Weekly Report for Week Ending February 23, 2006



Due to the Staffing Committee Meeting scheduled February 27, 2006, there will be no LIGO Executive Committee meeting that day.


Special Announcements:


Weekly Report Highlights:

See Commissioning Highlights and L1 Interferometer in S5 concerning sensitivity improvements.


LSC Issues (Saulson)


***Just a quick reminder to make your room reservations soon for the March LSC meeting. The block of rooms reserved at the Hampton expires on the 24th, and at the other hotels there's only a bit more time.

LSC policy on seeking unpublished external data 21 Feb 2006, based on discussions at LSC Executive Committee meeting 17 February 2006

It may be that an ongoing gravitational wave search by the LSC shows a potential signal of a kind where electromagnetic (or other non-gravitational) observations might shed light on whether or not a signal is real. If so, the relevant Search Group should present the status of the analysis to the Detection Committee.

The Detection Committee should promptly evaluate the status of the analysis, in order to determine whether the gravitational wave data have been examined with sufficient completeness, care, and rigor. If so, and if it would aid the process of determining whether or not the apparent signal is legitimate, then the Detection Committee should recommend that the LSC seek information from external observations.

If such a recommendation is made by the Detection Committee, then the Search Group will be authorized to make appropriate contacts with scientists who have access to relevant data, or who can perform observations that can produce such data. Discussions with outside scientists should be carried out jointly by the leadership of the Search Group and by the LSC Spokesperson.

In such contacts, the outside scientists should be told that the inquiries are of a preliminary nature, and should be asked to keep both the request and its details confidential. Receipt by LIGO of external observations in this way, and/or significant assistance in the interpretation of external observations, is a significant contribution to the analysis in question and those responsible for the observations and their interpretation in this study will be offered authorship in publications that materially benefit from that assistance.

The recognition that data is useful in one specific case should also prompt consideration of whether it would be valuable to set up a collaborative research relationship on an ongoing basis.  If this is deemed to be valuable, then a data analysis proposal should be formulated and submitted through the ordinary LSC process.  The appropriate MOU with outside parties can then be negotiated.


LIGO Laboratory Administration (Lindquist)


STATUS OF LSC MOUs (Lloyd)

LSC MOUs and Research Plans and Progress Reports

  • No report this week.

SITE TELECONFERENCE (Lindquist)

A brief site teleconference was conducted Thursday, February 23, 2006.  Most of the issues discussed are addressed below:

  • Property—request for a new van for Livingston has been submitted.  The GSA was checking today and would report status.
  • Inventory at HanfordAn  inventory is scheduled at Hanford  the first week in March.
  • There are no open assigned actions.  The list of assigned actions updated through December 1, 2005 (the last time that it was updated) will be found Here.

PROPERTY MANAGEMENT (Luna)

>From: Rod Luna <rluna@ligo.caltech.edu>

  • Provided assistance to the Detector Group  (H. Armandula) with packing and shipping of three circuit boards and one cable to MIT (M. Barton), Account Number LIGO.PRLAS - 5.16 - NSFLIGO.FY02CA.
  • Provided assistance to the Detector Group (R. DeSalvo) with packing, shipping, and preparation of a Commercial Invoice for US Customs Clearance of  three Fused Silica Substrates to VIRGO, France.  Account Number LIGO.LFNS- 5.11- NSFLIGO.FYO2CA.
  • Prepared and send out inventory list for Hanford (J. Worden).
  • Tagged 2 Computers and 1 Printer.

DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

  • No report.

>From: Cleveland Mak mak_c@ligo.caltech.edu

Week Ending

February 23, 2006

In

Out

Packages

13

8

Faxes

12

19

  • Processing 2005 Travel Expense Report files.
  • Began processing approximately 40 HAM drawings recently submitted by PROMEC.
  • Update on Scanning--Progress continues on scanning of contract closeout files.

Finance and Accounting (Cunningham, Brambila, Kaufman)

>From: "Cronin, Holly" <Holly.Cronin@caltech.edu>

>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

  • Completed Invoice Attached orders for payment of invoices and assisted in resolving various issues with invoices.
  • Completed the reimbursement for LLO staff and submitted the invoice for payment.
  • The foreign draft for Gennaro voided earlier has been re-issued as a bank wire per vendor's request and the transaction completed.
  • Responded to inquiries pertaining to LIGO's vehicles at the sites. Working on coordinating the change of name and address on the Title for the LLO trailer.
  • Have several orders pending completion once the invoices are received.
  • Reconciled the charges billed to my credit card to date. Followed up on the status of a pending credit for the return of merchandise made to Tech Systems. The vendor will be posting the credit to my card. An erroneous charge billed to my pcard has been removed.
  • Completed change order #33 to GSI for the annealing samples and submitted it to the vendor.
  • Completed change order #3 to LSU for the ethernet monthly line charge and submitted it to the vendor.
  • Followed up on pending deliveries of orders that have long lead times.
  • Waiting for additional information on the University of Michigan to complete the change.

>From: Florence Kaufman <fkaufman>

SUBCONTRACTS MANAGEMENT (Jasnow, Salone)

>From: Gina Salone <gsalone@ligo.caltech.edu>

  • Nothing significant to report.

>From: Ed Jasnow <jasnow@ligo.caltech.edu>

  • A Request for Proposal was issued on February 22 for the design of the kinetic facade for the Livingston Science Education Center.  Proposals are due on Friday, March 3.
  • Petty cash accounts in the amount of $200 are being established at both sites.  The respective site administrators will be the custodians.
  • Finalization of plans for the relocation of the LDAS equipment at LLO is nearing completion.  Issues remaining are space for the Exploratorium exhibits and possible storage space for Advanced LIGO.

SUPPORT (Baldon, Hiroto, Lloyd)

>Irene Baldon

Worked on the usual new trips, expense reports, reconciling, calendar reservations, and itinerary entries.

>Julie Hiroto

  • A new order of Outreach brochures has been delivered.

>Dorothy Lloyd

  • No report.
  • Jim continued with data entry in the LIGO database and helping out in the DCC.

PROPOSALS and REPORTS (Lindquist)

See Advanced LIGO below.

CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)

  • Change Request CR-050010, Prototype Seismic Attenuation System for the HAM Chamber (HAM-SAS) was submitted by Dennis Coyne.  If approved, the change request will add the fabrication and test of a predominantly passive, seismic isolation system prototype for the HAM chamber, to the Advanced LIGO R&D program.  A LIGO Change Control Board has been scheduled for Wednesday, March 1, 2006.  Members of the Excomm are invited to participate in the discussion.

HUMAN RESOURCES (Akutagawa)

>From: Cindy Akutagawa <cindy@ligo.caltech.edu>

  • The next Staffing Committee meeting is scheduled for Monday February 27, 2006 and the DRAFT agenda for the meeting has been posted.
  • All files for the Staffing Committee are up-to-date and posted.

Quality/Safety (Tyler)

>From: Bill Tyler tyler@ligo.caltech.edu

The safety audits of the LIGO campus labs were recently completed.  Generally, the LIGO labs seem to have improved their safety practices and are doing much better in their "housekeeping."  However, a few safety concerns were identified that require additional discussion and corrective action.  All of the labs need to continue their efforts to dispose of unneeded/obsolete materials and equipment (not just a once-a-year task).  The draft audit report will be available next week for comment/revision..


LIGO Hanford Observatory (LHO) and Interferometer Operations (Raab)


Summary of Commissioning Activities at LIGO Hanford Observatory  (compiled by M. Landry)

Commissioning Highlights (F. Raab)

The visitors and resident staff who participated in the LHO commissioning break deserve a lot of praise. Not only are the sensitivity improvements strikingly good, the method was quite impressive as well.  People showed up in strength, we had good preparation, and there was great cooperation. Although we did not get nearly the 30 percent duty cycle for science mode operation that we had hoped for, the interferometers were returned to science mode for at least a few hours just about every night.  This helped ensure while people slept that the improvements in one area had not severely broken things elsewhere.

One of the consequences of the commissioning effort was the discovery that reducing flow rates in the HVAC system had dramatic effects on the attainable range of the detectors.  Obtaining stable temperatures in the LVEA and VEAs under this new operating condition will take some time and require gaining experience with what works and what does not work. This may cause some loss of duty cycle, since the varying lab temperatures require major realignments of the machines every time they lose lock.  However, a number of the commissioning changes have improved the ability to hold lock. We have some experience that we can run at higher powers during noisy daytimes than we could run previously during the quietest nights. We also have evidence that lock can be maintained at high laser power through high-wind episodes.  For these reasons I am hopeful that we will start to see improving duty cycles in the next few weeks as we get on top of the temperature-control issues.

Outreach (D. Ingram)

Recent activities have included a previously-mentioned exchange with Wapato Middle School and the LHO Open House.  Readers of the weekly who wish to subscribe to LHO's monthly newsletter can email outreach@ligo-wa.caltech.edu and write "Subscribe" on the subject line.


LIGO Livingston Observatory (LLO) and Interferometer Operations (Zucker)


MZ NOTE: A particularly intense week on L1.  More than our usual share of equipment glitches, but rapid (and creative) recoveries all round and a very welcome sensitivity improvement to boot.  Well done!

L1 Interferometer in S5 (O'Reilly)

L1 ran with ~58% duty factor in the past week. Major chunks of downtime resulted from a hardware failure of the Recycling Mirror satellite amplifier box on Tuesday and a thermal shift in the drumhead modes of the ETMs which resulted in downtime from Sunday morning to Monday afternoon. Range fluctuations seen on the Tuesday owl shift appear to have been due to a bad MMT3 optical lever laser.

On Friday we increased the power to 7 W and saw an immediate improvement in the range. We also reduced the air handler flow rates in an effort to see if they contributed to the noise. We saw no obvious effect from the flow rate reduction, however on Sunday morning the interferometer became unstable. This was finally traced to a shift in the eigenfrequencies of the drumhead modes of the ETM optics, which took them outside of their stopband filter. We believe this shift was due to wider temperature variations resulting from the reduced air conditioning flow rate. The flow rate was returned to normal and the stopband filter was also widened in order to avoid this problem in the future. On Wednesday we decided to run the air handler controllers in manual mode at a fixed current. This appears to be a more robust mode of operation than using the servo. The flow rate should be high enough to maintain temperature stability. We are a little surprised that the detector is sensitive to temperature shifts on the order of a couple of degrees C.

We replaced a faulty RM satellite amplifier box on Tuesday, the failure of which extended our maintenance period. We added the L1:LSC-ETMY_EXC_DAQ channel to the frames and also diagnosed the problem with the BSC5 ACCZ signal. This turned out to be an extra gain of 10 which was applied to the adjacent magnetometer channel in the .ini file.  This problem is believed to also affect the EX-BAYMIC signal.

During the Tuesday owl shift the Inspiral Range showed variations on the order of 1 Mpc with a period of ~45 minutes. This was apparently due to fluctuations in the MMT3 optical lever laser. The laser was replaced, but due to high microseism we have not yet returned to a 12 Mpc range.  Until we do we cannot say definitively that the problem has been fixed.  Smaller variations also appear in some of the other optical lever sums.

There was some investigation of the "mystery" noise. Excitations of angular degrees of freedom at micro-seismic frequencies did not show any increase in the 50-100 Hz region. However, excitations applied to the HEPI POS_X and POS_Y signals resulted in a distinct enhancement of the noise in this region. It appears that the ETM motion is amplified in this region, perhaps by the tidal servo.

We reached a new sensitivity record during the week, 12.2 Mpc. This was chiefly due to the higher power and low micro-seism.

Safety and Security (Riesen)

no report

Outreach (Thacker)

Friday, 2/17, attended Math/Science Partnership Regional Meeting Saturday, 2/18, conducted teacher Professional Development for Southern University PD program Monday, 2/20, conducted LLO school visit; 81 middle school students + 12 adults Thursday, 2/23, conducted LLO school visit; Runnels School Honors Physics class Prepared material for each school visit; made reservations for various future school events Worked on education research w/ Lisa Szechter Prepared material for new wave exhibit

L1 CDS (Bogue)

  • working with Bruce Sears on ilog issues.
  • built a backup for the beamcentering servo.  This project ran into the same pci-X problem that Dave Barker is seeing elsewhere in CDS.  Although the specs for pci-X declare that it is backwards compatible with pci, the orientation of the port made it so you cannot plug in the spiricon card.  I called spiricon to see if they had a new model coming out.  They were unaware of the discrepency between their card and the pci-X standard.
  • did some troubleshooting on the framegrabber monitor setup.  The monitor was fine.  The cable is fine.  The framegrabber got rebuilt with a new os and the base computer changed, although not the video card, so I'm not sure where the problem was coming from.
  • continuing to work with Hanford on resolving the discrepencies between the channel configuration at the sites.

CDS software (Khan)

1) Worked with Doug Lormand on diagnosing problems with LVEA Weather Station.

2) Prepared a tutorial on 'How to Analyze LIGO Seismic Data using MATLAB and Ligotools'. The tutorial is designed to help SURF students get familiar with LIGO data archive.

Computing and Network Security (Roddy)

  • spent a bit of time looking at some IDS alerts that turned out to be false alarms.  Due to the particular machines involved, I was a bit concerned about them.  Turned out to be legitimate NFS traffic.
  • installed a couple of replacement servers in the racks.  These will replace some aging servers.
  • set up a couple of user accounts.
  • Opened a trouble ticket with the mathworks over a license issue.  An old defunct license would not release.
  • worked on a problem with Touro.  It would not allow NIS+ users to log on at the console, however it would allow login via ssh.  A reboot ended up fixing the problem.
  • usual rounds of backups, parts ordering, user support, etc.
  • still working with Dave on the LHO router.

Data analysis (Yakushin)

Storage/Condor/LDAS admin:

1) On Tuesday night the tape library got into an unstable state.  It was necessary to power cycle the library and reboot dataserver.

2) Downloaded LIGO-VIRGO simulation frames from MIT to LLO.

Data analysis:

Working on validating the new S4 simulation results (obtained on Burst MDC frames generated with V4 calibration) for LSC, APS presentations and paper.


Initial LIGO Detector Science & Engineering (Coyne)


No report.


40 Meter Interferometer (Weinstein)


IFO Commissioning

  • Osamu and Noriyasu measured the calibrated noise spectrum of the XARM, and the Fabry-Perot Michelson (FPMI). Measuring the XARM with POX 33 MHz, the noise floor is at ~ few times 10^-15m/rtHz with tuned up whitening gain. The FPMI, measured with AP at 166 MHz, is much noisier: the floor is at ~ 10^-13 m/rtHz. This is apparently due to noise at the demodulator. He will work on reducing this, and/or switch to demodulation at the AP at 33 MHz.
  • Osamu and Noriyasu refined the FPMI autolock script and tested it. They also are locking the DRMI routinely. Full lock in RSE remains a bit elusive; much work is required to reoptimize all the servos with the new laser. In progress.
  • Osamu and Noriyasu were stymied by problems in using dtt to take spectra and transfer functions (timeouts, etc). Probably due to time synch problems. We need Alex to fix this.
  • Monica is working on measuring the shot noise contribution to the DARM noise. She needs more DC signals into the LSC system and will work with Ben on that. She's also working on measuring the optical lever noise. She will try to measure the noise at the AP, in the FPMI or PRFPMI configuration, and calibrate to m/rtHz using Osamu's method.
  • We have a new A/C unit in the control room, which is now cooling the laser chiller effectively (as well as making the room more comfortable for humans). The MOPA temperature servo can now do its thing, and MOPA_HTEMP shows constant temperature at 18.55+-0.03 degree. The chiller water stays at 20deg. So we're out of the woods with the laser temperature fluctuations, which were making it impossible to operate the interferometer.

IFO Modeling

  • Monica's e2e model of the full 40m configuration now holds lock for many seconds, using Osamu's seismic noise block.

DC detection development

  • Steve has sent the new in-vac mounts for the DC readout beam line to the shop for re-machining.
  • Ben reports that his in-vac photodiode mount for the DCPD is fully fabricated, including the PEEK parts. He machined several of the parts himself in order to make them in an expedient manner. The entire mechanical assembly is now finished.
  • Ben is working on the DCPD satellite box schematic and the testing of the head electronics.
  • Ben is working on a list of the remaining electronics boards needed for the DC readout controls.
  • Sam Waldman is working on the DC readout in-vac steering mirror PZT driver schematic. He has ideas for many improvements on the current design, and will work with Jay to make a board. He needs a laser to test is ASC system (and we also need one to test the OMC and other aspects of the in-vac DC readout beam line).

Electronics, Controls, Computers

  • Electricians installed two new cable trays to route AC cords, requiring less long extension cords. This was an issue raised during the safety inspection.
  • Alex configured the network and network yellow pages service on op540m, so it can be used now to run Epics screens, etc.
  • The EPICS vacuum controls still have problems that need Jay's attention.

Lab Infrastructure

  • Royal Reinecke will be SURFing at the 40m this summer. She is starting by characterizing Mike Smith's long awaited oplev telescope. She just went through the standard 40m safety training with Steve.
  • Steve notes that we don't have adequate monitoring of the temperature in all the relevant locations (control room, IFO hall, PSL enclosure, and even in the vacuum chamber). This requires some attention to PEM-type channels in EPICS.
  • Steve continues to research cooling solutions for the new maglev turbopump.

Thermal Noise Interferometer (Black)


Installation of the ring dampers is proceeding according to plan.


LASTI (Ottaway)


No report.


Data Analysis and Computing (Lazzarini)


Simulation and Modeling (Yamamoto)

Mechanics modeling  (S.Yoshida)

Continued comparison of AdvLIGO HAM and LIGO 1 HAM seismic isolation performance putting LIGO 1 MC on the HAM tables. There are questions about the ground motion used for this simulation, and have not obtained conclusive result yet. Started to consider ground yaw motion using LIGO 1 HAM stack box.

40m model (M.Varvella)

The full power in the cavities (power recycling, arms) has been maintained for more than 6 seconds with a servo loop on for all the degrees of freedom and the radiation pressure on for arms mirrors.  Problems occur when a seismic motion is added: still under investigation. The open loop transfer functions of the all degrees of freedom are in progress.

Static IFO Simulation (H.Yamamoto, M.Araya)

Still building infrastructure. Based on the discussion at the last COC modeling, the first version of SIS will calculate fields with completely static mirrors. This will show the optical resonance, but not the optical spring resonance.

e2e weekly meeting (Hiro, Osamu, Monica, Sany)

Hiro gave a tutorial about the FUNC_X coding.  (/home/e2e/public_html/ME2ET/060223/T040005-Addendum.pdf)

Data Analysis Activities (Lazzarini)

Brown:

Started full coincidence analysis of S5 BNS search for first epoch of S5 (Nov 4 to Feb 6).  Added data quality flags and Q-scans to S5 online BNS glitch pages.  Repaired and restarted online BNS searches after disk crash at LHO.  Continued to review S3/4 inspiral analysis.  Wrote LIGOLwMon DMT monitor to allow output from generic XML data (e.g. GRB alerts) to be displayed in the control room.  Made changes to LSCdqInsert requested by Keith to allow easier administration of DQ flags.  Installed new server certificates in segment database replication engine.

Chatterji:

  • Performed a preliminary study of Q Scans and online Q Pipline triggers around the time of GRB060218 (password required).

http://ldas-jobs.ligo.caltech.edu/~shourov/qscans/grb060218.html

  • Added segment and data quality information to Q Scans.
  • Continued Q Pipeline analysis of S5 data for the March LSC and April APS meetings.
  • Provided feedback on current draft of coherent network analysis paper.
  • Provided triggers for LIGO/Virgo study of network detection efficiency in coincident burst searches.
  • Provided support to Duncan Brown for adding QScans to the summary of loudest single detector binary neutron star inspiral triggers.
  • Send proposed modifications of the FrameL frgetvect mex function to Benoit Mours

Lazzarini: Wrote a technical note describing the effect of finite angular resolution antenna pattern on the pixel statistics of a spatially resolved stochastic background map.  see http://www.ligo.caltech.edu/docs/T/T060027-02.pdf

Mendell:

I am still working with Mike Landry to analyze the pulsar hardware injections in the S4 data, and waiting for the final set of S4 SFTs to be generated to begin a production run of the StackSlide code.  I hope to have some results to report within a week.

Shawhan:

  • Defined a number of data quality flags based on S5 second trends.
  • Updated segwizard to display S5 data quality information from daily dump of the segment database.
  • Checked S5 WaveBurst high-threshold triggers against available data quality flags.
  • Updated the metaio core code and LIGOtools package to build properly on 64-bit machines, and to provide 32-bit and 64-bit MEX- files simultaneously on the LIGO Lab clusters.

Sutton:

I wrote a test version of a ring finder function for the coherent analysis pipeline.  This function examines sky maps from our "xpipeline" and looks for the rings that are characteristic of linearly polarized GWBs.  When it finds the rings it can get good pointing accuracy (<1 degree), but it often misses the rings, so this remains an open problem.  I've also been systematically editing and debugging the NetworkSimulator codes, as Maria Principe and I prepare a paper on this software package.

Yakushin:

Working on validating the new S4 simulation results (obtained on Burst MDC frames generated with V4 calibration) for LSC, APS presentations and paper.

LIGO Data Analysis System

Software Systems (Maros)

LDAS

A new option allowing the setting of the md5sum output directory based on the output directory (PR#2953) for createRDS commands has been finished. This does include documentation and regression tests.

To support 64-bit compilation, the 8.4.12 version of TCL has been tested on tandem-ii. Although some jobs could complete, there are several problems that need to be addressed before this version can be used by LDAS. The getFrameCache command causes a memory leak in the diskcacheAPI which eventually causes the restart of the API.  Several of the APIs running under Linux core dump when a job is submitted twice in a row.

To support large files, the 4.0.2 version GCC has also been tested on tandem-ii. LDAS appears to run well with this version of the compiler. The current limitation is that it is unable to compile Globus Toolkit 4.0.1 under Linux.

System tests were done on ldas version 1.8.86.

TCLGlobus

Efforts continue to resolve the memory leaks within the XIO-based Tcl channel interface.

It has also been noted that the default timeout for the XIO-based Tcl channel interface is too short. The code is being modified to have it be a tunable parameter via the fconfigure command.

GRID COMPUTING

Site TACC (Texas Advanced Computing Center, UT Austin) authenticates with a LIGO VO member proxy. Due to TACC being down, no further tests have been conducted.

UIOWA supports the LIGO VO and 921 DAGs of a 943 DAG work flow were completed before the Globus resources on UIOWA went down.

All nodes in the OSG-ITB test bed have been yum updated.

Working with Alex Sim, the LBNL SRM/DRM development lead, we determined that the version of srmcp in the VDT has a bug preventing interoperability with SRM/DRM on the LIGO testbed and has filed a bug report. Alex delivered an older version of the srmcp client package and configuration of that package has begun on the SRM  testbed.

Hardware Systems (Anderson)

Caltech

(Dan Kozak)

  • Worked on recovery of down /archive filesystem at LHO.
  • Did the weekly receiving/ingesting of tapes from the sites.  We're now caught up on ingesting.
  • Set up dataserver-test to mount /archive and /scratch.
  • Compiled lists of tapes for shelf storage at LHO & LLO.
  • Got archiving of /home started at CIT & LHO.  Am monitoring to tune various intervals associated with this.
  • Worked with Igor to sort out the _very_ confused L700 tape robot at LLO.
  • Fixed some staging problems at LLO.

(Phil Ehrens)

  • Working on the upgrade of the tandem-4 system to Solaris 10 Update 1 and FC4. The cd-rom drive in ldas-suntest4 was bad as were two of three spare scsi cd drives that were available.  The scsi dvd drive was removed from ldas-suntest1 and transferred to ldas-suntest4.
  • Placed correct version of 3ware raid tools into /ldcg/stow_pkgs for use in new 64-bit opteron cluster nodes.
  • Various grid certificate management duties.
  • Assisted LDAS developers with various development and configuration issues.
  • Did general cleanup of synchrotron equipment room.
  • Further documented Solaris 10 setup procedures. Added new script for grabbing all disk partition info into a single file.

(Erik Espinoza)

  • Kickstart changes

-         Added virtual interface eth0:1 on 10.9.0.0/255.255.0.0 subnet.

-         Created /usr1/frames.

-         Changed fstab to use dataserver-cluster for /archive/frames & / home.

  • Troubleshooting nodes

-         node151 - fs corruption, recovered journal and put back in service.

-         node323 - replaced motherboard, back in service.

-         node297 - motherboard replaced, running memtest.

-         node106 - rebooted machine after memory related crash, back in service.

  • Added wiki for 3ware CLI Rebuild Instructions.
  • Requested CPU grease from ASA.
  • Received information from temptrax for temperature monitoring system.
  • Tested all hardware from RMA in "ldas-pcdev2".
  • Tested WD2500YD Hard drive in different rebuild scenarios.

(Stuart Anderson)

  • Helped with major SAM-QFS/Solaris upgrades at LHO.
  • Working on problem when attempting to delete 12M files in one command.
  • Received first RMA request for the new Opteron cluster to replace some of the early component failures.

MIT

(Keith Bayer)

  • Duct work finished - will get the operators guide and a run down on the unit next week preparing to shutdown the cluster so we can move it out of the way of the new nodes coming in on Monday.

Livingston

(Igor Yakushin)

  • On Tuesday night the tape library got into an unusable state. It was necessary to power cycle the library and reboot dataserver.
  • Downloaded LIGO-VIRGO simulation frames from MIT to LLO.

Hanford

(Greg Mendell)

  • Since last weeks LDAS downtime at LHO, RDS generation and transfer of RDS data from LHO to CIT has caught up, as has data archiving and publishing. All LDAS services are running again at LHO.

(Ben Johnson)

  • Users were allowed back on the cluster on Monday the 20th.
  • Grabbed new image of node2 with system imager. Presently installing on newly networked nodes.
  • Publishing scripts are now all reading from a single frame.cache file.
  • Fixed some broken LLO->CIT transfers. The cause appeared to have been RLS errors.

General Computing (Wallace)

MIT

(Keith)

  • Working on building Solaris 10 mail server / perhaps with POP and IMAP.  Will investigate UW-IMAP to see if it integrates well etc.
  • Finished Solaris 10 integration into LDAP
  • Spec'd and purchased laptop for professor
  • Spec'd and purchased new fairly cheap linux compute server (Dual Opteron 265 w/ 8GB Ram from Genstor for $2800)
  • Tried to make an older desktop machine run quieter for a disgruntled user

Livingston

(Shannon)

  • Spent a bit of time looking at some IDS alerts that turned out to be false alarms.  Due to the particular machines involved, I was a bit concerned about them.  Turned out to be legitimate NFS traffic.
  • Installed a couple of replacement servers in the racks.  These will replace some aging servers.
  • Set up a couple of user accounts.
  • Opened a trouble ticket with the mathworks over a license issue.  An old defunct license would not release.
  • Worked on a problem with Touro.  It would not allow NIS+ users to log on at the console, however it would allow login via ssh.  A reboot ended up fixing the problem.
  • Usual rounds of backups, parts ordering, user support, etc.
  • Still working with Dave on the LHO router.

Hanford

(Christine)

  • Setup another new laptop for a user.  There are two more new laptops on order and I have two more old laptops to re-build and add to the loaner pool.
  • Lots of purchasing this week, including external USB hard drives for users, more hard drives and batteries for the loaner pool laptops, video server for the auditorium, software upgrades and replacement laptop carrying case.
  • The modems are not working since they were connected to the new phone system.  Did some additional testing and discovered that they do work, but only at 9600 baud instead of the 115200 baud.  Still looking at what needs to be done to fix this.
  • Continued build of the latest MRTG and RRD to display network usage.

CIT

(Mike)

  • Loaded an Engineering workstation with GC software, plus Solid Works. This workstation is for Dennis Coyne's group to test out before we push these workstations out to Engineers who are running Solid Works.
  • Finished up loading an IBM laptop for Rod Luna; I have also transferred all his data, including e-mail from his workstation to this laptop.
  • Ghosted a couple of workstations, and one laptop.
  • Called in a Dell computer that is having problems with hard disk over heating. They are sending out a replacement drive.
  • Continued work on the Spam Filters searching for false positives.
  • Did an inventory on printing supplies with Christian.
  • Backed up Barry Barish's laptop before he took off to India. This went well now that his hard disk has been replaced.  I have also sent back his damage hard disk to IBM.
  • Setup electronic signature for Ed Jasnow. This is a bit tricky on how to set this up on Adobe 7.0  I will have to write up a "Cheat Sheet" on this.
  • Other misc. support that included restoring data, printing, and a few networking issues.

(Veronica)

  • LSC:  Ongoing support of the March meeting website and applications.  Assisted Irene in resolving the issue of duplicate transactions.  Updated the database of participants.  Working on a webpage for the LSC presented talks.
  • LIGO:  Security patches of the Windows servers.  Working on the website for the Elba meeting.  Encoded the footage off a DVD into a stream.  Updates to the LIGO website.

CaJAGWR:  Taped and compressed the video of the last talk.

(Christian)

  • Finished transferring all of Ed's file and setting to new system.
  • Replaced toner cartridges on the HP 5500 printer. The printer is getting service this week after getting many paper jams.
  • Replaced toner cartridges and Drum kit on the HP 2550 printer.
  • Installed SolidWorks 2006 on two different engineering systems for testing purposes.
  • Continue working on troubleshooting a wireless problem found on the third floor of West Bridge.  Other misc.: Continued onsite software/phone support.

(Larry)

  • P-card reconciliation took some time still waiting for one last invoice from Dell.  The dual core quad CPU unit from Monarch computers has finally been repaired and shipped back to us. We should receive it in the next couple of days.  Monarch has had the machine since the first of December. Getting any communication from them has been difficult at best. The only reason I know it has been shipped is because of the FEDEX notice that I have received and was able to track it back to Monarch.  Ordered a number of misc. items for different people. Still working on the h/w configuration for the new PDMvault server to be ordered.  Working on the CISCO maint. contract.
  • Setup a number of new mail aliases. Removed a couple of old accounts. Still working on the list of accounts to be removed from the system.
  • Updated the E2E FC4 server to see if the performance would improve but no luck.
  • Took care of a couple of printer issues. It looks like we need to purchase a new printer for Millikan. They have basically worn the unit out.
  • Assisted Mike in resolving a couple of e-mail issues.
  • Working a couple of logistical issues for the upcoming LSC meeting at Hanford.
  • Continued usual user support and spam filtering work.

Mail Statistics for Feb 16-22, 06

Mail Statistics

February 23, 2006

Rejected Messages

29,335

Virus Messages

597

Accepted Messages

23,253

Total Messages

52,588

 


Advanced LIGO and Supporting R&D (Shoemaker)


From: David Shoemaker dhs@ligo.mit.edu

The NSF will perform a Baseline Review of Advanced LIGO at MIT, May 31-June 2. This milestone will allow the NSF to supply the National Science Board with the information they need to judge Advanced LIGO’s readiness for funding in Fiscal Year 2008.

Advanced LIGO Management

From: Phil Lindquist <lindquist_p@ligo.caltech.edu>

Advanced LIGO Review Preparations (Lindquist)

The following documents have been prepared and distributed:

Positions Summary List - The first step in preparing for the Advanced LIGO Review is to review the Positions Summary List to check whether the projected positions are consistent with expectations and needs.  We also need to know what positions will be required to support continuing Operations activities through the Advanced LIGO Construction effort and what positions will be available to help with Advanced LIGO.  Task managers were requested to review and respond by February 17.  A limited number of responses have been received.

LIGO Operations Budget Model (FY 2006 - FY 2008) - This file is a full detailed budget projected through FY 2008.  It assumes that funding will be level at $33 million in FY 2007 and FY 2008.  Operations Task Managers will be requested to review and update as needed.

Projection of Advanced LIGO Operations Costs - This model projects budgets through 2014 (steady state Advanced LIGO Operations) including a summary of increments that were provided by task managers for the June 2003 NSF Review.  These estimates have been escalated to FY 2014 dollars.  We will request a review and update by the Operations Task Managers.

Project Execution Plan - A strawman draft Advanced LIGO PEP was distributed last week for review and update.  I am requesting responses by March 3, 2006.  An update of the Organization and Staffing sections was distributed this week.

From: Dennis Coyne coyne@ligo.caltech.edu

Advanced LIGO Systems

No report this week.

Seismic Isolation

From: Ken Mason <kmason@ligo.mit.edu>

Advanced Ligo Seismic Isolation Procurement Status

The two large Stage 0 plates have arrived from Arland Tool. After the quad controls prototype is installed, we will set up a rack in the LASTI high bay to store the large parts.  We anticipate all parts for stage 0 to be here by 3/1 to start assembly.

We met with Arland Tool to discuss delivery of remaining parts. The Stage 1 plates scheduled to arrive on 3/1 will fit through the elevator if held crated vertically.  The stage 2 plates which are aproximately 1500#s each will need to come in through the overhead door. Arland has offered to take their fork truck with them when they make the delivery to help us.

From: "Joseph A. Giaime" jgiaime@ligo.phys.lsu.edu

Agenda for the weekly SEI telecom

Friday, Feb. 24, 2:30 pm Eastern, 1:30 pm Central, 11:30 am Pacific time

Announcements

Single Stage HAM - Joe - model by Corwin

  • We need more info from Corwin to get Brian the input he needs; Brian will contact Corwin with a list.  It remains to make WAGS between 10 and 100 mHz.
  • Also, we need to give Brian a definitive set of noise floor data for the HEPI platform.

BSC SEI status, Ken/ Dennis

  • Two stage 0 plates received from Arland.
  • All stage 1 plates are done, and will be shipped next week.
  • Displ sensor target material (1100 Al) can't be obtained in the thickness requested.  So, Ken will redesign both the post and the target to work with a thinner target.
  • Log entry from Ken on platform assembly scheduling.  Some issues:
  • We might need a place to park the SUS when it is not on the 'dummy' and not under the SEI.
  • We will probably want to schedule a test of the SEI, in the BSC, in vacuum, with dummy masses without the SUS connected to it.
  • We should compare Brian's old list of SEI sys-id /commissioning tasks (from the critical review) to evaluate which things go in which periods of Ken's schedule.
  • The blade test fixture from ASI requires more study in order to make the modifications for the new blade lengths.

BSC work, adaptive modeling and FIR (Rich M)

  • See Rich's entries in yesterday's LASTI log, which show the latest adaptive feedforward results on BSC HEPI, plus a new try at tilt correction on the BSC using a new (but unexplained) tilt coupling model.
  • We should start working with Rolf to implement the adaptive feedforward in LIGO hardware.  Perhaps it could be tested at LASTI in the next few months and considered for installation at LLO in half a year.

ETF platform work, tickle testing, thermal testing – Matt

Frame damping - Tarm

  • Constrained layer damping parts mostly gathered, awaiting the Soundcoat damping epoxy, which will be used to glue it all together.
  • Thermal testing report in SEI log entry.  Putting more power in the coil than is used in operation, a small temperature change is seen (only) right at the actuator mount point.  We need to calibrate the power being deposited in the actuator coil during these tests for next week's report.
  • Next: the frame damping test.
  • Tickle testing experiment: largely done and working.

Suspension

From: Calum Torrie ctorrie@ligo.caltech.edu

Bob Taylor, Mark Barton and I are completing the assembly, suspension and alignment of the quad c-ptype at MIT. We are working with Ken, Myron and Brett at MIT. Janeen was also here earlier in the week.  As you can see it is fully assembled and suspended. We have just completed aligning all of the stages. The next step is to install all of the osems and magnets.

You can follow progress at http://thread.mit.edu/view/index.shtml

Calum Torrie (and Bob Taylor)

From: Ken Mailand kmailand@ligo.caltech.edu

I've completed a load test on the plate style fixture, in the CES in the shop, I will disassemble and start the part cleaning process. I will get the steel plates plated asap after they are de-burred and prepared.

Also for Calum, I'm working on a smaller table option, to use the fixture inside the LASTI BSC chamber, minus the bridge and circular track assembly.

Core Optics

From: Bill Kells kells@ligo.caltech.edu

I spent 4 days at LHO observing scatter from the 4 TM HR surfaces of H1. For each TM the scatterometer was mounted at one of the VP observation points which had previously been used for this purpose. The idea was to compare to those previous measurements (c. mid '03 last) to determine any systematic change in scatter (contamination).

First the relative (amongst the 4 TMs) conclusion:

Taking ETMy as benchmark, the observed scatter ratios for ETMy:ETMx:ITMx:ITMy were = 1: 2.6: 1.6: 0.84 (note, since the observation points were different for different TMs these are NOT relative scatter losses). This is to be compared to the same ratios for observed scatter at the same VPs taken in 2003: 1: 2.0: 1.34: 0.63.  The largest ratio change since '03 is ETMy: ITMy which is now observed to be ~25% less. Note that ETMy: ITMx (the replaced ITM) also appears to scatter less, but only by ~16%. The "untouched" ETMs now have a ~23% different scatter ratio.

Now the absolute scatter level:

Previous ('03 and earlier) measurements used a PD in the scatterometer telescope which had been carefully absolutely calibrated. However I discovered in the  midst of last weekend's measurements that this PD had been removed and a different (less sensitive) model substituted. The nominal PD manufacturer specs. indicate that the new PD is 2.6 times less sensitive at 1064. Taking into account that the ifo input power (H1:IOO-MC_PWR_IN) is 6.6 times higher now (wrt previous '03 meas.) and the arm cavity "boost" (H1:LSC-LA_PTRX/Y) is about 25% higher now, there remains an absolute discrepancy factor ~2.6 (lower now) in observed scatter if it is assumed that ETMy (above benchmark) has not changed.  My best guess is that the nominal Manufacturer spec. ratio 2.6 is highly inaccurate. We will test this.

Note that the ifo performance (that is the overall recycling gain) is consistent with the only modest decrease in relative scatter/loss. By this I mean that a cursory trend study of arm cavity "boost" over the last 3 years seems (but this may be subject to much interpretation) to indicate an optical gain increase of ~20-25%. This is inconsistent with the nominal large (> factor 2) decrease in nominal absolute scatter/loss.

Pre-Stabilized Laser

From: Peter King pking@ligo.caltech.edu

I have been updating the PSL costing, as per the meeting last Thursday.  A number of things have changed since the original costing was done; manufacturers making products redundant being one.

Still no joy with regard to communicating with the Xilinx DSP board.  The Xilinx technical support person assigned to the case is off on holidays.  In using a much older computer to talk to the DSP board, a problem with one of the examples was encountered.  Although the software routine correctly identified the card and its address, it failed to successfully boot the on-board FPGA.  This might be an issue with which version of Matlab is used, although I somehow suspect not.

Auxiliary Optics

From: Michael Smith <smith@ligo.caltech.edu>

VERTEX LAYOUT

Following a suggestion by the IO group, the BSPO and REFL beam were routed to HAM3. This frees up all the view ports on HAM1 for IO control signals.

The new ZEMAX layout is being incorporated into the SW vertex layout.

SLC

Hiro is still working on obtaining transfer functions for scattered light noise in the ADLIGO RSE configuration with the optical spring effect.

Other Laboratory R&D

From: Riccardo DeSalvo desalvo@ligo.caltech.edu

Valerio, Virginio

We have completed our 3D simulation of HAM-SAS mechanical structure. One of the most important features of this model is the introduction of saturation effects due to distributed masses and the moment of inertia and counterweight. Saturations can, in principle, compromise the overall attenuation performance of the passive attenuation system. The results obtained from the simulation look quite promising. The predicted attenuation performances are met with a large margin above 2Hz and below 200 mHz with a good safety margin. The methods and approximations used in the model and the results obtained are described in detail in the Technical Note T060037-00-R.

At the same time we are evaluating a new mechanical simulation tool for evaluation of effects of asymmetries, integrated in Maple symbolic environment, that is called DynaFlexPro.

Yumei

  • Writing the report of the Q factor tests of the IP.
  • Simulating a resonant damper in ANSYS Classic.

Anamaria, Riccardo

Studying the behavior of glassy metal blade GAS springs.


For additional information about this report, contact S. Whitcomb or P. Lindquist