Ric brought back -- all look good
received clean test items (not baked) -- will be FTIR & vacuum tested
Alberto Stochino will help on HAM-SAS at LASTI (must come to CIT first as condition of his fellowship) -- available end of September
Planning to get Yoichi Aso's
support at LASTI from
Electronics
LVDT card was shipped to
card did
not work -- short circuit on one of 8 channels
some
other manufacturing issues noticed as well (e.g. poor registration of parts to
the through holes)
Ben
laid out the following in Protel (to be sent to PCB
Express this week):
coil
driver interface bd
stepper
motor interface bd
ADCs
& DACs cabling into 25-pin connectors
Ben will work on ceramic boards for 8 15-pin connectors to 3 25-pin connectors for in-vacuum use
Modeling
Valerio: Maple Dynaflex toolbox for simulation can't seem to handle our application (works OK on simple models, but seemed to fail when the number or complexity increase)
Cassy: has been working on I-Deas
modeling of triple pendulum -- some modes are wrong -- will export to Dennis to
have a look
plan is to join to the HAM-SAS model
From: Ben Abbott abbott_b@ligo.caltech.edu
Seismic
I have made the schematics for, and layed-out the PCBs of 5 boards for the HAM-SAS and ISI systems. They will go to PCB Express in the next week.
I'm currently working on the last board for HAM-SAS, the in-vacuum breakout board. The schematic is done, and the PCB will be finished in the next week, or so. Some research on in-vacuum circuit boards is still needed.
The last two modules that ISI needs to be designed are the ISI Interface board, and the Coil Driver. I plan on doing the ISI Interface Board in the near future, and Mohana will continue to work on the Coil Driver when she gets back.
From: Mark Barton
<m.barton@physics.gla.ac.uk>
This week I moved my collection of suspension modeling software and models to a hopefully more permanent home under the E2E umbrella. It's now at http://www.ligo.caltech.edu/~e2e/SUSmodels/ .
I also added a number of new triple models.
Ian Wilmut has floated the idea of an AdvLIGO beamsplitter and/or FM
that would be a triple with two blades in the upper mass instead of four as in
GEO, so as to enable recycling of bits of the quad design. To support this I
did a triple model with dual blades. For good measure I also did a variant with
blade lateral compliance, in case this was relevant for the heavier design. It turns out that:
(i) As might be
expected, leaving all parameters the same gives much the same mode frequencies
except for the highest pitch mode involving antiphase
motion of the top and middle masses. Because this involves stretching of the
relatively stiff wires rather than the more compliant blades, the frequency of
the mode goes way up, from 1.2 Hz to 6.7 Hz.
(ii) The effect on the pitch mode can be
almost exactly cancelled by the same trick that was used in the quad: simply
reducing the intermediate wire half-spacing, i.e., the lever arm to pitch, from
15 mm to 2.3 mm. As in the quad, this is awkward because it puts the
intermediate wires inside the fibres, but there might
still be some net advantage. This will be argued out with Ian, Norna et al. over the next few weeks.
(iii) The blade lateral compliance doesn't
appear to produce a significant effect, at least for the beamsplitter.
I generated symbolic state-space matrices for
all these variants and created a new master "ssmake"
file for the GEO-derived Matlab software that loads
the appropriate set according to flags in the data structure that describes the
pendulum. It also includes other features originally developed for the quad
including automatic wire- flexure correction and support for ribbons. Hopefully
this will be the last word on triple models for some time.
From: Janeen Romie romie_j@ligo.caltech.edu
Attended the LSC last week, along with the auxilliary meetings of the OMC group on Monday, the Opto-Mechanical Layout group on Thursday afternoon and the Scimon Camp on Friday. The meetings were all fruitful and timely.
Provided updates to the schedule and milestones to Dwight last week. Working on various scheduling issues with SUS & COC group members and Dwight.
Provided rev C of the ETM test mass drawing and the associated DCN to Gari Billingsley.
Coordinating with Bob Taylor for the initial LIGO osems needed by
Worked up OMC requirements that are needed for ongoing work; sent to Norna, then Dennis.
Planning a trip to Caltech Sept 10-14 to coordinate with a Caltech visit by Calum Torrie and Alastair Grant.
From: Ken Mailand kmailand@ligo.caltech.edu
I'm using the latest information from Ian and working on a lower quad installation arm shop drawings, also a 'conveyor' version to be used at the LASTI site. The majority of the installation arm parts are in the CES shop.
I'm working on the DLC mounts, the PO Telescope, and cavity beam dumps for Mike Smith.
From: GariLynn Billingsley Billingsley_G@ligo.caltech.edu
The LASTI TM blank has been sent to General Optics for polishing. This is occurring much later than we had planned. We were urged to go for a competitive bid, and it turned out the way we expected, one company being quite a bit less expensive than another, yet with acceptable performance. The estimated delivery date is no later than December 18, 2006. Allowing for 2 months of coating we will still be able to supply the TM to LASTI without causing schedule delay.
Our absorption test stand has been changed into the scatter configuration. We are pursuing an understanding of the relationship between scatter observed at the observatories and scatter measured in the lab.
FYI
Heraeus has introduced a new material, available
in sizes up to 150mm diameter that is comprable to
good
Heraeus has now offered as a standard product that which we used to call Suprasil 311SV and 312SV (very low OH absorption). The new product designations are Suprasil 3001 and 3002. The 3001 is the high homogeneity version. e-mail billingsley_g at ligo if you are interested in data sheets.
From: Helena Armandula ahelena@ligo.caltech.edu
Research on First Contact
I talked with Ashot Markosyan
from
From: Michael Smith <smith@ligo.caltech.edu>
Hartmann Probe Beam - Back to the drawing board! The recent optomechanical design meeting at the LSC conference
uncovered the fact the the Hartman beam cannot be
injected through the MMT2 mirror, because of the intentional and unintentional
thermal lensing that will occur in the IMMT beam
path. Therefore, the Hartmann X beam will be injected with a beam splitter
through the same off-axis parabolic telescope that receives the ITMX PO beam
along the BS AR ghost beam path. The
Hartmann Y beam will be injected through the OMMT2 mirror. By doing this, we still require only one
off-axis
Ken Mailand
completed a SW model of the
Luke Williams completed a SW design concept for the SOS errant beam baffle. Phil Willems is investigating the possible heating damage to the oxidized stainless steel baffle material from a 1mm dia 125 W beam; it may be necessary to use oxidized copper, or highly reflective stainless steel.
The SUS group has a conceptual design for attaching the elliptical baffle to the quad-suspension.
The wedge angles of the COCs for the folded IFO are being investigated using Zemax. At the moment, it appears that most of the folded IFO COC wedge angles will be different from the non-folded COC wedges.
From: David Reitze <reitze@phys.ufl.edu>
Input Optics PDR planning (All) - UF is in the initial stages of planning for the AdL IO PDR slated for sometime in October. This will cover the MZ design, the mode cleaner, the aMMT, and ancillary IO subsystems
Faraday isolator characterization (Questschke, Franzen) - been characterizing the AdvLIGO (and eLIGO) FI alignment and position tolerances for purposes of designing a better rotator housing. In the process, we learned that calcite polarizer performance is limited by scatter (either from the surface or intrinsic), but have essentially flat and very good extinction ratios ( > 3 x 10^5) over the 0 - 100 W power range.
EOM noise characterization (Wan Wu) - The intensity stablization servo for the YAG laser was built and proven to be working properly. We still have 10^-6/sqrt(Hz) relative intensity noise due to the dark current noise and other electronic noise of the photodetector; working on the phase noise - amplitude noise coupling problem.
Adaptive IO MMT (Arain) - One phase of experiments regarding adaptive optics for Ad. LIGO had been completed. A tunable positive lens with a range from infinity to 4 m has been demonstrated. We have submitted a paper titled "Adaptive beam shaping by controlled thermal lensing in optical elements" for LSC review. The idea is to have an adaptive telescope built into input optics for in-situ mode matching into the arm cavities of the interferometer. Further experiments are being planned for thermal compensation in Advanced LIGO.
From: Rolf Bork rolf@ligo.caltech.edu
Met with B.
Wilke and M. Hewitson at
Preliminary measurements of the
General Standards DAC being used for the LASTI and 40M OMC controls show that
the output noise is slightly less than
10uV/rtHz on a 10Vp-p output.
Measurements were done using 32768 SPS. Further measurements and a
report will be concluded in the next several weeks.
From: Riccardo
DeSalvo desalvo@ligo.caltech.edu
Livia and John
We have been working on calibrating mirror tilts using an optical lever. Using our new calibration previous results appear closer to those from FFT simulation.
This week we completed a new analysis of previous data. Currently designing an experiment to simultaneously measure the angular position of our Mexican Hat mirror whilst recording the intensity profile of the resonating beam. We hope this experiment will bring this investigation to completion.
Valerio
Testing the new LVDT card, found a problem, but it seem to have better sensitivity than the previous version.
Marie, Mike K amd Mike F
More measurements on glassy metal Q factor.
For additional information about this report, contact Stan Whitcomb or Phil Lindquist