Weekly Report for
Week Ending May 18, 2006
The LIGO Executive
Committee Agenda for Monday,
May 22, 2006 will be:
(Meeting time: 10:30 am Pacific Time)
1. Announcements
2. Comments
on Weekly Report
3. LSC
Issues (Saulson)
4. LIGO
Lab Operations
- Administration
(Lindquist)
- Sites
(Raab, Zucker, Shoemaker)
- Commissioning
(Fritschel), Detector (Coyne)
- Campus
Research Facilities
- 40
Meter (Weinstein)
- TNI
( Libbrecht)
- LASTI (Shoemaker)
- Data
Analysis and Computing (Lazzarini)
5. R&D
and Advanced LIGO (Shoemaker)
6. CHANGE CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION AS
NEEDED
Special Items:
- Preparations for
Advanced LIGO Review (May 31 – June 2)
- LIGO Organization
Chart (Executive Session)
Special Announcements:
Weekly Report Highlights
No report.
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
SITE TELECONFERENCE (Lindquist)
- There
was no site teleconference Thursday, May 18, 2006.
- There
are currently no open action items.
The list of assigned actions updated through December 01, 2005 (the
last update) will be found Here.
PROPERTY MANAGEMENT (Luna)
>
- Provided
assistance to the Detector Group (H. Armandula)
with Packing and shipping of a metal test mass (LASTI Mode Cleaner) to
Stanford (N. Robertson) Account Number LIGO.SUS - 5.10 - NSFLIGO.FY02ON.
- Provided
assistance to Barry Barish with packing and
shipping of an LHO poster to FERMI Lab.
Account Number BCB.40145-1-ENDOW.401450.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- Continued
to sort/refile those "P" documents
that were extracted from the shelves for electronic scanning.
- Scanning
- Progress continues on scanning of contract closeout files.
- Activity:
|
Week Ending
05/18/2006
|
In
|
Out
|
|
Packages
|
28
|
6
|
|
Faxes
|
20
|
15
|
FINANCIAL SYSTEMS (Cronin, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Routed
the Exploratorium change order for the exhibits in Group C for review and
approval. Change order #5 will be
issued once change order #4 has been approved and returned.
- The
6-month funding allocation was submitted to MIT.
- Submitted
purchase orders for the sites which included the $20K order from CDW for
the computer system for Hanford.
- Working
on charges received from JPL for Raytheon.
>From: Florence Kaufman <fkaufman>
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- Two
modifications are being issued to the contract with the Exploratorium on
the Outreach Cooperative Agreement.
The first, Change Order No. 4, allocates $128,000 to cover the
final group of six exhibits, Group C.
The second, Change Order No. 5, allocates $145,000 to cover the
remaining support for all exhibits.
This brings the total allocated for exhibits and supplemental work
to $885,000, the amount contained in the Exploratorium proposal.
- The
prototype for the kinetic facade for the LLO SEC has been assembled at HPD's facility in Boulder, Colorado. It will be inspected by LIGO personnel
next week.
- Slippage
of the schedule by the Limerick Company in the development of the seismic
isolation system prototypes for Advanced LIGO is being examined regarding
the causes and possible recovery.
PROPOSALS and REPORTS (Lindquist)
- Advanced
LIGO—incorporated edits into the Cost Estimating Plan and returned to
the Project Group.
- Operations
Annual Report—prepared a proposal for assignments for contributions
to the Annual Report for Operations. Will distribute. Requesting inputs by June 23.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- A Staffing Committee meeting was held on Monday.
The minutes and action items from the meeting are in progress and when completed
will be posted on the SC web page.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
Nothing significant to report this week.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of S5 Activities at LIGO Hanford Observatory
(compiled by K. Kawabe)
Another week of good running. Duty cycle of H1 was just 85% this week, with typical
inspiral range of 13+ to 14+ Mpc
(15 Mpc was reported once). Duty cycle of H2 was a
bit larger than 83%, with typical range of 7 Mpc.
Highlights from the elogs:
LIGO Livingston Observatory
(LLO) and Interferometer Operations (Zucker)
LLO Science Education
Center Kinetic Art
Project (Romie)
On May 23rd, we will go to Boulder
to see and review the prototype. They are working this week on defining the
position of the winches for the lock-down mechanism, so as not to hit the lamps
in the gallery area. Charlie Danaher just circulated a number of views of the
locking mechanism. Our regular weekly meetings with HPD & Exploratorium are
Thursdays at 2pm Central.
Initial LIGO Detector Science & Engineering (Coyne)
CDS
see weekly commissioning minutes in the commissioning archives
DMT
John Zweizig
Last week I worked on a
new release of the DMT software. This changes arevmostly
to support reading and writing FrStat structures in
frame files. This will pave the way for
implementing a new Calibration frame format. Software to read and write a prototype version
of this calibration format is also being implemented to test that the FrStat support is sufficient for this purpose.
Scattered Light
See Bill Kells’ report on optical scattering
in last
week’s weekly report for Advanced LIGO.
40-Meter Interferometer (Weinstein)
IFO Commissioning
- Rob,
Rana and Sam have made considerable progress in
lock acquisition. They have cleaned up many of the LSC PD signals,
adjusting phases and gains, matching the 133 MHz and 199 MHz signals, etc.
The DRMI now locks in only a few seconds.
- With
the DRMI locked on just the single demod signals
(REFL33_I, REFL33_Q, and SP166_I) they can easily explore the full space
of double-demod signal phases to optimize
signals for each DRMI degree of freedom. They can then hand off the
controls to the optimized double-demod signals
in preparation for adding the arms.
- Starting
with a locked DRMI, they offset-lock the arms using the DC transmitted
signals, and tune up the RF signals. They can then switch to the RF
signals for DARM and zero that offset. The full IFO is now locking well
and robustly and there is some confidence that the signals are well tuned
up and understood. Up next is more CM servo work
and reducing the CARM offset to zero to bring the carrier to full
resonance in the arms. So far, they have been able to re-establish the
digital common mode servo, and the fast AOM path was also briefly, apparrently successfully, enabled.
- Rob
developed the autoalign scripts, adding one for
the SRM mirror. There is now an alignAll script
which automates the alignment of the entire IFO.
- The
input MC reflected beamline and LSC diode is now
on the AP table (much shorter beam path) and works well.
- Dan
and Rana have set up the MC WFSs
on the AP table with 45degree mounts, and Dan is positioning lenses for
the correct Guoy phases (modeled by Monica) and
pickoffs for the correct amounts of power on each of the WFS heads.
IFO Modeling
- Osamu
continues to develop his e2e model of 40m and AdLIGO,
his analysis of the AdLIGO length sensing noise,
and development (with Kentaro) of alternative AdLIGO length sensing schemes.
DC Detection and Vacuum Squeezing Development
- Rob
and Sam have aligned the in-vac DC readout beamline that will go in the vacuum, using a crystal
laser, and they are now switching to an NPRO (borrowed from the TNI) so
that they can lock the OMC with it. They are adding the PZT steering
mirrors onto their alignment chain. They may be ready to disassemble the
system for cleaning and baking as early as next week.
- The
DCPD Satellite box is now successfully tested by Ben, and is awaiting
front and back panels to arrive early next week.
- Rob
is specifying the correct alignment of the DC PDs
in their mounts so that Ben can do the final machining on the DCPD head
mount.
- Ben
continues to work on the QPD whitening board layout.
- Jay
continues to work on the OMC PZT driver board and the steering mirror PZT
driver board.
- Bob
got in some cable so we can pre-make the cabling for the DC readout
controls.
- Vacuum
windows for the OMC reflected and transmitted beamlines
are being baked out by Bob.
- Go
and Osamu continue to work on the squeezer. With 1.5 W into the SHG, it
gets hot, and the SHG cavity becomes unstable. They lowered the oven
temperature, and the cavity became stable, delivering up to 400 mW of green light continuously.
- Go optimized
the alignment of the OPO cavity using the seed beam, and did a temperature
scan to find the largest amount of green light from the OPO operated as a
SHG. He then aligned the pump beam into the OPO. He is now trying to get
some parametric gain in the OPO. converting one
green to two IR photons.
PSL
- Several
laser tripoffs in the last month have been
traced to user error with the PSL enclosure. Everyone is now fully aware
of the care that must be used to avoid having the PSL enclosure trip off
the laser inadvertently.
- Steve
will arrange to have the PSL enclosure interlock changed so that it only
shutters the MOPA laser, not trip off its power. This should help to avoid
tripoffs that could damage the laser.
- In
addition to tripoffs, the MOPA head temperature
wanders and the temperature servo is unable to stabilize it. Steve
believes that this is due to temperature excursions that are accompanying
the squeezer work being done on the PSL table, stressing the ability of
the MOPA temperature servo to maintain head temperature stability. Steve
will consult with Peter King and other experts on what to do about this.
Electronics, Controls, Computers
- Rana replaced the ETM and ITM suspension controller
violin mode 1st (2nd?) harmonic (884 Hz) notch filters with 4th order
Elliptic Bandstop filters, which work much
better.
- Rana noted that many of our EPICS channels have names
that are non-standard, look nothing like the naming conventions used at
the sites, and don't match front-end names. He has renamed a large number
of channels in the LSC system.
Lab Infrastructure
- Steve notes that the particle counters are
recording extremely high values, presumably due to the weather. He'll keep
an eye on it and keep the HEPA filters running as often as possible.
Thermal Noise Interferometer (Black)
This week we ran into some trouble with the
mode cleaner. The OSEM controller for the input mirror is acting up. It is not
damping the yaw motion to spec, and the side magnet of the output mirror is
also exhibiting excess motion. We are in the process of correcting both of these
problems.
LASTI (Ottaway)
No report.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Yamamoto)
Adv.LIGO FP (Osamu Miyakawa,
Hiro Yamamoto, Mark Barton)
Using the FP model with quad suspensions, ASC scheme is being
investigated. In order to have the test
mass to be pitch free when strong ration pressure is pushing the mass (not
torque, linear force induces pitch because the mass is suspended) to tilt 4.7 micro
radian, the top most mass should have finite pitch in opposite direction with
almost the same magnitude, -4.3 micro radian.
So some kind of alignment sensing is needed to control the test mass
pitch using the top mass.
There was confusion about the yaw dof, and a few
bugs were identified and fixed. Still some results are to be digested before
yaw control is achieved.
Static IFO Simulation (Hiro Yamamoto)
Adv.LIGO version of FFT-like simulation tool development -- still building
fundamental building blocks and doing validation.
Simulation engine code (Bruce Sears)
Finished (1) modifying the input code to skip efficiently sections related
only to graphical front end and (2) implementing the output control scheme
using a template file to organize and reduce unnecessary output data.
ALFI (Melody Araya)
Continuing with the ALFI enhancement to have "comment" notes in an
edit window. Currently
working on sizing and moving the widget.
Data Analysis Activities (Lazzarini)
Brown:
- Worked
on S4 ringdown analysis pipeline
- Continued
with review of BBH inspiral S3 analysis
- Worked
on LISA supermassive black hole analysis with
Tapir group
- Updated
BNS glitch pages at observatories so that they glitches which do not have
an associated DQ flag are highlighted
- Provided
segment database support to Igor and Ben
- Gave
talk at Riverside
Community College on
LIGO science
Mendell:
- StackSlide jobs have finished at LLO with the final S4
L1 results. Jobs are running at LHO
and should finish with a few days.
The results will be incorporated into the S4 PowerFlux,
StackSlide, and Hough paper, and presented at
the June LSC meeting at MIT.
Shawhan:
- Provided
comments on a draft of the astrophysics section of the Advanced LIGO
Project Execution Plan.
- Completed
generation of out-of-lock, light dip, and overflow data quality flags
through May 2.
- Did
a study of the "safety" of the light dip and overflow data
quality flags using hardware injections.
- Worked
with Erik Katsavounidis to draft a Charter for
the LSC Burst Analysis Group.
- Started
writing the first draft of the S4 LIGO-only untriggered
burst search paper.
Sutton:
I've spent most of my time on coherent analysis issues and the Xpipeline analysis package.
I used Lazarus black-hole merger results from Leo Stein's thesis to show
that the coherent consistency test we detailed in gr-qc/0605002 works quite
well for two-polarization GWBs. I've been profiling and optimizing the
sky-map function for Xpipeline. I found a way to partially vectorize the "for" loop over sky positions to
cut the analysis time by 40%. I edited
Stephen Poprocki's SURF project proposal on searching
for black-hole mergers with Xpipeline. I'm currently working on my coherent analysis
talk for the GWADW meeting at Elba and a bursts talk for my visit to Benevento
next week.
Yakushin:
- Planning
the work with my summer SURF student;
- Together
with Sergey debugging some problems with LIGO-GEO simulation using
coherent waveburst.
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS
Work continues on supporting 64-bit compilation of LDAS for Solaris 10. The
Build rules for TCL/TK 8.4.12 have been modified and are under testing. The
previous situation where the peername of a socket was
not being returned has been corrected with the modification to the build rules
of TCL/TK. This still leaves BLT and the
globus toolkit yet to be compiled 64-bit.
The effort to make the diskcacheAPI not hang when
performing an lstat on a hung NFS file system
(PR#3015) did not scale to ldas-dev. This will need
further investigation to understand why the modified code possibly caused jobs
sent to the diskcacheAPI to timeout.
The system tests on ldas were done using version
1.8.178. Job rate performance has dropped significantly. Network traffic is
being investigated as a possible cause.
TCLGLOBUS
Version 1.0.0 of TCLGlobus was officially released
this week. This includes the RPM package for the lscsoft
which is based on LDG 4.0.
The major effort continues to be the Workflow GUI tool. There were many fixes
to the logic behind the buttons as it has started to be tested internally.
GRID COMPUTING
Added staff member to grid-mapfile
for testing the LIGO work flow planner.
Upgraded to VDS 1.4.4 on submit host.
Added preference items using cascading menus and tabs to
GUI specification for the LIGO Work Flow Planner. Assisted Mary and Michael
on integration issues with Virtual Data System (VDS) components and inspiral pipeline examples. Began
testing partially completed functionality of the LIGO Work Flow Planner on the
OSG ITB.
Monitored some of the OSG Support
Center meeting via VRVS
conferencing system.
Determined that the Burst Analysis team needs more time to
complete a release of the analysis for use in the LIGO Work Flow Planner.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Normal
S5 tape ingestion stuff.
- Helped
Greg with re-adding SFTs to CIT's
collections.ini and adjusting LDR queue depth (ongoing).
- Got
lots of Sun replacement hardware.
Many T3 power supplies, 3510-10 chassis and 3510 disks.
- Worked
with Sun enginner John Higgins to find the root
cause of 3510-10's strange behavior.
We've got it narrowed down to disks.
- Restarted
globus-gridftp-server on ldas-cit. Two child processes were still hanging
around, but the main process had died at some point.
- Fixed
(either cleared and restaged or recopied from sites) damaged files at CIT.
- Followup work on LLO upgrade, mainly a problem with a
tape that had failed to label.
- Unstuck
non-staging files on CIT gateway (by staging them on dataserver). A umount/mount of /archive is in ldas-cit's
future.
(Phil Ehrens)
- General
grid cert support tasks.
- Updated
Fedora Core 4 on machines m9, m27, m28, m90, m94, and couch. Wrote script
to automate a set of configuration tweaks for desktop machines and to run
yum update.
- Diagnosed
strange behavior of globus enabled processes
which causes all shared objects related to globus
to attempt to search /home/condor for dependencies.
- Installed
utility in /ldcg_admin/log_mon for dumping BIOS
configuration information as reported to OS at boot.
- Various
cluster maintenance tasks.
(Erik Espinoza)
- Upgraded
the LDAS-CIT cluster BIOS version and enabled ECC scrubbing. This significantly increased the
stability of the cluster nodes.
- Enabled
condor QUILL service but there are problems with
this.
(Stuart Anderson)
- Upgraded
to Condor version 6.7.19. This allows the setting of a few default cluster
configuration settings for users. Initially just WantRemoteIO
is set to False.
- Enabled
condor setting to prevent permanent allocation of cpu resources to individual cluster users.
- Reported
a segfault problem with condor QUILL.
- Installed
the first DMT offline RPM build from Junwei Cao on the LDAS-CIT cluster.
- Upgraded
LDAS-CIT to LDG version 4.0, both 32- and 64-bit versions from Junwei Cao.
- Received
3 more equipment racks and installed in 215 Synchrotron.
- Reported
slow kernel response to deleting a large list of files to Sun.
- Staging
additional data into the cluster for parallel access (All LIGO minute
trends, S5 second trends, SFT files).
MIT
(Keith Bayer)
- Condensation
pump servicing wall mount
sayno
a/c units failed.
- Ordered,
received, and replaced pump
- Dataserver V880 panic'ing
with memory troubles sun called (Case 1045484) and will be onsite to swap
memory tomorrow.
- Replaced
failed hdd in cluster node45.
Livingston
(Igor Yakushin)
- 3510
firmware was upgraded.
- SAM-QFS
was upgraded on dataserver and gateway;
simultaneously Lisa and Dwayne upgraded SAM-QFS on fb1; if no problems
with the upgrade are found, we will upgrade SAM-QFS on fb0 during the next
Tuesday maintenance period.
- Studying
Q-replication documentation (segment database is using Q- replication).
- There
were occasional network problems observed in the LDAS network. It is not
clear yet what causing them and whether they still present after dataserver and gateway were rebooted this Tuesday; if
this problem continues, we might have to powercycle
the LDAS network switch.
- LDRed WNB1B_BN_S5 burst MDC frames from PSU to CIT.
(Dwayne Giardina)
- Ejected
tapes for shipment to CIT and imported and labeled new tapes, problems
arose with a drive during labeling. Dan fixed the issue with the tape
drive and I was able to continue.
- Samfs upgrade on FB1 with Lisa.
- Worked
with Ben to get trend publishing, realtime
frames publishing, Disk2Disk scripts, and createRDS
monitor scripts restarted and working correctly after Tuesday maintenance.
- Continued
working on a ganglia replacement to monitor our cluster statistics, made
some progress on Monday, but haven't had time to do more.
Hanford
(Greg Mendell)
- SFTs generated from h(t) for
the pulsar group have been published at LHO and LLO between Dec. 17, 2005
and Jan. 31, 2006. Most of these
have transferred (or are in the process of being transferred) to CIT and
then to AEI via LDR. The SFTs can be found using
LSCdataFind, using 1_H1_1800SFT_hoft,
1_H2_1800SFT_hoft, or 1_L1_1800SFT_hoft with the -type option. The 1800
refers to the fact that these are 1800 second SFTs.
Work on generating SFTs for the other S5 times,
and how to generate and transfer 60 s SFTs is
underway.
(Ben Johnson)
- Brought
up several nodes via kickstart. Everything
essentially works.
- CRC
mismatch scans completed on Monday. Completed initial write-up of results,
and I am on to stage 2, finding out which channels were affected by the mismatches.
- Sent
LDR PR fix priorities to Kevin and Brian.
- Replaced
bad disk on t3-23.
- Finished
initial lscsoft-user-env cleanup utility, in perl. I need to figure out how to incorporate it into
the current sh/csh scripts.
General Computing (Wallace)
MIT
(Keith)
- Rebuilding
hacked windows lab pc that was offering anon ftp
- Received
backup server w/ AIT4 tape drive
- Working
on integrating stunnel into new mailserver/fileserver
Livingston
(Dwayne)
- DNS
entries added for CDS
- KVM
trouble in control room for Allen's computers - replaced Sany's old PC with new one, old hard drive in an
external case so he has access to old files
- security
server Windows updates and reboot - logs on new loghost
were growing rapidly, turned of
named query logging, did a little cleanup (i.e. zipping old log files) -
www.ligo-la.caltech.edu is now hosted on a different machine. we no longer
have ~{user} websites on www.ligo-la.caltech.edu. They are still available on alix for now, and should soon be available on touro. I was attempting to find a way around this and
ended up temporarily removing shared /home accounts from GC machines. Shannon
pointed out my error and corrected it.
In the long term, we want to find an alternative to the ~{user} websites.
- minor
assist to Shannon troubleshooting
auditorium audio system problems
- still having some issues with site gates and the kantech security server.
- applied
latest Solaris patch cluster to touro, going to
configure it to serve user websites
- created
new GC account for user
- other
usual user requests and support
Hanford
(Christine)
- The
Sun computers Larry ordered for me through the Sun matching grant
arrived. I have 5 new computers to
set up.
- The
PR for the new disk and tape backup systems has gone through, that
hardware should be showing up soon.
- Shipped
a new laptop to Daniel at MIT. The
laptop he originally took with him has died several times and Dell has
been unable to permanently fix it.
CIT
(Christian)
- Millikan - Replaced toner cartridges on HP 5500
printer.
- Created
a backup of Rod Luna and Ed Jasnow workstation.
- Rich
Abbott - Configured new laptop with the standard Ligo
image for Rich.
- Worked
on the Spam Filters with Mike and Larry.
- Continuing
working on updating all of the visitors' workstation this week.
- Worked
with Mike on getting backup images burned to DVD.
- Worked
with Larry in removing some of the old monitors.
- Reloaded
laptop that was returned to the loaner pull this
week.
- Other
misc.: Continued onsite software/phone support.
(Veronica)
- LIGO: An ongoing work on the website for the
Advanced LIGO NSF Review. Updates
of the LIGO website. User support.
- LSC: Updates of the database of the technical
papers. Addressed a few mailing
list related issues. Updates to the
presentations of the past meeting.
Dealt with a failed hard disk on one of my machines. The replacement was DOA so took some
troubleshooting; now loading the s/w, hope to have it back up and running
shortly.
(Bruce Sears)
- (BS)
iLog Maintenance: (0.5 days) General iLog
maintenance (user adds, keyword adds, etc.)
(Mike)
- Testing
Microsoft's critical updates with GC and engineering software. All have
passed. I spent time updating all NTSRV's with
this series of critical updates.
- Worked
on documentation for PDMWORKS installation and backup process.
- This
week there was a lot of work on the mail servers. Clamd
seemed to be having problems. Multiple clamd
processes were started which stops the out going mail from working. We
have updated the clamd software and are watching
the servers closely. So far everything
seems to be working ok.
- Surplus
some old computers/monitors that had hardware problems.
- Cleaning
up our ghost backup server, to free up some disk space for end of month
backups. Burning old ghost images of NTSRV's to
DVD. Christian gave me a hand with this, by using his DVD burner as well.
- DCC
issues: The database needed to be compacted. Users were not able to get
in. After many reboots and killing processes, I was able to compact the
database which enabled users to login.
- Spam
Filters: Ongoing work searching for false positives, and adding additional
rules.
- Other
additional onsite user support, plus some work cleaning-up, and labeling
network cables in the Bridge Annex server room.
(Larry)
- Worked
a number of procurement issues. Reconciled last months
p-card. Delivered a number of items
out. The USB pocket drives have become popular for those that travel, we
will need to get a few more of those units. Tracking down a couple of orders. Our
SUN order should be arriving soon and a couple of Dell items are still on
back-order. Presently, working on another procurement from SUN. Assisted a couple of the other groups on
getting their procurements started.
- The
computer system sent to Monarch for repair has been returned. Hopefully, we will be able to check it
out in the next couple of days.
- Working
on getting things ready for the SURF students. This includes removing the
old SURF accounts. Along the same
lines old unused accounts are being looked at and listed for possible
removal in the near future.
- Worked
on the mailservers. The clamav
has been having problems. It has been updated but we are still keeping an
eye on things. We've had a couple
of good sized spam storms which has also been causing some concern.
- Worked
on a couple of network switch issues. The problems appeared to have been
caused by bad cables.
- Worked
a number of printer issues. Including resetting the printserver.
Most of the problems were caused by a couple of print files requiring the
wrong size of paper.
Mail Statistics for May 11-17, 06
|
Mail Statistics
|
May 18, 2006
|
|
Rejected Messages
|
29,231
|
|
Virus Messages
|
2,060
|
|
Accepted Messages
|
25,280
|
|
Total Messages
|
54,511
|
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Systems,
Management
Systems
from Dennis
Coyne
See also:
AdL Systems web page
AdL
Systems email archives
Records
Of Decisions or Agreements (RODA) status web page
Working on preparation for the upcoming NSF review of AdL costs, schedule & planning.
Vacuum Compatibility
Vacuum Preparation & Residual Gas Assay (RGA)
See also the Vacuum Bake Lab
- I
received word from Jannen that they need a new
set of cables for the Quad SUS at MIT (Brett). I am just about done with
the first three and I am waiting on some more Cooner wire to build the other two. If
it comes tomorrow I will be able to complete the task and ship to cables
on the 15th. [The cables were finished by the 17th.]
- I
have built the temperature controller for the bake out of the stepping
motor. I am continuing to work on the oven that I will be baking the
stepper motor in; this should be complete by Friday. I will begin the bake
on Monday the 22nd. . I would like to be around (
present in the lab) for a least the first 8 hours of the bake to
make sure the electronics is functioning properly and for safety. [The
stepping motor is used by the HAM-SAS system and may have application to
other AdL systems.]
- I
received two view ports from MIT that I have cleaned and am baking.
High-Irradiance, Contamination-Exposure Cavities
Lee Cardenas, Liyuan Zhang
Cavity # 1: OTF Lab. at W. Bridge: No Change.
- The
new sample wire used for in-vacuum cabling is still in the chamber. The cavity is locked and we were taking
absorption and total loss (ring down) measurements every day. Total test
hours 1728. Can be replaced when another sample is available.
Cavity #2: nothing new
Cavity #3: OTF Lab at Lauritsen Room 38: No
Change.
- The
flex circuit material is in the cavity.
The cavity is locked and we were taking absorption and total loss
(ring down) measurements every day. Total test hours 2136. Can be replaced
when another sample is available.
Scatter/Absorption Test Measurement prototype In progress!
- Dr.
Zhang has completed the scanning of the 4ITM07 mirror for the influence of
the particulates on scattering. The test was performed in two stages, one
when the surface is dirty/contaminated and the
other when the surface is cleaned. We have a witness sample IM04 which has
a nominal absorption of 3.3ppm/cm.
Misc. tasks: the design for the enclosures for the two NPRO'S; one in West Bridge
is in progress. For the one at Lauritsen,
will be looked into to comply with safety. Most likely the enclosure will be similar to
the one for the 60 watt laser in West bridge.
Seismic Isolation
Stage 0, 1, and 2 has been
assembled to the test stand using alignment pins. We are now waiting for
spring, locator, and actuator parts from Limerick Machine.
The design modifications
of the spring tester for the longer stage 0-1 springs has been designed and
sent to a machine shop. The actuator sensor target has also been redesigned to
accommodate availability of material.
From: "Joseph A.
Giaime" jgiaime@ligo.phys.lsu.edu
Agenda for the weekly SEI
telecom
Friday, May 12, 2:00 pm
Eastern, 1:00 pm Central, 11:00 am Pacific time
BSC SEI status
- Complete stage 1 mounted to
stage zero.
- They expect to mount stage 2
next week.
- small actuator parts, locators,
spring ass'y parts still due from Limerick.
- Ken is happy with calibration
fixture design mods for stage 0-1 spring.
Rich will go over Ken's dwgs.
- Weights seem to be coming in
low by a couple of hundred pounds. MIT would appreciate any extra
load cells from HEPI. Joe will look.
- seismometer inventory is needed,
Each of us will inventory our site and submit results to SEI log.
- Brian has prototype of L-4C
readout amplifier and wiring harness. Ben will finalize the design,
including the L-4C version to be sure that we all agree.
- Requirements for 'dirty' test
of the BSC SEI prototype:
- fit check: does it hang
straight, can we carry out the spring mount adjustments to center the
payload?
- modal freqs
of rigid body and stage flex modes.
- tilt-horizontal coupling versus
requirements.
- (Electronic 'LIGO-brand' rack
equipment won't be ready, so we will use dSpace.)
- Need to install and drive one
vertical and one horizontal actuator per stage.
- Need (TBD) geophones per
stage.
Stanford: seismometer,
platform
- Platform work: frame crated
and paperwork underway to ship to the U.K.
- Platform re-balanced,
re-commissioning underway. Ballast moved to outer rim of optics
table, to lower roll and pitch modal frequencies, and achieve better
passive isolation. Stage 1 loops closed.
- Four L-4C vertical witness
seismometers to on the optics table to be used to flesh out data for
coherent noise extraction paper. Also, there are two GS-13s and an
STS-2.
- Matt is almost finished
machining parts to hold down L-4Cs. After they are mounted, then
sys-id for stage 2 can proceed.
- William is setting up second dSpace machine to control 1-Hz pendulum, which will
eventually be used to control Tarm's vertical
seismometer.
- Tarm has finished initial design
of the vertical seismometer experiment, and will begin making parts.
From: Jay Heefner jay@ligo.caltech.edu
LASTI HEPI
- Completed installation of all
electronics hardware and cables for BSC and Y HAM. Initial checkout of all
input and output channels was successful. Testing of controls has been
started and will continue for the next few weeks.
- X HAM electronics are
currently tied up with Laurent's tests. When he is finished, they will be
moved to the BSC racks and tested.
AdL SEI ISI
- Prototype of capacitive
position sensor interface chassis has been assembled and is being tested.
- Internal pod cables and
preamps for GS13s, L4Cs and STS2s are being assembled.
LASTI Ponderomotive
Experiment
- Began collecting and assembling components for controls
From: Ben Abbott
<abbott_b@ligo.caltech.edu>
SEI
I am working with Virginio on the LVDT Driver. We're finalizing a
design scheme. I have begun to gather
the information that I need to start working on the ISI coil driver.
LED Failures
I have gotten the results
from the Eraser Company. I went over them results with Bob Taylor, and we
decided that the best way to go is the Stripping pot method. They are
available at www.eraser.com. Their
part# is AR1221, and they are $1609.00 each. The materials that go with
them are as follows: Dip strip $43.00, Dip Clean $22.50, and Dip Strip
Neutralizer kit $59.50. Bob and I looked at their samples under
magnification, and the result of the chemical strip is a clean, unmarred
surface. I think that the cost is well worth it.
From: Dennis Coyne coyne@ligo.caltech.edu
HAM-SAS
1) Fabrication Status (Riccardo DeSalvo, Dennis Coyne)
- Assembly:
The "dirty" (i.e. not prepared for ultra-high vacuum service)
assembly planned for week of 6/5, will now to be limited to GAS filter
assembly due to welding problems for the aluminum support table. Ric and Dave still plan to visit G&M to assist in
assembling and testing whatever can be done at this time. The schedule is
delayed at least a week. Once the welding plan is settled, then the
schedule will be re-evaluated. Riccardo DeSalvo arrives at Galli
& Morelli (G&M) next Monday. He plans to
assemble 6 Geometric Anti-Spring (GAS) filters (if ready). Ric then goes to the Elba
conference and then back to G&M.
- Welding:
Caltech received some aluminum weld samples from Tecnoinox
for evaluation. Ric and Yumei
sectioned the welds and took photos. A draft report on their findings has
been prepared. While some of the T-joint welds look promising, there is a
clear line at the interface where fusion was not complete. The egg-crate
welds were all poor. Technoinox is trying some
significantly different weld preparations (machining). These weld
preparations are similar to the weld details used by Allied Engineering
for the initial LIGO aluminum structures (drawing D972202-E ). Tecnoinox will test weld this week & send samples
to Caltech for sectioning, photo-microscopy & approval.
- UHV
Clean Testing: G&M (Chiara) will speak
with Eurolab tomorrow regarding FTIR testing of
the UHV-cleaned sample parts. Caltech (Dennis) will send samoe sample FTIR reports to Chiara
for Eurolab.
- UHV
Cleaning: G&M's subcontractor for
cleaning, Paolo Soldi, has completed their
building modifications (not doen for LIGO, but
had to be completed to allow our work to begin). G&M (Chiara) will discuss plans and the possibility of
installing a dishwasher @ G&M for small part cleaning local to the
assembly.
- Clean
room: G&M's subcontracted company is
working on building the clean room. Frasconi
(Virgo) has been helping with project, esp. clean room setup. G&M is
preparing the space (cleaning & painting).
2) LASTI Test Plan (Dave Ottaway)
- MIT
(UROP) student will start in late May.
- We
plan to instrument the floor with 3 Guralp
seismometers (3 axis each) and 6 L4Cs for the table top. All instruments
are on hand or orders have been placed.
3) Simulation & Controls Design (Virginio Sannibale, Valerio Boschi, Yumei Huang)
- A dynaflex model of the HAM-SAS system has been
assembled by Virginio & Valerio.
Dynaflex is a 'toolbox' for Maple that creates a
symbolic dynamic model, which can then be reduced to linear state-space
model (for example to import to Matlab for
control system synthesis).
4) Electronics (Ben Abbott, Jay Heefner, Virginio Sannibale)
- Promec (Gianni) is making cable drawings (incl. strain
relief).
- Jay,
Ben and Virginio will finalize wiring/cabling so
that cabling orders can be placed soon (in-vacuum cable lead times are 6-8
weeks).
- Ben
& Virginio are working on the LVDT Driver to
finalize a design scheme.
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
Bob Taylor got the new osem cables to MIT this morning. I spoke with Dave Ottaway yesterday after the SUS Weekly and filled him in on
the meeting discussion on the quad frequency measurements and damping tests. He
feels sure they can accomplish what we need by June 12th. These results
are needed for the quad review by the UK group.
Working
with Dwight, Carol, Justin, Norna and Dennis on the
SUS cost and schedule presentation for the NSF Review. Provided a
combined cost of each suspension to Carol & Dwight.
From: Mohana
Mageswaran <mohana@ligo.caltech.edu>
I am designing the AdL Satellite Amplifier. And ordering the needed parts
From: Ken Mailand kmailand@ligo.caltech.edu
I'm working on a lower
quad installation arm concept, and a simpler part that may be used at the LASTI
site, will send out an email for comments and input. I'm cleaning up existing
fixture drawings for the DCC. I sent Frédéric Cleva, @ virgo information on our quiet
chiller coolant per his request.
Core Optics
From: Bill Kells kells@ligo.caltech.edu
- reviewed the PI status for
Peter/ Dave O
- Prepared talk for Elba
- participated in the COC
"internal review"
From: Helena Armandula ahelena@ligo.caltech.edu
Advanced LIGO COC
Started
the manufacture of the prototype mirror carrier to be used for the LASTI test
mass.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
After much testing, the Xilinx evaluation licence expired.
Unfortunately I did not get to test the
hardware during this period. The full-blown version was ordered; this
version according to Xilinx's technical support works
for the development kit that we have.
Auxiliary Optics
From: Michael Smith <smith@ligo.caltech.edu>
TCS
A Zemax
conceptual layout of the CO2 laser heater has been added to the SW Vertex
Layout for both the non-folded and folded IFOs. The
CO2 laser heater beam may be occluded by the structure of the Fold Mirror and
ITM combined SUS in the folded IFO.
LAYOUT
The positions of the COC
mirrors for the non-folded IFO were corrected in the Zemax
model to agree with Coyne's T010076-01 specification. ^The solid works vertex
layout is being revised.
NSF Presentation
The Cost/Schedule
presentation slides and back-up supporting data were sent to Carol and David.
For additional information about this report, contact Stan Whitcomb or Phil Lindquist