Weekly Report for
Week Ending May 11, 2006
Due to the LIGO Staffing Committee Meeting May 15, 2006,
there will be no LIGO Executive Committee meeting scheduled that day.
Special Announcements:
Weekly
Report Highlights
Livingston
reaches noise level corresponding to a ten thousandth the size of a proton!
No report (vacation).
LIGO Laboratory Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
LSC MOUs and Research Plans and Progress Reports
SITE TELECONFERENCE (Lindquist)
A brief site teleconference was conducted Thursday, May 11, 2006. The following were among the items discussed:
- The
Livingston Science Education Center (SEC) is holding schedule. The week saw a spate of detector
disturbance because of trenching for the various water lines and the heavy
equipment involved. This is
expected to be completed this week.
- There
are no open assigned actions. The
list of assigned actions updated through December 1, 2005 (the last time
that it was updated) will be found Here.
PROPERTY MANAGEMENT (Luna)
>From: Rod Luna <rluna@ligo.caltech.edu>
- Worked
with personnel at Washington
State University
to finalize the loan agreement for 63 Cluster Nodes and 3 racks.
- Prepared
a list of items that need to be tagged due to Oracle Problems that
affected government purchases from FY'02 to FY'06.
- Provided
assistance to the General Computing Group with the packing and shipping of
2 Laptops and 3 Projectors for the LSC meeting @ MIT. Account Number LIGO.DIR 1.1.1
NSFLIGO.FY02ON.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
- Held
several discussions with various LIGO staff regarding design issues for
the Synergy software. These issues
centered on the overall storage hierarchy submitted documens. A draft has been cut and submitted to FileHold for review.
A meeting is scheduled early next week with Ian Booth of FileHold. We
want to ensure that the document profiles, which contain the fields
required for capture of the metadata, provide the necessary data for the
Synergy software to automatically file the document in the correct location.
>From: Cleveland Mak mak_c@ligo.caltech.edu
|
Week Ending
May 11, 2006
|
In
|
Out
|
|
Packages
|
25
|
12
|
|
Faxes
|
22
|
22
|
- Processed another small handful of revised HAM
drawings from Promec.
- Completed
processing large batch of confidential/sensitive documentation.
- In
the process of sorting/refiling those
"P" documents that were extracted from the shelves for
electronic scanning.
- Scanning
- Progress continues on scanning of contract closeout files.
COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Completed
the purchase of the new Chevrolet vehicle for Hanford, and requested for the check to
be delivered by 5/10/06 so that delivery could be coordinated with the
trade-in of the vehicle. The check was federal expressed on Monday 5/8/06.
- Completed
change order #3 to Nor Cal Products for the base plates and chambers for
MIT. Submitted the order to the vendor. Received the signed modification
and order acknowledgement.
- Working
on the change order to University
of Michigan and the
change order to Promec.
- Updated
the subcontract database to reflect the recent grant amendments.
- The
MIT order for the six month allocation has been routed from Legal Counsel
to the AVP office.
>From: Florence Kaufman <fkaufman>
- Completed
reports for the Visitor Award and the Outreach Awards as of the end of
April.
- Completed
and sent out reports for the Hanford Conference Account, the Hanford and
Livingston Discretionary Awards, the Low Noise Award and the MIT Grid
Awards.
- Prepared
an analysis of various amounts related to the Exploratorium Purchase
Order.
- Prepared
two Cost Transfers for expenditures incorrectly charged to the Visitor
Award when it should have been charged to the Ops Award.
- Responded
to Project Accounting's request for budget realignments required in both
the Ops and Outreach Awards. These
realignments merely change the Oracle budget at the project level, total budget for the Award is not effected. These realignments are required whenever
the expenditures in a Project number exceed the budget assigned in Oracle
for that Project Number, so that NSF can be requested for reimbursements
based on expenditures made, because the Caltech billing system does not
allow for billing in costs in excess of budget at the project level.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- The
LLO Science Education Center (SEC) remains on schedule, although there was
some extra effort required in the connection of water, fire, and sewage
lines. These issues have been resolved, and the construction continues as
planned.
- The
contract with the Exploratorium for the LLO SEC exhibits is being modified
to add the final set, Group C, which consists of six exhibits. This will add $128,000 to the contract
total.
- Work
on the design prototype of the kinetic facade for the LLO SEC continues on
schedule. The prototype is
scheduled to be reviewed in two weeks at the contractor's facility in Boulder, Colorado.
PROPOSALS and REPORTS (Lindquist)
- Prepared
budget models for Operations during and after the Advanced LIGO
Program. Provided to Stan for
comment and modifications.
- Prepared
the monthly report for LIGO Operations and sent to the NSF. We are going to have to start work on an
Annual Report soon.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- The
next Staffing Committee meeting is scheduled for Monday, May 15. All files for the Staffing Committee are
up-to-date and posted on the SC web page.
- Prepared
numerous appointment and reappointment memos for various Visitors and Post
Docs.
- Preparing for the arrival of the REU students.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
Nothing significant to report this week.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary
of S5 Activities at LIGO Hanford
Observatory (compiled by M. Landry)
Both IFOs met S5 goals this week, with H1 running
at 87% duty cycle, 13-14Mpc, and H2 at 85%, 7Mpc. Of note is that we have
turned off useismic feedback on H1 as it appears to
be costing us a few hundred kpc when true useismic noise is low. This software and hardware
path was modified for PEPI; investigations are underway.
Highlights from the elog are bulleted below:
- offsite NDS requests that activated excitation test
points (monitor points only, not AWG excitations themselves) took us out
of science mode. Methods to close this loophole are being
reviewed.
- two strange trucks drove near the mid and end X
stations; the DOE was contacted and it turned out the drivers were well
surveyors. The surveyors have been reminded of policy to notify us
if they drive near LHO, and we asked for any records of other S5
visits. Data quality flags are being created by scimons.
- fan
6 was exonerated
as a killer of inspiral range
- h1
AWG problems continue to require reboots;
pulsars, which were often dropped in the last three weeks of running, are
now off, so we watch test points for indication the cpu
has failed
- winds roughly orthogonal to the end station (about 72
degrees to the x-axis, i.e. nearly in the y-direction) appear to drive
seismometers 5 times more
in x than in y. More here.
The result is suprising and calibrations and
orientations will be confirmed in followup
studies (one such study: EY anemometer realigned
by 120 deg).
- new
DMT code monitoring RMS strain was loaded
- PEM
injections were made on both IFOs
- the
4k FSS glitches returned,
and ISS/FSS cross coupling was investigated
- 4k MC
and CM loop transfer functions were obtained
- the
4k optical gain goes off
during long lock stretches
- As GEO has joined
S5 full time, GEO status is being imported
into the control room
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
Last week was quite a roller coaster ride. As we left our cliffhanger last week,
the Y arm input test mass (ITMy) had hung itself up
on 5/2 during unusually intense construction activity. Daredevil HEPI stunt
flying failed to shake it loose by Thursday evening, so we mobilized for an
emergency vent on Friday 5/5. The mirror was found unharmed and in good
spirits, but lightly wedged between its limit stops; it was easily liberated.
We were back under vacuum by Friday evening, degassed a little over the
weekend, and back in Science mode Monday night. Less than a
week, soup to dessert.
The LLO team deserves highest recognition for flawless professionalism,
tireless dedication and (gulp) nerves of steel. These guys are awesome.
But wait, there's more: the noise and inspiral
range got better after the vent!
An unknown noise term has polluted our low-frequency spectrum for over a
year, defying efforts to understand it and robbing 2 or 3 Mpc
off our range. Somehow the events of last week made it drop away. It's clear we
will learn something very deep from this, just not yet sure what.
One compelling theory (due to Rai) is that we had
enhanced dissipation and corresponding force noise due to surface mobility of
static charges, perhaps generated between the mirror and the stops during prior
"bump" events. This particular mirror had kind of a reputation for
bumping.
It's worth reflecting that our noise level corresponds to a ten thousandth
the size of a proton; nobody's been here before.
Meanwhile, we'll take it. 14+ Mpc inspiral range, in essentially
perfect agreement with our computed noise budget. Check out the 5/11 LLO ilog.

All of which serves as a great welcome and introduction for our new local
run coordinator, Igor Yakushin...
L1 in S5 (Yakushin)
- On
Tuesday May 2 ITMY mirror got stuck.
- Attempts
to unstuck it without going inside failed.
- On
Friday May 5 the commissioning team went inside and unstuck the mirror.
- On
Monday May 8 evening the vacuum was restored in the chamber with ITMY and
L1 rejoined S5 run.
- As
a bonus, we got our inspiral range increased to
about 13-14 Mpc and the noise below 100Hz
reduced.
- However,
L1 occasionally loses lock without any apparent reason and generates
glitches each few minutes. So there
is some work to do to make it stable and increase duty cycle which was
about 30% during recent days.
#MZ 5/12: It looks like the stability issues may have been at least partly
resolved last night by some tuning of marginal loop parameters and an ISC table realignment.
L1 CDS (Bogue)
- fb0 had hardware failure. Worked with sun engineering to
troubleshoot the problem and get it repaired. While fb0 was down, it was necessary to
move its disk array over to fb1 so that we could get dmt
working again. Thanks to Dwayne and
Dan Kozak for their help with that.
- Reprogrammed
the IP numbers on the true time.
Had a long discussion with Szabi about
our timing system and where the truetime fits
into it.
- Designed
new web pages for cds. Working closely with the operators to
get the main page swapped over to the new design. Once the main page is swapped, the other
pages can be migrated as time allows.
LLO Outreach (Thacker)
- Developed
and conducted outreach program for ST.
Jude School
5/8
- Developed
and conducted outreach program Victory
Academy 6th grade
5/10
- Developed
and conducted outreach program Pine
View Middle
School 5/11
- Accepted
delivery for and set up remaining 5 exhibits from Exploratorium Group B.
- Set
up Directorate teleconference and reviewed minutes for posting.
#MZ: We have now received 30 interactive exhibits, of which 7 are on temporary
loan at Southern. 6 more are on order for October delivery. We have received preliminary assessments
regarding pedogical effectiveness. The executive
summary goes something like "THEY ROCK!!!!!"
AdL Suspensions and Isolation, Outreach and Very Very Large Art (Romie)
Advanced LIGO Suspensions
Bob Taylor has agreed to a goal of Tuesday, May 16th for delivery of new osem cables to LASTI. Dave Ottaway
and the LASTI Crew have agreed to finish the required testing of the quad by
June 12th. These results are needed for the quad review by the UK group.
Discussion on the details of the remaining tests will take place at the SUS
meeting this coming Tuesday.
Completed the SUS NSF dry run presentation yesterday with Norna. Carol, Dwight, Norna,
Justin and I have a meeting this morning about the costs and schedule. The
final viewgraphs will be submitted to David by Wed, May 17th. The comments from
the dry run reviewers were very helpful and welcome.
LLO Science Education
Center Kinetic Art
Project
HPD have closed most, if not all, of the actions that came out of the PDR.
They are moving forward on schedule, as is the building construction. On May
23rd, we will go to Boulder
to see and review the prototype.
LIGO computing and network security (Roddy)
- last of the AUP emails are trickling in.
- The
network went down again yesterday.
This time Bell South rolled to two new fibers between the
Livingston and Denham COs at ~21:30 last night. We'll see if this fixes it. I was not contacted this time before the
circuit went down. In general they
always contact me before they do any intrusive maintenance/repairs. If nothing else it would have let me
know what was going on last night when we went down. I made a couple plots to compare to the
outages from two years ago. They
look almost identical, though I am not sure the
problem is identical.
- Still
working on the web server replacement.
- ordered various bits of hardware, books, etc.
- working
with Charter still on a quote for a backup network connection
- rebuilt a Dell workstation with a new hard drive, etc.
for the scanner PC replacement.
Installed windows, office, scanner, card reader, etc.
- made contact with a local IT Security company and made
inquiries into working with them on network audits, etc.
General Computing and LDAS Support (Giardina)
GC
- received a new PC for a user. Installed Matlab
and MS Office on it. Took the hard
drive from old PC, placed it in an external chassis, connected
it to new PC and currently running virus scan on it. It is badly infected.
- assisted
Bonnie with new LLO website development
- Bellsouth
network dropped out again. I have
spoken with engineers on a possible backup solution, and will talk more
with Shannon about this.
- replaced
two printer catridges
- email
config on a laptop for a user
- multiple
restarts of apache on web server
- other
usual user requests and support
LDAS
- ejected
tapes for shipment to CIT and imported and labeled new tapes
- replacement motherboard for node99 is requiring case
modifications and power supply wiring extension. I have questioned if this is how we want
to proceed, as we have more replacement motherboards that will cause the
same problems, or do we want to order motherboards that fit our chassis.
- searched for tapes that were ?mistakenly? ejected and
re-introduced them to the library
- continued working on a ganglia replacement to
monitor our cluster statistics
Initial LIGO Detector Science & Engineering (Coyne)
No report.
40 Meter Interferometer (Weinstein)
IFO Commissioning
- Rana and Monica moved the MC reflected beam line to
the AP table, shortening the beam patch dramatically. They reduced the
light hitting the PDs to a safe level,
eliminating the need for a fast shutter. They then re-phased the RF
demodulation and are able to lock the MC. Steve moved a ccd camera over to look at
the MCR light. The WFSs were also moved, but
they require new cables which are being made by Bob, and new Guoy telescopes which are being designed by Monica.
Dan is working on 45-degree brackets for holding the WFS boxes so that the
PD is a +, not x, as was done at LLO, to reduce some of the coupling
between pitch and yaw. The MC WFS will need to be re-diagonalized.
- The
small AP table is now a bit more crowded, (containing the AP RF, SP, and
MCR beam lines, and the MCT beam going to the PSL table), but still has
room for the DC readout QPDs and a path for the
squeezed vacuum beam line. There are no longer any beam lines going all
the way to the SP table.
IFO Modeling
- Monica
is cleaning up her e2e simulation of the 40m. She succeeded in locking the
simulation, using Osamu's seismic model. Optimization of sevo gains is in progress. She is also working on
locking with DC signals at TRX and TRY.
- Osamu
is working on new length sensing schemes from ALIGO, using lower RF
frequencies. It is harder to test such schemes at the 40m due to the short
power recycling cavity, but he's trying to find such a scheme.
DC Detection and Vacuum Squeezing Development
- Rob
and Sam continue to put together and pre-align the DC readout beam line,
in preparation for installation into the vacuum. We need to get a good
NPRO for alignment and OMC locking.
- Rob
and Sam are working out an in-situ alignment procedure for the DC readout
beam line after installation, using an NPRO (to be borrowed from
somewhere) and a fiber feed.
- Osamu
touched up the MZ alignment. There's a lot more reflected light when in
lock, because the modulation depths have been turned up to make IFO
locking easier.
- We
tentatively plan to install the DC readout beamline
in the vacuum in the 3rd week in July, when Rob comes back from his
honeymoon. Bob can have everything cleaned and baked before then.
- The
DCPD/OMMT Satellite box has been stuffed by P.R. and Ben is testing it
now. Everything seems to be working well, but Ben wants to make a
comprehensive test procedure for it to make sure that it all works well.
- Ben
is working on the front panels for the DCPD/OMMT box. They should be done
soon.
- Ben
is finishing the schematics and layout for the QPD Whitening board.
- It
is believed/hoped that Jay is working on the design of the steering mirror
PZT driver board and OMC PZT driver board, as well as the new AA and DAC
interface boards for the PCIX-based controls.
- Ben
made retaining clips for the OMMT mirror to replace the clips that came
with it. The original clips were much too big, and covered a large portion
of the mirror surface. The replacement clips are made from titanium, and
are much smaller than the originals.
- Go
and Evgueny are optimizing the SHG; they are
getting 620 MW of green light. "Seeing the green come out of nowhere
is very beautiful." - Rana. This higher
power makes it harder to acquire lock, and they are trying different
methods to make it easier. They also installed the pump beam path into the
OPO. They are generating green light in the OPA as well, to help guide the
pump beam. They are also observing daily alignment drifts; this may be due
to the MOPA trips (see below), or something else drifting upstream. They
are investigating.
PSL
- We
started seeing laser head temperature hiccups around 2 weeks ago. Osamu
thought they were consistent with PSL enclosure trip-offs. Steve did a
controlled test, opening the PSL enclosure when it was interlocked, and
saw precisely the same kind of hiccup. Either the enclosure is getting
bumped, or an enclosure sensor/relay is getting flaky. Steve will try to
locate a flaky sensor/relay. Meanwhile, the bumps should set off an alarm;
this will be re-enabled. And an interlock trip-off should not trip off the
MOPA. Steve will look for a softer way to provide the personnel
protection.
Electronics, Controls, Computers
- Dan
ran a new heliac cable to the 33 MHz pockels cell, to replace a broken one.
- Ben
ordered 6 of the YAG-444-4AH (the RoHS compliant
version) PDs from Pacer. Four are for the 40m,
and two are destined for Livingston.
Richard wrote that he had plenty, and didn't need any ordered for Hanford.
- Front
end test points continue to become unavailable for no apparent reason,
requiring restarts of the c0daqawg processor.
- We continue to have heaps of computer problems. Rob
noticed that the RGAlogger hasn't been running for
months, and the conlogger also needed to be
restarted.
Thermal Noise Interferometer (Black)
After some thought and additional modeling, Dennis
was able to explain the anomalous hump in the noise floor with the
o-ring-dampers installed. It seems there are mechanical modes of the o-rings
themselves at a few kilohertz, and what we were seeing was the low-Q, on
resonant thermal noise of these modes.
Based on Dennis' model, we tried kapton tape in place of the o-rings.
The tape lays flat against the mirror and
therefore presents very little mass to stick up and wiggle. This resembles the
models of Gras, et al., who modeled ring dampers as essentially massless strips of loss, much more than the o-ring does.
While we were doing the experiment, Dennis was also working on a finite-element
model for the kapton tape, using the material
properties of kapton and our TNI mirror dimensions.
This model will not be as good as it sounds, since we do not know the material
properties of the adhesive that sticks the tape to the mirror, but it ought to
be at least close.
While the o-rings were very good at damping
the mirror Q's, they also increased the broadband noise floor. The kapton tape proved less destructive in terms of noise (the
noise floor returned to the coating thermal noise level), but it was also
relatively ineffective at damping the mirror Q's. Q reductions ranged from none
to 50%, depending on the mode.
No report.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Yamamoto)
Advanced LIGO LSC/ASC design using e2e (Hiro)
Matt wrote a setup to study the lock acquisition issue of AdvLIGO,
using a FP arm. This is consisted of a adv.LIGO BSC, double chain quad pendulum and a FP
cavity. His focus was mainly LSC design
to study the required force on ETM.
The setup has been expanded to study ASC/LSC in a more realistic condition.
New setup now includes the radiation pressure and uses modal model, instead of
plane wave. The quad pendulum model was replaced by one which is based on the new
reference design, from the old model based on 2003 design. Several WFSs in front and one QPD beyond ETM have been attached.
There was a meeting held, Rana, Vuk, Osamu and Hiro, to discuss
how to proceed using this setup to design and test LSC/ASC. Physics issues
discussed were:
- Main
missing piece is ASC.
- Local
dumping design is very primitive, and assumes that ETM and ITM can be
actuated in the same way.
- Locking
process, even at very low power input, needs ASC to make the in-lock state
stable. Strong local dumping will make this locking process easier.
- It
was suggested that the code is modified so that filter specification
format used at the site/40m can be read in directly to the simulation
code.
Hiro is cleaning the setup, together with a simple
documentation and example scripts. It
was found that, in order to simulation the test mass motion with enough
accuracy at high frequency region, > 10Hz, the statespace
calculation needs to be carried out using quad precision. This is because the frequency dependence is ~
1 / f^8 in the high frequency region, together with several high Q resonances
in the low frequency region. During this
work, a gcc bug was found which has to do with the
allocation of array of long double. It could be gcc
4.1 issue, not quite identified yet.
Advanced LIGO Mechanics modeling (Sany)
Completed e2e analysis of suspension point to optic's yaw
coupling for AdvLIGO quad suspension. The
computations were made using Mark Barton's most recent model (20060331 as built
off-diagonal model). For comparison, the same computations were repeated for a
completely symmetric case (keeping other parameters the same). When the
symmetry is assumed, only suspension point Yaw (of the six degrees of freedom)
is coupled to the optic's Yaw, as expected.
With the actual asymmetry (based on the most recent design) taken into
account, the computation shows slight coupling from suspension point X (normal
to the optic surface) and Roll to the optic's yaw. However, the magnitudes of
the corresponding transfer functions are on the order of 1e-10 or less,
indicating that the couplings are effectively negligible.
40m modeling (Monica)
The 40m configuration using the Osamu seismic model has been tested : the in-lock state is kept for the 5 degrees of
freedom, but without radiation pressure. This will be tested next. Trying to get the in-lock state for the 5
degrees of freedom using the transmitted power at the end mirrors to build CARM
and DARM error signals : still under investigation.
Modeling code (Bruce, Melody)
A new version of e2e, 3.1.6 released which is needed to simulate the latest QuadFP package.
Melody helped Rana to install e2e package on his
laptop. She helped Hiro
to properly create a distribution tarball. A proper
process needs to be taken to include all changed made properly included in the tarball.
Bruce is working on improving the input and output parts of the modeler
code.
ALFI (Bruce, Melody)
Melody
- Continuing
with the ALFI enhancement to have "comment" notes in an edit
window. Currently working on the
GUI portion.
- Made
a bug fix for the Rename option (not to write the DISPLAY setting for all nodes, only the
ones with non-default settings).
Bruce
- Analysis
of a bad Alfi bug which can cause Alfi to crash after the setting of two identical
instance nodes are made (PR 541).
Data Analysis Activities (Lazzarini)
Brown
- working
in fixing problems with black hole ringdown
analysis pipeline
- meet
with Diego to discuss his progress with the physical template family
search
- continued
review duties for S3/4 inspiral BBH review
- made
detailed plan for Alex's SURF project
- discussed
data access in the control room with Stuart and John Z
- tested
new LDG 4.0 build for Stuart
Chatterji
- Investigating
minute trend data from environmental channels to exclude periods of erroneous
data from veto studies.
- Reorganizing
X Pipeline CVS repository to prepare for open science grid feasability studies
- Continued
investigation of chirplet extensions to the Q
Pipeline.
- Drafted
proposal for dedicated detector characterization workstations in LIGO
control rooms.
Dupuis
- working
on building multi-detector frequency-spindown
maps for first 6 months of S5 for certain pulsars
- preliminary
results show that:
- we
have beat the spindown limit for the Crab by a
few percent
- we
are within a factor of 3.5 from the spindown
limit for J0537-6910
- we are within factor of 16 for J2124-3358 and
constraining its ellipticity to less than
1.5e-7 (!)
Mandic
I continued working on the S4 all-sky stochastic paper. A draft has been
reviewed by the review committee, and by others, and I am in the process of
making the suggested changes to the paper.
I am also working with X. Siemens on the accessibility of the cosmic strings
models to the LIGO stochastic search.
Mendell
An update on the StackSlide S4 analysis was given
at Tuesday's CW telecon and posted on the pulgroup S4 investigations page. A review is scheduled for
tomorrow.
Shawhan
- Generating
data quality flags for various conditions (out-of-lock at ends of
segments, light dips, suspension controller overflows) for the period
February 7 through May 2. I have
had to deal with missing trend frame data; I ended up writing a program to
re-generate trend frames from raw frames, and am currently running it to
generate trend data for selected LLO channels over a four-day interval in
March.
- Sorted
out estimates of Burst Group computing needs with Albert Lazzarini and Erik Katsavounidis.
- Drafted
a charter for the Burst Group with Erik Katsavounidis.
LIGO Data Analysis System
Software Systems (Maros)
LDAS
Continued working on having the diskcacheAPI being
robust to NFS file systems that are not available (PR#3015).
Nearly completed the explicate setting of the version of tclsh
used by tcl scripts. This allows for tclsh to come from some other
source than /ldcg/bin/tclsh and is part of the 64-bit
port.
The "Test All Cmds" option from cmonClient's Test menu has been made more reliable by
adding timeouts to each of the scripts used by the command.
System tests were done using version 1.8.72 of LDAS.
TCLGlobus
The web pages have been updated for 1.0.0 release of tclglobus.
The source code distribution is available and the RPM will be made available
once built and tested against LDG 4.0.
GRID COMPUTING
The prototype of the WorkFlow GUI has most of the
functionality for saving basic workflow characteristics.
Tested srmcp commands with
latest release of srmcp and DRM 1.2.11.
Several commands are not working including tests from a Dcache
to the DRM. Requested
use of the FNAL development Dcache for
interoperability tests.
Attended bi-week TG-Storage meeting. Requested the
VDT support people help determine what version of VDS they provide so that
coordination with FC4 glibc releases can be
accomplished.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Normal
S5 tape ingestion stuff.
- Fixed
file that wasn't staging on ldas-cit and staged
it on dataserver-cit so MIT could continue
pulling data via LDR.
- Working
on re-adding SFTs to CIT's
collections.ini (had to remove them to get LDR to work at all).
- Determined
which tapes to eject for shelf storage at LHO.
- Posed
question to sam-managers list about getting
metadata information out of a samfsdump file (no
good answers yet).
- Set
up script at LHO/LLO to collect information about virtual memory, I/O and
processes when we get a "Shared server not responding" message
in the /var/adm/messages log.
- Helped
Lisa Bogue at LLO mount the /fb0_frames on fb1
while fb0 was down with hardware problems.
Also coached the reversal of this once the machine was repaired.
(Phil Ehrens)
- Added
per-machine sorted logging to log_mon.tcl report
facility. This is still in the
testing phase.
- Spec'd and ordered sound insulation foam and
installation adhesive to be installed on inside doors of cluster room.
- Investigated
strange of attempts to mount /home/condor on various desktop machines. No
conclusion reached. Resulting log
entries look like: automount[4142]: lookup(nisplus):
lookup for condor failed:
- Partial
success automount[4142]: failed to mount
/home/condor
- Drilled
metal ears for rackmount installation of foundry
switch salvaged from CACR.
- Various
GRID certificate related tasks.
- Various
cluster support tasks.
- Various
LDAS related tasks.
(Erik Espinoza)
- One
node crash, node216.
- Completed
ldas-kickstart for Livingston,
shipping Fri (5/12).
- Worked
with AMD to get them involved in our node crashing situation.
- Flashed
nodes to BIOS v 1.1 w/ new settings for ECC Scrubbing.
- Troubleshooting
GC Print Server (Kuma).
- Tested
Development glibc & other development
packages on frog.
- Assisted
Junwei Cao w/ iptables on frog.
- Configured
Condor on frog, David Meyers will be conducting testing.
(Stuart Anderson)
- Continued
testing of latest SAM-QFS patch continues to look good.
- Continued
stress testing of backup 3510 unit has resulted in Dan getting Sun to
replace the chasis.
- Working
with Condor team to understand why Quill is not working.
- Worked
with Junwei to upgrade the LDAS-CIT cluster from
LDG-3.5 to LDG-4.0.
- Started
loading all LIGO minute trend frames into the LDAS-CIT cluster.
- Started
investigating VMware.
Livingston
(Dwayne Giardina)
- Ejected
tapes for shipment to CIT and imported and labeled new tapes.
- Searched
for tapes that were ?mistakenly? ejected and re-introduced them to the library.
- Continued
working on a ganglia replacement to monitor our cluster statistics.
Hanford
(Greg Mendell)
- I
am continuing to work on SFT publication, and making LDR transfer of RDS
and trend frames from the sites to CIT more robust.
(Ben Johnson)
- I've
re-installed the OS on 15+ nodes with kickstart.
Despite having to go in and configure the BIOS on each one for network
booting, it works very well.
- Updated
QFS on fb0 to 4.5.10.
- Created
a no-globus-on-client LDRdataFindServer.
General Computing (Wallace)
MIT
(Keith)
No report this week
Livingston
(Dwayne)
- Received
a new PC for a user. Installed Matlab and MS Office on it. Took the hard drive from old PC, placed
it in an external chassis, connected it to new PC
and currently running virus scan on it.
It is badly infected.
- Assisted
Bonnie with new LLO website development
- Bellsouth
network dropped out again. I have
spoken with engineers on a possible backup solution, and will talk more
with Shannon about this.
- Replaced
two printer cartridges
- Email
config on a laptop for a user
- Multiple
restarts of apache on web server
- Other
usual user requests and support
(Shannon)
- Last
of the AUP emails are trickling in.
- The
network went down again yesterday.
This time Bell South rolled to two new fibers between the
Livingston and Denham COs at ~21:30 last night. We'll see if this fixes it. I was not contacted this time before the
circuit went down. In general they
always contact me before they do any intrusive maintenance/repairs. If nothing else it would have let me know
what was going on last night when we went down. I made a couple plots to compare to the
outages from two years ago. They
look almost identical, though I am not sure the
problem is identical.
- Still
working on the web server replacement.
- Ordered
various bits of hardware, books, etc.
- Working
with Charter still on a quote for a backup network connection - Rebuilt a
Dell workstation with a new hard drive, etc. for the scanner PC
replacement. Installed windows,
office, scanner, card reader, etc.
- Made
contact with a local IT Security company and made inquiries into working
with them on network audits, etc.
Hanford
(Christine)
- Set
up more laptops. Made a loaner laptop dual boot WinXP/FedoraC4.
- Started
getting user accounts and computers ready for SURF students and summer
teachers. Started cleaning up the Computer User Room and Staging building
office. Updating some older
computers and going through spare monitors to find ones that work.
- Started
cleaning out the server room to make room for new servers,disk system and tape drive.
- All
site staff have now signed off on the new Computer
Use Policy.
CIT
(Mike)
- Bridge
Annex server room: installed an additional server in the rack with the new
UPS.
- Trouble-shot
a LAN network connection for Rich Abbott. This turned out to be a faulty
network HUB. Replace this with a new switch and ran a new network cable.
Christian gave me a hand with this.
- Look
into a problem for Bruce Sears regarding his LINUX workstation. This turned out to be a hardware issue.
Larry and I took a look at this, which we ended up swapping him out with
another LINUX box that I had pre-loaded with (Fedora core 4.)
- DHCP
Server: Ran out of IP numbers. Went through and freed up IP numbers that
were not being used.
- Spam
Filters: Continued work on searching for false positives.
- Some
misc. user support.
(Christian)
- 3flr
W/B - Replaced toner cartridges on HP 5500 printer.
- Created
a backup of Julie Hiroto and Cindy Akutagawa laptop and workstation.
- Worked
on the Spam Filters with Larry Wallace.
- Continuing
working on updating all of the visitors' workstation this week.
- Linda
Turner- Corrupted profile in thunderbird. Created new profile and
transferred back all of her email and folders .
- Other
misc.: Continued onsite software/phone support.
(Veronica)
- LIGO:
A website for the AdvLIGO NSF review. Updates to
the website of the PAC meeting. Installed a new newsletter. Updates to the
Elba website. Updates to the roster
database. Prepared high-resolution images for several publishers. Working
on the makeover of the LIGO homepage.
Updates to the current LIGO website. User support.
- LSC:
Updates to the upcoming meeting website. Updates of the technical papers
database and the webpage of observational results.
Maintenance of the LSC-related mailing lists.
(Bruce Sears)
- Fix
of iLog installation at LHO. (0.5 days)
(Larry)
- Worked
a number of procurements for different groups. Still working on maint. contracts. Delivered a number of items. Arranged for a couple of people to have
portable disk drives to backup their notebook computers. Received a number of drives for
distribution to those that travel and need a backup drive. Tested out a new projector, the unit so
far performs well. Started working
on the procurement for a couple of new UPS.
- Cleaned
up a number of accounts. Working on getting more accounts removed and trying
to free up more disk space.
- Sent
out a reminder to those needing to signoff on the new AUP. There are still about 20 more people
that need to reply.
- Continue
work with the spam filters. We had a couple of spam storms but things held
up. Worked on a mail problem for
Linda Turner with Christian. The large files she
receives appears to cause her core mail file to become corrupted.
- Assisted
DCC with a number of different issues.
- Worked
a couple of web issues, mostly links needing to be updated.
- General user support
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Systems, Management
Seismic Isolation
The final stage 1
subassembly has been completed. All three stages are built and ready for final
assembly.
The test stand has been
lowered to the assembly height and leveled. Stage 0 and the stage 2 optics
table has been assembled onto the test stand.
There are still many
locator, spring, and actuator parts which have not been delivered by Limerick
Machine. These parts are 8 weeks late and we are trying to put pressure on them
to deliver them.
An internal review of the
advanced ligo seismic subsystem was held on 5/2.
Several good comments have been received which will be added to the
presentation.
From: Riccardo
DeSalvo <desalvo@ligo.caltech.edu>
HAM-SAS
PROMEC Gianni
- all drawings in construction
done
- cabling drawings still being
reviewed/revised
- added end stop to vertical
movement to prevent damage to cabling
- shipping crate drawings still
pending
- counterweight bell details
urgent now by Monday -- Yumei & Dennis to
calculate
Caletch/G&M: The contract reflecting
the latest changes was done
Tecnoinox, Marcello
Problems
with through penetration in weld samples potentially a serious problem:
(Reminder: Allied Engineering & Hytec found it
difficult to perform these welds and required special weld preparation). The old know how was, partially retrieved and
provided to Tecnoinox (example T970250-00 and
C980468-00), the old technique involves TIG welding with heath barrier trenches
to confine the heath in the welds, surface preparation techniques in the last
few minutes before the welds, and using different gases atmospheres. There is
consensus that the 5082 Aluminum used is the best choice, rather than the
stiffer 6000 series alloys. Tecnoinox has consulted welding experts and made several
tests with a modified MIG and tried several suggestions as well as making TIG
welds on thinner plates. They have
achieved what is at first sight some good
results. They are sending the samples to
Caltech for evaluation where Yumei and Riccardo will perform micro-cutting and photography to
certify the full penetration and non porosity of the weld. They also send the samples to an Ultra-sound
testing company. There is still plenty
of potential to solve the problem, otherwise we can
always switch to stainless steel.
Some
already machined parts have been sent through the cleaning process and have
been sent to Eurolab, a company specialized in
cleanliness tests. Eurolab
has visited G&M and collected the parts after discussing on the technique
to be used and took samples of oils and other fluids that may have been in
contact with the parts for possible back-tracing of the residuals. They will perform FTIR tests in a bath. They are not familiar with performing the
test on large parts by pouring the solvent over the part and back in the tank,
as done by LIGO, but will study it and perform.
The clean
room has been ordered.
Ric suggests doing dishwater cleaning at G&M for small parts
if environmental problems like waste fluids can be solved. Can make the
cleaning a more nimble operation. Cleaning chemistry should be in any case oversighted by Soldi. Large parts
would still go to Soldi’s.
Fabrication Schedule: Chiara was busy with Eurolab’s
visit and the welding problem and could not update the production status list.
The list this time will appear on G&M web site. However everything seems to
proceed as expected, with the exception of the end-stop modifications and the
CW production that still waits for the design from Caltech. In any case not a
critical item.
There is a chance that the
welding problems may introduce some delay in the IP assembly, probably
absorbable, while the GAS filters will be unaffected. Riccardo
is scheduled to go to G&M to start partial assembly on the 21st of May. Riccardo and Dave O. will have a 4 working day overlap in
mid June. By then the dirty assembly should be concluding and only some
counterweight tests should be ongoing. G&M will consider the impact to the
schedule of the welding problems and advise us. At the moment it appears that
at worse Dave may have more work if the weld generate
delays.
Valerio presented LVDT measurements: http://www.ligo.caltech.edu/~citsas/HAM-SAS/Weekly20060510.ppt. Basically the resolution is sufficient, but some
small improvements should still be implemented.
We will likely plan to have a coarse & fine mode of operation so
that in the coarse mode the LVDT range is ~1cm and in the fine mode the range
is ~2mm. Ben Abbott taking charge of the
electronics, made a meeting and will meet again with Virginio, Valerio and Riccardo to get Ben up to speed and discuss cabling,
packaging, impedance matching, etc.
Other issues
- Alberto Stochino
and Peter Raffai working on magic wand and IP
papers
- John Wilson of Flomerics Thermal and Air Flow Consulting Services,
following a visit of Riccardo at Flomerics, prepared a Quote for a BSC Chamber Airflow
Study. In evaluation.
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
Advanced LIGO Suspensions
Bob Taylor has agreed to a
goal of Tuesday, May 16th for delivery of new osem
cables to LASTI. Dave Ottaway and the LASTI Crew have
agreed to finish the required testing of the quad by June 12th. These results
are needed for the quad review by the UK group. Discussion on the details
of the remaining tests will take place at the SUS meeting this coming Tuesday.
Completed
the SUS NSF dry run presentation yesterday with Norna. Carol, Dwight, Norna,
Justin and I have a meeting this morning about the costs and schedule. The
final viewgraphs will be submitted to David by Wed, May 17th. The comments from
the dry run reviewers were very helpful and welcome.
From: "Mark Barton"
<mbarton@ligo.caltech.edu>
This week I spent a fair
bit of time assisting people using my modeling software: Hiro,
who's working on AdvLIGO actuation schemes, Sany, who's working on an integrated SUS/SEI model, and Ian
Wilmut of Birmingham, who's investigating the behaviour of the adjustment mechanisms in his "marionette"
quad prototype, and Rich Mittleman, who's working
with the controls prototype.
I also tracked down more
and better as-built numbers for the controls prototype. As I suspected, some of
the mass numbers had been inappropriately rounded. Also, for historical
reasons, the blade spring elastic constants had been expressed in terms of
"uncoupled frequencies". (A UFC is the bounce frequency for a blade
loaded with its share of just the one mass directly below (as opposed to of all
the masses below it in the chain). It's useful as a rough estimate of the
vibration isolation performance of a single stage.) Sure enough, the UFCs we had been using had been computed with as-designed
masses and converted back to elastic constants with as-built number, introducing
anerror. Norna and I have
now settled on a final set of numbers, which will be circulated in the next day
or so.
From: Ken Mailand kmailand@ligo.caltech.edu
I'm working on a lower
quad installation arm concept, and a simpler part that may be used at the LASTI
site, will send out an email for comments and input.
Core Optics
From: Bill Kells kells@ligo.caltech.edu
Prompted by the review of
the COC "internal review" slides being passed around I have re-assesed the reqirements for the Adl COC in view of what we know now about LIGO I
optics. The requirements must be stated
much more precisely, commesurate with the much
tighter loss budget for the arm cavities (optics). It may be not (nearly) so
simple to require that the AdL optics be polished
"to the same level of precision" as was achieved in LIGO I.
One LIGO ITM (2ITM04 which
was the "bad" 2k X itm which was replaced)
was scanned for HR surface scatter (loss) at the LMA lab in Lyon.
We received the (very nicely done !) results, have had
a conference call explaining them, and have discussed their import within the
OWG. For comparison/control purposes LMA
also similarly scanned 3 1" dia superpolished &HR coated test mirrors which we
understood the loss of from "contamination cavity" measurements. It
must be appreciated that the LMA scatterometer only
senses loss in the micro-roughness regime (surface scales < 1mm).
These LMA results are
puzzling in that they are hard to reconcile (in some respects) with our own
scan (which also only probe the micro-roughness regime). For 2ITM04 they
conclude a mean (over ~50cm^2 scanned) scatter loss of ~6ppm and more
interesting an upper bound for the surface background (that is points where
there is no enhanced scatter due to defects) scatter of ~2ppm. This is
surprising since our OTF scans (of this same mirror) give a mean of 18ppm and a
background of ~11ppm. In particular the factor >5 discrepancy in bacground is worrysome since that
should be an invariant of the native surface polish and coating (i.e. not
contaminated, as the mean of a large surface scan is, by the hard to determine
point defect and dust scatter).
In addition they find no
evidence that there is any anomalous point scatter intrinsic to the HR coating
(as has been hypothesized to explain the "globular cluster" point
scattering so evident in IFO operation for these optics). They their mean
result of ~6ppm for the HR surface to be the true average scatter loss, whereas
we find < 70ppm in IFO operation).
On the other hand the LMA
results for the 3 1" superpolished, HR coated
optics are not so far from what we measure. they find
(average of 3) a surface background of ~5ppm, whereas we have typically found
~4ppm for such calibration optics.
It is their general
opinion that these discrepancies are somehow all due to different levels of
dust accumulated prior to the various scans being compared (and implicitly that
our IFO operational scatter is dominated by dust) They
have dramatic direct experience with such effects. But this is hard to
reconcile with all our observations (i.e. freshly cleaned HR surfaces do not
reduce to the loss levels they find, at least for ITM04).
From: Helena Armandula ahelena@ligo.caltech.edu
2ITM04 and Small
1"dia. Mirrors
Received the scattering data from LMA on 2ITM04 and three
1"dia. mirrors. The full report is in
the DCC OUT under doc. # C060061-00. After receipt of the report we had a
teleconference with the Lyon folks to clarify
details. At this time we are fine tuning
our understanding of the different implications.
Input Optics
From: David Reitze
reitze@phys.ufl.edu
Electro-optic Modulation (Wan
Wu, Guido Mueller)
- We have started looking into
various EOM designs using a single crystal to provide all modulation
frequencies for the initial LIGO upgrade; developing FEM models to predict
the behavior of the electric fields and aid in designing the electrode
spacing.
- continuing working on a laser intensity
stabilization servo for the EOM noise measurements. Working on problems
with the reference voltage offset. In addition, considering a digital
servo based on IIR filter design.
IO Mechanical Design
(Luke WIlliams)
- Made a new layout for the
Mach-Zehnder modulation to accommodate high
power operation.
- Created a revised layout for
the AdvLIGO IO that uses single part assemblies
to reduce the complexity of the drawing. Continuing to add the
auxiliary beams.
- Starting to work on a vacuum
compatible design for the Faraday Rotator.
IO MMT (Dave Reitze)
- circulated a RODA to SUS specifying the
physical dimensions of the MMT3 mirror. Negotiating with SUS for
final values of the dimensions
Thermal Compensation (Muzammil Arain)
- Continuing on our search for
negative dn/dT material, a new Glass from Schott
(N-PK51) seems to be an alternative to CaF2. This glass has considerably
lower thermal conductivity value of 0.92 W/(m-K).
Also it is available in large sizes. We plan to buy some glass plates for
characterization. In addition, a sample of CaF2 has been obtained and
optical characterization experiments are underway.
Faraday Isolator (Ken Franzen and Simon Stepuk)
We have continued to study thermal lensing effects
in a 100 W beam passing through the AdLIGO Faraday
Isolator prototype two times. By positioning a DKDP crystal close to the FI (~
cm) followed by careful alignment and orientation we found that the beam
appears to be rather decent (~ Gaussian). We are now trying to quantify these
results more in detail.
NSF Review (Dave Reitze)
- based on many useful reviewer
comments, have revised IO cost and technical presentations for the May AdvLIGO review
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
With Xilinx's
customer support from Ireland,
we established that one of the software packages I use is installed and working
correctly. Now it would appear that there is a bug with the evaluation
version of the other software package that I'm using - the one allowing the Simulink interface to the hardware - in that it may not
actually do any hardware interfacing.
The full-blown version does. This should be resolved by the end of
the week.
Auxiliary Optics
From: Michael Smith <smith@ligo.caltech.edu>
PO MIRROR
Chris Echols completed a
preliminary SW model of the PO mirror bezel.
TCS
I have developed a ZEMAX
model of amodified initial LIGO TCS CO2 laser
projector for heating the Compensation plates in front of the ITMs for the non-folded IFO. I am adding a conceptual
layout of the CO2 laser heater into the SW Vertex Layout drawing.
Controls, Data systems
From: Jay Heefner
<jay@ligo.caltech.edu>
LASTI HEPI
- The conversion of the LASTI
HEPI system to PCIX based LIGO controls is in progress and should be
completed by the end of the week.
AdL SEI Internal Seimic Isolation
- The backplane board and the
interface board for the capacitive position sensors are due back this
week. They will be stuffed and tested in the next two weeks. We will then
have a full prototype of the capacitive position sensor interface chassis
ready for test in LASTI.
From:
mohana@ligo.caltech.edu
I am in LASTI this week. I
am doing the HEPI installation with Jay and Rich. We put all the new
electronics in and powered up the rack today.
All the cables are put in the the subsystems
and we will test the HEPI electronics tomorrow with the software.
For additional information about this report, contact S. Whitcomb or P. Lindquist