Weekly Report for Week
Ending July 13, 2006
Past Weekly Reports
There
will be no LIGO Executive Committee scheduled Monday, July 17, 2006 due to the LIGO
Staffing Committee meeting scheduled that morning. The next Executive Committee Meeting will be
scheduled Monday, July 24, 2006.
Special Announcements:
Weekly Report Highlights
From D.
Ingram: We have learned that NSF's
"Einstein's Messengers" DVD about LIGO has won a CINE Golden Eagle
award.
Discussions continue concerning the MOU with Virgo. The LIGO PAC (July 11,
12) gave useful advice.
Planning has stepped up for the MOU Review Panel meeting 8-9 August at MIT,
and for the LSC meeting at LSU, 14-17 August.
LIGO Laboratory Administration
(Lindquist)
STATUS OF LSC MOUs (Lloyd)
SITE TELECONFERENCE (Lindquist)
- A
site teleconference was scheduled for Thursday, July 13, 2006. The following were among the issues discussed:
- Financial
Reports – F. Kaufman is going to investigate the possibility of
generating a version of the monthly report that we can give broader
distribution to aid the account managers.
A version will be provided to the account managers to elicit their
comments.
- Livingston Science Education
Center –
work continues towards a September completion and a November Opening
Ceremony.
- Volunteers
at the Sites – A process has been developed. 1) a release must
be signed an sent to HR, 2) a criminal background check will be done, 3)
the volunteer will sign a volunteer agreement form that will be provided,
4) the volunteer will be covered under the CIT umbrella insurance policy
for medical treatment only. E.
Jasnow will prepare an email with additional detail.
- There
are currently no open action items.
PROPERTY MANAGEMENT (Luna)
>
- Assisted
Riccardo De Salvo and Francesco Fidecaro in preparing a commercial Invoice
for a Seismic
Attenuation Tower.
- Coordinated
the disposal of two old monitors at the 40M lab.
- Working
with Property Services to reconcile Fabrication Accounts 1999-2003.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
- No
report. [L. Turner and G. Stokes
continue to provide FileHold with database information required to assure
that the conversion is smooth and with accurate results. The target of having all key documents in
a database for the LSC meeting holds. –pel]
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- Continued
to assist in the process of conversion of current data to the new document
center database.
- Processed
a few submitted sets of drawings.
- Scanning
- Progress continues on scanning of contract closeout files. Relocated 40+ boxes of scanned documentation
to another unused cubicle in room 23 to accommodate new employee.
- Activity:
|
Week Ending
07/13/2006
|
In
|
Out
|
|
Packages
|
32
|
9
|
|
Faxes
|
14
|
21
|
FINANCIAL SYSTEMS (Cronin, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Completed
change order #15 to Venturi Staffing and submitted to the vendor.
Requested and received the renewal of the Certificate of Insurance.
- Working
on completing change order #3 to Ares Corp and submitting for routing.
- Placed
the order for the HVAC upgrade for the Hanford Observatory. Waiting for
the Certificate of Insurance.
- Placed
the memory order for Hanford.
- Completed
change order #3 for Limerick and
submitted it to the vendor.
- Completed
change order #9 for George Stokes and submitted it to the vendor.
- Submitted
documents requested to the auditors.
>From: Florence Kaufman <fkaufman>
- Sent
out all monthly reports for June.
- Worked
on calculation of potential adjustments to budgets for unfilled positions
and positions filled but not budgeted as of the end of June 2006.
- Attempted
to close the LIGO.HSAS/1 NSFLIGO.FY02ON account which was created in error
when we had requested the fabrication account for the HSAS system. Notified that the account could not be
closed without also closing the fabrication account LIGO.HSAS/1 NSFLIGO.FYO2CA,
because the project section of the POETA's is the same. Because both these accounts have to
remain open, care should be taken to indicate the appropriate account
number in preparing Purchase Requistions, Tech Mart Orders and P-card
orders for the HSAS fabrication effort.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone <gsalone@ligo.caltech.edu>
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- Construction
of the LLO Science Education
Center remains on
schedule for beneficial occupancy at the end of August, with opening
ceremonies scheduled for November 13.
- Bids
for the fabrication, assembly, and installation of the kinetic facade for
the LLO SEC are scheduled to be received on July 14.
- The
contract with Charter Communications to provide fiber optic communications
for LLO is being held up because of Charter's requirement for a grant of
easement onto the land. Since
Caltech does not own the land occupied by LIGO, we cannot grant the
easement. Caltech's position, as
developed by Assistant General Counsel Peggy Luh, is that the service
agreement already provides Charter with the authority to come onto the
site. This position has been
communicated to Charter, and we're awaiting their response.
- Caltech
has received a purchase order from the NSF in the amount of $30,000 to
provide graphic materials in support of their video about LIGO,
"Einstein's Messenger."
Three graphics arts companies in the Tri-Cities area are being
solicited to submit bids.
- Cathy
Funaro, of Accounts Payable, has been designated by the Director of Procurement
Services, Tina Lowenthal, to be co-located at LIGO to handle the payment
of invoices. Cathy starts on July
24.
- Agreement
was reached with representatives of the Office of General Counsel and
Human Resources regarding the processing of volunteers and docents at both
observatories.
- Interviews
are being conducted by auditors of the NSF Office of Inspector General
with various members of the LIGO staff regarding proper allocation of time
charged.
PROPOSALS and REPORTS (Lindquist)
We are assembling the Annual Report for LIGO FY 2006 Operations. Much of the content has been received from
contributors, but there are still a few sections yet to be received. This report is due to be submitted to the NSF
by August 1, 2006.
The Large Facilities Projects Monthly Report for June 2006 has been sent to
the NSF.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
- There
are no open change requests.
- Change
Request CR-060005, Increased Mechanical Fabrication Costs for the
Prototype Seismic Attenuation System for the HAM Chamber (HAM-SAS),
submitted by R. DeSalvo and D. Coyne, has been approved. The LIGO Change Control Board met
Monday, July 10, 2006 as part of the normally scheduled meeting of the
Executive Committee. The board
recommended approval as indicated and the change request has been
signed. Minutes of the CCB meeting
have been distributed (LIGO-M060098-00-P).
The original signed version of the document has been filed in the Document Control Center.
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- The
next Staffing Committee meeting is scheduled for Monday 7/17. I am preparing a DRAFT agenda.
- Prepared numerous appointment and reappointment
memos for various Visitors, Post Docs, and Term Staff.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
Nothing significant to report this week.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary
of S5 Activities at LIGO Hanford
Observatory (compiled by M. Landry)
The last two weeks have yielded solid lock stretches and rapid
relocking at LHO. Conlog reports, for the last 14 days, duty cycles
of 84.4% on H1 and a resounding 90.1% on H2, despite several shifts with high
winds this week. We of course benefitted from quiet conditions over the
July 4 holiday weekend. The outstanding problem running the IFOs remains
glitching in the H1 PSL/ISS/PMC subsytems. Progress was made this week in
tracking this down to the PMC - and we expect to swap out both the PMC and the
servo card in the next two weeks during one (extended) Tuesday maintenance
downtime.
S5 highlights from the last two weeks of LHO elog are bulleted below:
- we
went over our 4h maintenance time on a difficult
Tuesday, in which the 2k REFL photodiode was accidentally and lightly
jostled and had to be replaced, and the PMC on the 4k had to be
re-jumpered. Both investigations are detailed in logs below.
- a
chilled water pump cycled
off and on over a week ago, and is now being watched closely
- calibrated
templates for violin modes were added to the scimon checklist... this will
allow us to track the amplitude of these lines between IFO epochs
- current
noise
from bias modules is a limiting noise source for all IFOs; bias currents
were obtained and compared
- standard
weekly updates: range and duty cycle from last
week, and this
week, plus IFO
maintenance budget (current usage at LHO: 7h 45m on H1, 9h 45m on H2
- scimons
looking at various things, such as potential instrument
lines
- accelerometers
on were added to oplevs to aid in injection studies (tap tests)
- acoustic
injection/beam spot tuning
was performed on both IFOs
4K IFO
- update
on ISS glitching: it's likely the PMC...
more on glitching here
- really
nice turnaround
on TCS ITMY was made when we lost 15V supply and required new one
- details
were retroactively posted
on the H1 ETMX shaking/charge up event, showing the optic alignment,
showing pitch and yaw decaying back to (or near) original positions
- despite
the holiday weekend, we did have some seismic
disturbances which impacted the range, including something seeming
isolated at MX in the 3-30Hz band
2K IFO
DAQ, CDS
- we
lost a key directory with S5 reference spectra; it is not clear how
they were erased, and backups were insufficiently new - backup mechanisms
are being modified and improved
- the
Tuesday cds maintenance
was summarized
- wiki
accounts are now available
to the entire LSC
Outreach (D. Ingram)
We have learned that NSF's "Einstein's Messengers" DVD has won a CINE Golden Eagle award.
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
L1 in S5 (Frolov)
This week science data taking was mostly smooth with duty cycle close to 70%
and binary inspiral range around 14 Mpc. There were two unplanned multi hour
interruptions in the run. The first one
on Saturday night due to problems bringing the HEPI system up after an
earthquake. The second one on Wednesday was a sudden unexplained lock loss
followed by difficulties acquiring lock. Interferometer locking was restored after
changing lock acquisition parameters. The
root cause of the locking problems is still not understood and is being
investigated. Other issues included
recurring cooling problems in the LDAS room and the failure of the vacuum
system read back electronics at the Y end station. Both issues were resolved and did not affect
data taking or storage, nor the interferometer vacuum.
LLO Safety and Security (Riesen)
Installing secondary containment
trays in our chemical storage cabinets.
Relocating emergency exit signs in the staging building's hi-bay
area. Troubleshooting the side gate's
intermittent "opening deactivation" sensor. Sent off
torque wrenchs for their annual calibrations. Taking inventory and inspecting clean room
garb for abnormal wear and tear.
Replacing worn garb.
Ordered 3 ea. EV-7215 IR viewers. 2
have been turned in as unusable (dropped, broke). Received laser table beam blocks needed for
the HPLF and Optics Lab. Completed
safety orientation for Ashly Kimball. (site admin. temp.) Found no laser nor
site safety concerns this reporting period.
Humongous Educational Kinetic Art Installation (Romie)
LIGO SEC Kinetic Art Project
Quotes are due tomorrow at 5pm. Answered a number of questions from
contractors. Jonas from HPD is sending the drawings to me today.
LLO Outreach (Thacker)
Prepared two new activities for teachers and students; prepared and
delivered children's program for 1st - 5th grade. Mentored RETs; exhibit development, &
comprehensive curriculum ties to activities are being developed. Website educational materials are being
prepared. Developing new outreach
posters for St. Parish Technology Conference in late July
L1 CDS (Bogue)
- vacation
- added
2308 filter modules to the daq.
This required a reduction in the amount of lookback on fb1.
- swapped
in a replacement server for delaronde, one of the dmt servers.
- built
an anonymous rsycn server for medm screens.
- helped
Joe G. with some LSC web stuff.
LIGO Computing and Network Security (Roddy)
- Still
working with Caltech & Charter Communications on the backup network
connection. There are some issues
with Grants of Easement, etc.
Waiting to hear back from Charter at this time.
- Network
outage over the weekend for about 2 hours.
This was again somewhere in the Bell South circuit, not LLO or LSU.
- Working
on the LLO vulnerability assessment.
- Ordered
a temperature monitor for LDAS. If
LDAS chooses to use a different method, I will use it in the computer
users room to monitor GC servers.
If LDAS chooses to use it, I will likely duplicate the same system
in the CUR.
- Attended
a free VMware seminar in Baton
Rouge. The
seminar had some useful information and possible future items useful to
GC.
- Worked
with Dave on firewall changes to LHO's CDS NAT router. Needs some further changes.
General computing and LDAS admin (Giardina)
- security
server activity logs automatic archival and posting to website had
failed. I was cron errors due to
GID changes. I manually ran the
missing weeks, and fixed the cron problem.
All is well.
- new
GC and email accounts for 2 users
- with
Shannon(mostly Shannon), troubleshooting
various network issues, switch swap, etc.
- with
Shannon(again mostly Shannon), mail
server disk issues.
- installed
backup software on new hire PC, connected external drive
- began
creating rules for our spam filter, this will be an ongoing process
- other
usual user requests and support
- ejected
tapes for shipment to CIT, imported and labeled new
- failed
disks in T3-8 and T3-1, replaced with disks from spare units. we are down to 8 spare disks. I am going to check directly with disk
vendor on warranty status.
- numerous
changes and additions to cluster_mon
- with
Bernie, racked the 3 new 3511s, connected power
- replaced
network cable for nodes 57 and 182
- replaced
power supply in nodes 114 and 121.
also one of our recent arrival nodes has a bad power supply. I only have one spare and am waiting
for more to arrive, as this is not yet a production node.
- node31
has bad hda, and node35 continually freezes up. need to replace hda in node31 and
troubleshoot node35
- found
3 "missing" tapes that the robot could not detect. They were in the silo. I re-injected them and robot now finds
them.
- verified
the additional channels added to the frames would not consume all of
/frames filesystem. Lisa reduced
look-back to help avoid this, and we should be OK.
- L4
createRDS restart required due to reduced look-back of full frames. Process was looking for a directory
that had been removed.
- L4
Publishing restart repeatedly failed.
Call to the expert(Ben) resolved.
Ben discovered LLO was running old versions of the publishing
scripts.
- need
to swap network cable at our work area in the LDAS room
- under
high load yesterday, some nodes ( in a rush I neglected to write down
which ones (BAD! BAD!) ) made / filesystem read only. They would only respond to ping, local
console was frozen with the disk errors on screen. Rebooting brought them back to
life. I will keep a close eye on
these, as we may experience higher disk failure rates due to the recent
HVAC problems in the LDAS room
Data Analysis (Yakushin)
Storage/Condor/LDAS admin:
- Condor
was upgraded to version 6.7.20.
- LSCdataFindServer
was patched.
- We
had another two incidents with the east HVAC unit in the LDAS room: on Sat
07/01 and on Sat 07/8 (the previous one was on 06/27). All three incidents
were identical: a blown fuse in the outside unit. As a result the indoor
unit circulated hot air resulting in high temperature in the eastern part
of the LDAS room. We believe that the cause for these failures was
identified and fixed during the last repair: two of the control wires were
swapped (it looked like they were shorted). The result of the first
incident: T3-18 (part of /frames) went down later that night and required
power cycling (the control room had to switch to using fb0 until it was
fixed); some corrupted frame files were tracked down and removed
afterwards. The result of the second incident: 3511-2 (part of /home) shut
itself down due to the high temperature; after it was brought up, several
corrupted files were found; also one of the T3 disks failed and was
replaced. The result of the third incident: 3 failed T3 disks that had to
be replaced. We are working to install temperature probes in the LDAS room
so that operators can promptly notice any HVAC problems from the control
room. It might be useful to have LDAS room temperature in the raw frames
together with other PEM channels as is done at LHO (H0:PEM-LDAS_ROOM_TEMP0
and H0:PEM-LDAS_ROOM_TEMP1).
- Two
new 3511s (that will replace /frames T3s in couple weeks) and 1 JBOD for
fb0 are upgraded to the new firmware and are currently tested.
- The
transfer of h(t) and new burst MDC frames from CIT to LLO continues (very
painfully and slowly due to the huge mess with h(t) production and poor
LLO's network).
- The
new burst MDC and h(t) frames are published to LDR at CIT.
- Transferring
GWN2 burst MDC frames from PSU to CIT. After 3776 (out of 4248) files were
transferred, LDR is stuck (looks like a problem with publishing the frames
at PSU).
Data analysis:
- Published
S5 production triggers on h(t) and DARM_ERR (version 2 calibration): http://ldas-jobs.ligo-la.caltech.edu/~igor/TRIGGERS/S5.
- Working
on publishing SG2 and SG3 simulations triggers.
- The
simulations on GA2, WNB2 and SG4 are still running.
- All
the above will be a part of the burst search paper on the first few months
of S5 (from the beginning of S5 to April 03) as discussed during the last
burst f2f meeting at MIT.
- Working on online coherent waveburst
infrastructure.
Mechanical and Optical Systems
(Coyne)
See Advanced LIGO
Controls and Data Systems (Bork)
A draft of a technical note detailing the measurement
result for the PCIX ADC modules has been completed. The note should be
available for distribution next week. Additional, more detailed, tests are
planned for next week and beyond. Preliminary results show that the input
referred noise of the module is ~10uV/rtHz on a 40Vp-p input and a sample rate
of 16384Hz. In comparison, the Pentek 6102 has an input noise of ~15uV/rtHz on
a 10Vp-p input.
Anti-Alias, Anti-Image, and Timing Interface boards for HAM SAS, LASTI ISI,
40M DC detection and the LASTI Squeezing Experiment are being fabricated and
tested.
We met with the 40m staff to get up to date on the Output Mode Cleaner
controls. Rana has since provided an updated controls diagram, which we are
still reviewing. Installation of OMC controls has been requested in the next
few weeks, but we'll know better exactly where we are schedule wise next week.
We received the computer for the Ponderomotive experiment controls and are
doing some initial testing. This is the first multi-core, multi AMD Opteron CPU
system that we have tried the real-time Linux on. Once we got an update to
Linux 2.6.16, it seems to work fine.
40-Meter Interferometer (Weinstein)
IFO Commissioning
- Rana,
Sam and the students continue to work on locking the IFO in the full
DRFPMI configuration. Jenne found and fixed a busted cable on AS166 RFPD,
and now the signal is increased by a factor 50. This thing has been busted
since January; its repair will surely facilitate lock acquisition efforts!
After that, they locked all 5 degrees of freedom easily and brought the
arm power up to ~ half-full, before noise sources stymied further
progress. Under investigation.
- Monica
has diagonalized the mode cleaner WFSs and the system now works well. She
is developing diagnostic tools for the control matrix.
- Royal
has calibrated the oplevs on all four test masses using the arm power
variations as the mirror alignment is changed. She is studying the oplev
servo noise and working to identify the sources of high-frequency noise
(oplev laser, electronics). At low frequencies, there are indications that
some of the damping servos are not working right. To be investigated.
- Using
her calibration of the test mass oplevs, Royal has measured the beam
angular jitter in the interferometer, and extrapolated through the signal
mirror and output mode matching telescope to predict the jitter that the
output mode cleaner will see, and resultant transmitted power
fluctuations. Rana used this information to specify the requirements for
the alignment control and the output mode cleaner servo.
- David
and Osamu continue to develop the noise budget model. David added the
model of the DRFPMI optical response to replace the simple
Initial-LIGO-like cavity pole model. They remeasured the XARM noise
spectrum with the dewhitening filters turned on; the noise floor at high frequencies
was ~ 10^-17 m/rtHz, but with lots of lines.
- David
will begin measuring the analog transfer functions from the DAC, through
the dewhitening filters, to the coil drivers. Then he'll tune the digital
compensating filters and make sure that the switches do the right things.
This could significantly improve the noise spectrum.
IFO Modeling
- Monica
continues to develop the AdVIRGO e2e package, starting with just one arm.
It locks at low power, and she is learning how to deal with the radiation
pressure as the power is turned up.
- Osamu
in continuing to work on modeling the alignment instability in AdLIGO,
with e2e.
- Jenne
is beginning some calculations to estimate the effect of the Sidles-Sigg
angular instability in the 40m mode cleaner, to see if we can measure it.
DC Detection and Vacuum Squeezing Development
- Sam
and Darcy are making final measurements on the DC readout beamline prior
to disassembly for clean/bake. The OMC transmission is only 50%, which
they traced to a ~0.5% clipping of the beam at the small (7 mm dia) curved
PZT-mounted mirror. They are working on various methods to fix this, but
it might require ungluing the mirror and replacing it with a spare. They
have remeasured the OMC mirror transmissivities (input couplers are 1.54%),
finesse (213), total round trip loss (5.8%!), and other parameters.
- Darcy
found that our first TT PZT stack developed a resonance at ~ 80 Hz, with a
strong pitch-yaw coupling. Opening up the case, they found a loose glue
joint. They sent the stack back to Piezo-Jena, and Rich is ordering a
spare stack. This will surely delay our vacuum installation significantly.
Fortunately, Darcy reports that the 2nd TT PZT stack is fine, no
resonances below ~450 Hz.
- Rich
is taking the lead on assembling the controls for the DC readout. He and
Ben are reviewing the wiring diagram and filling in the details. They
walked through the 40m this morning to better visualize the placement of
the electronics and cabling.
- Rana,
using data from Royal, gave Rich the specs for the tip-tilt PZT and OMC
PZT drivers. Rich has a first cut of the driver board. As a backup, he is
ordering the commercial drivers from Piezo-Jena.
- Ben's
QPD Whitening board is back from PCB Express. It looks fine, and parts are
arriving today to put it together.
- Ben
has a little more machining to do on the DCPD mount to make a place for
the resistors to be mounted, and to lower the possibility of capacitive coupling
of the head to the base.
- The
DC PD seems a little noisy, so Ben has brought it back to the Wilson House
for more testing.
- Ben
got more of the ceramic resistors that we plan on using for the in-vacuum
photodiode, and gave a good sample to Bob for RGA testing. The larger
sample should let us know whether they are really vacuum compatible.
- Rolf
has the computer and PCIX boards (ADC, DAC, RFM) for the controls, and he
and Alex are working on assembling the system. Jay will provide the
anti-aliasing, anti-image and IO chassis interface cards.
- Rana
and Sam have drawn up a block diagram of the controls software to be
implemented by Rolf (OMC length control and tip-tilt alignment control
servos using dithering). Rolf had no objections, but he notes that several
new software functions need to be implemented.
- Go
installed the new PPKTP crystal for the OPO. He saw lots of
second-harmonic-generated green light from it, indicating that it has a
high chi2 nonlinearity. He replaced the old SHG with the swapped-out OPO,
expecting it to be more stable; after mode-matching and alignment, he
locked it stably for an hour, and saw green light at room temperature.
He's preparing the in-vacuum parts (one fixed mirror and one movable
mirror) for injecting the squeezed vacuum into the asymmetric port. He verified
that these mirrors remain highly reflective even at incident angles far
from 45degrees.
PSL
- The
PMC transmission was oscillating ~5% diurnally and drifting low by 5-15%
over the last couple of days. Matt touched up the alignment of the input
beam and brought it up ~15%.
Electronics, Controls, Computers
- Jenne
has built a ~4 MHz notch filter and low-pass filter for the mode cleaner
servo, in an effort to reduce high frequency noise that Rana believes is
due to the beat between the IFO control sideband at 33 MHz and the mode
cleaner control sideband at 29 MHz. She and Rana will implement it soon.
- Bob
is ready to install new RF distribution panels at the RF rack and the LSC
rack, in the near future. It will take a couple of days and be somewhat
disruptive.
- Jenne
has completed a mount for an AM laser to be used for PD testing. She
measured the RF response of all the LSC RF photodiodes on the sensing
tables, and all seem to have reasonable response functions. She's fixing
an unwanted notch in the AM laser setup at 4 MHz and will retest all the
RF photodiodes again. She'll also compare her AM laser test setup with the
one at Wilson House.
- The
RF lines from our optical spectrum analyzers at the AP and SP drift about.
To see if this was due to thermal drifts, David installed thermal
insulation (foam jackets) and temperature sensors on the OSAs and sent
them in to the DAQ system. If necessary, he'll set up heaters and thermal
stabilization servos. Work in progress.
- Rana
has identified a code bug in the filter modules which causes the front-end
cpus to run much slower when the gain is set to zero. Setting it to 1e-6
fixes the problem. rolf has been alerted.
- Vuk
copied over IFOtest from LLO to the 40m, and got it working. It performs
automated checks of the various gains, switches, filter modules etc.
Lab Infrastructure
- Steve
replaced the failed RGA with a spare, baked out by Bob, and is in the
process of calibrating it. It seems to give sensible results.
- Steve
arranged for a "doggy door" installed between the IFO hall and
the clean room in Bob's lab, to facilitate the running of cables (and
small parts) between the two rooms. The overpressure in Bob's clean room
keeps a steady flow of clean air into the IFO hall.
- Steve
reports a large spike in the particle counts on July 4th.
- Sally Sharaf, visiting from Rochester to work with Go on vacuum
squeezing, received lab safety training from Steve, and an entrance eye
exam.
Thermal Noise Interferometer (Black)
Report for W/E 7/6/2006:
All of the linearalized models we can come up
with for thermal self locking give integer power laws in the frequency
response, and Royal saw a non-integer-power-law response last summer. Something interesting is going on here, but
we haven't yet determined if it is a physical effect or some systematic error
in the measurement.
Report for W/E 7/13/2006:
The ring dampers are finished, and we are in
the process of installing them.
The new laser has a much better beam profile
than the last one, and Mike is in the process of installing it in the photo
thermal experiment.
LASTI (Ottaway)
No report.
Blackburn:
Worked with Sanjit Mitra (visiting student from IUCAA) to install FTOOLS Software (trip down memory
lane for me) on his workstation to allow for easy extraction of WMAP datasets
stored in FITS Tables for use in stochastic analysis efforts.
Brown;
- Continued
to work on a couple of Tapir projects: LIGO-EMRI analysis and LISA SMBH
analysis.
- Helped
Lisa get the S4 ringdown pipeline working.
- Continued
to work with SURF student Alex to discuss his project.
- Got
production numerical relativity runs set up and running. Working on integrating them into Condor
on our cluster.
- Did
some maintenance for the online BNS search to fixed problems caused by the
recent cluster downtimes.
- Help
David with some issues he was having with the inspiral DAX.
- DASWG
stuff: Released Glue version 1.7, dealt with some issues with the segment
database (helped Keith with segment insertion and fixed a replication
issue) and checked new calibration frame specification.
- Wrote
talk for and attended PAC meeting.
Chatterji:
- Presented
status of LIGO/Virgo joint data analysis to PAC meeting.
- Continued
preparation for low threshold Q Pipeline search of early S5 data.
- Continued
working with Rubab Khan (SURF student) to develop a clustering extension
to the Q Pipeline. We have completed
the infrastructure for evaluating the performance of different algorithms,
and a first version of a density based clustering algorithm.
Dupuis:
- prepared
and gave a talk on pulsar searches at the PAC meeting
- continued
S5 pulsar search investigations
Mandic:
- I
made a first-pass at the S5 H1L1 all-sky stochastic analysis. The analysis
was done with ~1-sec time-shift (i.e. blind), and it yields the
theoretical sigma of 1.7e-5 for the flat spectrum, which is 2.5x better
than S4, but still not as sensitive as the BBN bound. The analysis
revealed 4 correlated lines (48.0 Hz, 180 Hz, and two simulated pulsars), but
is otherwise very clean.
- I
updated the S4 all-sky stochastic paper, to include the BBN bound in the
study of cosmic strings. The paper should be submited for another round of
LSC review next monday.
- I
continue to work with Xavi S. on the implications of the S4 stochastic
result on the cosmic strings models. We are planing to explore a larger
group of cosmic strings models (to include large-loop models), including
modifications to the calculation of the stochastic GW background. We are
also looking at other experimental bounds.
- With
my SURF student M. Lukic, we continue to look at the time-shift approach
to analysis of H1H2 data.
Mendell:
I am continuing work on the S4 PowerFlux, StackSlide, and Hough S4 paper.
This week I have been running jobs to follow-up outliers, and producing plots
of these. Between now and the LSC meeting the goal is to have a close to final
draft of this paper, which I think is doable.
Shawhan:
- Investigaged
Data Viewer issue at LHO.
- Rebuilt
pulsar simulation code for hardware injections with a later date for
validity of leap second information.
- Reviewed
S3/S4 time-domain known pulsar search paper draft.
- Worked
with Chris Pointon on antenna response calculations.
- Set
up new home page for the Burst Group.
- Debugged
SeqInsert problem at LLO.
Grid research (Blackburn)
TCLGLOBUS
The issues that were holding back the release of TclGlobus 1.3.0 have been
resolved. The problem was with firewall settings on a server being used to test
one flaver of Fedora Core Operating System. Switching to a different server
with this OS which didn't have the firewall restriction resolved the failures.
The plan is to have the release later next week.
GRID COMPUTING AND OSG
- Resolved
all dependency issues for installing the Grid Job Submission Client on a
desktop as a standard unix users. Previously there were components that
could only be made to work if they were install as "root" -
making for a rather non-friendly client tool.
- Working
on a short list of open problem reports for the Grid Job Submission Client
in preparation for the first public demonstration at next week's joint
LIGO/VDS developer's meeting to be held here at Caltech. These PRs are
needed to enhance the experience in using this tool during the
demonstration.
- Began
organizing the face-to-face meeting here at Caltech with the VDS software
developer's from ISI for next week. Plan to focus on issues experienced
with running LIGO workflows on the OSG, but will also address issue
associated with running DAX/DAG translations via Pegasus on the LIGO Data
Grid.
- Met
via Telecom with Pegasus/ISI engineers, GADU VO work flow engineer, Illy
Narsky (OSG App Coordinator) and Kent Blackburn on work flow engineering
issues on OSG.
- Worked
with Kent Blackburn, removed three segments of gravity wave files that
caused the HIPE analysis to fail due to missing data. Re- running the HIPE
analysis without the problematic segments succeeded.
- Attempting
to create a HIPE analysis for the full S5 data set using Java 1.5 based
gencdag uses all the available memory (600 MB) on the submit host. Further
analysis of the memory requirements is underway and may require support
from the VDS developers.
- Worked
with Michael Samidi and Kent Blackburn, to fix Problem Report bugs for
supporting HIPE analysis in the
LIGO Work Flow Planner.
- Successfully
ran a substantial subset of the S5 data with HIPE on the STAR_BNL OSG
production site and on the LIGO-CIT-ITB test bed site.
- Attended an OSGStorage Technical Group meeting, OSG
Council and OSG Integration Test Bed meeting telecoms.
Laboratory Computing (Anderson)
LDAS Software Systems (Maros)
*** Note add by Anderson:
Thursday night testing was the first stable running of the LDAS development
software in 3 Months after major infrastructure changes--Congratulations Ed and
Mary!
To help with the timeout issues in several of the APIs, a new extension to
Tcl was written called setTIDCallback. This allows for a new model of
programming at the Tcl layer where the application can register a callback on a
C++ thread that is invoked when the state of the thread is changed. It has been
shown to be more reliable than TCL's trace variable semantics. It has been
incorporated into the metadataAPI, frameAPI, ligolwAPI, and eventmonAPI.
Communication errors between the manager and metadataAPI have been observed.
It appears as if the manager has sent the API a request which the receiving API
never receives or perhaps just never processes. This issue remains under
investigation.
System testing was done using 1.8.235. There were minor patches that needed
to be applied to fix some of the errors being reported. The LSync test still
does not match up with the diskcache's cache.
The LDAS-TEST system is currently being used to isolate when a problem with
the createRDS commands was introduced. The current working theory is that it
may be the result of a change to the tool set used to build the software. Both
the upgrade of GCC to 4.0.3 and the removal of STLport are under investigation.
LDAS System Administration (Anderson)
Caltech
(Dan Kozak)
- Restored
some deleted files for Diego.
- Helped
Larry Wallace with the setup of his new 3511 RAID unit.
- Helped
Igor with filesystem problems associate with the HVAC going out and the
RAID boxes shutting down due to the temperature.
- Copied
some L0 frames back to LLO from CIT (the copy 1 tape at LLO had a bad spot
on it and the files were unreadable).
- Worked
on figuring out why the nightly metadata dumps of /home (CIT) aren't
finishing in a timely fashion. So
far we've found ~10M superflous files, we'll see if the dump performance
improves when they are all removed.
- Helped
Igor set up the new 3511 JBOD at LLO.
- With
Dwayne's help, located some "missing" tapes at LLO.
- Doing
testing to determine optimal stripe size for new 3511 based /frames at LLO
(ongoing).
(Phil Ehrens)
- Upgraded
Sunopteron to Solaris 10 upgrade 2. Using the upgrade path worked smoothly
on this machine.
- Attempted
to upgrade ldas-suntest3 to Solaris 10 upgrade 2 via the upgrade path.
After chewing on the first cd for nearly 2 hours, the upgrade failed with
a message that c0t0d0s0 could not be successfully upgraded.
- Added
test to log_mon to detect absence of condor_master process on cluster
nodes.
- Made
log_mon watchdog cron script log_mon_mon.tcl robust against multiple
restarts due to log_mon parsing of VERY large logfiles.
- Updated
and added MANY sysadmin wiki documents.
- Created
script for backing up critical files, network configuration and partition
information that works without modification for both Linux and SunOS.
- Added
usage path to grid user addition script that causes it to only synchronise
cluster node user information by cloning the /usr1 directory info, passwd
and group files from ldas-grid.
- Investigated
cause of loss of printing capability on a number of Millikan 6th floor
machines. It seems that anyone who attempted to print during kuma's
downtime wound up with a mangled printer configuration. This is properly
fixed by re-enabling printers by hand via 'ssh root@$host 'lynx localhost:631'.
Alternately, the file /etc/cups/printers.conf can be edited to set the
'State' of affected printers to 'Idle' and then restarting cups, at which
point running 'lpq' should show no queued docs if things worked.
(Erik Espinoza)
- Ran
tests with LC_ALL="C" on frog, including ring code from Duncan.
- Looked
for possible side effects for tweaking i18n settings globally.
- Found
and reported restart bug in log_mon, caused log_mon to keep restarting.
- Assisted
Michael Samidi & Kent Blackburn on finding Condor dependencies
(including list of compat rpms).
- Restarted
print spool for Ed Maros on ngc101.
- Rebuilt
ligoconf rpm for GC Desktop (removed /etc/ld.so.conf.d/ldas.conf).
- Configured
ldas-jobs@CIT web server for web indexing.
- Disabled
SELinux on ldas-pcdev2@CIT.
- Fixed
local copy of lscsoft repo.
- Installed
PostgreSQL @ LLO, LHO, & MIT.
- Assisted
in Condor 6.7.20 @ LLO & LHO.
- Tested
Quill @ LHO, LLO, & MIT.
- Looked
into legacy openssl lib mismatch.
- Contacted
ASA (again) about heatsink brackets.
- Restored
node321, node322, and node324 into working order.
(Stuart Anderson)
- Upgraded
Condor to 6.7.20 at LHO and LLO.
- Synchronizing
copies of S5 h(t) frames between CIT and LHO/LLO.
- Finished
removing the old /ldcg/lib setting in ld.so.conf on all the production
clusters.
Livingston
(Igor Yakushin)
- Condor
was upgraded to version 6.7.20.
- LSCdataFindServer
was patched.
- We
had another two incidents with the east HVAC unit in the LDAS room: on Sat
07/01 and on Sat 07/8 (the previous one was on 06/27). All three incidents
were identical: a blown fuse in the outside unit. As a result the indoor
unit circulated hot air resulting in high temperature in the eastern part
of the LDAS room. We believe that the cause for these failures was
identified and fixed during the last repair: two of the control wires were
swapped (it looked like they were shorted). The result of the first
incident: T3-18 (part of /frames) went down later that night and required
power cycling (the control room had to switch to using fb0 until it was
fixed); some corrupted frame files were tracked down and removed
afterwards. The result of the second incident: 3511-2 (part of /home) shut
itself down due to the high temperature; after it was brought up, several
corrupted files were found; also one of the T3 disks failed and was
replaced. The result of the third incident: 3 failed T3 disks that had to
be replaced. We are working to install temperature probes in the LDAS room
so that operators can promptly notice any HVAC problems from the control
room. It might be useful to have LDAS room temperature in the raw frames
together with other PEM channels as is done at LHO (H0:PEM-LDAS_ROOM_TEMP0
and H0:PEM-LDAS_ROOM_TEMP1).
- Two
new 3511s (that will replace /frames T3s in couple weeks) and 1 JBOD for
fb0 are upgraded to the new firmware and are currently being tested.
- The
transfer of h(t) and new burst MDC frames from CIT to LLO continues (very
painfully and slowly due to the huge mess with h(t) production and poor
LLO's network).
- The
new burst MDC and h(t) frames are published to LDR at CIT.
- Transferring
GWN2 burst MDC frames from PSU to CIT. After 3776 (out of 4248) files were
transferred, LDR is stuck (looks like a problem with publishing the frames
at PSU).
(Dwayne Giardina)
- Ejected
tapes for shipment to CIT, imported and labeled new.
- Failed
disks in T3-8 and T3-1, replaced with disks from spare units. we are down to 8 spare disks. I am going to check directly with disk
vendor on warranty status.
- Numerous
changes and additions to cluster_mon.
- With
Bernie, racked the 3 new 3511s, connected power.
- Replaced
network cable for nodes 57 and 182.
- Replaced
power supply in nodes 114 and 121.
Also one of our recent arrival nodes has a bad power supply. I only have one spare and am waiting for
more to arrive, as this is not yet a production node.
- node31
has bad hda, and node35 continually freezes up. need to replace hda in node31 and
troubleshoot node35.
- Found
3 "missing" tapes that the robot could not detect. They were in the silo. I re-injected them and robot now finds
them.
- Verified
the additional channels added to the frames would not consume all of
/frames filesystem. Lisa reduced
look-back to help avoid this, and we should be OK.
- L4
createRDS restart required due to reduced look-back of full frames. Process was looking for a directory that
had been removed.
- L4
Publishing restart repeatedly failed.
Call to the expert (Ben) resolved.
Ben discovered LLO was running old versions of the publishing
scripts.
- Need
to swap network cable at our work area in the LDAS room.
- Under
high load yesterday, some nodes (in a rush I neglected to write down which
ones (BAD! BAD!)) made / filesystem read only. They would only respond to ping, local
console was frozen with the disk errors on screen. Rebooting brought them back to life. I will keep a close eye on these, as we
may experience higher disk failure rates due to the recent HVAC problems
in the LDAS room.
Hanford
(Greg Mendell)
- I
have been performing routine sys admin tasks, but have nothing much to
report since the last Weekly. I will soon be generating and publishing
into LDR SFTs for the pulsar group made from h(t) for times these are
missing, once new h(t) files are synchronized between the sites and
Caltech. And I am working to help
procure another order of tapes for archiving the S5 data throughout the
next year.
(Ben Johnson)
- Installed
new 3511 JBOD on fb0. This included updating firmware on old 3511 on fb0
and growing fb0's /fb0_frames filesystem.
- Finally
have a LSCdataFind client and server that support the --show-times option.
- Upgraded
Condor to 6.7.20. Shutting down condor caused a user's dag to fail; this
appears to be due to not using the ldas-grid:/usr1 directory for the
dagman log files. Removed /ldcg/lib from the cluster's ld.so.conf at the same
time as the upgrade.
- Replaced
two T3 HDDs. One in /frames, one in the /dmt T3. Plans are to move /dmt
over to /fb0_frames when possible.
- Working
with Malik Rakhmanov (and Vern Sandberg, when he returns from the PAC
meeting) on how to identify where and how possible glitches/corruption can
enter the data stream.
General Computing (Wallace)
MIT
(Keith)
- Reviewed
a number of ldap logistical issues with Larry.
Livingston
(Dwayne)
- Security
server activity logs automatic archival and posting to website had failed.
They were cron errors due to GID changes.
I manually ran the missing weeks, and fixed the cron problem. All is well.
- New
GC and email accounts for 2 users
- With
Shannon(mostly Shannon), troubleshooting
various network issues, switch swap, etc.
- With
Shannon(again mostly Shannon), mail
server disk issues.
- Installed
backup software on new hire PC, connected external drive
- Began
creating rules for our spam filter, this will be an ongoing process
- Other
usual user requests and support
(Shannon)
- Still
working with Caltech & Charter Communications on the backup network
connection. There are some issues
with Grants of Easement, etc.
Waiting to hear back from Charter at this time.
- Network
outage over the weekend for about 2 hours.
This was again somewhere in the Bell South circuit, not LLO or LSU.
- Working
on the LLO vulnerability assessment.
- Ordered
a temperature monitor for LDAS. If
LDAS chooses to use a different method, I will use it in the computer
users room to monitor GC servers.
If LDAS chooses to use it, I will likely duplicate the same system
in the CUR.
- Attended
a free VMware seminar in Baton
Rouge. The
seminar had some useful information and possible future items useful to
GC.
- Worked
with Dave on firewall changes to LHO's CDS NAT router. Needs some further changes.
Hanford
(Christine)
7/6/06 weekly
- Still
setting up new computers.
- Set
up a new account for a new SciMon, directed a new short-term visitor to
the reception office to get checked in.
The visitor wants me to provide him with a GC Linux computer, so
I'm working on finding something suitable.
- Spent
some time working with Dave to figure why dataviewer wasn't working on GC
computers. The display isn't
automatically being set. There are
several versions of the dtt and dataviewer startup scripts, trying to
figure out which version works best.
7/13/06 weekly
- Finally
have a Cisco engineer working on the problems with the router. His first comment is that our current
router can't do GigE bandwidth. The
most it is capable of is 300 Mb/s.
He also thinks that much of the dropped packets and congestion
problems are caused by poor fiber between LIGO and PNNL. This is something we have known about
since the beginning, but the reflections and losses on the fiber line have
been so far deemed to be acceptable.
The Cisco engineer will be here next week to do a more thorough
exam of the problems. Right now it
sounds like I need a new router in order to get GigE bandwidth and
possibly in order to get the backup network working.
- Working
on the cybersecurity vulnerability assessment for Albert and Shannon.
- Reviewed
the Nessus scan that Shannon did from CIT
just before 4th of July. Started
cleaning up the computers that had security holes.
- Still
setting up new computers.
- The
Sun Ultra 25 computers that I ordered through TechMart have not shown
up. I am trying to get a status on those.
- Removed
the hard drives from 6 computers that are being taken to be surplussed at
an auction house.
- Other
user support for summer visitors.
CIT
(Mike)
- Problems
with my sysadmin laptop. I ended up having to reload this from scratch. I
still have a few more applications to load that I support.
- Backed
up Barry Barish's laptop.
- Setup
PAC meeting with wireless access point plus other misc. support.
- Looking
into renewing our Primavera maintenance contract. This will give us access
to download the latest version of this software. It looks like I will be
loading a new server for this upgrade/migration. We are currently running
on server 2000, we will be upgrading to server 2003.
- Started
loading a new Sun server for the home accounts. Larry is finishing this
installation up. I had many problems using the vi editor working off a
VT100 terminal connection. Larry has decided to purchase a video card for
these types of servers.
- Microsoft
released its monthly patch cluster. I tested these patches with all
GC/Engineering software. All have passed.
- Finished
up end of month backups on all NTSRV's.
- Other
misc. user support.
(Veronica)
- LIGO: Worked on the Educational Resources
website. Installed and tested the
backend apps, updated the frontend.
Updates of the Elba website. Updates /support of the PAC
meeting. Updates of the LIGO
webpages. Worked with Dave Beckett
on the how-to of webpage updates for the newsletter. Updates of the roster database.
- LSC: Updates of the database of technical papers
and the LSC-related mailing lists.
(Christian)
- Alan
Weinstein - Hardware failure on laptop. Rebuilt new hard-drive with Windows XP and transferred back all
of Alan's data and settings.
- Bill
Kells- transferred all of Bill's data and settings back to his new laptop.
- John
Miller - Configured new workstation with the standard Ligo image for John.
- Cindy
Akutagawa - Replaced drum kit on local printer.
- Cleveland- Replaced
old monitor with new LCD monitor.
- Gina
Salone - Replaced old monitor with new LCD monitor.
- Millikan
- Replaced toner cartridges on HP 5500 printer.
- 3flr
W/B - Replaced toner cartridges on HP 5500 printer.
- Worked
on the Spam Filters with Mike and Larry.
- Other
misc.: Continued onsite software/phone support.
(Bruce)
- iLog
Maintenance: (0.5
days)
General iLog maintenance (user
adds, keyword adds, systems work, etc.)
(Larry)
- The
procurement cycle continues. Still placing orders for different items. It
appears we need a number of new workstations and will be working on
acquiring one of SUNS new systems.
No work on the maint. contracts but they need to be worked on in
the near future. Worked with Mike
concerning some license issues and quotes.
Still working on a resolution to the Monarch computer issue. I hope
to hear something back on that next week.
- Still
working with the PMA group in trying to get a air-conditioning unit for
the computer room upgraded.
- Working
with Mike on a number of new installations. The Solaris10 installs needed
some minor tweaks but overall they went OK.
- Rebuilt
one of the major home drives. The build took a full 24 hours and then
recovering from stale NFS handles trickled in for about a week. Along that same line the new home
account server has been built. Thanks to Dan Kozak the new drive system is
installed on the server and we are presently testing it out. Transferring
home accounts to the new system should start next week.
- Tested
out a new projector system. It looks like we will be able to replace the
existing projectors with quieter ones.
- Started
working on a little project for Stan in getting something setup for the
display cabinet in front of the LIGO office.
- Worked
with Gina on a number of procurement and office equipment items.
- Still
adding student accounts. This and the orientation of the new students has
been taking up some time the past few weeks.
- Working
on and delivered a couple of documentation items for Albert.
- Repaired
another E2E machine. They are starting to get to the point where they need
to be replaced.
- Assisted
the DCC with a number of document items.
- Repaired
the backup tape system again. The tapes are getting to the point to where
they need to be replaced. The system also will need to be augmented in the
near future to accommodate the increased amount of data being generated.
- A
lot of misc. user support.
- Worked
a number of e-mail issues. So far all the problems were found to be
enduser misunderstandings, typo's, items going to their junk file,
incorrect addresses....
Mail Statistics for Jun 29, 06 - July 12, 06
|
Mail Statistics
|
7/13/2006
|
|
Rejected Messages
|
79,9771
|
|
Virus Messages
|
4,148
|
|
Accepted Messages
|
40,017
|
|
Total Messages
|
119,994
|
Note 1. Possibly a couple hundred more
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Systems,
Management
Modeling and Simulation (Hiro Yamamoto)
Advanced LIGO LSC/ASC study using FP with Quad suspension (Osamu)
Investigation of a FP cavity with AdLIGO parameter is almost done. We got
several numbers as result. First, lock can be acquired with less than 0.5%
(~3kW inside cavity) of full power if radiation pressure exists. Even if lock
is acquired, pitch offset due to the radiation pressure by 10% of full power
brakes the lock if there is no ASC. E2E says that the ASC using WFS is possible
with AdLIGO quad-suspensions by feeding back the control signals to penultimate
mass with 10Hz band-width. RMS test mass angle fluctuation will be less than 10-9m
(depends on filters and gains) and control signal will be 0.1mN (Max 20mN).
Optical spring in ASC has been seen in frequency domain on E2E. It will be 4-5Hz and this frequency agrees
with models well.
Advanced LIGO Mechanics : preparation for it (Sany and SLU group)
Continued e2e modeling of LIGO 1 Mode Cleaner. Feeding DAQ ground motion
signals recorded at LLO as input to the e2e HAM1 and HAM2 boxes, computed MC
transmitted beam?s angular fluctuation. By
adjusting the MC suspensions? Yaw local damping gain, the power spectrum of the
computed transmitted beam?s Yaw motion is very close to the corresponding DAQ
signal (the MC transmitted beam Yaw recorded at the same time as the DAQ ground
motion). The spectrum of the computed transmitted beam pitch motion appears to
be different from the corresponding DAQ pitch motion; especially, there is a
high peak around 1 Hz in the computation. This indicates that the position and
pitch local damping is not working well in the e2e model. We are currently
looking into the problem.
Advanced Virgo Simulation (Monica)
Tests of lock acquisition for one Fabry-Perot cavity (with AdVirgo
parameters) have been performed: the cavity has been locked using the reflected
and transmitted signal independently with a laser of 20W. The feedback filter
has been improved in order to avoid a strange oscillation at 1kHz that was
preventing modler_freq to work properly.
Static IFO Simulation (Hiro)
Code development of SIS still going. A FP version is finished. The loss due to the orange peel structure was
revisited. The loss is estimated to be a few ppm. In order to
validate this calculation, and to study the effect of surface aberration in
general, a noise generator has been implemented. This code generates surface distributions with
a given rms with frequency spectrum of f0, f-1 (most
likely one) and f-2.
ALFI ( e2e front-end) (Bruce, Melody)
Keep working on new feature implementations : primitive using templates, GUI
based comments and grouping of objects.
Seismic Isolation
Joseph Giaime Agenda for
the weekly SEI telecom
Friday, July 7, 2:00 pm
Eastern, 1:00 pm Central, 11:00 am Pacific time
BSC SEI Status
- received
the stage 1-2 shims this week. Stage 0-1 shim modification designed
and ordered.
- John
(summer student) has made mass simulators for the actuators.
- John
is also making a SEI web site similar Oddvar's HEPI web site.
- Rich
is working on the mass & cg calculations.
- John
remeasured the pod can resonance w/o mass loading; data aren't reduced,
but resonance moved from 75 - 100 Hz.
- Hole
for barrel nut in the riser for 0-1 springs is undersized. Myron is
reaming it out a few mils.
- Ken
is having difficulty getting through to accu-glass regarding our overdue
wiring order.
- Shyang
teaching Joe H how to lock/unlock seismometers and change 'programs.'
- Joe
H and Ken W assembling and examining seismometer pods. Modifications
to wiring harness to be communicated to Ben.
Stanford
- Tarm
working on seismometer machining.
- Brian
& Dan collaborating on calculation relating thermal sensitivity and
resonance frequency of Euler spring, as compared with non-buckling spring
geometry.
- Corwin's
HEPI paper in final edits.
- Matt
& Brian wiring L-4C's for noise test.
- Witness STS-2 acting 'oddly.'
BSC Seismic Isolation Assembly and Test
Problems were encountered with the spring installation fixture. The fixture
has been redesigned and the modifications made which allow us to install the
longer stage 0-1 springs. New shims to compensate for the softer springs has
been designed and ordered. The stage 1-2 shims have arrived and the stage 0-1
are expected shortly.
Dummy masses to replace the actuators during assembly have been designed and
ordered. This will prevent damage to the actuators as the stages are released
from the alignment pins and hung on the springs.
The in-vacuum cables from Accu-Glass have been received and sent along with
several flanges and feedthroughs to Bob Taylor for cleaning.
A telephone conversation was held this week with Ken Smith of ASI to review
the blade/rod tuning procedures. Rich Mittleman is running through the
calculations accounting for softer blades.
From: Ben Abbott <abbott_b@ligo.caltech.edu>
HAM-SAS
The new front panels for the Virgo Coil Drivers have come in, and look
great. Paul assembled the boxes with the new connector, and I'm going to
give them a quick check to be sure that the pinout is correct.
The results of my test of the in-vac Cooner wire's ampacity can be found at http://www.ligo.caltech.edu/~babbott/Cooner_wire_ampacity.pdf
I'll write the results up into a tech note sometime soon.
From: Riccardo
DeSalvo desalvo@ligo.caltech.edu
BSC Clean Air Flow Study
Riccardo went to Flomerics for the kickoff meeting. This project is to study the feasibility of
establishing a clean air laminar flow in the BSC chambers using the optical
bench and an additional donut structure as plenum to generate the shower and a
perforated floor to recover the laminar flow. The study is performed with Flovent, a FEA gas
flow program. The clean (and dry) air
shower is developed in response to the necessity of avoiding in Ad-LIGO
particulate and film mirror contaminations like the one found in Hanford. On top of
preventing contamination, the dry air flow should also keep the transpiration
away from the BSC walls, and possibly shorten the pumpdown time of any access
and thus improve the observatory duty cycle.
John Wilson at Flomerics has responsibility of this project. Riccardo and John Worden are providing the
scientific and technical feedback. Ken Mailand and Dennis Coyne the solid
work necessary to define the mechanical conditions. The first flow simulations, showing the
laminar/turbulent flow inside the BSC chamber and around the SUS may be ready
as soon as early August.
HAM SAS Prototype Advancement
Present: Valerio, Jay, Ben, Dennis, Dave, Chiara, Riccardo
Announcements
- have
decided to have G&M purchase an (G&M to provide written
quote)
- Riccardo going to G&M
saturday for 3 weeks, Valerio already there, can help Riccardo for the
first week. Virginio the
following week for ~10 days. Dave
may go in the week across July/August
- FTIR machine for LIGO ordered to G&M and
ordered by G&M from thermo Nicolet. Will be delivered to G&M
end of July
- The Change Request to cover increased welding
costs and fabrication of a 3m oven for bake-out was discussed by the LIGO
Change Control Board (CCB) and accepted, the corresponding order is out
and will get to G&M soon. Preliminary
construction meeting was held (Chiara, Marcello, Carlo Gianni). Oven
thermal insulation availability issues makes that a precise schedule cannot
be done until next week.
Fabrication issues/status:
all drawings practically up to date including weld preparation drawings, cabling
routing design and pinout completed. Pinout verifird by Ben and Riccardo
on latest drawings.
The base top plate that was mis-machined has been replaced with a new
one. The new machining is done, it is going for cleaning and welding will
follow friday or early next week. The final machining of the base
structure will be done next week after inspection from Riccardo.
The clean room floor is in house and being laid. The clean room will
follow immediately after. End of next
week we will be able to use part of the surface for the dirty assembly, next
week we are still in the small room.
Status of Test Plan for LASTI (Dave)
Clean room arrived in LASTI, and being prepared. Virginio preparing test instruments to be used
at G&M for the dirty status tests.
Simulation & Controls Design (Virginio, Valerio, Yumei, Dave &
Cassey)
Cassey working on FEA model
Valerio advancing model on Dynaflex, now possible to insert asymmetries.
Electronics (Ben/Jay, Virginio)
Coil driver panels made by Ben, Valerio has spoken with Federico Paoletti,
who will provide the additional 2 coil driver units (3 already available, 4
needed). Customization of LVDT boards
lagging, Valerio will go again to talk with Francesconi and speed him up.
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
Double checking the RM design information Norna sent. Reading over the OMC paper Norna sent. Participated
in the Quad PDR #3 on Monday. Supporting Steve Penn and Gregg Harry on their
thermal noise experiment. Checked, redlined and faxed osem drawings for Stuart
at Univ. of Birmingham.
From: Ken Mailand kmailand@ligo.caltech.edu
I'm using the latest information from Ian and working on a lower quad
installation arm shop drawings, and a 'conveyor' version to be used at the
LASTI site. The
existing 5 axis fixture has been disassembled, the stainless hardware
change out is ongoing, other parts are being modified for stability.
Core Optics
From: Bill Kells
kells@ligo.caltech.edu
From: GariLynn Billingsley Billingsley_G@ligo.caltech.edu
From: Helena Armandula ahelena@ligo.caltech.edu
LASTI
Repaired and shipped magnet assemblies.
A carrier and storage box for the LASTI test mass have been designed, I am
in the process of getting a shipping box designed for it.
Advanced LIGO Coatings
First Contact. Optical absorption
measurements, before and after, on a mirror covered with the strippable film
are the same (within the instrument's error).
A report will follow.
CSIRO
Preparing single material layers to measure Young's modulus.
Input Optics
From: David Reitze reitze@phys.ufl.edu
AdL Adaptive telescope (Muzammil Arain)
One phase of experiments regarding adaptive optics for Ad. LIGO had been
completed. A tunable positive lens with a range from infinity to 4 m has been
demonstrated. We have submitted a paper titled "Adaptive beam shaping by
controlled thermal lensing in optical elements" for LSC review. The idea
is to have an adaptive telescope built into input optics for in-situ mode
matching into the arm cavities of the interferometer. Further experiments are
being planned for thermal compensation in Ad. LIGO. Also working on TCS
review.
AdL ISC/CDS interfaces (Volker Quetschke, Guido Mueller, Dave Reitze)
- Alignment
sensing and Control - Guido has developed a Finesse file to analyse ASC
signals for advanced LIGO.
- Volker
and Dave have had discussions with Rich Abbott and Peter Fritschel to
identify IO-CDS interfaces for AdL.
AdL Mode Cleaner (Volker Quetschke, Guido Mueller, Dave Reitze)
- using
Comsol Multi-Physics package to compute mode cleaner mirror resonances for
AdL.
- based
on discussions with PSL about pointing noise and ISC, we are looking
seriously at reducing the finesse of the mode cleaner from 2000 to ~ 400
or so (final value pending PSL pointing data)
AdL Modulation (Stacy Wise, Volker Quetschke, Jeremy Pidgeon (REU
student))
- finalizing
LIGO technical note for MZ noise couplings in Advanced LIGO
- Jeremy
is setting up a AM/PM experiment for sideband cross-product suppression.
AdL Faraday Isolation (Ken Franzen, Luke Williams, Dave Reitze, IAP
group)
- discussions
with the IAP group on redesign of the AdL Faraday rotator housing are
ongoing. A new case has been proposed by Luke and is being studied
by the IAP group for issues relating to magnetic field homogeneity.
- the
LLO high power test lab is performing more isolation measurements on the
AdL FI
Mechanical (Luke Williams)
- Designed
a new breadboard and component mounts for the Mach-Zehnder interferometer
for high power modulation.
- Looked
at position of MMT3 (in a triple suspension) in a stable power recycling
cavity layout. By moving the MMT3 toward the center of HAM1, a
triple will fit in the layout.
- working
on a design for spatially segregated wavefront sensors to eliminate cross
talk.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
An attempt to implement a 1 Hz low-pass filter with a sample rate of 200 kHz
using the FPGA was made. Unfortunately the large number of taps required to implement this filter was beyond the
memory capacity of the PC host. The filter was realised by paring back
the sampling rate to 44.1 kHz. The measured transfer function of the
filter was consistent with the design and it's magnitude was flat down to 0.18
Hz. Glitches in the DAC output are a concern however and it is not
obvious to me how to remove these just yet.
Auxiliary Optics
From: Michael Smith <smith@ligo.caltech.edu>
LAYOUT
Non-folded IFO
A complete list of optical component data, organized by HAM and BSC tables
was prepared and given to Dennis for updating the T010076-01 Optical Layout for
Advanced LIGO document. The component data includes their locations in gobal
coordinates, their surface normal vectors and the main optical beam vectors.
An updated Vertex optical layout, D060024 was checked in to the PDM Works
vault.
OPTLEV
All optical lever beams in the non-folded IFO vertex were modeled in Zemax
and SW. Luke and Chris will mount optical lever transmitters and receivers on
appropriate support structures.
STRAY LIGHT CONTROL
Concepts for errant beam baffles, IO baffle, and Input Modecleaner baffle
were modeled in Zemax and SW. Concepts
for the ITM Arm cavity baffle "surfboard" with holes for optical
lever beams were modeled in Zemax. Cavity
beam dumps were modeled in Zemax. Ken Mailand is working on the SW model.
PO Telescope
An ACAD conceptual design for the PO Telescope/Hartmann Telescope is being
modeled in SW by Ken Mailand. This telescope serves a dual function as a
Hartmann probe for the ITMx and ITMx PO telescope. A Hartmann Telescope is
needed to probe the ITMy. The BS PO telescope was eliminated by making the BS
PO mirror the primary mirror of a beam reducing telescope.
I will visit Tydex, J. S. Co in St.
Petersburg, Russia
on Aug 4; they are a potential source for large, off-axis parabolic mirrors
From: Chris Echols <cechols@ligo.caltech.edu>
Building outlines inserted into vacuum equipment layout (D060165).
Penultimate end stations moved to 56.730m from origin per Mike Smith's
request. Buildings overlap but okayed by Mike. Replaced "BSC
Support Rod" in vault with D060141_BSC_Support_Rod_ICD. Replaced
"BSC Chamber and Support Rods" with D060142_BSC_Overall_Assembly_ICD
in D060100 and 20007970 bsc. Acquired LIGO numbers for ASI and Hytec
drawings for renaming per LIGO standards (renaming not started yet).
Inserted new spools into vacuum equipment layout (D060165) showing new optical
viewport locations between HAM3 and BSC2, and HAM4 and BSC 2. Modelled
spools A-1, A-7 and B-9 per PSI fabrication drawings and inserted into vacuum
equipment layout assembly.
Controls, Data systems
From: Jay Heefner jay@ligo.caltech.edu
- A
draft of a technical note detailing the measurement result for the PCIX
ADC modules has been completed. The note should be available for
distribution next week. Additional, more detailed, tests are planned for
next week and beyond. Preliminary results show that the input referred
noise of the module is ~10uV/rtHz on a 40Vp-p input and a sample rate of
16384Hz. In comparision, the Pentek 6102 has an input noise of ~15uV/rtHz
on a 10Vp-p input.
- Anti-Alias,
Anti-Image, and Timing Interface boards for HAM SAS, LASTI ISI, 40M DC
detection and the LASTI Squeezing Experiment are being fabricated and
tested.
Other Laboratory R&D
From: Riccardo
DeSalvo desalvo@ligo.caltech.edu
John Miller
This week I began my appointment as a long-term visitor (from the University of Glasgow) with LIGO. I spent last Summer
working on non-Gaussian beams at Caltech and have now returned on a more
permanent basis to continue this work.
Antonella Iuorio and Livia Cerullo
just arrived from University of Sannio (Benevento)
in the framework of the summer exchange program with Virgo/EGO/VESF. Livia will join John working on the mesa beam
interferometer. Antonella joins the TNI
experiment (E. Black). Two more exchange
students, Riccardo Ciolfi (from University
of Roma I) and Alberto Stochino (from University of Pisa, already a SURFist at Caltech 2
years ago) will arrive in the next weeks to work on the 40 meter and on test
mass studies respectively.
Yumei Huang
I simulated in computer and calculated by hand the stress of the Flex Joint
of the invert pendulum as well as generated a diameter versus nominal load
curve. I'm writing the report about the Flex Joint study.
Marie Giron
This past week I have been getting more acquainted with the glassy metal
spring (LM001). We took many test runs by adding balls to the mass
hanging from the springs to make sure the data looked clean (before
fitting). We found some big jumps in the graphs, figured out what was
causing them (things hitting wires), and have taken data since then. I am
now fitting the displacement data.
Michael Floyd
This week I have run tests at the synchotron with Marie, filtering the data
with both electronic and digital filters, to test the new DAQ hardware, and a
newer version of labview. I have also been fitting the graphs to find the
residuals and the noise of the system to determine whether or not the noise of
this DAQ is more or less than it claims, and whether or not it has more or less
noise than the DAQ Marie is using.
For additional information about this report, contact Stan Whitcomb or Phil Lindquist