Weekly Report for
Week Ending March 2, 2006
The LIGO Executive
Committee Agenda for Monday,
March 6, 2006 will be:
(Meeting time: 10:30 am Pacific Time)
1. Announcements
2. Comments
on Weekly Report
3. LSC
Issues (Saulson)
4. LIGO
Lab Operations
- Administration
(Lindquist)
- Sites
(Raab, Zucker, Shoemaker)
- Commissioning
(Fritschel), Detector (Coyne)
- Campus
Research Facilities
- 40
Meter (Weinstein)
- TNI
( Libbrecht)
- LASTI (Shoemaker)
- Data
Analysis and Computing (Lazzarini)
5. R&D
and Advanced LIGO (Shoemaker)
6. CHANGE CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION AS
NEEDED
Special Items:
- New advisory
bodies--LIGO Lab Board and LIGO Academic Advisory Council (J. Marx)
- Preparations
for Advanced LIGO Review (May 31 – June 2)
Special Announcements:
Weekly Report Highlights
No report.
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
SITE TELECONFERENCE (Lindquist)
- A
site teleconference was held Thursday, March 2, 2006. The following issues were discussed:
- Financial
Tracking Report—the end-of-March reports for Operations and
Outreach have been posted. The
current spending rate for FY 2006 is projected (very approximate at this
point) at $32 million for LIGO Operations.
- Livingston
Science Education Center Construction—Received
a large load of materials today for the exterior of the building. Proposals for the kinetic façade are
expected tomorrow.
- Relocation
of LDAS Equipment—A change order was
issued this morning for construction of the structure to house the
equipment.
- Hanford Inventory—R. Luna will be
in Hanford
next Monday and Tuesday to conduct an inventory.
- GSA
Van for Livingston—Still waiting on the
GSA. FEMA took most of the
vehicles.
- The
list of assigned actions updated through December 01, 2005 will be found Here.
PROPERTY MANAGEMENT (Luna)
>
- Provided
assistance to the Detector Group
(H. Armandula) with packing and shipping a
coated mirror to Stanford (R. Route),
Account Number LIGO.OPT - 5.4 - NSFLIGO.FY02ON.
- Prepared
letter for the disposition of 80 computers (2U rack-mounted nodes + 4
racks) by the LDAS group (A. Lazzarini).
- Tagged
2 Computers and 2 Monitors.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- Continued
to process 2005 Travel Expense Report files.
- An
additional 19 HAM drawings were submitted by Promec
and have been processed.
- Scanning
Project--Continuing scanning of contract closeout files.
- Activity:
|
Week Ending
03/02/2006
|
In
|
Out
|
|
Packages
|
29
|
5
|
|
Faxes
|
25
|
24
|
FINANCIAL SYSTEMS (Cronin, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Completed
invoice-attached orders. One order
had sales tax included in the invoice total which the adjustment has been
requested to remove the tax. Requested the vendor to update the tax code
so that future orders do not incur sales tax.
- Completed
change order #170 to Triad to allocate funds for three individuals for
FY2006. The change order was routed
for approvals.
- Finishing
up change order #7 to the University
of Michigan.
- Completed
change order #34 to GSI to add funds to cover a pending invoice.
- Responded
to the initial request and subsequent request from the auditors on A-133
filings.
- Working
on change order the University
of Florida.
- Working
on obtaining the A-133's for 2005 for the subcontracts.
>From: Florence Kaufman <fkaufman>
- Completed
and sent out reports for Ops&R&D,
Outreach and Visitor Awards as of the end of February.
- Prepared
a Cost Transfer to correct travel expenditure for a visitor that had been
charged in error to the Ops Award instead of the Visitor Award.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- A
field change order was issued to Cangelosi-Ward,
the construction contractor for the LLO SEC, to construct a small building
inside the storage area of the staging building. This will house the re-located LDAS
equipment, which could not be located on the second level due to floor
loading restrictions. This building
must be constructed quickly since the LDAS equipment is currently
occupying space reserved for exhibits to be delivered by the Exploratorium
next month. Since Cangelosi-Ward was already on the site, they would
have no mobilization effort. The
cost of this change is approximately $49,000.
- A
request for a revised proposal was sent to Galli
& Morelli on the HAM SAS as a result of
Wednesday's CCB action. The
revision was requested to reflect a series of additions and subtractions
that had evolved since the original proposal was submitted in November.
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
- The
usual new trips, expense reports, reconciling, calendar reservations, and
itinerary entries.
>
>Dorothy Lloyd
- No
report
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
PROPOSALS and REPORTS (Lindquist)
We have prepared a FastLane request for a
Supplement to the LIGO Visitors Program (NSF Award PHY-0245117). We are requesting an additional $30K for
stipends and travel expenses for four Participant students to spend the summer
working in Italy
on the VIRGO Program. We are ready to submit
it to NSF.
For the status of efforts to prepare for the Advanced LIGO Review see Advanced LIGO below.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
- Change
Request CR-050010, Prototype Seismic Attenuation System for the HAM
Chamber (HAM-SAS) was submitted by Dennis Coyne. The request provides
authorization and funding for the fabrication and test of a predominantly
passive, seismic isolation system prototype for the HAM chamber, for the
Advanced LIGO R&D program. A LIGO Change Control Board was held
Wednesday, March 1, 2006. The change request was approved. Minutes have been posted
(LIGO-M060034-00-P). The signed
original is in the Document
Control Center.
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- A Staffing Committee meeting was held on Monday,
February 27, 2006. The minutes and action items from the Staffing
Committee meeting are in progress and when completed will be posted on the
SC web page. The next Staffing
Committee meeting is scheduled for Monday, March 27, 2006.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
Nothing significant to report this week.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of Commissioning Activities at LIGO Hanford Observatory (compiled by M. Landry)
When running, both H1 and H2 exhibit excellent science mode locks of ~14Mpc
and ~7Mpc respectively, with lower Burstmon pixel
fractions (~0.2) than recorded prior to the commissioning stint. However
this week has seen long outages on both IFOs,
particularly H1. Both machines unlocked early Wed a.m. (possibly due to a
quake in the Philippines),
and H1 remained down for 43h. Double and triple coincidence was restored
early Friday morning. The outage on H1 was complicated by very strong
microseism ~1um/s and technical problems such as the failure of h1dcuepics
(below).
S5 highlights are bulleted below:
- the
standard set of S5 range and duty cycle plots was updated
- the
Tuesday maintenance period was summarized,
as was the associated recovery
4K IFO
- a new post-commissioning-epoch calibration was loaded
on the 4k. The range (as expected from new filters) had been low by
about a half Mpc; this was restored to Sensemon upon restart with the new calibration
- the
TCS power sequencer/ioc failed
during a lock stretch; as the ITMX was not getting any mods
to annulus heating, the range of this lock decayed until lockloss and a reboot of the controlling IOC
- after
the Philippine quake, there were many steps taken prior to re-establishing
science mode running, some being summarized here,
here,
and here.
- a study
of input beam jitter was posted, suggesting the input beam landing on the
RM is too mobile
2K IFO
- POB/POY
glitching on 2k impacted locking on the
weekend. In order to return to stable locking, restoring the
alignment based on SUS INMON values appears to be the right way to go,
suggesting drifts in electronics dominate over real physical alignment
drifts due to the stacks. More on POB/POY switching
- in
the post commissioning epoch, the (formerly more stable) 2k is now less
stable than 4k, in the sense it unlocks more readily
- the
TCS servo was then disabled
owing to high ASI_CORR
- 2k
AS triggering to save lock losses has been more
difficult to implement than 4k counterpart
CDS
- a failed
h1dcuepics power supply was swapped
out
Outreach (D. Ingram)
Richard McCarthy represented LHO's interest in
Read Across America Day (3/2) by reading aloud to
three classes at Sacajawea Elementary in Richland. Fred Raab produced a new talk, "LIGO for Chemists" and
presented it to ~90 Hanford High chem students as
part of their LHO field trips on 3/1 and 3/2. Greg Mendell
will deliver a June talk as part of the annual Mid-Columbia
Literary Festival (scroll down) produced by Columbia Basin
College and the
Mid-Columbia Library Foundation.
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
L1 Interferometer in S5 (O'Reilly)
For the past week L1 had a duty factor of ~50% with the main culprits being
our old friends microseism and construction. We again had trouble with the RM satellite
box, the old one was repaired and reinstalled on Monday and the problem now
appears to have stabilized.
There were some interesting studies in the elog:
Luca Matone investigated glitches using (among other
things) the new QScan tool, Dan Busby found some
interesting and puzzling correlations between PEM channels when the
interferometer acquires/loses lock, noise coupling measurements by Valera Frolov and a comment on
the acoustic/seismic sensitivity of the WFS signals by Rana
Adhikari.
Due to the observance of the local Mardi Gras
holiday there was no maintenance at Livingston
this week. Unfortunately, due to the
aforementioned microseism, the interferometer decided to take a Mardi Gras holiday as well.
Safety and Security (Riesen)
The main gate now has IR Photo Obstruction Sensors installed to keep the
gate from closing if the IR beam is not being reflected back to the sensor
head. More units are on order for the side
gate. I have re-certified the HPLF
concerning all laser safety requirements.
The new 100 watt laser is installed and ready for action. Ken Franzen has the
helm and is the sole sponsor for two U of Florida people who will assist him in
his tasks. Both visitors have met all LLO safety requirements. Working with Bill Tyler on
the upcoming LLO safety audit.
Found no laser nor site safety concerns this
reporting period.
Outreach (Thacker)
- 2/24
Outeach Program to Holden High physics;
- 2/25
Outreach Program to Riverside Baptist
Church father/son group;
- 2/25
attended evening program at St. Georges Observatory, Schriever, LA and gave 5 min. talk about LIGO and
its outreach program; prepared for LSU student recruitment visit this
Saturday.
L1 CDS (Bogue)
- Worked
on getting framegrabber fully functional after
its OS upgrade. I'm still trying to
resolve a labview version/licensing problem on
it.
- Made
a trip to the optometrist to discuss problems with my laser safety
glasses.
CDS Software (Khan)
- Fixing
Weather Station problems with Doug Lormand's
help.
- Developing
a CDS map for diagnostic purpose.
General Computing (Giardina)
- completed script for NIS group changes. It is usable, but would like to tweak it
before passing it out.
- kantec related errors with
new gate. errors
possibly stem from kantec upgrade back in
September. never
tested this scenario until today. going to research kantec
site, or contact Chuck Brannon if needed.
- used Christian's unattended XP install DVD to reinstall
FRAMEGRABBER PC. Not all software
was installed / registered due to license issues before I left for
vacation. Lisa has reclaimed this
PC. Other than some post install
Adobe Acrobat issues, it was smooth sailing.
- other
usual user requests and support
LDAS Support (Giardina)
- tapes
ejected and shipped to CIT: LL0516,
LL0517, LL0525, LL0586, LL0621, LL1360, LL1363, LL1364, LL0542, LL1367,
LL1386, LL1387, LL1393, LL1396, LL1397, LL1398, LL1399
- tapes
ejected for local storage: LL0072,
LL0081, LL0101, LL0102, LL0142, LL0212, LL0231, LL0275, LL0278, LL0285,
LL0297, LL0299, LL0308, LL0315, LL0318, LL0321, LL0322, LL0404, LL0420,
LL0459, LL0465, LL0468, LL0477, LL0478, LL0479, LL0480, LL0481, LL0483,
LL0486, LL0494, LL0495, LL0652, LL0676, LL0384, LL0182, LL0620, LL0606,
LL0166, LL0226, LL0319, LL0071, LL0000, LL0280, LL0410, LL0416, LL0295,
LL0287, LL0293, LL0332, LL0307, LL0305, LL0348, LL0396, LL0341, LL0311,
LL0042, LL0075, LL0462, LL0446, LL0473, LL0422, LL0451, LL0638, LL1690,
LL1087, LL1714, LL0587, LL0490
- tapes imported into L700 library: LL1366 - LL1419, LL0730-LL0749,
LL0751-LL0755 **** Tape LL0750 was passed over three times
and never recognized by robot.
- email
configuration changes on FC4 machines with GC interface
- createRDS errors were found
to be caused by incorrect 'H' in a .ini
file. corrected
by Lisa.
- configured LDAS FC4 machines for a centralized syslog on ldas-gridmon.
- stopped
sendmail on ldas-grid
until we create appropriate aliases to significantly reduce bounced emails
Computing and Network Security (Roddy)
- I
got pulled into a discussion about the ilog
performance. So, I have spent a
fair amount of time determining where the bottlenecks are in the ilog. It is a
bigger issue at LHO, but performance is slightly lacking at LLO also.
- had a machine that would spontaneously power off, then
would not reboot. Turned out that
the overtemp setting in the bios was set to 68
degrees celsius.
The setting was a bit to conservative and
would cause the machine to shut down.
- working on pulling a bunch of archived files off of a raid
controller and a couple of disks.
The files need to be restored onto media that is more accessible.
- Still
working with Sun to try and get a support contract purchased. This has turned into a difficult
process. I now have a direct number
to someone who can place the order, but we are playing phone tag. Buying a support contract has never been
this difficult before.
- Working
on some paperwork issues with the Pcard folks
from last year.
- Dell
is claiming that a system purchased on a credit card was not paid
for. I will have to dig up the
records to show that it is already paid.
- Spent
some time troubleshooting some network issues. Turned out that it was LSU blocking
several class A subnets, they claim because of DoS attacks.
Most of the people at LSU were not even aware of the blocking, so
it took a while to figure out what was going on.
- more of the usual... Hardware orders, digging through
IDS logs, etc.
Data Analysis (Yakushin)
- Testing
the coherent version of waveburst on S4 data.
- Participating
in the telecons to review the modifications done
to waveburst for S5 in preparation for the APS
and LSC presentations of the burst search on the first few months of S5.
- Fixing
CorrPower and Event display matlab
scripts used in waveburst online analysis that
got broken as a result of the switching to the new matlab
version.
- Changed
(all?) the html links for S5 online waveburst
analysis that previously pointed to ldas-pcdev1.ligo.caltech.edu to point
to ldas-jobs.ligo.caltech.edu instead.
E2E (Yoshida)
Continued analysis of ground and HAM table-top Yaw motion
using LIGO 1 e2e HAM stack box. Using horizontal seismic position sensor
DAQ signals (e.g., L1:SEI-MC1_POS_H1_INMON, etc),
created time series of X, Y and Yaw motions of the base on which the HAM stack
is placed. Using this time series as input to the stack box, computed the
table-top X, Y, and Yaw motions. These table-top motions will be given to a
small optic suspension box placed on top of the HAM table, and the resultant
OSEM Yaw signal will be compared with the corresponding DAQ signal recorded at
the same time as the seismic sensors.
Started preparing AdvLIGO Mode
Cleaner (MC) modeling with e2e. We are currently learning how to use AdvLIGO triple suspension Mathematica
codes written by Mark Barton to create a space state matrix to simulate AdvLIGO MC optics.
Initial LIGO Detector Science & Engineering (Coyne)
CDS
see also the CDS weekly meeting minutes in the commissioning archives
CDS Software
Rolf Bork
- Continuing
work on changes requested for Fast ADCU. This is scheduled for
installation at LHO next Tuesday.
- Pepi code is ready for installation at LHO next
Tuesday.
- There has been mention in various meetings of the
desire to add adaptive filtering and FIR filter modules to our present
list of standard
algorithms. I hope to meet with a few people at the LSC meeting to firm up
requirements and an implementation approach.
40-Meter Interferometer (Weinstein)
IFO Commissioning
- Osamu
and Noriyasu worked on re-acquiring full lock,
but ran into many problems, associated with the new laser (different
optical gains, etc), and changes made to the length control front-end
code. Osamu found a bug in the code and worked around it. He was able to
lock the FPMI and also move to CARM/DARM, but when trying full RSE lock
the system becomes unstable as the CARM offset is brought to zero. Under
study.
- Alan,
Osamu and Rob are trying to understand the magnitude and phase of the
optical transfer functions taken back in October by Osamu while varying
the CARM offset (and therefore, the power buildup and optical spring). The
magnitude of the TFs agree
beautifully with the theory expectations and with Rob's Optickle simulation; but the phase is a little bit off
(consistent with something like a small negative delay). Rob thought it
might be a phase difference between DARM_IN1 and PD1Q, but Osamu measured
that and saw no phase difference at all. Under investigation.
- Monica
continues to commission the various pieces of the noise budget estimation
code. Ben wired the AS166 DC signal into EPICS for use in computing the
shot noise contribution to the noise budget. Monica modified the code to
make the shot noise budget semi-automatically. She's now working on
measuring the coil driver / daq noise in the
test mass suspensions.
IFO Modeling
- Monica
continues to develop and debug the control loops in here e2e model of the
40m. To aid in debugging, she is calculating the OLTF of the loops; so
far, she has done DARM and MICH,
and is working to understand the results.
DC Detection Development
- Ben
is working on the DCPD satellite box. He has talked to Rob and gotten the
specs for the filters, so now the design can be finalized.
- The
beamsplitter for the DCPD detector was coated
incorrectly, so Steve sent it back to CVI for recoating.
- Steve
ordered more vented screws for the OMC.
- Sam
and Jay agreed on some modifications to the driver board for the PZT
steering mirrors in the in-vac DC readout beamline. Sam continued to investigate the resonances
in the PZT mirrors. In the DLC mounts, there are several resonances below
1 kHz, including one as low as 150 Hz, limiting the bandwidth of the
proposed ASC servo. Sam mounted mirror on bricks, and found no resonances
below 650 Hz. So, we need better mounts!
- Jay
and Rolf propose to use the new PCIX-based readout architecture for the DC
readout data acquisition and controls. Jay will draw up a detailed plan
(building on Rob's block diagram) in his spare time. We can hope to have a
system in place in a couple of months.
Electronics, Controls, Computers
Lab Infrastructure
- Steve
is building a beam tube for the MCR beam, and has sent it out for
anodizing. Steve is also building beam tubes for the high power beam path
on the PSL table.
- A troop of Pasadena
boy scouts visited the lab on Friday.
Thermal Noise Interferometer (Black)
No report.
LASTI (Ottaway)
No report.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Yamamoto)
40m modeling (Monica Varvella)
DARM and MICH
open loop transfer function have been simulated. A comparison with Twiddle
result will be done at least for MICH
as there are no real data to compare with.
Still debugging the control system for CARM, PRC an SRC.
Mechanical simulation for AdvLIGO (Sany Yoshida)
Continued analysis of ground and HAM table-top Yaw motion
using LIGO 1 e2e HAM stack box. Using horizontal seismic position sensor
DAQ signals (e.g., L1:SEI-MC1_POS_H1_INMON, etc),
created time series of X, Y and Yaw motions of the base on which the HAM stack
is placed. Using this time series as input to the stack box, computed the
table-top X, Y, and Yaw motions. These table-top motions will be given to a
small optic suspension box placed on top of the HAM table, and the resultant
OSEM Yaw signal will be compared with the corresponding DAQ signal recorded at
the same time as the seismic sensors.
Started preparing AdvLIGO Mode
Cleaner (MC) modeling with e2e. We are currently learning how to use AdvLIGO triple suspension Mathematica
codes written by Mark Barton to create a space state matrix to simulate AdvLIGO MC optics.
Static IFO Simulation (Hiro Yamamoto, Melody
Araya)
Many lines of codes, no interesting usage yet.
Adv.LIGO simulation using twiddle (Hiro Yamamoto)
The scattering noise effect is calculated using twiddle to help Mike to
design support optics to suppress the noise due to various scattering noise
injected back into COC.
Dual core, quad CPU machine (Hiro Yamamoto)
We purchased a dual core quad CPU machine. We had trouble running e2e
simulation at the speed same as dingle core quad CPU machine. One issue was operating systems (OSs), which was solved by Larry
who installed different OSs and latest patches. Now the module simulating a dual recycling
cavity runs 1/2 ~ 1/4 of the speed expected from single core machine. One possibility is that two machines comparing
have different versions of gcc. Now the latest gcc is installed and the comparing will be done using same
binary built using this latest gcc 4.1.0.
Data Analysis Activities (Lazzarini)
Brown:
Spent most of the week working on the LIGO EMRI problem Ran full S5 BNS
analysis from Nov 4 - Feb 6 and posted results for iulgroup. Tracked down the problem with segment
database replication caused by the RAID crash on ldas-cit
Dupuis:
- working
on follow-ups in S5 TDS search
Chatterji:
Mendell:
Mike Landry and I completed an analysis of the first 4 hardware injected
pulsars in the S4 data using the StackSlide code.
These and other S4 results are posted here (usual access retrictions
apply):
http://www.lsc-group.phys.uwm.edu/cgi-bin/enote.pl?nb=puls4stackslide&action=view&page=17
A few minor bug fixes that do not affect any results (but do prevent a rare seg fault during Monte Carlo
simulations) where also checked into the lalapps/src/pulsar/StackSlide
directory since the last Weekly. We are
now rerunning on the SFTs with the S4 version 4 calibration, and finalizing the settings for a production
run. The next code review is tomorrow,
March 3, 2006.
Yakushin:
- Testing
the coherent version of waveburst on S4 data.
- Participating
in the telecons to review the modifications done
to waveburst for S5 in preparation for the APS
and LSC presentations of the burst search on the first few months of S5.
- Fixing
CorrPower and Event display matlab
scripts used in waveburst online analysis that
got broken as a result of the switching to the new matlab
version.
- Changed
(all?) the html links for S5 online waveburst
analysis that previously pointed to ldas-pcdev1.ligo.caltech.edu to point
to ldas-jobs.ligo.caltech.edu instead.
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS
Currently running through unit tests of 32bit compiled LDAS using GCC 4.0.2.
Working on providing 64bit version of libraries and packages needed for
64bit compilation of LDAS. The packages that have been completed are tcl and fftw3. The packages that still need to be done are tk, globus toolkit, and openssl.
Enforcement of expired X.509 certificates on persistent connections has been
added to cmonClient (PR#2994). With this change, a
user is prompted for his/her passphrase if their
certificate has expired before commands will be sent through the persistent
connection.
A new option (-md5sumregexp) has been added to the createRDS
command (PR#2953). With this option it is possible to have the md5sum file be
in a directory other than the output directory of the RDS.
The sleep proc was eliminated (PR#2997). This has marginally increased the
overall through put of LDAS.
The system tests were done using LDAS version 1.8.100. Also, the testing
library LDASJobH has been updated to support -email persistent_socket
and the dataStandAlone/putStandAlone loops have been
converted to use persistent sockets.
TCLGLOBUS
Debugging code has been added to aid in memory leak issues within TCL Globus. A warning message is emitted if there is more than
a 2MB increase and a core dump is generated if the increase is greater than
200MB.
Support has been added to the TCL Channel interface allowing for the
creation of GSI and non-GSI sockets.
GRID COMPUTING
Working with Kent, documented LIGO app test results and
recent issues for OSG Executive Board in a report requested by Ruth Pordes.
Obtained OSG Production access to two sites at the
UFL: UFlorida-PG
and UFlorida-IHEPA.
All nodes have been yum updated. Added initial support for
srmcp on osg-itb-se.
Filed bug report with OSG goc and notified Rob
Quick regarding failure of srmcp in OSG 0.4.0 cache
to work on FC4 with SRM/DRM on FC4.
Working with Alex Sim, the LBNL SRM/DRM
development lead, tested a new version of srmcp
delivered by Timur Perlmutov,
the FNAL srmcp development lead that addressed the
bug. Confirmed that the new version of srmcp
supports transfers from a local file system to the LIGO ITB SRM/DRM on FC4.
Attended an ITB telecom related to issues for ITB 0.3.6
Attended a VDS telecom with the VDS/ISI folks on OSG
issues related to work flow planning.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Did
the weekly receiving/ingesting of tapes from the sites.
- Mounted
/archive/backup/40m (read-only) on kitalpha.
- Worked
on failure of 3510-11 (CIT's /export), finally
determined that the problem was the secondary controller--once it was
pulled out the unit has been working.
I've called it in to Sun.
- Did
a _lot_ of work with Sun on determining the problem with 3510-10 (our
test/spares unit). An intermittent
power supply has now become a dead power supply and we may also have a bad
slot in the RAID unit.
- Helped
put a Sun GigE card in ldas-cit
to replace a possibly dying SysKonnect one.
(Phil Ehrens)
- Supported
Mary Lei and Mike Samidi in LDAS related tasks.
- Set
up machine "maasim" as an additional
graduate student machine.
- Modified
a perforated floor tile in the synchrotron computer lab to fit over
mismatched subfloor pedestals.
- Installed
pre-release version of system monitoring, reporting, and notifying software
on ldas-kickstart.
- Debugged
some issues between users and LSCrenewCert
script and reported findings to Junwei Cao.
- Worked
with Mary Lei to get the tandem 4 development system running required
parts of LDAS.
(Erik Espinoza)
-
node297 crashed during
weekend, replaced cpu's. Repeat crash during week,
found bad memory. Currently offline.
-
node125 crashed during
weekend, replaced power supply. Currently online.
-
node167 crashed during
weekend, network related crash. Rebooted and put back to service. Currently
online.
-
node151 crashed during week,
replaced 3ware card (raid array disappeared while running). Currently online.
- Modified
kickstart nfs
configuration to async for higher performance.
- Specified
monitoring system for purchasing, asked Larry to put in order
- Recently
tested kickstart on node297, kickstart
brings machine to current configuration automatically.
- Searched
online for system monitoring solution, have narrowed down to three. Will
evaluate on test systems:
-
Zabbix
-
Big Sister
-
Argus
(Stuart Anderson)
- Helped
with LDAS-CIT RAID system crash and Gigabit Ethernet performance problem.
- Copied
all of the S4 L1 RDS frames into the cluster for faster access by Condor
jobs including tuning of NFS parameters for improved performance.
- Attending
Solaris 10 class to learn new OS features, e.g., dtrace,
zones.
MIT
(Keith Bayer)
- Received
80 1URM nodes from Caltech.
- Receive
4 4URM pcraid units from Caltech.
- Cluster
is partially down due to moving racks around etc.
Livingston
(Dwayne Giardina)
- Email
configuration changes on FC4 machines with GC interface.
- CreateRDS errors were found to be caused by incorrect
'H' in an .ini file,
- corrected by Lisa.
- Configured
LDAS FC4 machines for a centralized syslog on ldas-gridmon.
- Stopped
sendmail on ldas-grid until
we create appropriate aliases to significantly reduce bounced emails
Hanford
(Greg Mendell)
- At
the request of the calibration team and for h(t)
generation downstream, the sample rate of LSC-DARM_CTRL_EXC_DAQ for H1,
H2, and L1 in the S5 Level 1 RDS frames was increased from 4096 Hz to the
full raw sample rate of 16384 Hz at GPS time: 824862720 = Feb 25 2006
00:31:46 UTC = Feb 24 2006 16:31:46 PST = Feb 24 2006 18:31:46 CST. An elog about the change was made at LHO and LLO. The
users of the channel were consulted and emailed about the change.
(Ben Johnson)
- Brought
4 nodes back on-line.
- Helping
Xavi restart h(t)
publications.
- Attending
Solaris 10 training class.
General Computing (Wallace)
MIT
(Keith)
- Copying
data off of lancelot for older accounts
- Investigating
imap on Solaris 10
- Investigating
PAM/LDAP/imap+pop+sendmail on Solaris 10
Livingston
(Dwayne)
- Completed
script for NIS
group changes. It is usable, but
would like to tweak it before passing it out.
- Kantec related errors with new gate. Errors possibly stem from kantec upgrade back in September. Never tested this scenario until
today. Going to research kantec site, or contact Chuck Brannon if needed.
- Used
Christian's unattended XP install DVD to reinstall FRAMEGRABBER PC. Not all software was installed /
registered due to license issues before I left for vacation. Lisa has reclaimed this PC. Other than some post install Adobe
Acrobat issues, it was smooth sailing.
- Other
usual user requests and support
(Shannon)
- I
got pulled into a discussion about the ilog
performance. So, I have spent a
fair amount of time determining where the bottlenecks are in the ilog. It is a
bigger issue at LHO, but performance is slightly lacking at LLO also.
- Had
a machine that would spontaneously power off, then
would not reboot. Turned out that
the overtemp setting in the bios was set to 68
degrees celsius.
The setting was a bit to conservative and
would cause the machine to shut down.
- Working
on pulling a bunch of archived files off of a raid controller and a couple
of disks. The files need to be
restored onto media that is more accessible.
- Still
working with Sun to try and get a support contract purchased. This has turned into a difficult
process. I now have a direct number
to someone who can place the order, but we are playing phone tag. Buying a support contract has never been
this difficult before.
- Working
on some paperwork issues with the Pcard folks
from last year.
- Dell
is claiming that a system purchased on a credit card was not paid
for. I will have to dig up the
records to show that it is already paid.
- Spent
some time troubleshooting some network issues. Turned out that it was LSU blocking
several class A subnets, they claim because of DoS attacks.
Most of the people at LSU were not even aware of the blocking, so
it took a while to figure out what was going on.
- More
of the usual... Hardware orders, digging through IDS logs, etc.
Hanford
To be reported next week
CIT
(Christian)
- Installed
Microsoft Visio 2003 for Julie H.
- Configured
loaner laptop with the Ligo image. Out most of the week on a family
emergency.
(Mike)
- Problems
with the DCC SQL Server. There seems to be two bad hard disks, this server
does not have LED lights that would let us know which drives have failed.
This server is being worked on a daily basis, which does not give me the
time to shut this server down to run diagnostic tools on each individual
hard disk (16) to find out which drives are bad. I tried doing this while
the server was running being that it is hot-swappable, and ended up
corrupting the OS. I had to restore this server from a ghost image. This
took a lot of work to get the two servers talking again. This is an older
server and Larry has decided to replace this server.
- Loaded
a new Dell PC for Mike Smith to test out his engineering packages before
we make an attempt to transfer over his data from his old workstation to
this box. This required me to load many engineering packages.
- Ran
end of month ghost backups on all critical NT Servers. My ghost server ran
out of disk space. I ended having to install an additional hard disk to
move data over to make room for the rest on my backups. I have started burning some of these
images to DVD.
- Continued
work on the Spam Filters searching for false positives.
- Other
misc. user/phone support.
(Veronica)
- LSC: Ongoing support of the March meeting
website and applications. Addressed
several issues related to the online credit card payments. Website updates. Addressed the issues of bouncing e-mail
addresses from the lsc-all, some were due to an
outdated address and others were being relayed to a blacklisted address.
- LIGO: Website updates. Worked on a few video editing
projects. Working on the website
for the Elba meeting. Prepared the information from the LSC
roster database for the DCC. Taped
a video of a seminar and made DVDs for the TAPIR group.
- CaJAGWR: Taping
/video processing of the last seminar, website updates.
(Bruce)
- (BS)
iLog Software and Policy Development: (2/13 5.0
days)
-
Ongoing discussion with sites about requirements for
new version of iLog.
-
Addition of the Quick Post capability.
-
Implementation and testing of new iLogPost
routine for robot posting to the new version of iLog. Discussion of same with sites.
-
Debugging of the gnats setup for an iLog
PR system.
- (BS)
iLog Software and Policy Development: (2/20 4.0
days)
-
Finished iLogPost and
completed testing on it. Distributed
-
Input of all old emails regarding new features and bugs
in iLog into new iLog gnats
PR system.
-
Ongoing discussion with sites regarding what to
prioritize.
-
Checked and closed out some of the PRs
which had already been fixed in the new version.
- (BS)
iLog Software and Policy Development: (2/27 5.0
days)
-
Much testing of iLog
performance problems at LHO. Discussion
with Hanford of
possible source and solution of this problem.
It has been decided to install iLog in a
faster dedicated server at this point.
-
Work on the auto thumbnailing
of uploaded images by iLog (PR 16).
-
Work on "Today" button issues (PRs 14, 18, 22).
(Larry)
- The
continual process of purchasing continues. Ordered a number of items for
different groups as well as items that are supported by the GC group. Still working on the CISCO contract.
Trying to get a local dependable vendor to do the contract renewal.
Presently, getting suggestions from others on Campus on the vendors they
are using. Placed an order for two
new servers to replace the DCC and the PDMworks
systems.
- Received
the dual core quad cpu
system back from Monarch. The system now reboots itself every 2-4 hours.
The OS has been updated but did not improve anything. I will be installing
another OS to see if that resolves the issue. So far the Monarch support
people have not been able to offer any assistance. They did at least reply
to my e-mail request this time.
- Restored
a user file system from 1999. This restoration reminded me how slow things
can be. It took about 12 hours for the system to go through the three
tapes and restore the files. Hopefully, the project of getting the old
tapes updated can get started this year.
- Most
of the backups on the user accounts are finished. Then on to the system
files. Had to modify the scripts
again, in order to handle the increase in the size of the data on the home
accounts.
- Working
with Hiro on the performance issue with the dual
core quad CPU systems. I've updated
the FC4 OS and applied the latest patches. With that Hiro
was able to narrow down where the problem may be. Evidently, the problem is with a
specific module in the E2E program that he is running. We are checking to see if there may be a
cache or buffer issue along with the possibility of a compiler version
problem, on that specific machine.
- Working
on debugging a wireless problem Riccardo has
been having in his office. It now
looks like it may be just the location of his desk is where the signal
gets blocked.
- Resolved
a number of small h/w problems for different people, bad monitor,
corrupted disks, bad memory...
- Assisted
in the webcamXP setup with Carol W. This time it
appears to have worked without any problems. We've found that if there are
going to be a large number of people connecting (20+) that the server unit
should have a wire connection and plenty of memory.
- Continual
work with the spam filters. Mike and I went through a list of items to
make sure we are on the same page when checking the filters. The number of spam messages getting
through the filters has increased quite a bit the past few weeks.
Mail statistics for Feb 23- Mar 01, 06
|
Mail Statistics
|
March 2, 2006
|
|
Rejected Messages
|
26,981
|
|
Virus Messages
|
588
|
|
Accepted Messages
|
28,541
|
|
Total Messages
|
55,522
|
Advanced LIGO and Supporting R&D (Shoemaker)
second draft of the
Advanced LIGO Systems
See
also:
AL Systems
web page
AL
Systems email archives
Records of Decision or Agreement (RODA)
See also the RODA
status web page
A RODA (M060032-00)
to eliminate the photon actuator from the baseline, and rely upon the
electrostatic drive, has been issued for review and signatures.
Requirements/Design
Working on conceptual design of the vibration isolation of the in-vacuum ISC
reflected and pick-off port table (primarily for the purpose of costing the
system).
Interface Issues
See the "Interfaces" section of the AL Systems
web page
Helping Carol Wilkinson to review costing, schedule and
planning in preparation for the NSF AL review.
Vacuum Compatibility
Residual Gas Assay (RGA)
See also the Vacuum
Bake Lab
Last week, I worked with The Suspension group at MIT. I cleaned and began two bake jobs of Quad
parts for Helena and Calum. Today & Friday, I will start scanning
those bake jobs and do some more oven cleaning.
Scatter/Absorption Test Measurement System
Lee Cardenas, Liyuan Zhang, Bill Kells
We have encountered with another situation!! and a
bad one, because the laser aperture cooling body started leaking
and we had to stop the laser.
We had this situation before and we fixed it after we had weld the edges of the body. Now, we decided to get a new one since this
part it is a SS body and to weld it, it is hard. We found
out from the manufacture that the new body also leaks!! Good thing I have requested to be tested and
pressurized before send it. We'll get this unit tomorrow and
be able to replace it and re-align the laser again!! and hopefully
recover the previous signal output from the test mirror.
High-Irradiance, Contamination-Exposure Cavities
Lee Cardenas, Liyuan Zhang
Changes indicated in yellow highlight.
|
Cavity
(Location)
|
Material/Item
|
Start
|
End
|
Comments
|
|
Cavity
#1
(OTF Lab, Bridge)
|
“Cable
wire” (material type?)
|
~11/17
|
TBD
|
Taking measurements daily. We noticed that the laser power is going down. We
may have to do a small re-alignment to recover the previous power output.
|
|
Cavity
#2
(OTF Lab, Lauritsen)
|
NA
|
NA
|
NA
|
We continue working on setting up the system
|
|
Cavity
#3
(OTF Lab, Lauritsen)
|
OSEM Flexi-circuit cable,
qty ~ 45
(Helena Armandula,
SUS)
supplied
by Univ. Birmingham (Stuart Aston)
|
~9/30
|
TBD
|
taking daily absorption & ring down
measurements
DuPont Flexible
Circuits. The whole part to be constructed of 'flexi' i.e. no 'rigid'
sections. (Stuart Aston,Univ. of Birmingham,
SUS/UK subsystem)
- Start Laminate: Kapton (LF8515)
(document link: http://www.dupont.com/fcm/products/H-73244.pdf
Coverlay
(x2): Kapton (LF0110)
(document link: http://www.dupont.com/fcm/products/H-73245.pdf
DuPont Pyralux Series - Kapton /
Acrylic Adhesive system.
(document link: http://www.dupont.com/fcm/products/H-73246.pdf
|
|
Queue
Priority
1
|
2
Cleaned 50ppm transmission mirrors, 1 in dia.,
REO coated --
|
TBD
|
TBD
|
witness
samples for the LHO vertex volume (added in 6/29/2005 vent)
|
|
Queue
Priority
2
|
Stepper
Motor (Riccardo DeSalvo,
possible SUS or ISC use)
|
TBD
|
TBD
|
Stepper Motor sample had been placed into Cavity #1: Power
dropped from 175 mW to ~25 mW
after introducing the stepper motor sample, and continues to decrease. It is very
hard to keep cavity locked. The stepper motor may have contaminated the
mirrors. Will re-test when a cvity becomes
available again.
To be rebaked soon using the
self-heating capability of the stepper motor (not just the oven heater
controls)
|
Seismic Isolation
BSC Seismic Isolation
Procurement
The stage 0-1 and stage
1-2 springs have returned from heat treating. The machine shop
made them .004" oversize in thicknes and are
now grinding them to their finished size within .0002".
A cart has been designed
and is being built to bring in all the large parts vertically from our dock to
the assembly area in the high bay. The three stage 1 plates will be delivered
next monday with this
rolling cart.
The instrument housings
have been delivered to Joe Giaime in Livingston. They will be assembled, tested, and filled
with trace gas in Livingston.
All fasteners and other
off the shelf hardware has been ordered this week.
From: "Joseph A.
Giaime" jgiaime@ligo.phys.lsu.edu
Agenda for the weekly SEI telecom Friday, Feb.
24, 2:30 pm Eastern, 1:30 pm Central, 11:30 am Pacific time
Announcements
Single Stage HAM - Joe -
model by Corwin
- We need more info from Corwin
to get Brian the input he needs; Brian will contact Corwin with a
list. It remains to make WAGS between 10 and 100 mHz.
- Also, we need to give Brian a
definitive set of noise floor data for the HEPI platform.
BSC SEI status, Ken/
Dennis
- Two stage 0 plates received
from Arland.
- All stage 1 plates are done,
and will be shipped next week.
- Displ sensor target material (1100
Al) can't be obtained in the thickness requested. So, Ken will
redesign both the post and the target to work with a thinner target.
- Log entry from Ken on
platform assembly scheduling. Some issues:
- We might need a place to park
the SUS when it is not on the 'dummy' and not under the SEI.
- We will probably want to
schedule a test of the SEI, in the BSC, in vacuum, with dummy masses
without the SUS connected to it.
- We should compare Brian's old
list of SEI sys-id /commissioning tasks (from the critical review) to
evaluate which things go in which periods of Ken's schedule.
- The blade test fixture from
ASI requires more study in order to make the modifications for the new
blade lengths.
BSC work, adaptive
modeling and FIR (Rich M)
- See Rich's entries in yesterday's
LASTI log, which show the latest adaptive feedforward
results on BSC HEPI, plus a new try at tilt correction on the BSC using a new
(but unexplained) tilt coupling model.
- We should start working with
Rolf to implement the adaptive feedforward in
LIGO hardware. Perhaps it could be tested at LASTI in the next few
months and considered for installation at LLO in half a year.
ETF platform work, tickle
testing, thermal testing – Matt
Frame damping - Tarm
- Constrained layer damping
parts mostly gathered, awaiting the Soundcoat
damping epoxy, which will be used to glue it all together.
- Thermal testing report in SEI log entry.
Putting more power in the coil than is used in operation, a small
temperature change is seen (only) right at the actuator mount point.
We need to calibrate the power being deposited in the actuator coil during
these tests for next week's report.
- Next: the frame damping test.
- Tickle testing experiment:
largely done and working.
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
Advanced LIGO Suspensions
Went to
LASTI Feb 15-22.
The quad suspension was delivered to MIT the second week of February. With the
help of Rich, Ken, Myron and Brett, the US SUS folks installed the structure
components onto the rigid stack on the test stand, re-suspended the masses and
installed the osems and cabling. Some more LED
failures, which are being investigated. Worked on tablecloth
cover issue with Calum & Mark.
With
Rich and Ken, worked up a schedule for the SEI and SUS work at LASTI for the
next 10 months.
Attended Carol's NSF preparatory
meetings but am just getting down to the details of the work. Will meet with she and Dwight tomorrow on schedule and cost.
Made
plane and conference reservations for LSC. Working on the SUS Workshop schedule and
location. Considering the Shilo
Inn in Richland on March 23 to save commute time
as some folks have early afternoon flights out of Pasco.
From: Ken Mailand kmailand@ligo.caltech.edu
I'm dissembling and
starting the part cleaning process on the plate fixture I spoke with Bob on
scheduling. CES is adding modifications before the steel parts are plated. Also for Calum, I'm
working on a smaller table option.
From: Jay Heefner jay@ligo.caltech.edu
AdLQuad SUS Controls
- Design and sent out for fab the new ADC and DAC adapter cards needed for the
PCIX I/O chassis to be used in LASTI. This required the redesign and refab of of the AA and AI
interface boards. These have been redesigned and sent out for fab. All boards are due next week.
- A new timing interface board
is also required. This board should be designed and out for fab by Friday.
AdL SEI ISI
The new Capacitve Position Sensor chassis has been received and
assembled. This is the chassis that will eventually be mounted near the vacuum
flange on the BSC. The signal conditioning and interface board for the sensors
has been designed and is awaitng layout. The power
board is complete and has been successfully tested with the ADE sensor boards.
The backplane for the chassis is 75% complete.
Core Optics
From: Helena Armandula ahelena@ligo.caltech.edu
Advanced LIGO Coatings
Started
the testing of First Contact, a strippable coating material that protects and
cleans mirrors.
Optical absorption evaluation and FTIR testing are being conducted at this
time.
There is a paper by Jean
Bennett, from the Naval Air Warfare Center in China
Lake, and Daniel Rönnow, "Test of Opticlean
strip coating material for removing surface contamination". It describes the testing of this material for
residue that could produce scattering after the film was peeled off from the
mirror surface. No residue that produced scattering was found. (Applied Optics, Vol.39, No.16; June 2000 -
Pages 2737-2739)
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
The Xilinx
DSP adventure continues with their web support personnel apparently deciding to
contact their technical support staff. Still no joy on
this front, despite cc-ing the technical support
manager. Given the rate of progress thus far, it may have been
faster to use an XT.
The update to FY2006 of
the PSL costs is nearly complete. All the critical labour
estimates have been revised.
Auxiliary Optics
From: Michael Smith <smith@ligo.caltech.edu>
VERTEX LAYOUT
The BSPO and REFL beam
were routed to HAM3.The new ZEMAX layout has been incorporated into the SW
vertex layout and placed in the PDM Works vault. I have begun to layout the 2K IFO in Zemax.
SLC
Hiro is still working on obtaining
transfer functions for scattered light noise in the ADLIGO RSE configuration
with the optical spring effect.
Controls, Data Systems
From: Rolf Bork
<rolf@ligo.caltech.edu>
- Working
on revised cost estimates; waiting on some numbers from Szabi on Atomic Clock data for the timing system (by
Friday).
- Continuing work on the code
infrastructure for Lasti. In particular, we are
working on getting the entire infrastructure, including DAQ and GDS, to
operate at any rate (2^^n ) up to 128KHz (latter
eventually required by the Ponderomotive
Experiment).
- Updated the Ponderomotive experiment CDS document after meeting
with Nergis. A draft is located at the bottom of
my web page under "Lasti CDS docs".
There are also links there to the Lasti CDS
overview and Lasti suspension controls docs.
Other Laboratory R&D
From: Riccardo DeSalvo desalvo@ligo.caltech.edu
For additional information about this report, contact Stan Whitcomb or Phil Lindquist