Weekly Report for
Week Ending March 30, 2006
Due to travel by some of the principals, no LIGO Executive
Committee meeting has been scheduled for Monday, April 3, 2006.
Special Announcements:
Weekly
Report Highlights
The LIGO/TAMA S2 Inspiral paper was accepted by
Physical Review D this week, and the S3 Burst paper was published in the Amaldi meeting proceedings in CQG.
The final version of the new LSC Bylaws, as approved at last week's LSC
Council meeting and edited to remove typos, has now been submitted to the DCC.
Work continues of revision of the draft LIGO/Virgo MOU, in light of comments
made at the LSC Council meeting..
LIGO Laboratory Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
LSC MOUs and Research Plans and Progress Reports
SITE TELECONFERENCE (Lindquist)
A site teleconference was conducted Thursday, March 30, 2006. The following were among the issues
discussed:
- Livingston Science Education
Center—Not totally closed up yet; still missing some glass,
doors, etc. However, the weather
has been very cooperative so they are doing very well relative to the
schedule.
- Livingston
Access Gate—the gate is up and running.
- There
are no open assigned actions. The
list of assigned actions updated through December 1, 2005 (the last time
that it was updated) will be found Here.
PROPERTY MANAGEMENT (Luna)
>From: Rod Luna <rluna@ligo.caltech.edu>
- Provided
assistance to the Detector Group
(H. Armandula) with packing and shipping
a coated mirror to Stanford (R. Route), Account Number LIGO.OPT - 5.4 -
NSFLIGO.FY02ON.
- Coordinated
the disposal of old monitors and printers. Account Number
LIGO.DAT-1.5.3-NSFLIGO.FY2ON.
- Assisted
Bill Tyler in disposing a Glove Box.
- Tagged
two File Servers for Larry Wallace.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
- Supported
the LSC preparing and processing over 135 presentations.
- Presented
an overview of the new document management system to the LSC.
- Met
with Sam Finn to discuss integration of his new LSC E-mail system into the
new Synergy software for the DCC.
- Met
with Dennis, Calum, Todd, and Rich to define the
workflow process needed by the Engineering group generally, and the
Electronic engineering specifically for the Synergy software. This began to help flesh out the
metadata needed and determine which information would be collected within
the workflow versus in a regular document upload.
>From: Cleveland Mak mak_c@ligo.caltech.edu
- No
report (Personal Leave involving new small person that kinda
looks like Cleveland).
COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Completed
change order #171 to Triad and issued the change to the vendor.
- Completed
the renewal of two computer maintenance orders for LLO and for LHO from
Sun Microsystems to go into effect 4/1/06.
- Working
on the purchase for the fan with the arm for the LIGO Hanford Observatory.
- Issued
the subcontract to High Precision Devices and federal expressed it to the
vendor.
- Working
on revising the terms and conditions for the University of Florida
to the original TCs.
- Waiting
for a response from University
of Pisa to proceed
with the payment for the fellowship.
>From: Florence Kaufman <fkaufman>
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- Construction
of the LLO SEC continues slightly ahead of schedule due to continued good
weather. The glass front remains
the only part of the building not enclosed.
- The
Galli & Morelli
contract for the HAM-SAS for Advanced LIGO has been reviewed by the NSF,
and their only requirement was the addition of some flowdown
clauses. Those clauses have been added,
and the revised contract sent back to the NSF electronically. Upon receipt of their approval, the
contract will be awarded to Galli & Morelli.
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
Worked on the usual new trips, expense reports,
reconciling, calendar reservations, and itinerary entries.
>
No report (Vacation).
>Dorothy Lloyd
- Processed
the usual requisitions for POs and payment request, and approved and
submitted the weekly incoming invoices to accounts payable for payment.
- Updated
contract invoice log and reconciled petty cash fund.
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
PROPOSALS and REPORTS (Lindquist)
NSF has advised us that they are ready to fund us for the last half year of
LIGO OPS pending receipt of a budget.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- The
minutes and action items from the March Staffing Committee meeting have
been posted on the SC web page.
- All
files for the Staffing Committee are up-to-date and posted on the SC web
page.
- Prepared numerous appointment and reappointment
memos for various Visitors, Post Docs, and Term Staff.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
Nothing significant to report this week.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of Commissioning Activities at LIGO Hanford Observatory (compiled by M. Landry)
For the second week in a row, both LHO detectors have achieved S5 target duty
cycles at decent binary inspiral range (H1 90% at
~14Mpc, H2 87% at ~7Mpc). This was achieved despite downtime on Saturday
on H2 due to alignment and ISS trouble after a magnitude 5.0 quake off the
coast of Northern California . It thus seems that the additional fan (started Wed
15th) has stabilized temperatures sufficiently for reasonably rapid relocking.
An issue actively being tracked is an apparent occasional corruption of 1/16th
of a second of FB1 data, perhaps not seen in FB0.
This week's range and duty cycle update can be found here.
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
L1 Interferometer in S5 (O'Reilly)
We had a very good week of data taking with a duty factor slightly above 70
percent. Weather, local activity
(including construction), and diligence all contributed to the improved
performance.
The major activity of the week was the completion of the LDAS move. This was
accomplished and all data from the backup framebuilder
fb0 was successfully archived.
Maintenance period on Tuesday was relatively uneventful. The major change
was to acquire the 100 kHz fast channel. This brings us into line with LHO configuration
and does increase the frame size. As a consequence fb1 now has reduced look
back of ~6 days.
A strong 128 Hz line has been seen in the data. This should be investigated
during our commissioning break.
On Monday April 3rd LLO will start a two-week commissioning break. The last
weekend of the break will be used to assess the stability of any changes and to
perform any needed characterizations including calibration.
LLO Outreach (Thacker)
Two visits to local High School (five 9th grade physical science classes);
prepared and executed lesson two middle school visits to LLO; prepared and
executed two "half-day" programs assisted in data collection effort
with Lisa Szechter prepared for Washington Parish,
Math/Science Partnership Workshop at LLO
AdL Suspensions and Isolation (Romie)
Held a fruitful Suspensions Workshop after the LSC meeting
last week at LHO. Notes from the workshop should be available next week.
Actions from it will be statused at the SUS weekly telecon.
After the workshop, I've been primarily working on NSF Review material.
General Computing (Giardina)
I've been mostly consumed by LDAS for the past two weeks.
- continued software installs on Janeen's
new PC. Requested Algor license from Larry Wallace and Mike Pedrazza
- other
usual user requests and support
LDAS Support (Giardina)
- LDAS
move to new location
- ejected
tapes for shipment to CIT and imported tapes into L700
- L700
problems recognizing tape drives and tapes were getting hung up. This appears to have cleared after
several reboots and some manual intervention by both myself and Igor.
- Fiber
connection between CDS and LDAS was damaged during move. A temporary fiber was pulled and a
connection was established, then we had the original fibers repaired.
- worked with Lisa to reduce on-disk look-back of full
frames on fb1 /frames filesystem. After new fast channel was added, we
were dangerously close to running out of space. Reducing from 7 days to 6 days leaves us
with 10% free in anticipation of acquiring additional channels.
- node99 is still having problems. I will resume looking at that this
afternoon.
- Replaced
two T3 failed disks.
Computing and Network Security (Roddy)
- Did
some work straightening out the lab the other day. I will soon need a test environment
again. Still lots of old stuff that
needs to be tossed, straightened or moved in there. mounted a
couple of machines in the rack.
- Set
up a Linux box for Lisa & DMT folks.
They need a dedicated box for running a specific monitor.
- adjusted the backup schedules.
- Made
some adjustments to the router to accommodate the ilog
move. Ended up causing a problem
with routing LSU IP addresses. Took
a couple hours to figure out what the problem was. Turned out to be a
subnet problem on a virtual interface.
CDS (Bogue)
- Moved
all DMT data from the old ldas sam-fs t3 to the 3511 attached to the backup framebuilder
- Moved
all of /cvs/cds to a disk array with more
available disk space.
- Worked
with Shannon to move the ilog server out of GC and into CDS.
- Reconfigured
the daq on the backup framebuilder
to increase the lookback (we have more disk space
now).
- Reconfigured
the daq on the primary framebuilder
to decrease the lookback. The disk was full due to acquisition of
L1:LSC-AS_Q_FAST.
Thanks to Dwayne for all of his hardwork
in addressing our disk space issues.
- Supported
the ldas move.
- Installed
a new boot disk on poplar. Worked
with John Z. to get it properly configured.
- Added
DMT /export/home to the weekly cds backup.
CDS Code (Khan)
Setting up an alternate development system based on Linux operating system;
for testing and developing CDS related software bugs
Data analysis (Yakushin)
Storage/Condor/LDAS Admin
- LDAS
move was successfully finished with all the services been restored on
Friday. The new LDAS room is still under construction though: the
installation of walls is not finished yet.
- u1d7@t3-6
and u1d8@t3-20 failed and were replaced by spares. The replacement disks
were ordered from SUN.
- Disk
10 failed in 3510 and was replaced.
- Two
fibers running between LDAS FC switch and the GC patch panel were damaged
during the move and fixed on Friday.
- Ordered
a barcode scanner for the tapes.
- /archive
file system developed a problem on Monday: the speed of writing to it
dramatically dropped, the speed of reading from it was not affected. We
are temporary archiving frames to /home and expect to fix the problem with
/archive during LLO commisioning period next
week.
- On
Saturday tape robot stopped working. It turned out that there was a tape
stuck half way in the robot's arm and half way on the shelf. Moving this
tape manually to a shelf fixed the problem. According to the SUN engineer,
it was most likely due to the fact that the robot had not yet calibrated
itself after the move.
Data Analysis
- Gave
a presentation at LSC meeting on the results of the burst search during
the first few months of S5.
- Continue testing and tuning the coherent waveburst version on S4 data.
Initial LIGO Detector Science & Engineering (Coyne)
No report.
40 Meter Interferometer (Weinstein)
IFO Commissioning
- Go
and Osamu are measuring the noise spectrum of FPMI at high frequency (~1
MHz). The demod board was very noisy, so they
switched to another mixer. The noise is at a level of ~1e-11 m/rtHz, compared with shot noise expectation of 1e-15 m/rtHz. This appears to be due to the photodetector electronics. Osamu will follow up.
Meanwhile, they will try to measure the noise in a DC readout scheme
suggested by Rob.
- Monica
and Dan continue to develop the noise budget software for the 40m
environment. They have measured the oplev
couplings and transfer functions with the FPMI locked, and can plot the oplev noise budget traces. They are now working on the
MC WFS contributions. They are modifying the XML templates for many, many
channels. They will soon take a calibrated noise spectrum in the FPMI
configuration.
- Last
week the MC was very unstable. Osamu found the MCR beam was clipped at the
beam tube newly installed by Steve. The WFS signals had big offsets that
could not be zeroed electronically. There might still be some clipping of
the beam, or the WFS itself might have been damaged. Dan will follow up on
the potentially damaged WFS photodiodes.
IFO Modeling
- Monica
continues to develop her e2e simulation of the POX and POY loops, reducing
the offset that appears in the full DRFPMI configuration. She is now
starting an AdIRGO model in e2e.
- Rob
announces the first release of Optickle, a new matlab-based frequency-domain IFO simulation tool that
includes quantum noise, radiation pressure, DC and RF readout, simple user
interface, and lots of example configuration files. It can calculate TFs from any point to any other point in the
simulation. He already has used it to note that the near-zero terms in the
length control matrix from DARM to any double-demod
short-DOF port get significantly larger when the
radiation-pressure-induced optical spring is included. He is now handing
the code off to Osamu to study the quantum shot noise in all the control
loops, for AdLIGO. See Rob to obtain the code.
DC Detection and Vacuum Squeezing Development
- Sam
and Rob mounted the mirrors on the OMC body, and mounted the curved mirror
on the PZT with a few dabs of epoxy. They then tried to see FP resonances
with a small crystal laser, but the laser power was drifting, and there
was mode hopping. So instead they directed some of the main laser beam
from the IFO reflected port beam (which was already on the table, ~10 mW) into the OMC. They see nice FP flashes. They tried
locking the cavity with the PZT-actuated mirror, using offset locking.
However, the curved mirror was shaking too much (the epoxy was not yet
fully cured), and the amplifier was insufficient. They then tried dither
locking, but had similar problems. So now they are waiting to fully cure
the glue joints securing the PZT to the bracket and the bracket onto the
OMC body; waiting 24-72 hours.
- Rob
will set up the output MMT next, aligning it with a HeNe
laser. Sam will set up the steering PZT mirrors and test to see if the
mounts are sufficiently rigid.
- The
driver electronics for the tip-tilt PZT steering mirrors are still under
design. Sam is deriving noise requirements, and Jay is designing a board
with 2*2 PZT drivers, incorporating read-back of the tip-tilt strain
gauges and a fast "shutter" level.
- Jay
has finished a detailed control electronics schematic for the DC readout,
based on digital controls with a PCIX-based system.
- The
DC readout control software will be developed in "Bork-space", a
new suite of power tools by Rolf to design the controls in simulink and then have it automatically generate the
front-end code, EPICS screens and databases, etc. This will be fun!
- Ben
is almost finished laying out the PCB for the DCPD Interface board. He has
met with Jay to make sure that the board is the correct design to fit with
Jay's system schematics.
- Jay
says that we can use oplev PDs
and interface boards instead of QPDs for
monitoring the DC readout beams; they will be less noisy.
- Steve,
Osamu and Go installed a pickoff beam path on the PSL table to direct ~
2.7 W of laser light (which was being dumped) onto Go's
squeezer setup. They also shifted the MCT beamline
(which was on the NW corner of the PSL table) over to make more room, and
removed the Tropel. go
installed the SHG optics, assembled the SHG cavity in its oven with a
curved output coupling mirror. He also drew up version 2 of the squeezer
layout. Parts for the SHG enclosure (for safety and acoustic noise) are
being machined at the Caltech machine shop.
Electronics, Controls, Computers
- Dan
and Ben did a comprehensive survey of the fast DAQ channels. from the PSL/IO DAQ interface board. Ben is assembling
a list of which interface board channels go to what signal names on the dataviewer screen. This list has slightly changed from
the last time that he did this survey. He also compiled a list of the
signal conditioning on the two Generic DAQ Interface boards. He will write
up a table showing each channel's electronics from beginning to end.
- Dan
worked with Ben to debug the AP 166 demod board,
studying how the LO levels affect the noise.
Lab Infrastructure
- Steve
measured the tranmission of IR light through our
new laser safety glasses: Laservision's white
frame "LC542" only for 1064nm OD 5+,
and Bacou-Dalloz's blues-gray frame
"31-20200" for 532 & 1064nm OD 5+. These have dielectric
coating and they reflect the laser beam. He checked this at different
incident values with 2.5W ~2mm beam diameter.
Thermal Noise Interferometer (Black)
We are still debugging our increased noise
floor in SAC after installing ring dampers. The extra noise does seem to be
coming from the south arm cavity itself, as opposed to the control electronics
or the photodetector, and it scales with the power in
a way consistent with it being an actual length noise.
No report.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Yamamoto)
QuadFP (Hiro Yamamoto)
Hiro worked on implementing ASC in QuadFP setup so that ASC and angular instability can be
studied.
40m modeling (Monica Varvella)
The offsets in the POX and POY error signals have been reduced tuning the
right demodulation phase. The CARM open
loop transfer function has been simulated.
SUS & SEI for Adv.LIGO (Mark Barton, Sany Yoshida)
Sany studied the effect of the SEI - active and
passive - to the table top motion. Mark
has calculated a transfer function from the longitudinal motion of the
suspension point to the yaw motion of the test mass. This is part of the understanding of the yaw
noise motion to be properly implemented in the simulation to test the angular
instability.
Modeler Coding (Burce Sears, Hiro
Yamamoto)
Hiro worked on further improvements of FUNC_X
input format. Now using two templates, UNC_X_SettingTemplate.cc and FUNC_X_SettingTemplate.h,
all code fragments for FUNC_X can be defined in a natural C++ environment.
Bruce worked on the input of modeler.
More reorganization of parser code and introduction of a new modeler
directive in box files to inform the modeler when all modeler data has been
read in (the modeler does not need to continue reading through the file if the
rest of the file only pertains to information for the Alfi
graphical editor.)
Static IFO Simulation (Hiro Yamamoto, Melody
Araya)
Melody worked on setting up scripts for the maintenance and distribution of
the SIS package. Hiro
worked on the fundamental coding of SIS.
Data Analysis Activities (Lazzarini)
Brown:
- Found
a strange glitch in the H2 excitation channels with the online inspiral code.
Informed Shourov and the glitch group and
they've been pursuing the cause.
- Looked
at issues involved in implementation of the physical template family with
Diego.
- Finished
a chapter for a book on e-science workflows describing the tools available
to construct inspiral pipelines.
- Fixed
segment database replication from LLO to CIT, all segment database
services are now fully operational.
- Wrote
some slides describing said database in preparation for hand off of the
maintenance to Igor.
Chatterji:
- Investigated
occasional 1/16th of a second data repeats in the data recorded by te fb1 framebuilder
(password required). http://ldas-jobs.ligo.caltech.edu/~shourov/corruption/
- Updated
Q Pipeline trigger lists and coincidence results for LIGO/Virgo study.
- Investigating
parameter estimation for the Q Scan utility.
Mendell:
The current focus is on updating S4 StackSlide
results presented at the LSC meeting for review next week, and presentation at
the APS meeting.
Shawhan:
- Studied
efficiency curve fits and uncertainties for S4 all-sky burst search.
- Prepared
a talk presenting an overview of gravitational wave signals and data
analysis methods.
Sutton
This week my co-authors and I finished our paper on coherent consistency
tests for GWBs.
I sent the paper to Saulson and it has been
posted for LSC review. Since then I have
been editing/debugging NetworkSimulator codes with
Maria Principe for simulating bursts searches.
Yakushin
1) Gave a presentation at LSC meeting on the results of the burst search
during the first few months of S5.
2) Continue testing and tuning the coherent waveburst
version on S4 data.
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS
Work has resumed on the two problematic compression mode
DIFF_ZERO_SUPPRESS_SHORT and ZERO_SUPPRESS_INT_FLOAT (PR#1828). Initial tests have been encouraging as the
unit tests that originally demonstrated a problem now produce correct results. Much validation of this code remains to be done.
FFTW 3.1.1 has been installed on ldas-dev for
validation with LDAS (PR#3005). When upgrading FrameL
to v6r20 (PR#3008), no shared object was generated. Benoit Mours
is looking into the issue.
Testing of LDAS was done using version 1.8.130 of the software.
TCLGLOBUS
Version 0.5.0 of TCL Globus was officially
released. This included source distribution and RPMs
for the LSC software group. The release notes can be found at http://tclglobus.ligo.caltech.edu/
release_0_5_0.html
The unit tests for the Globus GRAM Client have
been completed and most of the documentation for this API has been done.
A list of tasks for the 0.6.0 release is available at http://tclglobus.ligo.caltech.edu/cgi-bin/tclglobus_critical.cgi.
Work continues on why the TCL file event does not get triggered when
incoming data is sent in rapid succession.
GRID COMPUTING
Reinstalled Condor 6.7.13 on submit host and tested against Condor 6.7.17 on
test bed cluster. Determined that DAGMan
(client side component) of Condor 6.7.17 is unreliable. Reported bug.
Successfully ran Inspiral pipe work flow to
completion on seven additional OSG 0.3.6 sites as part of the OSG 0.3.6
validation effort: CMS_BURT_ITB,
LIGO-CIT_ITB, Purdue_ITB, IUPUI_ITB, CIT_ITB_2,
BNL_ITB_Test1, and UFlorida_IGT.
Attended a bi-weekly STORAGE-TG telecom on metadata mods to support SRM.
Attended a VDS telecom to advocate for modifications
to vds-get-sites required for compatibility with OSG
ITB GridCat.
Determined that under OSG 0.3.6 at Purdue_ITB with
maxjobs = 200, the Inspiral
pipeline can execute in 19 minutes versus 52 minutes with maxjobs
= 20, given a workload of 943 DAG nodes. Transfer time to this site is 37.5
minutes for 5.1GB.
Held a teleconference with the developers of Pegasus to
discuss improvements that would facilitate running the binary inspiral workflow on the OSG.
Hardware Systems (Anderson)
Caltech
(Stuart Anderson)
- Received
and integrated 77 more Opteron nodes into
LDAS-CIT with help from Phil, Erik, Patrick, and Shourov.
- Upgraded
Condor from 6.7.16 to 6.7.18 to fix a major security hole.
- Working
on individual SAM-QFS filesystem slowdown at LHO
and LLO.
- Met
with Sun Microsystems for a look at their short and long term product
plans.
- Relocated
the LDAS-CIT servers to the other side of the computer room.
(Espinoza)
- Deployed
77 new nodes
- Rebuilt
ldas-kickstart
- Shipped
RMA package to ASA Computer
- Worked
with Phil on ldas-kickstart for possible hack
- Configured
cabinet power distribution units & liebert pdu's
- Worked
on kickstart for other sites
MIT
(Keith Bayer)
- Brought
ldas-gridmon back online.
- Brought
datacon back online.
- Sent
property stickers and serial numbers for 70 old cluster nodes to Caltech.
- Contacted
shipping company for cost estimate w/r/t 70 nodes and racks - will get a
site review and estimate.
Livingston
(Igor Yakushin)
- LDAS
move was successfully finished with all the services been restored on
Friday. The new LDAS room is still under construction though: the
installation of walls is not finished yet.
- u1d7@t3-6
and u1d8@t3-20 failed and were replaced by spares. The replacement disks
were ordered from SUN.
- Disk
10 failed in 3510 and was replaced.
- Two
fibers running between LDAS FC switch and the GC patch panel were damaged
during the move and fixed on Friday.
- Ordered
a barcode scanner for the tapes.
- /archive
file system developed a problem on Monday: the speed of writing to it
dramatically dropped, the speed of reading from it was not affected. We are temporary archiving frames to
/home and expect to fix the problem with /archive during LLO commissioning
period next week.
- On
Saturday tape robot stopped working. It turned out that there was a tape
stuck half way in the robot's arm and half way on the shelf. Moving this tape manually to a shelf
fixed the problem. According to the SUN engineer, it was most likely due
to the fact that the robot had not yet calibrated itself after the move.
(Dwayne Giardina)
- LDAS
move to new location.
- Ejected
tapes for shipment to CIT and imported tapes into L700.
- L700
problems recognizing tape drives and tapes were getting hung up. This appears to have cleared after
several reboots and some manual intervention by both myself and Igor.
- Fiber
connection between CDS and LDAS was damaged during move. A temporary fiber was pulled and a
connection was established, then we had the original fibers repaired.
- Worked
with Lisa to reduce on-disk look-back of full frames on fb1 /frames filesystem.
After new fast channel was added, we were dangerously close to
running out of space. Reducing from
7 days to 6 days leaves us with 10% free in anticipation of acquiring
additional channels.
- node99 is still having problems. I will resume looking at that this
afternoon.
- Replaced
two T3 failed disks.
Hanford
(Greg Mendell)
- We
are working to understand and resolve a number of issues with the archive
and cluster home directory filesystems at LHO
and LLO. The essential functions of
data archiving, RDS generation, and data
publishing are working, though until these issues get sorted out some
services will run more slowly than normal, such as jobs running on the
clusters.
(Ben Johnson)
- Disk2Disk
troubles at both sites. At LLO due to slow /archive writes, and at LHO due
to /ldas_outgoing NFS troubles.
- Assisting
Dave Barker with 16th-second sample repeat problem on fb1.
- Gave
Solaris 10 overview to LHO sysadmins.
- Gateway
is occasionally failing to export /export to GC and LDAS. Don't know the cause yet.
- High
load on dataserver due to nfsd
(has gone up > 210). Cluster job types have not changed except for Vladimir's powerflux jobs. The large number of files
created/recreated/possibly destroyed could be clogging up sam-fs /home.
- Educated
user not to request 16kHz data 40,000 seconds at
a time.
General Computing (Wallace)
MIT:
(Keith)
- Begun
working on remote backup service, spec'd out hardware for backup server
- Burn
testing new hard drives for gc fileserver
- Setting
up new Linux and Sun machines with ipf firewalls syslog
reporting aide (tripwire) scripts ldap
authentication and home dir access
- Moved
lancelot and enoki
from optics lab to pump room
- Reloaded
firmware into Arena Industrial II raid array
- Installed
new Linux box into DMT network
- Working
to get home directories setup correctly
- Moved
pc into high bay to support Ken/Myron installation work.
Livingston:
(Dwayne)
I've been mostly consumed by LDAS for the past two weeks.
- continued software installs on Janeen's
new PC. Requested Algor license from Larry Wallace and Mike Pedrazza
- other
usual user requests and support
(Shannon)
- Did
some work straightening out the lab the other day. I will soon need a test environment
again. Still lots of old stuff that
needs to be tossed, straightened or moved in there. mounted a
couple of machines in the rack.
- Set
up a Linux box for Lisa & DMT folks.
They need a dedicated box for running a specific monitor.
- Adjusted
the backup schedules.
- Made
some adjustments to the router to accommodate the ilog
move. Ended up causing a problem
with routing LSU IP addresses. Took
a couple hours to figure out what the problem was. Turned out to be a subnet problem on a
virtual interface.
Hanford:
(Christine)
- Took
a couple of days off to recover from the LSC meeting. The rest of the week has been spent
responding to proposed changes as a result of the incidents at the LSC
meeting.
- Set
up a password protected web page for a user. Helped a user with some email problems.
- Started
putting together a new budget reflecting the changes in WAN connection
charges which started last FY.
CIT:
(Mike)
- Troubleshot
DSPACE workstation for Mark Barton, due to a hardware failure. This was a
power failure to the motherboard after user tried installing additional
hardware. After reseating all hardware and power connectors, I was able
get this workstation up and running again. I also installed additional
memory to accommodate new hardware.
- Look
into borrowing a license from our FLEXLM server for Janeen
Romie to run Algor in
LLO. I can only borrow for a license for 30 days at a time. The only way
around this in order for Janeen to use our
FLEXLM server to run Algor is to set her up a
VPN connection which will put Janeen back on the
CIT network.
- Continued
work on loading two new servers with Server 2003, to replace our SQL, and
LLPDMWORKS servers. I came across
many issues with this due to these servers were burned in using LINUX.
When it came to installing server 2003 I came across many issues that
required updating the BIOS and downloading updated drivers for hardware to
work with 2003 server. I also had to call ASA regarding a BIOS setting
that was preventing me from seeing the primary hard disk. I am in the
process of loading and configuring SQL server to run with the new DCC
database application SYNERGY.
- Daily
work on spam filters searching for false positives.
- Other
misc. tasks and user support.
(Christian)
- Created
a backup of Irene Baldon, Cindy Akutagawa, Phil Lindquist and Rod Luna's workstations.
- Gina
Salone - Upgraded Gina's system from Windows
2000 to Windows XP.
- Basement
E/B - Replaced toner cartridge on HP 4600 printer.
- Patrick
Sutton - Helped Patrick install 6th floor Millikan
network printer to his laptop.
- Working
on finding a particular backup software that can
work with different operating systems. So far, Altiris
and Retrospect are looking pretty good.
- Other
misc.: Continued onsite software/phone support.
(Veronica)
- LSC: Posted the bulk of the March meeting
talks (something close to a 100). A
request has been made to restrict access to the listing of the
closed-sessions talks (vs to the actual files), this still needs to be finished. Updates to the technical papers
database.
- LIGO: Installed the website for the Elba meeting, ongoing updates. The backend database got corrupted and
attempts to compress/repair it did not work, so I had to install a new
database and import the data. It
took some server-level troubleshooting to rule out other causes. Updates to the LIGO website. Taped 2 special LIGO seminars and burned
them to DVDs for Kip Thorne.
- CaJAGWR:
Website updates.
(Larry)
- Continual
work on procurements. Mostly misc. support items. Working on Foundry maint.
contract. Time to get everything on it lined
up. SUN was able to answer some
questions concerning the matching grant program and the paperwork for that
purchase has now started. Resolved
a couple of Dell billing issues.
Working on list of items to purchase for conference support.
- Went
over items and support that GC will supply for future conferences. There have been a number of meetings
concerning this subject but I believe most of the concerns have been
worked out.
- Assisted
Mike in a couple of h/w setup for the new DCC and PDMworks
server installations. Discovered
the UPS can't handle the additional power load of the machines, we are now
in the process of getting another UPS purchased. The new machines also put out a lot more
heat than some of the other equivalent boxes.
- Working
on monthly backups and trying to repair a problem with the backups on one
of the servers.
- Spent
time working with the DCC and getting files moved over for web access.
- Assisted
Veronica on a couple of WEB issues concerning DCC and ELBA.
- Worked
a number of documentation items. The most important one working with a
group on changes being made to the GC computer use policy.
- Assisted
Barry in resolving some of his telecommuting issues. Hopefully, everything is working OK, we will know more when he returns from his trip.
- Continue
working the e-mail battle. Presently, trying to track down a problem on
one of the servers. It has a process that hangs on a regular basis (once a
day) causing problems for people trying to send out messages.
Mail Statistics for March 23-29, 06
|
Mail Statistics
|
March 30, 2006
|
|
Rejected Messages
|
34,093
|
|
Virus Messages
|
1,829
|
|
Accepted Messages
|
17,881
|
|
Total Messages
|
51,974
|
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Systems, Management
Systems
from Dennis
Coyne
See also:
AL
Systems web page
AL Systems email
archives
Records of Decision or Agreement (RODA)
See also the RODA
status web page
Requirements/Design
- Presented
the status of the optical & mechanical layout status at the LSC
meeting. See G060098-01.
- Calculated
the atmospheric pressure load induced deflections for the proposed vacuum
separation plate used to isolate the ISC Tables for read-out from the main
vacuum system. (i.e. between the output tube and
HAM6 and between HAM1 and the relocated HAM2 chamber). Discussed the
implications with John Worden and Kyle Ryan. The deflections appear to be
significant enough that further finite element calculations are warranted.
Interface Issues
See the "Interfaces" section of the AL Systems web page
- At
the SUS Workshop following the LSC meeting at LHO, Justin Greenhalgh led discussions with the SUS group on
actions to resolve definition or provide clarification for the Interface
Control Documents (ICDs) between SUS and other
subsystems.
Vacuum Compatibility
Residual Gas Assay (RGA)
See also the Vacuum Bake Lab
- I
have been working with Ken Mailand on the Quad Adjusrer Platform this week. We have disassembled it
and had the large plates plated to prevent rusting. I have cleaned all the
parts and Ken began reassembling it yesterday in the clean room at the
Synchrotron.
- I
have finished the bake job on the Faraday Isolator. It failed the RGA
test. The unit was assembled before cleaning. I will ship the Faraday
Isolator today (to Ken Franzen at LLO for
performance measurement).
- Cleaned
some tooling for quad suspensions (Calum) on
Friday of last week.
- I
stripped and re-cleaned some magnets for Helena.
- I
participated in the discussion of the quad controls prototype OSEM
failures (part of the SUS Workshop held at LHO following the LSC meeting).
High-Irradiance, Contamination-Exposure Cavities
Lee Cardenas, Liyuan Zhang
Nothing significant
Advanced LIGO Project Management
from
Carol
Wilkinson
Preparations for the NSF Review of Advanced LIGO
Preparations for the NSF Review of Advanced LIGO, scheduled for May 31, are
progressing. We are slightly behind schedule but can finish in time with some
concentrated effort. Subsystem leaders with assignments to complete should make
this effort a high priority in order to meet the deadlines.
Cost revisions are nearly complete and will be frozen on April 5.
Adjustments to the baseline costs may continue after that date as decisions are
made to eliminate or reduce scope, but the baseline will be set by April 20.
The Risk Management Plan has been drafted and the first simulations for the
cost and schedule contingency analysis will be run during the first week of
April. The risk plan includes a risk registry of potential events and
mitigation efforts that will be tracked throughout the project lifecycle.
The Project Organization Chart has undergone some revisions. Lead roles and
responsibilities are being refined. Work has started on identifying and
assigning personnel to work on production and installation for the various
subsystems. These personnel include those who currently have operations roles
and have not been working on advanced LIGO. A transition plan to move personnel
from operations to the project and back is in the early stages of planning.
The Project Execution Plan is still in very rough draft form and needs some
intensive work. Those who were assigned responsibility for sections should work
with Carol Wilkinson to complete their assignments by April 12.
Progress Updates
Progress updates for Advanced LIGO subsystem development for the period from
January 1 through February 28 are complete and posted on the project website.
The next update will be for the period March 1 through April 30, due by May
5. Progress update files will be posted on the web and notices will be sent to
subsystem leaders in advance of the due date.
Meetings & Reviews
Future near term planned meetings & reviews are indicated in the table
below.
Changes since last report are listed in blue.
Late or critical items are in red.
|
Date
|
Sub sys.
|
Review
|
Topic(s)
|
Enabling event(s)
|
Schedule motivation
|
Status
|
|
Jul 11-13, ‘05
|
SYS
|
SYS Mtg
|
CDS infrastructure & HAM
Isolation Req’s
|
|
|
Report in progress
|
|
12-Jul, ‘05
|
SUS
|
PDR, Review 2
|
Electronics req & design; Focus
is on the front end electronics (UK) -- limited Digital
controls/electronics (US) review
|
|
|
Report in progress
|
|
~Oct 05
|
SYS
|
PDR, Review 1
|
Engineering & Implementation ('generic')
Requirements;
Interfaces
Revised Optical Layout
Optomechanical Layout
|
completion of generic requirements definition;
completion of first draft of ICD; revision to optical layout; establish
integrated opto-mechanical equipment layout
|
timely system level definition enables/helps
define subsystem reqmnts & design
|
|
|
~ Nov 4, ‘05
|
SUS
|
SUS PDR
Review 8
|
Ribbon/Fiber/Ear/ Bonding PDR
|
Completion of the ribbon, fiber, and ear and fabrication
and bonding design and processes
|
|
Report in progress
|
|
Nov 29, ‘05
|
SEI
|
HAM SAS PDR
|
Review modeling, analysis, design for HAM soft system
|
Revised HAM SEI requirements.
|
Timely decision for proceeding with HAM SEI prototype.
|
Report Out. CCB
approved 2/27/06
|
|
~Dec 05, ‘06
|
SYS
|
PDR, Review 2
|
CDS Infrastructure
Stable Recycling Cavities
Lock Acquisition
Modulation Scheme
Power Induced Instability
|
Sufficient CDS requirements & concept work
(also 7/11-13 mtg)
E2E Modeling for AL
40m Progress on Acq. & Mod.
|
CDS Infrastructure is key to subsystem
electronics req.
Stable cavity is key to IO MMT design
|
|
|
~Jan17. ‘06
|
SUS
|
SUS PDR Review 9
|
Wires for MC Triples
|
|
Timely report to allow progress on MC triple final design
work
|
Report in progress
|
|
~Jan 06
|
IO
|
PDR Review 1
|
PDD, Faraday Isolator, RTP-based modulators
|
SYS PDR?
|
|
Work
delayed on
FI, allows more
systems to be
reviewed
|
|
~Feb 21 , 06
|
SUS
|
PDR, Review 5
|
Triple design
|
Available SUS/US staff
|
Enable SUS/US final design phase
|
Delayed as Quad controls
PT takes preced.
|
|
~Feb 22, 06
|
AOS
|
AOS DRR/CD
Review 1
|
Stray light control, PO
mirror and telescope, optical lever, initial alignment system
|
SYS PDR?
|
Delay stray light control review until other systems can be
reviewed at the same time.
|
Delayed from
Oct. to allow review of
add. systems.
|
|
~Mar 06
|
IO
|
PDR Review 2
|
Mach-Zender, Adaptive mode matching, Mode
Matching Telescope
|
Determination of whether a stable recycling
cavity will become part of the AL
baseline; SYS PDR 2
|
|
Waiting
for stable
RC decision
|
|
~April 11, 06
|
SEI
|
HAM isolation req’s
review
|
Isolation requirements in HAM chamber
|
|
Need before reviews on single stage stiff
system and SAS
|
Delayed by preparations for NSF review
|
|
~April 13 ‘06
|
SEI
|
CDR on single stage HAM SEI
|
Evaluation of single stage ISI design against
revised requirements
|
HAM Isolation req’s
review
|
Need for NSF baseline review in May
|
Delayed by preparations for NSF review
|
|
~April 06
|
SUS
|
PDR, Review 6
|
quad controls prototype test results
ribbon process/design
|
completion of LASTI testing; may need to have
partial review with quad PDR before end of testing
|
timely incorporation into final design effort
on the noise prototype
|
|
|
~May 06
|
SEI
|
HAM Critical Design Review
|
Recommendations w.r.t.
HAM prototype development based on ETF results
|
Completion of SEI/BSC critical design reviews;
LSC review of ASI HAM configuration design
|
Delay until requirements are revised. timely decision on
proceeding with SEI/HAM prototype
|
Delayed from Aug.
|
|
~May 06
|
COC
|
PDR
|
Metrology, Handling fixtures, Coating,
Cleaning Process, Optics prelim. design
|
SYS PDR?
|
|
|
|
~June ‘06
|
SUS
|
PDR, Review 3
|
Quad design
|
Completion of the quad controls prototype
assembly; installation at LASTI
|
timely transfer, to RAL & UB efforts, of
lessons learned from the controls prototype
|
Delayed until shipping to LASTI.
|
|
TBD
|
AOS
|
AOS DRR/CD Review 2
|
Thermal Comp., Photon drive
|
SYS PDR?
|
|
Moved
forward
for timely finish
of AOS CDR’s
|
|
TBD
|
SUS
|
PDR, Review 7
|
BS, FM/ITM SUS design
RM design
non-cavity SUS
|
design work completion (has yet to start on FM/ITM, not mature
for RM)
|
|
|
>From: Phil Lindquist lindquist_p@ligo.caltech.edu
Advanced LIGO Review Preparations
Positions Summary List – No progress
although several system discussions did occur this week.
LIGO Operations Budget Model (FY 2006 - FY
2008) – No progress.
Projection of Advanced LIGO Operations Costs – No
progress.
Project Execution Plan – No progress.
Seismic Isolation
Advanced LIGO Seismic Isolation Procurement
Status
The two large plates which
make up the optics table and the stage 2 center plate
has been delivered. The last two large plates which make up the stage 2 keel is scheduled for delivery on Friday 1/31.
Myron and Fred have
leveled the granite table and we will begin to assemble stage 2 after we recieve the keel plates on friday.
We have received all of
the assembly tooling required to begin assembly.
Richard Mittleman has been troubleshooting the blade calibration
fixture using "dummy" blades. The maraging
steel blades have been shipped on wednesday
and are scheduled to arrive at MIT on friday. We have
worked with ASI to understand how to set up and use the calibration fixture.
Additional design is still needed for shims to be used with the new softer
springs.
Preliminary
From: "Joseph A.
Giaime" jgiaime@ligo.phys.lsu.edu
Agenda for the weekly SEI telecom
Friday,
March 10, 2:00 pm Eastern, 1:00 pm Central, 11:00 am
Pacific time
BSC SEI status, w/ new targets: Ken/ Dennis,
- Ken has redesigned the
displacement sensor target to make use of the thinner high-purity aluminum
that we have been able to buy. We will have these made, with the request
that they polish the face flat after bolting it to the holder.
- Ken has spoken with Ken at ASI
regarding the intended use of the blade test fixture, and learned of the
purpose of several features shown in ASI's
drawing. The test method should be reproducible, albeit requiring a empirically-derived scaling factor to learn the true
force. We decided to proceed with assembly and spring testing.
- Hardness tests performed on
blades and rods.
- Blades deformed by 0.004"
during hardening.
- Joe Hanson at LLO will set up
to assemble and test the pods. Ken will send the internal cable, and
Jay will send a GS-13 updated circuit board.
BSC work, adaptive
modeling and FIR (Rich M)
- work concentrating on SUS
debugging
ETF platform work
- Thermal testing (Brian)
- Three thermal sensors plus
reference resistor installed in ETF platform's stage 1, and vacuum tests performed.
Changes at the several milli-degree level seen
when 0.06 dSpace units DC offset turned on.
Normal operation at Stanford needs an rms value
of about 0.1 dSpace units.
- Up to 50 mK
change seen on the support table over 10
min test, and about 10 mK at the actuator.
- Follow-up work with hour-long
tests (to probe full time constant), indicates that the 0.06 dSpace units current should cause 35 mK, implying the normal operation power should result
in an actuator temperature change of 0.5 mK.
- Tickle testing (Matt)
- Automatic diagnostics
development system (i.e., tickle testing) progress shown here.
- Frame damping (Tarm/ Brian)
- 1 mm thick small
square of dyad epoxied between frame and
buttress beam, photos
here. 60 Hz frame resonance's effect on rX response reduced by factor of 8 or so, as seen here.
- Next up: adjust size of
damping layer to look for an optimum. The layer currently in use
has a k of 5e5 N/m, and if this is implemented (probably by the SUS
group) we would need to find a bellows that is less stiff than that.
- There is also the question of
how and whether the buttress would fit in current table layouts. It
might be difficult.
- It also appears that the
unbolting and rebolting of the lower structure
resulted in a factor of ~4 Q change and a half hertz frequency
change. Attachment bolts are rubbing in their through holes, and
they found that retightening the bolts in situ upped the Q to nearly its
old value.
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
Held a
fruitful Suspensions Workshop after the LSC meeting last week at LHO. Notes from the workshop should be
available next week. Actions from it will be statused
at the SUS weekly telecon.
After the
workshop, I've been primarily working on NSF Review material.
From: Ken Mailand kmailand@ligo.caltech.edu
Bob has cleaned the
fixture plates and hardware parts, work on the fixture
including plating has been completed. A
full preliminary assembly has been completed, adjustments will be made
tomorrow.
The smaller assembled lift
table and minor modifications are complete, a shipping crate for the fixture
and lift table, is ready.
Rod has contacted a
shipper to pick up the crate from the synchrotron assembly area. The assembly work has been completed
on the quad setup fixture and table, it can be shipped Friday.
From: Helena Armandula ahelena@ligo.caltech.edu
From: Jay Heefner jay@ligo.caltech.edu
AdL SUS Controls Prototype
- Preparations and testing of
equipment and software needed to install the controls for the Quad at
LASTI scheduled for next week.
AdL SEI ISI
- More GS13 preamps are being
stuffed and tested for LHO.
- Completion of the capacitive
position sensor chassis has been on hold for other higher priority tasks.
It should be resumed in the next few weeks.
- Additional L4C preamps were
stuffed and sent to Stanford.
From: Rolf Bork <rolf@ligo.caltech.edu>
From: Ben Abbott
<abbott_b@ligo.caltech.edu>
LED failures:
I have written up a report
on the LASTI LED failures which can be found on my website here: www.ligo.caltech.edu/~babbott/LED_Report_new.pdf
Core Optics
From: Bill Kells kells@ligo.caltech.edu
No particular new
"results" this period, but I have been participating in the
intensified discussion and analysis (of the 4TIM07) data for understanding the
situation for Adl with regard to cleanliness and
contamination. In particular the particulate nature of the 4ITM07 contamination
is being elucidated. One thing we are revisiting is whether there is similar
contamination on the AR side (some initial investigations indicated not).
From: Gregg Harry
<gharry@ligo.mit.edu>
The lutetium-doped tantala/silica coating has been partially evaulated for mechanical loss and optical absorption.
This was done at MIT, Glasgow, and Stanford.
MIT mechanical loss
numbers by mode, for the three lowest modes, are 3.6e-4, 3.3e-4, and
4.2e-4. Glasgow's
cumulative phi at higher frequency is 3.8 +/- 0.5e-4. This is compared to a phi
of about 4e-4 typical of undoped tantala/silica
from CSIRO, so minor improvement at best in thermal noise performance.
Optical absorption
measured at Stanford is 10-12 ppm, well above the 0.5
ppm advLIGO spec.
This is probably a fatal flaw, especially considering the lackluster mechanical
loss.
Further coating work with
CSIRO will likely focus on the silica doped titania which did show some improvements in thermal
noise properties.
Input Optics
From: David Reitze
<reitze@phys.ufl.edu>
Mechanical design and
layout (Luke Williams)
- This week I have worked on the aligo IO layout,
routing all of the auxiliary beams (MC trans, MC refl,
IFO REFL, FI MON1, FI MON2, HEAT1, HEAT2, OL1, OL2, OL3, OL4, OL5, and
OL6). A complete layout should be in the PDMWorks
Vault by tonight.
EOM characterization (Wan Wu) - Our experiment is
aiming at hunting the small variation of the modulation index with 10*-8/sqrt(Hz) (relative noise) near 10 Hz using two phase-locked NPROs, one modulated with the EOM. Currently, we have the
two NPRO laser phase locked to each other with a 10 MHz offest
and relative phase noise suppression below 1 mrad/sqrt(Hz). The current
measurement sensitivity is limited by the laser intensity noise; an intensity stablization
servo for the laser is under construction.
Thermal Compensation in
Advanced LIGO (Muzammil Arain) - We are playing
around with the idea of using negative thermo-optic coefficients (TOC) material
to compensate substrate thermal lensing in the ITM
substrates. Initial research shows the viability of using calcium fluoride
(CaF2) as the potential compensation plate material. Further investigations are
being done into the material properties and availability of CaF2 and other
compatible material.
LLO HPTF (Simon Stepuk,
Ken Franzen) - The 100 W IPG
laser was returned from UF and installed in the LLO HPLF. The new version of
the laser is behaving well (!), except that the RS232 communication protocol
has been changed. We are working on changing our LabView
code accordingly to be able to monitor the laser. We have also measured
the thermal drift in a 100 W beam passing through calcite polarizers.
It was found to be less than 20 microradians.
Faraday Isolator - The prototype AdvLIGO FI was tested for vacuum compatibility and failed
miserably. This was not unexpected, because i) it was
not assembled in a clean environment, and ii) the casing was not optimally
designed for in-vacuum operation. We are in discussions with the IAP
group about this; the plan is to pre- clean and bake the components before
assembly and then assemble at one of the sites in a clean environment.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
- Elements of the PSL risk registry
were completed and sent to Dwight.
- I borrowed an Innolight NPRO from Eric Black (thank you) to measure
the intensity noise to see if features seen with the OEM Mephisto model were commonplace. At first glance
the low-frequency intensity noise is different; however with the noise
eater engaged, there is a large peak at approximately 50 kHz.
I have been sitting through the training material from Xilinx for setting up
Auxiliary Optics
From: Michael Smith
<smith@ligo.caltech.edu>
SLC
Hiro has obtained some preliminary
transfer functions for light injected into various ports in the ADLIGO RSE
configuration without the optical spring effect. We are in the process of
converting the transfer functions into the K-factors that I use in the scattered
light noise analysis.
AOS COST & SCH
The AOS cost figures were
updated and sent to Dwight Carter. I have revised the manpower requirements and
am working on the schedule and the risk assessment. I have completed the revision of the schedule
and the risk assessment.
Controls, Data Systems
No report this week.
Other Laboratory R&D
From: Riccardo DeSalvo desalvo@ligo.caltech.edu
Missed
several weeks due to travel. This is more a monthly
than a weekly.
Two Amaldi papers published and now available.
The third contribution, on optimized coatings, will be available later
separately.
www.ligo.caltech.edu/~desalvo/Amaldi-HAM-SAS.pdf
www.ligo.caltech.edu/~desalvo/Amaldi-Flat-top-beam.pdf
Yumei
- Done simulation and
actual resonance measurements of magic wand prototype for Alberto Stochino's paper.
- Done Simulation of resonant
damper with different blade joints
- Done simulations of HAM SAS
Spring Box internal modes studying different stiffeners, report #
T060066-00-E
- Working on HAM SAS static load
and IP counterweights
Valerio, Virginio
We are continuing to work
on HAM-SAS simulations. We are trying to add the triple pendulum chain to our
existing horizontal and vertical simulations. At the same time, we began to
make noise measurements on the LVDT sensors that will be used in HAM-SAS. This
will allow us to obtain more accurate control models simulations.
In the meantime we have
evaluated two new software packages, Dynaflex Pro and
BlockBuilder, from Maplesoft.
The first is a completely symbolic mechanical simulator and so it can be
integrated in the Maple models we already developed. BlockBuilder
is able to convert any Maple object, e.g. motion ODEs,
in linear objects - such as state-space, zero-pole-gain, tf - and to generate automatically Simulink blocks from Maple symbolic models. This last
feature seems particularly useful since our control models are all made with Simulink.
Riccardo
- Preparing HAM SAS production,
kickoff meeting at Galli&Morelli next week
- Designing SAS isolators for
external optical benches.
- Discuss future developments of
Mesa beam test interferometer with LMA, Juri Agresti (Pisa), John Miller (Glasgow), and others. We concluded that there is no advantage
in building Mexican Hat mirrors small enough for the present 7 m rigid
structure cavity. Such small
mirrors are hardly feasible and would cost more tha
building a longer vacuum system with larger, cheaper mirrors.
Following that consideration we are studying the feasibility of a longer,
fully suspended interferometer. This study, as
well as completion of the measurements with the present setup, and studies
of beam stability in power recycled mode, are expected to be part
of John Miller doctoral thesis.
- Working with Marco Tarallo and John Miller in writing up the paper
including the experiments and data collected so far with the MH
interferometer.
- Discussed at LMA Optimized
mirror options with Vincenzo Pierro
(Sannio) and the local experts.
- Reviewed the local method to
measure material Q-factors on coatings on thin diving boards. The techniques to evaluate systematics improve the quality of the data treatment,
and possibly measure poisson and Young moduli.
- Discussed
the possibility to increase the data quality by using diving boards welded
to thick substrates, contributed by Glasgow.
For additional information about this report, contact S. Whitcomb or P. Lindquist