Weekly Report for Week Ending June 1, 2006



Due to the LSC and Burst F2F meetings at MIT June 2 - 6 , there will be no LIGO Executive Committee meeting June 5, 2006.


 

Special Announcements:   Advanced LIGO Baseline Review completed. See Advanced LIGO Development below.

 


LSC Issues (Saulson)


·        Peter Saulson attended the Elba meeting, where there were discussions on many aspects of global collaboration. The LIGO-Virgo MOU was the subject of some private discussions with Benoit Mours and others. Most detector projects presented their plans for commissioning, running, and upgrades. We had a round-table discussion on network scheduling issues, at which we grappled with the problems of ensuring enough coverage to do good observing, while also not unwisely delaying the advent of more sensitive interferometers.


LIGO Laboratory Administration (Lindquist)


STATUS OF LSC MOUs (Lloyd)

  • No report.

SITE TELECONFERENCE (Lindquist)

  • No report.
  • There are currently no open action items.  The list of assigned actions updated through December 01, 2005 (the last update) will be found Here.

PROPERTY MANAGEMENT (Luna)

>From: Rod Luna <rluna@ligo.caltech.edu>

  • .No report.

DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner  <turner@ligo.caltech.edu>

  • Finished the "final" draft of the conversion requirements and statement of work with FileHold -- waiting for all the signatures of both sides of the fence.
  • Worked non-stop to prepare our current database for conversion over to Synergy.  This involved writing numerous queries to isolate "pockets" of documents that could be moved over to the new system.  Beginning with 45,000 records, queries so far have defined and allocated about 13,000 records.  Work will continue in creating queries that further assign document from our side over to their new location in Synergy.
  • Attending the LSC to facilitate receipt and posting of all presentations.

>From: Cleveland Mak <mak_c@ligo.caltech.edu>

  • Worked on assembling multiple complete copies of the Cooperative Agreement with all its amendments.
  • Worked on assembling queries in preparation for the migration of current data into the new database.
  • Worked on "cleaning out" the keyword and organization lists in preparation for migration to the new database.
  • *Update on Scanning* - Progress continues on scanning of contract closeout files.
  • Additional Activity:

Week Ending

05/18/2006

In

Out

Packages

17

2

Faxes

18

21

 

FINANCIAL SYSTEMS (Cronin, Brambila, Kaufman)

>From: "Cronin, Holly" <Holly.Cronin@caltech.edu>

>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

  • Completed the package for change order #5 to The Exploratorium and routed it for approvals. It is pending approval.
  • Attended the weekly team meeting and several campus meetings.
  • Placed purchase orders as requested.
  • Completed the p.o. closeouts for May 2006 and submitted the monthly report. Researched open orders with balances that are over 3 months old. Closed several po's.
  • Followed up on the status of orders not yet delivered to check on due dates.
  • Responded to various inquiries related to invoices.
  • Renewed the maintenance agreement for the fax machine in Bridge. There are problems with Oracle in printing out this p.o.
  • Renewed the maintenance agreement for Linda's document scanner

>From: Florence Kaufman <fkaufman@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Jasnow, Salone)

>From: Gina Salone <gsalone@ligo.caltech.edu>

  • Nothing significant to report.

>From: Ed Jasnow <jasnow@ligo.caltech.edu>

  • No report.

PROPOSALS and REPORTS (Lindquist)

  • The NSF has provided the LIGO Operating funds for the last half of FY 2006.
  • Requests for material for the LIGO Operations Annual Report have been distributed.  Contributions are due Friday, June 23, 2006.

CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)

  • No open change requests.

HUMAN RESOURCES (Akutagawa)

>From: Cindy Akutagawa <cindy@ligo.caltech.edu>

  • No special activities to report other than preparing for the summer students.

Quality/Safety (Tyler)

>From: Bill Tyler tyler@ligo.caltech.edu

No report.


LIGO Hanford Observatory (LHO) and Interferometer Operations (Raab)


Summary of S5 Activities at LIGO Hanford Observatory  (compiled by M. Landry)

The latter part of this week saw some of the finest running the project has ever had; see here for an example FOM that shows (2X14 +7)Mpc for extended lock stretches.  Duty cycles for the IFOs for the week were 84% on H1 and 90% on H2.  H1 did struggle for periods this week at a lowly 12Mpc; part of the problem was a bad setting on the QPDs.

Elog highlights are bulleted below:

  • Our standard pie chart showing downtime contributors was updated. Also shown there is a comparison with previous pies: winds are down, and we now have a better accounting for why we lose lock, i.e. less "unaccounted for" losses
  • A scimon study of truck traffic on the 240 highway past EY was performed
  • Mt. St. Helens resumed activity last week and may have been responsible for some lock losses
  • Another photon cal line at lower frequency (719.1Hz) was added briefly to H2, in order to study sytematics between the photon cal and official cal procedures
  • The weekly range and duty cycle report can be found here
  • Recall the problematic injection machine h1awg0 has required near-daily reboots for the last several months.  The most recent spate of reboots has occurred since the April commissioning period. An important advance was made on this problem when loading of the cpu was reduced by removing the unused photon calibrator line (we alternately arms monthly but typically left both test points defined), and now monitor slow channels instead of test points whenever possible.  The result has been a far more stable h1awg0, with no reboots during this week. 
  • The TCS laser on the X-arm showed power instabilities, and a fix was prescribed.
  • h2susepics resumed flaky behaviour

Outreach (Ingram)

  • LHO welcomed real-time lunar images from the Rattlesnake Mountain Observatory into our auditorium as part of this year's multi-partner National Astronomy Day program.  Thanks to Richard McCarthy and Josh Myers for creating the capability for LHO to receive RMO's image transmissions, to Greg Mendell for his fine presentation, to Justin Garofoli (wearing his AASTA hat) for his service on the mountain and to the staff for additional backup.

LIGO Livingston Observatory (LLO) and Interferometer Operations (Zucker)


L1 in S5 (Yakushin)

  • We had a very good week with 75% duty cycle and about 14Mpc inspiral range. On Sunday our duty cycle was even 94%!
  • The lock was interrupted only by earthquakes, trains and construction.

L1 CDS (Bogue)

  • DMT filled up the disk space on london over the weekend.  Keith Riles and I got enough disk space to keep going for awhile.  This is a larger problem that will need to be addressed soon.
  • Modified the london web server to run perl as a cgi rather than a module.  The next big project in cds should be replacing the web server with something more up-to-date and easier to maintain.
  • There is a new design for the cds web pages ready to go live.
  • Wrote some perl scripts to play audio alerts in the control room when we drop out of science mode or when a gamma ray burst event occurs.
  • Worked on the corner weather station code.  The code is now stable, but I would like to spend some time verifying the values coming out of it.

Safety/Security (Riesen)

  • Nearing completion of the last 3 Action Items from our Safety Audit.  They should be completed by the end of next week.
  • Working with Allen on the fire alarm system re-work. The site security system is now receiving correct data from the new fire alarm system.
  • Rupal Amin and I are getting the Optics Lab ready for his Optical Power Amp experiments.  All safety hardware has been verified as operational, the area has been re-cleaned and organized for Rupal's move in. 
  • Ordered laser safety glasses with an OD>5.00 at 808nm.(an OD of >3 meets the requirements, but these would be special order and hard to get).
  • An LLO Laser Safety SOP addendum has been written for the CEO Optical Power Amplifier and will be sent to Mike Zucker for review and sign off prior to the starting of the experiment and adding it to the current LLO Laser SOP plus all associated signage.
  • Conducting Safety orientation for the arriving students and new staff members.

LLO Outreach (Thacker)

  • Prepared for upcoming exhibit training.

AdvLIGO Suspensions and Isolation, Outreach and Very Very Large Art (Romie)

  • (MZ for Romie) Janeen is at MIT participating in the AdvLIGO Baseline Review.

LIGO Computing and Network Security (Roddy)

  • Mail server lost an internal disk this morning.  I am temporarily running on an external disk to get services back up. There will need to be some scheduled downtime in the near future to install more reliable disks.
  • Ran a network scan of the LLO network from offsite.  The scan originated from the LSU network.  Several things to follow up on.
  • Coordinated with CIT to run a network scan of the CIT networks. 
  • Currently have partial results.  There will most likely be a large number of items to follow up on.
  • Still working with Charter Communications on contractual issues for the backup network connection.
  • Started setting up replacement dial-up server for modem access.  Had to stop on this to restore mail services.
  • Working on some of the technical BGP issues for the backup network connection.  We may or may not need some additional hardware for the connection.  It is also possible that we may need the same additional hardware just for reliability issues.
  • Ordered various bits of hardware.
  • Ordered new backup tapes.  About to run out of what we have...
  • Investigating a couple of security issues - one relating to some grid software
  • Investigating a couple of IDS alerts at LHO-CDS.  One relating to the FMCS web server.

Data Analysis (Yakushin)

Storage/Condor/LDAS admin:

 

  • Studying Q-replication and WebSphere documentation (Q-replication and WebShpere are used to keep segment databases at sites in sync).
  • After last week reboot of dataserver and gateway I have not noticed any more network interruptions inside LDAS network and decided not to reboot the network switch for now.
  • LDRed SG1C_S5 burst MDC frames from PSU to LLO and CIT.

 

Data analysis:

 

  • Continued working on LIGO-GEO simulations.
  • Generated waveburst triggers on SG1C_S5 burst MDC frames that cover a period between Feb 15 and May 2.

 


Initial LIGO Detector Science & Engineering (Coyne)


 

No report (participating in AdvLIGO baseline review).

 


40-Meter Interferometer (Weinstein)


No report.


Thermal Noise Interferometer (Black)


·        Nothing exciting to report this week. We are debugging electronics and getting ready for SURF students.


LASTI (Ottaway)


No report.


Data Analysis and Computing (Lazzarini)


Simulation and Modeling (Yamamoto)

No report this week – attending Elba Conference.

Data Analysis Activities (Lazzarini)

Shawhan:

 

  • Produced segment lists for offline burst analysis for S5 through May 2, using a number of data quality flags.
  • Released new versions of a few LIGOtools packages.
  • Drafted the remaining sections of the paper describing the S4 LIGO untriggered burst search.

 

Sutton:

 

  • I spent the past week at the GWADW 2006 in Elba, Italy.  I delivered a talk on "Recent advances in coherent network searches for gravitational-wave bursts". 
  • During the previous week I was in Benevento at the Universita degli studi del Sannio, talking about time-frequency burst detection with Innocenzo Pinto and Maria Principe, and giving some seminars on burst detection and coherent search techniques.

 

Yakushin:

 

  • The results of the waveburst simulations on SG1_S5, covering the period from the beginning of S5 to May 2, are published at

             http://ldas-jobs.ligo-la.caltech.edu/~waveburst/S5_LIGO_ONLINE_2/SIMULATIONS/index.html

  • The events found by high-threshold analysis up to now are summarized at

             http://ldas-jobs.ligo-la.caltech.edu/~waveburst/S5_LIGO_ONLINE_2/bigtable.html

  • The techical document describing the waveburst version currently used for online analysis is submitted to DCC: LIGO-T060112-00-Z

LIGO Data Analysis System

Software Systems (Blackburn)

 

LDAS

 

  • Using TCL 8.4.12 has shown problems within LDAS. Using this version of TCL, there appears to be a higher rate of missed tracing of variables. Work has focused on modifying the trace syntax to use that of TCL 8.4.12 instead of the legacy syntax based on TCL 8.3.5 which is causing the problems. This has shown some improvement. This effort should be completed by next week.
  • Work has started on supporting LDAS on the Opteron running Solaris 10. The current stumbling block is GCC and building the C++ compiler. It is a known issue and is slated to be fixed in a future release. Efforts are shifting to use Sun Studio.
  • System testing was done using ldas version 1.8.193 and using TCL 8.4.12. Weekend testing were not carried out do to a bug in the start up of the test scripts. Higher than normal job failure rates continue in association with the TCL 8.4.12 upgrade.

 

TCLGLOBUS

 

  • Investigation of the connections timing out when connecting to LDAS manager while using GLOBUS 4.0.2 is still under investigation. Three versions (XIO-based TCL Channels, raw TclGlobus, C program using Globus API) of the same program have been created in an attempt to determine which level of interaction is causing the delay. These programs need to be enhanced to record at the millisecond resolution.
  • Attended the VDT weekly "office hours" telecon. No follow up on the inclusion of TclGlobus into VDT at this time. The VDT has formally requested the OSG executive board to review the inclusion of TclGlobus into VDT.

 

GRID COMPUTING

 

  • Received a response from the Condor team requesting additional debug information regarding registered bug related to FC4/glibc/DAGMan. Planning has begun to set up one system for debugging with Condor 6.7.18 -  6.7.20 to demonstrate which combinations of glibc and Condor DAGMan abort while attempting to execute a work flow consisting of an Inspiral analysis on the OSG.
  • Using a simple Burst analysis provided by Shourov in MatLab R13, constructed a work flow consisting of set of DAG nodes designed to execute the Burst analysis on the LIGO Caltech OSG cluster. Condor DAGMan has successfully executed the Burst analysis including the MatLab interpreter on the LIGO-CIT-ITB OSG cluster.
  • Worked with the Michael, and Kent on the LIGO work flow planner specification. The work flow planner code base has been checked into CVS.
  • The OSG Council meet to discuss agenda and plans for the upcoming Consortium meeting August 21-23 in Seattle.

 

Hardware Systems (Anderson)

 

Caltech

 

(Dan Kozak)

 

  • Helped a little with racking equipment to ship to the observatories.
  • Worked with Eric to try to figure out the dataserver-cit automount of node170 problem. We've tried swapping the Linux hardware, checking the Linux software installation.
  • Provided some small support for recovery from hung T3 in /archive at LLO.
  • Closed case with Sun regarding problem 3510 (-10/12).  After replacing 6 of the 12 drives, the unit has been functioning fine for almost a week.
  • Figured out which LLO tapes to eject for shelf storage.
  • In the course of getting caught up on all L0s, found a corrupt (truncated) L0 frame file at LLO. Ben believes this was caused by the dd from /frames to /archive failing. The ingesting procedure flagged it, but we'll need to look into getting the info early, while there's still a change to re-copy it from /frames.
  • Still trying to figure out why rsync claims that 500,000+ files would need to be rsync'd from LLO's /archive/frames/S5/L0 to CIT when it is not the case.

 

(Phil Ehrens)

 

  • Wrote and installed certcheck.tcl automatic certificate expiration detection and notification tool. This script is called as a daily cron task and logs imminent cert expiration beginning one week before expiration. The log entries are recognized by log_mon.tcl and email is sent to the appropriate admin.
  • Wrote mcelog module for log_mon.tcl which dumps mcelog data into a sensible file hierarchy that is visible via a web browser.

 

(Erik Espinoza)

 

  • Worked with Phil to log Machine Check Exceptions.
  • Reconfigured all IPMI cards due to a few machines being swapped.
  • Configured lm_sensors, working on getting rrdtool to create charts.
  • Coordinated telecon w/ AMD, SuperMicro, ASA, & Kingston for RAM stability issues.
  • Looked into Symantec Antivirus Issue.
  • Tested a few different options on node170:

-         Raised number of nfsd, didn't work

-         Swapped hardware, also didn't work

  • Replaced disk on node155.
  • Rebooted node40 (rwsem.h crash).
  • Upgraded ldasbox5, dataserver (dev), metaserver (dev), & beowulf (dev) to latest available updates + glibc for testing.
  • Looked into possibility of Jumbo packets on Cisco 6509 + nodes.
  • Added xfig/transfig packages to kickstart.
  • Installed fftw3 development package on couch.
  • Looking into BIOS issue on "slow" returned nodes.

 

MIT

 

(Keith Bayer)

 

  • Supporting AdvLIGO meeting.

 

Livingston

 

(Igor Yakushin)

 

  • Continue studying WebSphere documentation.
  • t3-24, which is part of /archive, froze on Monday morning and had to be power cycled. A few corrupted L0, L1, L3 frames were found and fixed.
  • Installed xfig and transfig on ldas-grid and the nodes per Shourov's request.
  • Per Laura's request copying S5 L3 frames to the nodes.
  • Found several 'damaged' L3 LHO S5 frames. Ran 'undamage' on them. At first glance it helped.

 

Hanford

 

(Greg Mendell)

 

  • I am still working on realtime SFT publishing.

 

(Ben Johnson)

 

  • Researching IPFirewall rules for LDAS sites. Successfully firewalled both client and server for NFSv4 using only port 2049.
  • Publishing and/or datafind server problem revealed this weekend. Online user, inspiralbns, was not getting the full list of files it needed. The segments were there, but not all URLs. The problem has since gone away. Will follow up.
  • A photon calibrator was turned off this Saturday, May 27. H1AWG0 has been running stably since (as of yesterday at least). Only ONE CRC mismatch frame at LHO has been found in the 5 days since (it  occurred on May 30).

General Computing (Wallace)

MIT

 

(Keith)

 

  • Spent this week doing various prep related stuff for the Advanced LIGO Review and the LSC conference.

 

Livingston

 

(Shannon)

 

  • Mail server lost an internal disk this morning.  I am temporarily running on an external disk to get services back up.  There will need to be some scheduled downtime in the near future to install more reliable disks.
  • Ran a network scan of the LLO network from offsite.  The scan originated from the LSU network. Several things to follow up on.
  • Coordinated with CIT to run a network scan of the CIT networks. Currently have partial results. There will most likely be a large number of items to follow up on.
  • Still working with Charter Communications on contractual issues for the backup network connection.
  • Started setting up replacement dial-up server for modem access. Had to stop on this to restore mail services.
  • Working on some of the technical BGP issues for the backup network connection. We may or may not need some additional hardware for the connection. It is also possible that we may need the same additional hardware just for reliability issues.
  • Ordered various bits of hardware.
  • Ordered new backup tapes.  About to run out of what we have.
  • Investigating a couple of security issues - one relating to some grid software.
  • Investigating a couple of IDS alerts at LHO-CDS. One relating to the FMCS web server.

 

Hanford

 

(Christine)

 

  • Installed two additional paper drawers on the OSB color printer. One of the paper drawers was damaged in shipment, but thanks to some help the drawer was fixed without having to be sent back.
  • Set up more new computers, still have 6 more computers to set up.

 

CIT

 

(Mike)

 

  • Ghost backups on NTSRV's. I ran end of month ghost backups on all critical NT servers.
  • Went through ten SUN Ultra 10 workstations that we had in stock. I ended up keeping 2 good one's, and surplus 8 workstations. Most of these workstation's are inoperable.
  • Spent time on maintaining the mail servers, through out the week including the weekend.
  • Continued work on the DCC servers. More issues this week that required much time keeping these servers up and running. One issue was user error this had the public side of the house down for a couple of hours.
  • Held down the fort while Larry was out on his day of vacation.
  • Worked on the wireless access points; removing old mac addresses and adding a few new ones.
  • Spam Filters: There was a lot of work over the holiday weekend keeping up with the filters, searching for false positives.

 

(Veronica)

 

  • Ongoing support of the AdvLIGO NSF Review. Misc. user support. Addressed a DCC server issue. Updates of the LSC mailing lists.

 

(Christian)

 

  • Mike Smith - configured new system with the engineering Ligo image for Mike and transferred all his data.
  • Lee Cardena - upgraded Lee from Windows 2000 to Windows XP and transferred all his data.
  • Worked on the Spam Filters with Mike and Larry.
  • Other misc. - continued onsite software/phone support.

 

(Larry)

 

  • Still working the procurements. Purchased a number of UPS units to replace the old worn out units. Still trying to get Monarch to respond on getting the server repaired. PMA has a new contact on campus that has worked with Monarch in the past, I will try to get them to help out. Purchased more supply items. Received the SUN equipment and presently going through the order list to make sure we got everything that was ordered.
  • Setup one of the new SUN workstations running Solaris10. Attached a dual 24inch monitor system on it. It looks pretty nice. Something I may need to consider for future upgrades for those that need a lot of screen space.
  • Worked with Mike, Christian and Rod in getting a bunch of old equipment removed. We are now just waiting for transportation to take it away.
  • Worked with Keith on a couple of logistical issues concerning the NSF review.
  • Still working on account cleanup and removal. There are quite a few accounts that I still need to check out.
  • Worked a number of DCC issues. Both for the DCC and some of the endusers.
  • Assisted a number of users with different issues.
  • Started monthly backups.
  • The e-mail saga continues. The filter database is getting to be in pretty bad shape and will probably need a rebuild in the not too far future.

Mail Statistics for May 25-31, 2006

Mail Statistics

May 18, 2006

Rejected Messages

34,599

Virus Messages

1,557

Accepted Messages

25,281

Total Messages

59,880

 


Advanced LIGO and Supporting R&D (Shoemaker)


Advanced LIGO Systems

>From: David Shoemaker  dhs@ligo.mit.edu

  • Advanced LIGO Baseline Review completed. It was a resounding success, thanks to the work of the entire LIGO/LSC Advanced LIGO Team.


For additional information about this report, contact Stan Whitcomb or Phil Lindquist