Weekly Report for
Week Ending March 16, 2006
Due to the LSC Meeting March 20, 2006, there will be no
LIGO Executive Committee meeting scheduled this Monday.
Special Announcements:
Weekly
Report Highlights
No report. LSC Meetings currently in
progress.
LIGO Laboratory Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
LSC MOUs and Research Plans and Progress Reports
SITE TELECONFERENCE (Lindquist)
A site teleconference was conducted Thursday, March 16, 2006. The following were among the issues
discussed:
- Contract
for CES Kinetic Façade—the contract has been awarded.
- SEC
Construction—Building nearly enclosed, but there is still some
fairly noisy equipment on site disrupting S5 operations.
- Property—Capital
equipment at Livingston has not been
tagged in accordance with policy (within five working days). Corrective action is being discussed.
- Teleconferencing—a
brief conversation with the president of Accuconference is scheduled
immediately following this meeting to discuss options relative to recent
service issues.
- There
are no open assigned actions. The
list of assigned actions updated through December 1, 2005 (the last time
that it was updated) will be found Here.
PROPERTY MANAGEMENT (Luna)
>From: Rod Luna <rluna@ligo.caltech.edu>
- Updated
Hanford
inventory in the Caltech's property records system.
- Provided
assistance to the General Computing Group with the shipping of 5 Laptops
and 3 Projectors for the LSC meeting @ LHO. Account Number LIGO.DIR 1.1.1
NSFLIGO.FY02ON.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
- No
report (at Hanford
for LSC meeting).
>From: Cleveland Mak mak_c@ligo.caltech.edu
|
Week Ending
March 16, 2006
|
In
|
Out
|
|
Packages
|
42
|
7
|
|
Faxes
|
13
|
16
|
- Worked on old stack of MOU's/Progress
Reports (checked for database entry, electronic copies and hard copies on
file).
- Total
volume of incoming packages was much higher than normal.
- Scanning
- Progress continues on scanning of contract closeout files.
COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Working
on change order #2 to Cangelosi Ward.
- Completed
change order #36 to Excel Engineering to add funds to cover pending
invoice and submitted it to the vendor.
- Received
change order #16 to the University
of Florida back from
routing and submitted it to the vendor.
- Completed
change order #31 to Galli and Morelli and submitted to the vendor.
- Placed
various purchase orders for goods and services which included repair of
equipment, reprint color charges, reimbursements for various individuals
at LIGO sites, and electrical work.
- Responded
to LSU, Ag Center's request for approval of a change in Principal
Investigator.
>From: Florence Kaufman <fkaufman>
- Notified
by Property Services Department that they require a
"justification" whenever expenditures for a fabrication account
exceeds the estimated cost for the fabrication which was indicated on the
original Fabrication Equipment request by more than 20 percent. This justification or explanation can be
in the form of an e-mail to the Property Services Department explaining
the reason for the increase, such as scope change, etc.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- The
contract for the design of the kinetic facade for the LLO Science
Education Center (SEC) was awarded to HPD, Inc. Representatives of HPD attended a meeting
in San Francisco
with Mike Zucker and representatives of the
Exploratorium to view their kinetic exhibit models.
- The
LLO SEC construction remains on schedule, and the building will shortly be
fully enclosed (See photo). They
still expect about two or three more weeks of noisy construction
activities.

- The
construction of the LDAS structure inside the Staging Building
is nearly complete, and movement of the LDAS equipment into the structure
is scheduled for next week.
- The
review package for the HAM-SAS prototype for Galli
& Morelli is being reviewed prior to being
submitted to the NSF for approval.
The NSF should receive this package early next week.
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
Worked on the usual new trips, expense reports,
reconciling, calendar reservations, and itinerary entries.
>
No report.
>Dorothy Lloyd
- Processed
the usual requisitions for POs and payment request, and approved and
submitted the weekly incoming invoices to accounts payable for payment.
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
PROPOSALS and REPORTS (Lindquist)
Advanced LIGO Review Preparations (See Advanced LIGO and Supporting R&D (Shoemaker)).
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
- Change
request CR-060004 was submitted by Allen Sibley, March 16, 2006. This change request moves budget
previously discussed and approved into account WBS 3.12 (LDAS Maintenance)
to cover the costs for the new ground-floor LDAS enclosure. The enclosure
provides infrastructure (HVAC, electrical, lighting, communications. etc)
and sound attenuation for the LDAS complex. Using account 3.12 assures proper
allocation of taxes and overhead.
Since this request only moves budget into the appropriate account
and does not allocate any additional budget, we have not scheduled a
meeting of the LIGO Change Control Board.
If there are no concerns, the change request will be approved at
the end of next week (March 24).
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- The
next Staffing Committee meeting is scheduled for Monday, March 27 and I am
gathering information for the agenda.
All files for the Staffing Committee are up-to-date and posted on
the SC web page.
- Prepared numerous appointment and reappointment
memos for various Visitors, and Post Docs.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
Nothing significant to report this week.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of
Commissioning Activities at LIGO Hanford
Observatory (compiled by M. Landry)
Duty cycles remain a concern at LHO, with this week numbers (H1 - 77%, H2 -
73%) lower than targeted. As the mean-time-to-lock on both machines
appears higher since the HVAC modifications, one more fan was turned on
Wednesday morning for the LVEA to bring us back to 75% of the air flow of
pre-commissioning levels. We will monitor
the effect on duty cycles in the coming week and hope the mean-time-to-lock
drops below its current ~1-1.5h value.
Some elog
highlights are bulleted below:
- the
2k MC servo gain was varying by 6dB on measurements, so the MC
servo card was swapped out
- TCS
enclosure for the 4k improved laser power and stability markedly
- duty
cycle and range plots, with extrapolation
to the end of the run
- the
H1 steering mirror was found moved
to new place, not near historical location, and the IFO was aligned around
this
- Burst
studies
were made on H2
- dust
levels on ISCT10 indicated some problem which was later attributed to gaps
in the shroud
- links regarding duty cycle (Garofoli):
"I now [calculate] a rolling lookback of
the statistics over the past
7 days. Additionally, these are archived so that you can get the
one for this
week. To find the current day's archive, just look in the first
link directory (ie here).
-J.G."
Outreach (D. Ingram)
Raab and Ingram hosted a meeting of the LHO Local
Educator Network (outreach advisory group) on 3/15. Josh Myers and Kyle
Ryan hosted a pair of Pasco High students for job shadows on 3/6.
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
S5 run summary (Franzen)
The week offered us several challenges: - It was observed that the power in
the 60 Hz harmonics were elevated more than an order of magnitude. This of
course reduced our inspiral range and also affected
the AS_Q histogram in the Figure-Of-Merit 2 display. The cause was found to be
due to a ground loop at IOT1.
- During
the week the IFO experienced several lock-losses during seismically quiet
times. The lock-losses were sometimes preceded by WFS oscillations. The
cause was found to be railing of the RBS servo, which in turn was caused
by misalignment of the beam on the REFL PD. The cause of this probably originated in
the installation of the lower PSL PZT mirror last week.
- After
the two items described above were resolved the system has been behaving
rather well, also thanks to the low seismic noise. The exception was the
occurrence of 1/f DARM noise in the 40-300 Hz region for 30 minutes around
midnight Tuesday to Wednesday. This phenomena has
been observed a few times earlier and the cause is still unknown.
- fb1 frame files were found to be corrupted. The data
was recovered from fb0 frames.
The major maintenance activities were:
- HEPI
development,
- SUS
channels added to daq,
- framebuilder 3511 was installed, and
- MC
WFS relief servo was reinstalled
LLO Outreach (Thacker)
Narrowed the final Exploratorium Exhibit purchase to candidate list of
8. Met with new
Exterior Exhibit contractor at the Exploratorium location to discuss direction
of effort.
LLO LDAS (Yakushin & Giardina)
(Yakushin)
Storage/Condor/LDAS admin:
- Made
more layouts for the computing equipment in the new location taking into
account the actual constraints of the room under construction;
- Scheduled
StorageTek/SUN engineer to help us with the tape
robot move next Friday;
- Scheduled
tape drive firmware to be upgraded to RQ.35.405 during next Tuesday
maintenance period. StorageTek engineer also
recommended to upgrade tape library code to
3.1.0.
- Received
final quotes for 1 year service contract for the SUN equipment, working on
PO;
- Installed
lscsoft on the nodes on Kipp's
request;
- Fixed
fftw3 rpm on ldas-grid on Kipp's
request;
- fb1
produced no more frames with incorrect checksum after last week daqd crash and restart; Disk2Disk and create RDS
scripts are switched back to use fb1 frames; users are notified that they
can resume using /frames;
- made
/cluster visible to ldas-jobs on Shourov's request;
- restored data on node209 after its disk was replaced.
(Giardina)
- ejected tapes for storage and imported tapes into L700
* ejected tapes for shipment to CIT
and imported tapes into L700 * LDAS
external network connection was lost temporarily due to power outage for
electrical work in new LDAS room.
Internal and framebuilder connections
remained up.
- working with Lisa on the 3511 setup.
- preparations
for LDAS move to new location
Data analysis (Yakushin):
1) Continue testing coherent version of waveburst
on S4 data; the results will be presented at the LSC meeting; 2) Working on APS
slides for my S5 burst talk. The current draft is available at http://ldas-jobs.ligo-la.caltech.edu/~igor/APS.
LLO General Computing (Giardina)
- finished with installing base image for Janeen's new PC, however having issues with Solidworks install complaining about file missing from
disk 3.
- main gate appears to be working correctly, at least for
now. Found a loose wiring
connection, and replaced a faulty component with one from the side
gate. Rich ordered and received
replacement and one spare.
- one of the Foundry EdgeIron
switches in the OSB failed. East
side offices were without network connection for most of the morning. Shannon
replaced inactive connections on the working switch with those that were
from the east side offices.
- removed
paper jam in copier, and straightened piece that was causing jams
- temporary power outage for new LDAS room electrical
work caused GC network outage in part of high bay building. LDAS lost its connection to outside
world, but internal LDAS and connection to framebuilder
remained OK.
- other
usual user requests and support
LLO CDS Computing (Bogue)
- Worked
with Dwayne and Dan to configure the sam-fs filesystem on the backup framebuilder. Dwayne and I are currently working on
reconfiguring the daq to give us more look back
on that machine.
- Continuing
to work with brian and
folks from hanford
to identify and resolve our channel discrepencies.
- Finished
the initial build of a new server for cds.
- Worked with ldas folks on
the framebuilder data corruption problem that we
had last week. Implemented recommended configuration changes
on the framebuilders to support future
troubleshooting.
Initial LIGO Detector Science & Engineering (Coyne)
DDS
See the CDS weekly meeting minutes in the commissioning archives
DMT
No report
Absorption Measurements on 4ITM07
Bill Kells
Although all the nails are not quite in the ITM07 "postmortem"
coffin, A few outstanding conclusions persist (and are being rapidly
sharpened).
1. Our (actually L. Zhang performing all the diligent instrumentation) most refined
"absorption
scans" of the contaminated ITM07 surface give a mean sampled area (~ 1
cm2) absorption of 12 ppm.
(Note that we have come to realize that the "absorption scan"
method we employ is not physically equivalent to the mean surface heating which
a LIGO cavity beam would induce. The heating beam size and vacuum /or/ air
environment can make crucial differences depending on the nature of the
contaminant).
2. A different ~ 1 cm2 sampled area of the same mirror, but
simply cleaned, and then scanned in exactly the same manner gives a mean
absorption of only 0.6-0.7 ppm. In this respect (to
cleaning) ITM07 responded to cleaning similarly to the in situ cleaned H1 ITMy.
3. Our calibration piece in this is a surface cleaned, 1" dia. test optic which is well characterized (at Stanford,
and in our OTF contamination cavity setup) to have a uniform ~19 ppm absorption characteristic of the HR coating itself.
When scanned (identical method as in 1. and 2. above) this calibration piece
shows a clean pixel histogram peak at 19 ppm.
4. D. Ottaway's latest H1 ITM lensing
analysis (LIGO-T050074-01-R) boils his conclusions for ITMx
down to: all ifo
observations consistent with 1. 13ppm pure HR surface
absorption; or 2. 42 ppm/cm
pure substrate bulk absorption. If I take the reasonable value of
~4ppm/cm for the actual bulk contribution and the rest being HR, then
this HR attributable value is ~12ppm (amazingly equal
to that found in 1. above!).
5. Although the mean of all pixel absorptions in the scan 1. (above) is 12ppm, the distribution is highly irregular. ~90%
of the pixels in this scan contribute to a histogram peak at ~ 1 ppm (per pixel absorption). However the remaining 10% form
a long tail (out to 100s ppm/pixel) above 10 ppm/pixel which dominates the mean absorption. That is, the
HR surface is extremely irregular in absorption (strikingly so in comparison to
2. and 3. above), not seemingly characteristic of a uniform [contaminant] film.
Of course, like all examined optical surfaces, ITM07 (which has been sitting
around in lab air for months) has a lot of surface "dust" particles
on it. Note that, if totally absorbing, only ~ 10 (10 micron) 2
per cm2 could cause the affliction we found in H1. We easily see
(with a microscope) this [gemetrical] level of
"dust”! However due to the details of our absorption scan technique
(step size an irregular ~ 100 microns. Probe heating beam dia.
> 100 microns, and other factors) it has not yet been possible to absolutely
conclude that the scan mean absorption of 12 ppm is
entirely due to distinct surface "dust". At this point is appears
that there very well may be an anomalous [quasi] uniform component (say ~ 1-2 ppm) as well.
Note from Dennis Coyne: This means that we can not currently say
conclusively whether outgassing in the current vacuum
environment coats the optic at a level which could be detrimental for ADL. Liyuan and Helena
will try to remove just the dust particles and see if the subsequent absorption
level is ~0.6 ppm. It is not clear whether any
techniques for removal of just the dust will work.
40 Meter Interferometer (Weinstein)
IFO Commissioning
- Rana, Rob and Sam made some progress in restoring full
lock. They can reliably lock the DRMI+2ARMs interferometer in the
anti-spring state with offset-CARM; acquisition was taking 1-3 minutes,
and lasting until they broke something. They could engage the digital path
of the CM servo, but not the AO path. They continue to be stymied by LSC
signal electronics problems, (see electronics section below) and are
working through them.
- Dan
and Monica are measuring the couplings from various channels into DARM,
including secondary loops, mirror alignments, oplev
loops, etc. They have determined suitable excitation levels. Now they just
need to lock the IFO and start measuring couplings. They have been
thwarted so far by various problems in the scripts, AWG, test points, etc,
and are working through the problems.
- Osamu
and Steve adjusted the alignment and minimized the reflected light in the
Mach Zehnder and input mode cleaner systems.
- Alan
is circulating a new draft of the 40m optical response paper; hope to
submit for LSC review in the next couple of weeks.
IFO Modeling
- Monica
continues to "commission" the length control servos in her e2e
simulation of the full 40m/AdLIGO optical configuration. She is measuring
the OLTFs of the different loops with DARM on
and off and radiation pressure on and off. MICH looks sensible and she is moving
on to SRC. She found the problem with her POX and POY loops that made
single arm locking difficult, and is following up on it.
- Rob
is back from NAOJ Japan, where he worked on a prototype displacement noise
free interferometer, with Seiji, Yanbei and
Keiko. Two publications are in the works.
- Rob
has implemented RF readout in his Optickle
modeling tool (matlab-based, with full
implementation of the Corbitt et al quantum
formalism).
- Osamu
is working on AdLIGO noise calculations.
DC Detection Development
- Ben
talked with Todd and procured some of the electronics that are needed for
the DC readout scheme. The OpLev chain is
preferred by Rana for DC detection alignment,
but none of the boards are here. He spoke with Jay, who felt that we
should all sit down and design the system, then
decide which electronics we should make based on our requirements. Ben
will get a meeting together with Rana, Sam, and
Jay to make this happen soon.
- Sam
added an optical chopper onto his DC readout alignment control test beamline, to diagnose the anomalous loss of phase. He
traced most of it to the oplev QPD readout board
which has two 800 Hz butterworth LPFs. He's thinking about how to fix this in a
modified board for the final system, in consultation with Jay and Rana.
Electronics, Controls, Computers
- Ben,
Dan and Rana have been looking at the noisy LSC demod boards. Ben and Rana
measured the noise with different LO input levels, and the amount of RF
leakage, and discovered some anomalies. The demod
board for ASPD 166MHz signal appears to be a factor of 10 more noisy than
the other boards. Ben is testing it at the Wilson House to determine if
the fault lies in the board. Meanwhile, Rana is
finding various problems with both the demod
boards and the PD DC Interface Boards, which are crucial for lock
acquisition.
- Ben
entered the LSC Whitening Interface Board connections at 1X2-2-12 into the
ilog.
Lab Infrastructure
- Bob
cleaned the beam tubes for the PSL enclosure, and Steve is installing
them. Should be done by next week.
- Steve is
experimenting with turning off the HEPA filter in the PSL enclosure during
commissioning to see what effect is has on the Mach Zehnder
drift and the laser noise.
Thermal Noise Interferometer (Black)
Since our last report, we have finished
installing the ring-damped mirror and re-aligned the interferometer. We closed
the chamber, and Akira has taken some preliminary data. Details to follow.
No report.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Yamamoto)
e2e weekly meeting
This week, we had an informal meeting with Kentaro
Somiya from AEI to discuss about the modeling of IFO
with optical spring.
Scattering noise simulation ( Hiro
Yamamoto )
Transfer functions from various injection points (PRM, SRM, ITM(AR and HR side) and ETM) with phase and amplitude
modulation to the CR amplitude at the dark port were calculated. The ratio of these transfer functions and the
DARM to the dark port CR amplitude signal will be used to set the final
requirement of the upper limit of the scattering field back injection. One problem found is that the frequency
dependence of the noise transfer function is different from the DARM transfer
function. The calculation was carried out without optical spring, because there
is no adv.LIGO simulation available which has optical
spring and LSC servo to stabilize the system.
The effect of the optical spring will be inferred using 40m simulation
with optical spring with a minimal LSC servo.
Static IFO Simulation (Hiro Yamamoto, Melody
Araya)
At the last optics modeling meeting, several important topics were pointed
out, including the loss budget in an arm), for which this SIS can shed a light
by simulating a FP configuration.
Programming is still going on to fill the lower level
...
40m modeling (Monica Varvella)
Comparison of different open loop transfer functions for the degree of
freedom DARM with and without radiation pressure and with and without the MICH loop closed. The DARM stability seems not be affected by
the MICH
loop. The same comparison has been done
for the MICH
degree of freedom with and without radiation pressure and with and without the
DARM loop closed. In this case the DARM
affects the MICH
loop not allowing to cross the UGF; probably it is
necessary to take into account also the contributions of the recycling mirrors.
Mechanical Simulation for adv.LIGO (Sany Yoshida)
Analyzed e2e modeling of Mode Cleaner transmitted light Yaw motion. Actual DAQ seismic motion recorded at LLO was
fed as seismic input to the e2e MC box. HAM table Yaw motion was created in
accordance with the model reported last week (i.e., create table top yaw as
“floor yaw to table top coupling” plus “additional phase
delay on table top due to differential translational motions ’). Power
spectrum of the computed MC transmitted Yaw motion has a broad peak in 0.5
1.5 Hz while the corresponding experimental MC transmitted beam Yaw signal
(DAQ) has a valley in the same frequency region. Computed MC optic’s yaw
motion also has a valley in this frequency region. The reason for this
discrepancy in MC transmitted Yaw spectrum between computation and experiment
is unknown.
Modeler Coding (Hiro Yamamoto, Bruce Sears)
Hiro modified the fast DRM code so that scattering
light can be injected to the side of mirrors facing to inner side of a
Michelson cavity. Bruce is improving the
box file loading code by utilizing the knowledge of the new box file format.
Data Analysis Activities (Lazzarini)
Brown:
- Looking
at results of S5 BNS search
- Inspiral review duties for S3 and S4 BNS and MACHO -
Working on parameter estimation for EMRIs -
Wrote a chapter for the book "Workflows in e-Science"
Chatterji:
- Performed
time shift study of double coincident H1H2 and triple coincident H1H2L1
triggers from the online S5 Q Pipeline analysis through Feburary 1.
- Prepared
preliminary slides about the online S5 Q Pipeline analysis for the April
APS meeting.
Mandic:
- I
have performed several tests and updates to the S4 all-sky stochastic
analysis, including hardware injection error estimates, marginalization
over the calibration uncertainties for the all-sky result, study of the
frequency dependent theoretical sigma etc.
- I
have completed several tests suggested by the review committee, and I have
produced several figures and tables to be shown at the LSC meeting (and
potentially at the APS meeting). I have also posted a new version of the
S4 all-sky paper on the stochastic ILOG.
Mendell:
StackSlide results for the S4 H1 and L1 data from
50 to 340 Hz are under going review for presentation at the LSC and APS
meetings. I am working on these talks and a paper with S4 results using the PowerFlux, StackSlide, and Hough
methods.
Shawhan:
- Calculated
sensitivities for S4 all-sky burst search, incorporating uncertainties
from fit parameters and calibration.
- Prepared
for LSC Meeting and Burst Group face-to-face meeting.
Sutton:
I've spent the week putting most of the finishing touches on the paper for
the coherent analysis consistency test presented at GWDAW. The main efforts have been to fix the
whitening by training on data excluding the injected signal, setting up
simulations to check the whitening and various test statistics, and a lot of
editing of the paper.
Weinstein
- Continuing
the review of the inspiral analysis.
- Yet
another reading of the LIGO-TAMA BNS paper.
- Review
of Alex Dietz' GWDAW paper.
- Continuing
work with Lisa on the ringdown search, including
a review of her GWDAW paper.
Yakushin:
1) Continue testing coherent version of waveburst
on S4 data; the results will be presented at the LSC meeting;
2) Working on APS slides for my S5 burst talk. The current draft is
available at http://ldas-jobs.ligo-la.caltech.edu/~igor/APS.
LIGO Data Analysis System
Software Systems (Maros for Blackburn)
LDAS
LDAS is now using version 4.0.3 of GNU's compiler.
This required all programs under /ldcg to be
recompiled. On the first night of running, the system was observed to be
considerably slower. Looking at what changed, the slowness could be attributed
to some debugging code that was committed to CVS. It has since been removed.
An issue remains with flushing data from globus
sockets which prevents receiving all commands that were sent in a rapid
succession.
System tests were performed on version 1.8.115 of LDAS.
TCLGlobus
Investigation of a rare core dump (once a month or less) revealed a possible
logic error with the TCL Channel interface for globus
sockets. The library now unregisters the channel from
TCL before calling globus_xio_close( ).
Some work has been done to address the memory leak seen. Further testing is
required to establish how much of the memory leak has been eliminated with this
work.
GRID COMPUTING
Successfully ran Inspiral pipe work flows to
completion on three OSG 0.4.0 sites for the first time: OSG_LIGO_PSU, TACC and
UIOWA-OSG-PROD.
A problem was discovered with FC4 latest kernel (2.6.15-1.1833_FC4smp) which
causes Condor 6.7.17 DAGMan/Condor-G to have problems
processing events. Going
to revert to version 2.6.15-1.1831_FC4smp of the kernel to find a stable
platform.
Attended an ITB telecom related to roll-out of ITB 0.3.6.
Attended a VDS telecom to examine a proposal to alter the
metadata in GridCat used by vds-
get-sites to enable correct worker node path to VDS. Attended
a storage telecom on SRM and OSG storage developments.
Successfully validated the Inspiral pipeline work
flow with a pre- release of OSG 0.3.6 installed on an OSG integration test
host: CMS_BURT_ITB.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Tried
to help isolate problems on LLO's fb1.
- Worked
on coming up with a better SQL query for LSCdataFind.
- Setup
LLO /home and started rsync of /archive/home to
it.
- Started
tracking down files that hadn't made it to CIT via LDR.
- Freed
up a bunch of slots in LLO's L700 tape silo.
- Standard
S5 L0 frame file ingestion.
(Phil Ehrens)
- Various
certificate related duties.
- Support
for LDAS developers.
- Ongoing
development of integrated monitoring/logging/notification toolset.
- Helped
move 13 nodes and did a bit of cabling in the machine room.
(Erik Espinoza)
- Installed
rack mount rails on two racks.
- Worked
with Stuart and Phil to move 78-90 to second rack.
- Submitted
bugzilla (RH) for kernel bug 185481 and 185655.
- Ordered
RMA for CPU's from ASA Computers.
- Replaced
CPU's on node329, no affect.
- Replaced
disk1 on node151, back in operation.
- Configured
temptrax temperature monitoring system. Will put
probes in place soon.
- Updated
kickstart for Ganglia support.
- Filled
out TAR for CondorWeek.
(Stuart Anderson)
- Helped
with analyzing fb1 frame writing problem at LLO.
- Started
Ganglia on the new CIT cluster.
- Submitted
several problem reports/queries to the Condor development team.
- Helped
analyze problem with latest LDRdataFindServer
patch and reverted it due to performance problems.
- Started
staging the S5 L1 RDS frame data into the LDAS-CIT cluster internal disk
storage for faster access.
- Generated
an updated list of S5 files that LDR failed to transfer to CIT.
- Helped
prep the CIT computer room for acceptance of another 77 Opteron nodes.
MIT
(Keith Bayer)
- Coordinated
power setup to new cluster and servers.
- Had
new Gigabit Foundry switch installed.
- Brought
two pcarids from Caltech online.
Livingston
(Igor Yakushin)
- Made
more layouts for the computing equipment in the new location taking into
account the actual constraints of the room under construction;
- Scheduled
StorageTek/SUN engineer to help us with the tape
robot move next Friday;
- Scheduled
tape drive firmware to be upgraded to RQ.35.405 during next Tuesday
maintenance period. StorageTek engineer also
recommended to upgrade tape library code to
3.1.0.
- Received
final quotes for 1 year service contract for the SUN equipment, working on
PO;
- Installed
lscsoft on the nodes on Kipp's
request;
- Fixed
fftw3 rpm on ldas-grid on Kipp's
request;
- fb1
produced no more frames with incorrect checksum after last week daqd crash and restart; Disk2Disk and create RDS
scripts are switched back to use fb1 frames; users are notified that they
can resume using /frames;
- Made
/cluster visible to ldas-jobs on Shourov's request;
- Restored
data on node209 after its disk was replaced.
(Dwayne Giardina)
- Ejected
tapes for storage and imported tapes into L700.
- Ejected
tapes for shipment to CIT and imported tapes into L700.
- LDAS
external network connection was lost temporarily due to power outage for
electrical work in new LDAS room.
Internal and framebuilder connections
remained up.
- Working
with Lisa on the 3511 setup.
- Preparations
for LDAS move to new location.
Hanford
(Greg Mendell)
- Data
corruption in the CDS raw LLO frames from the fb1 framebuilder
were resolved when the daqd restarted. This
caused no gaps in the archived raw data or with RDS generation, since
these used good frames from the LLO backup framebuilder
fb0. All LDAS services are running smoothing at LHO and LLO.
(Ben Johnson)
- Fixing
data gaps due to RLS registration failures at Caltech.
- Turned
on dmt archiving again.
- Working
on tape catalog program again.
- Verified
that cronjobs require a valid /etc/shadow entry
on the grid machines to operate.
- Working
on getting PO for $14k Sun support
contract for LHO.
General Computing (Wallace)
MIT:
(Keith)
- Ordered
faster SCSI drives to upgrade GC fileserver
- Benchmarking
/ testing new opteron workstation
- Troubleshot
desktop
- Continuing
work on new mailserver w/ imap
and ldap
- Ordering
copper gig-eth cards for enoki and lancelot
Livingston:
(Dwayne)
- Finished
with installing base image for Janeen's new PC,
however having issues with Solidworks install
complaining about file missing from disk 3.
- Main
gate appears to be working correctly, at least for now. Found a loose wiring connection, and
replaced a faulty component with one from the side gate. Rich ordered and received replacement
and one spare.
- One
of the Foundry EdgeIron switches in the OSB
failed. East side offices were
without network connection for most of the morning. Shannon
replaced inactive connections on the working switch with those that were
from the east side offices.
- Removed
paper jam in copier, and straightened piece that was causing jams
-Temporary power outage for new LDAS room electrical work caused GC
network outage in part of high bay building. LDAS lost its connection to outside
world, but internal LDAS and connection to framebuilder
remained OK.
- Other
usual user requests and support
Hanford:
(Christine)
- Tried
to test the backup network again.
It has deteriorated since the last time we looked at it. Now I am unable to ping ESnet and vice versa.
Looked like it was a bad connection on the media converter at PNNL,
but when that was fixed and I tried to test again the link dropped out the
moment I switched to the backup circuit.
I've ordered new media converters and PNNL is again trying to clean
up the fibers between our sites.
PNNL and Charter have a planned 2 hour down time of our primary network
sometime on Sat. or Sun., 3/18 or 3/19.
They still have not given me a final schedule. PNNL is working with me to try to get
the backup network working prior to the planned down time.
- Richard
installed a new video/audio server in the Auditorium for the LSC. I'll send out an email to lsc-all with the IP address when I know which sessions
will be broadcast.
- Helped
two users run pine to edit their Inbox on the mail server. Several emails with blank headers have
been going around and Netscape is unable to handle them.
- Setting
up for LSC. The projectors won't
arrive until Friday morning.
Fortunately, there are only two meetings on Friday so I have enough
projectors and laptops on site to cover those meetings. I've installed a NAT router for the
Auditorium wireless and have setup a third wireless AP in the Auditorium
building. I had to set up wireless
and wired again in the Staging building for meetings.
- The
Cisco sales rep came to visit me and promised to send me the names of
Cisco partners in WA, but I haven't heard from him yet. I've sent a follow up email. Cisco said they would renew my support
contract, but I haven't received any notification that it has been
done. I've left phone and email
messages. I think I won't replace
this equipment with Cisco equipment.
CIT:
(Christian)
- Created
a Dual Boot system with Windows 64 and 32 bit for Peter's new system. I
also installed configured Mathlab to work on
both operating systems.
- Installed
and configured Webcam XP for Dennis - Replaced
toner cartridges on HP 5500 printer.
- Called
Dell support to have Phil's motherboard checked and replaced on laptop.
- Replaced
Mike's old CRT monitor with a new LCD monitor - I
replaced Hiro's old CRT monitor with a new LCD
monitor.
- Re-imaged
laptops that were returned to the loaner pool this week.
- Worked
with Mike P. and Dwayne on getting a new image of Solidworks
for installation.
- Other
misc.: Continued onsite software/phone support.
(Veronica)
- LIGO: Investigated a report of a choppy video
stream, played with various player bandwidth settings so see how the (mis)match between the default setting and the actual
available bandwidth affects the video quality. We normally encode the stream for the T1
bandwidth so it may get choppy over a slower connection. Part of the solution would be to provide
several versions for different connections. Installed security patches on the
Windows servers. Updates of the CIT
and MIT webpages. Continued working on the Elba website.
Taped a talk by Sam Waldman and made a set of DVDs for TAPIR, other
video editing work. A
high-resolution image for a publisher.
- LSC: Continued support of the March meeting
website and applications.
Troubleshooting of the registration and the online credit card
payment apps. Updates of the
technical papers website and database.
- CaJAGWR: Video
of the last talk, compressed it for streaming. Website updates.
(Larry)
- Working
on a number of procurement items.
Finally, got the paperwork going for the CISCO maint.
contract put in.
Ordered a number of tools to help in some of the rewiring we will
be working on in the next couple of weeks.
Ordered misc. items such as batteries, disks and cables for other
groups. Most of the items have already been received and delivered. Still working on the SUN matching grant
list. Just waiting for input from one more group. Ordered an update to the streaming video
server software.
- Reworked
some of the cabling in one of the closets. Mainly, in preparation to redo
the whole thing and get it cleaned up.
- Still
troubleshooting the dual core quad cpu
box from Monarch. I've been sidetracked on to a number of other items and
have not been able to devote any large segments of time to it.
- Worked
with the group on the streaming video server issue. We discovered that
there are settings which can cause problems on reception of the video also, slow connections up to the lowend
DSL speeds can have performance issues.
New videos will be setup to operate at different speeds. Also, we
are setting up a new server and updating the s/w.
- Spent
a great deal of time performing disk recovery and repair.
- Resolved
a number of account issues. Setup a new account. Cleaned out a number of
e-mail aliases.
- Worked
the spam filters
Mail Statistics Mar 9-15, 06
|
Mail Statistics
|
March 16, 2006
|
|
Rejected Messages
|
31,652
|
|
Virus Messages
|
2,179
|
|
Accepted Messages
|
31,003
|
|
Total Messages
|
62,655
|
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Systems, Management
Advanced LIGO Review Preparations
From: Phil Lindquist lindquist_p@ligo.caltech.edu
Positions
Summary List – No progress.
LIGO Operations Budget Model (FY 2006 - FY
2008) – No progress.
Projection of Advanced LIGO Operations Costs – No progress.
Project Execution Plan – No
progress.
See also:
AL
Systems web page
AL Systems email
archives
Records of Decision or Agreement (RODA)
See also the RODA
status web page
- RODA
to Eliminate the Photon Actuator from the baseline (M060032-00) is being signed
- A
draft RODA to eliminate OSEM sensors for global control OSEMs in the quad (lower 3 stages) is being reviewed
Requirements/Design
- Held
a systems meeting to discuss relaxed HAM isolation requirements (Peter Fritschel) and optical layout status (Mike Smith,
Dennis Coyne, Luke Williams); synopsis here
Interface Issues
See the "Interfaces" section of the AL Systems web page
Vacuum Compatibility
Residual Gas Assay (RGA)
See also the Vacuum Bake Lab
- Cleaned
magnets and Baking for Helena.
- Cleaning
parts for Ken Mailand' s Quad installation platform/fixture.
- I
have assembled 30 LED boards for Ben Abbott's OSEM failure investigation.
- I
have repaired two OSEMs for the Quad and am
waiting for the other two to arrive from MIT for repair then I will ship
all four back.
High-Irradiance, Contamination-Exposure Cavities
Lee Cardenas, Liyuan Zhang
Seismic Isolation
From: "Joseph A. Giaime"
jgiaime@ligo.phys.lsu.edu
Agenda for the weekly SEI
telecom, Friday, March
10, 2:00 pm Eastern, 1:00 pm Central, 11:00 am Pacific
time
BSC SEI status, w/ new targets : Ken/ Dennis
- Ken has redesigned the
displacement sensor target to make use of the thinner high-purity aluminum
that we have been able to buy. We will have these made, with the
request that they polish the face flat after bolting it to the holder.
- Ken has spoken with Ken at ASI
regarding the intended use of the blade test fixture, and learned of the
purpose of several features shown in ASI's
drawing. The test method should be reproducible, albeit requiring a empirically-derived scaling factor to learn the true
force. We decided to proceed with assembly and spring testing.
- Hardness tests performed on
blades and rods.
- Blades deformed by 0.004"
during hardening.
- Joe Hanson at LLO will set up
to assemble and test the pods. Ken will send the internal cable, and
Jay will send a GS-13 updated circuit board.
BSC work, adaptive
modeling and FIR (Rich M)
- work concentrating on SUS
debugging
ETF platform work
- Thermal testing (Brian)
- Three thermal sensors plus
reference resistor installed in ETF platform's stage 1, and vacuum tests performed.
Changes at the several milli-degree level seen
when 0.06 dSpace units DC offset turned
on. Normal operation at Stanford needs an rms
value of about 0.1 dSpace units.
- Up to 50 mK
change seen on the support table over 10
min test, and about 10 mK at the actuator.
- Follow-up work with hour-long
tests (to probe full time constant), indicates that the 0.06 dSpace units current should cause 35 mK, implying the normal operation power should result
in an actuator temperature change of 0.5 mK.
- tickle testing (Matt)
- Automatic diagnostics
development system (i.e., tickle testing) progress shown here.
- Frame damping (Tarm/ Brian)
- 1 mm thick small
square of dyad epoxied between frame and
buttress beam, photos
here. 60 Hz frame resonance's effect on rX response reduced by factor of 8 or so, as seen here.
- Next up: adjust size of
damping layer to look for an optimum. The layer currently in use
has a k of 5e5 N/m, and if this is implemented (probably by the SUS
group) we would need to find a bellows that is less stiff than that.
- There is also the question of
how and whether the buttress would fit in current table layouts. It
might be difficult.
- It also appears that the
unbolting and rebolting of the lower structure
resulted in a factor of ~4 Q change and a half hertz frequency change.
Attachment bolts are rubbing in their through holes, and they found that
retightening the bolts in situ upped the Q to nearly its old value.
Suspension
From: Janeen Romie
romie_j@ligo.caltech.edu
Working
on information for Carol & Dwight in preparation for the NSF Review in May.
Sent
around a preliminary schedule of discussions for the SUS Workshop at LHO
next week. Participated in the RAL
readiness review yesterday. Participated in the meeting with Brian Lantz about damping options
for the quad structure. Participated
in an interview with a mechanical engineer for a position at Caltech with
From:
"Mark Barton" mbarton@ligo.caltech.edu
This week I made major
revisions and additions to the instruction manual that Calum
and I have been preparing for the quad controls prototype. It will be released
shortly as T060039-00. I also released (<http://www.ligo.caltech.edu/~mbarton/SUSmodels/>)
a lot of modeling stuff that I've been working on:
- A new version of the modeling
toolkit with a fix for a numerical precision issue that's been plaguing
some of the new models.
- A new version of the quad
model that allows for lateral compliance of the blades. This is the first
version of the model to give really good agreement for all modes of the
controls prototype with all as-built parameters (even the finicky
fundamental pitch mode), and is now the preferred version for most
purposes.
- A
new version of the quad model with both pitch and lateral blade
compliance. This turns out to be of academic interest only, because the blade
torsion effect is negligible (about a 2% perturbation of one higher pitch
mode).
From: Ken Mailand kmailand@ligo.caltech.edu
Bob is cleaning the plate
fixture parts, CES has completed additions to the large plates, they are going
to plating tomorrow, and final assembly may be complete by the end of next
week. We have purchased a smaller
assembled lift table, for the LASTI work in early April. Minor modifications will be made to the table,
a shipping crate for the fixture, and table, will be ready by this Friday.
From: Ben
Abbott <abbott_b@ligo.caltech.edu>
LED failures:
I am waiting for the LEDs that failed at LASTI on Thursday to arrive so that
they can be sent back to Honeywell with the others. Once they are
received at Honeywell, they will all be autopsied, and if the cause of failure
can be identified I will try to make the LED boards that I have fail in the
same way. This should determine if the new LEDs
are more susceptible than the old LEDs to the
perceived failure mode. It will also, hopefully, indicate what should be
changed to stop the failures in the first place.
Misc:
I have finished up the
layout of a back panel for the PCIX effort. It should be back from Front
Panel express tomorrow.
Core Optics
From: Bill Kells kells@ligo.caltech.edu
Although all the nails are not quite in the ITM07 "postmortem"
coffin, A few outstanding conclusions persist (and are being rapidly
sharpened).
1. Our (actually L. Zhang performing all the diligent instrumentation) most refined
"absorption scans" of the contaminated ITM07 surface give a mean
sampled area (~ 1 cm2) absorption of 12 ppm. (Note that we have come to realize that the
"absorption scan" method we employ is not physically equivalent to
the mean surface heating which a LIGO cavity beam would induce. The heating
beam size and vacuum /or/ air environment can make crucial differences
depending on the nature of the contaminant).
2. A different ~ 1 cm2 sampled area of the same mirror, but
simply cleaned, and then scanned in exactly the same manner gives a mean
absorption of only .6-.7 ppm. In this respect ( to cleaning) ITM07 responded to cleaning similarly to the
in situ cleaned H1 ITMy.
3. Our calibration piece in this is a surface cleaned, 1" dia. test optic which is well characterized (at Stanford,
and in our OTF contamination cavity setup) to have a uniform ~19 ppm absorption characteristic of the HR coating itself.
When scanned (identical method as in 1. and 2. above) this calibration piece
shows a clean pixel histogram peak at 19 ppm.
4. D. Ottaway's latest H1 ITM lensing
analysis (LIGO-T050074-01-R) boils his conclusions for ITMx
down to: all ifo
observations consistent with 1. 13ppm pure HR surface
absorption; or 2. 42 ppm/cm
pure substrate bulk absorption. If I take the reasonable value of
~4ppm/cm for the actual bulk contribution and the rest being HR, then
this HR attributable value is ~12ppm (amazingly equal to that found in 1. above !).
5. Although the mean of all pixel absorptions in the scan 1. (above) is 12ppm, the distribution is highly irregular. ~90%
of the pixels in this scan contribute to a histogram peak at ~ 1 ppm (per pixel absorption). However the remaining 10% form
a long tail (out to 100s ppm/pixel) above 10 ppm/pixel which dominates the mean absorption. That is, the
HR surface is extremely irregular in absorption (strikingly so in comparison to
2. and 3. above), not seemingly characteristic of a uniform [contaminant] film.
Of course, like all examined optical surfaces, ITM07 (which has been sitting
around in lab air for months) has a lot of surface "dust" particles
on it. Note that, if totally absorbing, only ~ 10 (10micron)2 per cm2 could cause the affliction
we found in H1. We easily see (with a microscope) this [gemetrical]
level of "dust" ! However due to the details
of our absorption
scan technique (step size an irregular ~ 100microns. Probe heating beam dia. > 100microns, and other factors) it has not yet
been possible to absolutely conclude that the scan mean absorption of 12 ppm is entirely due to distinct surface "dust".
At this point is appears that there very well may be an anomalous [quasi]
uniform component (say ~ 1-2 ppm) as well.
From: Helena Armandula ahelena@ligo.caltech.edu
Adv. LIGO Coatings
Procured
preliminary quotes / designs for the storage cases and the transit cases of
Adv. LIGO mirrors. We'll review the designs to see that they
meet Adv. LIGO requirements within a few weeks.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
I went over the risk
assessment materials again. An updated basis of estimate was forwarded to
Dwight.
Thanks to Christian, Mike
and Larry for getting the DSP computer up and going. I managed to talk to
someone at Xilinx that had a sympathetic ear about my
software adventures in getting an evaluation copy of their system generator
software. Registration for getting a copy involved being stuck in an
infinite loop on their webpage. The software promised to have a nice interface
to Matlab. That sorted all that remained was to
install the software, or so I thought. After many installations of Matlab, caused by some rather oddball characteristics of Xilinx's software, it would appear that the software does
run. I think the problem is that most of their software development takes
place on Linux platforms even though a large fraction of their users are
Windows based, as the error messages encountered had a distinctly Unix flavour about them.
Auxiliary Optics
From: Michael Smith <smith@ligo.caltech.edu>
VERTEX LAYOUT
A preliminary Zemax layout of the 2K IFO was added to the vertex layout
file in PDM Works vault.
Luke Williams from UFL has
loaded the proposed stable recycling cavity IO beam train into the PDM Works
vault. He is developing a conceptual layout of optical lever beams for
all the suspended optics in the IO beam train.
SLC
Hiro is still working on obtaining
transfer functions for scattered light noise in the ADLIGO RSE configuration
with the optical spring effect.
AOS COST
The AOS cost figures have
been updated and are being sent to Dwight Carter. I am working on the schedule
and the risk assessment.
Controls, Data systems
No report this week.
Other Laboratory R&D
No report this week.
For additional information about this report, contact S. Whitcomb or P. Lindquist