Weekly Report for
Week Ending August 3, 2006
Past Weekly Reports
The LIGO Executive
Committee Agenda for Monday,
August 7, 2006 will be:
(Meeting time: 10:30 am Pacific Time)
1. Announcements
2. Comments
on weekly report
3. LSC
Issures (Saulson)
4. LIGO
Lab Operations
- Administration
(Lindquist)
- Sites
(Raab, Zucker,
Shoemaker)
- Commissioning
(Fritschel)
- Optics
and Mechanics (Coyne)
- Control
and Data Systems (Bork)
- 40m
(Weinstein)
- TNI
(Libbrecht)
- LASTI
(Ottaway)
- Lab
computing (Anderson)
- Science
Group (Lazzarini)
5. Enhancements
(Adhakari)
6. Advanced
LIGO (Shoemaker)
7. Change
Control Board/Technical Review Board Session as needed
Special Items:
Special Announcements:
Weekly Report Highlights
Dot Lloyd was busy this week (with support from Szabi
Marka, Albert Lazzarini,
and Peter Saulson) posting all of the contributions
for the LSC MOU Review Panel meeting to be held 8-9 August at MIT.
Final arrangements are being made for the LSC meeting the following week at
LSU.
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
SITE TELECONFERENCE (Lindquist)
- There
was no site teleconference scheduled Thursday, August 3, 2006.
- There
are currently no open action items.
PROPERTY MANAGEMENT (Luna)
>
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
- Continued
to migrate the DCC database metadata over to the
new Filehold system.
- Two-thirds
of the DCC database has been allocated to a specific one-to-one location
in the Filehold system. The remainder will be completed by
Monday morning.
- Had
status meeting with Filehold regarding
development progress on their side, data conversion on ours. We are on schedule to have full LIGO
functionality demo for upcoming LSC meeting.
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- Continued
to assist in the process of conversion/allocation of current data to the
new database.
- In
the process of determining if all of the latest revisions of the PSI
As-Built drawings are on file in the DCC.
- Scanning
- Progress continues on scanning of contract closeout files.
- Activity:
|
Week Ending
08/03/2006
|
In
|
Out
|
|
Packages
|
15
|
6
|
|
Faxes
|
14
|
5
|
FINANCIAL SYSTEMS (Cronin, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Completed
change order #6 to Lawrence Berkeley National Labs. Coordinated the wire
transfer payment to the vendor for the past due charges for FY05, and for
the new FY06 period.
- Received
the large-dollar purchase order for LHO issued to Disk-O-Tape back from
routing, and the purchase order was sent to the vendor.
- Working
on the order for the ILC brochure.
>From: Florence Kaufman <fkaufman>
- Completed
and posted the report for Operations as of the end of July on the network.
- Working
on an Inter Award Cost Transfer to correct the charge for a Post Doc in
the Detector Group, for the period from September 05 through July 2006,
from 100% to 50%.
- Working
on an Intra Award Cost Transfer to move p-card charges from the MIT
account LIGO.ADISC/5.6 to LIGO.ISCA/5.
- Working
on an Intra Award Cost Transfer to allocate a portion of the cost paid in
July for the Solid Works Designer from Task 5.22 to Task 5.10.
- Alerted
Cindy that costs charged to the Visitor Award for students sent to Italy
were charged to an incorrect expenditure type, which resulted in the
imposition of $9000 of unwarranted Indirect Cost. Will work with Human Resources
Department to get it corrected.
- Notified
Cindy that travel expenditures were paid for students sent to Italy,
according to Cindy no travel expenditures were to be paid. She is to work with Irene to see how
this can be corrected.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- The
contract with Lawrence Berkley Laboratories to provide network services to
the Hanford Observatory has been extended to September 30, 2007. The $12,000 fee for the coming year was
paid in advance as required by DoE laboratories.
- The
State of Louisiana
now has a new tax exemption form which essentially provides the same
category exemption as our letter from the Department of Revenue, i.e., we,
and our subcontractors, are acting as agents of the Federal
Government. We are finding that our
letter is acceptable in some cases, and others require the new form. In the latter case, the form simply
needs to be signed by an authorized Caltech representative, who may be
designated members of the LLO staff.
PROPOSALS and REPORTS (Lindquist)
- Submitted
the Annual Report for LIGO FY 2006 Operations to the NSF.
- Submitted
a Proposal for a Supplement to the LIGO Operations Cooperative Agreement
to the NSF. The Supplement is for a
small amount of funding for materials to support the LIGO Video,
Einstein’s Messengers.
- Assembled
a summary of LIGO Laboratory contributions for the LSC MOU Review and
submitted it to P. Saulson. Late additions will be inserted as needed.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
The LIGO Change Control Board met Monday, July 24, 2006 as part of the
normally scheduled meeting of the Executive Committee. Two change requests were discussed:
- CR-060006
is for funds to buy enough data storage tapes to get through another
calendar year of S5 data acquisition.
The board recommended approval.
- CR-060007
adjusts the FY 2006 budgets to reflect actual staffing through June 30,
2006. The board recommended
approval.
The board recommended approval as indicated and the change requests have
been signed. Minutes of the CCB meeting
have been prepared, and an electronic version has been provided to the DCC
(LIGO-M060114-00-P). The original signed
versions of the change requests have been filed in the Document Control
Center.
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- No special activities to report.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
Nothing significant to report this week.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of S5 Activities at LIGO Hanford
Observatory (compiled by M. Landry)
Sufficient time has passed since the swap of the PMC and associated servo
card (last week Tuesday) to confirm that the work was a success and that the
glitch rate previously observed in photodiodes on the laser, the PMC error
point and other PSL channels such as ISS ones is significantly reduced (see elogs here
and here
for example).
Duty cycles for the LHO machines this week were: H1 84 percent, H2 92
percent. Some of the downtime on H1 is
accounted for by periods in which PMC gains had to be reassessed, i.e. we
expect that as the running conditions for this subsystem stabilize, future
impact on the duty cycle should be negligible.
Processes on the h1awg0 machine that serve excitations to the 4k IFO became
unstable last week; all injections were turned off temporarily, and this week,
burst/inspirals restored. The awg
processor has remained stable since. Historically during S5 h1awg0 has had
periods such as this, in which excitations such as pulsar injections fail but
cal lines remain. Why the processes stabilize is a mystery.
S5 highlights from the LHO elog are bulleted
below:
- a study
to chase a wandering RF bump observed in the LVEA radio channels was
performed during the Tuesday maintenance period
- Final
tallies for usage of the IFO maintenance budget for July were, including a
slight overage on H1: 25h 25m H1, 11h 25m H2.
- the range and duty cycle update is available here
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
LIGO SEC Kinetic Art Project (Romie)
Four RFQ packages have gone out to local machine shops and four other RFQ packages
have gone out to local welding shops. Comments
are due Friday, quotes due 8/11. Procurement of individual items on the
BOM is ongoing.
Mechanical
and Optical Systems (Coyne)
Most of the group’s efforts are reported under the Advanced LIGO Project.
- Migrated
the PDMWorks vault server from 2005 service pack
4.1 to 2005 service pack 5.0. Connecting to the
vault server prompts a request to upgrade. The new service pack seems to
be working fine.
- Considering
an update to our SolidWorks seats (from SP3.1 to
SP5.0). This will be coordinated with LSC partners.
- Liyuan, Lee, GariLynn
continue measurements on scatter loss on initial LIGO optics.
- We’ve been informed that the current LIGO
document revision sequence (defined for example in section 4.8.7 of
Drawing Requirements, E030350-A) will be changed in favor of the FileHold revision sequence/approach. Engineering needs
to determine the consequences and implications of this change. The hope is
that by using the FileHold built-in approach, we
will have a more error-free and seamless revision control. On the other
hand, we use our version code to indicate other metadata (e.g. B2
indicates that the drawing has been formally released into configuration
control with a DCN and it is the 2nd schematic revision to the B revision
artwork for an electronics drawing). A means to adapt our configuration
control procedures to the FileHold document
control system needs to be developed.
Controls and Data Systems (Bork)
See Advanced LIGO.
40-Meter Interferometer (Weinstein)
All the SURF students have prepared five minute talks for their trip to LHO
and are off on their junket.
IFO Commissioning, Electronics, Controls, Computers
- Rana and Sam are going through the LSC RFPDs and re-phasing them (since the cables have all
been modified to strain-relief them). Several single demod
RFPDs have been rephased.
They are encountering difficulty in phasing the double demod
signals. Work in progress.
- Steve
is measuring the response of the electronics chain from RFPDs to mixer to whitening boards to ADC, by
injecting signals at different frequencies. He's getting the response he
expects, dominated by whitening board TF.
- Royal
measured the oplev P/Y dark (electronics) noise.
She got generic whitening boards from Wilson House and will modify and
implement them for all 4 oplevs, to try to
reduce the electronics noise.
- Royal
measured the laser intensity noise of all 4 oplev
lasers. She also measured the TF from input current to output power. Power
could be modulated up to high frequencies, > 100 kHz. But intensity
noise is not quite a problem right now.
- Royal
finished measuring the mirror motion due to servo for all 8 DOFs. Made a noise budget for all of these. And then
through to DARM at the DC PD.
- David,
Jenne and Sam have implemented the new MC servo
board; this required rewiring and debugging of the cross connect wiring,
testing of digital controls with tester boards, testing of the board, etc.
All seems to work ok, but there are problems with readback
of some MC signals (err point, fast channel, and MCL monitors) into the
EPICS screen.
- The
MC is now locked and working fine. After some PD phasing and tuning, they
measured the MC loop gain: the UGF is up to 80 kHz. It could be better: the
MC OL gain has odd resonances at ~80, 90 kHz, and seems to fall off at
~230 kHz, probably due to PMC. Darcy will measure the PMC finesse. One day
we'll replace the PMC with a low finesse one. Sam says that more gain
could be obtained by further tweaks to the AOM, but this is difficult to
do because of all the stuff in the way on the PSL table.
- The
MZ stopped locking. Sam, with help from Jenne,
David, and Rob, debugged the system and found a bat XYCOM cable connector.
They gave it a good squeeze, and the MZ is now behaving.
- David
constructed some insulating houses for the OSAs
on the AS ISC table. The temperatures on the OSAs
are being monitored and logged. Steve will also move the particle counter
to that table; it has a coarse temperature readback.
David will watch all these, and the OSA display, to see if the temperature
fluctuations are real, are reduced by the insulation, and/or are correlated
with the OSA peak drifts.
- Jenne's AM laser is all put together with flex tubing.
She used it to check the MZ RFPD. She will measure all the RFPDs when she gets back from LHO.
- Dan
and Monica rotated the MC WFS's by 45degrees a
few months ago, and has now changed the MEDM
screens to correctly represent this. He needs to also change the MCLock screen, DC signals.
IFO Modeling
- Jenne has completed a working Simulink
model of the radiation pressure-induced angular instability in the mode
cleaner, and has checked her results against the predictions from Sigg's paper. She will generate OLTFs
with different input powers; the pitch/yaw pendulum response will be
altered in the presence of the optical torques. She'll then try to measure
these with the real MC, again at different input powers and different
angular offsets of the mirrors.
- Osamu
is working with Kentaro on alternative length
control schemes for AdLIGO. They are exploring
different RF sideband configurations, and also ways to implement variable
signal detuning. So far, 9 and 45 MHz works with
fixed signal detuning, but implementing variable signal detuning is more
difficult. He is preparing a talk for LSC meeting.
- Seiji
learned the current lock acquisition procedure from Rob, and is
documenting it and studying it in simulation (Finesse) to see how our LA procedue works and how to improve it.
DC Detection and Vacuum Squeezing Development
- Darcy
and Rob disassembled the DC readout beamline and
gave all the parts to Bob. Now they're preparing for re-assembly and
realignment on the clean room flow bench. They are running the NPRO laser
through fiber to get it to the clean room.
- Bob
has been preparing detailed travellers for all
the DC readout parts. All parts cleaned, OMMT in for bake; will put all
the OMC and other parts in by the end of the day. Baking copper at 120;
anneals at 145. Working on in-vac cables and
connectors.
- No
report from the Wilson House group; they're at a meeting at MIT.
- Shally and Go made lots of progress on the vacuum
squeezer. They Rebuilt the OPO oven and cavity. They still saw elliptical modes,
but then they turned the (ostensibly spherical) output coupler, and got a
circular mode. They temperature-tuned the OPO by maximizing green output.
More alignment and temperature tuning got parameteric
gain up to 7.8. They set up the homodyne detector with fiber-fed LO and
seed field. Fringe visibility of 88%; good, to be improved. They looked
for squeezing by dithering the seed beam path length, and antisqueezing observed. Hopefully can see squeezing
soon. With 3dB of squeezing, they will do quantum noise locking to lock
the squeeze angle and the OPO.
- Latest news: they now observe 1 dB of vacuum squeezing
(and anti-squeezing). This is the
first observation of CW squeezing at 1064nm with PPKTP in the world. The seed was completely blocked. So, this is the observation of pure
squeezed vacuum.
Lab Infrastructure, Bake Lab
- Dan continues to flesh out the new 40m Wiki. He
encourages anyone who pulls out a board to take a photo of it for the Wiki.
Thermal Noise Interferometer (Black)
No report.
LASTI (Mittleman)
ISI Assembly
We have succeeded in floating the first (with the second stage pinned to it)
stage. The spring stiffness was not what
we expected; it came out about half way between the ASI values and the values
that we measured on the spring tester.
We will have to look into this further.
After adding some weight we were able to get the platform to be level
and at the correct height.
Jay has delivered and tested the first position sensor controller. It is now working on the bench, installing
and aligning them is going to be challenging.
Quad-Pendulum Controls Prototype
Brett is preparing for our next vacuum incursion. All of the components for
the quad-structure thermal test have been assembled and are in the cleaning
process.
CIT Science Group (Lazzarini)
No report.
Laboratory Computing (Stuart)
LDAS Software Systems (Maros)
The ldas-dev system is now building 64-bit
libraries for Solaris. These have been running each night for the past week
with 0 errors. Currently the Tcl Socket interface is
being used to submit jobs as there have been some issues discovered with
compiling tclGlobus for 64-bit. These issues should
be resolved soon.
The cmonClient has been enhanced to display a
message of bad passphrase instead of the full text as
returned by grid-proxy-init. This makes
error message easier for the user to understand. Also, a timeout value to gt_xio_socket calls has been added. The length of the
timeout is controlled by the resource variable ::TCLGLOBUS_SOCKET_TIMEOUT.
Lastly, printing of graphs is being modified to allow queuing. This
eliminates wasted banner pages.
When users are identified to have an invalid login to the ldas system, a message directing the individual to contact
Edward Maros instead of Kent Blackburn is now
generated.
The system tests were performed using version 1.8.256 of LDAS. All the tests
except for lsync passed. The lsync
test still is unable to see RDSVerify and some
/scratch directories. This continues to be under investigation. The socket
tests for 64bit Solaris to 32bit Linux were run. The results were similar as
those with 32bit Solaris.
LDAS System Administration (Anderson)
Caltech
(Dan Kozak)
- Continued
working on scripts to collect stats about the files in our filesystems from the nightly samfsdumps
(ongoing).
- Collected
data to guide our policy for releasing files in /home at CIT.
- So
far my modified nfsfind on gateway at CIT has
reported only 3 .nfs* files found. I'm going to wait until early next week,
but I think the normal find and delete cron job
should only be run once a week.
- Did
more work with the Sun 15k drives (so far they seem to have no advantage
over 10k drives for us). Waiting
for Phil to finish with samtest to continue.
- Fixed
damaged SAM-QFS files at CIT that are now being
reported by log_mon.
- Set
up /scratch on ldas-suntest4 (as per Mary Lei).
- Generated
tape list for shelf storage at LHO.
- Compressed
many of Alexander Dietz's files (ongoing).
(Phil Ehrens)
- Completed
portability enhancements to certcheck.tcl and shasumcheck.tcl and installed them into ldas-sw. The shasumcheck and certcheck
scripts are running on an ever-increasing number of machines as they are debugged.
- Worked
with Mary Lei to configure the ldas-tandem4 system to be similar to the
ldas-tandem5 system. ldas-tandem4 had previously
been configured for a special purpose.
- Various
and sundry x509 certificate related tasks.
- Ongoing
attempts to install Solaris 10 upgrade 2 via the "upgrade" path
are proceeding slowly. There are still unknown dependency issues that
require the use of a backup device when upgrading on some machines.
- Discovered
a number of expired certs on the machines kitalpha ad ldas-cit. Currently evaluating the significance of these
apparently long unused certs and whether they
should be replaced or simply removed.
(Erik Espinoza)
- Begun
work on ldas-kickstart at MIT.
- Corresponded
w/ Supermicro about ram shipment.
- Created
gpg keys, asked Shannon
for copy of Nessus scan.
- Looked
into ldas-pcdev1/ldas-grid grid-mapfile issue
with Phil.
- Tested
Infineon ram shipped (accidently
shipped by ASA).
- Node264
rebooted on Mon July 31, will be replaced w/ node326 upon next crash.
- Clean
up of Condor crash July 29.
- Will
begin syncing of kickstart at LLO for Dwayne.
(Stuart Anderson)
- Helped
track down cause of last Condor crash.
- Worked
on Cyber Security Vulnerability report.
MIT
(Keith Bayer)
- pcraid 5 board appears dead
with the unit out of warranty. Will
try to swap drives over to another pcraid unit.
Livingston
(Dwayne Giardina)
- Ejected
tapes for shipment to CIT, imported and labeled
new tapes.
- Added
entries to /etc/hosts for new nodes and kickstart.
- More
cluster_mon additions/changes.
- Received
warranty check on seagate drives from T3s--not
supported.
- Unleashed
another email flood from the nodes after power outages. Caught my mistake this time and
hopefully it won't happen again.
Hanford
(Greg Mendell)
- Major
gaps in 1800 second SFTs from the beginning of
the S5 run up to the present have now been filled in. These SFTs are being generated and published for the pulsar
group. The generation and publication of these SFTs
is continuing to run in real-time, with the transfer of the SFTs from the sites to Caltech occurring via LDR.
(Ben Johnson)
- Purchased
workbench/shelving and several plastic containers to help organize and
cleanup the LDAS room. Commenced LDAS room cleanup.
- Working
on ipfilter instructions and setups for LLO,
MIT, and CIT.
- Found
a good guide on creating a SMF manifest for RPC service-dependent firewall
rules.
- Last
of blank 9940 tapes moved to the LDAS room to acclimate. There are now a
total of about 18TB of blank tapes left (includes blanks in the library).
- Aided
a few cluster and LDAS users, mainly dealing with the perennial question,
"How can I access data?" and "I am having trouble with
accessing data set X."
General Computing (Wallace)
MIT:
(Keith)
- Troubleshot
webserver that had scsi drive not responding errors. These errors are strangely similar to
the powerd trouble on solaris
10 although I haven't changed any configuration on this solaris 9 box in some time. A simple reboot brought everything back.
- Continue
working on replacement sys-admin stuff
- Documenting
various systems
Livingston
(Dwayne)
- Created
GC accounts for a few SciMon camp attendees.
- Continued
training our spam filter
- Other
usual user requests and support
Hanford
(Christine)
- Most
of the week spent working on the Cybersecurity
Vulnerability Assessment report.
- Moved
some home directories around to alleviate a full disk.
- Renewed
the maintenance contract for one of the personal Matlab
licenses.
- Downloaded
the latest VPN client from Caltech.
CIT
(Mike)
- Finished
up loading Melody Araya's Sun workstation and swapped out her old Sun
workstation with the new one.
- Worked
on loading DCC servers, one as the web server the other SQL server. There
is more work to be done on these servers. We are in Demo mode right now.
Engineers from File Hold are looking into the many configuration issues we
came across.
- Worked
the spam filters.
- Loaded
a Sun workstation for Bruce Sears.
- Ran
End of month ghost backups on all critical NTSRV's.
- Started
loading an X2100 Sun server.
- Added
an additional printer to our print spool for Syd.
This printer can be used for Synchrotron as well.
- Other
misc. user support and additional work in the B/A server room.
(Veronica)
- LIGO: Working on the website for Academic
Advisory Council. Troubleshooting
the database on the back end.
Building a database update tool.
Updates to other LIGO-related webpages. User support.
- LSC: Updates of the database of papers under
review. Updates of the LSC webpages and mailing lists. Continue working on the database of the MOUs. Advised
Keith Riles on the setup for videotaping the scimon
seminar at the upcoming LSC meeting.
- Project
Science: Web updates.
(Bruce Sears) (1.0 days)
- General
iLog maintenance (user adds, keyword adds,
systems work, etc.) - Fixed the user-add admin tools at LHO (broken when
the web server
was switched.)
(Christian)
- Dorothy
Lloyd- Created a backup of Dot's workstation.
- Cindy
Akutagawa- Helped Cindy print
a mail merge document in word.
- 3flr
W/B - Replaced toner cartridges on HP 5500 printer.
- Ken
Mailand- Restored backup image of Ken's
workstation after the registry became corrupted.
- Configured
new workstation and laptop with the standard ligo
image.
- Worked
on the Spam Filters with Mike and Larry.
- Other
misc.: Continued onsite software/phone support
(Larry)
- Procurement
issues still taking time. Finally,
received some information from Foundry. I have a few items I need confirm
before I get a quote from them.
Checked on the order for a couple of workstations and still working
on the quad cpu sandbox
order. Tracked down a number of
items that were ordered last week. Some were just delivered to the wrong
location and one was lost in the shipping process, replacement has since
arrived.
- Took
care of a couple of licensing issues.
Still have a issue being worked on with
the SUN backup s/w license. That should be resolved soon since I have
copies of the paperwork verifying we do own the license. Renewing the Comsole
license.
- Worked
with Mike on the Solaris installation on various boxes. Updated the h/w on
a couple of the SUN boxes. Also, helped him out on the setup of a new printspool for a printer that has been relocated.
- Worked
with the DCC, Mike and FileHold in dealing with
the installation of the s/w for the new DCC system. A lot of time has been
spent on this by all parties.
- Continual
user support. Regular account modification, e-mail changes and application
support. We've had another visitor
show up and another SURF student. Both of which I need to still setup
accounts for once they've turned in the paperwork. Resolved a number of hardware issues for
different people. Most have been driver issues but there were a couple of
items in-which the h/w itself no longer functions.
- Worked
on documentation for various items.
- Worked
a number of e-mail issues. Spent time with Livingston
getting rid of a internal spam storm. People are still sending out large
e-mail messages which has causes problems
especially when we are getting large amounts of spam.
Mail Statistics for July 27- Aug. 2, 06 (Doesn't include the internal spam
storm)
|
Mail Statistics
|
08/03/2006
|
|
Rejected Messages
|
35,706
|
|
Virus Messages
|
1,335
|
|
Accepted Messages
|
28,423
|
|
Total Messages
|
64,129
|
Advanced
LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Systems
Systems
from Dennis
Coyne
See also:
AdL Systems wiki web page
AdL
Systems email archives
Records
Of Decisions or Agreements (RODA) status web page
- Assisted
Justin Greenhalgh with the nonlinear impact
dynamic analysis of the earthquake stops for the quad suspension and
interpretation of impact test results.
- Provided
weld non-destructive evaluation & cleaning qualification guidance to
RAL for the quad structure (to be included as an
update to the Generic Requirements and Standards for Detector Systems, E010613-01).
- Advised
the SUS/UK group that the beamsplitter
suspension structure design should be approached as a minimal enclosure
around the suspended mass chains, stiffened with stays or struts to the
optics table (rather than making the suspension frame considerably larger
in an attempt to meet stiffness requirements). This approach is possible
since the layout has eliminated the two pick-off mirrors in the BS
chamber.
- Provided
FTIR rinsate guidance to G&M for the HAM-SAS
prototype cleanliness qualification (using high purity isopropyl alcohol).
- Assisted
MIT summer student with finite element modeling questions for the triple
suspension (to be joined to the HAM-SAS dynamic model)
- Reviewed
and approved solid model to be used by Flomerics
in analysis of the BSC in-chamber, laminar air shower concept (a concept
proposed by Riccardo DeSalvo;
see pg. 14 of G060130-00)
- Received
cable clamp liners for LASTI & 40m Lab (composed of the low outgassing flourel
formulation); to be put in the queue for vacuum baking
- Assisted
in writing the Enhanced LIGO review committee report
- Optomechanical layout meeting scheduled at LSU/LLO
just after the LSC meeting, Thu 8/17 late afternoon and Fri 8/18 morning
- Working
on the Quad Suspension Preliminary Design
Review #3, committee’s report
- Working
to finalize the ETM wedge angle (with GariLynn
Billingsley and Mike Smith). The angle is needed very soon for the quad
noise prototype suspension. The basic issue is whether to dump the first
few ghost beams in the beam tube baffles or in an arm cavity baffle. We do
not want the beam to hit the cyropump surfaces.
In initial LIGO the ETM wedge is large (2 deg) and the beam is separated
from the main beam before the cryopump &
beam tube.
Vacuum Compatibility
Vacuum Preparation & Residual Gas Assay (RGA)
See also the Vacuum Bake Lab
Bob Taylor
- I
have received the cables from Ken and I will not be able to get them in an
oven until Monday due to the multiple bake jobs that are in progress from
the 40m DC detector Project.
- I
have completed the stainless conflats bake out
for Ken at MIT
High-Irradiance, Contamination-Exposure Cavities
Lee Cardenas, Liyuan Zhang
Cavity # 1: OTF Lab. at W. Bridge: No Change.
[Still measuring absorption & total
loss on wire sample daily. Ready for new sample.]
Cavity #2: No change
Cavity #3: OTF Lab at Lauritsen
Room 38:
A HAM-SAS stepper motor assembly is in the cavity. The
cavity is locked and we are taking measurements every day for absorption and
ring down. Preliminary indications are that this unit is clean. We will
continue taking measurements until the test is completed.
Scatter/Absorption Test Measurement:
The new 1.0 watt HeNe laser from Melles Griot has been installed
and aligned. Performing a test to measure the noise.
AdvLIGO LSC/ASC design using FP arm model with
quad suspension (Osamu, Hiro)
If electronic noise of WFS PD
is tuned to high power case, relatively the electronic noise with low power
will be high. In AdLIGO, high and low power ratio has
a factor of 1000, so it is interesting to see noise performance with low power
case, specially control noise for penultimate mass due to the f^3 filter. I am
adding electronic noise to the model and if noise is over the dynamic range,
actuation to test mass should be considered.
Static IFO simulation (Hiro)
The effect of mirror surface aberration was studied further. Summary and
support figures are available in www.ligo.caltech.edu/~hiro/AdvLIGOSim/COC. In short, the rms of the surface roughness needs to be required to be
less than 0.5 ~ 0.6 nm. With this requirements,
statistically 10% of the surface can have loss more than 25ppm. There is no
simple figure - rms or p-v in central region or
coefficient of zernike
polynomial - found which is strongly correlated to the loss.
The code development is going. Better lock point finding, faster relaxization of field, better beam setting, lens in mirror
out of various sources, dual recycled Michelson.
Modeler (Hiro, Bruce)
Bruce stated to learn how instances of primitive objects are created on the
fly when the simulation runs. With this
knowledge, he will implement primitives with variable inputs and outputs.
Mechanical Simulation for advanced LIGO (Sany and
SLU team)
(1) E2e modeling (Quave and Yoshida)
MC transmitted light?s
pitch spectrum computed by our e2e model shows much higher peaks near SOS pitch
and position resonance than the corresponding DAQ signal. On the other hand, MC
transmitted light’s yaw spectrum computed by the same model is very close
to the corresponding DAQ signal. Obviously, this is due to the fact that the
pitch local damping is not as good as the yaw local damping. So we started to
modify the local damping of our SOS e2e model. To begin with we made a simple
damping servo model. Initial tests with step inputs to suspension point z
(normal to optic) and yaw look good. Also with the same ground motion as
before, the pitch and position peaks in the optic’s motion are much lower
than before.
(2) Outreach (Sutton, Anderson, Norwood, Parkinson and
Yoshida)
Sutton and Anderson drafted lab procedures for six LIGO SEC exhibits (Giant Slinky,
Standing Wave, Variable Length Pendulum, Pipes of Pan, Hot Light Exhibit and
Soap Bubble Interference). These procedures will be discussed among Southeastern
LIGO Outreach team members in the next few weeks. The master copy of the draft
is available at LLO. We will keep updating this copy as we revise the draft.
The procedures will be tested in our Physics Lab courses for non science majors
in the fall semester.
Seismic Isolation
BSC Seismic Isolation Assembly and Test
The springs and rods for stage 0-1 and stage 1-2 have been installed. Before
floating the stages we instrumented the system with 3 sets of dial indicators
from stage 0 to stage 2. Each "corner" has a vertical, radial and
tangential indicator. The system was initially set up to accommodate the softer
spring constant that we measured on the spring tester and the original blade
launch angle. This translated to ~550lbs less then the nominal load on stage #2
and -150lbs removed from stage #1. When we started to release the 0-2 pin we
found that the platform wanted to rise by about 100mils, we added 349lbs and
were able to bring the optics table to its nominal position and level to within
.001" over the table surface.
The next step is to float stage 1 separate from stage 2 and to set the
locator stops. We found that tooling will be required to hold the locators in a
locked position before they can be installed.
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
Provided the annual update of the LIGO Lab input to the
LSC MOU Review/Planning Process. Norna
provided helpful comments and edits. Thank you Norna.
Coordinating with Gregg and Doug on how best to fix the
broken quartz wire standoff on Gregg's thermal noise experiment optic.
Doug will handle the regluing as spare standoffs are
at LHO. I will send more music wire to Gregg from the same spool as the wire I
sent originally.
Provided an ITM drawing to Gari
Billingsley for review. Talked to Helena about upcoming visits/meetings to coordinate
the ribbon/fiber/welding/bonding/ear development and deployment for noise
prototype.
Updated the LASTI Controls Test Document. Will update it again with the blade ECD damping test.
From: Ken Mailand kmailand@ligo.caltech.edu
I'm using the latest information from Ian and working on a lower quad
installation arm shop drawings, also a 'conveyor' version to be used at the
LASTI site. The existing 5 axis fixture
has been disassembled, the table and other parts are at the paint stripper, the parts will be chrome plated next week for use in the
clean area.
I'm working on the DLC mounts, the PO Telescope, and cavity beam dumps for
Mike Smith.
Core Optics
From: Bill Kells kells@ligo.caltech.edu
From: GariLynn Billingsley
<Billingsley_G@ligo.caltech.edu>
From: Helena Armandula ahelena@ligo.caltech.edu
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
I have been going over the design and implementation of various digital filter
topologies for programming the DSP since I ran into a limit with the canned
routines.
I completed stuffing an interim-power photodetector
board. I hope to test it later this week.
The interfaces for the frequency shifter is being
added to the PSL interface.
Controls, Data systems
From: Rolf Bork rolf@ligo.caltech.edu
AdvLigo
- An
AdvLigo CDS design and planning meeting was held
this week at MIT.
- Lasti ISI: Capacitive position sensor chassis and 4
sensors have been delivered to LASTI for test. We will test them starting
tomorrow.
Lasti Ponderomotive Experiment
- The
SUS receiver module has been designed and is due back from PCB Express
next week. The front panel has been ordered and is also due next week.
- System
drawings for the suspensions are in progress and should be complete very
soon.
- AA
and AI chassis are on hold for delivery of DRV135s which are due next
week. The interface and power boards are complete as are the chassis.
ADC Testing: quick test of the PCIX ADCs using
128KSPS decimated to 16384 SPS shows that the input referred noise drops to
~3uV/rtHz. This input noise and the
40Vp-p dynamic range compare very favorably to ICS110s used in LIGO. Further
tests will be conducted to verify and document performance.
Other Laboratory R&D
Marie, Mike Floyd, Mike Koyfman
This past week we have fit a good sized portion of the data. We finished tests on both springs at 40
degrees and are now moving to a higher temperature. We are going to start comparing the different
runs of the same setups to choose the best data, determine the Q-factors, and create
plots of the Q-factor and frequency.
For additional information about this report, contact Stan Whitcomb or Phil Lindquist