Weekly Report for
Week Ending May 4, 2006
The LIGO Executive
Committee Agenda for Monday,
May 8, 2006 will be:
(Meeting time: 10:30 am Pacific Time)
1. Announcements
2. Comments
on Weekly Report
3. LSC
Issues (Saulson)
4. LIGO
Lab Operations
- Administration
(Lindquist)
- Sites
(Raab, Zucker, Shoemaker)
- Commissioning
(Fritschel), Detector (Coyne)
- Campus
Research Facilities
- 40
Meter (Weinstein)
- TNI
( Libbrecht)
- LASTI (Shoemaker)
- Data
Analysis and Computing (Lazzarini)
5. R&D
and Advanced LIGO (Shoemaker)
6. CHANGE CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION AS
NEEDED
Special Items:
- Preparations
for Advanced LIGO Review (May 31 – June 2)
Special Announcements:
Weekly Report Highlights
No report.
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
- Emery-Riddle's August 05 MOU was converted to LSC
format and has been accepted and signed by Saulson
along with the Attachments D, A, T and OPT.
SITE TELECONFERENCE (Lindquist)
- There
was a site teleconference Thursday, May 4, 2006. The following were among the items
discussed:
- Financial
Reports – Reports for the end of April have been posted. For recurring costs, we are running at
86 percent of budget and project that we will spend $32 mill8on in FY
2006.
- Livingston Science Education
Center –
The building should be enclosed to the weather within weeks.
- Van
Acquisition for Hanford
– We have a low bid and a check will be mailed this week for a
Wednesday pickup.
- There
are currently no open action items.
The list of assigned actions updated through December 01, 2005 (the
last update) will be found Here.
PROPERTY MANAGEMENT (Luna)
>
- Attended
the Exports Controls Seminar in Washington
DC.
- Provided
assistance to the Detector Group (C. Torrie)
with shipping, packing, and preparation of a Commercial Invoice for US
Customs Clearance of 6 boxes to the Scotland. Account Number LIGO.TEC-1.3-NSFLIGO.FY02ON.
- Assisted
Hanford
(J. Worden) in the purchase of a new van.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- Processed
another small handful of revised & new HAM drawings from Promec.
- Processing
a large batch of confidential/sensitive documentation.
- Scanning
- Scanning of non-electronic 'P' documents is complete. Scanning of contract closeout files has
resumed.
- Activity:
|
Week Ending
05/04/2006
|
In
|
Out
|
|
Packages
|
23
|
15
|
|
Faxes
|
22
|
26
|
FINANCIAL SYSTEMS (Cronin, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Completed
change order #3 to the Exploratorium and submitted it to the vendor.
- Completed
the internal modification fund transfer on the new Galli
and Morelli subcontract and federal expressed
the signed subcontract to the vendor.
- Placed
credit card orders as requested.
One called for the export of the goods to Italy. Arrangements have been made for the
export which is scheduled for delivery next week.
- Working
on completing the changes to the terms and conditions of the University of Florida subcontract.
- Completed
the package for the MIT change order and routed it for review and
approval.
>From: Florence Kaufman <fkaufman>
- Completed
the monthly reports for the fiscal year for Operations and R&D and for
Outreach as of the end of April and posted them on the network.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- The
LLO SEC construction remains slightly ahead of schedule. Preparations are being made for installation
of the glass front wall, which will fully enclose the building.
- A
successful preliminary design review for the prototype of the kinetic
facade was conducted last week.
Only a few minor design issues remain to be resolved.
- Notification
was received that DEMCO is now in the system for electronic funds transfer
for payment of monthly power invoices at Livingston. Next month's bill will be the first
under the new EFT arrangement.
- Research
is being performed by the Caltech Office of General Counsel to see if
security background checks for volunteers are required by law in either Washington or Louisiana.
PROPOSALS and REPORTS (Lindquist)
See Advanced LIGO below.
It’s time to work on Monthly Report for the NSF.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- The
next Staffing Committee meeting is scheduled for Monday, May 15. All files for the Staffing Committee are
up-to-date and posted on the SC web page.
- Prepared
numerous appointment and reappointment memos for various Visitors and Post
Docs.
- Preparing for the arrival of the REU students.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
Nothing much to report, mainly working to "close" the Livingston
Action Items assigned to the Caltech organization. An e-mail has been distributed regarding the
AI for the fire extinguisher check period requirement. The Federal requirement
is monthly visual check and annual maintenance service. The AI regarding Site volunteers is in work,
the "key" Campus organizations have been contacted and have agreed to
provide the necessary information.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary
of S5 and Commissioning Activities at LIGO Hanford Observatory (compiled by M. Landry)
S5 Highlights
- weekend
running was solid on both IFOs but h1 AWG issues
remained: had to boot h1awg0 several times... through the week, h1awg0
continued to require reboots but at a lower frequency
- Monday
locking was interrupted for six hours due to high winds, with gusts in
excess of 50mph
- Tuesday
we had our scheduled power outage care of the FFTF (reactor, which was
undergoing electrical maintenance), from 9:10-9:35am PDT. The IFOs were back to locking
by early afternoon (much more quickly than the recent unscheduled power
outage several weeks ago).
- the
range and duty cycle update was posted
- we're
considering a periodic "IFO maintenance" period (with frequency
and duration t.b.d.), separate from Tuesday
"site" maintenance, for interferometer jobs orthogonal to site
ones
- blrms seismic tracks
the h1 inspiral range with high precision
- some
questions of the effect of fans on IFO performance still linger, such as
how much if any noise fan 6 adds... the seismically isolated unit may not
add noise at all despite first considerations (seismic comparo
here)
- most CDS systems came back well and quickly after the
scheduled power outage; framebuilders were more finicky.
Outreach (D. Ingram)
LHO recently hosted the Yakama Nation Tribal School and the monthly meeting of
the WSU-TC Latino
Outreach Collaborative. A multi-partner bilingual
event occurred on 4/22. National Astronomy Day
will unfold on May 6.
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
Bulletin on Stuck ITM:
Assuming ITMy does not free itself Thursday night
(see Ken's report below), the LLO vertex volume will be vented to atmosphere
Friday morning 5/5 so it can be manually released.
The repair duration at ambient pressure, and the subsequent pumpdown period to degas adsorbed water, will depend on
what's found inside. We will issue a
projection for rejoining S5 as soon as we have enough info.
Thanks to everyone for your patience and especially to LHO
for unrelenting 24/7 expert support.
L1 in S5 (Franzen)
The duty cycle during last week was only 37 percent due to a series of
unfortunate events:
- ISCT4
fast shutter malfunction on Thursday. The shutter did not open properly
and was swapped to a spare.
- AS
trigger problems.
- TCS
script problems.
- Thunderstorm
(Saturday evening).
- AWG
problems.
- Several
large earthquakes in South America and in the Tonga islands during Sunday.
- ITMY
which seemed to have received some charge during heavy construction work
going on outside during the Tuesday maintenance period. We lost our
ability to align the optics properly and could not use HEPI to compensate
like during previous times when this has happened. During Wednesday we
tried to recover by purging the chamber with dry air and shaking the
corresponding HEPI. However it did
not help. We are presently preparing to vent the system in order to go in
for an inspection and a fix.
L1 CDS (Bogue)
- Spent
most of this week updating CDS documentation.
- Came
up with a design to update the main web page on london.
- We
had more problems with dtt and test points this
week. This time it was on the framebuilder side.
- Looked
at using system tools to replace the off-the-shelf software we are using
for screen captures. I think sdtimage will provide the same functionality.
LLO Outreach (Thacker)
- developed
and conducted Professional Development for East Baton
Rouge physics and physical science teachers
- developed and conducted program for Franklinton High
School advanced mathematics school visit.
- exhibit
maintenance
AdL Suspensions and Isolation, Outreach and Very Very Large Art (Romie)
Advanced LIGO Suspensions
Working with Brett, Pradeep and
Jay this week, to work out final cabling, osem &
electronics issues.
Completed updating the SUS WBS Dictionary this morning.
Working with Caroline on a number of SUS estimate issues in
preparation for the SUS dry run on Tuesday. Working on
the cost/schedule presentation for Tuesday.
LLO Science Education
Center Kinetic Art
Project
Participated in the HPD Kinetic Art PDR last Thursday.
On May 23rd, we will go to Boulder
to see and review the prototype.
LIGO Computing and Network Security (Roddy)
- The
LLO network went down for a while yesterday. Ticket was opened with Bell South and
they arrived this morning. The
network came back up last night without intervention. Fujitsu has had a product advisory that
has been out for ~1 yr to replace the former version of the repeater
cards. So, Bell changed three of the six cards on
the circuit today. I will keep an
eye out for dropouts on the fiber and if there are any more dropouts they
will likely replace the cards on the other segment. Most dropouts are not noticed since they
last < 5 seconds.
- Spent
some time planning the network drops for the outreach building. The network drops will be "field
routed" and the conduits just stub off above the drop ceiling. Ordered the CAT5 for the network and
CAT3 for the phone.
- Troubleshooting
web server problems. Haven't been
able to figure out exactly why Apache is bombing a couple times a day,
though I also haven't had much time to look into it.
- Worked
with Dwayne on the DNS/loghost rebuild.
- Began
working on a Dell to replace the old HP scanner PC. Work stopped when I was short one power
adapter. It has been ordered and it
is on the way.
- fixed
the wireless in the auditorium
General Computing and LDAS Support (Giardina)
- solidworks reinstall on Janeens
PC to revert to correct version for the PDMWorks
vault, all appears to be well
- apache has been requiring restarts on alix. need to migrate to a new server weighs heavier.
- installed FC5 on Sun X2100. This is our new loghost
and internal DNS. named and syslog-ng have been
configured on the machine and it is now in production. old
loghost/DNS server was failing intermittently.
- assisted
Bonnie with new LLO website development
- got
a crash course from Shannon on what to do
when there is trouble with network connection between LSU and LLO
- other
usual user requests and support
- ejected tapes for shipment to CIT and imported and
labeled new tapes
- replaced
hda in node125 with hdb
from node10, new hdb in node10; replaced hda in node162 with hdb from
node11, new hdb in node11; replaced hdb in node154 with new; replaced hdb
in node164 with new
- attended Condor Week 2006 with Stuart and Erik
- working
on a ganglia replacement to monitor our cluster statistics
Data Analysis (Yakushin)
Storage/Condor/LDAS Admin
1) GHLTV-SG21_V4_S4, GHLTV-SG22_V4_S4, GHLTV-GA2_V4_S4, GHLTV-WNB1_V4_S4,
GHLTV-SG1_S5, GHLTV-SG1B_S5 burst MDC sets were copied from PSU to CIT via LDR.
2) RLS and LDR servers at LLO were restarted in order to revive downloading
of L3, h(t), L4 LHO frames to LLO.
Data Analysis
1) Continue working on applying coherent waveburst
to LIGO-GEO S4 data.
2) Preparing a techical document on the S5 version
of the incoherent waveburst.
3) Regenerated waveburst online analysis page with
S5 version of waveburst
http://ldas-jobs.ligo-la.caltech.edu/~waveburst/S5_LIGO_ONLINE_2. Once the V2
calibration is officially released, I might have to redo it again.
4) Integrated QScan into waveburst
online analysis pipeline to do a follow-up study of loud triggers.
Initial LIGO Detector Science & Engineering (Coyne)
Nothing significant to report
40-Meter Interferometer (Weinstein)
IFO Commissioning
- With
much increased RF modulation and LO oscillator levels at the LSC rack (see
below), DRMI locking is much easier and more robust. Re-optimization of
loop gains in progress.
- Rob
and Rana have a new easier way to lock the DRMI
(no arms) using only single-demod signals at the
SP (no double-demod). This allows them to tune
up the demod phases, offsets, and diagonalizing the plant for the double-demod signals is much easier, and the control can be
handed over to those tuned-up signals before adding the arms.
- Osamu
continues to work on the noise budget with Monica and Dan. They have made
tremendous progress. The code Osamu developed at LLO for improved
measurement of the frequency noise has been brought over and implemented
at the 40m. Most of the main noise sources for the 40m FPMI have been
measured, including frequency noise, seismic, oplevs,
MICH, calibrated DARM noise, Dark noise,
frequency noise, seismic, oplevs, MICH, and their sum
(total predicted DARM noise). Still need intensity noise; to measure, we
need an analog output from the front end (AWG) to actuate on the PSL
intensity. We will maybe use a spare, unused ASC (or IO suspension) Pentek DAC channel, Also
missing is oscillator phase noise.
- The
noise budget indicates that the FPMI sensitivity is limited by dark noise
above ~200 Hz, which will be improved when we increase the optical gain by
locking the PRFPMI or DRFPMI. At that point, the noise budget code can
measure the PRC and SRC loop noise. But we need to implement into the noise
budget code a reliable model of the DRFPMI frequency dependence, including
optical spring and RSE peaks.
- The
signal from the MC transmitted RFAM PD went away, possibly because an
upstream optic was disturbed. The MC autolock
script, which uses that signal to sense when the MC is in lock, was
changed (by Rob) to use another PD.
IFO Modeling
- Monica
is updating the seismic model in her e2e model of the 40m, using Osamu's
model. It's 100x higher at 10 Hz. Now she's
trying to lock with the much larger seismic noise.
- Monica
is developing a Bench model for AdVIRGO.
DC Detection and Vacuum Squeezing Development
- Ben
reports that the DCPD/OMMT Satellite box is being stuffed by PR and should
be finished soon. Ben has started the front panels for that box.
- Ben
is finishing the QPD Whitening board layout for the DC readout beamline.
- Ben
gave Bob ten more resistors (for the in-vac DC
PD) to bake and scan. They are an easily mountable wirewound
type.
- Ben
machined the DCPD beamsplitter mount to allow
for retaining clips to be screwed on, and Dan made and installed the
retaining clips. It's not a neat solution, but it works.
- Ben
reports that Jay is working on the layout of the TT steering mirror PZT
driver board and the OMC PZT driver board. Also, the PCIX-based computer,
and ADC and DAC cards, are in hand. The ADC and
DAC interface boards are designed and will be ordered soon.
- Rob
and Sam tried locking the OMC with the crystal laser borrowed from LLO,
with no luck; it was too noisy. We need to find a spare NPRO.
- Rob
and Sam are unhappy with the mounting of the small curved mirror on the
output MMT, and are thinking of alternative mounts using a new mirror.
- Go
and Evgueny installed the new OPO cavity,
aligned and mode matched the seed beam, found the cavity modes, and
optimized TEM00 transmission of seed beam. Next step is to align the pump
(frequency-doubled) beam. They also mode matched into and out of the mode
cleaner fiber they use for the local oscillator beam, and got 90%
throughput. with Osamu, they are designing a
single remote-insertable In-vac
pickoff mirror for their squeezed vacuum.
PSL
- Steve
continues to monitor the PSL power. The internal MOPA AMPMON photodiode
from Lightwave, strongly humidity dependent, was
replaced by a new PD (thorlabs PDA55) external
to the MOPA and calibrated to watts. We now have a reliable way to monitor
the MOPA power before it goes through the PMC.
- Steve
and Rob noted that the PSL head temperature had a couple of
"hiccups" in the last week; one was possibly due to optical
feedback when a shutter was closed, but one or two others have no known
cause, and everything fell out of lock. Being closely watched.
- The
MZ frequency noise is large, and the servo drifts into saturation easily.
Steve will construct a plastic box around the MZ to protect it from
acoustic noise and accidental bumps.
Electronics, Controls, Computers
- Dan
and Rana measured RF LO levels at LSC rack, and
found lots of problems and inadequate LO levels.
- Rob
redid much of the RF distribution wiring, replacing the old frequency
distribution boxes with Mini-Circuits ZFSC-3-13's. He then turned up the
modulation at the RF distribution rack, and now there is much more LO and
RF signal going into the LSC rack (although the 199 MHz is still a bit low).
The Heliac for the 166MHz to the pockels cell has bad connector - to be fixed.
- To
aid in noise budget work, we need to have the seismic spectrum from the
accelerometers at the vertex and at the ends, always available to the
front end controls. Steve will set up the accelerometers and run the
cables.
- Our
controls computers continue to be a mess, with many things not working on
them. We will try to enlist help from solaris
experts.
- We
need to prepare our PC computers for the onslaught of SURF students this summer.
Lab Infrastructure
- Steve
had the electricians install a 20m breaker from isolation transformer
panel to the DCreadout rack.
- Steve reports that a vacuum foreline
gauge failed, to be replaced.
Thermal Noise Interferometer (Black)
No report.
LASTI (Ottaway)
No report.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Yamamoto)
Adv.LIGO mechanics simulation (Sany Yoshida, Mark Barton, Hiro
Yamamoto)
The standard quad state space model in e2e is now based on the reference
configuration updated recently, instead of the old reference configuration in
2003. The main difference between 2003
and new one is the spacing of the suspension wires. In 2003, spacing of wires
between the second mass from the top and the penultimate mass was wider than
that between the penultimate mass and the test mass. In the latest reference
configuration, it is opposite. I.e., the spacing of wires between the the penultimate mass and the test mass is wider. When a FP setup is used to see the difference
(no ASC control, just mechanical effect), the correlation of pitches between
the penultimate mass and the test mass is much stronger than the old reference
case. Mark provided us SS parameters of the new reference configuration,
together with one with descent asymmetries included.
Sany continued e2e analysis of AdvLIGO
quad-sus based on Mark Barton's mathematica
model. His primary interest at this point is to see the level of couplings
between various degrees of freedom at the suspension point to those of the
optic. Completed computation for one case in which the quad-sus
was assumed to be perfectly symmetric (with somewhat obsolete mechanical
parameters of the suspension). Will continue similar computations for cases
with more recent mechanical parameters including asymmetric (off-diagonal mass).
40m modeling (Monica Varvella)
Another attempt to keep the in-lock state is under investigation using the
seismic model implemented by Osamu in e2e. The noise level around 10 Hz is
almost two order of magnitude higher than that one obatined
with Monica model : it will be probably necessary to
increase some gains for the control system previously used to get the
stability.
QuadFP (Hiro Yamamoto)
Working on to setup FP with quad suspension, radiation
pressure, ASC and LSC. This is intended to be used by ISC experts to
investigate a realistic design for adv.LIGO. A preliminary mass position and pitch motions
are available in www.ligo,caltech.edu/~hiro/AdvLIGOSim/FP_pitch.pdf
and FP_pos.pdf.
These show how the masses and pitches change as the FP power goes up
from 1W input to 1000W input. It is observed that the basic pitch mode at 0.4
Hz is excited.
Modeler Code (Bruce Sears, Hiro Yamamoto)
Bruce is working to modify the output part so that one can control the
output list more easily and effectively.
Hiro modified the code to (1) make FUNC_X more
close to normal C++ code and (2) added a few modules for QuadFP
setup.
ALFI (Melody Araya)
Continuing with the ALFI enhancement to have "comment" notes in an edit window. Parsing the comment elements from a box
files is mostly done. Currently working on the
GUI portion.
Data Analysis Activities (Lazzarini)
Brown:
- Attended
LIGO/Condor meeting at UW-Madison.
- Scimon shifts at LLO
- Did
some housekeeping on online inspiral search
- Enhanced
online inspiral glitch pages at LLO, will
propagate up to LHO this week
Chatterji:
- Identified
potential clustering algorithm extensions to the Q Pipeline for further
study by a summer undergraduate research fellow.
- Investigating
the prospects of a chirplet extension to the Q
Pipeline.
- Continued
writing of a proposal for a mock data challenge using 3 hours of single
detector GEO, LIGO, and Virgo data
- Reviewing
draft of the LIGO/Virgo burst PRD paper
Dupuis:
- working
on summarizing the results for pulsar analysis using the first 6 months of
S5
Mandic:
I studied the accessibility of the stochastic GW background produced in
cosmic string models to LIGO. It appears that there is a class of cosmic string
models that is accessible to LIGO, but not to other measurements of the
stochastic GW background. I plan to work with Xavi
Siemens and possibly others toward a publication.
I worked on the S4 all-sky stochastic search paper. I made modifications to
reflect the new analysis results regarding Bayesian statistics, software
injections, implications of various m
Mendell:
I am continuing work on the StackSlide S4
analysis, and the paper with PowerFlux and Hough
results. An update will be ready by next week's pulsar telecon,
and I hope a review this week or next.
Shawhan:
- Fixed
duplicated information in conlog files at LLO.
- Reviewed
pulsar analyses.
- Considered
the importance of having two interferometers at Hanford.
Sutton:
This week I made final edits to the Xpipeline
coherent analysis paper and sent it to gr-qc and
PRD. I also studied the use of time
delay estimates in Xpipeline to restrict the region
of the sky that needs to be studied.
Finally, I read portions of Stein's thesis (former SURF student working
with Xpipeline) and sent him comments.
Yakushin:
1) Continue working on applying coherent waveburst
to LIGO-GEO S4 data.
2) Preparing a techical document on the S5 version
of the incoherent waveburst.
3) Regenerated waveburst online analysis page with
S5 version of waveburst http://ldas-jobs.ligo-la.caltech.edu/~waveburst/S5_LIGO_ONLINE_2.
Once the V2 calibration is officially released, I might have to redo it again.
4) Integrated QScan into waveburst
online analysis pipeline to do a follow-up study of loud triggers.
LIGO Data Analysis System
Software Systems (Maros for Blackburn)
LDAS
After examining another program which also tries to overcome stuck NFS
calls, a new plan is being formulated to overcome problem report 3015. It
should be implemented by next week.
The work of cleaning up the hard coding of /ldcg/bin/tclsh
has completed and is currently being tested on a tandem system. The "TEST
ALL" feature of cmonClient has completed
successfully. This instance is using TCL/TK as provided by Fedora Core 4 and
version 8.4.12 for Solaris.
System testing used version 1.8.165 of ldas.
TCLGlobus
Based on user feedback, the installation documentation for TCLGlobus has been modified.
GRID COMPUTING
Work has focused on providing a GUI OSG workflow manager. The basic screen
layouts and menu items have been designed. Efforts are underway to implement
the design.
Assisted VOs GROW and ATLAS with
running their applications on LIGO- CIT-ITB for OSG 0.3.7 validation.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Built
new /samtest filesystem
out of 3510-10 and 3510-12. Did
lots of work with 3510-10 to try to make it work reliably (ongoing).
- All
caught up receiving Sun parts (3510 disks, controllers, T3 disk, V880
power supplies) except for T3 power supplies.
- Replaced
bad power supplies in samtest (V880).
- Normal
S5 tape ingestion stuff.
- Continued
to try to close the gap on L0 files that haven't made it to CIT in a
timely fashion.
- Rearchived all data on odd bad tape at LHO (from last
week).
- Worked
on some tape drive problems at LLO.
- Unwedged stuck gridftp-server
processes on ldas-cit (staging stuck).
(Phil Ehrens)
- General
cluster maintenance tasks while Stuart Anderson and Erik Espinoza attended
Condor Week.
- General
GRID certificate related tasks.
- Investigated
various modes for x509 based authentication of aliased domains under
Apache. Multiple DNS entries and multiple virtual interfaces provide the
most transparent solution, but a single globbing
DNS entry is usable with client browsers requiring a per-session
click-through to accept use of a single installed cert for an aliased
server name.
- Trivially
ported the log_mon.tcl integrated
monitoring/security/
reporting application for monitoring of desktop
machines. Only resource file mods were required (yay!). 13 machines on the Millikan
6th floor are currently being monitored.
I wrote a cron script which is run by the
client machines to provide tripwire style file modification detection, and
that is curently being tested on four desktop
machines on the 6th floor of Millikan. Documentation for this project is being
maintained in the LDAS sysadmin wiki, q.v. The cron script writes to syslog
using the UNIX 'logger' utility, with the service flag "shasumcheck" identifying it's
entries. All machines with this utility installed write their logs to a
central syslog server where analysis occurs and
reports are generated.
- Configured
ldas-suntest3 and ldas-suntest5 to use the Solaris installed Apache.
- Discussed
ongoing LDAS requirements with LDAS developers.
- Tested
lsync.tcl, the "standalone" diskcacheAPI on the Linux 32 bit and 64 bit platforms.
It fails to start properly on either platform. This program is currently tested as part
of the LDAS distribution on Solaris only (where it runs fine). I opened a
problem report against the failure of lsync.tcl
on Linux.
(Erik Espinoza)
- Contacted
AMD about our node issues and provided info requested.
- Gave
Ben info on cloning BIOS information.
- Built
Postgresql 8.1 RPM packages for FC4 x86_64.
- Wrote
Quill Config for ldas-grid.
- Troubleshooting
job negotiation on Condor, jobs not matching properly.
- Looked
up spare Xeon mobo, making list of compatibility
for shipping.
- Testing
AMD debug tools.
- Node
Issues - 327 Up, 3 arriving from ASA Soon.
-
5/4 node116 - Kernel Panic (rwsem.h:43)
-
5/4 node57 - Kernel Panic (rwsem.h:43)
-
5/1 node68 - Kernel Panic (MCE CPU0)
-
5/1 node59 - Kernel Panic (Watchdog CPU3)
-
5/1 node43 - Kernel Panic (MCE)
-
4/25 node325 - Kernel Panic (MCE CPU1)
-
4/25 node177 - Bad Disk (Disk 4, port 3)
-
4/24 node68 - Kernel Panic (MCE CPU1)
-
4/24 node4 - Kernel Panic (rwsem.h:43)
(Stuart Anderson)
- Continued
testing of small file deletion problem on SAM-QFS.
- Attended
one day LIGO-Condor summit meeting.
- Started
planning condor configuration changes to implement job scheduling policies
that are more closely aligned with LIGO needs.
- Started
modifying cluster data staging tool to handle larger full frame
directories (since each directory is larger than what one node can hold).
- Continuing
discussions with condor development team on dagman
related issues.
- Considering
options to make data access easier in the control rooms.
MIT
(Keith Bayer)
- Upgraded
pcraid9 to latest Fedora kernel in hopes of getting beyond an nfs memory problem.
- Talked
with another shipper about cluster nodes to WSU.
Livingston
(Igor Yakushin)
- GHLTV-SG21_V4_S4,
GHLTV-SG22_V4_S4, GHLTV-GA2_V4_S4, GHLTV-WNB1_V4_S4, GHLTV-SG1_S5,
GHLTV-SG1B_S5 burst MDC sets were copied from PSU to CIT via LDR.
- RLS
and LDR servers at LLO were restarted in order to revive downloading of
L3, h(t), L4 LHO frames to LLO.
(Dwayne Giardina)
- Ejected
tapes for shipment to CIT and imported and labeled new tapes.
- Replaced
hda in node125 with hdb
from node10, new hdb in node10; replaced hda in node162 with hdb from
node11, new hdb in node11; replaced hdb in node154 with new; replaced hdb
in node164 with new.
- Attended
Condor Week 2006 with Stuart and Erik.
- Working
on a ganglia replacement to monitor our cluster statistics.
Hanford
(Greg Mendell)
- I
have published S5 1800 second and 60 second version 2 SFTs
at LHO and LLO for times between Dec. 17, 2005 and Jan. 31 2006, making
these SFTs available via LSCdataFind
at the sites. These SFTs were generated from h(t). I will be working to publish SFTs
for times before and after this, and to transfer these SFTs
from the sites to CIT via LDR, where they will be made available to the
tier II centers.
(Ben Johnson)
- Upgraded
LDAS servers and fb1 to the latest SAM-QFS patch level.
- Upgraded
LDAS 3510 RAID unit to the latest firmware level.
- Integrated
diskcacheAPI functionality to enhance LDRdataFindServer, currently in testing at CIT.
General Computing (Wallace)
MIT
(Keith)
- Working
on SMF startup scripts for Solaris 10 -Switching back to native Solaris
LDAP client utilities
due to lack of working ldap
cache. Takes about 5 seconds to
process each mail message due to continual
ldap lookups without using the
cache. I have put stunnel
in between Solaris and my SSL/TLS required ldap server to make the connection secure
(and possible) - someday Sun might
make a decent operating system.
- Getting
ideas software on windows for scientist
- Investigated
webcamXP and Bosco
screen share utilities
Livingston
(Dwayne)
- Solidworks reinstall on Janeens
PC to revert to correct version for the PDMWorks
vault, all appears to be well -Apache has been requiring restarts on alix, need to migrate to a new server.
- Installed
FC5 on Sun X2100. This is our new loghost and internal DNS, named and syslog-ng have been configured on the machine and it
is now in production. The old loghost/DNS server
was failing intermittently.
- Assisted
Bonnie with new LLO website development - Got a crash course from Shannon on what to do when there is trouble with
network connection between LSU and LLO
- Other
usual user requests and support
(Shannon)
- The
LLO network went down for a while yesterday. Ticket was opened with Bell South and
they arrived this morning. The
network came back up last night without intervention. Fujitsu has had a product advisory that
has been out for ~1 yr to replace the former version of the repeater
cards. So, Bell changed three of the six cards on
the circuit today. I will keep an
eye out for dropouts on the fiber and if there are any more dropouts they
will likely replace the cards on the other segment. Most dropouts are not noticed since they
last < 5 seconds.
- Spent
some time planning the network drops for the outreach building. The network drops will be "field
routed" and the conduits just stub off above the drop ceiling. Ordered the CAT5 for the network and
CAT3 for the phone.
- Troubleshooting
web server problems. Haven't been
able to figure out exactly why Apache is bombing a couple times a day,
though I also haven't had much time to look into it.
- Worked
with Dwayne on the DNS/loghost rebuild.
- Began
working on a Dell to replace the old HP scanner PC. Work stopped when I was short one power
adapter. It has been ordered and it
is on the way.
- fixed
the wireless in the auditorium
Hanford
(Christine)
- We
had a planned power outage Tuesday morning. One of the Hanford sites adjoining LIGO needed to
do maintenance on their electrical which is on the same line as ours. Everything came back with out any
problems, except for one monitor that seems to be dead.
- I
tested the backup network connection again. If I plug a computer in to the media
converter I get a network and can ping ESnet and
the world. If I plug my Fastethernet interface on the router in to the media
converter, I see Transmit and Receive lights flashing, but I don't have a
network. I can't ping anyone except
my router. I've contacted
Cisco. There are a few more tests I
can try.
- Continued
working on the PR and competitive justification to buy the new disk and
backup systems.
CIT
(Mike)
- Ran
monthly ghost backups on all NTSRV's.
- Worked
on cleaning up home accounts, to free up some disk space.
- Continued
work on spam filters searching for false positives.
- Setup
SCR for (Dry Run) ADV LIGO NSF Review. Christian and Larry helped out
setting up, and monitoring these meetings as well.
- Started
working on documentation on the new DCC servers that are hosting our new
software "Synergy," regarding installation, how these two
servers interact with one another, and the monthly backup process. Doing
some research on how to get legato backup software to work with Domain
Controllers.
- Put
together a backup scheme on the PDMWORKS server. Larry and Christian
helped out with this project. The services for the Vault must be stopped
in order to get a true backup of the Vault. We have written some .bat
scripts to do this. These scripts stop, and start the service upon
completion of the backup. This is done by running these scripts using the
Scheduler that comes with Server 2003.
- B/A
server room: Assembled and installed a new UPS that Larry purchased. We
also re-routed some network cables and relocated a few rack mounted
servers. Christian gave me a have with this.
- Other
misc. user support.
(Bruce)
- iLog Maintenance: (0.5 days),
General maintenance and user account creation.
(Christian)
- 3flr
W/B - Replaced toner cartridges on HP 5500 printer.
- Created
a backup of Irene Baldon workstation.
- Continuing
working on updating all of the visitors' workstation this week.
- Updating
the Ligo Inventory IP address database.
- Mike
and I installed new UPS/Backup in the server room.
- Worked
on debugging/testing of Bosco a screen sharing
utility. Assisted in Webcam XP setups.
- Other
misc.: Continued onsite software/phone support.
(Larry)
- Tracking
down a number of procurement items.
Still working on the computer from Monarch. They still have not
found the problem. Placing orders
for new laptops and generating a new order for a dual core quad cpu unit. Working on the Foundry maint. contract.
- Spent
a good part of Saturday getting computers back on line. We lost a UPS that
supported a couple of the core servers. No known reason why it died, there
was no warning and it will not come back on-line.
- Worked
on the monthly backups. Still have some work to do to finish them up.
- Assisted
Christian on some of the Webcam XP setup. Also,
assisted in testing out the Bosco s/w pkg., it wouldn't
work properly being accessed from behind a NAT router. We may look into
the problem in more detail if we don't find another s/w solution.
- Assisted
the DCC on a couple of items. Also, worked a little on a posting for the
LSC.
- Continual work on user accounts, mail aliases and
going through the spam filters.
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Systems, Management
Seismic Isolation
Internal review preparations and execution.
From: "Joseph A.
Giaime" jgiaime@ligo.phys.lsu.edu
Internal review preparations and execution.
From: Jay Heefner jay@ligo.caltech.edu
AdL SEI
- Prototype preamps for the L4C
and GS13 pods were fab'd, tested and sent to Joe
at LLO for a fit check.
- The design for the backplane
and interface boards for the capacitive position sensors has been
completed and the files sent out for fab. They
should be back in ~ 1 week.
LASTI
- Continued final assembly and
checkout of components for LASTI HEPI conversion next week.
- Completed design, fab, and test of new ADCU AA interface chassis to be
installed next week.
From: Riccardo DeSalvo
<desalvo@ligo.caltech.edu>
HAM SAS
Ed Jasnow:
has received the signed order from G&M, got it signed at Caltech, and sent
back to G&M their official copy
BOM revised by Chiara and Riccardo according to
modifications agreed in kickoff meeting (parts removed, added or revised and
quantities revised) and sent to DCC and Ed Jasnow for
no cost modification of order. http://www.ligo.caltech.edu/~desalvo/HAMSAS/BOM-D051299-01.doc/
Gianni: Construction
drawings finished delivered to DCC, from now on we expect only design changes
“as built” or modification suggested by actual construction.
Still working on:
- Cablings drawings
- Crating and shipping drawings
Technoinox: delayed delivery material for
samples of through penetration weld tobe sent to
Caltech for inspection, and processed through cleaning and FTIR. Ready by Wednesday. In preparing the base structure they
proposed additional scalloping to improve cleanability.
Proposal accepted and implemented in drawings and in re-cutting parts.
Chiara:
Fabrication Schedule: Part
fabrication status list & schedule temporarily available at http://www.ligo.caltech.edu/~desalvo/HAMSAS/a-Produzione_ESEGUITI(5-May).doc/
to be posted with weekly revisions on the G&M web site Sent photos of some
parts soon (later will post to the G&M web page). Clean chamber preparations ongoing. A bid
delivered (somewhat unsatisfactory), waiting for other bids. Expect to decide
Wednesday 10th.
Preliminary tests for
cleaning & baking
Paolo Soldi
only needs 2 days to perform cleaning for the test He has been given several
parts for testing: one iron, one SS, one Aluminum
(including part #77 GAS filter plate after adding venting holes). After cleaning and baking, G&M will
arrange for FTIR testing by Eurolab
Eurolab (the FTIR company, see http://www.eurolab.it/) to visit G&M
Thursday 11 and either perform test or collect parts -- they also need to
decide how to organize the sampling of the other parts.
Ric:
- made revisions of the assembly
procedure document (removed or revised calibration & tuning at G&M
and removed optics table) discussing revisions with G&M
- 150 kg of UHV foil sent by Ric to G&M
- ordered polyimide paint for
the coils, arrived in Caltech Thursday
- ordered higher temperature
magnets to replace previous alloy magnets
- sent web camera to G&M
Simulation &
Controls Design
Virginio:
working on triple pend + HAM-SAS simulation -- has calculated the
transmissibility for longitudinal direction -- no surprises -- will extend to
other dofs & look at back reaction to SUS triple
forces -- will have some preliminary results for next week
Valerio:
Measuring the LVDT readout
noise
Yumei:
Inverted Pendulum (IP)
dynamics modeling ongoing
Electronics
- Ric & Jay met late last week
for further determining cabling ¬ reviewed in-vac
cabling -- defined LVDT, actuator and motor connectors -- 9pin D from Accuglass
- Gianni making in vac drawings
- Marwan, which is making the coils,
will pre-wired them to Gianni's dwgs
- Marwan is repackaging the LVDT electronics
for us to minimize the cable routing -- defined dimensions of LVDT board
as 1U or 2U high for 19 in rack
- Virginio will review the Marwan design for the possibility of small changes of
impedance match to coils as well as cabling/connectors
- Jay to talk to Ken, next week
while at LASTI, about ordering extra cables to allow sufficient number to
test effect of possible acoustic shorting of the isolation system (can
double or triple fold a single long ~25' cable for this purpose)
Suspension
From: Janeen
Romie romie_j@ligo.caltech.edu
Working
with Brett, Pradeep and Jay this week, to work out
final cabling, osem & electronics issues.
Completed
updating the SUS WBS Dictionary this morning.
Working with Caroline on a number of SUS estimate
issues in preparation for the SUS dry run on Tuesday. Working
on the cost/schedule presentation for Tuesday.
From: Ken Mailand
kmailand@ligo.caltech.edu
I'm working on a lower
quad installation arm concept, and a simpler part that may be used at the LASTI
site, will send out an email for comments and input.
From: Helena Armandula
ahelena@ligo.caltech.edu
Requested and received an
up-dated quote for the gold coating of the electrostatic drive to support the
Adv. LIGO SUS NSF review.
From: "Mark Barton"
<mbarton@ligo.caltech.edu>
This week I did some
modeling work to help Ian Wilmut understand the
"marionette" quad prototype being assembled at Birmingham, specifically, the expected
response of the equilibrium position to manipulation of the various adjustment
mechanisms. First I created a customized version of the quad model with a large
number of extra parameters representing perturbations to the geometry. However
initially I wasn't getting sensible equilibrium positions because I had long
ago taken a shortcut in my pendulum modeling toolkit and left the wire
stiffness terms out of that part of the calculation. This was fine for
symmetrical pendulums and/or pendulums that didn't rely on the wire stiffness
for stability. However the AdvLIGO quad would fall over in pitch if not for the
elasticity of the wire, so I had to go back and add this as an option. The new v2.5 toolkit has been giving sensible
results so I released it on the modeling website (<http://www.ligo.caltech.edu/~mbarton/SUSmodels/>).
I've also been working
with Norna to come up with a final parameter set to
describe the as-built controls prototype, as well as an improved version of the
Matlab model that is equivalent to the latest version
of the Mathematica model and includes the effects of
lateral compliance of the blades. The Matlab code is
completely done and the parameter set is almost done except for some blade
parameters that need to be double checked against the lab book.
Core Optics
From: Bill Kells
kells@ligo.caltech.edu
We now have some very nice
data for simultaneous ITM07 scans measuring both HR scatter and absorption. The
"control" here is a thoroughly cleaned patch of the same surface
(previously know to have ~ factor 10 less mean
absorption). The cleaned patch mean scatter loss (scatter signal to loss was
calibrated with auxillary scans of previously
measured standard surfaces) was found to be consistent with the scatter loss
level of other CSIRO polished LIGO I TMs, and was about a factor 10 less than
the mean scatter of the un cleaned, contaminated scan. To check that this
dramatic increase is not due merely to "ordinary" (non-absorptive)
dust accumulation in the lab, we look at the detailed correlation of scatter
vs. absorption for all scan pixels. Indeed there is a strong increase in
scatter for minimally absorbing points. However there is a strong true
correlation of the dominant high absorption points with high scatter values.
Two issues are being
worked on with regard to parametric instabilities. First there are new
simulation results from Australia
(Pablo Barraga). Several problems with the previous
round of simulation of the RT cavity loss for high order cavity modes had been
pointed out. In addressing these, Pablo has arrived at significantly lower
diffractive loss values. This now disagrees with the "consensus"
values arrived at by various routes (e.g. Biplab Bhawal) last summer. I've been working on resolving the
various issues at work here: which results (if any) are correct.
Second, since the March
LSC meeting A. Melissinos and Stefanos have more
measurements on H1 at the FSR. They claim clear evidence of the onset of an
"instability" as the ifo
power is increased. I am working on discussing this with them to get a better
understanding of what is being observed (its hard to reconcile the phenomenon
as described with a true PI, though it seems that something interesting has
been found).
From: GariLynn
Billingsley <Billingsley_G@ligo.caltech.edu>
Scatter & Absorption investigation
Liyuan completed a new analysis of
scatter and absorption data from 4ITM07. In this analysis average scatter and
absorption correlate well, though we still have to investigate the absolute
calibration of the scatter signal, as it does not yet show the value measured
at the Hanford Observatory.
Absorption calibration is
quite consistent with that seen at Hanford. The current noise level on the coating
absorption measurement is approximately .2ppm on average and .5ppm peak to
peak. Liyuan
believes this is due to the instability of the HeNe
probe beam power. He will be looking at ways
to stabilize this in preparation for the more sensitive requirements of
Advanced LIGO coating absorption measurement.
From: Helena Armandula
ahelena@ligo.caltech.edu
Advanced LIGO Coatings
CSIRO is optimizing a Ti
doped silica coating to minimize optical absorption.
Scatter measurements on
2ITM04 continue at Lyon.
Input Optics
From: David Reitze
reitze@phys.ufl.edu
Internal
review preparations and execution.
Pre-Stabilized Laser
From: Peter King
pking@ligo.caltech.edu
Preparation for the NSF baseline
review continues with cross-checking between various files to see if things are
consistent.
My adventures with Xilinx continue.
After ordering some evaluation software that actually generates the bitstream for the DSP board, I received an empty envelope
with a packing slip stating that the software CD was enclosed. So far their customer service has been sadly
lacking. I was promised that a copy
would be sent out ASAP. We shall
see. On the plus side I did receive some
training materials that ought to come in handy.
Auxiliary Optics
From: Michael Smith
smith@ligo.caltech.edu
PO MIRROR
Chris Echols,
is working on a SW model of the PO mirror
bezel.
LAYOUT
I have revised the layout
as follows:
- use the BS prompt reflected ghost
beam from the AR surface to extract the ITMX PO beam. This eliminates the
suspended. ITMX PO mirror. Use the same ITMX PO telescope to launch and
receive the Hartmann ITMX recycling cavity beam, separating the IFO beam
and the Hartmann beam with a dichroic beam
splitter.
- make the first BS PO mirror
the primary mirror of a beam reducing telescope, eliminate the other two
suspended BS PO mirrors, the secondary mirror of the BS PO telescope is
suspended on a SOS on HAM4.
- the Hartman ITMX and ITMY
recycling cavity beam expanding telescopes are the identical off-axis
parabolic design as the ITM PO telescopes, to eliminate the glint of the
IFO ghost beam back into the IFO and to reduce back-scatter.
- the Hartman BS, ITMHRX, and
ITMHRY beam expanding telescopes will be a refractive design.
- OMMT mirror 1, LOS; and OMMT
mirror 2, SOS form a beam reducing telescope. OMMT mirror 3, SOS, steers
the dark port beam through an output Faraday isolator and delivers the
reduced beam to the ISC detection chamber.
PO TELESCOPE
I am arranging to visit Tydex J.S. Co., the source in Russia
that produces off-axis parabolic mirrors, while I am on vacation in Russia
in July.
NSF REVIEW
I scrubbed the AOS
schedule to eliminate redundant first article fabrication for all three IFOs.
Controls, Data systems
From: Rolf Bork
rolf@ligo.caltech.edu
- Assembling and packing all the
parts to install new PCI-X based Hepi controls
for three chambers at Lasti next week.
- Alex updated our standard
filter module software. Besides IIR filters, we can now define and load polyphase FIR filters into any of the 10 filter slots
within a filter module (mix and match). In Ligo Hepi, we had to have one filter module to do the downsampling, one piece of custom code to then do the polyphase FIR, and then a third filter module for upsampling. In this scheme, all three filters are
loaded into the same filter module.
- Armed with this new code, I
was able to generate the full code set for three chambers from my Simulink file. I will try to test this code as much as
possible before everything is gone, but I'm sure more testing will be
required once we get set up at Lasti.
- Thanks to Stuart Anderson, who
sent me an email pointing to a computing news
posting, I was able to locate a vendor which provides optical links for
PCI express. With the PCI express expansion system we are now testing, the
copper cable limit is 3 meters. Using this fiber link, we can go 300
meters. That would allow us to remote our computers from the I/O chassis,
plus get the other advantages of fiber (no ground loops). I have an email
in now to verify with the vendor of our PCI express expansion unit that
this fiber product is in fact compatible.
Other Laboratory R&D
From: Riccardo
DeSalvo desalvo@ligo.caltech.edu
Suspensions Seismic General Issues:
Riccardo:
Following the emerging
post mortem results from the Hanford
ITS test mass (both particle and a deposited film seem to have contributed to
the anomalous heating), studying methods to prevent future pollutions of test
masses either by dust or outgassing.
Discussing with Bunting, identified slightly different Nd
magnet alloy that allow raising their baking temperature from 80C to 150C.
These magnets are slightly less or equal in strength than those usable in the
Suspensions. It appears that now the highest limit in suspension baking
temperature is given by the OSEM at 125C.
Discussed
with Flometrics on methods to establish laminar flow
in the BSCs during installation.
They will make a business
proposition on how to study and solve the problem. The preliminary idea emerged
from the discussion at LMA and discussed at the last LSC seems viable.
From the discussion it
emerged that there would be a fringe benefit on top of controlling the dust
problem. Establishing a flow of laminar flow would also circulate dried air,
which would drag out the personnel breathing humidity (as well as their heath)
before it can come to the surfaces and reduce the water burden to be pumped out
before opening the gate valves.
For additional information about this report, contact Stan Whitcomb or Phil Lindquist