Weekly Report for Week Ending March 23, 2006



Due to the LIGO Staffing Committee Meeting March 27, 2006, there will be no LIGO Executive Committee meeting scheduled that day.


Special Announcements:


Weekly Report Highlights

Many people were at the LSC Meeting held at Hanford this week.  Therefore, reported activity is less than normal (and this report is a little late).


LSC Issues (Saulson)


A very successful LSC meeting was held at LHO this week. There were 169 registered participants. Among the highlights were accounts of many recent data analysis results, and sessions on Advanced LIGO as well as enhancements to initial LIGO. At the LSC Council meeting, we

  • Admitted a new group from Montana State, Billings (Matt Benacquista)
  • Had a very positive discussion about the draft MOU on collaborative research with Virgo (Benoit Mours participated in part of the discussion.)
  • Approved the new LSC Bylaws, after amending them to have the appointments made by the Spokesperson be put up for approval by the Council.
  • Discussed the new LIGO Board, and suggested that the second LSC member (besides the Spokesperson) be elected by the Council.

LIGO Laboratory Administration (Lindquist)


STATUS OF LSC MOUs (Lloyd)

LSC MOUs and Research Plans and Progress Reports

  • No report this week.

SITE TELECONFERENCE (Lindquist)

A site teleconference was conducted Thursday, March 23, 2006.  The following were among the issues discussed:

  • Livingston Science Education Center—reporting a little ahead of schedule due to cooperative weather.  The roofing systems are nearly complete and interior partitioning is going up.
  • Livingston LDAS Structure Status—the computers have been moved into the structure and powered up.
  • Van for Livinsgton—according to the NSF the earlies for a GSA van is March 2007.  Should consider purchase or lease.
  • P-Card Training at Livingston—Jennifer Mertz and Ed Jasnow will be going to Livingston April 19 to do P-Card training.
  • There are no open assigned actions.  The list of assigned actions updated through December 1, 2005 (the last time that it was updated) will be found Here.

PROPERTY MANAGEMENT (Luna)

>From: Rod Luna <rluna@ligo.caltech.edu>

  • Provided assistance to the Detector Group (H. Armandula) with packing, shipping, and preparation of a Commercial Invoice for US Customs Clearance of four Fused Silica Substrates and four Teflon Caps to Lyon, France.  Account Number LIGO.OPT - 5.4 - NSFLIGO.FY02ON.
  • Prepared new guidelines for Capital Equipment tagging.

DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

  • No report (LSC meeting)

>From: Cleveland Mak mak_c@ligo.caltech.edu

  • No report (New Child.)

COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman)

>From: "Cronin, Holly" <Holly.Cronin@caltech.edu>

>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

  • Completed change order #2 to Cangelosi Ward for the LDAS Housing structure at LLO and submitted it to the vendor. Requested and obtained the renewals for the Insurance certificates from Cangelosi Ward. Distributed copies. Distributed copies of the certificates.
  • Prepared the procurement package for Galli and Morelli and routed it for approvals. Caltech approvals were obtained. Once the NSF approval is obtained, then Caltech will sign the purchase order and contract and send it out for distribution.
  • Holding change order to LSU #1022280 for the weather station while we are getting information about the rate that applies to this order.
  • Working on change order #171 to Triad for an 8-month extension of the time period for one contractor.
  • Working on several issues with the subcontract to University of Florida.
  • Still following up on a pending credit that is still outstanding for the pulse generator that was returned for credit.

>From: Florence Kaufman <fkaufman>

  • Prepared a Cost Transfer correct the payment to the Exploratorium from the Hanford Outreach account to the Livingston Outreach account.
  • Provided a summary of travel expenditures incurred for Detector Installation and Commissioning from 1998 to 2002 to Dennis Coyne.
  • Attended a meeting regarding classification of LIGO summer students.  The appropriate expenditure type to be used is "Stipend - Participant Support", this expenditure type is exempt from Indirect Cost.
  • Notified PMA division that incorrect expenditure type had been used on payment in the Visitor account, which resulted in the imposition of Indirect Cost.  Expenditure type is to be corrected.
  • Financial reports can be found at: http://docuserv.ligo.caltech.edu/~fireport. (For passwords contact Florence)

SUBCONTRACTS MANAGEMENT (Jasnow, Salone)

>From: Gina Salone <gsalone@ligo.caltech.edu>

  • Nothing significant to report.

>From: Ed Jasnow <jasnow@ligo.caltech.edu>

  • The construction of the LLO Science Education Center remains on, or possibly ahead of, schedule due to a long string of good weather.  The roofing is nearly done, which will result in the complete enclosure of the building.
  • The LDAS structure is complete to the point that the computers have been moved, powered, and are now in operation.  A few finishing touches remain on the structure itself.
  • Three e-mails were sent out concerning teleconferencing.  The first was a list of techniques from AccuConference to make teleconferences clearer.  The second was a list of countries that can be directly dialed for the same rate as a domestic call.  The third was the domestic and international access numbers for a backup system to the current AccuConference system.  Essentially, these are the numbers to the old system, and an be used if there are any issues with the new system.
  • The contract with Galli & Morelli for the design of the prototype HAM-SAS was approved by Caltech Purchasing Services and forwarded to the NSF for review and approval on Tuesday, March 21.

SUPPORT (Baldon, Hiroto, Lloyd)

>Irene Baldon

Worked on the usual new trips, expense reports, reconciling, calendar reservations, and itinerary entries.

>Julie Hiroto

No report.

>Dorothy Lloyd

  • Processed the usual requisitions for POs and payment request, and approved and submitted the weekly incoming invoices to accounts payable for payment.
  • Jim continued with data entry in the LIGO database and helping out in the DCC.

PROPOSALS and REPORTS (Lindquist)

Advanced LIGO Review Preparations (See Advanced LIGO Review Preparations)

CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)

  • Change request CR-060004 was submitted by Allen Sibley, March 16, 2006.  This change request moves budget previously discussed and approved into account WBS 3.12 (LDAS Maintenance) to cover the costs for the new ground-floor LDAS enclosure. The enclosure provides infrastructure (HVAC, electrical, lighting, communications. etc) and sound attenuation for the LDAS complex.  Using account 3.12 assures proper allocation of taxes and overhead.  Since this request only moves budget into the appropriate account and does not allocate any additional budget, we have not scheduled a meeting of the LIGO Change Control Board.  There were no comments or concerns expressed, and the change request will be forwarded to J. Marx for his signature.

HUMAN RESOURCES (Akutagawa)

>From: Cindy Akutagawa <cindy@ligo.caltech.edu>

  • The next Staffing Committee meeting is scheduled for Monday, March 27. The DRAFT agenda for the Staffing Committee has been posted on the SC web page.
  • All files for the Staffing Committee are up-to-date and posted on the SC web page.
  • Prepared numerous appointment and reappointment memos for various Visitors, Post Docs, and Term Staff
  • Processed time sheets and submitted to payroll.

Quality/Safety (Tyler)

>From: Bill Tyler tyler@ligo.caltech.edu

No report.


LIGO Hanford Observatory (LHO) and Interferometer Operations (Raab)


Summary of Commissioning Activities at LIGO Hanford Observatory (compiled by M. Landry)

The LSC meeting took place this week, and our largest-ever crowd of 174 participants joined for data analysis updates, technical sessions and face-to-face meetings.  Many thanks go out to Terry Gunter, Terry Santini, Tara Brown, Corky Ray, Christine Barker, Linda Turner, Mike Pedraza, Richard McCarthy and others for making the meeting such a success.

Recall last week the air flow in the LVEA was brought to ~75% of the pre-commissioning level via the starting of a third HVAC fan.  The hope was to improve lagging duty cycles through better temperature control, which appears to have worked: duty cycles for the week were H1 - 86%, H2 - 85%, at about 14Mpc and 7Mpc, respectively.  These duty cycles meet our target goals for S5.  While we benefited from low microseism throughout the week, there was considerable activity on the site given the LSC meeting.  Temperatures have indeed stabilized (for a more recent trend, click here).

Some S5 elog highlights are bulleted below:

  • the standard set of range and duty cycle plots was posted
  • PulsarMon shows distinct features compared to other FsOM, in that it monitors the noise only at 59.5Hz (0.1Hz below the Crab)

4K IFO

  • glitching on the 4k was supressed by lowering the ISS gain.  In follow-up studies, the VCO control signal was observed to have a peak at 249kHz.
  • the unity gain frequency of the mode cleaner was again found to be problematic, this time a factor of 2 too low, and thus flaky electronics are suspected.  The ugf is to be remeasured each time the MC relocks.

2K IFO

  • small optic 'hold' servos were readied, and will be tested, in order to ensure the optics remain roughly fixed in angle relative to their cages, as this has been shown to speed relocking

CDS

  • the new Sun ilog server crashed and had to be replaced
  • the Tuesday CDS maintenance summary is given here

LIGO Livingston Observatory (LLO) and Interferometer Operations (Zucker)


No report.


Initial LIGO Detector Science & Engineering (Coyne)


CDS

See the CDS weekly meeting minutes in the commissioning archives

DMT

No report


40 Meter Interferometer (Weinstein)


Keisuke Goda ("Go") from Nergis' Quantum Optics group at MIT will be visiting for the next ~ 6 months. Please make him welcome!

Fumiko Kawazoe visited from NAOJ in Japan and gave a talk on the status of her 4m RSE prototype interferometer. She has locked the FPMI and is moving on the PR and RSE.

Osamu presented a status report on 40m progress at the LSC technical plenary session.

IFO Commissioning

  • Because of some jostling, the beam exiting the MCR beamline was misaligned. Dan realigned things and re-established MC lock.

IFO Modeling

  • Monica now has all of the length control loops implemented and tested, except for PRC (which comes next) in her e2e simulation of the full 40m/AdLIGO optical configuration. She fixed the problem with her POX and POY loops and the OLTF now looks fine.
  • Osamu presented some calculations by him and Kentaro on AdLIGO shot noise sensitivity and loop couplings including exploration of various different sensing schemes, at the LSC session on AdLIGO ISC.

DC Detection and Vacuum Squeezing Development

  • Rob, Sam, Ben and Jay have been working out the details of the DC readout controls. Jay is drawing up detailed schematics for the digital controls, based on PCIX technology (instead of VME).
  • Rob and Sam glued the OMC PZT to its bracket and the small mirror to the PZT.
  • Go installed some of the components of the vacuum squeezer onto the PSL table, and installed pickoff mirrors to direct the dumped light from the meain PSL beam over to his setup.
  • Go continues to develop his conceptual layout of the squeezer system on the PSL table.

Electronics, Controls, Computers

  • Rana found that the PSL/IO Anti-Aliasing chassis from the PSL rack was almost useless; many of the signals were railed or extremely noisy. Dan is desoldering all the filter chips and replacing them each with a single jumper wire.
  • Rana changed the DAQ datarate for the X and Y arm QPDs from 2048 to 16384. He then discovered an aliasing problem that is supposed to be performed by low-pass filtering in the front end code. He asked Rolf to fix it.
  • Rob and Rana re-commissioned the AO path of the Common Mode servo, using REFL_DC (from SP33) as the signal.
  • Rob made some changes to the LSC code, including the addition of the REFL_DC signal, and a re-implementation of fast input matrix ramping without incuring cpu slow-down.
  • Ben continues testing of the noisy I&Q Demod board for ASPD 166MHz.

Lab Infrastructure

  • Steve finished the installation of protective beam tubes on all the high-powered beamlines in the PSL enclosure, including the MCR beamline.
  • Steve put the PSL enclosure HEPA filters on a Variac and is running them at 40% of 120V. It is much quieter and particle counts are zero for 0.3 and 0.5 micron at the north west corner of psl optical table.
  • Steve and Go have assembled several pairs of laser goggles which work in both the IR and the green, for protection when working with the new second-harmonic-generator (SHG).

Thermal Noise Interferometer (Black)


Initial data from the TNI shows that, while the ring-dampers do reduce the in-situ Q's of the mirrors as expected, they also increase the broadband noise floor. This was not expected, and we are debugging to make sure this is not due to some other, technical noise source.


LASTI (Ottaway)


The majority of the LASTI crew were at the LSC so we had limited progress at LASTI this week.


Data Analysis and Computing (Lazzarini)


Simulation and Modeling (Yamamoto)

Scattering Noise (Hiro Yamamoto, Mike Smith)

The result of e2e simulation of scattering noise was discussed among Hiro and Mike.  Mike needed more injection points of scattering noise source.  Hiro will finish the calculation next week.  Calculations to confirm the result using twiddle and e2e 40m configuration will follow.

Quantum correlation in e2e (Hiro)

During the discussion with Somuya and others last week, it was suggested that a simple way to properly include the quantum correlations among the radiation pressure noise and shot noise is to inject vacuum from the dark port. The first test to be done soon is if the sensitivity curve can be reproduced without the current explicit implementation of radiation pressure and shot noise.

QuadFP  (Hiro)

The FP setup with quad pendulum is updated to have WFSs and QPD so that Rana will be able to test ASC which has been designed in SINLINK using a parameterised pendulum.

40m simulation (Monica)

The open loop transfer functions for XARM and YARM with POX and POY demodulated at 33MHz have been simulated: the feedback filter for the arms has been improved to get stability in order to acquire those transfer functions.

Static Interferometer Simulation (Hiro, Melody)

The script to create a distribute package of SIS software is being developed.  The object definition parser code has been modified so that object can be defined in the code. This is to streamline the setting of the simulation setup.

modeler code (Bruce)

Completely reorganizing the parser code.  It is a bit jumbled  from past additions perhaps.  The main problem being that some  base class members are expected to contain data which should only  be expected to be in the derived class.  Rather difficult to  disentangle, but worthwhile for when the parser needs modification.

Data Analysis Activities (Lazzarini)

Chatterji:

Attended LSC meeting.  Gave presentations on proposed slides for the April APS meeting, details of the Q Pipeline search applied to S5 data, and an overview of the QScan utility.

Dupuis:

  • attended pulsar face-to-face and LSC meeting

Mendell:

Preliminary results from the Stackslide search for continuous gravitational waves from LIGO S4 data were presented at the March pulsar F2F/LSC meetings. The talk has been submitted to the DCC as LIGO-G060082-00-W.

Shawhan:

  • Updated the technical details document for the S4 all-sky burst search.
  • Organized and attended the Burst Group face-to-face meeting.
  • Attended the LSC Meeting and gave a few talks.
  • Updated segwizard to allow queries for data quality flags at or near a specified GPS time.

Sutton:

I spent all week at the bursts face-to-face meeting and the LSC meeting.  I presented the results of the coherent network analysis test for discriminating gravitational-wave bursts from instrumental noise.  I also had some fruitful discussions about network analysis, particularly with Rakhmanov and Heng.

LIGO Data Analysis System

Software Systems (Maros)

LDAS

A new unit test has been added to verify that LDAS can handle large frame files (>4Gb) (PR#2135).

Efforts continue on the 64 bit port of LDAS. Rules have been added for building Xerces (XML parser by IBM) 64 bit.  It has been demonstrated that Globus GSI authentication adds considerable overhead to job processing.  CmonClient is now bundling requests so all requested graphs will appear.  The nightly testing scripts have been updated to submit using either gsi or non-gsi sockets.  System testing of LDAS was performed using version 1.8.123 of the software.

TCLGlobus

The remaining problem reports for the 0.5.0 release have been closed and a release of the software is expected early next week.  The library now check for X.509 service credentials for client program running with service credentials.  Online TclGlobus documentation supporting LDAS's usage of Globus sockets has been completed.  Nine of twenty-five Globus GRAM Cache have now been incorporated into unit tests.

GRID COMPUTING

Attended an ITB installation and validation telecom on OSG 0.3.6.  Installed Condor 6.7.17 and OSG 0.3.6 on the LIGO-CIT-ITB cluster.  Successfully ran Inspiral pipe work flows to completion on two OSG 0.3.6 sites as part of the OSG 0.3.6 validation effort: ITB_INSTALL_TEST, and FNAL_FERMIGRID_TEST.  Worked with four other OSG 0.3.6 sites to determine problems related to the inability of those sites to execute the LIGO application.

Hardware Systems (Anderson)

Caltech

(Dan Kozak)

  • Fixed problem with LLO's fb1:/dmt getting I/O errors because it could no longer see the underlying device (reasons unknown).  Used devfsadm to get the device back and then it worked again.  Spent some time 
  • writing this up and explaining the various FC/QFS/Solaris issues with this kind of failure to those in the line of fire at LLO.
  • Talked to Kevin Flasch a bit about the LDRdataFindServer SQL query.
  • Did much work associated with the LLO LDAS room shutdown.  Besides the normal "make sure everything is on tape" I also ended up repacking some tapes that SAM-QFS had strewn data across.  This work will continue when the system comes back up.
  • Called in, received and installed power supply for 3510-10 at CIT.
  • Normal ingestion stuff, but discovered a bug/misfeature in Ben's Disk2Disk script.  While it correctly flagged last week's bad LLO frames and didn't copy them, it did write their md5sums to the .md5 file.  Ben has fixed this at LHO and I'll remind him to do so at LLO once we're up and running again there.

(Phil Ehrens)

  • DOE cert enabled Apache on ldas-test and documented procedures in sysadmin wiki.
  • Added "tripwire" module to log_scan.tcl unified log monitor, ID, and reporting tool. log_scan will now report any modification to critical system config and binary files.

(Erik Espinoza)

  • Moved node151 to node327 (reccuring raid issues).
  • Building and documenting kickstart servers for other sites (should be completed early next week).
  • Ran temperature probes for LIGO CIT data center, http://ldas-kickstart.ligo.caltech.edu/cgi-bin/realtime
  • Wrote email notification script for high temperature alerts.
  • Rebooted node247 (kernel panic).
  • Looked into sendmail vulnerability.

(Stuart Anderson)

  • Finished copying S4/S5 L1/L3 RDS frames into the CIT cluster for quicker data access. These data are not yet published into LSCdataFind.
  • Helped coordinate the LLO LDAS equipment move.

MIT

(Keith Bayer)

  • With help, the 80 node cluster has been wired for 100Mb/s and Gigabit ethernet.
  • Cluster nodes have been configured for running at MIT.
  • Condor cluster has been brought on-line.

Livingston (Stuart for Igor and Dwayne)

  • Moving the LDAS equipment (including electrical and HVAC) to a new location in the same building.

Hanford

(Ben Johnson)

  • Attended a few sessions of the LSC meeting including the DASWG discussion.
  • Consolidated and inventoried tape cabinet in LDAS room. There are now 1013 tapes in the cabinet, and I have record of each tape's slot and VSN. I took about 45 minutes to perform the inventory: 30 for the  scanning, 15 for the verification later (number in drawer == number scanned in drawer + fixes).
  • Nearly finished with the tape catalog software. I have already used it to insert the initial inventory of tapes as well as to find and remove 3 previously missing tapes.

General Computing (Wallace)

MIT:

(Keith)

  • Ordered SCSI enclosures for upgrading GC fileserver
  • Rebuilding sendmail 8.13.6 to incorporate security patch
  • Wrote some documentation on LDAP
  • Supplied data taking pc and new static ip for Eugeniy's lab project
  • Received copper gig-eth cards for SB1000's

Livingston:

(Shannon)

  • This has been the week for disk failures.  One RAID controller died on Monday AM.  The RAID is completely dead and had only been in service for a couple of weeks.  I initially suspected power supply issues, so had the vendor send out a power supply.  Replaced it and this did not fix the problem.  I will likely have to send this unit back.  Unfortunately there was a bit of probably irreplaceable data there.  Then on Wednesday morning, I found a failed drive on the file server RAID.  I replaced the drive, then during reconstruction, a second drive failed.  Irrecoverable for a RAID 5 unit...  This machine was also the backup server, and as such all of the tape indexes, etc. were on the RAID.  Luckily I had originally set it up so that there was a standalone tape drive installed dedicated solely for backup up the backup software.  The software was installed on its own slice on the RAID drive, so restoring the backup software was relatively easy after the RAID finished rebuilding.   I lost a total of 4 drives on this RAID in one day.  The drives are about 2 months from the warranty expiring.  After I had the backup software restored, I was able to start restoring the rest of the data that was on the RAID.  I lost my software mirrors since I intentionally did not have them being backed up.  This data is easily replaceable from various repositories (CIT, Open Source stuff, etc.).  For some reason I had to restore twice, since the first pass only restored the directories?  Haven't figured this out yet in the last few hours.
  • updated the IDS rulesets.
  • updated the IDS web interface with the newest version - More pouring through logs (IDS, syslog, etc.) - Set the mail server to check against the sbl-xbl.spamhaus.org lists.  This should cut down a fair amount of spam.  Still haven't managed to get the logs to work though.  I will have to open a support case with Sun.
  • Received the contract info from Sun on our support contracts.  One is expiring this month.  I will have to review what is under contract and decide what can be dropped and what needs to be added for hardware support.
  • Matlab licenses are up for renewal this month.  Will have to work with Mathworks on a quote.
  • RMA'd a couple of hard drives.  Maxtor as usual is nearly impossible.  Western Digital is a piece of cake.  Total of six drives dead this week.

Hanford

(Christine)

  • LSC meeting support:  Two incidents of computer misuse by LSC attendees were reported by ESnet.  This LSC had the most attendees of any meeting held to date at LHO.  The wireless network was intermittent and there wasn't enough of most everything.  The break out meetings were spread all over the site in three buildings which required a lot of walking and carrying equipment.
  • Backup network troubleshooting:  Replaced the media converters between PNNL and LIGO with 100 mb converters instead of 10 mb.  We are now seeing receive and transmit traffic through the media converters, but I am still unable to get to ESnet over the backup circuit.  PNNL thinks the problem may be at my router as they are able to ping ESnet from their end over the backup circuit.  Amerion is able to ping both ESnet and LIGO over the backup circuit.  PNNL has suggested some configuration changes to try on the router.

CIT

(Sears)

  • iLog Maintenance: Working with Dave Barker at LHO to port iLog to a new server.

(Mike)

  • Loaded an updated server to replace our current media server; this is an going project.
  • Continued work on spam-filters with Larry W.
  • Worked at LSC conference most of the week.

(Veronica)

  • LSC:  Ongoing support of the March meeting.  Installed the presentations webpages.  Updates of the Technical Papers website, other LSC-related pages.
  • LIGO:  Ongoing work on the Elba meeting website.  Configured and troubleshoot the database backend, this part is ready to go.  Working on the rest of the scripting.  Updates of the CIT /MIT websites.  Did more video editing per Stan's request.  User support.

(Christian)

  • Created a backup of Julie Hiroto and Florence Kaufman workstations.
  • Irene Baldon- Replaced toner cartridges on Irene's local printer.
  • Worked with Dwayne on getting Solidworks installed on Janeen's workstation.
  • 3flr W/B - Replaced toner cartridges on HP 5500 printer.
  • Larry and I mounted two new servers on a rack mount to be configured in the server room.
  • Re-imaged laptop that was returned to the loaner pull this week. Also, a laptop was returned to the loaner pull this week with a dead hard- drive.
  • Waiting to see if I can find any extra drives to reconfigure the laptop.
  • Other misc.: Continued onsite software/phone support

(Larry)

  • Continual work with different procurement items. Wrapped up a few orders for different groups.  Streaming-video s/w license has been renewed and the upgrade should be installed next week.
  • Assisted DCC in posting of documents. The web service for one of the document directories was having some performance problems. The directory was moved to another machine to eliminate the performance problem, which did work, however the investigation continues on why the first machine was not performing as it should.
  • Worked a number of LSC meeting logistical issues with Christine and Mike. A change of procedure by the GC group in support of the conferences has already been changed. Basically, more support will be provided for these meetings.
  • Installed a couple of new s/w pkgs. for different people.
  • Worked a couple of h/w installations including a couple of units with Christian.
  • Assisted Barry B. with various issues. Time to look at some new tools for the mobile users.
  • Continual work on the spam filters.  We had a nice spam storm this past week. Over 3000 spam messages in less than 5 minutes.
  • Reviewing and updating the GC usage policy with Albert.

Advanced LIGO and Supporting R&D (Shoemaker)


AdL report absent due to intensive networking at the LSC meeting.


For additional information about this report, contact S. Whitcomb or P. Lindquist