Weekly Report for
Week Ending May 25, 2006
Due to the Memorial Day holiday, there will be no LIGO
Executive Committee meeting May 29, 2006.
Special Announcements:
Weekly Report Highlights:
No report.
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
- Received the MOU between the Advanced LIGO United
Kingdom (ALUK) Group complete with signatures. This will be submitted to
the DCC and posted..
SITE TELECONFERENCE (Lindquist)
- A
site teleconference was held Thursday, May 25, 2006. The following
items were among those discussed:
- Budget
Adjustments--Hanford
has expressed an interest in realigning budget for FY2006. It is our understanding that the
adjustments do not increase the total and individually are less than
$50K. If this is the case, no change request is required although
the Business Office should be kept in the loop.
- Livingston Science Education
Center--still on
schedule and going well.
- Science Education Center
Kinetic Facade--Mike and Janeen visited the
vendor responsible for the design task. Some beneficial
modifications have been made to resolve corrosion of the bearings,
etc. The vendor is touring
potential fabrication facilities and checking on permits. All design
works appears first rate and ahead of schedule. The FDR is scheduled
June 22, 2006.
- Property
Issues--The trip tentatively planned to Livingston
has been cancelled. Property will attempt to address all open issues
from Pasadena.
- Site
Volunteers--Caltech Legal seems to be leaning towards security
background checks for all site volunteers. Caltech has a company
that will do this, but it could be too expensive.
- Next
Meeting--There will be no site teleconference Thursday, June 1, 2006
since most participants will be in the Advanced LIGO Review at MIT.
- There
are currently no open action items.
The list of assigned actions updated through December 01, 2005 (the
last update) will be found Here.
PROPERTY MANAGEMENT (Luna)
>
- Provided assistance to the General Computing Group
with the packing and shipping of 1 Laptop for the LSC meeting @ MIT.
Account Number LIGO.DIR-1.1.1-NSFLIGO.FY02ON.
- Provided documentation to justify tax exemptions for
purchases on LHO and LLO accounts. (Finance Tax Audit)
- Prepared property records for 7 pieces of equipment
located at LLO.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner
<turner@ligo.caltech.edu>
- Last week attended the AIIM (Association for
Information and Imaging Management) Conference in Philadelphia. Attended about 20
sessions covering various aspects of document management, legal issues,
best practices, and trends to be aware of and planning for.
- As guest editor, provided oversight on the June issue
of Document Magazine. Submitted Guest Editor Viewpoint article for
that same issue.
- While in Philly, met with fellow Editorial Advisory
Board Members for /Document Magazine/ to plan content, contributors, and
assignments for the next six issues of the magazine.
- Finished a final draft of the file hierarchy upon
which all files will be located in the new Synergy Document Management
system. In Synergy, the hierarchy consists of up to four levels of
indentured filing.
- Spent two full days finalizing the Requirements
Definition document with FileHold.
This document is expected to be signed and released by Caltech for Synergy
to begin the required development work, and submit a schedule to us of
milestones. With a signed off Requirements Document back to FileHold tomorrow, we are on target for a rollout at
the August LSC meeting in Louisiana.
- With the file hierarchy set, all profiles were
reviewed to ensure that all metadata was requested necessary for automatic
file of document uploads into the correct file location. This
involved 14 unique document profiles (a profile is the system form
containing all the metadata needed for the specific document
description). Some of the unique profiles are:
Financial/Budgets, Contractual, MOU's,
Presentations, Multi-Media, Human Resources, Change Requests, Management,
etc. In most cases, substantial work was required. Fields were
added/deleted, editing rules applied, and order and flow of requested data
entry sequenced.
- A total of 27 drop-down menus were designed to
support each profile, minimizing amount of typing required by author at
upload. Most of the metadata required at upload uses a "point
& click" from these drop-down menus.
- George Stokes is working with me to create
"rules" for migration of data on the DCC side over to the
correct file locations within Synergy. These rules will be written
in SQL and will be conversion ready for Synergy with all testing and
validation being done against our records prior to the migration.
Once migrated, Synergy will enact their own validation and testing and the
results of both sides will be compared for accuracy -- if done right, each
should reflect the other's count of documents, etc.
- George began building the required tables, logs,
forms, and testing queries needed to support the sanitizing of our current
database so that there is clean data going over to Synergy. This is
a huge effort but will allow FileHold the time
needed to complete their development and testing in a timely way to
support our August rollout.
- Set up a list of queries to address large blocks of
documents that are straightforward in their content. These will be
the first documents for George to handle on our side, testing his tables,
etc. for correct logical processing.
- Worked on a data input flow sheet for each document
profile. This will show which fields are seen first, and based on
menu item selection, which further fields are required prior to
upload. This also will verify that I have accurately covered through
the fields both the data required and the necessary information for the
system to file the document to the right location.
- Began planning for SURF orientation and am in the
process of distributing last year's presentation to each of the speakers
who were involved in the orientation, so they can edit and update for this
year's SURF orientation on June 13.
- At Jay's request, began planning various options for
a staff/SURF social. Beaches, parks, and other summer activities are
options under consideration.
- Started preparing the various forms and paperwork for
the upcoming LSC in Boston
next week.
>From: Cleveland Mak
<mak_c@ligo.caltech.edu>
- Fulfilled
numerous document number and posting requests.
- Processed/distributed
3 DCN's.
- *Update
on Scanning* - Progress continues on scanning of contract closeout files.
- Additional
Activity:
|
Week Ending
05/25/2006
|
In
|
Out
|
|
Packages
|
32
|
10
|
|
Faxes
|
26
|
15
|
FINANCIAL SYSTEMS (Cronin, Brambila, Kaufman)
>
>From: "Brambila, Ruth"
<Ruth.Brambila@caltech.edu>
- Followed
up on the status of an out of print book which the publisher has just
recently shipped from the United
Kingdom.
- Routed
change order 4 for the Exploratorium and submitted it to the vendor.
Working on change order 5 for the Exploratorium.
- Working
on the Sun Microsystems order for LIGO Livingston Observatory for which
the matching grant expires next week.
- Placed
orders with vendors for the sites and for Caltech. Followed up on pending
orders that have long lead times.
- Received
the pending invoice for the May 2006 report and submitted it to P-card
Administration.
- Obtained
information on Raytheon's pending charges through JPL associated with
services provided two years ago.
- Working
on closing out p.o.'s and preparing the monthly
report for submission next week.
>From: Florence Kaufman
- Worked
on updating monthly reports.
- Submitted
a Cost Transfer to move travel expenditures from LIGO.STO to the
fabrication account LIGO.HSAS.
Expenditures had been charged to the LIGO.STO account because of
delays in setting up the LIGO.HSAS account.
- Discussed
issues related to addition to the Exploratorium contract with Mike Zucker, Ed Jasnow, and Gina Salone.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone
<gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow
<jasnow@ligo.caltech.edu>
- A
Request for Quotation (RFQ) is being prepared for the manufacture and
installation of the kinetic facade for the LLO SEC. Proposals will be scheduled to be
received around July 21.
- The
LLO SEC remains on schedule, with beneficial occupancy scheduled for early
September.
PROPOSALS and REPORTS (Lindquist)
- The
GPRA estimates for LIGO Operations have been submitted on FastLane. GPRA stands for Government Performance
& Results Act, which requires us to identify goals relevant to LIGO
operation for the fiscal year. FastLane is
the NSF system for submitting reports, proposals, etc.,
electronically. LIGO performance for this fiscal year will be based
on the integrated number of days of operation in Hanford-Livingston
coincidence.
- Requests
for material for the LIGO Operations Annual Report have been
distributed. Contributions are due Friday, June 23, 2006.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa
<cindy@ligo.caltech.edu>
- The minutes and action items from the SC meeting are
posted on the SC web page.
- Preparing for the arrival of the REU students.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
No report.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary
of S5 Activities at LIGO Hanford Observatory (compiled by
K. Kawabe)
Rough week starting with high wind, followed by
thunder storm and subsequent power glitch, various computer problems and loud
construction activities. Both of the IFOs failed to
meet S5 goal. The H1 duty cycle was 60.9% with the inspiral
range varying from 12- to 13+ Mpc. H2 duty cycle was
73.3% with the inspiral range varying between 6 and
7- Mpc.
Highlights from the elog
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
>From: Janeen
Romie <romie_j@ligo.caltech.edu>
·
LLO
Science Education
Center Kinetic Art
Project - Yesterday, we went to HPD to
see and review the prototype. A number of issues were agreed upon. The
prototype was exciting, especially since Boulder,
CO was experiencing gusts of
about 30mph yesterday morning. Charlie Danaher from HPD will be visiting LLO
tomorrow for the day.
Initial LIGO Detector Science & Engineering (Coyne)
Working Advanced LIGO
(reported below)
CDS
See weekly commissioning minutes in the commissioning archives
DMT
No report.
40-Meter Interferometer (Weinstein)
IFO Commissioning
- Rob
and Rana continue to improve lock acquisition.
Following more and more tweaking, signal quality improvements and lock
acquisition code and script work, we are now firmly in a region where it
is easy to acquire DRMI+2arms lock, and do a bunch of signal handoffs.
Work on reducing the CARM offset to zero and returning to full arm
resonance continues.
- Dan
continues to work on getting the MC WFS system back up after the move to
the AP table (greatly shortening the beam path), 45 degree reorientation
of the WFS heads, guoy phase recalculation, and
power optimization to ensure WFS head safety without the need for fast
shutters. He awaits the appropriate beamsplitters,
on order; meanwhile, he'll get it working with imperfect beamsplitters, modify the matrix to handle the
45degree rotation, diagonalize the servo and get
it recommissioned.
IFO Modeling
- Monica
is in Europe, preparing a talk on her e2e simulation efforts for the Elba meeting.
DC Detection and Vacuum Squeezing Development
- Rob
and Sam have more-or-less completed the DC readout in-vac
beamline alignment, on the bench, using an NPRO.
All components are in place, including the PZT steering mirrors (not yet
powered). The OMC dither-locks at 20 kHz, "like butter". They
are working on improving the mode matching. The output mode matching
telescope has a variety of problems, making the mode matching difficult,
but not impossible. They have a plan for aligning and mode matching after
installation in vacuum. They are now checking out the DC photodiodes, and
will soon be ready to dismantle the entire thing for vacuum cleaning and
baking. The system will then be reassembled and pre-aligned on a clean
flow-bench in preparation for installation, currently scheduled for
mid-July.
- Rob,
Sam, Ben, Rolf, Rich and Jay had a summit on the DC readout controls. Most
of the required controls should be ready in time for installation.
- Ben
reports that the DCPD Satellite box's front and back panels will be here
any day now.
- Ben
is finalizing the QPD whitening board design.
- Bob
tested some resistors for vacuum compatibility, and found that the
gold-bodied power resistors failed the RGA scan. We'll have to go with the
ceramic bodied ones.
- Jay
built and tested a prototype for the tip-tilt PZT mirror driver needed for
both the LASTI Ponderomotive and 40m DC readout
controls.
- Bob
baked the conflats for the DC readout beamline ports (OMC reflected and transmitted, to QPDs) and gave them to Steve.
- Go has
been working on the stability of the SHG cavity. It's still susceptible to
seismic and acoustic noise, but its stability is better than before. Work
continues.
PSL
- Steve
and Dan, in the process of rewiring the PSL enclosure interlock,
discovered that the interlock cable was flaky, causing some of the
spurious interlock trips we've been experiencing lately. With help from
Ben and Rich, they rewired the interlock so that it shutters the power
amplifier rather than tripping the NPRO; much more gentle for the laser!
As a bonus, the EPICS control of the power amplifier shutter now works.
- The
PSL head temperature is still observed to be fluctuating, but less than
before. There have been no sharp spikes in HTEMP in the last few days.
Steve continues to watch this closely.
- Steve
covered the PSL trip switch with a guard to prevent it from accidentally
being pushed.
- Rana noticed that reflection from the squeezer back to
the PSL NPRO makes it much noisier, despite the presence of two Faraday
isolators in the MOPA box. He blocked the light path and the noise went
away. Go installed a Faraday isolator in his squeezer path, but it had
little effect. He traced it to reflection from the OPO, not the SHG.
- Steve
noticed that the PSL FSS can lose lock (overnight) when IFO is left in LA
mode; could this be due to the fast CM servo? Under investigation.
Lab Infrastructure
- We
had approximately 60 visitors to the lab on Saturday, as part of Caltech
Alumni / Seminar day.
- Steve
reports that after the rains, the particle count is now back down to
normal in the lab (it follows the outside particle count very well,
unfortunately).
Thermal Noise Interferometer (Black)
No report.
LASTI (Ottaway)
No report.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Yamamoto)
Effective this week, Hiro's report will appear
under the Advanced LIGO section.
Data Analysis Activities (Lazzarini)
Chatterji:
http://ldas-jobs.ligo-wa.caltech.edu/~shourov/qscans/lockloss/
Dupuis:
- working
on S5 frequency/spindown searches for
interesting pulsars.
- worked
through S3/S4 time domain pulsar paper.
Mandic:
- I
have finalized the first draft of the paper discussing the results of the
all-sky stochastic search using S4 data, and I sent the paper for review
by the LSC and Peter Saulson.
- I worked
with Xavi Siemens on the accessibility of the
cosmic string models of stochastic GW background to LIGO.
Mendell:
- All StackSlide jobs have finished with what I hope are the
final results. Work continues on incorporating these into the S4 PowerFlux StackSlide, and
Hough paper for presentation at the June LSC meeting at MIT.
Shawhan:
- Worked
on writing the paper describing the LIGO S4 all-sky burst search.
- Revised
the set of burst hardware injections.
- Tracked
down a Epics/conlog problem noticed by Myungkee Sung.
Yakushin:
- Continue
working on LIGO-GEO simulations
- Generated
waveburst triggers on SG1C_S5 burst MDC frames
that cover a period between Feb 15 and May 2.
LIGO
Data Analysis System
Software Systems (Blackburn)
LDAS
Testing of Tcl/Tk 8.4.12 has moved
to ldas-dev. Most of the failures are due to tasks
taking too long in an API. This issue is being investigated.
64-bit Solaris LDAS has been tested using username/password authentication.
There remains issues with building globus on Solaris.
This too is being investigated.
There has been a drop in the nightly job rates on the ldas-dev
system. There is some speculations of some network issues. There was a
dramatic drop in the job rate when globus 4.0.2 was
used. This issue is not yet understood and attempts to characterize the issue
are under way.
System testing was done using 1.8.186. As mentioned above, we are seeing a
significant reduction in throughput with the new globus
4.0.2 which is resulting in higher failure rates (up to about 3%).
TCLGLOBUS
The Workflow GUI's preference dialog has been extended to use a notebook layout
so all preferences are on one screen and can be quickly manipulated by the
user. Also, GSIFTP monitoring has been added with a progress bar.
The guild package is being certificate enabled via the tclglobus
package. This allows it to use authenticate with the LDAS manager using user
certificates. The LJrun package still needs to be
modified.
This week we began the process of adding TclGlobus to
the VDT software package set. We have had several email communications with the
VDT lead, Alain Roy at Univ of Wisc
Madison. The new software questionnaire for inclusion into VDT has been
submitted. At this week's VDT office hours, the TclGlobus
team was asked to provide a summary of the package and how we distribute and
test. The meeting was very useful and cleared up several of the open questions
on both sides. The TclGlobus team also raised
community awareness of a GSI authentication issue recently found in Globus 4.0.2 to this community.
GRID COMPUTING
Upgraded the GUMS server to latest release from OSG 0.4.1 cache. Configured the
GUMS server with latest list of OSG VO sites. Preliminary testing of the GUMS
server to begin with the test bed cluster.
Determined that the VOMS web admin interface precluded adding new LIGO accounts
to the LIGO VOMS from Caltech. This problem was resolved by Murali
at PSU.
Work continued with the Michael and Mary on the LIGO work flow planner
specification. GSIFTP monitoring and work flow planning, execution, and restart
functions are complete. Preference Menu items and Tabs are not yet implemented.
A number of bugs have been discovered, and reported. These bugs have not yet
been resolved.
Obtained from Shourov, a simple Burst analysis in MatLab for testing execution of MatLab
applications on the OSG. Also with help from Kent, identified a second simple Matlab test program for reading frame files that is posted
on the DASWG Matlab web site.
Attended an ITB telecom with agenda items on SRM/DRM testing and privilege
components.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Installed
11 T3 power supplies, all are working fine.
- Expanded
the size of CIT's /home metadata.
- Worked
with Sun on the problems with (now) 3510-12. Got them to swap 6 of
the 12 drives so we can try to determine which drive(s) are causing the
issue.
- Provided
a small amount of followup support for the LLO
fb0 upgrade.
- Figured
out which LHO tapes to eject for shelf storage.
- Moved
some misplaced h(t) files to their correct location at CIT and
re-registered them in RLS.
(Phil Ehrens)
- Worked
with Stuart Anderson and Dan Kozak to prepare
racks for shipment to LLO and LHO. Racks will be moved to loading area
Friday morning and will be shipped out Tuesday.
- Wrote
certcheck.tcl script for creating syslog entries warning of imminent expiration of grid certs.
- Worked
on documentation of log_mon.tcl on Wiki.
- Various
cluster maintenance and support tasks.
- Assisted
LDAS developers with a number of issues related to the move to the current
Tcl branch.
(Erik Espinoza)
- node7
has been returned to service, bad memory.
- frog
has been fixed, running Condor tests with David Meyers.
- Communicating
with AMD & ASA regarding Machine Check Exceptions.
- Handling
RMA of memory.
- Assisted
Phil in wrapping racks for observatories.
- Looking
into Condor Quill issues.
- Catching
up after being out sick.
MIT
(Keith Bayer)
- Installed
wall brace for condensation tank.
- Facilities
fixed liebert humidifier sensor.
Livingston
(Igor Yakushin)
- Studying
Q-replication and WebSphere documentation
(Q-replication and WebShpere are used to keep
segment databases at sites in sync).
- After
last week reboot of dataserver and gateway I
have not noticed any more network interruptions inside LDAS network
and decided not to reboot the network switch for now.
- LDR'ed SG1C_S5 burst MDC frames from PSU to LLO and
CIT.
(Dwayne Giardina)
- Ejected
tapes for shipment to CIT. imported and labeled new tapes problems arose
with a drive during labeling. restart samd fixed
and labeling was successful on second try.
- QFS
upgrade on FB0 with Lisa.
- Ordered
replacement motherboard for node99.
- RMAd three failed node disks that had been sitting in
LDAS room.
- Replaced
failed power supply in node115.
- Continued
working on a ganglia replacement to monitor our cluster statistics, I like
what I have so far, but much work is needed.
- I
will be visiting LHO the first week of June.
Hanford
(Greg Mendell)
- Now
60 second SFTs, as well as 1800 s SFTs, generated from h(t) for the pulsar group have
been published at LHO and LLO between Dec. 17, 2005 and Jan. 31, 2006, and
have been transferred to CIT via LDR. The types are 1_H1_1800SFT_hoft,
1_H2_1800SFT_hoft, 1_L1_1800SFT_hoft, 1_H1_60SFT_hoft, 1_H2_60SFT_hoft,
and 1_L1_60SFT_hoft, for use with LSCdataFind
with the –type option. Work on generating and publishing SFTs for the other S5 times, and a proposal to
concatenate the 60 s SFTs, with 30 of these per
file for better transfer efficiency, is under way.
(Ben Johnson)
- Have
perl script to remove non-statable
entries from user environments. Need to find a way to incorporate it into
the user setups on the lab clusters.
- Finished
analysis of May 11-12 CRC mismatches at Livingston.
No actual data mismatches, looks like an EPICS issue.
- Ejected
a batch of 55 tapes (S5 L0 data) to give us more breathing room for data
archiving.
- Solaris
10: Reading up on ZFS. Still researching a good dtrace-based
NFS-server diagnostic. Most folks on dtrace-discuss
apparently use OpenSolaris and have more useful
kernel symbols at their disposal.
- Added
ssh public key to cluster (most nodes anyway).
Still need to make sure all nodes got the key.
General Computing (Wallace)
MIT
(Keith)
- Ordered
two AMD desktops to support incoming UROPs.
- Setup
for adv ligo review: configured hp2600
semi-portable laserjet printer; tested wireless
connectivity; tested projectors working on backup for Caltech adv ligo website.
- Troubleshot
laptop for scientist.
- Rebuilt
windows desktop after MIT security found an anon ftp service running
on it
Livingston
(Dwayne)
- User
was having email attachment issues. Reconfiguring e-mail client
solved problem.
- Ordered
PCI - USB adapter for high-power laser lab computer - Installed Autocad 2006 on a user PC.
- Continued
investigating possible workaround for ~{user}
websites as we are receiving several complaints that they are no longer
available on www.ligo-la.caltech.edu
and links are broken.
- Other
usual user requests and support.
Hanford
(Christine)
- Started
setting up the new Sun computers. I am also cleaning and rearranging
the server room to accommodate another rack for 4 more servers, the new
disk system and the new tape backup library.
- Finally
got around to removing the old, dead, black and white printer from the
printer room. The color printer is now on a base with wheels and
I've ordered two more paper drawers.
- I
heard from PNNL that they have transitioned their circuit to ESnet from 1GigE to 10GigE effective 5/16/06.
The LHO circuit is still 1GigE over a 10GigE circuit.
- Updated
the software available for install from our PC Standard sys area.
- Ordered
a backup GigE NIC for the Cisco router.
Also ordered a different FastEthernet NIC, only
one connector as opposed to two. The card I have has two connectors
which causes it to use more bandwidth across the router backplane, even
though I only use one connector.
CIT
(Mike)
- Spent
a lot time this week trying to keep the DCC servers running. I am
still trying to figure out what the deal is on these servers. Larry
had to give me a hand with some of these issues.
- DCC's nightly process workstation had a hardware
issue. This turned out to be a dead power supply. I had an identical
non-working computer in our storage area which I used for parts, to swap
out the power supply. This workstation is up and running.
- Continued
work on the spam filters searching for false positives.
- Installed
a rack mount server that came back from Monarch computer.
- Worked
on swapping out Hiro's monitors from a CRT to a
LCD on his LINUX workstation. This gave me some issues trying to get the
dell drivers to work with the LCD monitor.
- Cleaned
up many old surf students/visitor home accounts. I removed these accounts
to get ready for this summer. This is still an on going project.
- Recovered
data for a few users.
- Trouble
shot a users laptop with a wireless connection issue. This turned out to
be a dead internal card. I have loan him a Orinoco
card until he receives his replacement from IBM.
- Other
misc. support.
(Bruce Sears)
- iLog Maintenance: (0.5
days) Writing iLog
admin documentation. General iLog maintenance
(user adds, keyword adds, etc.)
(Christian)
- Phil
Willems - Called Dell support to have Phil's
motherboard and CD- Rom checked and replaced on laptop.
- William
Kells - Configured new laptop with the standard Ligo image for Bill.
- Cindy
Akutagawa - Installed and configured Dreamweaver 8 on Cindy's workstation and laptop.
- Mike
Smith - Configured loaner laptop for Mike to use on travel.
- Millikan - Replaced toner cartridges on HP 5500
printer.
- Worked
on the Spam Filters with Mike and Larry.
- Other
misc.: Continued onsite software/phone support.
(Veronica)
- LIGO:
Ongoing work on the Advanced LIGO NSF review website. Updates
of the PAC meeting website. Helped Julie with the posting of Jay's
presentation for the All-Hands meeting.
- LSC:
Website updates. June meeting website updates. Worked with Larry
on the password issue for the Closed Talks section of the past LSC
meetings presentations. LSC-related mailing lists issues.
(Larry)
- Still
working procurement issues. Distribution of past ordered items continues.
The USB drives have been the hot item and it is good to see people using
them. Received the computer back from Monarch and it is not working
correctly. No word back from them yet. Placed orders for different supply
items. Still working on maint. contracts.
- Worked
on a number of DCC issues. Assisted Mike on some problems that he was
addressing as well as a couple of other requests that I had
received. Presently, we are trying to keep the current system running
until the new DCC system is implemented. I don't want to have to do a
rebuild and then a month later do another one.
- Working
on cleaning up accounts. Still have over 100 accounts to go through and
clean off of the system. We've made a dent. Along the same lines, a home
account system was repaired over the weekend. We are purchasing a replacement
disk system since the one we are using is rather old and doesn't
allow for hot swaps.
- Worked
a number of web issues for different people. Most were file link
issues.
- Helping
Keith with some of the logistics for the upcoming mtgs. at MIT.
- Assisted
the E2E group with a couple of computer issues. Both h/w and environment
problems were resolved.
- Worked
a number of e-mail issues for different people, setting up vacation
messages, restoring lost e-mail and cleaning up of e-mail issues
on client boxes. We've a number of people with large mail boxes (over
500MB) which do need to be cleaned out. Worked the spam filters and
related issues.
Mail Statistics for May 18 - 24, 2006
|
Mail Statistics
|
May 25, 2006
|
|
Rejected Messages
|
25,267
|
|
Virus Messages
|
1,805
|
|
Accepted Messages
|
26,728
|
|
Total Messages
|
51,995
|
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Systems,
Management
Systems
from Dennis
Coyne
See also:
AdL Systems web page
AdL
Systems email archives
Records
Of Decisions or Agreements (RODA) status web page
Working on preparation for the upcoming NSF review of AdL
costs, schedule & planning.
See comments from
Mike Smith & Chris Echols regarding optomechanical
layout work under AOS/layout.
Modeling and Simulation
Hiro Yamamoto
Static (Stationary) IFO Simulation (Hiro,
Melody)
The framework and basic objects are getting ready. By the middle of June, a FP cavity simulation
will be available. About the adaptive
grid size technique. The concentric cavity has a very small waist size. To use
FFT for that kind of case, i.e., the beam size changes substantially as it
propagates, it was argued that the grid size needs to be changed. It was not
clear if this treatment is necessary if the intermediate state is not observed,
i.e., starting from ITM with beam size of 6cm and observing on ETM with same
beam size. An explicit calculation showed that the adaptive grid size technique
is important. With 70cm window size, and 128 grids, the error propagating from
ITM to ETM is completely negligible if the calculation is split into two, ITM
-> center, center -> ETM, and the adaptive grid size technique is applied
for each. If the calculation is done in one step without using adaptive grid,
larger error is observed. The error becomes larger as the beam spreads more to
outer side. E.g., LaguerreGauss(3,3) mode, the error
is ~0.1% per trip without using adaptive method. Using adaptive method, the
error is essentially the numerical accuracy.
Higher order modes which tends to spread wider are more problematic for
PI, so the use of adaptive technique is important.
QuadFP (Osamu, Hiro,
Mark)
A setup simulating an Adv.LIGO arm cavity,
consisted of two double chain quadruple pendulums sitting on a BSC chamber with
a design performance, has been tuned up to be ready to study the ISC design,
especial the transient stability and other effects from the low power lock to
the full power operation. A use of different coordinate systems between e2e and
that used for the quad pendulum statespace introduced
an inconsistency problem, which is fixed now.
After Elba, we will look into the
details about the requirements.
One issue is that ITM pitch tilt is induced by the radiation pressure force
by the amount of several micro radian, and this needs to be corrected without
actuating the test mass itself. Another issue is how serious the yaw
instability is with descent LSC is working.
quantum noise in e2e (Hiro)
e2e implements the radiation pressure noise and shot noise separately using
the photon counting. Discussions with Somuya and
others motivated to study the more explicit implementation of the quantum
noise in e2e so that the readout scheme
can be simulated. The idea is the
injection of vacuum field from the dark port.
The first trial shows reasonable magnitude of radiation pressure noise is
observed, while the shot noise is 1000 times smaller. But this is a promising
start.
alfi : GUI of
e2e (Melody, Bruce)
Visual graphical comment is being added in alfi,
which corresponds to text comments in text oriented programming.
And alfi
is being updated to make it more robust and to fix bugs.
Vacuum Compatibility
Vacuum Preparation & Residual Gas Assay (RGA)
See also the Vacuum Bake Lab
Bob Taylor
- I
have baked the Stepper motor and will scan it on Friday. It began cooling
this afternoon.
- I
finished the bake job for Ken Mason and shipped the view ports to MIT.
High-Irradiance, Contamination-Exposure Cavities
Lee Cardenas, Liyuan Zhang
Cavity # 1: OTF Lab. at W. Bridge: No Change.
The new sample wire used for in-vacuum cabling is still in the chamber. The cavity is locked and we were taking
absorption and total loss (ring down) measurements every day. Total test hours
>1728. Can be replaced when another sample is available. Electronic noise is coupling to the laser
signal. The laser signal is not stable
and it goes out of lock often. We are
checking the noise background from the electronic equipment that are attached
to the laser signal to discriminate the source.
Cavity #2: Design for the laser enclosure is under way for both locations,
the OTF and Lauritsen Labs.
Cavity #3: OTF Lab at Lauritsen Room 38: No
Change.
The flex circuit material is in the cavity.
The cavity is locked and we were taking absorption and total loss (ring
down) measurements every day. Total test hours >2136. Can be replaced when
another sample is available.
Scatter/Absorption Test Measurement prototype In standby mode.
Finishing up for the
review.
Seismic Isolation
From: Ken Mason <kmason@ligo.mit.edu>
BSC Seismic Isolation Construction
We have recieved 22 of 31 parts from Limerick Machine. 5 are
scheduled to be delivered today and the remaining four are scheduled to be
delivered 5/31. Limerick is driving parts to
us as soon as they are off the machine.
Finite element analysis of
the blades verify the deflection results Rich Mittleman
is getting with the spring test fixture. Both the test fixture and FEA show the
blades 15% softer than the solid model. We are designing various shims to
compensate for this.
Plates have been designed
to hold geophones without pods on the seismic structure for testing and to
simulate the mass of the pods.
From: "Joseph A.
Giaime" jgiaime@ligo.phys.lsu.edu
Agenda for the weekly SEI
telecom Friday, May 19, 2:00 pm Eastern, 1:00 pm Central, 11:00 am Pacific time
BSC SEI status
- Parts for stages 0, 1 and 2
received and assembled on LASTI test stand. See today's LASTI ilog entry.
- See SEI log entry 621 for
list of all parts, including the ones still expected.
- Soft Aluminum sensor target:
vender will meet 0.0002" flatness, but we will allow best effort on
the mirror finish we specified.
- May needs more Fluorel cable clamp inserts.
- Will send pod components for
one GS-13 to Dave at LASTI.
- LLO now has one of each kind
of pod harness, and will test assemble.
- Stanford will send
high-current coil driver to Rich for modal testing.
Stanford: seismometer,
platform
- Matt installed four vertical
witness L-4Cs on optics table of platform.
- All stage 1 loops, plus stage
2 damping loops closed. Pitch and roll loops designed and will be
tested. These new loops will take advantage of the higher moment of
inertia and retune the notches.
- Stanford platform witness
seismometer to be swapped out so that all low-power STS-2's will go into
pods for the prototype.
- Tarm continues to work on his
seismometer experiment.
- William is building a second dSpace machine for seismometer work.
From: Ben Abbott
<abbott_b@ligo.caltech.edu>
SEI:
Virginio and I finalized the plan for the
LVDT Driver.
I am still gathering ISI
coil driver information.
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
Working on the SUS cost
and schedule back-up information for the NSF Review. Worked with Norna, Dave Ottaway and Calum this morning on sdchedule
information
From: "Mark Barton"
<mbarton@ligo.caltech.edu>
This week I brought up to
date the damping and thermal noise code in my model of the AdvLIGO
quad noise prototype, incorporating all the noise sources and parameter values
from Bench v4.1. I was then able to confirm independently a result that Geppo Cagnoli had derived from a
somewhat simpler model.
For default values of loss
as in Bench v4.1, the thermal noise is not quite 10^-19 m/rtHz
at 10 Hz but it asymptotes very quickly to the f^-2 line through that point.
(The excess noise in this case is from sidebands of the vertical resonance at 9
Hz, via an assumed vertical-horizontal coupling factor of 10^-3.)
However if the loss at the
metal wires in the stage above the fibres is 10 or 30
times greater, as from the use of machined maraging
wires (with drum heads for easy clamping) rather than drawn carbon steel, then
sidebands of a horizontal mode at 3.4 Hz become visible and asymptote rather
slower. It's not a huge effect but together with some other difficulties with
the maraging proposal it makes it not worth pursuing
for the moment.
From: Ken Mailand kmailand@ligo.caltech.edu
I sent to LASTI quad
fixture drawings to the DCC. I'm
working on a lower quad installation arm concept, and a simpler part that may
be used at the LASTI site, will send out an email for comments and input.
Core Optics
From Gregg Harry (gharry@ligo.mit.edu)
We got preliminary results
from a nanoindenter measurement on a 4.65 micron
CSIRO pure tantala coating. The peak Young's modulus was 161 GPa,
compared to the canonical value of 140 GPa we
typically use. This causes a 2 Mpc drop in BNS
range, with all other values held constant. I have yet to talk at length
with the lab that made these measurements, and am not sure this is the final
number. It does illustrate, as always, how sensitive advLIGO
reach is to many of these mechanical parameters that are not as well known as
they should be.
I also have a report from
Steve McGuire and Ed Doomes on the X-ray fluorescence
measurements on titania doped tantala
samples. The titania concentrations are in good
agreement with the other two measurments except for
Formula 3. The Southern group is looking into this discrepancy. There is also evidence of Fe and Cr, which
may be coming from the substrate.
From: GariLynn Billingsley
<Billingsley_G@ligo.caltech.edu>
Input Optics
From: David Reitze
reitze@phys.ufl.edu
AdvLIGO EOMs (Wan Wu, Charles Perry)
We
are still working on an analog intensity stabilization servo. A single pole FIR
digital compensation filter has been designed; looking into the Labview programming details. Also, we continue the work to
nail down the appropriate way to characterize the noise in the demodulated PD
signal.
LIGO upgrade EOMs (Guido
Mueller)
Analyzed
the distortions in a phase modulator with split electrodes. Conclusion is that the
distortion is a quadratic effect (very small) and only affects the spatial
phase modulation distribution; something we believe we can tolerate. Ordered a
4x4x40mm RTP crystal w/o electrodes to test different geometries.
LLO HPTF (Simon Stepuk and Ken Franzen)
- Thermal lensing
effects were measured in new DKDP and TGG crystals in prototype Faraday.
The results reveal that the FI itself produces f=18.7 +/- 2 m thermal lens
at 70 W. The DKDP overcompensate it by 2.5 times; need to thin the DKDP.
- Also discovered that DKDP is
very fragile; it chipped during a very gentle mounting procedure.
- An experiment to determine how
the thermal lens depends on the angle between light polarization axis and
the DKDP axis revealed no strong dependence.
IO Mechanical (Luke Williams)
- Posted the AdvLIGO
IO nonfolded IFO layout to the pdmworks vault. This layout shows all of the
in-vacuum IO components, the main beam, the heating beams, the FI pickoff
beams, the MC pickoff beams, and optical levers on many of the suspended
optics. I will continue to add optical lever beams to the
remaining suspended optics.
- Designing a new breadboard for
the Mach-Zehnder interferometer experiment for
high power operation.
- Designing vacuum compatible
case for the IAP Faraday rotator.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
The full version of Xilinx's software arrived. I am waiting for the licence number in order to activate it. Hopefully
their customer service will be somewhat quicker than their technical support.
Some of AEI's labour hours and costings were clarified to me by Benno. I'm glad that that's sorted out now. My
viewgraphs for the NSF review were modified accordingly.
Auxiliary Optics
From: Chris Echols <cechols@ligo.caltech.edu>
LAYOUT
New HAM and BSC models (SolidWorks native) were created from original prints,
including flange and bracket details: D060142 for the BSC and D060157 for the
HAM. A new pick-off mirror bezel and related conceptual assembly were created
(D060131), as well as a conceptual configuration showing the ETM Telescope. A new
top level Advanced LIGO layout was created (D060169) that includes the vacuum
equipment layout and the optics layout.
From: Michael Smith <smith@ligo.caltech.edu>
LAYOUT
Data
from Zemax was extracted to create an Excel table
summarizing the positions and normals of the COC
mirrors and ray vectors for the principal ray paths--for inclusion into Coyne's
T010076-01 specification.
NSF Presentation
Final preparations for Cost/Schedule
presentation are underway.
Controls, Data Systems
From: Rolf Bork rolf@ligo.caltech.edu
- Finished installation of PCI-X
based controls for Hepi at Lasti
last week. We also incorporated a couple of change requests:
- Added a watchdog to the quad
suspension controls, similar to that done for suspension systems in Ligo. This state of this watchdog is also transmitted
to the BSC Hepi controls as part of its watchdog
system.
- To allow Mittleman
to use his DSpace system for adaptive filtering
tests on Hepi, the Hepi
code was modified:
- Two spare inputs are setup to
receive analog signals from DSpace and insert
these signals into the BSC control chain.
- The BSC geophone signals are routed
through the HAM X Hepi outputs to provide these
signals to DSpace (HAM X Hepi
is not presently being used). Jay is putting together an adapter module to
convert these signals from the normal 50 pin D connector to BNC jacks
(ready next week).
- We fixed the problem with AWG
signals noted after the installation of the Quad controls (one cycle drop
out every 2.5 sec). This turned out to be a problem with the AWG timing
algorithm.
- Work has begun to upgrade the
CDS infrastructure (Framebuilder, AWG, etc) to
run at higher sample rates than the present system max of 16KHz (adding
capability for 32KHz, 64KHz and 128KHz). Higher rep rate requirements are
coming from the Ponderomotive Experiment and the
Output Mode Cleaner tests.
- Starting to assemble a by chamber
and by subsystem channel count. We
need at least a ballpark figure in order to help us determine CDS
equipment locations, module densities and other infrastructure issues. I
hope to have a spread sheet put together in about 2 weeks.
From: Jay Heefner jay@ligo.caltech.edu
LASTI
- Beginning production of
Anti-Alias and anti-image chassis for Ponderomotive,
AdL SEI ISI and HAM SAS systems.
- Gathering coil drivers and
satellite amps needed for Ponderomotive experiment.
- Beginning system layout
drawings for Ponderomotive experiment.
LASTI and 40M
- Built and tested a prototype
for the tip-tilt PZT mirror driver needed for both the Ponderomotive
and and OMC controls.
For additional information about this report, contact Stan Whitcomb or Phil Lindquist