Weekly Report for
Week Ending April 13, 2006
Due to the LIGO Staffing Committee Meeting April 17, 2006,
there will be no LIGO Executive Committee meeting scheduled that day.
Special Announcements:
A new version of the LIGO Computer
Use Policy has been signed by the Directorate. It is available from the DCC at http://www.ligo.caltech.edu/docs/M/M020105-04.pdf.
Weekly Report Highlights
The quad controls prototype was
installed into the LASTI BSC Chamber on Thursday (See
below).
Telecons were held on Wednesday and Thursday
afternoons to run through most of the LIGO talks for the upcoming LSC meeting.
At a meeting of the LSC Executive Committee on Friday, the agenda was devoted
to discussion and approval of the talks.
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
- The new MOU with the University of Sannio at Benevento and University
of Salerno (TWG) with Attachments DAT, OPS, SUS and Z, has now been signed
by Saulson and will be forwarded on to Marx for
signature.
SITE TELECONFERENCE (Lindquist)
- There
was a site teleconference scheduled for Thursday, April 13, 2006. The following items were among those
discussed:
- MIT
Contract – We will issue a no cost extension. Funding for the second half of the
fiscal year should follow shortly.
- Livingston Science Education
Center –
Remarkable progress reported owing to good weather. Inspections of plumbing and electrical
scheduled for next week.
- Kinetic
Façade for SEC – A preliminary design review is scheduled for
April 27th via teleconference.
Additional funds may be required for a prototype.
- Safety
Audit at Livingston – A safety audit is scheduled at Livingston for Monday and Tuesday, 17th and 18th of
April.
- P-Card
Training – Scheduled for Wednesday at Livingston.
- There
are currently no open action items.
The list of assigned actions updated through December 01, 2005 (the
last update) will be found Here.
PROPERTY MANAGEMENT (Luna)
>
- Provided
assistance to the Detector Group (H. Armandula)
with shipping and preparation of a Commercial Invoice for US Customs
Clearance of one large mirror to Lyon,
France. Account Number LIGO.OPT - 5.4 -
NSFLIGO.FY02ON.
- Provided
assistance to LHO (J. Worden) in clearing a vehicle title from the
Treasure's Office.
- Prepared
Capital Equipment procedures to comply with the 5K threshold from Caltech
and the Federal Government.
- Coordinated
the termination of a Carnet with US Customs for the Gingin
equipment in Australia.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- No
special projects to report.
- Continued
to process presentations from March LSC Meeting.
- Performed
various searches on the database for certain words in the keywords &
titles category in order to remove sensitive material and information from
public access and viewing.
- Scanning
- Progress continues on contract closeout files.
- Activity:
|
Week Ending
04/13/2006
|
In
|
Out
|
|
Packages
|
15
|
7
|
|
Faxes
|
23
|
19
|
FINANCIAL SYSTEMS (Cronin, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Obtained
the credit that had been pending for the return of the Agilent
Pulse Generator shipped back in Jan. '06.
- Updated
the subcontracts database to reflect the change in PI and grant amendment
number.
- Attended
the Data Warehouse training session.
- Working
on the purchase of the van for the LIGO Livingston Observatory.
- Closed
out paid purchase orders and submitted the monthly purchase order close
out report for March 2005.
- Completed
change order #172 and #173 to Triad and submitted them for routing.
>From: Florence Kaufman <fkaufman>
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- Both
the Exploratorium contract and the contract with HPD will be modified as a
result of the decision to build a prototype of the kinetic facade for the
front of the LLO
Science Education
Center. The Exploratorium contract will be
increased by $10,000, while HPD has not yet submitted a proposal for their
effort.
- A
passenger van is being purchased for LLO.
This will replace a GSA pickup truck, which will be returned to the
GSA at the time the new van is delivered.
- Because
of shortened payment requirements by the Benton County Public Utilities
District, they have been set up to receive electronic funds transfers for
their payments. This method will
also be examined for DEMCO to eliminate the fee for credit card payments.
- A
no-cost extension to September 30, 2006, will be issued to MIT. The additional funds required for the
extended period will be added upon completion of a review of the funds
remaining on the contract.
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
- Worked
on the usual new trips, expense reports, reconciling, calendar reservations,
and itinerary entries.
>
>Dorothy Lloyd
- Met
with procurement and PMA staff members to provide procurement some
feedback on TechMart use within the PMA division.
- Processed
the usual requisitions for POs and payment request, and approved and
submitted the weekly incoming invoices to accounts payable for payment.
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
PROPOSALS and REPORTS (Lindquist)
- Budgets
have been provided to the NSF for the funding for the last half of FY 2006
Operations.
- An
annual report will be required for Operations due at the end of July. I will be preparing an outline with
assignments.
See Advanced LIGO below.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- The
next Staffing Committee meeting is scheduled for Monday, April 17. The
DRAFT agenda for the Staffing Committee has been posted on the SC web
page. All files for the Staffing Committee are up-to-date and posted on
the SC web page.
- No special activities to report.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
Nothing significant to report
this week.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary
of Commissioning Activities at LIGO Hanford
Observatory (compiled by M. Landry)
For the second week in a row, some commissioning
activities were pursued in the days, with science running in the eves, given
that LLO is in full commissioning mode. On Sunday we had a site-wide
power failure which took ~12h to relock
IFOs, and several days to fully recover from. A
crow
may have caused the outage. Duty cycles for the week were 45% on H1 and
64% on H2; the standard range and duty cycle update can be found here.
Commissioning/science mode highlights are bulleted below:
- coil
drivers are likely not the source of mid-frequency upconversion
- violins
were tested on H1, Q values extracted
- 4k
IFO WFS were found to be saturating
- useismic feedback was being recommissioned
on the 4k, and PEPI software debugged
- a SoHold servo was implemented on the 4k steering
mirror to maintain optic alignment when compared to its cage
- a spur
was seen in magnetometers at 123.995Hz
- we had a duotone
timing-monitor failure on H1
LIGO Livingston Observatory
(LLO) and Interferometer Operations (Zucker)
L1 interferometer in S5 (O'Reilly)
Commissioning work continues at LLO. Among the highlights:
- ISCT4,
the anti-symmetric port table, had been mounted on viton
rubber stoppers and shows improved isolation.
- WFS
bandwidths have been increased and we already have seen some improvement
in stability during construction.
- Investigations
of 60 Hz noise (no joy), and backscattering using new Coil Monitor boards
(no conclusions yet).
- New
DTT installation courtesy of Daniel
- SM
readback is fixed after being broken for a long
time.
- New
WFS4 diode and a new 2 mm SPOB diode awaiting installation.
- Some
new scripts to check interferometer health are being developed.
A major event during the week was a power outage on Tuesday. This was timed by fate to coincide exactly
with the arrival of the Ice Cube collaboration for a tour. It turns out that you can give a tour without
electrical power.
We recovered from the outage reasonably smoothly, after once again
rediscovering the stuck slider problem.
Commissioning is expected to wind down Friday night and then we can evaluate
how much better we are over the weekend.
L1 CDS (Bogue)
- Pulled
the old ultra10's and swapped in blade 1500's in the LVEA. Replaced the crt's with flat panels.
- Worked
with everyone else on the power outage.
Took the opportunity to review our ups setup. Control6 is currently on ups and can be
removed. The kvm
switches are not on ups which means we have no
video during a power outage.
- l1iocstat
wasn't starting up properly. I
think the scripts are correct but that they are running before the nfs mounts finish.
I put a sleep into the epics script to see if that would take care
of it.
- Worked
on boot issues with poplar, the part of DMT that runs most of our FOM's.
- Changed
all of the cds root passwords.
- Clearwater, the DMT nameserver, had disk troubles. Resolving this required a restart of all
of DMT.
LLO Outreach (Thacker)
4/7 assisted in tour for Ole Miss physics
department
4/7 worked with architect's interior
designer to down select interior colors for LIGO SEC
4/8 assisted at Tangi
Schools Math Science Partnership teacher development at LLO
4/11 assisted with Ice Cube Tour
4/11 presented at evening science fair, Nesom
Middle School, Tickfaw, La
4/12 developed and executed visitor program
for Clinton Middle School
4/13 developed and executed
visitor program for Hammond
East Side Upper
Elementary School (middle
school)
AdL Suspensions and Isolation, Outreach and Very Very Large Art (Romie)
Advanced LIGO Suspensions
Working on NSF Review material. Still have more to
submit. Hope to get to it today. Dwayne
has installed Solidworks, Algor
and Ansys on my desktop. I hope to start working on
it very soon, so that Dwayne may uninstall & reinstall Solidworks
on my laptop.
Working with Calum and the
others at MIT. I will be going there with Mark Barton next week.
LLO
Participating in a weekly meeting with HPD on the kinetic wall installation
on Thursdays at 2pm Central. We are working on scheduling a PDR with them for
sometime the week of April 24th. I have
been answering detailed questions on the blueprints and requirements from Jonas
at HPD, with the help of Allen Sibley.
LIGO Computing and Network Security (Roddy)
- At
LHO today-Saturday. Working on CDS
router/IDS with Dave.
- Attended
Educause Security conference in Denver.
General Computing (Giardina)
- Delivered
almost finished PC to Janeen. Email setup remaining.
- Site
power outage on Tuesday. Brought
down some essential GC servers after realizing power would not be restored
before batteries were drained. Did
not get all shut down cleanly before batteries supporting KVM and monitor failed. When
power returned, most came back online OK.
However, there were problems with DNS server loading NIC
drivers. With Shannon and Tom, we
were able to resolve the problem.
- Installed
and configured ntpd (Network Time Protocol
Daemon) on abundance.
- Apache2
VirtualHost problems on support.ligo-la.
Commented out a couple lines in config file and
restarted apache.
- other
usual user requests and support
LDAS Support (Giardina)
- ejected
tapes for shipment to CIT and imported tapes into L700
- u1d9@t3-1
failed, replaced with u1d8 from spare T3-13, rebuilt raid array on T3-13
- ejected
tapes for storage and imported tapes into L700
Data Analysis (Yakushin)
Storage/Condor/LDAS admin:
- Due
to the fire outside the site, we had a several hour power outage on
Tuesday. Since we got an advanced notification of the event, the LDAS
equipment was cleanly shut down before the outage happened.
- There
is a tape (LLO0938) stuck in the drive 44 of the tape robot. SUN
technician should come to repair it today.
- u1d9@t1
failed and was replaced with a spare.
- Downloaded
WNB1_BN_S5 burst MDC frames from PSU to LLO and CIT.
Data analysis:
- Continue
polishing APS presentation and participating in the preview telecons.
- Continue testing and tuning the coherent waveburst version on S4 data.
Initial LIGO Detector Science & Engineering (Coyne)
No report (returning from Italy)
40-Meter Interferometer (Weinstein)
IFO Commissioning
- Monica
and Dan continue to work on the noise budget, including contributions from
seismic noise, optical levers, mode cleaner angular noise, frequency
noise, and electronics noise (coil drivers, DACs,
etc). They tried taking a calibrated noise spectrum with the FPMI, but the
AP166 RFPD signal was too noisy. Under investigation.
IFO Modeling
- Monica
continues to work on improving her e2e simulation of the 40m/AdLIGO
configuration, with full 5 length DOF control system. She finds that the
system won't stay in lock with all 5 DOFs under
control, with radiation pressure on all mirrors. Under investigation.
DC Detection and Vacuum Squeezing Development
- Ben
is managing the acquisition of control electronics to be bought/made/designed
for the DC readout system, including custom boards (TT-PZT steering mirror
driver board, DCPD in-vac board, DCPD satellite
board, OMC driver board), cables, and PCIX-based
ADCs/DACs. It looks like we could get everything
together by early June.
- Jay
is working on the design of the TT-PZT steering mirror driver board.
- Ben
sent out DCPD in-vac board and DCPD satellite
board out to PCBexpress for fab.
They should be back next week for stuffing.
- Jay
procured and tested the QPDs for the DC readout
alignment control system.
- Steve
and Go put together a new open frame equipment
rack for the squeezer electronics, taking power from a new circuit
(unconditioned power).
- Go
got his second harmonic generator (SHG) working. He replaced the shaky
6-axis mount with a 3-axis positioner, realigned
and mode matched, and then easily locked te SHG. He swept the temperature from 81 to
92degC for phase matching. The cavity lock is stable for hours. At
maximum, he's getting 400-500 mW of green light
out of 2 W input beam. He expects up to 600 mW with improved mode matching and alignment. The
intensity stability is ~1-2% at peak output.
Electronics, Controls, Computers
- Rob
made major changes to the length control and lock acquisition front end
code, including: (a) fast input matrix Ramping; (b) "bait &
switch" which allows one to switch from a demodulated diode signal to
some calculated signal, during lock acquisition; (c) a new lock
acquisition mode word which summarizes the state of the most relevant lock
acquisition settings with a set of bits that can be turned on or off via
scripts and enabled wuth a user request button;
(d) the "moving zero" filter code that compensates for the
optical spring peak as the CARM offset is reduced is now more flexible;
(e) and the code is generally cleaner and easier to read.
- The
MC WFS QPDs are probably damaged from too much
light power. Ben went looking for spare QPDs,
but found none. He plans to order a bunch for the 40m and the rest of the
lab; 8 week lead time.
- A
breaker was accidentally switched on the electronics rack housing the
digital suspension system. After some struggles, the system was restored.
Lab Infrastructure
- Steve
is thinking of how to add a mezzanine optical table in the PSL enclosure to
provide more table space for the mode cleaner reflected, mode cleaner
transmitted, AP and SP beamlines.
- Osamu
and Rana are at LLO to help with commissioning
activities.
- Bob is at MIT to help with the quad suspension
controls prototype at LASTI.
Thermal Noise Interferometer (Black)
We have performed several tests and are
becoming increasingly convinced that the new, higher noise floor really does
originate in SAC. The logical conclusion is that this is due to the ring
dampers, which models predicted would not happen. Dennis Coyne is helping us by
taking a closer look at the FEA models, and we have gotten in touch with Andre Gretarsson.
Also, we have been improving the general
state of the lab after the February safety inspections. This week we bought
some new laser goggles and beam viewing equipment to replace old, worn out
items.
LASTI (Ottaway)
Controls Prototype
This week the local LASTI staff and a lot of visitors prepared the Quad
Controls Prototype mounted on the solid spacer for installation into the BSC
vacuum tank. In addition to this, quad
alignment fixturing was tested and the suspension was
accurately aligned to a fixed reference within a couple of hundred microradian accuracy.
Potentially this number could have been a factor of three lower but the
measurement was limited by the suspension damping on the quad. This remains an outstanding issue that will
be looked at next week. The suspension
frame was characterized using the ossems on the top
mass as a shaker. A 45 Hz resonance was
confirmed on the frame resonance.
The quad controls prototype was installed into the LASTI BSC
Chamber on Thursday.
Double Triple Experiment
Laurent measured a very clean transfer function from the top mass to the
bottom mass from 6 Hz to 35 Hz. We are still plagued by an unknown noise bump
between 15 Hz and 100 Hz that may be coming from the PSL (It is not in the
VCO). This will study this further next week.
Laser Amplifer for PSL Power Upgrade
All components have finally arrived. We are studying how to properly align
main beam through the amplifier and Faraday rotator for the single pass
experiments, so as to aid in the double/quad pass ones.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Yamamoto)
QuadFP (Hiro)
Modifying QuadFP, advLIGO
high power arm simulation, to use modal field for ASC study is still going.
Stationary IFO Simulation (Hiro, Melody)
Building frame and builind SIS is still going.
Mechanics Simulation for Adv.LIGO (Sany Yoshida)
Based on Mark Barton's model, created an e2e box file to
simulate the AdvLIGO Mode Cleaner's small optic
suspension. Using Mark's mathematica
code, created a state space matrix and included it in the e2e box file. The
results of the initial test with impulse inputs to the suspension point seem
reasonable.
40m modeling (Monica)
PSD simulations have been performed with and without seismic noise in order
to test the control loops. Some changes
in the LSC code have been made to try different strategies for the in-lock
state (different error signals and DC signals).
The optical response of the full 40m has been simulated controlling the
5 degrees of freedom.
Data Analysis Activities (Lazzarini)
Brown:
- Prepared
APS talk on S5 BNS search
- Learning
about Markov Chain Monte Carlo methods for parameter estimation
- Worked
with Diego on physical template bank search
- Working
on EMRI project
- Started
looking at LISA supermassive black hole search
- Wrote
undergraduate colloquium for Whittier
College
Chatterji:
- Incorporating
comments I have received regarding my APS talk and associate technical
document on the early S5 online Q Pipeline search.
- Continued
development of Q transform based parameter estimation.
- Identifying
a potential three hour segment of S4 H1 h(t) data
for a proposed initial data exchange with Virgo.
Dupuis:
- analyzing
recent S5 data (up to 8 April) for known pulsars
- produced
high resolution spectrograms of H1 and L1 data for March (see at bottom of http://www.ligo.caltech.edu/~rejean/S5/j0537/
apr4/index.html)
- verified
absence of anomalous signals in some excitation channels
- working
on developing a code to fold the h(t) data to see profile of signals
Mandic:
I have completed the checks of the S4 all-sky stochastic analysis, requested
by the review committee. This includes software injections, estimate of timing
errors, bayesian analysis of the calibration
uncertainty with different priors on Omega_GW,
post-processing with different data quality cuts (and with no cuts at all) etc.
The tests did not reveal any problems with the S4 all-sky stochastic result.
Mendell:
StackSlide S4 results for the April APS meeting
will be (were) presented at the LSC telecon, Thu.
Apr. 13, 2006.
Shawhan:
- Reviewed
pulsar analyses and S2 F-statistic paper.
- Worked
on my APS talk, and gave other people comments on theirs.
Sutton:
My main occupation this week was working on my APS talk covering the burst+stochastic searches.
I've been working on an improved power spectrum estimation algorithm for xpipeline. The
improved algorithm is designed to follow the noise floor for broad frequency
bins (our burst analysis works with very short integration times) and suppress
the effect of strong narrow lines.
Yakushin:
- Continue
polishing APS presentation and participating in the preview telecons.
- Continue
testing and tuning the coherent waveburst
version on S4 data.
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS
Focused on getting all compression modes described in the frame spec working
(PR#1828). Corrections to frameCPP have been made.
Testing uses both frameCPP and FrameL
to verify the correctness of the encrypted data. The data has been decrypted
and compared to the original data. Errors discovered with FrameL
during this process have been reported to the Virgo group for correction. The
64-bit versions of the code still need testing.
Discussed tools and techniques needed to migrate 32
bit framebuilder code to 64 bits with Alex Ivanov and Rolf Bork. Will need to
prepare a 64 bit version of the frameCPP for CDS once
the testing mentioned above is completed.
TCLGLOBUS
Of the 46 function that comprise the Globus GSSAPI
package:
- 2
are not supported as they have declarations but no definitions
- 44
have been documented and tested.
- 4
remain to tested (gss_wrap, gss_unwrap,
gss_mic, and gss_verify_mic)
GRID COMPUTING
Evaluated the distribution of OSG Production sites for
batch system and cluster size at the request of the LSC Computing Committee.
Top level statistics are:
Total Number of Sites: 52
Total Number of VOs: 25
Total Number of Batch Slots: 19078
Number of Condor Batch System
Sites: 26
Number of PBS Batch System
Sites: 18
Number of SGE Batch System
Sites: 3
Number of LSF Batch System
Sites: 2
Number of Unknown Batch System
Sites: 3 (Probably fork job manager
only)
The quantity of most interest to the CompComm was
the fraction of sites using condor for the batch system (0.50), managing (0.38)
of the resources.
Assisted system administrator at NERSC on supporting VDS on OSG NERSC- PDSF
compute nodes.
Installed OSG release 0.3.7 on LIGO-CIT-ITB cluster and Installed VDS 1.4.4
on submit host. Experienced problems submitting the binary inspiral
jobs after the client side upgrade. Have brought this to the
attention of the VDS group but need to further evaluate before handing off to
them for fix.
Validated three OSG 0.3.7 ITB sites with the Inspiral
pipe application using previous version of submit tools from VDS.
Attended OSG telecom on OSG 0.3.7 validation results.
Hardware Systems (Anderson)
Caltech
(Phil Ehrens)
- Added
throttling code to log_mon.tcl and debugged the
script further. Documentation on wiki reflects the current state of the script
accurately.
- Updated
wiki pages dealing with machine configuration
issues for both Linux and Solaris machines.
- Installed
Solaris 10 update 1 on the Sun v40z machine in the ldas-
dev system.
- Installed
FC4 on the Sun x2100 machine in the ldas-dev
system.
- Various
certificate management tasks.
(Erik Espinoza)
- Shipped
3 nodes to ASA Computer for repairs.
- Configured
Sun Opteron (v40z) for LDAS development.
- Configured
FC5 on Dell D610 and passed along info to Kent Blackburn.
- Investigating
update to BIOS for new Opteron cluster nodes
(currently 1.0b, new version is 1.1), asking Supermicro
for details.
- Assisted
Phil in deployment of Sun x2100 for LDAS development.
- Node68
crashed due to bad memory. Subsequently a hard disk died. The machine is
now running.
- Node11
died, talking to tech @ ASA Computer. Machine moved to the end of address
space (node325).
- Installed
Linksys Gig-E 24 port switch w/ Stuart.
- Moved
Temptrax to rack w/ Linksys.
- Tracing
NIS+/Glibc bug (FC4 w/ Latest Update). Filed bugzilla #188761.
- Sent
contact @ Western Digital serial numbers for proper tracing.
- Working
on ldas-kickstart for Livingston.
(Stuart Anderson)
- Decommissioned
two Foundry network switches and installed a new 24- port Cisco switch.
- Reorganized
some of the equipment in 215 Synchrotron so that two racks of old
equipment are now free to be shipped to the Observatories.
- Working
with Dan to further characterize SAM-QFS performance after deleting
several million files.
- Reworked
the S5 plots to monitor the delay in transferring frame files over the
network (http://www.ldas-cit.ligo.caltech.edu/lag.html).
MIT
(Keith Bayer)
- Rebooted
ldas-pcdev1 & ldas-sundev1 with updated packages
Livingston
(Igor Yakushin)
- Due
to the fire outside the site, we had a several hour power outage on
Tuesday. Since we got an advanced notification of the event, the LDAS
equipment was cleanly shut down before the outage happened.
- There
is a tape (LLO0938) stuck in the drive 44 of the tape robot. SUN technician should come to repair it
today.
- T3
disk u1d9@t1 failed and was replaced with a spare.
- Downloaded
WNB1_BN_S5 burst MDC frames from PSU to LLO and CIT.
(Dwayne Giardina)
- Ejected
tapes for shipment to CIT and imported tapes into L700.
- T3
disk u1d9@t3-1 failed, replaced with u1d8 from spare T3-13, rebuilt raid
array on T3-13.
- Ejected
tapes for storage and imported tapes into L700.
Hanford
(Ben Johnson)
- LHO
site-wide power outage (unplanned) occurred this past Sunday. The LDAS
systems ran out of UPS power, but there were no hardware faults caused by
the outage. Software is currently running.
- I
have found *no* CRC mismatches at LLO or LHO that were not associated with
either a front-end or framebuilder reboot, since
Alex started testing his new code.
- Talked
with Chris Messenger about GEO segment publication. My two action items
are to send him information about the bulkpublishstate
scripts, and to send him and Martin Hewitson
info about inserting their own/correcting GEO data quality information.
- Got
the old SunBlade 100 (old admin machine) running
Sol10 U1. I was also able to get it to use Sun's Update Manager in sort of
the "public" mode (a.k.a. no support contract required).
General Computing (Wallace)
Lazzarini/Roddy
A new version of the LIGO Computer
Use Policy has been signed by the Directorate. It is available from the DCC at http://www.ligo.caltech.edu/docs/M/M020105-04.pdf.
Jay and Stan will circulate an
announcement in the near future to LIGO Laboratory personnel.
MIT
(Keith)
- Ordered
backup server
- Working
on misbehaving windows laptop
- Working
on linux/sun automounting
- Visitor
support
- Configuring
printing support on new linux opteron box
- Ordered
various spare parts
- Added
new urops to gc:
Forrest Funnell, Brian Pepper
Livingston
(Dwayne)
- Delivered
almost finished PC to Janeen. Email setup remaining.
- Site
power outage on Tuesday. Brought
down some essential GC servers after realizing power would not be restored
before batteries were drained. Did
not get all shut down cleanly before batteries supporting KVM and monitor failed. When
power returned, most came back online OK.
However, there were problems with DNS server loading NIC
drivers. With Shannon and Tom, we
were able to resolve the problem.
- Installed
and configured ntpd (Network Time Protocol
Daemon) on abundance.
- Apache2
VirtualHost problems on support.ligo-la.
Commented out a couple lines in config file and
restarted apache.
- other
usual user requests and support
(Shannon)
- Attended
Educause security conference.
- Working
on router and IDS with Dave Barker.
Hanford
(Christine)
- On
Sunday morning a crow going after eggs in another bird's nest flew in to
the power transformer for the site and caused a power outage. Once power was restored all of the GC
network and computers came back on their own without any problems. I did have to run fsck
on two file systems on two servers.
Only other problem was that when the phone vlan
was added to the GC switch, the configuration was not saved to
memory. As the phones came back
online they started taking IP addresses from the GC DHCP server. As soon as the phone vlan
was re-entered and saved to memory this time, I was able to release the IP
addresses on the GC DHCP server.
- Updated
the security patches on the mail server.
- Still
working on the MRTG graphs of the network bandwidth.
- Finished
reworking the FY06 GC budget.
- Started
preparation to setup an IDS and port monitoring system.
- Writing
a PR to purchase more disks for the user directories and an updated backup
system.
CIT
(Veronica)
- LSC: Prepared the website for the June
meeting. Installed the scripts and
the backend for the registration and the online credit card processing
application. Updates to the database
of the LSC-reviewed papers. Update
of the LSC website and LSC-related mailing lists. Updates of the March meeting
presentations list.
- LIGO: Updates of the CIT and MIT
homepages. Support of the upcoming AdvLIGO review.
Videotaped a presentation by Kenji Numata
and burned DVDs for Kip's group. Helped Julie with setup of Jay's
website. Updates of the roster
database and mailing lists.
(Christian)
- Linda
turner - Finished transferring all of Linda's files and settings back to
her original laptop.
- Millikan - Replaced black toner cartridge on HP 5500
printer Ken Mailand - Restored missing files on
a test workstation for Ken.
- I
did an inventory on printing supplies.
- I'm
working on updating all of the visitors' workstation with the standard Ligo image.
- Other
misc.: Continued onsite software/phone support.
(Mike)
- Finished
up DCC Dual core server. This server is now ready for production. I spent
a lot of time trying to get ghost to work on these servers; using the SATA
controller card & hard disk that came pre-loaded with this server did
not work. I ended up installing an IDE hard disk using an IDE slot on the
motherboard. I am now able to use the ghost software to back up the OS. I
am using this same configuration for the PDMWORKS server.
- Started
configuring another Dual core server to replace PDMWORKS server. I am
working on getting the VaultData moved over, and
installing PDMWORKS Server side software. This is an on going project.
- Doing
research on how to backup the PDMWORKS Vault. So far it looks like there
is know way to backup and restore individual files from the Vault. The
only way to insure you have a reliable backup,
you must stop the PDMWORKS service, and then copy over the VaultData directory to another source. I have created
a DELETE project with in the Vault for Solid Works users to move files
they know longer need, rather than deleting them. I have also disabled the
delete option to insure data is not deleted by accident. I am still doing
more research on this.
- Continued
work on the Spam Filters, searching for false positives.
- Came
across some issues with the mail servers, after many attempts running
scripts and killing processes I ended up having reboot both servers. This was a last resort. Everything seems
to be running OK for now.
- Other
misc. user support.
(Larry)
- Worked
a number of procurements. Started getting things together for the SUN
matching grant purchase. Found a
few new items to look at before making the purchases for conference
equipment. Always something new coming out.
- Worked
on a number of DCC issues. Presently, part of the file system is mirrored
at another location in order to improve performance for web access to the
documents. This process will continue until the new DCC system is up and
running.
- Worked
a couple of document issues. Helped in making changes to the updated AUP
document. Everyone will be required to reread the document and sign off on
it when it goes out.
- Spent
part of the week attending the Educause
conference. It was good to meet a number of others having the same issues
and checking out their solutions. Spam and phishing
were two of the top subjects discussed. Overall we are pretty much in-line
with other educational institutions as far as solutions being used. It would have been nice to have
representatives there that are involved with large labs or projects
similar (in size) to LIGO.
- Assisted
Mike with his various projects.
- Worked
a couple of mailserver issues. Helped Mike take
care of a process problem.
Mail Statistics for April 6-12, 06
|
Mail Statistics
|
April 13, 2006
|
|
Rejected Messages
|
42,762
|
|
Virus Messages
|
2,097
|
|
Accepted Messages
|
58,095 (many spam
messages getting through)
|
|
Total Messages
|
90,857
|
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Systems, Management
Kickoff of work with vendor for fabrication of HAM-SAS.
Performing Monte-Carlo studies of cost and schedule.
Seismic Isolation
Installation of integrated quad suspension and seismic
spacer in LASTI.
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
Advanced LIGO Suspensions
Working
on NSF Review material.
Still have more to submit. Hope to get to it today. Dwayne has installed Solidworks,
Algor and Ansys on my
desktop. I hope to start working on it very soon, so that Dwayne may uninstall
& reinstall Solidworks on my laptop.
Working
with Calum and the others at MIT. I will be going there with Mark
Barton next week.
From: Jay Heefner jay@ligo.caltech.edu
LASTI HEPI
- Binary IO board received.
Chassis assembly started.
- Anti-Image Interface board
design completed and set out for fab.
- Anti-Image front panel
designed and will be sent out for fab tomorrow.
- Preparing for an early May
installation.
AdL Quad Controls Prototype
- Supporting testing of quad
controls using LIGO control system installed last week.
Core Optics
From: Helena Armandula ahelena@ligo.caltech.edu
LIGO I COC's
Shipped 2ITM04 and 3 - 1"dia. mirrors for scatter
characterization. Cleaning up files and
placing backed up LIGO I documentation in the DCC.
Silicate bonding
Participated
in a telecon with C. Cantley
and Norna giving technical support to Supriyo Sinha(from Stanford) on details of silicate bonding procedures.
The telecon was followed-up with an interchange of
E-mails.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
I have managed to get the Xilinx software going and talking to a Simulink
model but have not gotten a filter to work yet.
Otherwise I have been
scanning in vendor quotations for the up-coming baseline review.
Auxiliary Optics
From: Michael Smith <smith@ligo.caltech.edu>
TCS
I
completed a conceptual design in ZEMAX for Hartman sensor beams in the
non-folded IFO to sample the ITMs and the BS from within
the recycling cavity, and the HR faces of the ITMS. I have added the Hartman
sensor beams into the SW layout of the vertex.
WBS
I
am in the process of updating the AOS WBS dictionary.
Controls, Data systems
From: Rolf Bork rolf@ligo.caltech.edu
- We installed the new quad
controls at Lasti this past week. Equipment included a PCI-X I/O chassis
w/ADC and DAC modules, a dual Opteron front end
controller, and a new FrameBuilder. The new timing
system was also installed.
- We are continuing to work on
the new Hepi system, which we plan to install
the week of May 8. We will also be installing the new Myrinet
network switch (new net is already operating between the quad controller
and Framebuilder, but without a switch). I have
a GPS network time server on order as well, which has a one pps output to run the new timing system. This should
allow us to remove all remaining VME equipment on the next visit.
- We are adding software to
support FIR filters in the front end controllers, similar to the standard
IIR filters that were developed for LIGO.
We plan to support standard FIR filters, polyphase
FIR filters and adaptive filters. At least the first two will be ready for
the HEPI code install in May. The adaptive filters will probably come
later.
- Continuing
to work on the software which generates realtime
front end and EPICS code from MatLab files.
While this software successfully generated the code for the quad
suspension, it still needs to support more parts, such as polyphase FIRs, to produce
the HEPI software.
For additional information about this report, contact Stan Whitcomb or Phil Lindquist