Weekly Report for
Week Ending July 27, 2006
Past Weekly Reports
The LIGO Executive
Committee Agenda for Monday,
July 31, 2006 will be:
(Meeting time: 10:30 am Pacific Time)
1. Announcements
2. Comments
on weekly report
3. LSC
Issures (Saulson)
4. LIGO
Lab Operations
- Administration
(Lindquist)
- Sites
(Raab, Zucker,
Shoemaker)
- Commissioning
(Fritschel)
- Optics
and Mechanics (Coyne)
- Control
and Data Systems (Bork)
- 40m
(Weinstein)
- TNI
(Libbrecht)
- LASTI
(Ottaway)
- Lab
computing (Anderson)
- Science
Group (Lazzarini)
5. Enhancements
(Adhakari)
6. Advanced
LIGO (Shoemaker)
7. Change
Control Board/Technical review Board Session as needed
Special Items:
Special Announcements:
Weekly Report Highlights
Negotiations continue with Virgo on the MOU. The draft MOU will be an important topic of
discussion at the upcoming LSC meeting.
Wednesday was the deadline for submission of MOU revisions and Progress
Reports from LSC PIs. Szabi Marka invented a new pdf-based form that has simplified handling of the
information. Dot Lloyd, working with
Albert Lazzarini, has been busy posting the reports
as they come in, so that they can be read by MOU Review Panel members. The meeting of the Review Panel will be 8-9
August at MIT.
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
SITE TELECONFERENCE (Lindquist)
- There
was no site teleconference Thursday, June 27, 2006.
- There
are currently no open action items.
PROPERTY MANAGEMENT (Luna)
>
- Tagged
and created records for three computers and one server (General Computing
group).
- Provided
assistance to Mike Pedraza in shipping a package
to ASA computers.
- Coordinated
the disposal of six old Laptops.
- Resolved
issues with the Purchasing department involving freight charges for
equipment.
- Requested
to change the expenditure type from "Supplies - Allocable" to
"Equipment - Caltech" on PO#
S011848.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- Continued
to assist in the process of conversion/allocation of current data to the
new database.
- Completed
processing MOU's.
- Scanning
- Progress continues on scanning of contract closeout files.
- Activity:
|
Week Ending
07/27/2006
|
In
|
Out
|
|
Packages
|
23
|
13
|
|
Faxes
|
30
|
27
|
FINANCIAL SYSTEMS (Cronin, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Completed
the expenditure type change on the Sun Microsystems order to indicate it
is equipment, and not supplies.
- Completed
the internal fund transfer on Triad which had a pending invoice to be paid
before the month-end closed out on Thursday.
- Placed
the large order for the audio test equipment for Hanford. Corrected the expenditure type from
Supplies to Equipment.
- Routed
the large dollar order for the data cartridges for the Livingston
Observatory.
- Working
with several individuals to resolve differences on vendor's statements on
old items still being billed.
- Working
on the change order to High Precision Devices.
- Waiting
for the remainder of the documentation to be submitted on the Support
Services change order so that I can process it
>From: Florence Kaufman <fkaufman>
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- The
single bid for the Livingston SEC outdoor wall exhibit (kinetic facade)
from Southern Enterprises was rejected and the procurement was
cancelled. This was because this
bid was nearly three times the LIGO estimate for this effort. Instead, Livingston
will procure several items separately, and use in-house staff and the Livingston
SEC construction contractor, Cangelosi-Ward, to
fabricate, assemble and install this structure. This effort is now underway.
- The
agreement with Charter Communications to provide backup fiber optics to Livingston was signed by LIGO on Tuesday. This was after Charter dropped their
requirement for the grant of an easement onto the site. Caltech General Counsel responded that
since we do not own the land, we could not grant such an easement.
- Hanford has received
two quotations from graphics companies in the Tri-Cities area two provide
enhancement materials for the LIGO video.
This contract cannot be awarded, however, until the proposal is
re-submitted to the NSF. Caltech
could not accept the purchase order from the NSF for these services. It has to be received as a supplement to
the current operations cooperative agreement. It is expected that the proposal will be
re-submitted Friday.
PROPOSALS and REPORTS (Lindquist)
We are scheduled to submit the Annual Report for LIGO Operations to the NSF
next week. Final edits in progress.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
- A
change control board was held as part of the normally scheduled meeting of
the executive committee on Monday, July 24, 2006. Minutes are being prepared
(LIGO-M060114-00-P). Two change
requests were discussed:
- CR-060006
is for funds sufficient to buy enough data storage tapes to get through
another calendar year of S5 data acquisition. The board recommended approval.
- Change
Request CR-060007 adjusts the FY 2006 budgets to reflect actual staffing
through June 30, 2006. The board
recommended approval.
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- No special activities to report.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
No report.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary
of S5 Activities at LIGO Hanford
Observatory (compiled by M. Landry)
A major piece of work was completed on the 4k IFO
Tuesday in the swap
of both the PMC and it's associated servo card.
Initial indicators seem to indicate success
(more here),
in that lock losses associated with the PMC/ISS/PSL have not been observed
since the swap. However we clearly need more statistics as the glitching was transient in nature some times taking the 4k
out of lock ten times in 8h, at other times not glitching
for a full day.
Despite the twelve hour downtime on Tuesday,
reasonable duty cycles were achieved on both machines: for the last week of
running, H1 was in science mode 79 percent of the time, while H2 logged 85
percent. Ranges were typical.
FJR writes on S5, "As of Tuesday, July 20, we
have more than 30 percent of a year of triple-coincidence science data."
S5 highlights from the LHO elog
are bulleted below:
- a
recent update
to lists of instrument lines was posted; these are large ringers and those
seen in pulsar analyses tend to be smaller and more difficult to track
(later, another elog on the same topic was
posted here)
- IFO
maintenance
budget: currently for July we have used 25h 25m of 25h on H1, 11h 25m of
25h on H2. These numbers include 8h on H1 for the PMC swap (12h
total work, 4h under Tuesday maintenance, 8 additional hours to return to
science mode).
- more
photon calibration measurements were made this week, and a summary
of analysis from previous measurements was posted
- upconversion studies
were made on the 4k and analyses posted
- radio
noise was correlated against binary inspiral
range in this study
DAQ, CDS
- fb1
required a disk
rebuild, taking out frame broadcast to DMT monitors
- Tuesday maintenance CDS summary
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
From: Janeen Romie romie_j@ligo.caltech.edu
LIGO SEC Kinetic Art Project
We only received one bid for the Kinetic Art fabrication and installation
and the bid was nearly 3x the estimate so was turned
down. We have separated out the
procurement and installation into packages and identified a responsible person
for each package. Currently, the
pendulums are on order; we are waiting for shop drawings to approve. The winches should be under procurement this
afternoon. RFQ packages for machining
and weldments are going out tomorrow.
Mechanical and Optical Systems
(Coyne)
Input Test Mass (ITM) Coating Absorption Measurements
GariLynn Billingsley (7/13)
There have been four
coating absorption measurements of 4ITM08 (coated with 4ITM07 - the piece
removed from Hanford
last year due to High absorption). An image of the surface profile of 4ITM08
can be found here: http://ilog.ligo-wa.caltech.edu:7285/advligo/4itm08_hrabs_062706.
The raised (red) areas absorbed less
than the low (blue) areas. The surface structure was caused by aggressive
cleaning before coating. The blue areas are zones which have been etched
away. All measurements on 4ITM08 were higher than similar absorption
measurements on cleaned portions of 4ITM07.
While this is a blind end
in our effort to investigate changes in 4ITM07 due to environmental factors, it
may offer some interesting clues as to some of the origins of coating
absorption.
Controls and Data Acguisition (Bork)
No report.
40-Meter Interferometer (Weinstein)
IFO Commissioning
- David
and Osamu continue to develop the noise budget procedure and code. They
are studying the effect of whitening on the noise spectrum.
- Royal
measured the oplev laser intensity fluctuations and
determined that their contribution to the oplev
pitch/yaw noise, on the order of 1e-12 rad, is
negligible compared to other noise sources (jitter, electronics). She then
quantified the jitter noise on mirrors due to the imperfect filtering of
the oplev servos at high frequencies: ~1e-9 rad/rtHz at 100 Hz. She's working on the electronics
(dark) noise, and is continuing her study of the mirror motion and noise
budget in the oplev system.
- Rana and Royal are going through the oplev whitening electronics and finding differences,
and undesirable whitening stages. They designed some digital compensation
filters to patch the problem, which seems to work. Rana
replaced some filters on the ETMX oplev board,
changed the digital filtering, and reduced the jitter noise above 100 Hz
by 100x. More work is needed on the digital
filtering to get a better loop design. We should replace the existing
boards with RevB oplev
interface boards on all four test mass oplevs.
IFO Modeling
- Jenne continues to work with Rana
on a simulink angular instability model for the
mode cleaner.
- Osamu
continues to work on e2e simulation of the AdLIGO
alignment instability.
DC Detection and Vacuum Squeezing Development
- Darcy
and Rob completed their measurements of the DC readout in-vac beamline, including
measurements of the OMC finesse as a function of temperature. Darcy is
writing it all up, complete with photos, plots, etc.
- Darcy
and Rob have completely dismantled the DC readout in-vac
beamline (TT mirrors, OMMT, OMC, DCPD,
breadboard) and inventoried all the parts. Everything is now ready for Bob
to clean and bake.
- Rob
is fleshing out a detailed schedule / plan for venting and DC readout
installation.
- Go's in-vac components (picomotor translation stage and two mirrors/mounts) are
now in Bob's hands and are being cleaned/baked.
- Ben's
new QPD Whitening board is being stuffed in the back shop currently. Jay's
AA and AI interface boards are also in the queue.
- Ben
has finished all of the machining on the DCPD mount, including mounts for
the black glass beam dump and the power resistor. The whole assembly is
ready for cleaning in its current state. Because the mounts are going into
the vacuum, and won't be touchable, the whole assembly is now in the
machine shop being dimensioned including all of the modifications. This
way, if anywhere else wants a DCPD, Ben can have ones made in the future
with one phone call.
- Ben
has almost finished the system drawings for the OMC installation. He has
finished the drawings from the point of the AA and AI chassis through to
their modules in vacuum. The drawing at this stage was given to Bob so
that he could order the in-vacuum cables from Accuglass.
- Rich,
Sam & Rob decided we don't need the fast shutter to protect the DC PDs, and it complicates the design.
- From
Rolf: The OMC software is up and
running. I still want Rana to come over and look
at it to verify that it is correct. Major items added during the last week to
overcome a few hurdles:
-
M. Evans was in town and gave me some software
for the fast generation of sine/cosine signals (5 sine/cosine signals required
for OMC). I built a simulink part and then added the
function to the code which takes the matlab output
file and produces CDS front end code. It looks like these new oscillator
signals run very well and all are produced in well under a total time of 1usec
per 32kHz control cycle. The code, as written into the front end controller,
allows for frequencies and amplitudes to be changed on the fly. So, we will not
need to tie up 10 AWG channels to produce these signals. This could possibly
also be applied at the sites to generate the cal lines or at the 40m for LSC
dither locking signals?
-
The OMC controller to be installed at the 40m
lab is based on our new prototype designs that use Myrinet
as the realtime network instead of reflective memory
to communicate to the Framebuilder. To allow data to
be merged from the old and new systems, Alex modified the Framebuilder
software such that it can take data simultaneously from both types of network.
This will require further testing once the OMC system is installed.
-
The new OMC controls still need to use reflected
memory to communicate signals to the existing LSC controller. Driver code was
written and added to the new system to use reflective memory for this purpose
and this seems to work fine.
-
Rich finished prototyping the HV driver for OMC
length and tip-tilt drive to be used on the DC readout. A production version is
now being created. Parts must be carefully researched to ensure availability and
applicability. This is ongoing. Thanks to Paul Schwinberg
for his suggestions on the design.
-
Rich is contacting the outside testing service I
found during the LASTI build to see if they can help out on testing some of the
OMC stuff.
- Go
& Shally put the green pump beam into the
OPO and got some parametric gain, ~ 1.2. Aim for 10 or more. They need to
tune up alignment and mode matching, using correct OPO cavity length. they suspected a probem in
OPO cavity, disassembled it, noticed some heater burn, and repaired it.
PSL
- The
PSL FSS slow loop got into an infinite loop, requiring a reboot on the PSL
vme cpu.
Peter King came to look at it but doesn't know why / how it got into that
state. Rana figured out how to reset it without
having to reboot the cpu.
Electronics, Controls, Computers
- Ben
gave Sam the cross-connect drawing and installation instructions that he
made for the new Mode Cleaner servo. Sam will work with Bob in installing
the system, and will change the screens and code to match the new board.
- Ben
helped Sam make some tester boards for the new Mode Cleaner servo
installation. With these boards, the whole system can be checked in short
order.
- Sam,
Dave, Jenne and Bob worked on the implementation
of the new mode cleaner servo board. They redid the cross-connect wiring
for the new board and for the LSC photodiode interface board. They
modified the epics databases ioo.db and
mc_lock40m.db. David checked all the sliders and buttons on the new MC
Servo EPICS screen, and they all check out at the cross-connect. They labelled all the wires and cables, and are preparing
to install the board and commission it.
- David
and Osamu measured the transfer functions of the dewhitening
filters for the four coil drivers in each of the four test mass suspension
controllers. They used the spectrum analyzer tools to fit to a zpk model, copied it into Foton
and compared with the raw data. They then designed compensation filters
and installed them into the digital filter bank, and tested that they did
the job. The DARM signal is unchanged between digital and analog dewhitening filters.
- Ben
showed David how to balance the dewhitening
filters offsets, so that switching dewhitening
on and off happens smoothly. Ben did ETMY, and David did the rest.
- David
implemented temperature sensors in the optical spectrum analyzers at the
AS and SP ports. The data are going into frames and trending. The femp drifts seem high (2-3 degrees C); they will check
the sensor calibration. They plan to observe the OSA drifts and see if
they correlate with the temperature drifts; if so, they will install some
thermal insulation, and if necessary, heaters and
servos.
- Jenne is working with Steve to acquire more optics for
her AM laser test system.
- Steve
and Bob completed most of the RF cabling upgrade at the AS table, the LSC
rack, and the RF distribution rack. All cables are strain relieved, and
Steve tested signals through all the cables.
- As
part of the RF cable upgrade, the Mach Zehnder
cable was changed. Sam and Jenne re-phased the
signal, and made a new cable of optimal length. The pk-pk
error signal at the MZ servo board is now 273 mV, and the servo works real
good.
- Dan
set up a new GC hub and ran ethernet cables to
two connection-less WinXP
computers in the office area.
- Dan
is moving our old, rather primitive 40m Wiki
into the new 40m
section of the AdLIGO Wiki
and adding lots of content. Work very much in progress.
Lab Infrastructure, Bake lab
- The air conditioning in the lab started to fail
because the campus chilled water supply is overloaded, and the temperature
went up to 81degrees; the laser chiller couldn't handle it. Steve reset
the thermostat and opened doors, and got the temperature back down. We
need a real AC system in the lab!
Thermal Noise Interferometer (Black)
No report from the TNI this week. --Ken
LASTI (Ottaway)
Internal Seismic Isolator (ISI) Assembly (Contributed by Richard Mittleman)
Most of the last week has been taken up by tooling. The tooling supplied by
ASI to pre-load the blade springs has to be reworked. Some of the problems were
anticipated by ASI and some were not.
The stage 1-2 springs are installed and seem to fit properly, we will not
know for sure until we release them. We expect to get the tooling back from the
machine shop tomorrow and to finish installing the 0-1 springs. With any luck
we will try to float the system early next week.
Quad-Pendulum Controls Prototype (Contributed by Richard Mittleman)
During the last vent the vent we fixed the coupling between the chains,
installed one set of eddy current dampers and made a number of measurements to
try and track down the changed pitch frequency. It seems likely that the eddy
current damper is rubbing so we are planning to check on that during the next
vent. Brett is getting together and cleaning the parts needed to do some
preliminary thermal load testing on the structure, as soon as that is ready we
will plan another vent.
HAM SAS
Cassie has nearly completed the model of the triple pendulum in IDEAS. Some
nagging boundary conditions remain to get right. After this she will be ready
to join this to the HAM SAS model.
Initial LIGO Suspension Testing (Contributed by Gregg Harry)
We changed the clamping system for the wires in the initial LIGO suspension
experiment, putting on the wire collet block that
Steve Penn designed and had machined. We were able to get everything
reassembled and the collets hold the optic. We got a first round of violin mode
Q's Wednesday, which were disappointing. The problem may be galling of the collet with its shank. We are now pumping down on a second
attempt, where the collets were lubricated with some ethanol while tightening.
There is evidence from work done in Steve Penn’s group at Hobart and William
Smith College
that retightening the collets does improve the Q's.
CIT Science Group (Lazzarini)
Data Analysis
Brown:
- Worked
with Diego on implementation of physical template family
- Working
on draft paper describing LIGO-EMRI search
- Met
with Michele and SURF student Alex to discuss his project and progress
- Learned
how to use the visualization tools for the SpEC
numerical relativity code
- Released
glue 1.8 and bounced some segment database issues to Igor
Chatterji:
- Developing
text based QScan output for following candidate inspiral events.
- Helped
identify cause of coherent waveburst glitches as
corruption reading frame data.
- Continued
preparing for low threshold Q Pipeline search of early S5 data.
- Continued
working with Rubab Khan to develop and test
clustering extensions to the Q Pipeline.
Dupuis:
- performed
(another) simple sanity check of LAL barycentering
code
- worked
with Pinkesh to get him started on a pulsar
project
- looked
at some more excitation channels at frequency of J0537-6910
Mendell:
I have revised the StackSlide sections of the S4 PowerFlux, StackSlide, and Hough
paper, and I am continuing to make further revisions to have a close to final
draft for the August LSC meeting. Work
with my SURF student working on proper motion studies is yielding results that
I will report on at the August pulsar group F2F meeting.
Sutton:
My focus this week was again network analysis. I have finished the edits to the coherent
consistency test paper gr-qc/0605002 in response to the PRD reviewer's
comments. I have also tracked down a
source of bias in the xpipeline detection statistic
calculations to be due to the linear predictor error filtering code, and have
fixed that problem. Stephen Poprocki is now running large-scale analysis jobs on the
LIGO-Virgo data set using the corrected code.
Yakushin:
1) Found a bug in the new version of the frame library that was not present
in the older one shipped with ligotools. If a time
series is read from a frame not from the beginning but from a specified time in
the middle of a frame (calling FrFileIGetV from a
ROOT script and giving it a start time and length of the time series in
seconds), the time series starts a sample earlier than it should. As a result,
if a job time interval is covered by several frames, the time series from the
first frame is shifted by one sample while others are not (since they are read
from the start of a frame) and a glitch can appear on the boundary between the
first and second frames in a job (we found 5 such obvious huge glitches on S5
data that were very loud in H1 and H2 but not L1).
The incoherent waveburst results were obtained
with older version of the frame library and are not affected by this bug.
The coherent waveburst results are affected by
this bug and will have to be redone either by using older version of libraries
or by making waveburst's readframe() function robust
to this bug.
2) Corrected readframe() function used by waveburst to
be robust with respect to the bug in the frame library: a time series in a
frame is now always read from the beginning and the selection of samples for
analysis is done inside my code rather than inside frame library.
3) Rerunning coherent waveburst on S4 and S5.
4) Preparing presentation on waveburst online
analysis for GEO workshop.
Grid research (Blackburn)
TCLGLOBUS
Completed the official release of TclGlobus
1.3.0 source tarball, RPMs
and web documentation. RPMs will be provided
to Patrick Brady for inclusion in LSCSoft asap.
Began testing of the Job Submission Client using Condor
6.8.0 instead of the previously constrained version of 6.7.13 which has been in
use for several months due to bugs in version between these two releases.
Currently seeing issues at OSG production sites such as PSU, Nebraska and UWM which
may or may not be related to the new Condor. Retesting
with Condor 6.7.13 to verify.
Developed a LIGO workflow website with documentation for the job submission
client providing the following:
a.
software dependencies
b.
installation instructions
c.
download link for LIGO Workflow client GUI
In this week's DASWG meeting, several participants asked to hear details
about the job submission client and would like to see a version put up on a
common resource such as ldas- pcdev2 as soon as the client is sufficiently stable and user
friendly to warrant test-driving by interested LSC users.
GRID COMPUTING
Moved LIGO-CIT-ITB cluster from the 6th Floor Millikan machine room to the Synchrontron
LIGO machine room. After tracing down an issue with internet
connectivity, the cluster is back up and registered in the green on the OSG ITB
map.
Determined that a bug exists in the VDS planning tool gencdag in VDS release 1.4.5. Worked
to resolve this problem with VDT and VDS engineering teams. Since this
release was about to go into the next version of VDT for OSG testing, contacted
the appropriate members of the VDS, VDT and OSG to coordinate the generation of
a new VDS release in time for the next VDT release to prevent the OSG software
stack from being having this bug.
Worked with Michael Samidi and
Kent Blackburn, on compatability problems related to
fc4, glibc and DAGMan.
These seem to have now all been resolve using the compat-libraries
from FC4.
Tested partitioning technique recommended by the VDS team for decomposing
large DAXs. Reported on problems implementing the
partitioning technique to the VDS team and requested more documentation.
Worked with VDS engineers on methods to add a
site_verify.pl site admin script for testing proper VDS installation on OSG
sites.
Attended the following OSG telecons this week: TG-Storage(DM), ITB(DM, KB), Council (KB).
Asked to co-coordinate a session entitled
"Partnership & Communication" at the OSG Consortium meeting in
August along with Paul Avery.
Reported to LSC Computer Committee an issue with the way LSC members request
DOE certificates which began as a result of LIGO moving out of iVDGL and under OSG as the registration authority.
Laboratory Computing (Stuart)
LDAS Software Systems (Maros)
With Tcl/Tk 8.4.13 running successfully,
development efforts for C++ are shifting once again to
64 bit compilation. The system tandem-ii has been set up for this testing. All
unit tests except for one datacondAPI test pass. Work
has started to put the 64 bit packages on ldas-dev.
The failure of the "All User Commands" test observed during system
testing has been resolved by forcing a cancel at the end of the test. A problem
report (#59) has been filed against TclGlobus as the
usual flush mechanism does not work.
A memory leak in the diskcacheAPI associated
viewing and getting directories was resolved by cleaning up job information
when the ::$jobid array is
unset.
System testing used version 1.8.249 of LDAS. All system tests except the one
for lsync passed. Lsync
still is unable to see RDSVerify and some /scratch
directories. While running the tests, memory leaks were observed in the diskcacheAPI and the frameAPI.
Problem reports were filed against these memory leaks. On ldas-dev,
the "All User Command" test continues not to notify cmonClient when completed.
LDAS System Administration (Anderson)
Caltech
(Dan Kozak)
- Helped
with the final installation of the new /frames at LLO.
- Working
on scripts to collect stats about the files in each dump (ongoing).
- Consulted
with Ben about how to proceed after a multiple disk failure in a T3 (in
/frames) at LHO.
- Working
on collecting info to guide our policy for releasing files in /home at
CIT.
- Did
LDRdataFindServer upgrade.
- Modified
nfsfind on dataserver
and gateway at CIT to report on any .nfs* files
found rather than delete them so we can determine if this script needs to
run at all and if so, how frequently.
(Phil Ehrens)
- Experimented
with various combinations of actions in the interest of pursuing the
Solaris 10 u2 upgrade path. Successfully upgraded Suntest3 after breaking
all mirrored devices, commenting out all unneccessary
mounts from /etc/vfstab, and providing the
upgrade script with a "backup" device.
- Transferred
the OSG-ITB cluster from the Millikan 6th floor
machine room to Snchrotron 215A.
- Worked
with Mary Lei to convert the Tandem-IV system from a special purpose
development platform to a clone of the Tandem-V system.
- Much
cleanup done to certcheck.tcl, shasumcheck.tcl and log_mon.tcl
(and log_mon_mon.tcl) to make them run with
minimal changes on Solaris and Linux. Also made many cosmetic changes to
the report formats, removing ambiguity from email messages and redesigning
the report context algorithm so that spurious context was not generated by
publishing very old log entries as context lines to fresh incidents.
- Made
further research into the strategies of rootkits
which target Solaris systems and added rules to shasumcheck.tcl
specific to Solaris.
- Discovered
a source for video cards that can be installed in the small cases of the
Dell executive series desktop machines.
- Purchased
a barcode reader for Dan Kozak, and a trio of
non-contact thermometers for lab use.
(Erik Espinoza)
- Failed
Condor Schedd replacement.
- Restarted
Condor on Saturday, after crash due to disk being full.
- Reported
pgsql autovacuum
failures to condor team.
- Removed
non-root access to condor admin commands.
- Worked
with Ken to troubleshoot our 2 machines after shipping.
- Scheduled
and attended telecon w/ AMD, Supermicro,
Kingston & ASA (RE: Cluster stability).
- Node
Crashes: node171 7/25 & 7/22.
(Stuart Anderson)
- Working
with the Condor team to diagnose a severe Condor crash that occured 3 times under heavy load. We are currently
running a patched version that partially addresses the problem.
- Worked
with our vendors to come up with a plan to address the remaining cluster
node instabilites in the new Caltech cluster.
- Working
on various mitigating actions to handle the increase in Caltech campus
wide chilled water temperatures and the adverse impact this has on our comptuer facilities.
- Secured
space to hold tapes that we will soon need to start ejecting as the 6000
slot tape robot is nearly full.
- Obtined Change Control Board approval to buy another
year's worth of 9940 tapes to hold S5 data.
- Changed
the default version of Matlab on the LDAS-CIT
cluster from R14SP3 to R2006a.
- Changed
the default internationalization setting on the LDAS-CIT cluser from "en_US"
to "C" for performance reasons.
- Upgraded
the LDAS-CIT cluster to Condor version 6.8.0.
- Re-installed
LDG-4.0 on LDAS-CIT to solve a problem with submitting remote Globus jobs.
- Tested
the enhanced LHO router configuration and verified an expected factor of 2
bandwidth improvement. It is now possible to stream data from LHO to CIT
at 35MByte/s.
- Finished
mirroring the regenerated S5 h(t) frames from CIT
to LHO and LLO.
MIT
(Keith Bayer)
- Working
on pcraid#5 - out of warranty for parts but still has another month of
labor warranty. However, to ship it
back would cost more than it's worth at this point.
Livingston
(Igor Yakushin)
- fb1 got upgraded to 9.1 TB file system on two 3511s.
All the data was copied from the old file system to the new one (it took
about 5 hours). The old file system is still available in read-only mode.
Once we verify that the new file system works properly, the old one will
be decommissioned and used for spare T3 disks and controllers until we
convert /archive file system from T3s to 3511s some time next year.
- disk 4 in 3511-1 failed and was replaced by SUN.
- u1d4@t3-10
failed and was replaced by spare u1d4@t3-16.
- The
east HVAC still misbehaves: although the cold air is blowing down the air
ducts, the hot air seems to accumulate behind the racks much more than
before and the temperature on east HVAC yesterday got to 84F and there was
a high temperature alarm on the east HVAC panel. Apparently that HVAC is
not working up to its full capacity. We put a fan behind the racks so that
the hot air is blowing in the direction of the west HVAC. That solved the
temperature problem for now but I think the real solution would be to fix
HVAC. Unfortnately
at the moment it is not obvious what, if anything, is broken.
(Dwayne Giardina)
- Ejected
tapes for shipment to CIT, imported and labeled
new.
- Cleanup
of maillog files on all machines where sendmail had been disabled.
- More
cluster_mon additions/changes.
- Warranty
check on seagate drives from T3s. waiting on
response..
Hanford
(Greg Mendell)
- Tapes
for archiving the next year of S5 data have been ordered.
- Previously
I had generated and published into LDR SFTs for
the science mode times between Dec. 17, 2005 and Jan. 31, 2006. Real-time
generation and publication into LDR of SFTs has
been running since May 16, 2006. This left gaps in the published SFT data
between the beginning of the run in Nov and Dec 17, 2005, and between Jan.
31, 2006 and May 16, 2006. The gap between Jan. 31, 2006 and May 16, 2006
has now been filled in at LHO and LLO and the SFTs
for this gap are transferring via LDR to Caltech. I will next work on the gap between Nov
and Dec. 17, 2005.
(Ben Johnson)
- Resurrected
about 10 nodes. LHO is now running with 201 nodes. All currently running
nodes have had their OS install done via kickstart.
- Refining
firewall for LHO and CIT. My main stumbling block is ippool,
which does not behave as I would hope (apparently I cannot change ippools once created...until a reboot...).
- Installed
Sol10 U2 on olddataserver to explore problems
with ippools.
Also, since the server has 6 disks, I can experiment with ZFS.
- On
the LDR front, unstuck a Hanford
second trend file that was holding up the works at CIT. Also, the GC
router at LHO has been worked on by Cisco. We should theoretically have a
300Mb/s connection now (instead of 150 Mb/s).
General Computing (Wallace)
Note added by Anderson:
The LHO network connection is now able to sustain 35MByte/s to Caltech in an
initial one hour test thanks to the work by Christine and a Cisco Engineer
mentioned below. This is approximately a factor of 2 improvement.
MIT
(Keith)
- Continuing
to interview possible sys-admin candidates.
Livingston
(Dwayne)
- Troubles
with kantech security server. changed out
boards, chips in controllers at X-End, replaced brittle wiring in MSR.
- Installed
Windows updates on kantech security server -
completed setup of new laptop for Harry, handed over this morning -
Continued training our spam filter
- Other
usual user requests and support
(Shannon)
- Working
on a test VPN setup between LHO and LLO.
I have the software installed, set up CA, server, and client
certificates. Next step is to set
up the interface on the router. I
will likely do this while physically at LHO the 7-9th in case there is an
issue with the router reconfiguration.
Will work with Dave on this.
- More
firewall rules changes concerning the mail server, temperature monitor,
etc.
- Worked
with the fiber contractor for Charter Communications today to show him
where the fiber will need to be pulled.
He says there will likely need to be bucket truck access, etc. down
the right of way. The only access
available is from our side. There
is no access from Hwy. 63. They
will give me an estimate of the amount of time and access needed for
pulling the fiber to the mid station, at which point I will need to work
with the run coordinators to plan the installation.
- Travel
paperwork & planning, etc.
- Helped
Sany with a directory permissions problem with
some software from one of his previous students.
- Various
issues with the spam filter & mail queues this week. I expect this will go on for a while
since we recently brought the spam filter online.
- More
work on the LLO vuln. assessment.
- Looked
at wiring, etc. for some HVAC controls in the new building.
- Worked
with Bernie to get power (220v) pulled in for the v490 in the computer
user room.
Hanford
(Christine)
- The
Cisco engineer finally showed up yesterday afternoon. After 3 hours of dealing with problems,
he was finally able to get the IOS on the router updated to the latest
compatible version. He also moved
the WAN and LAN GigE interfaces off the main bus
and on to a controller card. I'm no
longer seeing congestion errors on the interfaces. The bandwidth available should be close
to 300 Mb/s, the max this router can deliver. I've asked Stuart to stress the network
and see how much bandwidth he can get.
The router is now able to handle jumbo frames, so this is an option
for data transfers. This IOS
supports SSH, so I have turned off telnet.
- The
backup network works to ESnet. We could ping the ESnet
router and a traceroute to Cisco.com got to
Cisco. However, pings to Cisco.com
and Caltech LIGO did not return and we could not get to any web
pages. The Cisco engineer thinks
that ESnet is not broadcasting our IP address
space so that packets can return via the backup circuit. I've sent an email to ESnet to get their opinion and schedule testing for
next Tues.
- The
Cisco engineer is also going to work with his sales rep to write up a
quote for an upgrade of my router.
The current router can't do GigE speeds
even though it will accept GigE interfaces. The engineer suggests an upgrade to a
7600 router.
- Still
trying to get the Fedora Core 4 NIS+ client working. For some reason the NIS+ server is unable to create a
callback to the Fedora client.
Running snoop on the server while running a niscat
command on the client showed that the client is sending destination
unreachable, administratively down messages to the server. I think this might be because I enabled SELinux. Anyway
there is more troubleshooting to do to get the NIS+ working.
CIT
(Bruce) (0.5 days)
- General
iLog maintenance (user
adds, keyword adds, systems work, etc.)
- Rechecking
the admin tools at LHO to be sure they are working after iLog was moved to ilog.ligo-wa.
(Mike)
- Reloaded
our backup server (atria) with Solaris 9. Robotic software stills needs to
be loaded.
- Finished
up Melody's new Sun Workstation.
- Worked
the Spam Filters and mail servers.
- Helped
Christian swapped out the printers in Millikan,
Bridge Annex, and Syd's office.
- Moved
some old computer equipment out of a cubicle for new user to work in.
- Made
room in my office to make room for another Sun workstation installation,
plus to reload two DCC servers with server 2003.
- Started
reloading DCC servers. This is to be ready for a Monday's Synergy
installation of their new software.
- Other
misc. user support, and work in B/A server room.
(Veronica)
- LIGO: Working on the website of LIGO
educational resources. Worked with
Dave Beckett on the how-to of web postings. Installed the last newsletter. Updates of the CIT and MIT
homepages. Elba
website update.
- LSC: Updates of the MOUs. In order to simplify the web posting of
the updates, installed a database of the past and current MOUs and a script-generating code. The new pages are up and running. Updates of the LSC webpages.
CaJAGWR, Project Science: Website updates/support.
(Christian)
- Created
a backup of Gina Salone, Ed Jasnow
and Florence Kaufman workstation.
- Ken
Mailand - Setup external hard drive for backup
proposes on Ken's workstation..
- Helena-
Assisted Helena synchronize her files offline in
XP.
- Millikan - Setup and configured new printer in Millikan with Mike.
- Bridge
Annex- Replaced 4600 printer with a duplex 5500 with Mike.
- Replaced
2500 printer in Julie and Cindy's room with 4600 printer.
- Syd Meshkov- Installed and
configured 2500 network printer in Syd's office
with Mike.
- Replaced
toner cartridges for Irene Baldon -Called Dell
support to have my motherboard checked and replaced on laptop.
- Worked
on the Spam Filters with Mike and Larry.
- Other
misc.: Continued onsite software/phone support
(Larry)
- Still
working procurement issues. Placed orders for a number of workstations and
related items. Worked with Gina on
a couple of different procurement items.
Purchased a number of misc. s/w items. In the process of updating
the maint. contract on
the Comsol s/w.
- Assisting
Mike with the installation of the s/w for the new DCC system. This includes having to purchase updates
to some of the support software.
- Assisted
different people that are working on different parts of the MOU renewal
and posting process.
- Took
care of a number of problems the SURF students. For some reason a number
of students lost the ability to ssh
into the LIGO servers. Reseting their account solved the problem. There were other issues in labs dealing
with printing and network connections.
Also, had to add a few more accounts. The students are still
arriving.
- Spent
time tracking down a E2E workstation problem. One
of the visitors attending the enhanced LIGO mtg. decided to remove a
network cable from one of the E2E groups
workstations and use it for their laptop.
- Still
working on the getting the backup server on-line. We've had a number of
interruptions which has put us behind schedule. The temporary backup system has been
working well. It has been tested out a couple of times and has proven to be
faster than the old system. The
problem is that it is not cross platform compatible. However, we are still
going to go to a disk assisted backup system.
- With
the high temperatures, the computer room air-conditioning was not able to
keep the room cool enough, we've had to move equipment around and turn
some of the sandbox units off. This has been a minor problem for the end
users but has taken some time to take care of things.
- The
mail system has been taking up some time. We've been getting a lot of spam
storms. Also, spent a little time going over some of the configuration
items with the Livingston group on their
setup. Presently, I estimate that
40%-50% of the e-mail being accepted on the system would still be
considered spam. The number of messages being checked for false positives has also jumped to about 1000+/day.
Mail Statistics for July 20-26, 06
|
Mail Statistics
|
7/27/2006
|
|
Rejected Messages
|
40,548
|
|
Virus Messages
|
1,773
|
|
Accepted Messages
|
30,316
|
|
Total Messages
|
70,864
|
Advanced LIGO and Supporting R&D (Shoemaker)
Systems
See also:
AdL Systems wiki web page
AdL
Systems email archives
Records
Of Decisions or Agreements (RODA) status web page
- Presented the Adv. LIGO status at the PAC
Meeting #20.
- Organizing
an optomechanical layout meeting following the
LSC meeting (either at LSU conference center or at the LLO site) for a
small group.
- Chaired
the Quad Suspension Preliminary Design
Review #3, (7/10) focused on mechanical design issues. The
design team presented responses to the
review committee’s questions. The
committee’s report will be issued soon. The report will recommend
proceeding to the final design phase including the fabrication of the
“noise” prototype for testing at LASTI.
Vacuum Compatibility
Vacuum Preparation & Residual Gas Assay (RGA)
See also the Vacuum Bake Lab
Bob Taylor
- I
have repaired the OSEMs that Brett shipped to me
from MIT and I have shipped them back to him today.
- I
have been doing some cleaning in the clean room in anticipation of the
work that the 40m is going to be doing in there.
- I
have been working on the OSEMs for Conor/ Janeen in between
bake jobs and other 40m jobs.
- I
have completed the bake out of accuGlass cables
for Ken Mason (LASTI) and have shipped them to him.
- I
am baking a large load of stainless conflats and
one view port for Ken Mason (LASTI).
High-Irradiance, Contamination-Exposure Cavities
Lee Cardenas, Liyuan Zhang
Cavity # 1: OTF Lab. at W. Bridge: No Change. [Still measuring absorption
& total loss on wire sample daily. Ready for new
sample.]
Cavity #2: No change
Cavity #3: OTF Lab at Lauritsen
Room 38: A new sample, a HAM-SAS stepper
motor assembly, is in the cavity. The cavity is locked. We were taking
measurements every day for absorption and ring down. Preliminary indications
are that this unit is clean. We will continue taking measurements until the
test is completed.
Scatter/Absorption Test Measurement:
Absorption test and measurements for the ITM08 mirror have been completed.
The existing HeNe laser was found to have a high
noise background. We ordered a new HeNe laser, from Melles Griot, with better power
and frequency stability. We are currently installing it and mode matching it.
Modeling and Simulation (Hiro Yamamoto)
AdvLIGO LSC/ASC design using FP arm model with
quad suspension (Osamu, Hiro)
We almost finished to write a technical paper for AdLIGO ASC. e2e PSD module is being fixed so that it gives accurate
results for complicated spectrums (mixture of steeply changing structures)
without manual adjustment. The next thing we should do before LSC
meeting is to see a dependence of optical spring frequency on beam
centering.
Static IFO Simulation (Hiro)
New results about the scattering loss calculation, which is closer to the
definition of surface aberration COC group uses. I set the rms of
aberration after subtracting up to 36 Wyko
polynomial. I should have subtracted only up to 3, i.e., tilt and power. Now
the new result:
rms = 1 nm : loss = 61 +- 20 ppm
rms = 0.5 nm : loss = 18 +- 5 ppm
These losses are around 60% of the previous calculation. These losses
include the diffraction loss, but not ETM transmittance. So, if we need to have the loss per mirror
< 25ppm, rms of 1nm is too loose. With 0.5nm, 3
out of 20 cases had loss more than 25ppm.
Code developments still going. The schedule was
changed so that Bill Kells and his SURF student can
use the code for their PI study.
Modeler (Hiro, Bruce)
Bruce finished the front end support of template based primitives. He has
started to work on the code in the simulation engine to actually utilize the
new primitive families in the simulation.
Mechanical Simulation for Advanced LIGO (Sany and
SLU team)
(1) E2e modeling (Quave and Yoshida)
Continued e2e analysis of LIGO I Mode Cleaner. It
seems that pos and yaw are cross-coupled and pos to pitch coupling is too high,
and that these couplings have substantial effect on MC local damping and MC
length sensing controls. The pos/yaw cross-coupling is most likely due to coil
force asymmetry. The OSEM sensor/coil efficiency settings are currently
investigated.
Started to build an e2e model of HAM SAS seismic isolation
using the new revision of matlab model created by V. Sannibale.
(2) Outreach (Sutton, Anderson, Norwood, Parkinson and
Yoshida)
In the last few weeks, the Southeastern
Louisiana University
group made some progress in LIGO outreach-related activities. We have been
awarded the 2006-07 LIGO Science Planning Grant (funded by LaSIP, Louisiana Systemic Initiatives Program).
Using the award, Anderson participated in the
Summer Institute in San Francisco, Norwood attended the MISE (Modeling Inquiry Science
Education) Summer Institute at Southern University at Baton Rouge as an observer, and Parkinson and
Yoshida attended the RIPPLE (Research and Inquiry-based Physics Project with
LIGO and Exploratorium) at Louisiana Tech as observers. Sutton started to design
experimental procedures for a physics course offered for education majors at Southeastern Louisiana University,
with the use of LIGO SEC exhibits in mind.
ALFI: e2e front end (Bruce, Melody)
Comment implementation is going based on more consistent strategy of alfi, instead of relying on tools of a commercial library
package used in alfi for GUI.
Seismic Isolation
BSC Seismic Isolation Assembly and Test
The rod end shims for the stage 0-1 required additional machining. We have
received the cut down shims and will make another attempt tomorrow to install
them. The installation tooling needed a longer power screw, which has been
made.
Additional finite element modeling was done in an attempt to better
understand the new blade shape and stress. These linear models agree with the
values measured in the calibration fixture and show the maximum stress at 40%
of yield.
From: "Joseph A.
Giaime" jgiaime@ligo.phys.lsu.edu
BSC SEI status
- received shims for the reduced-load spring
configuration.
- The
stage 1-2 blade is installed and looks to be correctly aligned and flat.
- New
installation tooling for 1-2 was built and works.
- For
stage 0-1, the installation is underway.
- We
expect that the full-weight configuration will require a significant
tooling redesign.
- Ken
has been working on a document detailing the alignment and tuning to
reflect the new experience.
- Pod
cables in fab at Caltech.
- L-4C
pods at shop to get the incorrectly threaded holes drilled out.
Stanford
- Matt
made some new measurements with the ETF platform, using new blend filters.
- Night-time
performance looks very good, especially at 1 Hz (2 x 10-11 m/√Hz).
Same old high vertical coupling to stage 1, but new higher moment of
inertia of stage 2 limited its damage.
- Relationship
among GS-13 witnesses and the FB sensor changes from run to run in the 1
Hz vicinity. This is not understood.
- Stage
2 control deserves a bit more tweaking. Then maybe 10 Hz
feed-forward.
- Tarm has assembled a vertical seismometer experiment
prototype, and posted some photos. This system uses BeCu flexures to constrain a horizontal bar to rotate
in one DOF, supported by Euler buckling springs. The new feature is
test mass buoyancy compensation, so that it does not require vacuum or a
hermetic box.
From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>
Clean
room and grey room, new floor laid in schedule, no show of the company supposed
to mount the clean room walls. They
promised to be here next Monday and deliver the clean room on Tuesday, one week
late. The absolute filters arrived and
are presently stored in the clean room. Not yet critical path, but getting
close.
Cleaning Facilities at Paolo Soldi.
I went to Soldi for a test etching of the welded
parts (test honeycomb). The new cleaning plant was not yet ready and the the etching with Caustic soda solution, acid cleaning and
neutralization with Tor-NS deoxydant
and degreaser (HCl, HF and H2SO4 solution) and tap
water was performed in a temporary vat outside the facility. No DI water
rinsing was done in this test (the test was only intended to establish the
procedure). The cleaning was reasonably
successful and eliminated all visible residues except some halo around the
welding. The rest of the surface was all clear and pristine, including all the weldings and all machined surfaces. The halo around the
welding, probably due to welding rod drawing grease, were enhanced by the basic
etching, but disappeared immediately with the acid degreasing process. A faint
halo, visible in the micro photos is probably due to the fact that the greasy
residue eliminated by the degreasing step shielded the aluminum in that area
from the etchant.
Micro photos also showed some small dark spots (weld residues) or
micro-pitting on the end surface of some welds, most of the spot disappeared
with the washings, while a few remained. These spots will be treated with
hydro-jet cleaning, wire brushing and scotch brite
scrubbing and/or somewhat longer alkaline etching, and/or alternating the two
basic/acid processing. More tests to follow before the cleaning process is
applied to the actual base structure. Please note that, contrary to the test
structure, the welds on the actual structure were performed with degreased
welding wires (the residue is likely to be weld-baked welding wire drawing oil)
and these spots are present in much smaller amount in the base structure.
The new cleaning facility as Soldi’s is late
and getting close to the critical path, but half of the acid proof floor was
already laid and during my one hour stay at Soldi’s,
the installation crew installed the 5th of the seven tanks and a half of the
trolley structure that will dip the parts in the solutions. Given
the fact that the installation had started (late) only two days earlier, I
found it believable that the installation will be finished by coming Saturday,
or Monday at worst. I have no idea of how long it will take to
commission the plant, but it is not a complex one. It is likely to be OK for
us. The problem is how hard it will be
to keep Soldi to a rigorous cleaning procedure. Chiara is made aware of the problem; during the cleaning
period she will be present at Soldi’s plant at
least twice a day, checking the process, as well as monitoring the cleanliness.
FTIR machine arriving from the US, expected delivery end of this
week.
Finished the welding of the base structure, found
and solved problems with weld contraction, that have been relaxed by
counter-stressing and heating them independently. At the end of the process the structure still
had <3 mm bumb, to be compared with the 7 mm
tolerance (overthickness) of the welded structure
before machining. The entire 5083
Aluminum structure was the relaxed in oven at 200oC for 2 hours, followed by
slow cooldown (to 150 degrees after 12 hours) between
2 steel plates and about 200 Kg weight. The structure remained essentially as
was before baking, without further relaxation.
A procedure has been identified and modification of
drawings have been done to avoid the weld induced structure warping
problem in further productions.
The structure’s resonances were measured, and we found a 35 Hz
resonance, warping longitudinally the shelves connected to the cross tubes
(high at the center of the tube and low at the two extremities, with the
structure body essentially stationary). This mode will be dramatically
stiffened by the cross tubes. The next resonances were above 100 Hz. Virginio even
questions if we need to bolt the base plate to the bottom of the structure,
which appears to be rigid enough as is. We can decide later if to bolt it on or
not. The base structure is presently
under machining. It will be essentially the last mechanical part to be
delivered.
We also baked the spare (fifth) filter at 150oC for 12 hours, stressed by 6
blades under tension. The filter base plate did not move (measurement precision
~ 50 micron). We properly suspended the
spring box. Virginio measured the spring box without
the stiffening bars, and found the lowest butterfly resonance at 46 Hz, roughly
in agreement with the simulations. Now measuring it again with the stiffening
bars. Started assemblying the vertical calibration structure (to tune the
magic wands using the fifth filter). We have a possible problem with the delivery
of commercial parts. Galli is being assured that we
will get delivery before the beginning of summer vacations but he has doubts,
some parts may produce critical path problems.
Electronics.
Virginio reports that Marwan
is late with the reformatting of the LVDT drivers. If Virginio does
not get reassurance within a few days, Ben can make the circuit by September.
From: Ben Abbott <abbott_b@ligo.caltech.edu>
HAM-SAS
I am in the process of finalizing a schedule for the electronics delivery of
the HAM-SAS system.
I am going to change the layout of the Coil Driver Interface board to match
the existing DAC and ADC connector styles. This shouldn't take too long
to change, and will ensure that we have enough DAC and ADC boards available
without having to order new ones.
ISI
The GS-13 and L4C cables and boards are finished in the back shop.
They will be mailed out before the end of the week, after a functional test can
be performed.
Suspension
ALUK held its latest Project Management Committee on 21st July
2006 (See LIGO-M060103-00-K).
A brief activity summary follows:
- All:
PDR#3.
- Documents
were submitted on 16th June with the exception of one document
from Birmingham
(see below).
- Website
www.eng-external.rl.ac.uk/advligo/_review
- Reviewers comments were received; a response was
generated and presented on 10th July.
- Final
review meeting pending.
- RAL:
Other technical work has included assembly of marionette; dynamics tests
on “sleeve”; receipt of second controls prototype structure
and preparation to test the upper part of the control structure (which is
very similar to that of the noise structure) with the sleeve.
- Glasgow:
Prototype ears ordered; CO2 welding machine basic development phase
complete; much work identifying suppliers and firming up on specifications
for non-metal penultimate and reaction masses for noise P-type; started
handover to RAL of technical spec for ribbon machine.
- Birmingham:
OSEM thermal tests; OSEM drawings complete; OSEM manufacturing study
complete (placing of orders awaits outcome of PDR#3); one member of the
team suddenly made unavailable by personal issues and a suitable stand-in
sought (at least one good candidate identified) – this delayed the
release of the OSEM drive electronics update document.
From: Janeen Romie romie_j@ligo.caltech.edu
Nothing significant to report.
From: Ken Mailand kmailand@ligo.caltech.edu
I'm using the latest information from Ian and working on a lower quad
installation arm shop drawings, also a 'conveyor' version to be used at the
LASTI site. The existing 5 axis fixture
has been disassembled, the fine steering ratio has
been doubled for better control. Ken Mason wants the lift table for future assembly, it is being stripped of paint, and chromed for use
in the clean area.
I'm working on the DLC mount, the PO Telescope, and the 6 Cavity beam dumps
for Mike Smith.
Core Optics
From: Bill Kells kells@ligo.caltech.edu
First, participated in (last week's, I know) TCS review for AdL (see comment forwarded to P. Willems,
et al via PF). Then into this week worked on questions to the designers and
transmitted to PF.
Main items had to do with PI.
- I
completed (and am still polishing and communicating with D. Ottaway who is pursuing similar and will speak on my
behalf at LSC) a T note (T060159-00-D, and see my last Autumn's NSF review
talk, based on the same simulation, G050578-00-I) on PI with both SCR and
PRC and arm Gouy difference. For one, this
speaks to the issue of how choice of SRC and/or PRC with significant Gouy phase (making "stable") impacts thePI thresholds.
- Finished
LSC review of latest paper on PI by Braginsky, Vyatchanin, Stagin, which
also extends their previous analysis to include SRC. This will be aired
(no doubt) at the LSC meeting. Their is one major point they discuss which
I may/may not disagree with them on (its not so clear what they conclude:
some contradiction between text and equations)
- My
SURFstudent and I are now getting first results
on calculating PI thresholds but not in the traditional (~ Russian,
Australian) individual mode pair method. Instead we use FFT to determine
the entire cavity field generated by each acoustic mode. This should
settle the question emphasized by K. Thorne that a "continuum"
contribution to Instability may have been missed in the previous mode
selective caculations.
From: GariLynn Billingsley
<Billingsley_G@ligo.caltech.edu>
Absorption and scatter caused by cleaning and handling materials for
Advanced LIGO optics were studied in a gross contamination experiment and found
to be benign. A LIGO1 optic was cleaned, measured, then
deliberately contaminated by cleaning solvent and by gloves dipped in cleaning
solvent to determine if we should undergo further contamination cavity testing
on gloves and solvent.
Absorption changed fro a baseline of 2.2 ppm
average to 2.1 average with dried solvent and 2.7
average with solvent washed gloves. Scatter changed from 40ppm baseline
to 45 with dried solvent and 904 with solvent washed gloves. The scatter
calibration is not absolute, we are planning further
study for purposes of determining the cause of scatter in LIGO optics.
From: Helena Armandula ahelena@ligo.caltech.edu
LIGO I - Scatter and Absorption Studies
Supported Liyuan with some experiments aimed at
measuring absorption and scatter on a coated surface after exposure to gross
contamination (methanol and wetted gloves).A report on the subject will be
available shortly.
Advanced LIGO Optics
A shipping case for Advanced LIGO optics was reviewed with a SILTON Cases
rep. After a few modifications on the drawings take place, it will be
circulated for comments.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
After trying a few simple
tests to include the Simulink blocks within System
Generator to perform operations on the ADC output, my conclusion is that
operations on the ADC output will have to be done using Xilinx's
building blocks. This requires somewhat more knowledge of the hardware than
I had hoped to get away with. Otherwise implementing a digital filter is
relatively straightforward.
Controls, Data systems
From: Rolf Bork rolf@ligo.caltech.edu
Advanced LIGO
- There
will be an AdvLigo CDS design workshop held at
MIT Tuesday and Wednesday of next week (Aug1,2).
- We
are presently testing our realtime code on our
first multi-CPU computer with multi-core processors. This testing is being
done to try and get some systems, such as Ponderomotive
front end controls, up to 64KHz and beyond. After
a couple of problems and false starts, we are making progress. While
prototype systems to date have locked the realtime
code to one cpu, we are
now able to divide the code up among three cores (fourth core runs EPICS,
AWG, etc). Where the Ponderomotive code was
running in 20usec/cycle on a single CPU, it now runs in 8usec/cycle when
split up among three cores. Initially, we had seen some timing problems in
sending code synchronization signals between the three cores, but that is
no longer the case.
- Internal
Seismic Isolation (ISI)
-
Mohanna is beginning work on
the coil driver units.
-
Jay, Ben and I will be visiting Brian Lantz at Stanford
on Aug. 7 to further detail the ISI controls requirements.
-
The GS-13 and L4C cables and boards are finished in the
back shop. They will be mailed out before the end of the week, after a functional
test can be performed.
-
Ben is the process of finalizing a schedule for the
electronics delivery of the HAM-SAS system.
General Electronics:
- Mohanna is finishing up work on the OSEM / Satellite
Amplifier adapter boxes.
- Rich
met with a local sheet metal shop and is developing a custom LIGO electronics
chassis for our future use. They indicated that a custom design can
be supplied in a 1u 19 inch format for about $91 per unit, which is
cheaper by 50% than the versions we are currently using. The custom design is a RF tight version
that will allow easier access to internal circuitry.
- Rich
received custom tester boards for ASC diodes. Will be taking them
along to MIT for analysis there next week.
Other Laboratory R&D
From: John Miller
<miller_j@ligo.caltech.edu>
John
I have been trying to fine tune the alignment of the cavity to improve lock.
At present I am able to achieve a strong lock or a good mesa beam, but not
both. I am only able to tilt the end mirror by around 6microrad before lock is
lost. This is down around 50% on past experiments. Hence I have been unable to
improve on previous tilt sensitivity measurements, although I have been able to
produce similar results tilting about a different axis. I have also begun to
study possible future developments for our cavity e.g. PDH locking and power
recycling.
Marie
This past week, I worked with one of my friends on understanding the fit
functions we are using and making sure it is a suitable fit. In the
process, we learned more about the beating caused by two different frequencies for
the motion of the mass and pendulum connected to the spring. We have
started to organize our data and put it in a binder so that the three of us can
compare easily. We also started taking measurements with the maraging blades (as opposed to the glassy metal blades) and
figured out how to acquire data from it. Mike found a problem in the
setup of the piping to drop the balls in, and we are getting the right tools to
fix it.
Yumei
- finish
the report about flex joint
- simulate
the small flex joint of leg and the bottom box of HAM-SAS
Michael Floyd
This week I fit graphs using a 5 variable fit, but had to switch over to an
8 variable fit in order to fit in beatings of the graph. Also, I finished
making adjustments to the copper piping which ran to the Maraging
Steel and switched the connection so that we could start taking tests with the Maraging Steel.
Antonella
This week I simulated the Pound-Drever-Hall error
signal with different phase values. I will now lock a laser to a cavity using
the Pound-Drever-Hall method to prepare me for work
at the TNI. The idea of this method is to measure the laser's frequency using a
Fabry-Perot cavity and feed this measurement back to
the laser to suppress frequency fluctuations.
My simulations show that the error signal is linear near resonance; this
will allow us to suppress frequency noise.
Michael Koyfman
This past week, I have been fitting and analyzing graphs of our experiment,
especially looking at the relationship between the frequency and attenuation factor.
I have also continued researching the systems involved in our experiment.
Livia
This week I have designed and constructed a voltage divider which reduces
the input by a factor of ~0.25. I have
tested my circuit and its performance is in close agreement with theory. I will
now use this device to improve the resolution of my tilt sensitivity
experiment.
For additional information about this report, contact Stan Whitcomb or Phil Lindquist