Weekly Report for
Week Ending March 9, 2006
The LIGO Executive
Committee Agenda for Monday,
March 13, 2006 will be:
(Meeting time: 10:30 am Pacific Time)
1. Announcements
2. Comments
on Weekly Report
3. LSC
Issues (Saulson)
4. LIGO
Lab Operations
- Administration
(Lindquist)
- Sites
(Raab, Zucker, Shoemaker)
- Commissioning
(Fritschel), Detector (Coyne)
- Campus
Research Facilities
- 40
Meter (Weinstein)
- TNI
( Libbrecht)
- LASTI (Shoemaker)
- Data
Analysis and Computing (Lazzarini)
5. R&D
and Advanced LIGO (Shoemaker)
6. CHANGE CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION AS
NEEDED
- A
change request CR-060003
has been posted for consideration during the Executive Committee meeting
scheduled Monday, March 13, 2006. CR-060003 is for the award and
implementation of a contract to design the exterior pendulum wave exhibit
for the LIGO Livingston Science Education Center (SEC).
Special Items:
- Preparations for
Advanced LIGO Review (May 31 – June 2)
Special Announcements:
Weekly Report Highlights
Plans are just about complete for the LSC meeting at Hanford 19-22 March.
The LSC Council will discuss, among other things, the proposed LSC Bylaws,
and the present draft of the new MOU with Virgo. Copies of both were placed in the DCC, and
pointers were distributed to the LSC membership for study in advance of the
meeting..
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
SITE TELECONFERENCE (Lindquist)
- A
site teleconference was held Thursday, March 9, 2006. Most of the items discussed are
addressed individually below.
- The
list of assigned actions updated through December 01, 2005 will be found Here. There are no open actions.
PROPERTY MANAGEMENT (Luna)
>
- Performed
a successful equipment inventory at Hanford
this week—99 percent.
- Disposed
of excess property at LHO (14 monitors, 3 printers, 1 computer, 1 TV and
25 keyboards..
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
Synergy Software Design
- Continued
to construct document profiles and identifying those fields required.
- Continued
to define all necessary pull-down menu tables for the myriad of metadata
fields.
- Held
numerous discussions with key staff members for input on data needing to
be captured.
- Met
twice with Ian Booth (FileHold) to stay on course and continue learning
about using Synergy.
- Continued
working with current and archived document records to prepare for the
actual conversion over to Synergy.
- Have
analyzed in our current system Media code and Group code to determine the
feasibility of retaining same structure in new system.
- Began
preparing a short presentation on progress of the document system for the
upcoming LSC meeting.
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- Completed
processing and filing of 2005 Travel Expense Report files. There were a total of 216 files.
- Scanning--Progress
continues on scanning of contract closeout files.
- Activity:
|
Week Ending
03/09/2006
|
In
|
Out
|
|
Packages
|
27
|
6
|
|
Faxes
|
18
|
21
|
FINANCIAL SYSTEMS (Cronin, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Completed
the no-cost extensions on three subcontracts (Arland Tool, Limerick, and Nor-Cal Products), and submitted the
changes to the vendors.
- Completed
the procurement package for the change order to University of Florida
to add operations and R & D funds for 2006. Submitted the package for
routing.
- Completed
distributing the change order to Triad, which was returned from routing.
- Working
on the change request to Galli and Morelli.
- Sent
out requests to obtain current A-133 certifications for this year.
- Responded
to the audit follow up request on the A-133's, and obtained the current
A133 for the Exploratorium which did not have any findings.
>From: Florence Kaufman <fkaufman>
- Prepared
a PTA Set-Up form and an request for budget realignment in Oracle to
accompany the Equipment Fabrication Request for the Seismic Attenuation
System (SAS).
- Prepared
a PTA Set-Up from and an authorization for budget realignment in Oracle
for a new non fabrication account for the DAQ system.
- Prepared
two Cost Transfers for minor charges that had been posted to incorrect accounts.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- The
review package for the HAM SAS contract with Galli & Morelli is being
prepared for submittal to the NSF.
The package will consist of a cover letter detailing the history of
the procurement, the contract, and the Galli & Morelli proposals. Upon completion of the package, it will
be reviewed by General Counsel (David Flores) before being sent to the
NSF. The contract value is
$332,852, and is expected to be sent to the NSF late next week.
- Construction
of the LLO SEC is on schedule, with the back of the building sided. High winds have prevented the
installation of the larger siding panels.
- Selection
has been made for a contractor to design the kinetic facade for the LLO
SEC. The change request to cover
this effort will be voted on at this Monday's Executive Committee
meeting. It is expected that the
contract to perform this design, valued at $47,000, will be issued late next
week.
- Construction
of the LDAS structure inside the Staging Building
at LLO is on schedule, and the equipment will be moved in on March 20.
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
- Worked
on the usual new trips, expense reports, reconciling, calendar
reservations, and itinerary entries.
>
>Dorothy Lloyd
- No
report.
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
PROPOSALS and REPORTS (Lindquist)
We have prepared a FastLane request for a Supplement to the LIGO Visitors
Program (NSF Award PHY-0245117). We are requesting an additional $30K for
stipends and travel expenses for four Participant students to spend the summer
working in Italy
on the VIRGO Program. This has been submitted.
For the status of efforts to prepare for the Advanced LIGO Review see Advanced LIGO below.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
- A
change request CR-060003
has been posted for consideration during the Executive Committee meeting scheduled
Monday, March 13, 2006. CR-060003 is for the award and
implementation of a contract to design the exterior pendulum wave exhibit
for the LIGO Livingston Science Education Center (SEC). Budget will
be moved from WBS 3.1 to WBS 3.10 to cover most of the cost.
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- No special activities to report.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
Nothing significant to report this time.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of Commissioning Activities at LIGO Hanford Observatory (compiled by M. Landry)
H1 banged in a pretty decent week, with a duty cycle of 77% and typical
ranges of 13.5Mpc, despite a period of high winds
Wednesday evening (which eliminated LHO locking). The H2 duty cycle was
71%, initially near 7Mpc, but more recently with highly
unstable ranges. Dust on ISCT10 was hoovered but the instability
remained; the machine has only recently stabilized (Fri a.m.) with the
suggestion (but no proof) of alignment as responsible.
Current lore on the post-commissiong epoch is that our H1 mean-time-to-lock
is greater than previous, but once we lock, we stay locked longer, and through
daytimes at higher ranges. We will see if the numbers support this
impression, but commissioning efforts of WFS bandwidth increases and ASPD
lockloss-saves appear to have worked admirably.
Some highlights from the week of science running (please see the full elog
for details and more entries):
- investigations
with the HVAC system and temperature control continue.
Turbulent air flow in the volume between fans and ducting may require
design of air foils, currently under assessment
- scimons
compared
LHO interferometer performance before and after the commissioning break
- linefinding
elogs identify ringers in both IFOs that have either been mitigated, or
are good candidates for mitigation... many of these lines, while clearly
instrumental, have not been eliminated from pulsar analyses as the
transfer function into the error signal is poorly understood
- forensics
on H1's downtime: the common mode unity gain frequency was restored to
20kHz, and the crossover frequency to 200Hz, in order for H1 to relock
consistently and with science-mode performance
- SoHolds
(small optics hold servos) that fix the optic relative to its cage were
initiated, with the expectation they will be installed next week
- a
study of traffic on the 240 highway has some suprising
results, in that it is difficult to correlate the arrival of a truck
at EY (minimum impact parameter) with 3-10Hz blrms noise in
seismometers. It may be that problem coupling is not at closest
approach, but at some other point (bumps or local strata)
- a
study of the effect of useism
on binary inspiral range was posted
- the
standard range and duty cycle Mathematica notebook was updated
- DMT
fixes
were made to several key monitors for S5
- a
filter and filter archiving loophole
was diagnosed, with implications for all IFOs, calibration and
configuation control
- a 4k ETMX-specific noise
budget was posted
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
L1 Interferometer in S5 (Franzen)
We had a busy week with several hardware problems resulting in only 32
percent duty cycle and a decrease in inspiral range:
- The
ETMY bias module failed and was replaced.
- The
ITMY SUS started to exhibit a large yaw offset after it tripped during
Thursday's construction. This has happened before and is probably due to
charge up. The problem was solved by adding an offset to HEPI.
- The
temperature changed at the Y-end station due to a chiller problem. This
changed the ITMY's butterfly mode which went outside its stop band in
drive and thus started to ring up. The situation was improved by extending
the stop band region.
- An
increase was observed in MICH
and PRC coupling to DARM at 105 Hz. The MICH_DAMP and PRC_DAMP gains were
tuned in order to fix the problem.
During Tuesday's maintenance the following was done:
- The
lower PSL periscope PZT mirror was exchanged since it has been broken for
some time.
- There
was a state vector code drop.
- The
DMT code was upgraded.
- The
LDAS was upgraded.
Unfortunately, we are experiencing periods with numerous glitches and
sometimes large drops in inspiral range:
- Excess
and intermittent 1/f DARM noise in the 30-100 Hz region. This problem
spontaneously disappears and the cause is not yet understood. It was
observed briefly during Monday day shift and for an extended time during
Wednesday morning.
- The
60 Hz harmonics became at least a magnitude order stronger after Tuesday's
activities.
AdL Suspensions and Isolation (Romie)
Working on reports for Carol in preparation for the NSF Review.
General Computing (Giardina)
- Received
new PC for Janeen. Unattended would
not work on it, due to being SATA.
Even adding drivers from floppy fails. Will build from scratch.
- More
site gate issues, discovered small bug in kantec software, contacting tech
support about it.
- Other
usual user requests and support.
LDAS Support (Giardina)
- Ejected
tapes for shipment to CIT and imported tapes into L700.
- LDAS
upgrade (no need for details here).
- Fixed
some email issues that were broken due to upgrade and my errors.
- Working
on repairing centralized syslog setup, broken after upgrade.
Computing and Network Security (Roddy)
Much of the last few days was spent analyzing a disk image from a hacked box
at Caltech. RuthAnne from CIT and I have
been comparing notes and there are a few curious items about the incident which
may be related to another recent incident on campus. It appears the hacker came in through a weak
root password. A more detailed report
will be circulated after all of the details are learned. This latest incident reinforces the need for
well managed passwords, *especially* root/administrator passwords.
- Implemented
some more aggressive logging and ssh monitoring at the firewall.
- Installed
some Netflow software. Still a few
quirks to work out.
- Not
100 percent pleased with both of the implementations I tried.
- More
backups, etc.
- Updated
the IDS rules.
- Since
Jan 1 of this year, there have been 269,111 ssh brute force and/or
dictionary attack attempts at LLO alone.
This reinforces the importance of strong password management. It only takes one correct guess to cause
headaches, both to the admins and the affected users.
Data analysis (Yakushin)
Storage/Condor/LDAS admin:
The cluster was down for 2 days for upgrade. The following work was done:
- Solaris
10 update 1 was installed on dataserver and gateway;
- SAM_QFS
patch was applied;
- New
file system was built on 3510 to store metadevice for the user home file
system that will be built on the two new 3511s;
- Firmware
was upgraded on 3510;
- Condor
was upgraded to version 6.7.16;
- Syskonnect
GigE card in gateway was replaced by Sun GigE to prevent potential
problems that were observed at CIT after they upgraded to Solaris 10
update 1;
- samfsck
was run on /frames and /dmt;
- node2
was made part of the cluster;
- several
nodes had bad disks replaced and data restored; a memory was replaced in
node30.
- /lal
was unmounted from all the computers but beowulf;
- /frames
and /archive/cluster were mounted on the nodes from dataserver-cluster
(previosly they were mounted from dataserver);
The upgrade is a joint work of Dan, Stuart, Dwayne, Lisa and Igor.
After LDAS upgrade we found that for a while fb1 generated corrupted L0 and
trend frames. However, we have no
reasons to believe at this point that it was a result of an LDAS upgrade.
Data analysis:
- Continue
testing coherent version of waveburst on S4 data;
- Participating
in the APS presentations review telecons;
- Working
on APS slides for my S5 burst talk.
E2E (Yoshida)
Obtained some results on ground and HAM table-top yaw analysis with e2e. To
make the analyses realistic, the following procedure was taken. First created
calibrated platform U, V (translational displacement in X and Y) motions and
Yaw motion using horizontal seismic position sensor DAQ signals (e.g.,
L1:SEI-MC1_POS_H1_INMON, etc). The
resultant platformþfs U, V and Yaw time series were fed into the e2e HAM stack
box input ports to compute small optics (SOS) OSEM Yaw signal. This OSEM signal
was compared with the corresponding DAQ signal recorded at the same time as the
seismic position sensor DAQ signals.
The analyses were made based on two different HAM table Yaw models. In the
first model (called the model A), only the platformþfs Yaw motion was used as
input to the HAM stack box, and the resultant HAM table top Yaw motion was fed
into the SOS box placed on top of HAM stack box. In other words, the stackþfs
Yaw-to-Yaw coupling only was considered.
In the second model (model B), the platformþfs U, V, and Yaw were all fed
into the HAM stack U, V, and Yaw input ports, respectively, and the table top
U, V, and Yaw motions were computed based on the stackþfs U-to-U, V-to-V and
Yaw-to-Yaw couplings. Then, additional table top Yaw was computed as
dV/dx-dU/dy (where U and V are the table top translational motions computed by
the stack box and x and y are the coordinate on the table) and this table top
Yaw was added to the table top yaw based on the Yaw-to-Yaw coupling (the same
as model A) to compute the total table Yaw, which was fed into the SOS box in
turn.
The additional table top Yaw in model B was computed to consider the
following effect. At the bottom of different stacks of the same table (say, for
example, the north stack and south stack of HAM 1) the platform experiences
east-west translational displacement with a certain phase delay. (This phase
delay causes the platformþfs Yaw motion mentioned above.) Then if the north
stack and south stack transfers the east-west displacement at a different rate
(i.e., the transferring speed of the displacement is different for the north
and south stacks), the phase delay will be enhanced at the table top; in other
words, the phase delay associated with the difference in the transferring speed
between the south and north is added to the initial phase delay existing at the
bottom of the stacks.
Results of the computation show that the model B is closer to the OSEM Yaw
DAQ signals in the overall shape of the power spectrum. The DAQ OSEM Yaw
spectrum has two broad peaks around 1.5 Hz and 2.8 Hz, which can be identified
as the stackþfs translational-translation first and second resonances,
respectively. The computed spectrum
based on model A shows only one peak around 1.5 Hz, while the computed spectrum
based on model B shows two peaks around 1.5 Hz and 2.5 Hz. This indicates the
above-mentioned effect of phase delay introduced by asymmetric stack response
is a possible cause for the HAM table Yaw..
Initial LIGO Detector Science & Engineering (Coyne)
CDS
see also the CDS weekly meeting minutes in the commissioning archives
DMT
No report
Optical Scattering
Bill Kells
Since being up at LHO 10
days back, I have thoroughly gone over the measurements of H1 TM scatter. The
results of this have been discussed several times: Using the ETM scatter as a
[relative] calibration (presuming it is not much different from what it had
been as far back as 2003 when measurements were last performed) I found that
both ITMs have ~ 20% less scatter (at a single fixed observation point) than
they did in '03. I do not think this is a significant change!
The absolute level of
scatter compared to '03 is more problematic. Since then the ifo input beam
power (H1:IOO-MC_PWR_IN) has increased 6.6 times and the arms optical gain
(LSC-LA_PTRX/Y) has increased about 25%. Normalizing against these leaves a
decrease in ETM scatter of ~1.8. If the
arm optical gain is assumed unchanged (since '03) then this apparent decrease
is ~1.5. Of course we cannot be assured
that the ifo input power monitor still has the same calibration, nor that the
efficiency thru the MC into the ifo is the same. This suggests though that the
relative power input into the ifo is not what we think it is by a considerable
factor.
A different issue:
Recently A. Melissinos and his student S. Giampanis made some measurements of
AS port demos signals at the arm FSR. They find evidence for a broad peak which
appears to be ifo input power realted (i.e. it was not there during previous
lower power runs). They claim it is evidence for a parametric instability associated
with a TM acoustic mode ~600 Hz higher in frequency. Something interesting is
going on here! I doubt that it is a PI, but have been looking into it and
discussing with Adrian.
40-Meter Interferometer (Weinstein)
IFO Commissioning
- Dan and Monica continue
to develop the noise budget measurements and code. They tried to measure
the contribution from shot noise, but find that they are limited by
electronics noise. Rana will fix the PD interface boards to reduce this.
They are now measuring the couplings of other loops and oplevs to DARM.
IFO Modeling
- The
magnitude and phase of the optical transfer functions taken back in
October by Osamu while varying the CARM offset are in beautiful agreement
with the B&C predictions, for three different offsets and arm powers.
The problem with understanding the phase turned out to be a bug in Alan's
interpolation of the data. Rob gets good agreement with Optickle. New
draft of the 40m optical response function paper has been prepared.
- Monica
continues to debug the control loops in her e2e simulation. She's taking
transfer functions, tuning demod phases, etc. She measured the MICH OLTF,
and Hiro compared it with a simulation from Twiddle; they appear to agree
well.
DC Detection Development
- Ben
continues work on the DCPD satellite box. He talked to Rob and got the
specs for the filters and the design is mostly finalized. Some questions
remain on the placement of one of the filters, either in the vacuum
nipple, or in the satellite box. It should be resolved shortly.
- Ben
has procured some of the electronics that are needed for the DC readout
scheme, including a PMC servo board containing the PZT driver we will use
to lock the output mode cleaner. The QPDs that were hard to get may be
replaced with an OpLev chain, instead. Ben will talk with Todd again.
- The
beamsplitter for the DCPD detector was coated incorrectly. Steve has
received a correctly-coated replacement.
Electronics, Controls, Computers
- Osamu
noted that the DARM signal from the AP 166 demod board has a lot of
electronic noise, presumably from the mixer. He and Rana will look at
different mixers, or a better RF amplifier upstream.
- Ben
did a survey of DC signals from RFPDs connected to the LSC Interface Board
at 1X2-2-12. He traced all of the connections, and found out where they
go, and will enter the list into the ilog.
- New
passwords have been implemented for the controls and root accounts on all
the 40m controls computers (which are behind a gateway that requires yet
different passwords).
Lab Infrastructure
- The
carpentry work in the 40m entrance alcove is done. Bob set up a drill
press there, and will post safety signs.
- Steve
replaced a Turbopump TP2 foreline pressure rose to 200mT after 10,000hrs
of running. Steve replaced the forepump with a rebuilt unit. He made a
mistake that caused the main vacuum pressure to jump to 1 mTorr, but he
quickly recovered from it. He also rerouted a vacuum exhaust line.
- Steve
is assembling the safety beam tubes for the MC reflected beamline and the
PSL high-power beamline, in the PSL enclosure.
- Dan took shifts at LLO and went to Mardi Gras.
Thermal Noise Interferometer (Black)
No report.
LASTI (Ottaway)
From: Thomas Corbitt tcorbitt@MIT.EDU
We measured an optical spring with the one gram suspended mirror to a
frequency as high as 530 Hz. We measured transfer functions of the total loop
gain and confirmed that it agrees with our model. This was significant since
this is the first time we've seen an optical spring of similar (or greater)
strength to our control loop. We also measured the noise reduction effects of
the optical spring (showed that the length noise in the cavity is reduced due
to the optical rigidity).
From: Richard Mittleman richard@ligo.mit.edu
Quadruple Pendulum
Brett and Brian (O'Reilly) have been working on the quadruple pendulum. This week they changed out two non-functioning
OSEMs and in the process discovered one of the causes for the OSEM failures.
There are some small wires in the OSEM bodies which appear to have become
fatigued and broken. Brett has taken
some preliminary system ID data on the local control OSEMs. There are some
resonances around 45-50Hz which will need to be investigated, the speculation
is that these are in the table cloth (OSEM support frame).
Triple Pendulum Cavity
Laurent has been struggling with OSEM problems also. This is a different failure
mode which is associated with a single channel and is intermittent with 3
failures over a month. We have not yet identified the cause of the problem. Jay
is sending us some new electronics with better protection for the diodes; we
are also going to change out the cabling.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Yamamoto)
Analysis of mirror YAW motion (Sany Yoshida)
Sany Yoshida gave a talk at this week's e2e meeting. His view graphs and the
summary of the result is available at http://www.ligo.caltech.edu/~e2e/ME2ET/060309/minute.html
This study uses the LIGO I data to find out the major source of the mirror
yaw motion, 1) ground rotation or 2) stack imperfection. His analysis seems to indicate the the major
yaw mode of the table top comes from the stack imperfection. This knowledge is valuable to study the
angular instability of the advanced LIGO IFO.
40m modeling (Monica Varvella, Hiro Yamamoto, Osamu Miyakawa)
Using e2e setup, Monica calculated the MICH open loop transfer function. The shape
showed two peaks corresponding to the optical spring at 40Hz and the RSE
optical resonance at 4kHz. Hiro used
twiddle to compare the MICH mode and DARM mode
signal generation process, and showed that the distribution of the DARM to dark
port xfer function and that of the MICH
to dark port Xfer function are of the same shape and the ratio of the magnitude
can be explained by the arm finess and the ITM transmittance. Osamu said that, experimentally, MICH loop design was done and MICH control functions well without taking
the optical spring effect into account. One possibility pointed out was that
DARM loop could suppress the optical spring effect. Monica will calculate a new
open loop transfer function of the MICH degree
of freedom with the DARM loop closed, and this will indicate how much the MICH loop is affected by
the DARM. Monica has simulated the SRC
open loop transfer function. She is still debugging the control system for CARM
and PRC.
Static Interferometer Simulation code development (Hiro Yamamoto, Melody
Araya)
Hiro discusses with Yi, Osamu and others to digest how various effects,
including the mode coupling and optical spring effect, should be included or
can be effectively excluded in the simulation, while still offering useful
results. Other than that, just coding,coding,coding....
Scattering noise calculation (Hiro Yamamoto)
Twiddle and e2e are used to calculate the signal propagation from various
anomalous injection points, like AR side of ITM. This is to assist Mike Smith to calculate the
requirement of scattering noise source back into IFO.
modeler code development ( Bruce Sears )
Bruce has started improving a code of model to load the definition file. The
original code was written long time ago, and a good speed improvements of
loading is expected by improving the code with the knowledge of the latest box
file structure.
FC4 library issue (Hiro, Stuart)
The cause of the slowness of the simulation code on saiph, a new dual core
quad CPU machine was traced to library loading/linking. Unlike our server homam, on saiph,
instructions to do +, -, * and / are done by library routine calls, not by
direct machine instructions. FC4 is installed on saiph, while SUSE is installed
on homam.
Data Analysis Activities (Lazzarini)
Brown:
- Working
on getting S5 BNS result.
- Attended
PCGM at UCSB.
- Working
on S4 ringdown search with Lisa.
- Restarted
online BNS search at LLO after maintenance
- Provided
support to Stuart on various condor/database issues.
Dupuis:
- worked
on monthly TDS analysis using February data
- worked
on constructing spectrograms of H1 and H2 using recent data
Chatterji:
- Gave
talk describing burst search methods at Pacific Coast Gravity Meeting.
- Upgraded
online Q Pipeline analysis to latest version of the online analysis system
(Onasys).
- Post-processing
triggers from the S5 online Q Pipeline analysis in preparation for the LSC
and APS meetings.
- Editing
paper describing coherent network consistency test
Mandic:
I have been working on the S4 all-sky stochastic paper, which is now nearing
its final form. The paper is now significantly longer, discussing the
individual H1L1 and H2L1 analyses in more detail, and includes a more detailed
description of the signal injections. I have also completed several checks
suggested by the review committee, regarding hardware injections, calibrations,
compiled Matlab, IFFT of the CC integrand etc.
Sutton:
I've devoted most of the past week to the coherent analysis project here at
CIT. (This is the effort to develop a
coherent network analysis algorithm which determines if a coincident event is a
GWB or a noise glitch.) I implemented a
method for combining sky maps from multiple overlapping data segments into a
single sky map based on the total energy in each sky pixel. This makes the algorithm robust against the
case where a signal overlaps a segment boundary. The combined map can be used for thresholding
and structure studies.
I've also done a lot of editing to the analysis and results section of the
paper. Finally, I've studied the
behaviour of the poorest- performing simulations to try to understand the
conditions under which the coherent consistency test breaks down. That's still a work in progess.
Weinstein:
- All
inspiral review, all the time.
- Helping
Lisa with her ringdown talk for PCGM and writeup for GWDAW.
Yakushin:
- Continue
testing coherent version of waveburst on S4 data;
- Participating
in the APS presentations review telecons;
- Working
on APS slides for my S5 burst talk.
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS
- Version
4.1.0 of GCC was tested on a tandem system. The running of the unit tests
showed that the compiler has issues that prevent it from being used for
LDAS.
- Started
testing with fftw 3.1. The unit tests have passed and it is onto full
system testing on ldas-dev.
- Utilized
the ability to retrieve the subjectName from globus sockets in managerAPI
log entries.
- Testing
was done using ldas version 1.8.100. Several of the system tests were
modified to use tclglobus. The updated tests include procReadWrite,
wrapperState, and db matrix.
TCLGlobus
- Currently
trying to debug a TCL file event issue where data exists on a globus
socket, but TCL never alerts the application of its existence.
- Added
a new fconfigure option for Tcl channel implementation to extract X.509
peer subject name.
OSG GRID COMPUTING
- The
OSG Executive Team contacted LIGO to express thanks for the report
generated last week that summarized LIGO's experiences to date while
running on the OSG production grid. The report will be used as a template
to gather reports from other VOs with the goal of assisting the facitilies
management team is reviewing production issues.
- Successfully
ran Inspiral pipe work flows to completion on three OSG 0.4.0 sites for
the first time: Purdue-ITaP, UFlorida-IHEPA, and UFlorida-PG.
- Worked
with TACC team to understand incomplete Inspiral pipe work flows under the
LSF job manager.
- All
nodes have been yum updated.
- Attended
an ITB telecom related to issues for ITB 0.3.6
- Attended
a VDS telecom with the VDS team on eliminating fork jobs in work flows,
dynamic removal of data after analysis and mutiple site work flows.
- Held
teleconference with the ISI VDS development team to discuss functionality
that would be very beneficial to the running of workflows for LIGO's
binary inspiral jobs on the OSG sites where data movement and storage of
of a greater importance than on the LDG.
- At
the request of Ruth Pordes, reviewed the "Science Automation
Institute" proposal to be submitted to the DOE for the purpose of
providing feedback to the OSG Executive Board in responce to a request
from SAI for a letter of support.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Weekly
receiving/ingesting of tapes from the sites.
- 3510-10
has been running for a week now without odd failures. It's important to make sure the SES
firmware is all at the same REV or you get spurious amber lights, but the
root problem was probably a bad controller & a bad power supply.
- Wrote
a benchmark script for Sean Cochrane (Sun) to use in testing SAM-QFS
metadata performance.
- Dealt
with CIT 3510-3 hanging (again) and replaced controller.
- Installed
fibre channel switch software at CIT/LHO/LLO.
- Helped
plan and execute LLO upgrade. Among
a lot of tasks, shrank /export to
make 2 drives available for a /home filesystem's metadata and configured
SAM-QFS after gateway and dataserver were upgraded to Solaris 10 Upgrade 1.
(Phil Ehrens)
- Installed
working version of custom log analysis and reporting tool on
ldas-kickstart. Ongoing debugging and adding of new features.
- Numerous
grid certificate related tasks. Many new users and a large number of
expiring host certs this week!
- Installed
Solaris 10 update 1 on ldas-suntest4.
(Stuart Anderson)
- Helped
support LLO Solaris/SAM-QFS upgrade.
- Worked
on Condor scaling problems as we reached 10-20K thousand jobs.
- Worked
on 3510 controller problem at CIT.
- Obtained
estimated ship schedule for the additional 77 Opteron nodes at Caltech (in
~2 weeks).
- Working
to help identify corrupt frame problem on fb1 at LLO. Currently this looks like it may be a
due to a memory leak in the framebuilder processes which eventually ran
out of memory.
(Erik Espinoza)
- Took
a look at the Foundry config @ Hanford cluster, possible update may be
necessary for kickstart.
- Installed
updated IOS into CIT Cisco 6509, awaiting reboot.
- Moved
nodes 100, 125 & 167 to 327, 328 & 329 respectively.
- Moved
CPU's in old node125 (currently 328) to old 167 (currently 329),
determined cpu's were bad.
- Returned
node327 & 328 back into service.
- Put
node297 & node400 into ctcs testing, node400 is crashing.
- Down
nodes: node297 (ctcs testing), node329 (awaiting cpus), and node400
(passed memtest, crashes in ctcs).
MIT
(Keith Bayer)
- Installed
new foundry switch with copper GEthernet Caltech will send LC fiber patch
cords
- Brought
2 pcraids on-line and will configure the other 2 today/ tomorrow.
- LDAS
at MIT is down until until we bring up the machines.
- Condor
is still up running old version with ~30 of the original cluster until I
can bring the new nodes on-line.
Livingston
(Igor Yakushin)
- The
cluster was down for 2 days for upgrade. The following work was done:
- Solaris
10 update 1 was installed on dataserver and gateway;
- SAM_QFS
patch was applied;
- New
file system was built on 3510 to store metadevice for the user home file
system that will be built on the two new 3511s;
- Firmware
was upgraded on 3510;
- Condor
was upgraded to version 6.7.16;
- Syskonnect
GigE card in gateway was replaced by Sun GigE to prevent potential
problems that were observed at CIT after they upgraded to Solaris 10
update 1;
- samfsck
was run on /frames and /dmt;
- node2
was made part of the cluster;
- several
nodes had bad disks replaced and data restored; a memory was replaced in
node30.
- /lal
was unmounted from all the computers but beowulf;
- /frames
and /archive/cluster were mounted on the nodes from dataserver-cluster
(previously they were mounted from dataserver);
- The
upgrade is a joint work of Dan, Stuart, Dwayne, Lisa and Igor.
- After
LDAS upgrade we found that for a while fb1 generated corrupted L0 and
trend frames. However, we have no reasons to believe at this point that it
was a result of an LDAS upgrade.
(Dwayne Giardina)
- Ejected
tapes for shipment to CIT and imported tapes into L700.
- LDAS
upgrade (no need for details here).
- Fixed
some email issues that were broken due to upgrade and my errors.
- Working
on repairing centralized syslog setup, broken after upgrade.
Hanford
(Greg Mendell)
- RDS
generation is running again at LLO, after Tuesday's filesystem update. We
are currently working to make sure no gaps were left in the raw or RDS
since the update. The leak in the refrigeration pipe to the 22 ton air
conditioner in the LDAS room at Hanford
has been fixed.
General Computing (Wallace)
MIT
(Keith)
- Received
x86 workstation and am running memtest on it
- Installed
new firewall / router for CDS network
- Still
investigating IMAP for our gc mailserver
- Working
on automounting (Sun, Linux) to multiple home directories
Livingston
(Dwayne)
- Received
new PC for Janeen. Unattended
install would not work, due to the unit being SATA. Even adding drivers from floppy
fails. Will build from scratch.
- More
site gate issues, discovered small bug in kantec software, contacting tech
support about it.
- Other
usual user requests and support
(Shannon)
- Much
of the last few days was spent analyzing a disk image from a hacked box at
Caltech. RuthAnne from CIT and I
have been comparing notes and there are a few curious items about the
incident which may be related to another recent incident on campus. It appears the hacker came in through a
weak root password. A more detailed
report will be circulated after all of the details are learned. This latest incident reinforces the need
for well managed passwords, *especially* root/administrator passwords.
- Implemented
some more aggressive logging and ssh monitoring at the firewall.
- Installed
some Netflow software. Still a few
quirks to work out. Not 100%
pleased with both of the implementations I tried.
- More
backups, etc.
- Updated
the IDS rules
- Since
Jan 1 of this year, there have been 269,111 ssh brute force and/or
dictionary attack attempts at LLO alone.
This reinforces the importance of strong password management. It only takes one correct guess to cause
headaches, both to the admins and the affected users.
Hanford
(Christine)
- Most
of this week has been spent trying to build MRTG and the RRD advanced
graphic tool. As with most
freeware, they require certain libraries, the latest perl and several
other utility packages. None of
these work with the Sun freeware binaries, they are all required to be
built from scratch. None of this
software will compile on the first try, it all requires environment
variables be set or something it needs is not in the path, etc. It is a real pain.
- Set
up the video/audio server for the Auditorium camera to be used for the
LSC.
- Had
CIT ITS add two new name/IP pairs to the DNS tables for CDS's new ilog
server and the web interface to the FMCS system. These servers are still being tested.
- Made
several purchases for users.
Looking into replacing the modem pool modems and router. Also getting quotes for upgrading the
disk storage and backup equipment for the user home directories.
- Helped
a user edit their Inbox on the mail server because a message was
corrupting the file and preventing Netscape from reading the file.
- Organized
a bunch of surplus computers, printers and monitors into a keep pile and a
throw away pile. When Rod Luna was
here this week he disposed of the throw away pile.
CIT
(Bruce Sears)
- iLog
Software and Policy Development:
- More
communications regarding requirements for new version of iLog.
- Set
up of a test iLog server for discussion about upgrading iLog at the
observatories.
- iLog
development documentation.
(Mike)
- Freeing
up some disk space on our Ghost Server, by adding an additional hard disk
using an IDE to USB convertor. These types of convertor's are great tools
to have.
- Continued
work on Spam Filters, searching for false positives, and other
administrative work on the Canit software.
- Additional
Backups: Ghosted NTSRV's Graffias & PC6. I'm working on testing some
additional backup software for the llpdmworks server.
- Worked
with Larry installing shelves to install the 2 network switches that are
currently setting on the floor in the 3rd floor network closet W/B.
Sometime next week we will be moving the switches off the floor and
installing these in the shelves plus re-cabling all network connections.
- Troubleshot
a network issue with Larry for Wilson House. Their network switch went
down. This has been swapped out with a backup switch.
- Working
with Larry searching for various workstations that were compromised. All
workstations were located, and are off the network. Users will have to
rebuild these systems.
- Cleanup
work in the B/A server room, making room for additional equipment.
- Other
misc. user/phone support.
(Christian)
- Finished
updating the laptops that are traveling to Hanford Observatory with the
latest security patches and virus definitions.
- Upgraded
Dot's workstation from Windows 2000 to Windows XP.
- Replaced
toner cartridges on HP 5500 printer.
- Installed
Thunderbird for Mike Smith on a visitors' workstation.
- Configured
Bob's new laptop with the Ligo standard image.
- Continuing
investigation to find a replacement s/w pkg. for the WebCAM XP tool. This
tool is OK and good for the price but a couple more utilities would be
nice. Other misc.: Continued onsite
software/phone support.
(Veronica)
- LSC: Ongoing support of the March meeting
website and backend applications.
Updates of the database of technical papers.
- LIGO: Copies of the Virgo Project DVD. Compressed the talk by Vuk Mandic for
streaming, and burned a DVD for the TAPIR group. Working on the Elba
website.
- CaJAGWR: Website updates. Set up the camera for taping the Tuesday
talk, assisted JoAnn with the howto, compressed the footage for streaming.
I was out of office for part of this week.
(Larry)
- Still
working in the world of purchasing.
Ordered more equipment for different people. Delivered a number of
items that have been received.
Finally, CISCO has agreed that the maint. contract renewal at the
present time should be done through them. They too were unable to find a
local third party for us to go through. I should be able to put in the
renewal online. Still adding to the
list for the SUN matching grant program. I am trying to make sure they
will deliver to the different locations.
- Had
a couple of printer issues resolved. Millikan will need a replacement soon
but the unit is no longer making the high pitched noise.
- Worked
and still working on a computer security incident. The major problem with
it has been the time involved and handling the distractions that go with
it.
- Reworked
a couple of the backups. One more tape is going to be redone, it lists OK,
but I still don't trust it.
- Restored
a number of files for different people.
- Relocated
a number of h/w items for different groups.
- Assisted
Christine and others with some of the logistical issues for the LSC
meeting.
- Ran
more diagnostics on the Dual Core quad cpu unit from Monarch. It failed
the memory test and is back to rebooting itself on a regular basis. When I
get a chance I will open it up and check the h/w and do some memory
swapping.
- Continue
working the mail filters. The whole thing is to the point that it needs to
be reset. A lot more getting through than normal.
Mail Statistics March 2-8, 06
|
Mail Statistics
|
March 9, 2006
|
|
Rejected Messages
|
28,170
|
|
Virus Messages
|
1,024
|
|
Accepted Messages (Half of these probably should have been
rejected)
|
45,965
|
|
Total Messages
|
74,135
|
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Systems
See
also:
AL Systems
web page
AL
Systems email archives
Records of Decision or Agreement (RODA)
See also the RODA
status web page
Requirements/Design
- Working
on conceptual design & costing of the vibration isolation of the
in-vacuum ISC reflected and pick-off port table.
- Luke
Williams visited Caltech this week, working with Mike Smith on the optical
layout. Had discussions with IO group (Dave Reitze, Dave Tanner, Guido
Mueller, et. al.) and Peter Fritschel on layout constraints and design
preferences. Trying to get workable stable and “unstable”
recycling cavity layouts to determine if 5 HAM optical tables (and
isolation systems) are sufficient, or whether a 6th table (and
isolation system) is needed.
Interface Issues
See the "Interfaces" section of the AL Systems
web page
- Helping
Carol Wilkinson to review costing, schedule and planning in preparation
for the NSF AL review.
Vacuum Compatibility
Residual Gas Assay (RGA)
See also the Vacuum Bake Lab
- I
have been working with Ben on his investigation into the OSEM failure
problem.
- I
have started to prepair the OSEMs that came from MIT, for rebuild. When I
get all of the Ceramabond off and get them clean again I will rebuild and
test them.
- I
built the diode boards for Rich to do his test. I am building more diode
boards for Ben.
- Have
cleaned 12 beam dumps for Steve at the 40M and will begin baking them as
soon as I receive the end peaces from Mike at the machine shop.
- I
will meet with Luke Williams today about the Faraday Isolator cleaning and
baking.
- I
had a meeting with Ken Mailand and Calum this morning about cleaning and
baking the tooling that Ken is designing for the Quad.
- Calum
& I also discussed the up coming trip in April to MIT in support of
the SUS quad installation/testing.
Scatter/Absorption Test Measurement System
Lee Cardenas, Liyuan Zhang, Bill Kells
Finally, The laser is running as a complete system. We have installed the new aperture cooling
unit and re-aligned the whole optical path and improve the mode match. Right now, we are scanning the big 4ITM07
mirror for absorption with a new calibration, having the Yag Laser spot at
150um and the HeNe spot at 450um in diameter. having measurements at different mirror depths
and scanning at different areas, and diameters. Mainly improving the absorption
test sensitivity.
High-Irradiance, Contamination-Exposure Cavities
Lee Cardenas, Liyuan Zhang
Changes indicated in yellow highlight.
|
Cavity
(Location)
|
Material/Item
|
Start
|
End
|
Comments
|
|
Cavity
#1
(OTF Lab, Bridge)
|
“Cable
wire” (material type?)
|
~11/17
|
TBD
|
Taking measurements daily.
|
|
Cavity
#2
(OTF Lab, Lauritsen)
|
NA
|
NA
|
NA
|
We continue working on setting up the system
|
|
Cavity
#3
(OTF Lab, Lauritsen)
|
OSEM Flexi-circuit cable, qty ~ 45
(Helena Armandula, SUS)
supplied
by Univ. Birmingham (Stuart Aston)
|
~9/30
|
TBD
|
taking daily absorption & ring
down measurements. So far it has been 60 days of
continuous test (1440 hours); three more days and the test will be completed.
DuPont Flexible Circuits. The whole
part to be constructed of 'flexi' i.e. no 'rigid' sections. (Stuart Aston,Univ. of Birmingham, SUS/UK subsystem)
- Start Laminate: Kapton (LF8515)
(document link: http://www.dupont.com/fcm/products/H-73244.pdf
Coverlay (x2): Kapton (LF0110)
(document link: http://www.dupont.com/fcm/products/H-73245.pdf
DuPont Pyralux Series - Kapton / Acrylic Adhesive system.
(document link: http://www.dupont.com/fcm/products/H-73246.pdf
|
|
Queue
Priority
1
|
2
Cleaned 50ppm transmission mirrors, 1 in dia., REO coated --
|
TBD
|
TBD
|
witness
samples for the LHO vertex volume (added in 6/29/2005 vent)
|
|
Queue
Priority
2
|
Stepper
Motor (Riccardo DeSalvo, possible SUS or ISC use)
|
TBD
|
TBD
|
Stepper Motor sample had been placed into Cavity #1: Power
dropped from 175 mW to ~25 mW after introducing the stepper motor sample, and
continues to decrease. It is very hard to keep cavity locked. The stepper
motor may have contaminated the mirrors. Will re-test when a cvity becomes
available again.
To be rebaked soon using the self-heating capability of the
stepper motor (not just the oven heater controls)
|
Advanced LIGO Management
second draft of the
Seismic Isolation
Advanced Ligo Seismic Isolation Procurement Status
- The
large Stage 1 plates have arrived from Arland Tool. The stage 0 and stage
1 plates have been moved into the high bay and placed on a pallet rack for
assembly.
- The
fastening hardware was received this week and is being organized into bins
by Fred Miller.
- Worked
on scheduling, cost estimates, boe, and staffing for advanced ligo seismic
isolation.
- The
position sensor target was redesigned to 2 pieces instead of 1 due to
unavailability of large diameter 1100 aluminum.
- Began
design of the blade calibration fixture shims to assure we are properly
loading springs through the entire test range.
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
Working on reports for
Carol in preparation for the NSF Review.
From: Ken
Mailand kmailand@ligo.caltech.edu
Bob is starting the
cleaning on the plate fixture parts. CES is adding modifications to the large
plates before they are plated. Also for Calum, we
have purchased a smaller assembled lift table, for the LASTI work in early
April.
From: Jay
Heefner jay@ligo.caltech.edu
AdL Cost and Schedule
- Spent many hours this week
reviewing and updating the costs and schedules for SUS, SEI, DAQ and ISC.
AdL SUS Quad Controls
Prototype
- New adapter boards and
interface baords for the LASTI install have been received and are being
stuffed. They should be ready by next week.
- The new timing interface board
design is complete and has been sent out for fab. It should be back next
week.
From: Ben Abbott
<abbott_b@ligo.caltech.edu>
LED Failures
I have spoken to many
people, trying to fully understand what has happened to the LEDs at
LASTI. Of the 6 LEDs that were sent back from the quad pendulum as having
failed LEDs, three were fine (turned out to be a problem with a cable), and one
had an unglued PD board but the LED was fine, but two of the returned boards
actually had non-functioning LEDs. Two other LEDs are suspected to have
failed on the triple pendulum, and these are being sent here for
diagnostics. Once I have all of the truly failed LEDs accounted for, I
will send them to Honywell for more refined diagnostics.
In the mean time, Jay,
Mohana and I took a hard look at the GEO driving electronics, noticed some
anomilies related to power supply interruptions, and came up with some measures
that should, at least, lessen the probability that the LED damage occurred as a
result of a damaging output from the electronics. The GEO electronics
were designed to drive an LED that is significantly more robust than the one we
are using. It is therefore conceivable that, although they have never
damaged a GEO LED, they could still damage ours. Mohana is retrofitting
the fixes onto two LED drivers that we have here, and she will send them to
LASTI when they are completed. The plan is to swap them out for the
drivers on the triple, and have those drivers sent to us for retrofitting for
the quad.
In parallel with that, Bob
is making me several LED boards with three batches worth of LEDs so that I can
destructively test them and determine if there is any robustness difference
between the original batch we got, and the batch that we got in 2005 that seems
to be failing.
I am finishing up the
layout of a back panel for the PCIX effort. It should be sent off this
week.
Core Optics
From: Helena Armandula ahelena@ligo.caltech.edu
Advanced LIGO Coatings
Received the first test
report on the FTIR analysis of First Contact. This is a strippable coating that
can be applied to a mirror to protect and final clean the mirror's surface. The results are in the dccdocs OUT, T060051-00
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
The PSL costing has been
updated to FY2006, with some minor revisions to the labour estimates. The
costing has been marked up and returned to Dwight. Also completed are the
risk factors up to the schedule impact.
I discussed some schedule
issues with Benno, with regard to delivery of the LASTI laser and the
observatory lasers. There has been some progress on the laser front with
the output power being up to approximately 170-180 W. However 20% of the output is in other
polarisations and the suspicion is on the birefringence compensation.
The Xilinx DSP adventure
continues with their web support personnel, who have apparently cast us
adrift. The hardware issue is apparently not present in the latest
release of their software, which for reasons best known to them is not released
with the hardware when you buy it. Attempts to get the latest version of
their software have not borne any fruit so far, as the link I was pointed to is
a customer support homepage.
Auxiliary Optics
From: Michael Smith <smith@ligo.caltech.edu>
VERTEX LAYOUT
The Zemax layout of the 2K
IFO is proceeding based on the following assumptions:
1. BS
wedge is the same as 4K IFO
2. BS
height same as 4K IFO
3. ITMY PO
mirror same height as ITMX PO mirror in 4K IFO
4. PRM and
MMT3 are at same elevation
The parameters of the BS
transmitted beam were adjusted as follows:
The ITMY
reaction mass wedge is adjusted to satisfy assumption 3.
The FMY is
steered to satisfy assumption 2.
The PRM
wedge is adjusted to satisfy assumption 4.
Under the above
conditions, the centerline height of the 2K PRM is -133mm global, compared to
-157mm global for the 4K IFO.
OPTLEV
Luke Williams from UFL is
at CIT this week laying out the proposed stable recycling cavity IO beam train
in SW. He is developing a conceptual layout of optical lever beams for
all the suspended optics in the IO beam train.
I am working with Riccardo
to develop a design concept for suspended optical lever transmitter and
receiver platforms, which should provide an order of magnitude improvement in
optlev noise.
SLC
Hiro is still working on
obtaining transfer functions for scattered light noise in the ADLIGO RSE
configuration with the optical spring effect.
AOS COST
Phil Willems and I are in
the process of updating the AOS cost figures.
Controls, Data systems
No report this week.
Other Laboratory R&D
From: Riccardo
DeSalvo desalvo@ligo.caltech.edu
Virginio and Valerio
Yumei Calun
- simulating and measuring wands
and dampers. The resonant damper designed in case of necessity for
the HAM spring box is being tuned to 60 Hz for possible use on the
quadruples
Tarallo
Stochino
For additional information about this report, contact Stan Whitcomb or Phil Lindquist