Weekly Report for
Week Ending June 22, 2006
The LIGO
Executive Committee Agenda for Monday, June 26,
2006 will be:
(Meeting time: 10:30 am Pacific Time)
1. Announcements
2. Comments
on Weekly Report
3. LSC
Issues (Saulson)
4. LIGO
Lab Operations
- Administration
(Lindquist)
- Sites
(Raab, Zucker, Shoemaker)
- Commissioning
(Fritschel), Detector (Coyne)
- Campus
Research Facilities
- 40
Meter (Weinstein)
- TNI
( Libbrecht)
- LASTI (Shoemaker)
- Data
Analysis and Computing (Lazzarini)
5. R&D
and Advanced LIGO (Shoemaker)
6. CHANGE CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION AS
NEEDED
Special Items:
- NSF
OIG Labor Allocation Audit
- Annual Report for NSF
Special Announcements:
Weekly Report Highlights
All three members of the Directorate attended the GWIC meeting at the University of Maryland,
and then the beginning of the LISA meeting at Goddard Space
Flight Center.
GWIC adopted Jay's suggestion that it
should construct (and maintain) a report on the various post-Advanced
gravitational wave detection projects that are being studied/proposed. Jim Hough was appointed to lead this task. During a discussion of collaborative data
analysis, Stan asked about the progress on joint bar-interferometer analysis.
The ensuing discussion led to a revival of interest in this project; several
of the IGEC leaders promised to work on a White Paper to lay out a plan to do
this, and are thinking of ways to devote substantial labor as well.
On Fri - Sat 23 - 24 June, a face-to-face meeting of the LIGO/Virgo Joint
Working Group is being held at Orsay.
LIGO Laboratory Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
SITE TELECONFERENCE (Lindquist)
- A
site teleconference was held Thursday, June 22, 2006. Issues discussed are address below.
- There
are currently no open action items.
The list of assigned actions updated through December 01, 2005 (the
last update) will be found Here.
PROPERTY MANAGEMENT (Luna)
>
- Provided
assistance to the Detector Group (H. Armandula)
with packing and shipping of two
coated samples from CSIRO to Stanford (R. Route), Account Number LIGO.OPT
- 5.4 - NSFLIGO.FY02ON.
- Provided
assistance to the Detector Group (R. DeSalvo)
with shipping and the preparation of a Commercial Invoice for US Customs
clearance of 400 Magnets to GALLI & MORELLI in Italy. Account Number
LIGO.HSAS-1-NSFLIGO.FY02CA.
- Created
a new Equipment database for Rich Riesen @ LLO.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
- No
report.
- [We
met with the FileHold Systems Inc. folks to
address the issue of work performed without the proper paperwork. After lengthy and intense negotiations
we have agreed to issue a change order that will increase the contract
value from $53K to $66K and update the statement of work to reflect effort
needed to assure the August rollout. –pel]
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- Continued
to assist in the process of conversion of current data to the new
database.
- Scanning
- Progress continues on contract closeout files.
- Activity:
|
Week Ending
06/22/2006
|
In
|
Out
|
|
Packages
|
42
|
11
|
|
Faxes
|
21
|
19
|
FINANCIAL SYSTEMS (Cronin, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Working
on completed change order #177 to Triad for approval routing. Change order #176 is still out for
approval.
- Completed
change order #5 to Great Impressions Janitorial and submitted it to the
vendor.
- The
MIT subcontract was requested by PWC auditors to check on the sub
recipient monitoring. I'll be submitting the folder for audit.
- Responded
to the request from the PWC auditors pertaining to FY2006 expenditures on
LIGO subcontracts issued to non-profit entities.
- Requested
for the closed subcontract issued to High Precision Devices to be pulled
from storage. The file was
submitted in response to an audit request.
- Followed
up with vendors on outstanding change order acknowledgements. Received a few, however, others still
need to be submitted.
- Researched
the taxability status of one-time LIGO orders that were placed in
2002. All 26 Purchase Orders were
coded and paid appropriately according to the tax status of each
order. This request was made as a
result of the current California
sales tax audit.
>From: Florence Kaufman <fkaufman>
- Prepared
2 Intra Award Transfer Forms to correct the allocation of payment for
Invoice # 11 to TRIAD.
- Notified
Caltech's Accounts Payable Department than an incorrect expenditure type
had been used on an Electronic Funds Transfer payment to DEMCO which
resulted in an unwarranted charge for Indirect Cost of $7,775. I have been informed that a correction
will be made.
- Questioned
whether expenditure type indicated on a PO for repair work at Livingston was appropriate. Correction is to be made, resulting in
an Indirect Cost savings of $2,695.
- Caltech's
Property Services Department is in the process of making corrections in
expenditure type from Equipment to Supplies for various charges to LIGO
fabrication accounts. The change is
required because fabrication accounts should not have any expenditure with
Equipment designations. The changes
are for acquisitions made in prior years because in recent years LIGO has
complied with the requirement to not have Equipment classifications in
fabrication accounts, however in previous years that was not the case.
- Prepared
a report for Jay's discretionary account.
- Prepared
a report for Riccardo De Salvo of the balance
remaining in his accounts, with a projection of known expenditures for the
rest of the fiscal year.
- Completed
and sent out report for the Visitor Award as of the end of May.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT
(Jasnow, Salone)
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- Construction
of the Livingston Science Education Center (SEC) remains on schedule for
the advanced completion date at the end of August.
- The
Final Design Review for the LLO SEC kinetic facade is scheduled for
Thursday, June 22. Upon successful
completion of this review, an RFQ will be prepared for the fabrication and
installation of this facade. The
facade must be completed prior to the opening ceremony of the SEC now
scheduled for November 13.
- The
LIGO staff at Caltech has been notified of an impending audit on payroll
distribution confirmation by the NSF Office of the Inspector General. This is an Institute-wide audit centered
only on assuring that people are correctly charging for the work they
perform.
PROPOSALS and REPORTS (Lindquist)
As mentioned last month, I need to assemble an Annual Report for the NSF for
LIGO Operations. I had requested inputs
by Friday, June 23. So far I have
received some material but much has yet to be submitted.
A monthly report for Operations for the end of May has been provided to the
NSF.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
- There
are no open change requests.
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- A
Staffing Committee meeting was held on June 12. The minutes and action items have been
posted on the SC web page.
- Most
of the REU/SURF summer students have arrived. I am working on the
paperwork for the remaining students that are coming from, or going to Italy.
- Prepared
numerous appointment and reappointment memos for various Visitors and Post
Docs.
- I
am in the process of finalizing my Kronos duties
and submitting for payroll.
- The next Staffing Committee meeting is scheduled
for July 17.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
Nothing significant to report this week.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of S5 Activities at LIGO Hanford Observatory (compiled by M. Landry)
Seismic noise in the 1-3Hz band was upconverting
and impacting IFO ranges from 1am to sometime after 7am; this has been traced
to excess spring runoff at the McNary Dam.
Some S5 highlights from the elog are bulleted
below:
- driving
test mass angle
d.'s o.f. produces
about twice as much upconversion as the same
drive level in straight POS excitations
- no
charging noise from test masses brushing on stops is observed in a
study of 16 large seismic events
- seismic
transient study: PSLmon was employed to obtain
50, 95 and 99 percentile seismic
levels in 1Hz bands of all stations, from 1-30Hz
- some
DMT dropouts
are due to cpu loading by PlaneMon...
the datapusher priority was raised to fix the
problem
- upconversion is argued to have multiple mechanisms,
and an onset level independent of frequency, see the full report here...
PEPI mitigation at 1.2Hz is desirable
- PEPI
hardware 0.1Hz poles (to prevent excess shaking of the ETMs)
were added. Next: code mods to handle more filters in end stations
- RDS
generation stuck when the DiskCache API went
offline
- multiple
hardware injection streams were started, apparently without landing excess
injections on the machine
- the
cosmic ray process is now monitored
daily by scimons
- Tuesday
summaries: maintenance,
and range/duty
cycle
- in
concert with L1 REFL work, we took about 2h and 45m to make photon
calibrator studies on both IFOs
- IFO
maintenance for LHO and LLO is summarized in the Initial
LIGO WIKI (current June LHO usage: 12h 17m of 25h for H1, 4h 13m of
25h for H2)
4K IFO
- ISS/FSS
glitching continues to be responsible for locklosses and glitchy
performance on the 4k, see for example here.
The impact can be significant,
e.g. 3h of ten during low seismic activity. The PSL was studied on
maintenance day, and measurements
such as the PMC open loop transfer function were obtained, but so far the
cause of the glitches is not yet understood
- when
making excitations for upconversion and IFO
maintenance studies, we have to workaround AWG by temporarily
eliminating photon cal excitations, and reapplying later
- as the mean-time-to-lock had grown unacceptably long on
H1, lock acquistion parameters were remeasured, so that now we are relocking in
minutes, a welcome improvement. The unity gain of the DARM loop was
later adjusted
- upconversion was not observed when a DC butterfly
injection was applied to ETMX
DAQ
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
L1 in S5 (Yakushin)
On Saturday, June 17, there was some confusion due to the outdated
instructions scattered in various readme files and
two obsolete scripts, "Center WFS4" and rbsautolock,
were launched by operators. That resulted in several hours of lock loss. Also
there was a suspicion that REFL beam was not optimally centered after the
interferometer got back online. It was decided that on Wednesday, June 21,
night Ken Franzen, during his owl shift and during
the time when LHO would be down for calibration measurements, would bring the
L1 down to realign REFL beam. To prevent further confusion caused by various
old readme files, it was decided to collect all the
current information into a single wiki and get rid of
the old readme files; this work is still under way.
To prevent the old rbsautolock script from been
accidentally launched, Rana renamed it and moved to
backup directory.
#MZ We took some lumps for trying to gently and "adiabatically" migrate our documentation into the new wiki
format. As a result of this incident, we are cutting the cord; from this point
forth the old docs system is off limits. Any complaints will be interpreted as
proposed WIKI contributions.
On Monday, June 19, evening there was a lightning that brought a few systems
down: LVEA pumps, MOPA, PSL chiller, etc. It took 3 hours to get back into
science mode.
On Tuesday, June 20, during the maintenance period the new outreach building
was connected to our power grid and we braced for possible power outage by
turning off HEPI, suspension, high voltage supplies for suspensions, HEPI
pumps. Fortunately, there was no power outage.
On Wednesday night and Thursday morning, Ken and Gary worked on RBS to
correct the problem caused by obsolete scripts running on Saturday. They ran
into problems with WFS4 and could not lock the interferometer during the owl
shift. On Thursday afternoon, it was discovered by Rupal,
Dan and Mike that the problem is probably due to a bad cable connection. We are
back in science mode now.
Despite of all the above problems, we still had 70% duty cycle during the
week with the inspiral range close to 14 Mpc.
L1 CDS (Bogue)
- Worked
with John Z. on building a replacement server for delaronde. This is strictly a hardware
upgrade. We ran into problems with
the skge ethernet
cards and the server swap had to be delayed.
- Worked
with John Z. on cleaning up the DMT files that were filling up the disk
space on the web server.
- After
having the root partition fill up a couple of times over on london,
the server crashed and there is data corruption on the disk. I will be working to get a replacement
server built and swapped in as soon as I can.
- Changed
london's home page. - Compiled a
list of filter module channels that are not being recorded in our
frame. These will be discussed at
our next cross-site channel meeting.
Humongous Educational Kinetic Art Installation (Romie)
Visited and qualified three machine shops this week in preparation for an
RFQ for the Kinetic Art fabrication and installation. The Final Design Review
is tomorrow. I've got a full size set of drawings and am reviewing their
drawings, presentation and BOM.
LLO Outreach (Thacker)
- monitored/presented
at SLU math/science partnership
teacher professional development
- outreach
staff training on interference activities
- developed
giant slinky "snack"
- developing
visitor scrapbook - completed most recent visitor program for the
scrapbook
- developed
written material correlating current exhibits with LIGO science themes
- mentored
RET teachers
- worked
on LIGOSEC Opening Event materials (invitation list; event program,
commemorative)
LIGO computing and network security (Roddy)
- working
on final nessus scan reports
- Continuing
to work the implementation details for the Charter network connection.
- Set
up two windows servers. Working on
testing AD, workstations, user profiles, automated software installs,
etc. Long list of things to test
before I consider implementing this on GC.
First "victims" will likely be the outreach computers
since they are more or less "disposable" and do not have any
important files/data on them.
Testing with a laptop also for the "roaming user" scenario.
- Working
some Mathematica install problems. The install scripts do not seem to
install the software completely.
- Set
up a windows workstation.
- Reorganizing
the computer lab again... seems to be a continual process.
General Computing and LDAS Admin (Giardina)
- NIS+ client install on chestnut, qscan
files backed up and rsync'ed, /home now automounts from NIS+
server
- other
usual user requests and support
- ejected
tapes for shipment to CIT, imported and labeled new
- assisted
Ben with h(t) C01 to C02 file rename at LLO
- shelved
82 tapes, imported and labeled new
- racking
'new' equipment received from CIT
- need
to replace a disk in node208, hoping to have kickstart
server up and running to test on node208
- publishing,
RLS, LDR, MySQL, gridftp
restart this morning due to rls and publishing
failures overnight
Data Analysis (Yakushin)
- Wrote
readCalibrationASCII function to be able to read
calibration in an ASCII format into waveburst
(previously I used calibration frames; however, the calibration group no
longer supports the old calibration frame format while the new one has not
been released so far).
- Reruning S5 incoherent waveburst
analysis on DARM_ERR using version 2 calibration.
- Reruning S5 incoherent waveburst
analysis on h(t) obtained with version 2
calibration.
- While
working on reruning waveburst
on h(t) at CIT, noticed some missing frames for
H2. Found them at LHO and sent Stuart and Xavi a
list of missing frames.
- Working
with my SURF student, Lisa, to improve the online waveburst
infrastructure. In particular, the current version does not handle
gracefully the absence of expected data. Lisa is writing a routine that
would check for data availability and reschedule jobs that cannot run at
the moment.
- Working on online coherent waveburst
infrastructure which is expected to be launched within the next couple
weeks. In particular, discussing with Adam Mercer how to integrate his
coherent event display into the pipeline..
Controls
and Data Systems (Bork)
No report.
40-Meter Interferometer (Weinstein)
IFO Commissioning
- Rana is back to work locking the IFO in the full
DRFPMI configuration, while Rob is away on vacation in Sweden. Jenne is
learning the ropes and the scripts.
- Monica
is using the WFS diagonalization code developed
by Rana and Dan, and is preparing to diagonalize the MC WFS system.
- Royal
has been working on testing Mike Smith's oplev
telescope, but she's having difficulty establishing a good spot on the PD
when the beam gets through the thing.
- Royal
is developing a scheme to calibrate our test mass oplevs
by wiggling the mirrors when the arm cavity is locked, and relating the
transmitted power to the mirror angle.
- Royal
is exploring oplev configurations which suppress
or cancel laser beam (mount) angle jitter.
- David,
working with Osamu, is learning the noise budget program. He is adding the
model of the DRFPMI optical response to replace the simple
Initial-LIGO-like cavity pole model. He ran on old data; the program ran
through, and he's looking at results now.
IFO Modeling
- Kentaro is working with Osamu and Peter Fritchel on new length sensing schemes for AdLIGO, and maybe 40m. The double-demod
offset needs to be understood better. He's checking the dependence on the
RF sideband imbalance.
- Valera
is visiting from LLO, and is working on AdLIGO
angular controls, optimizing the sensing matrix. He's also learning the
40m controls with Rana.
- Monica
continues to develop the AdVIRGO e2e package,
starting with just one arm. It locks, but only with radiation pressure
turned off.
- Osamu
in continuing to work on modeling the alignment instability in AdLIGO, with e2e.
DC Detection and Vacuum Squeezing Development
- Sam
and Darcy are trying to get the DC readout beamline
fully checked out, so that they can disassemble for clean/bake in less
than 2 weeks. They dither-locked the OMC, measured the FSR and finesse,
and scanned for PZT resonances. The finesse was around 220-230, low
compared to the design of ~300. They will assemble a careful procedure for
disassembly, re-assembly, alignment and testing on the clean bench, and
then installation, alignment and testing in the vacuum chamber.
- Ben
checked out the DC photodiodes. They are now functioning fine. The correct
regulators are in place, and the diodes are healthy. He still want to bolster the protection of the photodiode
elements, but he hasn’t implemented anything yet.
- Sam
and Rana are getting the DC PDs
mounted and testing their response and noise, using the DC PD satellite
amplifier built by Ben.
- Rob
and Sam tested the tip-tilt PZT that was wired incorrectly; it shows no
sign of being damaged. Rich, in consultation with Piezo-Jena
engineers, established the correct wiring. Rob measured its dynamic range.
- Sam
is driving the tip-tilt PZT mirror with our old existing board. It seems
to have a lot of excess noise at high frequencies. Under investigation. He
and Darcy plan to implement dither locking of two angular degrees of
freedom (along with the OMC length lock), soon. They will also test the
2nd tip-tilt PZT mirror to make sure it works correctly.
- Ben
reports that Alex is testing a computer with PCIE bus, at 32KHz, for us and LASTI. The order is in for components
for interface boards, expected in on July 29.
- Ben's
QPD Whitening board PCB layout is finished except for a check to make sure
all of the nets are complete. The board should go out in the next couple
of days.
- Rana and Sam are determining the noise and modulation
requirements for the tip-tilt PZT and OMC PZT drivers.
- Go
reports that Evgueny is testing a new PPKTP
crystal for the OPO. Go is preparing for this new OPO, including the mode
matching and is ordering new lenses.
PSL
- Steve
reports that the MOPA head temperature has been stable for the last 2
weeks. He once again removed around 500 cc of water from the chiller... a
great mystery.
- Steve
covered the top and two sides of the Mach Zehnder
with a Plexiglas box. The long-term drifting of the MZ servo has not
changed much since then. Rana suggests building
the other two sides.
Electronics, Controls, Computers
- Bob
plans on installing new RF distribution panels at the RF rack and the LSC
rack, in the near future. It will take a couple of days and be somewhat
disruptive.
- Jenne is building a mount for an AM laser to be used
for PD testing.
- Osamu
and David found a strange electronics noise on the PD2 photo detector;
under investigation.
Lab Infrastructure
- Steve
and Bob replaced the fore pump for TP2, and a new convectron
gauge controller installed. At that point, all the Vacuum EPICS channels
stopped appearing in EPICS and dataviewer. A DAQ
reboot seems to have fixed the problem.
- The presently-installed RGA filament has failed
(the electron multiplier failed long ago). Steve gave a spare RGA head to
Bob for baking. Bob will modify an oven head mount and bake it next week.
Thermal Noise Interferometer (Black)
This week we concentrated on training the new
SURF students. They learned how to lock a laser to a fixed-length Fabry-Perot cavity and to measure the open-loop transfer
function and noise in the system. This
went very well. They even learned how to align a laser to a cavity in
preparation for locking, and the whole process took less than a week.
Congratulations to all concerned!
Michael is now setting up his system to
observe thermal self locking. Greg has
come up with a simple dynamical model, and the plan is for Michael to test
Greg's predictions about the frequency response of a self-locked system. Michael
will first mode match and align his laser to his
cavity and reproduce Royal's results from last
summer. After that, he will start checking Greg's dynamical model
experimentally.
Matt and Cacey are
moving up from the training system to the main interferometer, learning how to
lock it, calibrate it, and take data. As
soon as we have a sample mirror with the new ring-damper design, they will
install it in the interferometer and evaluate its performance.
Akira is working on a drawing for the ring
dampers, based on a design Riccardo, Dennis Coyne and
I came up with.
All three SURF students are also reading
background papers, and they will start to give talks on them next week.
LASTI (Mittleman)
ISI Assembly
Brian O'rielly, Ken, Myron, Rich
We have done a resonant mode test of the horizontal version of the GS13 can.
We installed some dummy mass in the can to imitate the GS13 and then using endevco accelerometers measured the power spectra of the
motion of the can. There appear to be a
couple of resonances around 75Hz which could be a problem. We are going to
think about making the can stiffer, it should not be too hard. There are a number of entries on this and the
fit test in the SEI log some will be copied onto the Lasti
ilog soon.
Jon, Myron, Ken, Rich
Jon has finished measuring the first long blade spring on the spring
tester. This first measurement appears
to agree with the measurements of the short springs in that it is coming out
about 15 percent less then the number provided by ASI. There are entries on both the SEI and Lasti ilogs.
Quad-Pendulum Controls Prototype
Brett, Myron, Rich
We vented Lasti this week so that we could
investigate issue, make fixes and install new equipment. One of the chains on the Quad has some
strange transfer functions in the vertical and roll directions, after a visual
inspection we have not yet found anything wrong. One OSEM has been operating on the edge of
its range and also has a maximum signal about 50% of nominal so it has been
replace. We are planning to install the
eddy current damper on the chain which is not displaying funny resonances. There are a number of entries on the Lasti ilog about this issue.
Data Analysis (Anderson
for Lazzarini)
Here is the weekly report for Albert since he is on travel. Please put the E2E section under Advanced
LIGO and create a hyperlink to it.
Data Analysis Activities (Anderson)
(Vuk Mandic)
- I
am working on the analysis of the S4 H1L1 data at high frequency (~900
Hz). The goal is to use it as a cross-check of the ALLEGRO-L1 analysis.
- I
am preparing a new version of the S4 all-sky stochastic paper.
- With
a SURF student, M. Lukic, we started looking at
the possibility of using time-shifts to estimate instrumental correlations
for the H1H2 pair.
(Duncan Brown)
- Worked
with Tapir numerical relativity group to understand how to use their
binary black hole evolution code.
- Worked
with SURF student Alexei Zaliznyak on his
template placement project.
- Worked
on LIGO EMRI project: set up outline for Diego's implementation of the
physical template family and started implementing code necessary to evolve
basis vectors of spinning binaries.
- Worked
with Lisa to get the ringdown pipeline working
for S4 data.
- Continued
with inspiral BNS review work.
- Investigated
64 bit compatibility of LSC analysis software on the CIT cluster and
created new RPMs for lscsoft
repository. Created an x86_64 binary distribution of the LIGO ringdown analysis code which the Condor team will
incorporate into their test suite.
- Performed
some maintenance on the segment database for GEO segments and helped Chris
and Martin finalize the specification for inserting GEO science mode
information into the database.
(Gregory Mendell)
The SURF students I am working with are now up-to-speed on their projects,
so I am back to work on the S4 PowerFlux, StackSlide, and Hough paper. I am also writing a technical
report with Karl Wette from ANU on our work on
parameter estimation and its relationship to the PowerFlux
method. All of this will be reported on at the August CW F2F and LSC meetings.
(Igor Yakushin)
- Wrote
readCalibrationASCII function to be able to read
calibration in an ASCII format into waveburst
(previously I used calibration frames; however, the calibration group no
longer supports the old calibration frame format while the new one has not
been released so far).
- Reruning S5 incoherent waveburst
analysis on DARM_ERR using version 2 calibration.
- Reruning S5 incoherent waveburst
analysis on h(t) obtained with version 2
calibration.
- While
working on reruning waveburst
on h(t) at CIT, noticed some missing frames for
H2. Found them at LHO and sent Stuart and Xavi a
list of missing frames.
- Working
with my SURF student, Lisa, to improve the online waveburst
infrastructure. In particular, the current version does not handle
gracefully the absence of expected data. Lisa is writing a routine that
would check for data availability and reschedule jobs that cannot run at
the moment.
- Working
on online coherent waveburst infrastructure
which is expected to be launched within the next couple weeks. In
particular, discussing with Adam Mercer how to integrate his coherent
event display into the pipeline.
(Patrick Sutton)
These week I've been working with Stephen Poprocki (SURF) to compile and run our Xpipeline
coherent analysis package on the CIT cluster.
I've generalized the package to handle several of the different maximum
likelihood formulations proposed by various LSC groups, such as the constraint
likelihood. I've also optimized the code
for scanning large amounts of data in search mode. We're now running cluster jobs scanning the
LIGO-Virgo project 1b simulated data set.
Finally, I set up a first draft of the XPipeline
web home page, where we will be posting documentation and results.
(Peter Shawhan)
- Reviewed
pulsar analyses.
- Continued
to work on defining GEO science segments.
- Worked
with SURF student Chris Pointon.
- With
Erik Katsavounidis, wrote summaries of Burst
Group activities for LIGO annual report and data analysis white paper.
Simulation and Modeling (Yamamoto)
Se Advanced LIGO Modeling
and Simulation.
LDAS Software Systems (Blackburn)
LDAS
To get a different view of LDAS problems with Tcl/Tk
8.4, a threaded version was installed for a couple of days. It help to reveal
additional places were global variables were being used in callbacks. Tcl/Tk has been reverted to the non-threaded version.
The latest version of valgrind (3.2.0) has been
installed on ldas-dev. This tool is being used to
help analyze places to improve the code. It helps to identify some errors such
as use of uninitialized memory an
memory leaks. It only works for *86 systems running Linux.
System testing of LDAS was done using version 1.8.214. Failures continue to
be seen in the loop testing associated with the new version of TCL/TK. Code
rework is underway to correct this.
TCLGLOBUS
TCLGlobus 1.2.0 has been fully tested agains Globus 4.0.x. However an error was discovered with the
1.2.0 release of TclGlobus against the Globus 3.2.x release: The unit test for FTP control failed
when linking against globus toolkit 3.2.x. The fix
has been identified and implemented.
Inquired of the VDT developers during thier weekly
office hours what the schedule for inclusion of TCLGlobus
was likely to be. They have plans to include TCLGlobus
in the VDT 1.3.12 release due out in mid to late summer. This is same release
of VDT that will be used int he 0.6.0 release of OSG.
Began drafting the sections of the ITR annual report to
the NSF regarding TCLGlobus at the request of Erik Katsavounidis. This is due July 1st.
GRID COMPUTING
The set of packages needed to run the LIGO Workflow Planner from a
workstation has been identified. None of them require root. The means by which to distribute these
packages is yet to be decided.
Met via Telecom with Pegasus/ISI engineers and Kent Blackburn regarding
previous request for functionality to update vds-get-sites
utility to produce accurate tables tc.data
and sites.xml.
ISI engineers are exploring this request.
Obtained possible solution for supporting a native unix command entry in the VDS transformation catalog
(tc.data) from the ISI engineers. Will
test this possible solution next week.
Replaced the host certificate which had expired on
LIGO-CIT-ITB CE with the assistance of Phil Ehrens.
Working with Duncan Brown, determined that Duncan had inadvertently changed out the lscsoft library on kitalpha
necessary to link lal and lalapps
for hierarchical inspiral pipe analysis. To prevent
future resource conflicts, I am moving hipe
development to ldas-pcdev2 which is not maintained by Duncan.
Working with Michael Samidi and Kent Blackburn,
developed a model of deployment for the LIGO work flow planner that employs
ldas-pcdev2 as the stage-out host to meet the requirement for host-certificate
on the systems where staging of i/o is required.
Met with Shourov Chaatterji
and Kent Blackburn , to examine the progress made in
the last month to support the MatLab R13 based Q
pipeline burst analysis on the OSG. Determined that the X
pipeline under development by the Burst group is the appropriate candidate for
an OSG based tool. The X pipeline is new, under development and not yet
in a stage of maturity to use as a basis for an OSG port.
Testing of the LIGO work flow planner uncovered numerous bugs, each of which
has been added to the PR database.
Testing of the LIGO work flow planner with the inspiral
pipe analysis on Nebraska,
PSU and UWMilwaukee has been sucessful
this week. Testing on CIT_CMS_T2 and Purdue-ITaP has
resulted in failures with aborts. The failures on CIT_CMS_T2 are the result of misconfiguration of the CE. The Purdue-ITaP
failure mode is under investigation.
Laboratory Computing (Anderson)
LDAS System Administration (Anderson)
Caltech
(Dan Kozak)
- Normal
ingesting stuff.
- Gave
LLO a list of tapes for shelf storage.
- 3510
parts replacement (2 disks and a controller at CIT). All lights are green now!
- Fixed
stuck staging a number of times.
- Fixed
incorrect grid-mapfile entry for ldas-cit's LDRdataFindServer
- Worked
on characterizing and developing a workaround for SAM's
stagerd memory leak.
(Phil Ehrens)
- Added
SURF students to the GRID resource access files and helped them with
simple account related issues.
- Configured
new desktop machine m8 which is located on the 3rd floor of Bridge.
- Added
GRID sandbox capacity to m28.
- Created
GRID user addition script and used it to add five users.
- Detected
and corrected issuance of bad UID to Sanjit Mitra.
- Detected
and reported cascading failure of user home directory services. The log_mon.tcl script detected the first home directory
mount failure within seconds of it's occurrence.
- Wrote
do-on-all-nodes.tcl script for running ssh and scp
commands across the cluster using the /etc/nodes file. Output from the
script can be captured and used to track configuration changes without
additional reporting by hand.
(Stuart Anderson)
- Worked
on fixing the SAM-QFS crash after upgrading at CIT.
- Worked
on major water leak in the LDAS-CIT computer room.
- Upgraded
Condor at LDAS-CIT to version 6.7.20 to pick up a number of LIGO specific
bug fixes.
- Helped
profile an I/O intensive cluster job that needs tuning.
- Setup
8 cluster nodes for a successful test of the Caltech Numerical Relativity
code by Duncan Brown.
- Worked
with Erik to upgrade the kernel on the cluster nodes.
(Erik Espinoza)
- Assisted
Dwayne with NIS+
Configuration.
- Sent
FC4 Desktop configuration info to GC Admins.
- Rebuilt
Frog from scratch for testing.
- Tested
"ring" code for Duncan,
for use by Condor devs.
- Assisted
Ed Maros on WiFi for
laptop (ndiswrapper).
- Configured
http authentication on ldas-pcdev1.
- Worked
with Shourov for standardized ACL for
ldas-pcdev1/ldas-jobs.
- Investigating
MCE issues w/ Ken (Supermicro) & Sean (ASA)
-
Tested CPU re-greasing on node325 and node327 (was
node68). Conclusion, this did not
resolve the problem.
-
Currently testing 1:1 (slot for slot) ram swap between
nodes (node324:node325 & node326:node327)
- Worked
with Stuart on Condor/Kernel upgrade of cluster.
-
Upgraded fedora-ligo updates repo to add kernel 2.6.16-1.2115_FC4smp
-
ALL NODES: Upgraded kernel to 2.6.16-1.2115_FC4smp,
Removed legacy /etc/ld.so.conf.d/ldas.conf, executed ldconfig, rebooted
-
Moved PostgreSQL from /var/pgsql to /usr1/pgsql on ldas-grid
-
Re-enabled Quill on ldas-grid
-
Modified kickstart to match
new node configuration
-
Saturday June 17, 2006 - node50, node159, node255
-
Sunday June 18, 2006 - node325 twice
-
Monday June 19, 2006 - All nodes (Condor/Kernel
Upgrade), moved node68 to node327
-
Tuesday June 20, 2006 - node325
-
Wednesday June 21, 2006 - node95
MIT
(Keith Bayer)
- Moved
several cluster nodes over to different circuits in attempt to prevent the
power strips from tripping their internal fuses.
Livingston
(Dwayne Giardina)
- Ejected
tapes for shipment to CIT, imported and labeled
new.
- Assisted
Ben with h(t) C01 to C02 file rename at LLO.
- Shelved
82 tapes, imported and labeled new.
- Racking
'new' equipment received from CIT.
- Need
to replace a disk in node208, hoping to have kickstart
server up and running to test on node208.
- Publishing,
RLS, LDR, MySQL, gridftp
restart this morning due to rls and publishing
failures overnight.
Hanford
(Greg Mendell)
- I
am working on plans to purchase tapes for archiving the rest of S5 data,
and continuing to work on SFT generation.
(Ben Johnson)
- Kickstarted nodes 1-18, except node4 which has power
supply issues. This resulted in
loss of important user data on nodes 10 and 11. It otherwise went well.
- Ordered
8-port gigabit switch for the LDAS <-> GC connection
(ldas-grid/ldas-pcdev1/ldas-jobs, etc.). This will replace the old 16-port
fast ethernet hub. The hub will be kept as a
backup.
- About
to finish up work on a "--show-times" option to LSCdataFind, and corresponding support in the server.
- The
IPFilter setup is ready to test on ldas.mit.edu.
I even have a SMF .xml file to put in the necessary NFS-specific rules
after nfs/server has been started.
- The diskcacheAPI-based LDRdataFindServer is now running at LHO with no major
problems.
General Computing (Wallace)
MIT
(Keith)
- Dealing
with various urop issues
- Ordering
laptop for grad student
- Investigating
OpenVZ linux
virtualization utility
Livingston
(Dwayne)
- NIS+ client install on chestnut, qscan
files backed up and rsync'ed, /home now automounts from NIS+
server
- other
usual user requests and support
(Shannon)
- Working
on final nessus scan reports
- Continuing
to work the implementation details for the Charter network connection.
- Set
up two windows servers. Working on
testing AD, workstations, user profiles, automated software installs,
etc. Long list of things to test
before I consider implementing this on GC.
First "victims" will likely be the outreach computers
since they are more or less "disposable" and do not have any
important files/data on them.
Testing with a laptop also for the "roaming user"
scenario.
- Working
some Mathematica install problems. The install scripts do not seem to
install the software completely.
- Set
up a windows workstation.
- Reorganizing
the computer lab again... seems to be a continual process.
Hanford
(Christine)
- Still
setting up new computers.
- Created
a new account for a visiting teacher.
Set up a computer and printer for him in the Staging building.
- Requested
a new DNS alias for one of the CDS/GC gateways.
CIT
(Mike)
- Tested
Microsofts monthly critical updates, making sure
they're compatible with all OS's, XP, Win 2000,
Server 2000, and Server 2003; plus GC/Engineering software.
- Finish
loading Solaris 10 patches on a work station for Wilson House. I needed
some help from Larry to configure a dual head video card. Added some
documentation to the sysadmin FAQ on this.
- Additional
work on DCC. We now have Linda and Cleveland
up and running. This is only a
temporary fix until DCC gets migrated over to the new DCC system.
- Some
work on the DHCP server. We ran out of TCP/IP addresses again.
- Work
on the mail servers: Restarting services, and clearing out the mail queue.
- Spent
time working in the B/A server room, installing rack mount servers into
their new home. I also rerouted some power cables to take some stress off
one of the UPS's.
- Worked
with Cleveland
on an Adobe issue. I ended up having to reinstall this software, plus run
all updates.
- Worked
on the Spam Filters searching for false positives.
- Additional
misc. user support.
(Bruce Sears)
- iLog Maintenance: (0.5 days)
Finished draft
of iLog admin documentation.
General iLog maintenance (user adds, keyword adds, etc.)
(Veronica)
- Videotaped
and processed the SURF lectures.
LIGO website updates.
- LSC
website updates (authorlist, LSC-related mailing
lists). Working on the webpages for LSC educational resources.
- CaJAGWR website updates.
(Christian)
- Linda
Turner- Installed and configured new docking station for Linda.
- Irene
Baldon- Replaced toner cartridges on Irene's
local printer.
- Finished
reloading laptops that were returned from MIT this week.
- Working
on creating a new Ligo image for the new laptops
that are going to the loaner Pull.
- Worked
on the Spam Filters with Mike and Larry.
- Other
misc.: Continued onsite software/phone support.
(Larry)
- Worked
a number of procurement items.
Ordered a few more SUN items to go with equipment we just
received. Received the Dell items
that were ordered last week. Christian is working on the notebooks and all
other items have been distributed. Reconciliation
of the P-card took a more time than normal. Problems with getting
paperwork from vendors and a discrepancy on one of the orders took their
toll. Still working with Monarch on
getting the computer repaired. All of the memory is to be replaced this
Friday.
- Assisting
the SURF students with their issues is still taking time but it is
tapering off.
- Assisted
the LDAS group in some modifications they requested on different items
-Repaired a couple of disks on the home account server. We are in the
process of replacing the home account server. It will be a few weeks
before all of the h/w arrives and then another couple of weeks to get
everything transferred over.
- Worked
with the DCC group in troubleshooting a number of different items. They
have been receiving files that we are having problems converting to PDF.
- Worked
out some application licensing and configuration issues for different
users and different programs.
- Worked
spam filters with Mike and Christian. Also, a number of minor user
requests.
Mail Statistics for June 15-21, 06
|
Mail Statistics
|
6/22/2006
|
|
Rejected Messages
|
47,238
|
|
Virus Messages
|
2,406
|
|
Accepted Messages
|
23,144
|
|
Total Messages
|
70,352
|
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Systems
Modeling and Simulation
(Hiro Yamamoto)
ASC/LSC design for AdvLIGO using high power FP
arm (Osamu)
We are continuously investigating a FP cavity with quad suspension and AdLIGO laser power. Local damping gain has been set
correctly and strange drift was gone. However the number of DOF for Local
damping is still limited, and it might cause
unexpected noise on some masses. We will implement local damping into all DOFs as soon as possible.
Osamu gave a talk in the AdvLIGO ASC design
meeting and his material and simulation setup are available in http://www.ligo.caltech.edu/~omiyaka/AdLIGO_ASC/.
AdvLIGO Mechanical system modeling (SLU group
lead by Sany)
Continued e2e modeling of triple/quad suspension on AdvLIGO HAM/BSC tables. Table translational motions were created
using the e2e’s standard ground X and Y motions (the same ground motion
as SimLIGO uses), and the toy HAM/BSC model (the AdvLIGO seismic isolation model that creates table top
translational motions required by AdvLIGO
specification). Table Yaw motion was created by the same model as our model for
LIGO 1 HAM table (based on differential table top translational motions). These table top motions are passed to the suspension point
of the triple/quad suspension model one DOF at a time. We completed computation
with suspension Yaw input, and now continuing equivalent computations with
suspension X and Y inputs.
Also continued was e2e modeling of LIGO 1 Mode Cleaner. Several minor bugs were
found in the original MC box and have been fixed. With the e2e standard ground motion
to LIGO 1 HAM seismic isolation model, we have confirmed clear correlation
between MC 1 optic yaw motion and MC transmitted beam's yaw motion. More
detailed analysis is under way.
Adv.Virgo Simulation using e2e (Monica)
Investigation of one single arm (Fabry-Perot
cavity) configuration with Virgo parameters: the control system for the lock
works fine without including the radiation pressure. Next step modify the
control scheme in order to acquire and maintain the lock including the
radiation pressure on input and end mirror.
Investigation of the AdVirgo
configuration: attempt to lock one single arm (done with the demodulated
reflected light) without radiation pressure (excluding all the mirrors), then
the Michelson and the FPMI.
Static IFO Simulation (Hiro)
Code development for the FP
simulation (back end) is almost over and the user interface (front end) is
being implemented. A short summary talk
will be given in the COC modeling meeting on 23rd.
Seismic Isolation
BSC Assembly and Test
We have received all parts for the seismic isolation structure and spring
flexure fixture. After analyzing the position and angle of the stage 1-2
springs we have modified the rod mounting plate so that the mount can be
positioned as shown in the solid model from ASI and designed a shim to place
the spring at the correct height. The shim has been placed on order with Lavallee Machine.
Jon and Rich have assembled the flexure fixture with parts designed for the
new stage 0-1 softer springs. The first blade has been measured and found to be
14.6% softer than predicted by ASI. This is consistent with what we found with
the stage 1-2 springs. We will install this spring today and go through the
same analysis to calculate a new position for mounting the spring.
All mass simulators for the sensors have been recieved.
From: "Joseph A.
Giaime" jgiaime@ligo.phys.lsu.edu
Agenda for the weekly SEI telecom
Friday, June 16, 2:00 pm
Eastern, 1:00 pm Central, 11:00 am Pacific time
BSC SEI Status
- Last
part from Limerick received,
the stage 0-1 spring base.
- Expect
last part for stage 0-1 spring tester to be received soon.
- Tolerance
buildup seems to result in approx 0.02" vertical mis-positioning
of stage 2 with respect to stage 1. This will be corrected, probably
with shims, before stage 0-1 springs will be installed.
- Ken
Watts working on sensor pod electronics installation and testing at LLO.
HAM Conceptual Design
- Joe
& Brian will meet with Corwin next Tuesday to agree on a delivery date
and content of the conceptual (mechanical) design report.
- Meeting
held last week to discuss options for the HAM prototyping and the post-S5
upgrade.
Stanford: Seismometer, Platform
- Matt
has 11 DOF loops closed; They are looking for an
error in the sys-id analysis.
- Tarm preparing to carry out brazing and welding of
seismometer parts. Readout (in separate experiment) seems to work.
From: Ben Abbott
<abbott_b@ligo.caltech.edu>
Szabi
made a recommendation for the HAM-SAS stepper motor drivers, and Virginio and I will work together to prepare an order.
I corresponded with Gianni
about the wiring pinouts on the HAH-SAS
cabling. I'm waiting for him to get back with me.
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
Working with many folks on the differences in suspensions
between the nearly degenerate recycling cavity and the stable recycling cavity.
Mike Smith and Chris Echols sent and updated requirements list for the pick off
mirror suspension and for the ETM telescope suspension.
Working with IO and SUS folks on the recycling mirror size
and suspension.
Provided an update to the SUS progress schedule, through
June 1, to Dwight and Carol. Had a meeting with both
on Friday.
From: Ken Mailand kmailand@ligo.caltech.edu
I'm using the latest information from Ian and working on a lower quad
installation arm shop drawings, and a simpler 'conveyor' version to be used at
the LASTI site.
On the existing five axis fixture, the stainless hardware change out is
planned for next week, this will replace some alloy steel fasteners originally
installed.
Core Optics
From: Bill Kells kells@ligo.caltech.edu
Parametric instability studies have heated up for this summer. I have been
mostly occupied by getting my SURF student up and running on the computer
intensive study of the "infinite spectrum of HTMS" which may
contribute (simulaneously) to the PI feedback. Good
progress so far (extracting acoustic modes, properly normalized from IDEAS). The [arm] cavity sector of the problem is
awaiting the launch of Hiro's new FFT code version.
Also on the PI front, I've been digesting new results by Pablo Baranga, and D. Ottaway (his
recent note on the SRC influence, which I had modeled previously in '05). I had
discussed Pablo's new results with Ju Li and D. Blair
at GWADW in May. Also I've re-contacted B. Bhawal to
appreciate his take on these new developments (since they go beyond his
previous results on HTM coupling and loss).
Then, there has been ongoing monitoring of the OTF work on TM HR loss and
scattering, which progresses. Various new comments and results from VIRGO are
now adding a new dimension to this effort.
Then too, I have been studying the docs for the imminent review of AdL TCS, for early July.
From: Gregg Harry
<gharry@ligo.mit.edu>
We have the first two Q results on the silica-doped titania coating from CSIRO:
2809 Hz Q = 9.8 105
9811 Hz Q = 8.7 105
These are very high Q's, but the lower Young's modulus of titania means the loss angle isn't
that much improved over undoped tantala.
The lower index of titania vs tantala also is a drawback,
requiring thicker coatings. The importance of the Young's modulus to
evaluating this coating means we will plan to directly measure it with a nanoindenter.
From: Helena Armandula ahelena@ligo.caltech.edu
CSIRO finished and shipped another three-sample run (thick, thin and small)
this time using a Tantala/Silica mixture which
contains ~ 35 percent silica in Tantala. The refractive index of this mixture is 1.9,
approximately the same as the titania/silica mixture
sample we received previously. The total 30 x 1/4wave layer thickness is thus
also the same (~4.8 microns). The samples were also annealed for the same 24
hours at 500C. All substrates looked OK after annealing.
From: GariLynn Billingsley
<Billingsley_G@ligo.caltech.edu>
We have received polished samples of Heraeus 311
& 312 fused silica which will be characterized at Caltech then sent to
Hobart William Smith for annealing studies.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
Benno and I went through the AEI schedule for the
PSL to see that we haven't missed out on any tasks/milestones. The
adopted schedule will be the one that we report progress against.
I sent the drawings for the reference cavity vacuum chamber and vibration isolation
stack so that AEI will be able to fabricate a copy of the existing setup.
This is in the event that we recycle the existing hardware at the observatories.
Auxiliary Optics
From: Michael Smith <smith@ligo.caltech.edu>
Non-folded IFO
The allowed mounting space on the BSC1 optical table was determined to accommodate
the ITMY SUS and an estimated footprint for the BS PO mirror. The ITMY was
placed in the middle of its movement range, and the PRM position was set to
achieve a free spectral range for the PRC equal to 18.97164 MHz, as specified
in T010076-01--resulting in an optical path length of 8341 mm for the PRC; and
then, the ITMX and ITMY were moved to create a Schnoop
asymmetry of 400mm. The SRM was placed to provide an optical path length of
8327 mm for the SRC, as specified in T010076-01.
The maximum Schnoop asymmetry is approximately 676
mm.
An updated list of COC positions, surface normals,
and main beam ray vectors was created using Zemax.
A list of IO optical train component positions is in process, in conjunction
with Luke Williams.
PO MIRROR & TEL
A footprint for the BS PO mirror has been established as a maximum envelope
for the BS PO mirror SUS.
The heights of the BS PO mirror and ETM Telescope suspensions were
determined using Zemax. and
communicated to Janeen.
OPTICAL LEVER RECEIVER
I am assisting Royal Reinecke a SURF student in
setting up the prototype optical lever receiver test with the 40M IFO.
From: Chris Echols <cechols@ligo.caltech.edu>
Currently working on detailed layout for BSC 1.
PO MIRROR & TEL
Built a
revised SolidWorks conceptual model of the Pick-Off
Mirror suspension. Completed a revised AdLIGO conceptual
version of the ETM Telescope. Renamed the DLC
assembly and components per LIGO-T030143-03-D.
Controls, Data Systems
From: Jay Heefner jay@ligo.caltech.edu
AdL CDS
- Noise
measurements of the PCIX ADCs and DACs have been
started. Preliminary results show an ADC input referred noise of 10uV/rtHz
with a 40Vp-p (+/-20V) maximum input and a sample rate of 16384 samples
per second. This input referred noise was measured using both the standard
single tone and low pass filtered white noise. In the single tone tests
using a nearly full scale 100Hz sine wave the harmonics are all more than
80dB below the fundamental.
- DAC
testing will be started when the ADC tests are complete but should be
ready for review at the AdL CDS meeting
presently scheduled for the first week of August.
Anti-Alias and Anti-Image Chassis
- AA and AI chassis
production is currently on hold for delivery of DRV135s. One shipment has
supposedly shipped. This shipment will give us enough parts to outfit HAM
SAS, 40M OMC, LASTI squeezing experiment and AdL
ISI at LASTI. The next shipment is scheduled for July 29. If we do not
receive the first shipment soon we will need to produce partial chassis
for the higher priority systems.
LASTI Squeezing Experiment
- System wiring diagrams are started and should be
completed next week after discussions with Daniel and Nergis.
For additional information about this report, contact Stan Whitcomb or Phil Lindquist