Weekly Report for
Week Ending April 6, 2006
The LIGO Executive
Committee Agenda for Monday,
April 10, 2006 will be:
(Meeting time: 10:30 am Pacific Time)
1. Announcements
2. Comments
on Weekly Report
3. LSC
Issues (Saulson)
4. LIGO
Lab Operations
- Administration
(Lindquist)
- Sites
(Raab, Zucker, Shoemaker)
- Commissioning
(Fritschel), Detector (Coyne)
- Campus
Research Facilities
- 40
Meter (Weinstein)
- TNI
( Libbrecht)
- LASTI (Shoemaker)
- Data
Analysis and Computing (Lazzarini)
5. R&D
and Advanced LIGO (Shoemaker)
6. CHANGE CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION AS
NEEDED
Special Items:
- Preparations
for Advanced LIGO Review (May 31 – June 2)
Special Announcements:
Weekly Report Highlights
No report.
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
SITE TELECONFERENCE (Lindquist)
- No
site teleconference was scheduled for Thursday, April 6, 2006.
- There
are currently no open action items.
The list of assigned actions updated through December 01, 2005 will
be found Here.
PROPERTY MANAGEMENT (Luna)
>
- Provided
assistance to the Detector Group (C. Torrie)
with shipping of 1 crate to MIT.
Account Number LIGO.PRLAS- 5.16-NSFLIGO.FY02CA.
- Provided
assistance to the Detector Group (R. DeSalvo)
with shipping and the preparation of a Commercial Invoice for US Customs
Clearance of four accelerometers, two accelerometer drivers, and a balance
rod to GALLI & MORELLI in Italy. Account Number
LIGO.TEC-5.16-NSFLIGO.FY02ON.
- Provided
assistance to the Detector Group (H. Armandula)
with packing, shipping, and the preparation of a Commercial Invoice for US
Customs Clearance of an aluminum cap (old GEO cap) to Rutherford Appleton
Laboratories, UK.
Account Number LIGO.SUS-5.10-NSFLIGO.FY02ON.
- Provided
assistance to T. Gunter (LHO) with the shipment of five Laptops and three
Projectors to Caltech. Account
Number LIGO.DIR 1.1.1 NSFLIGO.FY02ON.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
- Nothing
significant to report.
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- Attempting
to get back up to speed after two weeks of personal leave (with very
little sleep). Began processing
large batch of presentations from March LSC Meeting.
- Scanning--Progress
continues on scanning of contract closeout files.
|
Week Ending
04/06/2006
|
In
|
Out
|
|
Packages
|
13
|
1
|
|
Faxes
|
28
|
23
|
FINANCIAL SYSTEMS (Cronin, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Issued
purchase orders for various goods and services for individuals at LLO,
LHO, MIT, and Caltech. TechMart requisitions are
being submitted directly from individuals at the LIGO Livingston
Observatory, the LIGO Hanford Observatory, and Caltech.
- Received
the invoice from the University
of Pisa and working
on completing the order to request for the wire transfer.
- Received
the current A-133 from the University
of Florida. The only
pending to be received is the University
of Michigan, which
is still in the works.
>From: Florence Kaufman <fkaufman>
- Completed
report for fiscal year 2006 Operations Award as of the end of March 2006
and posted it to the network.
- Completed
report for Outreach Award as of the end of March, and posted it to the
network.
- Completed
report for Visitor Award as of the end of March.
- Prepared
a summary of expenditures for Equipment, Supplies and Subcontracts for the
Detector accounts for 1998 to 2002 for Dennis Coyne.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- The
LLO SEC remains ahead of schedule due to good weather. Only the front of the building remains
to be enclosed.
- The
contract for Galli & Morelli
has been reviewed by the NSF, and the contract was found to be acceptable,
but they asked that several flowdown clauses be
added. A review of these clauses by
the Office of Sponsored Research concluded that many of them applied to a subaward rather than a subcontract. The clauses were examined by Dick
Seligman and Ed Jasnow, and several were
removed. This revised list was sent
to the NSF for concurrence.
- The
costs for the repair of the traffic gate at LLO and damage caused by
Hurricane Katrina will be submitted to Caltech's insurance group in the
Treasurer's Office for reimbursement.
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
- Worked
on the usual new trips, expense reports, reconciling, calendar
reservations, and itinerary entries..
>
- Entry
of NSF proposal for video instructional materials into FastLane
is pending return of Dale Ingram. Caltech
paperwork is being processed in parallel.
>Dorothy Lloyd
- No
report.
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
PROPOSALS and REPORTS (Lindquist)
See Advanced LIGO below.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- No special activities to report.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
Primary effort has been working with Rich Riesen
to document the close out of the previous safety audit action items and to
prepare the next audit agenda (LLO safety audit is scheduled for the 17th and
18th of April).
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary
of Commissioning Activities at LIGO Hanford
Observatory (compiled by K. Kawabe)
Up until Monday Apr/3/2006 both IFOs were running
fine, meeting the S5 target duty cycle (H1 93%, H2 90%). From Monday on, commissioning activities in
coincidence with the LLO commissioning break have been eating up the duty
cycle: PEPI, coil driver up conversion measurement, and violin Q measurement,
all for H1. Also new SOHO
servo was implemented in H2.
Excavation
work for a new bypass nearby LHO has started, making high seismic spikes
quite frequent. This is expected to
continue for several weeks.
This week's range and duty cycle update can be found here.
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
L1 Interferometer in S5 (Zucker)
We are in the middle of a commissioning break. Top tasks include rework to
HEPI control algorithms, increase of WFS alignment control bandwidth,
rearrangement of dark-port and pickoff optics to optimize SNR of auxiliary
length sensing, and vibration isolation of the dark port tables to remove
spurious seismic/acoustic interactions.
Spectacular progress will be reported next week.
Safety and Security (Riesen)
Found no site nor laser safety concerns this period.
LLO Outreach (Thacker)
4/1
Washington Parish Math/Science Partnership teacher professional
development; program plan & execution
4/4
Gilbert Junior High school visit; program plan
& execution
4/5
Visit to Springfield
High School; program
plans & execution
4/6
Frost Junior High program plan & execution
AdL Suspensions and Isolation, Outreach, and
Enormous Art (Romie)
Advanced LIGO Suspensions
Working on NSF Review material.
Solidworks on my laptop is badly in need of an uninstall/reinstall. I will be weeding through my 3100 Solidworks files to make file corruption less inevitable,
after a fresh install. Currently, my Solidworks
Explorer and PDMWorks lock up. Calum
has been quite helpful in working around my laptop's infirmity. Dwayne and
Shannon are working to install software on a new desktop for me.
Art
Held a meeting about the kinetic art exhibit last week
with HPD, the contractor, and the architect, and the designers. We will
have a weekly meeting on Thursdays to keep abreast of the progress.
General Computing (Giardina)
- I
finished software installs on Janeen's new
PC. Connected to license server
with help of Mike Pedrazza and Shannon
- changed
a users GC password
- security
server Windows XP updates
- I
spoke with Kantech tech support about the bugs
we have experienced with the gates.
They told me that we most likely have a wiring problem. I will pursue further.
- other
usual user requests and support
LDAS Support (Giardina)
- ejected
tapes for shipment to CIT and imported tapes into L700
- rebuilt
raids on T3-13 and T3-16
- replaced
hdb in node202
- node2 and node81 were reporting filesystems
marked as read-only, reboot seems to have cleared it up.
- node99 was non responsive. Removed from rack to troubleshoot and
not all LEDs would come on. Removing the case showed that metal
bracket fell across the motherboard.
Will try a new motherboard soon.
Data Analysis (Yakushin)
Storage/Condor/LDAS Admin:
- Condor
was upgraded to version 6.7.18.
- We
resumed using /archive.
- The
attempt to upgrade the firmware on the tape drive was unsuccessful: most
likely a hardware problem with the engineer's laptop. We shall try it
later again.
- Working
to apply my old database archiving scripts to the segment database.
Data analysis:
- Continue
polishing APS presentation.
- Continue testing and tuning the coherent waveburst version on S4 data.
Initial LIGO Detector Science & Engineering (Coyne)
CDS
see also the CDS weekly meeting minutes in the commissioning archives
Rolf Bork
Alex has been working with
Barker on getting the PEPI control software running at LHO.
DMT
No report
Optic Contamination & Loss
Bill Kells
I am continuing the
investigation/analysis of the contamination on 4ITM07, with regard to its
particulate nature. This has expanded to
consideration of the general cleanliness situation in LIGO, both now and for AdL. It is becoming
very clear that our combined understanding of LIGO I in situ performance
(perhaps beyond what we need to know for LIGO I requirements) is critical to
guide AdL. One
new direction in the analysis is to revisit the scans and data we have on AR
side absorption, as well as the previous correlation we have seen in scatter vs absorption [points]. For instance if the localized absorption on
the HR surfaces is indeed from some "carbonized" dust then we might
expect its nature to be quite different on the AR side (~not carbonized, yet
present).
Much work continues to pin down the character of the ITM07 loss/contamination.
Previously we have done a couple of OTF
scans of this HR surface while simultaneously montioring
scatter as well as absorption. However
that was early on (last summer), before we were as puzzled as we are now at the
character of the contamination. We are
reviewing the data from those scans to update conclusions. Also it is evident that an upgrade of the
technique ought to be able to determine whether the contamination is
"particle like" or "film like". New measurements to accomplish this are being
planned.
40-Meter Interferometer (Weinstein)
IFO Commissioning
- Osamu
and Rana are at LLO to help with commissioning
activities.
- Dan
is diagnosing the MC WFS's, which Osamu reported
to be noisier than before and which Dan suspects were fried by the beam
during some work a few weeks ago. He has measured OLTFs
of the MC alignment servos, which look ok but he doesn't know what they
should be compared to. He and Ben will replace the WFS photodiodes with
new ones to see if there's a difference. Ben is currently looking for the
stash of YAG444A Quad photodiodes that they used to have at Wilson House.
- Dan
and Monica continue to develop the noise budget software. They are in the
process of calibrating the DARM signal using a simple Michelson.
IFO Modeling
- Monica's e2e model of the full 40m control plant seems
to work well. She has measured the OLTFs for all
five length control loops. The CARM loop is derived from the
signals at POX and POY, and there is an offset (~ 1 pm) from full arm
resonance. She is working on undertanding and
reducing this. She can now lock all five degrees of freedom, and it
maintains lock throughout the 2-second simulation. It takes a good
fraction of a second for the fields and the mirrors to reach equilibrium;
under investigation.
DC Detection and Vacuum Squeezing Development
- Rob
and Sam glued the OMC PZT-mounted mirror bracket on to the OMC, and locked
the OMC to a pickoff beam from the main IFO REFL port. They measured the
finesse to be ~ 500 (design is ~ 100); the discrepancy may be due to the
polarization of the input beam being wrong. They were not able to lock the
OMC to the beam from the small crystal laser, due to too much noise on the
laser.
- That
laser was sent out for evaluation/repair by Steve.
- Next,
Rob will assemble the output mode matching telescope (OMMT) and align the
whole DC readout beamline (PZT steering mirrors,
OMMT, OMC, DCPD) together.
- Jay
has completed a draft of the DC readout control system layout and comments
have been received. Design of the system and the boards needed for
controls should resume next week.
- Ben
reports that the layout of the DCPD Satellite board is nearly complete.
He's just adding some annotation and test points, and it will be sent out
to PCB Express for fab.
- Go
assembled his second harmonic generator (SHG) in its oven and enclosure,
heated it up, and mode matched the PSL-picked-off light onto it. He
observes green light. He is having difficulty locking the SHG cavity
because of an oscillation somewhere. He put in a notch at 5 kHz, but a big
120 Hz oscillation remains; and there's lots of acoustic noise from the
HEPA filter. Work in progress to lock the SHG cavity.
Electronics, Controls, Computers
- Ben
replaced the 166MHz I&Q demod board in the
LSC rack. It was used for the AP 166 signal, but was very noisy. Ben was
able to find anything wrong. Meanwhile, the SP 166 demod
board was put in its place, so Ben returned this board to the SP 166 slot
in the rack. Later, he will do a quick measurement of conversion loss, and
check it against the other 166MHz board, and the Minicircuits
spec.
- Matt
wrote a suite of IFO Test perl scripts for doing
automated IFO diagnostics. He tested them at the 40m lab, then he and Vuk went off to
the sites to install them. Rana exercised a mode
cleaner test script at the 40m, and Rob is writing a new RestoreXarm script that makes use of the new suite. Rana and Rob plan to develop more scripts to test all
the various LSC/ASC systems (oplevs, WFSs, IFO length control loops in various
configurations).
- Rob
rewrote much of the LSC lock acquisition code to make use of a state
vector in which the various elements of the IFO configuration are encoded
in bits. This replaces the clunky " Mode 1,
Mode 2" of lock acquisition. Rob augmented Matt's IFO Test suite with
some code that reads and changes the bits in a lock acquisition state
vector, to make it easier to test, diagnose, and drive lock acquisition
sequences from scripts. Also, the input matrix code is now part of the LSC
code instead of being a separate routine. All of these changes are still
under test.
- Rana installed a new version of StripTool,
and used it to monitor the slow drift of the PSL power. This is basically
a replacement for having a fancy mechanical stripchart
recorder.
- Steve
noticed that the PSL FSS has been drifting out of dynamic range, requiring
some jiggling of the sliders. He is documenting the symptoms to diagnose
the problem.
- Our
operator control computers have various kinds of problems, and the whole
system needs to be fixed up. Rob is compiling a list of known problems in
the 40m wiki.
Lab Infrastructure
- The
maglev turbopump failed on Tuesday, and the
pressure in the main vacuum rose to 2.3 mtorr
before Steve noticed it. This underscores the need for a working alarm
system. Steve doesn't know why it failed, but he was able to restart it.
The software interlocks closed the main valve and protected the RGA.
Meanwhile, the new replacement maglev is ready to be swapped in when
needed.
- Steve
has called in electricians to add more AC outlets around the lab
(especially near the PSL) for auxilliary
equipment (such as Go's squeezer electronics)
without having to run long extension cords and power strips. This is the
last action item that came up during the safety inspection in January.
- Bob will be at MIT next week to help with the quad
suspension controls prototype at LASTI.
Thermal Noise Interferometer (Black)
Nothing significant to report.
LASTI (Ottaway)
Double Triple Experiment
This week we successfully installed a loop gain normalization stage that
improves the reproducibility of the measurement. In addition to this we clean
up the optical train to remove a time varying offset in the PDH signal.
Controls Quad Prototype
Jay, Rolf and Alex have been visiting this week to implement the LIGO
controls for the Quad. The Quad is being prepared for installation into the
vacuum next week. In addition to this Brett is performing a modal test of the
frame.
Advanced LIGO Internal Seismic
Assembly of stage 0 and stage 2 is rapidly progressing with Lee Cardenas's
help
Ponderomotive Effects Experiememt
We were able to increase the power going to the cavity by a factor of ~100
by locking at low power,
and increasing the power while locked. We haven't been able to
get to the highest optical rigidity possible yet, since our servo becomes unstable
at such high rigidities due to unity gain crossings at ~50 Hz that have no
phase margin. The highest optical rigidity we've measured is about 6x105 N/m
for a 4 kHz optical spring.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Yamamoto)
40m modeling (Monica Varvella)
The open loop transfer function for the PRC degree of freedom has been simulated : this step was the last one for checking the
feedback filters. The 5 degrees of
freedom (PRC, SRC, MICH, DARM and CARM) have been controlled reducing the
offset shown by the CARM degree of freedom : seismic
motions at ETMX and ETMY been are turned
on during the simulation after the system was set to be stable and also the
check of opening and close the servo has been performed; no radiation pressure
has been teaken into account by now. The lock is
stable till to 2s as the time of the total simulation.
Mechanical modeling for Adv.LIGO (Sany Yoshida)
Using Mark Barton's Mathematica model, created a
State Space Matirx in the e2e format to simulate AdvLIGO Mode Cleaner tripple suspension.
This SS matrix will be tested with an appropriate e2e file soon. Also started to revise AdvLIGO quad
pendulum model using Mark Barton's updated Mathematica
model.
Scattered Noise (Hiro Yamamoto)
Transfer functions to estimate effects of scattered lights injected back
into adv.LIGO have been calculated.
The ratio of these transfer functions and the DARM
transfer function can be used to set the upper limit of scattered lights. The result is summarized in LIGO Note
T060073-00-E.
Adv.LIGO FP modeling (Hiro
Yamamoto)
ASC detectors and frameworks are attached in the QuadFP
so that Rana and Osamu can study the ASC in a
realistic environment with double chain quad suspension and radiation
pressures.
Stationary IFO Simulation (Hiro Yamamoto, Melody Araya)
Still the basic physics components and program frameworks development going.
No physics yet.
Alfi (Melody Araya)
Some e2e interface bugs in PR have been addressed.
Data Analysis Activities (Lazzarini)
Chatterji:
- Drafted
technical document describing initial Q Pipeline search of S5 data through
2006 Feburary 1.
- Continued
investigation of framebuilder data corruption.
- Developing
Q transform based parameter estimation.
Mendell:
Updated StackSlide S4 results for the April APS
meeting were presented to the reviewers this morning, Thu. Apr. 06, 2006. The final APS slides will be posted next Tue.
Apr. 11, 2006.
Shawhan:
- Continued
working with Laura Cadonati to finalize S4
all-sky burst search results.
- Reviewed
the S2 F-statistic pulsar search paper, preparing for posting on gr-qc.
- Other
pulsar analysis reviewing LIGO Data Analysis System
Sutton:
I've spent most of this week preparing my APS talk on the current status of
the burst and stochastic searches. I
implemented a faster version of the NetworkSimulator
codes for estimating network false rates in bursts searches, and added
uncertainty estimates for the rates.
Maria Principe is using these codes to model the LIGO-Virgo Q- pipeline
analysis. I've also done some
development work on the xpipeline coherent analysis
package, specifically speeding up (vectorizing) the
computation of antenna response values, and writing a first version of the
waveform extraction function. I also met
twice with Leo Stein to work on the source localization problem.
Yakushin:
Software Systems (Blackburn)
LDAS
Efforts were focused on getting FrameCPP to
support the same complement of compression modes as FrameL
(PR#1828). To help verify the compression modes, several test wave forms were
added. They are saw tooth rising (going from a min to a max value with a
constant slope), saw tooth falling (going from a max to a min value with a
constant slope), saw tooth peak (going from min to max to min with a constant
slope), and square wave (stay at min value for half a cycle then go to max
value for the remainder of the cycle). There remains a point of discrepancy for
a single test when the square wave data set is being used. It is being
investigated.
The test cases that need to be added are 32bit vs
64bit compression and decompression. As data analysis is moving to 64bit
systems and compilation, it is important to verify that data compressed on
32bit systems can be decompressed on 64bit systems and that data compressed on
64bit systems can be decompressed on 32bit systems.
TCLGLOBUS
Work is moving forward on the next release of TCLGlobus.
Of the 46 functions in the Globus GSSAPI package, 15
have now been tested and documented.
Details can be found at http://tclglobus.ligo.caltech.edu/status-gt-4-0.html.
GRID COMPUTING
Created Pegasus tc.data and sites.xml table for LDAS_GRID to explore using
ldas-grid.ligo.caltech.edu as an additional Pegasus pool for work flow
analysis. Planning bench mark with Inspiral
work flow on this resource in the future.
Installed Condor 6.7.18 on LIGO-CIT-ITB test bed cluster.
Successfully executed the Inspiral work flow from a
submit host using Condor DAGMan 6.7.18. This fixed
issues with submitting jobs in 6.7.17.
Yum updated LIGO-CIT-ITB including installation of kernel 2.6.16-1.2069_FC4
Successfully ran Inspiral pipe work flow to
completion on one additional OSG 0.3.6 site uc_t2dev_itb. Ten OSG 0.3.6 ITB
sites have been validated to run the LIGO Inspiral
work flow. One site doesn't allow the LIGO VO to access resources, and one site
has insufficient disk space to run the LIGO binary inspiral
test workflow. One remaining site is still to be tested once they have upgraded
to the latest Condor release which fixes bugs identified in the current ITB
release.
Installed srmcp locally on
Worker Nodes of LIGO-CIT-ITB in support of srmcp
validation.
Worked with nanohub VO and grow VO validation
teams to support validation of their applications.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Worked
on bringing up systems/services at LLO after the LDAS equipment was moved
to it's new location. Lots of fibre
channel/robot issues after the restart, worked with Dwayne & Igor to
sort them out.
- Met
with Sun.
- At
both sites discovered problems with QFS filesystem
write performance after deleting large numbers of files. At LLO, this required us to temporarily
use space in /home (which wasn't effected) to store frames.
- Working
on reproducing QFS write performance problem on samtest.
- Normal
ingestion stuff, plus cleaned up from our first
unreadable data on a tape shipped to us (from LHO). I rearchived
the data at the site and let the normal process of tape ejection/shipping
get the data here, but I had to deal with some overlap from the previous
tape (i.e. some data on the bad tape had been ingested).
(Phil Ehrens)
- Researched
the "prelink" utility and reported on
it in the admin meeting.
- Investigated
failures and filed PR's for nodes 4,21,32,42,70,72,124,128,247,274,290 and
312.
- Installed
Solaris 10 update 1 on ldas-usndev1 and sunopteron.
- Added
optional prelink handler to shasum
module of log_mon.tcl.
- Added
cluster walking logic to log_mon.tcl.
- Added
new admin commands to log_mon.tcl to allow admin
to turn off reporting about a node during servicing.
(Erik Espinoza)
- Finished
kickstart server for Hanford.
- Deployed
node using hanford/kickstart and got approval
from Ben.
- Contacted
Western Digital for more info on WD2500YD Disks.
- Removed
prelink on cit/kickstart.
- Replaced
WD2500YD disks to WD2500SD on node75, node76 and node77.
- Looked
into various kernel panics.
(Stuart Anderson)
- Upgraded
all Lab sites to new security patched Condor version (6.7.18).
- Staged
all the current S5 h(t) data into the LDAS-CIT
internal disk storage.
- Received
and initially configured the old LLO fb0 3510 at CIT for eventual
integration into the CIT /archive filesystem.
- Worked
with Larry to order an additional small CIT cluster network switch.
- Found
a surplussed Foundry network switch to send to
LLO.
MIT
(Keith Bayer)
- Restarted
condor to cover root level exploit.
Livingston
(Igor Yakushin)
- Condor
was upgraded to version 6.7.18.
- We
resumed using /archive.
- The
attempt to upgrade the firmware on the tape drive was unsuccessful: most
likely a hardware problem with the engineer's laptop. We shall try it
later again.
- Working
to apply my old database archiving scripts to the segment database.
(Dwayne Giardina)
- Ejected
tapes for shipment to CIT and imported tapes into L700.
- Rebuilt
raids on T3-13 and T3-16.
- Replaced
hdb in node202.
- Node2
and node81 were reporting filesystems marked as
read-only, reboot seems to have cleared it up.
- Node99
was non responsive. Removed from
rack to troubleshoot and not all LEDs would come
on. Removing the case showed that
metal bracket fell across the motherboard.
Will try a new motherboard soon.
Hanford
(Greg Mendell)
- A
couple of problems required more than just routine maintenance last week.
A T3 raid box froze, crashing the fb1 framebuilder
filesystem, and the NFS fileserver daemon needed
to be restarted more than three times, due to a network card problem we
think. These were fixed without loss of data, and data archiving and RDS
generation are up-to-date and running smoothly again at LHO and LLO.
(Ben Johnson)
- RLS
server at LHO crashed Wednesday morning. Pointed Kevin Flasch
to the coredump.
- Assisting
in investigation of "slice" errors in the S5 and A4 data. Early indications point to the
ultra-fast (262kHz) and heterodyned FSR channels
as being correlated with the problem.
- Exported
+ imported 114 tapes. I used my tcatalog program
to find empty cabinet slots for them.
- t3-9 crashed last Thursday evening. There is still a
bad batch of files from this time on /frames/full. Disk2Disk told to copy
at that time.
- Unrelated
to the t3-9 crash, Disk2Disk is now running on fb0 as its primary source
of frame files. This is due to the suspicion that the "slice"
corruption affects fb1 more severely.
- Replaced
Sysconnect NIC in gateway with Sun NIC (both
Gig-E). The NIC was the LDAS-side NIC.
General Computing (Wallace)
MIT:
(Keith)
- Helped
out with numerous visitor requests
- Built
XP box for highbay camera experiment
- Spec'd out backup server
- Spec'd out small laserjet
for adv ligo
- Undergrad
computer support
- Worked
on fileserver upgrade as time permitted
- Rebuilt
maz (cvs/web server)
after power failure
- Looking
into backup software (especially the freeware 'bacula'
utility as it has windows/solaris/linux support)
Livingston:
(Dwayne)
- I
finished software installs on Janeen's new PC.
Connected to license server with help of Mike Pedrazza
and Shannon
- changed
a users GC password
- security
server Windows XP updates
- I
spoke with Kantech tech support about the bugs
we have experienced with the gates.
They told me that we most likely have a wiring problem. I will pursue it further.
- other
usual user requests and support
(Shannon)
Hanford:
(Christine)
- Working
on an amended budget that includes the drastic decrease in yearly ISP
expenses.
- Finished
re-building the latest MRTG and RRDTool. The new MRTG shows the same bandwidth
usage as the older one. I'm still
working on installing a CGI that builds the graphs using the RRDTool database.
RRDTool captures data near real-time and
can be displayed down to one minute averages instead of the 5 minute
averages of MRTG alone.
- Worked
with Larry on going over changes to the new GC AUP.
CIT:
(Veronica)
- LIGO: Videotaped and burned DVDs of the last
seminar. Updates to the Elba website. LIGO website updates.
- LSC: Postings of the presentations from the
March meeting. Updates to the webpages of the technical papers. Issues of bouncing
email; updates of the mailing lists.
- CaJAGWR: Videotaped the last seminar by Tarun Souradeep, compressed
it for streaming. Updated the website.
(Christian)
- Installed
the latest Microsoft Office patches on Helena's laptop.
- Created
a backup of Ken's workstation. Millikan - Replaced toner cartridges on HP 5500
printer.
- Working
on replacing Linda's wireless card on her laptop. Also, I've created a backup laptop for
Linda to temporarily use so I can format and reconfigure her current
laptop.
- Continuing
research on finding a particular backup software
that can work with different operating systems.So
far we have a couple that do work and are inexpensive.
Other misc.: Continued onsite software/phone support.
(Mike)
- Worked
most of this week configuring a new rack mount server to run with 64bit
version of Server 2003 to run with DCC database software. I ran a test
loading the 64bit version of the software, but came across many hardware
compatibility issues that require a lot of time to get the 64bit OS
loaded. After getting the OS to run I loaded the SQL server software which
I came across many issues trying to connect to synergy database. This now confirms that DCC software will
have to run on the 32bit version of server 2003. I have a few more tests
on ways to backup this server before we put this server into production.
- Called
in to Dell's tech support, for Linda Turner's laptop. This required a lot
of time on the phone going through many diagnostic tests trying to get her
laptop to work, before they would send out a replacement part to correct
the issue.
- Continued
work on the spam filters searching for false positives, and adding some
additional rule sets.
- More
than usual onsite misc. user support, that consisted of networking,
software, email, dhcp, and printing issues.
- Recovered
some Solid Works files for Calum Torrie. We are having problems getting the vault to
recognize these files as solid works drawings. This is an on going
project.
(Larry)
- Continue
working procurement issues. Ordered more items for the different
groups. Presently. going over SUN equipment items to be purchased. Waiting for some of the conference
equipment to get back so I can purchase a new projector and a bulb for one
of the old projectors.
- Worked
with Albert and Christine in modification for the new AUP that will be
going out in the near future.
- Resolved
a couple of e-mail issues. Mostly modifications to aliases and cleaning up
lock files.
- Rebuilt
a couple of SUN connections. Also, moved a LIGO computer back on to the
LIGO network.
- Went
through the last of the machines that had been hacked in last months
incident.
- Assisted
the DCC in a number of postings and modifications.
- Worked
with Mike a little on the testing of the new servers.
- Went
through the Monarch machine again. Still can't find the problem. They are suppose
to be sending out a new mother board but I've not seen anything from them.
- Resolved
a network problem. We had a couple of processes go south on some machines
which basically caused a DOS attack on one of the servers. Once the machines were reset things were
fine.
- Resolved
a few file issues for different people.
- Went
over conference logistics with others in the GC group. Just trying to
improve the conference support.
This will be a continual process as the conferences/meetings
increase in size and frequency.
- Finalized
the backups for the home accounts and finished up the backups for half of
the servers. Just a few more to go.
- Continual
work on user accounts and spam filters
Mail Statistics for March 30 - April 05, 06
|
Mail Statistics
|
April 6, 2006
|
|
Rejected Messages
|
34,373
|
|
Virus Messages
|
1,865
|
|
Accepted Messages
|
18,454
|
|
Total Messages
|
52,827
|
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Systems, Management
Systems
from Dennis
Coyne
See also:
AL
Systems web page
AL Systems email
archives
Records of Decision or Agreement (RODA)
See also the RODA status web page
Requirements/Design
- Submitted
a request to the Vacuum Review Board (VRB) to remove the vacuum bake of
the LVEA and VEA chambers from the ADL baseline plan and cost estimate.
After much email discussion the VRB has agreed. A RODA to document this
decision is in preparation.
- Discussions
on particulate contamination experience in initial LIGO (LSC session and a
special OWG meeting 3/31) have culminated in some funds being set aside in
the Facilities Modifications/preparations (FM) subsystem to implement a
clean air shower in the test mass (at least) chambers. Much more
definition of requirements and conceptual design work is required before
we can begin to implement. See also Bill Kell’s
report under initial LIGO regarding contamination investigation of ITM07.
Interface Issues
See the "Interfaces" section of the AL Systems web page
Vacuum Compatibility
Residual Gas Assay (RGA)
See also the Vacuum Bake Lab
- I
have been working with Ken Mailand on the
assembly of the Quad Adjuster Platfrom. Helping
to keep everything on schedule for the trip to MIT next week.
- I
cleaned and baked some magnets for Helena.
- I
cleaned some tooling for Calum.
- I
have been getting together all the tools, spare parts and modified parts
that Ken, Calum and I will need at MIT next
week.
- I
am repairing the OSEMs that Myron shipped from
MIT and will take them with me to MIT next week.
- I
have been cleaning up old scan data files and saving them to CDs.
High-Irradiance, Contamination-Exposure Cavities
Lee Cardenas, Liyuan Zhang
- Testing
continues on the flexible cable and “white cable” in two
separate cavities. The 3rd cavity is still not yet in
operation.
Advanced LIGO Project Management
from
Carol
Wilkinson
Preparations for the NSF Review of Advanced LIGO
Preparations for the NSF Review of Advanced LIGO, scheduled for May 31, are
progressing. We are slightly behind schedule but can finish in time with some
concentrated effort. Subsystem leaders with assignments to complete should make
this effort a high priority in order to meet the deadlines. Work is continuing
on updating the Basis of Estimates and the Work Breakdown Structure
descriptions.
Project controls personnel and subsystem leaders are preparing breakout
session presentations for each subsystem for an internal review that will be
held from late April to early May.
Cost estimates were frozen on April 5. The end result is about $1.5M higher
in base year 2006 dollars than desired, so some judicious trimming in a few
specific areas will occur. Contingency analysis continues with the Monte Carlo simulations for determining schedule and cost
contingencies.
The NSF is recommending a higher inflation factor than has been
traditionally used. This has lead to an evaluation of the escalation factor
that will be used by Advanced LIGO. We may present the NSF review team with our
preferred escalation factor and ask the review team to recommend the best
option.
The Risk Management Plan is under review. The risk plan includes a risk
registry of potential events and mitigation efforts that will be tracked
throughout the project lifecycle. When the plan is approved, a Risk Management
Team will be formed and subsystem leaders will receive risk management
training.
The Project Organization Chart has been reviewed by site managers and
personnel in lead roles are being assigned. A transition plan to move personnel
from operations to the project and back is in the early stages of planning.
The Project Execution Plan is still in very rough draft form and needs some
intensive work. Those who were assigned responsibility for sections should work
with Carol Wilkinson to complete their assignments by April 12. The most
critical sections are those on LIGO and project organization and management,
cost and schedule, and risk management. Efforts will be concentrated on those
areas to complete a draft by April 14.
Progress Updates
The next update will be for the period March 1 through April 30, due by May
5, unless project controls and subsystem leaders are too busy preparing for the
NSF review. Progress update files will be posted on the web and notices will be
sent to subsystem leaders in advance of the due date.
Meetings & Reviews
Future near term planned meetings & reviews are indicated in the table
below. Changes since last report are
listed in blue.
Late or critical items are in red.
|
Date
|
Sub sys.
|
Review
|
Topic(s)
|
Enabling event(s)
|
Schedule motivation
|
Status
|
|
Jul 11-13, ‘05
|
SYS
|
SYS Mtg
|
CDS infrastructure & HAM
Isolation Req’s
|
|
|
Report in progress
|
|
12-Jul, ‘05
|
SUS
|
PDR, Review 2
|
Electronics req & design;
Focus is on the front end electronics (UK) -- limited Digital
controls/electronics (US) review
|
|
|
Report in progress
|
|
~Oct 05
|
SYS
|
PDR, Review 1
|
Engineering & Implementation ('generic')
Requirements;
Interfaces
Revised Optical Layout
Optomechanical Layout
|
completion of generic requirements definition;
completion of first draft of ICD; revision to optical layout; establish
integrated opto-mechanical equipment layout
|
timely system level definition enables/helps
define subsystem reqmnts & design
|
|
|
~ Nov 4, ‘05
|
SUS
|
SUS PDR
Review 8
|
Ribbon/Fiber/Ear/ Bonding PDR
|
Completion of the ribbon, fiber, and ear and fabrication
and bonding design and processes
|
|
Report in progress
|
|
~Dec 05, ‘06
|
SYS
|
PDR, Review 2
|
CDS Infrastructure
Stable Recycling Cavities
Lock Acquisition
Modulation Scheme
Power Induced Instability
|
Sufficient CDS requirements & concept work
(also 7/11-13 mtg)
E2E Modeling for AL
40m Progress on Acq. & Mod.
|
CDS Infrastructure is key to subsystem
electronics req.
Stable cavity is key to IO MMT design
|
|
|
~Jan17. ‘06
|
SUS
|
SUS PDR Review 9
|
Wires for MC Triples
|
|
Timely report to allow progress on MC triple final design
work
|
Report in
progress
|
|
~Jan 06
|
IO
|
PDR Review 1
|
PDD, Faraday Isolator, RTP-based modulators
|
SYS PDR?
|
|
Work
delayed on
FI, allows more
systems to be
reviewed
|
|
~Feb 21 , 06
|
SUS
|
PDR, Review 5
|
Triple design
|
Available SUS/US staff
|
Enable SUS/US final design phase
|
Delayed as Quad controls PT
takes preced.
|
|
~Feb 22, 06
|
AOS
|
AOS DRR/CD
Review 1
|
Stray light control, PO
mirror and telescope, optical lever, initial alignment system
|
SYS PDR?
|
Delay stray light control review until other systems can be
reviewed at the same time.
|
Delayed from
Oct. to allow review of
add. systems.
|
|
~Mar 06
|
IO
|
PDR Review 2
|
Mach-Zender, Adaptive mode
matching, Mode Matching Telescope
|
Determination of whether a stable recycling
cavity will become part of the AL
baseline; SYS PDR 2
|
|
Waiting
for stable
RC decision
|
|
~April 11, 06
|
SEI
|
HAM isolation req’s
review
|
Isolation requirements in HAM chamber
|
|
Need before reviews on single stage stiff
system and SAS
|
Delayed by preparations for NSF review
|
|
~April 13 ‘06
|
SEI
|
CDR on single stage HAM SEI
|
Evaluation of single stage ISI design against
revised requirements
|
HAM Isolation req’s
review
|
Need for NSF baseline review in May
|
Delayed by preparations for NSF review
|
|
~April 06
|
SUS
|
PDR, Review 6
|
quad controls prototype test results
ribbon process/design
|
completion of LASTI testing; may need to have
partial review with quad PDR before end of testing
|
timely incorporation into final design effort
on the noise prototype
|
|
|
~May 06
|
COC
|
PDR
|
Metrology, Handling fixtures, Coating,
Cleaning Process, Optics prelim. design
|
SYS PDR?
|
|
|
|
~June ‘06
|
SUS
|
PDR, Review 3
|
Quad design
|
Completion of the quad controls prototype
assembly; installation at LASTI
|
timely transfer, to RAL & UB efforts, of
lessons learned from the controls prototype
|
Delayed until shipping to LASTI.
|
|
June ‘06
|
AOS
|
AOS DRR/CD Review 2
|
Thermal Comp., Photon drive
|
SYS PDR?
|
|
Moved forward
for timely finish
of AOS CDR’s
|
|
~Mar 07
|
SEI
|
HAM Critical Design Review
|
Recommendations w.r.t.
HAM prototype development based on ETF results, single stage analysis, and
SAS results
|
|
Delay timely decision on proceeding with SEI/HAM prototype
|
Delayed from Aug.
|
|
TBD
|
SUS
|
PDR, Review 7
|
BS, FM/ITM SUS design
RM design
non-cavity SUS
|
design work completion (has yet to start on FM/ITM, not
mature for RM)
|
|
|
Advanced LIGO Review
Preparations (Lindquist)
Positions Summary ListUpdated to
reflect information provided so far and reissued.
LIGO Operations Budget Model (FY 2006 - FY 2008) Updated to
reflect information provided so far and reissued.
Projection of Operations Costs during
Advanced LIGONo progress.
Projection of Operations Costs Post
Advanced LIGO ConstructionNo progress.
Seismic Isolation
Advanced Ligo Seismic Isolation Prototype
Assembly Status
We have received all the machined parts for stage 0 and completed the
assembly. We are in the process of assembling stage 2. http://emvogil-3.mit.edu/~kmason/SEI%20machining/stage%200%20Assembly/
From: "Joseph A.
Giaime" jgiaime@ligo.phys.lsu.edu
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
Working
on NSF Review material.
Solidworks on my laptop is badly in need of an uninstall/reinstall. I will be weeding through my 3100 Solidworks files to make file corruption less inevitable,
after a fresh install. Currently, my Solidworks
Explorer and PDMWorks lock up. Calum
has been quite helpful in working around my laptop's infirmity. Dwayne and
Shannon are working to install software on a new desktop for me.
From: Calum Torrie ctorrie@ligo.caltech.edu
From: Ken Mailand kmailand@ligo.caltech.edu
I'm working with Calum Torrie on site installation
tooling for the quad suspension.
From: Helena Armandula ahelena@ligo.caltech.edu
From: Jay Heefner jay@ligo.caltech.edu
AdL SUS Quad Controls Prototype
- The LIGO-based controls for
the quad controls are now installed at LASTI and testing of the system is
in progress. The system should be fully operational by the end of the
week.
AdL SUS Electronics
- A drfat
of the design requirements for the UK provided quad coil drivers
has been completed. It should be ready to send to the UK group by the end of the
week.
40 M OMC Controls
- A draft of the system layout
has been completed and comments have been received. Design of the system
and the boards needed for controls should
resume next week.
From: Rolf Bork
<rolf@ligo.caltech.edu>
Installed new Quad
suspension controls this week at Lasti. After encountering
a few problems with parts shaken loose during shipping, we are now up and
running. The new system includes a PCI-X I/O chassis, a dual Opteron realtime front end
computer, a dual Opteron Framebuilder
and new anti-aliasing and anti-imaging chassis. The EPICS and realtime front end code that is running was all
automatically generated from a Simulink model file using our new code generation software.
Core Optics
From: Bill Kells kells@ligo.caltech.edu
From: GariLynn Billingsley <Billingsley_G@ligo.caltech.edu>
Input Optics
From: David Reitze
reitze@phys.ufl.edu
Modulation (Stacy Wise, Volker Quetschke) - SW continues testing of the prototype parallel (MZ)
phase modulation scheme. The Mach-Zehnder
interferometer is locking to the required stability, and tests of the output
optical spectrum, residual differential motion, and frequency noise are
underway. VQ is working on synthesis of sidebands spectra free from intermodulational cross products using complex modulation.
HPTF@LLO (Ken Franzen, Simon Stepuk) - We received the Faraday Rotator from Caltech
(from the bake-out); it will reassembled to undergo further testing. During
visual inspection we found that the inner surface of the magnet contained a
residual white power, perhaps due to some corrosion. We measured the
magnetic field to be within 5% of the value obtained before the baking.
However, our measurement was performed with a different device, so we can't be
certain if the field changed during the bake-out. Also, we have succeeded in
modifying the data acquisition and control LabView
program of the IPG 100 W fiber laser.
AdvLIGO/iLIGO Upgrade EOM/Faraday
Isolator review (Dave Reitze)
- We have received the report from the review committee on the FI and EOM and
are drafting responses to the action items.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
The beam pointing
specification for the power stabilization photodetector
was calculated. This assumed that the suspended mode cleaner would
perform to specification and not introduce any additional beam pointing.
The levels were taken from T020027-00-D for a hot cavity. Other numbers
were based on the beam pointing coupling experiments done by Patrick Kwee and Frank Seifert from AEI. The beam on the
power stabilisation photodetector
should not wander outside a 400 micron diameter centered on the optimal spot on
the photodetector in order for the beam pointing to
be negligible.
Otherwise I am still
working through the Xilinx training materials.
Auxiliary Optics
From: Michael Smith
<smith@ligo.caltech.edu>
SLC
Hiro has determined the transfer
functions for light injected into various ports in the ADLIGO RSE configuration
without the optical spring effect. I am in the process of using that
information to analyze the scattered light noise in ADLIGO.
TCS
Phil and I have a
preliminary design concept for injecting Hartman sensor beams into the IFO to
sample the wavefront distortion due to heating of the
ITMs, ETMs, and BS. I have
made a preliminary layout in ZEMAX of Hartman telescope beams for sampling the ITMs in the non-folded IFO.
Controls, Data systems
From: Rolf Bork rolf@ligo.caltech.edu
Other Laboratory R&D
From: Riccardo DeSalvo desalvo@ligo.caltech.edu
For additional information about this report, contact Stan Whitcomb or Phil Lindquist