Weekly Report for
Week Ending August 17, 2006
Past Weekly Reports
There
will be no LIGO Executive Committee scheduled Monday, August 21, 2006 due to the LIGO
Staffing Committee meeting scheduled that morning. The next Executive Committee Meeting will be
scheduled Monday, August 28, 2006.
Special Announcements
Weekly Report Highlights
This
is a particularly brief status report due to the involvement of a large number
of LIGO personnel in the LSC Meeting held
this week in Louisiana.
This week we held a very successful LSC meeting at the Lod Cook
Conference Center
on the LSU campus. Attendance was around 170. In addition to the many formal
talks and informal conversations, several actions were taken. They include:
- The
LSC Executive Committee approved the S4 Stochastic all-sky paper.
- The
LSC Council approved, by large majorities, the applications for membership
from new groups at Andrews University, Rochester Institute of Technology,
and San Jose
State University.
- The
LSC Council enthusiastically endorsed the plans for Enhanced LIGO.
- The
LSC Council endorsed, by a large majority, the idea of close collaboration
with Virgo along the basic lines expressed in the current draft MOU. Many
good suggestions were made for ways to improve the MOU's
language.
At this meeting, we declared the official transition from the LSC's old structures to the new committees called for in
the Bylaws. In other words, we have now completed the LSC's
restructuring.
LIGO Laboratory Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
SITE TELECONFERENCE (Lindquist)
- There
was no site teleconference scheduled Thursday, August 17, 2006.
- There
are currently no open action items.
PROPERTY MANAGEMENT (Luna)
>
- Created
Property records for one server @ LHO and three servers @ LLO.
- Coordinated
the payment for taxes and duties to US Customs for the Gingin
equipment in Australia. Account Number LIGO.TEC-1.3-NSFLIGOFY02ON $9,814.80.
- Preparing
a Memorandum to clear old items from LHO's
inventory (eight Gateway computers).
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- No
special projects to report.
- Processed
two sets of drawings.
- Processing
presentations for the LSC Meeting this week at LSU.
- Scanning - Progress continues on scanning of
contract closeout files:
|
Week Ending
08/17/2006
|
In
|
Out
|
|
Packages
|
28
|
5
|
|
Faxes
|
23
|
17
|
FINANCIAL SYSTEMS (Funaro, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
>From: Florence Kaufman <fkaufman>
- Attended
a Sponsored Research Forum on August 8th.
- Noted
than incorrect expenditure types were for stipends paid to students traveling
to Italy,
which resulted in the imposition of $9000 in Indirect Cost. Corrections have now been made and the Indirect
Cost has been reversed.
- At
Ed Jasnow's request, started to work on a
process for a "Roll Up Signature
Mechanism" for the Payroll Distribution Confirmation (PDC) reports
that are required to be signed by Principal Investigators on a semi-annual
basis.
- Discovered
that we apparently have not received the Payroll Distribution Confirmation
report for the period from October 1, 2005 to March 31, 2006. These reports were supposed to have been
distributed on July 28th, and have to be turned in with signatures by
August 28th. Have requested a copy
of the report from Project Accounting.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence).
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- Four
bids were received for the machined parts for the LLO SEC outdoor wall
exhibit (kinetic facade). The bids ranged from $29,250 to $65,830. The low bidder, Scientific Fabrication
Service, Inc., of Plaquemine,
LA, was visited by Allen
Sibley and Janeen Romie,
and was found to be fully qualified to perform on this effort. A purchase Order will be issued to this
company this week.
- The
LLO Science Education
Center is nearing
completion, with beneficial occupancy scheduled for the end of this
month. At that point, an inspection
will be conducted and a punch list developed.
PROPOSALS and REPORTS (Lindquist)
No activity this week. We will soon
be modifying the budget model for FY 2007 to reflect organizational changes.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
- There
are no open change requests.
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- A meeting of the LIGO Staffing Committee is
scheduled Monday, August 21, 2006. The
agenda has been posted for Monday's meeting. All files are posted and up-to-date on
the web page.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
Nothing significant to report this week.
The LHO safety audit is planned for next week (Monday and Tuesday). The results of this audit will be reported
next week.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of S5 Activities at LIGO Hanford
Observatory (compiled by K. Kawabe)
Another very good week, with solid performance from both
of the interferometers.
Duty cycles this week (Tue Aug/08 to Mon Aug/014) were: H1 89.53 percent, H2
91.49 percent. Most notably, both H1 and H2 marked 100% duty cycle all day long
on Saturday 12/Aug.
As always, inspiral range of H1 was 13-14 Mpc at night, somewhat lower during the day. For H2, it was
7+ at night and 6.5-7 during the daytime.
There was no commissioning effort this week, although some maintenance activities
were done on Tuesday.
S5 highlights from the LHO elog are bulleted
below:
- The
only major maintenance this week was the upgrade of framebuilder
and testpoint managers. To resolve the awg instability problem reported last week, a first
attempt was made to move
two testpoint managers from two awg machines to fb0 as a single manager.
Unfortunately, since then CRC
mismatch errors began appearing, so we reverted back to the old
configuration. Since it was only on fb0, no data was lost due to this.
We're planning to give it a second try.
- H2
began showing some odd behavior once in a while (here,
here,
and here).
MC is locked to some odd position and the binary range drops to 2 Mpc. Reason still unknown.
- The
gain of H2 REFL1 was found to be 7 dB lower than it should be,
sometimes causing difficulty in getting to full power. A temporary fix was
made, a full fix is scheduled for next Tuesday
maintenance.
- Following
the fire drill from the week before, a contractor came on Friday to test
fire alarm sensors, making loud sound in control room. We
DQ flagged the SM data.
- The range and duty cycle update is available here.
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
No report.
Mechanical and Optical Systems
(Coyne)
No report.
Controls and Data Systems (Bork)
No report,
40-Meter Interferometer (Weinstein)
No report.
Thermal Noise Interferometer (Black)
No report.
LASTI (Ottaway)
No report.
CIT Science Group
(Lazzarini)
No report.
Laboratory Computing (Anderson)
LDAS Software Systems (Maros)
Work has begun on sunopteron and linuxopteron to get a fully functional /ldcg
for building LDAS. The process is slower than expected as changes are required
for 64 bit support for the opteron chip set. For
instance, sunopteron required gcc
4.1.1 to be installed to get a working C++ compiler.
Efforts to get TclGlobus 64bit working on
tandem-ii failed. After modifying the configuration scripts to be able to
build, it now appears that the code base itself is not 64bit clean.
Modifications to the cmonClient resulted in both
UWM and PSU have been removed from the server list (PR#3048) and an issue of cmonClient generating an error when displaying resource
differences on a platform without tkdiff (PR#3050)
being resolved.
The cntmonAPI was also modified. Database graphs
no longer incorrectly exclude non-X509 user connections (PR#3039). Also, the abortJob command for the "ALL USER COMMAND" test
is once again available under the username/password mode (PR#3038).
Some memory leaks for the getMetaData command have
been addressed (PR#3033).
Finally, the manager no longer leaks manager key into the log file
(PR#3043).
System testing of the LDAS software was done using version 1.8.270. Lsync continues to see RDSVerify
and some /scratch directories. Also ran Greg's createRDS
loop test on ldas-dev and got intermittent failures
due to frame thread callback sometimes failing to find .tmp
file. A new problem report was files describing this problem (PR#3040).
Additionally, changed password authority to emaros by updating the cntlmon
resource variable at all sites and tandems (PR#3037).
LDAS System Administration (Anderson)
Caltech
(Dan Kozak)
- Did
RLS cleanup for S5 Burst-MDC files.
- Did
some work with my new SAM dump to du script to
identify deletable data.
- Did
a throttled rm of some Laura Cadonati's
'trashcan' directories.
- Started
working on script to identify directories with lots of files in them.
- Worked
on LLO disk full condition (/archive).
While there were several problems, mostly human error
(/archive/backup/fb0_frames was marked archive -n from when we were rsync'ing to it, a couple of directories were pinned
to disk that shouldn't have been), there were some L0 files had not gone
to tape when they should have. I'll
start monitoring the logs from the nightly samfsdump
to try to catch this.
- Working
on repacking tapes at LLO from long ago (data strewn across many tapes
problem).
(Phil Ehrens)
- Upgraded
ldas-suntest5 and ldas-suntest4 to Solaris 10 upgrade 2. Documented upgrade glitches and required
workarounds. In general, it is inimical to the upgrade process to have
more than one submirror configured for a metadevice during the upgrade process, as the upgrade
process attempts to obtain exclusive lock on ALL existing local
partitions, as does the metadevice manager, so
that they are always in conflict when multiple submirrors
are defined.
- Reconfigured
filesystem on ldas-suntest2 to a mirroring
configuration. This required
copying 12Gb of files to a temporary location and
then copying them onto new mirrored partitions. I used the mv command to do this since it preserves links and
file ownership.
- Performed
extensive investigation of x509 certificate disposition on ldas gateway machines and began preparing scripts and
documentation for managing the critical certificates required for data
transfer and analysis.
- Cleaned
up a number of expired certs that were no longer
associated with any known activity. 54 certs or
links to certs were identified on ldas machines exclusive of user certs.
(Erik Espinoza)
- Deployed
kernel option "iommu=off" to first
rack (node1-45).
- Deployed
kernel option "iommu=off" to last 7
(node321-327).
- Attempted
to reproduce notification bug on frog (desktop), was actually a sendmail crash on ldas-grid.
- Re-enabled
Condor on node301-308.
- Created
home dirs for users on sunopteron.
- Enabled
snmp on Cisco 6509 switch.
- Crashed
nodes:
-
node246: 8/13
-
node143: 8/16
(Stuart Anderson)
- Successfuly tested a Linux kernel option to prevent
MCE GART errors on the LDAS-CIT Opteron cluster.
- Continued
testing of possible replacement memory for the LDAS-CIT cluster with mixed
results.
- Copied
the S4 Burst MDC frames into the LDAS-CIT cluster scratch disk space.
- Re-enabled
DedicatedScheduler in Condor pool to support
Parallel Universe jobs currently being used for numerical relativity MPI
jobs.
Livingston
(Dwayne Giardina)
- Ejected
tapes for shipment to CIT, imported and labeled
new tapes.
- Failed
disk in T3-4, replaced with disk from T3-16.
- Sorted
'failed' disks in T3-13 and T3-16, found 9 that were no longer reporting
as failed. placed
them all in T3-16 and built a new volume on those disks.
- /archive
reached capacity, disk2disk process were dead. Dan cleared up disk space, I restarted
disk2disk scripts.
- Organized
LDAS room, repackaged replacement parts, labeled boxes, removed most
cardboard containers from room, etc.
Need to make room for new tape storage cabinet.
- TempAlarm work, still trying to get email alerts
functioning properly.
Hanford
(Ben Johnson)
- Received
2160 tapes from disk-o-tape. We received the proper number, and they all
appear to be labelled correctly. I've only
checked the labels of ~1200 of them, but I assume the rest are ok.
- Discovered
the "ipfs" command, which should save
the ipfilter state table; good for reboots, and
reloading the ipf kernel module. Unfortunately, it does not work properly
on Solaris 10 U2 (or U1), due to what appears to be a Solaris bug (Sun doc
ID 5040248).
- DMT
monitors are now writing to the fb0_frames filesystem.
Work is still needed to move the backup script and LDAS+GC NFS mounts to
the new filesystem+dir.
- /frames@LHO is close to maximum capacity. Dave will
reduce the second-trend look-back to give us some breathing room.
- Assisted
MIT with getting the DiskCache dataFindSerer, and supporting processes, working.
General Computing (Wallace)
MIT
(Larry for Keith)
- Worked
documentation and getting things ready for the new sysadmin.
Livingston
(Dwayne)
- Created
GC accounts for a few more SciMon camp attendees
- Continued
training our spam filter
- One
WAP required power cycle
- Treating
a computer for spyware, scan is running now
- Discussed
new network setup with Shannon
- Applied
Windows updates to several computers, including security server
- Other
usual user requests and support
(Shannon)
- Set
up Solaris 9 & applied all current patches on the new V490.
- Installed
a substantial amount of software for the SciMon
camp this week. Installed this in
such a way that it should make setup of future DMT machines easier. This really needs to be done because the
DMT machines have never really been standardized at LLO.
- Updated
the IDS rulesets to catch the new microsoft vulnerabilities.
- Updated
the LHO CDS IDS as above.
- Worked
all day tuesday with
the fiber subcontractor for Charter.
- Did
some troubleshooting on the auditorium lighting with a Leviton
tech. Spent a couple of hours
trying to determine what we thought the problem was. We think we know where the problem is
and Allen is working on getting a replacement part and/or a tech out to
repair it. Lighting is done by
bypassing the unit for now.
- Poured
through the IDS logs.
- Put
together a rough drawing of the future network topology as part of the
planning for the new backup connection.
Spent some time going over the planned changes with Dwayne. Monday I will have to meet with Boyd at
LSU to discuss the changes.
- Investigating
switch software on the foundry switches.
Need to find out just what kind of MAC filtering they can do, or
perhaps 802.1x.
Hopefully they can do auto-assignment of VLANs
based on MAC address.
- pcard & travel reports,
etc.
Hanford
(Christine)
- PNNL
will have a power outage to upgrade their cooling and power distribution
systems which will take down the LHO primary GigE
network. The primary network will be down from 3 p.m. 8/18 through 10 a.m.
8/21. The backup FastEthernet network is now
working and will become the primary network during the above mentioned
times.
- Ran
some more tests on the backup network over the weekend. I was able to determine that with the FastEthernet interface card on its own controller on
the router the backup network worked for all outbound traffic, but not for
incoming traffic. Further tests
showed that ESnet did not automatically route
our IP addresses to the backup network.
- Worked
with ESnet on Tues. 8/15 to manually
re-configure the routers on both ends to route traffic on the backup
network. This worked with out
errors. The plan is to manually
re-configure the routers to use the backup network at 3 p.m. on Fri 8/18
and then about 10 a.m. Mon. 8/21 manually re-configure the routers back to
using the primary GigE network.
- Meanwhile,
PNNL was able to find an alternate fiber path for the backup network that
does not go through the same building and switches as the primary
network. The existing media
converters worked on the new fiber path.
This is a permanent change.
So now our two networks take separate paths from PNNL to Seattle.
- Notified
Dave that his CDS intrusion detection system is sending emails to the GC
root account. Dave is working with Shannon to fix this.
- Straightened
up the server room and computer user room for the upcoming safety audit.
- Still
working on the vulnerability report and the Linux NIS+ client.
CIT
(Mike)
- Continued
work on DCC's webserver
trying to get SSL to work. This is
an on going project. This has something to do with the way the webserver & SQL server comunicate
with each other. I have put in a call to File Hold's tech support
regarding this issue.
- Still
working on a Sun workstation for the W/B control room.
- Continued
work on maintaining our mail servers with Larry W.
- Swapped
out Bruce Sears with a new Sun workstation & monitor.
- Working
the spam filers searching for false positives.
- Surplus
old equipment, working with Larry and Rod on this.
- Other
misc. user/surf student support.
(Veronica)
- LIGO: Website updates. Roster database updates. High-resolution images for an online
project of NSF-supported observatories.
User support.
- LSC: Website updates. Posting the talks of the August
meeting. Keep working on the LAAC
website. Updates of the LSC-related
mailing lists.
(Christian)
- Installed
new 24 inch LCD monitor for Julie Hiroto and
Cindy Akutagawa.
- Irene
Baldon - Replaced toner and drum kit on Irene's
local printer.
- 3flr
W/B - Replaced toner cartridges on HP 5500 printer.
- Working
on creating and configuring Linux and Windows XP image on a Macbook Pro with Parallels software. Also, trying to
run Linux on a new Dell workstation with a 30 inch monitor.
- Worked
on the Spam Filters with Mike and Larry.
- Other
misc.: Continued onsite software/phone support.
(Larry)
- Worked
a number of procurement issues.
Sent in the list of items for the Foundry maint.
contract renewal.
Purchased a couple of notebook computers. Have a few more to order
and at least one more workstation to order. Working on a SUN disk system
order but this is still some time away.
Purchased a number of misc. items for people. Also, purchase a hard
case for notebook computers, will purchase a couple more, these are for
those that will be traveling to areas that will not allow the notebook as a
carry-on. Resolved the Primavera
payment issue. Helped Gina with the
new copier procurements. Spent a
number of hours doing the P-card reconciliation. The biggest problem this
time was getting invoice information from Dell.
- Assisted
Rod and Mike with some of the GC equipment removal. Mostly, getting a lot
of the old stuff put into a central location. Also, working with Rod on getting
equipment to foreign locations.
- Assisted/Assisting
Mike on a couple of OS installations.
- Working
with Christian on getting the 30inch monitor setup working in a LINUX
environment. The difficulty is getting h/w that will work in the space of
the display case and will drive the monitor.
- Assisted
the DCC with a number of issues. Most dealing with the new system.
- Checking
out the SURF students as they leave to their home institutions. This is
taking a little more time in-that many of them are getting extensions for
their accounts.
- Worked
a couple of small GC issues for the MIT group.
- Assisted
a number of users with different issues. Including plans for new setups
and logistical issues covering travel.
- Worked
the mail servers. The spam storms and people sending large files are still
causing problems with the system to where we have to monitor it on a
regular basis.
Mail Statistics for August 10-16, 06
|
Mail Statistics
|
8/17/2006
|
|
Rejected Messages
|
30,254
|
|
Virus Messages
|
1,683
|
|
Accepted Messages
|
21,356
|
|
Total Messages
|
51,610
|
Advanced LIGO and Supporting R&D (Shoemaker)
No report this week.
For additional information about this report, contact Stan Whitcomb or Phil Lindquist