Weekly Report for
Week Ending February 16, 2006
Due to the holiday we will not schedule the LIGO Executive
Committee meeting February 20, 2006.
Special Announcements:
Weekly
Report Highlights
No report.
LIGO Laboratory Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
LSC MOUs and Research Plans and Progress Reports
SITE TELECONFERENCE (Lindquist)
A site teleconference was conducted Thursday, February 16, 2006. The following were among the issues
discussed:
- Budgets—Reviewed under run for first four months due to
positions that have not been filled yet.
The under run mounts to on the order of $100K distributed over
several accounts. We therefore proposed
to defer a change request; to be reviewed again at the halfway point (end
of March).
- EXCEL
Subcontract—have tried to do our best to get all the pieces
together so that we can pay invoices; did experience issues with
communication. EXCEL may have to
reissue invoice.
- Plan
for LDAS Equipment in Livingston—tentative plan is to build
structure inside storage bay area, but this plan is still being
"annealed." $12K costs
for moving HVAC and for new ductwork.
Livingston on a crash program to
get the computers moved by the end of March from the area to be used for
the Group B Exploratorium exhibits.
- Property—request
for a new van for Livingston has been
submitted. Reportedly GSA is short
on vehicles in Louisiana.
- Inventory
at Hanford—An
inventory is scheduled at Hanford
the first week in March, 123 items, list to be provided.
- Volunteer
Docents at Sites—All will be covered by Caltech insurance policy
for Workman's Compensation. Docents
will have to sign forms that have been provided by Caltech to the site
heads.
- There
are no open assigned actions. The
list of assigned actions updated through December 1, 2005 (the last time
that it was updated) will be found Here.
PROPERTY MANAGEMENT (Luna)
>From: Rod Luna <rluna@ligo.caltech.edu>
- Assisted
Livingston (A. Sibley) in requesting a Vehicle upgrade from GSA.
- Coordinated
the disposal of old computers, monitors and Lab equipment. Account Number
LIGO.OPT-5.4-NSFLIGO.FY02ON.
- Provided
assistance to the LDAS Group (S. Anderson)
with coordinating the shipping of 3 computer racks to MIT (K. Bayer)
Account Number LIGO.DAT - 1.5.1- NSFLIGO.FY02ON.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
Document Management System
Ran several reports of sub-menus in our current to determine the number of
documents associated with each and determine whether or not certain fields will
be carried over to the new system and used for historical documents only or
integrated into the new system.
Discussed the idea of further dividing each category into
sub-types. The benefits of this would be to further define the
appropriate profile input for that document and make searches more tailored at
the front end. With this in mind, most
categories were divided into 3-6 sub-types.
Additionally, a couple of new categories were identified: forms, and
budgets/financial.
Began to identify "groups" within a group, ie.
Detector Group represents subgroups of Suspension, Seismic Isolation, etc. . . This is to
support the group collaboration environment as well as further define document
uploads.
Purchased and installed OmniPage Pro 15. This newest version provides a batch process that will OCR all PDF formatted documents
into text searchable documents. The only
thing that needs to be thoroughly investigated before setting up the batch runs
is to ensure that the program recognizes those .pdf
files distilled from native files that are already text recognizable since the
accuracy of that is superior to overriding with an OCR program. I spoke with the company's technician and
supposedly the program can tell the difference between .pdf
flies that are image versus text, so we'll set up a test environment in some
way to confirm this before handling our actual electronic library.
Interviewed several staff members from different areas of the project to
determine if there are any unique fields in their sections that would make
searches effective, ie., serial numbers in the electronics group, etc. These are being combined with fields already
standardized for all the categories and will be treated as not-required fields
in the appropriate categories of documents on upload.
Continued to refine the conversion requirements document
as the information gathering continues.
Hopefully this will be ready for distribution to the committee for
review by the end of February.
>From: Cleveland Mak mak_c@ligo.caltech.edu
|
Week Ending
February 16, 2006
|
In
|
Out
|
|
Packages
|
25
|
7
|
|
Faxes
|
18
|
15
|
- Processed/distributed
5 DCN's.
- Began
processing of 2005 Travel Expense Report files.
- Scanning
Project – continue to scan contract closeout files.
COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Completed
the change order to Ares for the two subtasks for the LIGO Hanford
Observatory. The change order has been completed.
- Followed
up on the status of deliveries and long-standing orders. I am still
waiting for a definite ship date on the custom actuators which we are
hoping to ship within the next week.
- The
website address for Procurement was changed this week, so I've made the
changes on the terms and conditions forms which are sent to the vendors so
that the correct web address is referenced.
- After
several follow-up phone calls, received the long awaited credit for the
sales tax billed for Hanford
on the Sun invoice. The payment for the invoice was processed yesterday
and paid.
- Working
on correcting the registration for the trailer purchased for Livingston and adjusting the associated costs.
- Completed
the close out of the Planning Systems subcontract. Received the signed
Release of Claims and closed the file.
- Working
on completing the change order to LSU to reflect the time period of the
MOU.
>From: Florence Kaufman <fkaufman>
- Completed
and sent out reports for DIA, Site Discretionary Accounts and Visitor
Award.
- Prepared
and submitted 3 Cost Transfers to transfer expenses to the recently
created fabrication accounts for DAQ and ISCCA.
- Prepared
and submitted Cost Transfer to relieve small overspent amount in the US
India Award so that the Award could be closed.
- Spent
some time trying to understand and resolve issues related to some recent
Excel invoices to ascertain whether the procedures that had been set up
regarding submittal of Work Orders had been followed. Determined that the Work Orders had been
prepared and submitted correctly, however the problem was that 2 of the
Excel invoices did not show the contract amount correctly. Allen Sibley is to request revised
invoices so that payment can be made.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- Construction
of the LLO Science Education
Center is on
schedule, with completion of the steel structure. Opening ceremonies remained scheduled
for sometime in November.
- A
Request for Quotation is being prepared for the design of the kinetic
facade for the LLO SEC. This design
was originally going to be done in-house, but the departure of the staff
member assigned to this task has made it necessary to contract out this
effort.
- Plans
are still in development for the movement of the LDAS equipment at LLO to
its permanent space. Currently, the
plan calls for construction of a framed facility inside the storage
bay. This re-plan was caused by the
determination of a structural engineer that the second floor of the
staging building would not support the load of the racks of computers
planned to be housed there.
- An
agreement with Human Resources has determined that authorized or approved
volunteers who are used as docents at both sites will be covered under
Caltech's umbrella insurance policy.
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
Worked on the usual new trips, expense reports, reconciling, calendar
reservations, and itinerary entries, as well as pulling the last of the 2005
trip files for permanent storage with DCC and setting up 2006.
>
No report.
>Dorothy Lloyd
- Processed
the usual requisitions, payment requests and invoices. Reviewed and
recorded invoice payments processed during the period December 5 through
February 10.
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
PROPOSALS and REPORTS (Lindquist)
See Advanced LIGO below.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
- Change
Request CR-050010, Prototype Seismic Attenuation System for the HAM
Chamber (HAM-SAS) was submitted by Dennis Coyne. If approved, the change request will add
the fabrication and test of a predominantly passive, seismic isolation
system prototype for the HAM chamber, to the Advanced LIGO R&D
program. This request was discussed
during the normally scheduled meeting of the LIGO Executive Committee
scheduled on February 6, 2006. Held
pending additional information..
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- No special activities to report.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
No report.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of
Commissioning Activities at LIGO Hanford
Observatory (compiled by M. Landry)
We're now into our second and final week of our commissioning break, with
efforts to increase IFO range and stability in days/eves, and science-mode
running at night, before returning to the S5 run
proper on Monday Feb 20. The weekend of the 18-19 will be run in science
mode to assess stability after the many mods, and to
obtain and update calibration.
There has been an awful lot of really good commissioning work in the last
two weeks, and some of those entries are point out below. Early Thursday
morning, the 4k was running at a binary inspiral
range of 13Mpc for many hours, grazing 13.6Mpc briefly (integrating the 4k
design goal, one gets 13.9Mpc). At the same time, the 2k had run for most
of the evening at 7Mpc (integrating it's informal
goal, you get 8.8Mpc). 4k efforts were concentrated on improving
stability by i) increasing the bandwidth of the WFS
angular control, ii) reducing AS_I saturations, and iii) minimizing scattered
light in the QPDs. A major find was that
reducing the flow rate in the HVAC system improved the noise in both IFOs at the sweet spot near 100Hz. Work on the 2k is
summarized here,
and including improved frequency noise with more power on the REFL port,
modifications to the pick-off electronics, a new TCS mask, and a balancing of
the ASPD snr's.
4K IFO
- TCSY
intensity noise was found to impact
the 120Hz line on H1 AS_Q. The TCS photodiodes reported sensitivity
to jostling of the laser cooling tubes
- Coherence
between AS port accelerometers on ISCT4
and WFS1 suggests that the ouput table should be
floated, as is ISCT10 on the 2k. There, this coherence is minimal.
- Shutting
down the HVAC system improved the binary inspiral
range of both machines by a Mpc.
Later in the week it was noted that simply reducing the air flow rates in
the HVAC still gave significant
gains in inspiral range. We settled on
half the nominal flow rate, for the latter part of the week, yielding our
13 and 7 Mpc run of early Thursday morning.
- FSS
and common mode bandwidths were increased
- scattered
light in the QPD boxes in the end stations was dumped
properly, reducing pitch and yaw coupling into the error point
- WFS2A's
unity gain was brought to 5Hz
- a filter
was added to minimize a 47Hz peak in AS_Q induced by optical levers
- two
geophones per endstation were mounted
on crossbeams, part of new PEPI
2K IFO
- PRC->DARM
coupling appears to be reducing
the H2 binary inspiral range in the first half
hour of lock. Servo filters were modified
to add phase margin at 100Hz. Modifications to the POB/POY
whitening path brought the calibrated noise spectrum to the 2k
informal design goal around 90Hz. The 2k displacement noise now
cleanly surpasses
the 4k interferometers, due to it's larger cavity
pole and the recent commissioning efforts. Later, PRC and MICH gains were boosted.
- old
problems and old solutions: a mobile broad peak at several kHz is pushed
higher by leaving a rack door open
- gold
star masks were installed on the TCSY laser, and later the power
was optimized, increased, out of the table
- a
swap of the 2k PSL MOPA power supply indeed eliminated a 71.75Hz
line in AS_Q
Outreach
About 350 people attended our LHO open house on Sat Feb 11; Dale Ingram will
report next week on this very successful event.
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
LLO S5 Report (Brian O'Reilly)
We had a duty factor of 47.5% for the week with the major impacts being
commissioning activities and construction. We took advantage of the
commissioning break at LHO to work on our own detector. The main focus was work
on the HEPI system.
The Guralp seismometer at the X-end was found to
be in the wrong orientation. This was fixed on Monday.
The annulus ion pumps were found to not be responsible for our 60 Hz
noise. Excitation of the ETMX BSC end
cap showed that scattering from this source is not important at our current
sensitivity.
Several measurements of the WFS2 loop show a significant change in its shape
since November. This may explain some of our lock losses.
The 10th harmonic of 60 Hz seems to have become a lot stronger since Feb.
10th, no explanation for this yet.
On February 10th the L1 NoiseBudget reported a
range of 11.2 Mpc. We are eagerly awaiting the
ice-cream truck.
Vibrations (
- The
HEPI sensor correction STS-2 that failed or was thought to be damaged on
February 20, with the main symptom 240 Hz oscillation, is now known to be
the same one that exhibited the same symptoms in prototype tests last
year. Our seismic team will be more
careful in the future.
- The
Streckeisen vender has been contacted to discuss
repair procedures.
- The
engineer who has been carrying out seismic tests near LLO has been
contacted. The tests are complete,
and data exchange may be possible.
- Steel
work for the Science
Education Center
appears to be largely done. We
expect material deliveries to periodically interrupt running in the near
future.
Storage/Condor/LDAS admin (Igor Yakushin)
- on
Duncan's
request made it possible for users to run cron
jobs on ldas-jobs;
- created
user directories on ldas-pcdev1:/usr1 on Duncan's request;
- downloading
S4 Burst-MDC that were redone at PSU with the final calibration version
V4; copying these MDC frames on the nodes; these MDC frames will be used
in S4 burst APS and LSC presentations and the paper;
- installed ImageMagick on the
nodes on Shourov's request; 5) requested a quote
for extending our service contract for SUN equipment (expires on 03/31)
for another year.
Data analysis (Yakushin)
- Rerunning
S4 waveburst simulations on the new S4_V4
Burst-MDC frames in preparation for LSC and APS meetings and for the
paper; 2) Preparing the material for the reviewers (Feb 19 deadline) for
my APS presentation about the burst search results from the first few
months of S5.
LDAS (Dwayne Giardina)
- tapes
ejected to be shipped to CIT: LL0514, LL0588, LL0611, LL0870, LL1693,
LL1694
- tapes
imported into L700 library: LL1360-LL1365
- tape
drive 44 needed cleaning
- implemented
Ben's userprio script in cron
: 0 1 * * * /root/ maintain_userprios.py > /root/userprios.out
2>&1
- email
configuration changes on: beowulf, node1-210, datacon,
metaserver, dataserver,
ldas(gateway)
- yum
config changes and install sendmail-cf
on: datacon,
metaserver, beowulf
(required for mail config changes)
- failed
disk u1d7 in T3-6, replacement received from Sun
- Node131
crashed during mail config changes, rebooted,
required fsck.
will monitor closely
General Computing (Giardina)
- still
working on script to change NIS
group ids, it works fine, just tweaking it and adding additional features
- other
usual user requests and support
- mostly
tied up with LDAS this week
Network and computing (Shannon Roddy)
- Wrapping
up the router software install for Dave.
Will fedex this evening.
- Worked
on some LDAS email issues. Tried to
find a suitable alternative to a domain wildcard.
- Worked
on the color-front printer. Thought
I had it fixed, it broke again and I have given up on it. The printer is => 7 years old and
gets heavy use, so I have ordered a replacement. If it is at all repairable, I will
likely place it in the outreach area once repaired.
- Fixed
a couple of configuration issues on the spam filter over the weekend. We really need to get it wrapped up,
completed, and filtering.
- Working
on getting a support contract purchased from Sun to support the LDAP/Mail
server install. Have the quote,
have called several times, and haven't gotten the right person on the
phone yet for a credit card order.
- Installed
a couple of software packages by request on the general computing /apps
share. An old version of matlab was specifically requested, along with some
toolboxes, etc.
CDS Computing (Lisa Bogue)
- Installed
a dozen new monitors in the control room.
- Working
with hanford to get our
channel list fixed up.
- Still
working on the 3511 for fb0. At
this point I'm waiting for assistance from caltech.
Initial LIGO Detector Science & Engineering (Coyne)
CDS
see the CDS
weekly meeting minutes in the commissioning archives
DMT
No
report
40 Meter Interferometer (Weinstein)
IFO Commissioning
- Our
replacement MOPA pulls more current and runs much hotter than the old one.
The chiller is in the control room, and the air conditioning in the
control room is broken. So the chiller is working too hard, and can't keep
the MOPA cold enough. The PID servo loop has no headroom, and the MOPA
temperature (and power) is fluctuating daily. This causes the
interferometer control loop optical gain to vary, making it hard to
acquire and keep lock. Attempts by Steve and Peter King to turn down the
MOPA current have not been successful. We're scrambling to get the air
conditioning working in the control room, to give the chiller some help.
Meanwhile, we're worried that we do not have a spare MOPA....
- Dan
and Monica are making lots of progress on getting the noise budget code
working at the 40m. The program now runs, but does not yet produce
meaningful predictions. They will consult with Rana
when he gets back next week.
- Osamu
and Noriyasu are reviewing the digital controls
infrastructure and code; Noriyasu plans to build
a similar system for TAMA. They have measured the ADC noise and DAC noise;
they look pretty reasonable. the Pentek ADC has a broad peak (the Pentek
"hum") and large 60 Hz / harmonics peaks. The LSC whitening
board DC gain is too low to see detector noise; we need to implement a
low-noise "detection mode" electronics chain as is done at the
sites.
- Rob,
Osamu and Noriyasu have been working on
acquiring full lock, but found a bunch of new problems, preventing long
locks. Part of the problem might be the instability of the PSL due to the
chiller problems mentioned above. It looks like each of the servos need
careful retuning to be able to once again acheive
robust lock. Osamu will work on this while Rob is away visiting Seiji in Japan next
week.
- Once
robust lock is again acheived, Osamu plans to measure
a calibrated noise spectrum, including high frequencies (MHz). He will
also explore the RF and HOM content of the AP beam, in preparation for DC
readout studies.
- Mike
Smith has a prototype optical lever telescope. We will bring it to the 40m
and test it soon.
IFO Modeling
- Monica
continues work on her e2e control model for the 40m. The DARM loop won't
hold lock for more than a fraction of a second; she and Osamu believe that
this is because the other degrees of freedom also need to be controlled
well, so she's now implementing all of them. She cannot take a meaningful
transfer function without the servos working well for all five length
degrees of freedom.
DC Detection Development
- Rob
has drawn up a fairly detailed layout for the DC readout controls,
including all cables, electronics modules, front-end and EPICS channels.
He's got two stages: in the first, the oputput
mode cleaner servo will be an analog system using an SR830 lockin. In stage 2, the servo will be all digital, using a prototype new PCI-X computer. He's
working with Ben to design and/or acquire the electronics that we don't
already have in hand, including the DCPD satellite box and the OMC PZT
driver / summing box.
- Sam
Waldman continues the development of the tip-tilt PZT driver boards.
- Ben
reports that the DCPD boards are functioning well. The last rev of that
board will be sent out next week for fab.
- Ben
got the in-vac photodiode mount for the DCPD
back from the machine shop, and it looks great. He has delivered the PEEK
for some of the remaining parts, and they are being manufactured
currently. There are four small parts that remain, and he will machine
those next week.
- Rob
and Dan moved the QPD and camera for the SP beamline
to another place on the SP ISC table, to make room for staging and pre-aligning
the DC readout beamline.
Electronics, Controls, Computers
- Bryan Barr continues to work on a publication
describing the Mach-Zehnder solution to the
"sidebands-on-sidebands" problem, and the resulting noise
analysis.
Lab Infrastructure
- Steve bought a new maglev
turbopump to replace the old and failing one.
The new one requires cooling water. Steve is looking into quiet cooling
water supplies, such as the system used to cool our MOPA, or the system
used to cool the TCS at the sites.
Thermal Noise Interferometer (Black)
This week, Akira finished the last of the Q
measurements, and we opened the chamber in preparation for installing the ring
dampers.
LASTI (Ottaway)
No report.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Yamamoto)
e2e meeting on February 16th (S.Yoshida,
V.Boschi, V.Sannivale, O.Miyakawa, H.Yamamoto)
Sany summarized the current status of the SEI/SUS
simulation modules for adv.LIGO. There are simple BSC and HAM modules based on
typical table top spectrum of adv.LIGO. In addition to these toy modules, there are
two modules available, one from the active isolation group and the other from
the SAS group.
A BSC statespace module provided by Brian Lantz is
being tested, with some known issues to be resolved.
One is an anomalous peak in a low frequency region.
Valerio explained the current status of the
HAM-SAS modeling, with a comparison with the requirements.
There are some idealizations, like perfect symmetries which suppress the
coupling of translational to rotational modes.
Valerio and Virginio
will provide a statespace module of HAM-SAS (in a
month or two) which can be used in e2e.
The optics table top yaw motion is important to study the angular
instability. The principal source of the yaw motion, either group rotation or
stack translation to rotation coupling needs to be identified. Some strategies are discussed how to identify
using the LIGO I data.
Their viewgraphs are available in e2e home page (http://www.ligo.caltech.edu/%20~e2e/ME2ET/060216/)
SEI/SUS for adv.LIGO simulation (Sany Yoshida)
Continued the analysis of AdvLIGO HAM table-top
and suspended optic motion using the e2e box made recently. Created different
ground motions as input to the HAM box and computed the table-top and suspended
optic motion using a LIGO 1 small optic suspension box. The results are being
compared with the case when LIGO 1 HAM stack was used.
40m simulation with LSC (Monica Varvella)
The feedback system for the 40m model has been investigated for the DARM and
the MICH
degrees of freedom: an instability has been observed
around 0.3s and it doesn't depends on the optical spring; probably is due to
the influence of the other degrees of freedom like CARM. Under
investigation.
The DARM open loop transfer function has been simulated again with the servo
loop on (as the previous time) and adding a seismic noise; under this condition
the transfer function failed because of the instability of the control.
The 40m optical response has been simulated again using the transfer
function from the mirror displacement to the dark port: it gave an optical
spring peak around 30Hz with the demod phase at 90°
and it failed just before simulating the peak with the demod
phase of 0°.
Modeler (Hiro Yamamoto)
A new version of e2e simulation package, e2e-3.1.3, has been released. It has two major additions.
(1) It is easier to include c++ code file in FUNC_X. Each FUNC_X help text has a short description
about the syntax. With this modification, you can create a legitimate C++ file
(thus you can fully utilize language sensitive editor, like emacs)
and it can be included in FUNC_X by @@INCLUDE filename syntax.
(2) modeler_freq can have
frequency dependent amplitudes. This
makes it easier to analyze the frequency dependence when a gain is strongly
frequency dependent.
There are several minor changes and bug fixes, including the compatibility
with gcc 4.
SIS - Static (or Stationary) IFO Simulation (Hiro
Yamamoto, Melody Araya)
Basic tool developments are going on tfor the
static IFO simulation.
There was a discussion at the last COC modeling meeting how optical spring
effect should or need not be included in SIS.
Hiro talked with Yi Pan about this issue and
Yi will provide a formulation to include the optical spring effect in the
Stationary IFO simulation. Yi will talk
about this at the next COC modeling meeting.
Data Analysis Activities (Lazzarini)
Brown:
- Worked
on Fisher matrix formalism for LIGO EMRI problem.
- Looked
at problems in LAL spinning waveform code with Diego.
- Fixed
problems with the ringdown code that was causing
Lisa to see corrupted waveforms in software injections.
- Documented
set up of online BNS search and helping transition the BBH search to the
new code.
- Diagnosed
and fixed problem with data quality publication caused by a combination of
clock skew error at CIT and an accidental double insert at CIT and LHO.
- Helped
Stuart figure out a work around for users to run LSCdataFind
and LSCsegFind until the 64 bit version of Globus is installed on the new CIT cluster.
- Working
on a chapter on LIGO workflows for a book on grid computing.
- Wrote
a web interface to the segment database that allows Keith and segwizard to get a daily text dump of the data: http://ldas-cit.ligo.caltech.edu/segments/S5/
- Interviewed
by Ray George from the Globus consortium for
their newsletter. Provided use information by LIGO of the globus tools.
Chatterji:
Here are a few items for the weekly report:
- Upgraded
installations of QScan on LHO, LLO, and CIT
computing clusters. Installed QScan on LHO, LLO, CIT, and MIT general computing
machines as well as the PSU computing cluster. UWM installation is in progress. http://www.ligo.caltech.edu/~shourov/q/qscan/
- Introduced
the LSC Channel Wiki with the help of Phil Ehrens and John Zweizig. It is meant to be a central repository
for information on the large number of auxiliary interferometer and
environmental channels that are available in the full frame files. Everyone is encouraged to contribute. http://ldas-jobs.ligo.caltech.edu/cgi-bin/chanwiki
- Contributed
new figure explaining null stream construction to coherent analysis
paper. Validating probability
distributions of coherent and incoherent energies.
- Modified
frgetvect mex file to
be more robust against errors in reading frame data. At the same time, the resulting binaries
are more portable across varios Linux
platforms. I am working on
incorporating the new versions into LIGOTools
- Continued
Q Pipeline analysis of S5 data for the March LSC and April APS meetings.
Dupuis:
Mendell:
I have run more tests of the S4 StackSlide
pipeline and am working to finalize the configuration scripts, instrument line
files, and get the final set of S4 SFTs generated. I
am also working with Mike Landry to analyze the pulsar hardware injections in
the S4 data. I will present results to the pulsar group and the reviewers
before the March LSC meeting.
Shawhan:
- Finished
my set of SciMon shifts at Livingston
- Did
a number of data quality studies (influence of trains on glitches at LLO;
light dips)
- Restored
GEO to GWIstat display
- Fixed
some things in the conlog software
Sutton:
I spent most of the past week working out the statistics of our coherent
network analysis sky maps, and editing the paper.
Yakushin:
- Rerunning
S4 waveburst simulations on the new S4_V4
Burst-MDC frames in preparation for LSC and APS meetings and for the
paper;
- Preparing
the material for the reviewers (Feb 19 deadline) for my APS presentation
about the burst search results from the first few months of S5.
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS
Support for non-GSI Globus sockets has been added
to LDAS for testing the overhead of GSI sockets verses TCL sockets. This is
being done to better understand the drop of 200 jobs an hour that has been
experienced since using GSI sockets for the nightly testing.
TCL code to support having the md5sums in a different directory than the
generated frame files of a createRDS command (PR2953)
is being tested. The new option is -md5sumregexp and takes a sed like substitution command to manipulate the output
directory.
A memory leak in the manager was discovered this week when using globus based testing scripts. Investigations so far
indicated that it is an issue within the TCLGlobus
package.
Testing of LDAS using GCC 4.0.2 suite of tools has begun on tandem- ii. This
is necessary for large file support (PR#2135). At this point all code does
compile with the compiler.
System tests were performed using ldas version
1.8.86.
TCLGlobus
A new option to fconfigure allows the caller to
obtain the X.509 subject name on the server side. This allows an application to
gain information about the individual who established the connection.
A memory leak has been discovered in the open/close operation for xio. It is under investigation.
GRID COMPUTING
The site Texas Advacned Computing Centern (UT Austin, TACC) has agreed to support the LIGO VO
for prototype testing of the LIGO application (inspirals). As this may be the first LSF jobmanager the LIGO app has run on, TACC will demonstrate
the robustness of the Condor DAGMan to Globus/GRAM interface. Previous tests employed PBS and
Condor job managers.
The OSG-ITB test bed nodes have been yum updated.
Alex Sim, the LBNL SRM/DRM development lead,
delivered examples of srmcp commands and additional
configuration information required for interoperability when using the srmcp (client) code from FNAL with the SRM/DRM server.
Karan Vahi, a VDS
development engineer, announced support for an SRM Java Class library
integrated in VDS 1.4.4.
The VDT integration team has agreed to integrate VDS 1.4.4 into VDT release
0.3.10 for support of OSG release 0.3.5
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Helped
plan and execute a major CIT upgrade involving hardware movement in Booth,
Sol10 U1 upgrades, 3510/11 firmware and configuration upgrades, splitting
out the user home directories to their own filesystem
and upgrading SAM-QFS.
- Hooked
up fibre connection for dataserver-cit's
10.9 interface.
- Added
GEO to LDR time lag plot.
- Helped
retrieve 30A extension cords we'd used in Booth.
- Called
in and received hardware replacement 3510 disks, T3 disks and a 3510
controller.
- Worked
on recovery/upgrade at LHO similar to the CIT one (ongoing).
- Did
the weekly receiving/ingesting of tapes from the sites (ongoing).
(Phil Ehrens)
- Patched
the configuration files for the FC4 desktop kickstart
install rpm and tested it by upgrading the machine "couch".
- Assisted
transfer of computing hardware to MIT.
- Diagnosed
IDE controller failure of machine metaserver.ldas-test,
which has now been removed from use.
The machine beowulf.ldas-test will be
renamed metaserver and will run the mpi API as well as the usual metaserver
machine tasks.
- Numerous
grid certificate related tasks including adding inspiral
task users and making them usable by Duncan Brown and Eirini
Messaritaki on the ldas-cit
computing resources.
- Discussed
various LDAS related issues with the LDAS development team.
- Installed
and configured a wiki expressly for the purpose
of maintaining IFO channel descriptions and information.
- Various
documentation updates on the sysadmin wiki related to machine configuration and grid tasks.
(Erik Espinoza)
- Diagnosed
the following (new) nodes:
-
node192 - memory swap, returned to service.
-
ldas-pcdev1 - memory swap,
returned to service.
-
node288 - running memtest,
still out of service.
-
node297 - possible mobo,
still out of service.
-
node323 - possible mobo,
still out of service.
-
node106 - crashed at the time of writing, out of
service.
- Worked
with Phil to fix the FC4 Desktop kickstart:
-
Removed partitioning info, it now prompts.
-
Disabled auto reboot.
- Updated
wiki for mail configuration.
- Worked
with LLO to get mail working appropriately.
- Re-racked
the IDE raid rack for shipment.
- Spent
time researching monitoring systems.
- Writing
docs to replicate/explain ldas-kickstart.
- Looked
into proposed disk change (WD2500YD) from ASA.
(Stuart Anderson)
- Shipped
out 2 racks of 80 computers to MIT.
- Helped
with major software/hardware upgrade of the archive filesystems
at CIT and LHO.
- Continuing
to work on LSC application issues in 64-bit mode on the new CIT cluster.
Livingston
(Igor Yakushin)
- On
Duncan's
request made it possible for users to run cron
jobs on ldas-jobs;
- Created
user directories on ldas-pcdev1:/usr1 on Duncan's request;
- Downloading
S4 Burst-MDC that were redone at PSU with the final calibration version
V4; copying these MDC frames on the nodes; these MDC frames will be used
in S4 burst APS and LSC presentations and the
- paper;
- Installed
ImageMagick on the nodes on Shourov's
request;
- Requested
a quote for extending our service contract for SUN equipment (expires on
03/31) for another year.
(Dwayne Giardina)
- Tapes
ejected to be shipped to CIT: LL0514, LL0588, LL0611, LL0870, LL1693,
LL1694
- Tapes
imported into L700 library: LL1360-LL1365
- Tape
drive 44 needed cleaning
- Implemented
Ben's userprio script in cron
: 0 1 * * * /root/maintain_userprios.py > /root/userprios.out
2>&1
- Email
configuration changes on: beowulf, node1-210, datacon,
metaserver, dataserver,
ldas(gateway)
- Yum
config changes and install sendmail-cf
on: datacon,
metaserver, beowulf
(required for mail config changes)
- Failed
disk u1d7 in T3-6, replacement received from Sun
- node131 crashed during mail config
changes, rebooted, required fsck. will monitor closely
Hanford
(Greg Mendell)
- I
am assisting Ben Johnson to get LDAS services running again at LHO, during
downtime this week. During this down time I also assisted Robert Schofield
in obtaining PEM data for times when our 10 ton and 22 ton air conditioner
in the on and off states. Liebert, also took advantage of the downtime to replace on our
22 ton unit the plenum grill with a much heavier and stiffer version, a
variable speed pulley with a fixed speed pulley, and the default belts
with a smoother variety that run with less noise.
(Ben Johnson)
- Accidentally
deleted a /archive LUN. Recovery is still under way.
- Continuing
to debug the GEO segment publishing. I can manually publish segments, but
still no automatic publication from within LDR's
local storage module.
- Had
to perform two S5/L0 ejections this past week due to low tape space in the
silo.
- Working
on a way to have the publishing scripts read from a single diskcacheAPI query script. Lessening the load on diskcacheAPI and reducing the number of frame.cache files / day.
General Computing (Wallace)
MIT:
(Keith)
Livingston:
(Dwayne)
- Still
working on script to change NIS
group ids, it works fine, just tweaking it and adding additional features
- Other usual user requests and support
- Mostly
tied up with LDAS this week
(Shannon)
- Wrapping
up the router software install for Dave.
Will FedEx this evening.
- Worked
on some LDAS e-mail issues. Tried
to find a suitable alternative to a domain wildcard.
- Worked
on the color-front printer. Thought
I had it fixed, it broke again and I have given up on it. The printer is => 7 years old and
gets heavy use, so I have ordered a replacement. If it is at all repairable, I will
likely place it in the outreach area once repaired.
- Fixed
a couple of configuration issues on the spam filter over the weekend. We really need to get it wrapped up, completed,
and filtering.
- Working
on getting a support contract purchased from Sun to support the LDAP/Mail
server install. Have the quote,
have called several times, and haven't gotten the right person on the
phone yet for a credit card order.
- Installed
a couple of software packages by request on the general computing /apps
share. An old version of matlab was specifically requested, along with some
toolboxes, etc.
Hanford:
(Christine)
- Created
a couple of new user accounts for students of LSC members and for long
term visitors to the site.
- Finally
was able to renew my Cisco service contract. In order to just renew the contract
instead of buying a new contract from a Cisco partner, I had to be put
back on Larry's contract.
- I
have also finally been able to find a Cisco sales rep in Washington. He is coming to visit Thurs.
afternoon. He is a Federal
Government sales rep as there are no education sales reps in WA. I'm hoping because we are NSF funded he
will agree to work with me or find me someone else who will. I have been trying for 5 years to get a
Cisco rep on site!
- Both
upgraded and degraded Matlab. Installed the latest version 7 service
pack 3 on the application server.
Then installed the compiler toolbox for version 6.5 and used the
license file for 7sp3 so that users can compile with 6.5. I also purchased another compiler
license for a total of two.
- Started
setting up two new laptops. Still
working on getting the older loaner laptops up to date. Had to buy new batteries for all of them.
CIT
(Christian)
- Installed
and configured Webcam XP software for Carol
Wilkinson and Phil Lindquist.
- Millikan - Replaced toner cartridges on HP 5500
printer.
- Irene
Baldon - Recovered lost data from Irene's
workstation after she deleted the files from the recycle bin.
- Configured
new system with the engineering Ligo image.
- Ed
Jasnow- Recovered lost emails from Ed's system
after his computer crashed. I also created a backup of his system and I'm
working on transferring all of his settings and data to a new system.
- Upgraded
my workstation and transferred all of my settings and data. I'm also
creating virtual machine images for testing purposes.
- Other
misc.: Continued onsite software/phone support.
(Mike)
- Continued
work on the Spam Filters, searching for false positives.
- Setup
an Engineering workstation for Mike Smith to test Solid Works on.
- Loading
a laptop with all GC software for Rod Luna.
- Program
a new access point for W/B 3rd floor due to poor wireless connection with
our current access points. We have put this in place to see if this helps.
Christian gave me a hand running multiple tests on this unit.
- Added
additional wireless mac addresses to access
points, and removed old mac addresses that are no
longer being.
- Worked
on loading a Sun Blade 1500 with Solaris 9.
- Ghosted
two workstations.
- Swapped
out my workstation with a newer workstation that was not being used. This
is a big job, due to all the data I needed to move to the new workstation.
I should have this finished up today.
- Other
misc. work that included e-mail, and printing issues.
(Veronica)
- LSC: Finished the setup of the March meeting
website. Configured/tested an
account with authorizenet.com to accept online credit card transactions
for the meeting. Installed a script
to generate a list of MAC addresses of participants, per a request from
Christine. The website and its apps
are up and running. Updates of the
website of LSC papers under review.
- LIGO: Installed a new website for Advanced
LIGO, assisted Dwight Carter with its setup. Installed PowerDVD
and upgraded Windows Media Player to Cindy's desktop. Prepared high-resolution images for
various publications. Posted
updates to the LIGO website.
(Larry)
- Worked
on a number of purchases. Mostly small misc. items for different
people. Getting quotes for the
CISCO maintenance contract.
Delivered a number of procured items. Reconciliation took some time because of
the number of items. Still missing a couple of invoices.
- Started
on a Solaris10 setup. The upgrade from Solaris 8 did not work well and
went to a fresh install. Still some playing around to do to get a good
configuration going on the box.
Installed Solaris 9 on another box and assisted Mike in
troubleshooting a installation he was working on.
- Worked
on the calendar tool. The reminder tool needed to be restarted by
hand. Also, setup a few more
calendars for different people.
- Spent
time with Christian and Mike going over the Webcam
XP s/w. It looks to be a good temporary solution but it still has its
limitations. However, it does perform better than using VNC for most of
our applications of the pkg..
- Worked
a number of account issues. Along the same lines we were able to clean off
a few of the old accounts. Still a lot of work to do in this area.
- Worked
the spam filters. Some more changes need to be made, we are trying to make
it to where we don't have to check as often for false positives but not
let too much get through. Having the spam filters on the individual mailtool has been of some help.
Mail Statistics for Feb. 09-15, 06
|
Mail Statistics
|
February 16, 2006
|
|
Rejected Messages
|
29,443
|
|
Virus Messages
|
1,349
|
|
Accepted Messages
|
33,406
|
|
Total Messages
|
62,849
|
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Systems, Management
Systems
from Dennis
Coyne
See
also:
AL Systems
web page
AL
Systems email archives
Records Of Decision or Agreement (RODA)
See also the RODA
status web page
Requirements/Design
- The
HAM_SAS review committee expressed a concern that the cabling for might
act as an acoustic path which could compromise the isolation performance.
I performed an analysis that shows under reasonable assumptions and
parameters, the isolation performance should not be compromised. A
technical memo will be written.
- At
the weekly Optomechanical meeting, Mike Smith
reported on a new Zemax optical layout
incorporated into the SolidWorks 3D layout which
corrects cavity lengths and mirror positions
- Provided
guidance to the SUS/UK group on welding for in-vacuum structures, in
particular procedures to maintain cleanliness.
Interface Issues
See the "Interfaces" section of the AL Systems web page
- Nothing
significant to report
Vacuum Compatibility
Residual Gas Assay (RGA)
See also the Vacuum Bake Lab
Scatter/Absorption Test Measurement System
Lee Cardenas, Liyuan Zhang, Bill Kells
We have re-assembled the housing for the Quantronix
Laser. All the water leaks checked and
the laser is back in operation. Now we
are recovering the last test for the 1" mirror absorption and after few
trials we were able to recover ~ 50% of the previous measurement. (We are
aiming on ~400ppm signal, so far only 200ppm) We are continuing working to get the max
absorption from the test mirror. So far
we have used a 200 um pinhole which it made a difference to improve the
signal. It may need to improve the mode
match, which is the
next step to try it and see the results.
High-Irradiance, Contamination-Exposure Cavities
Lee Cardenas, Liyuan Zhang
Changes indicated in
yellow highlight.
|
Cavity
(Location)
|
Material/Item
|
Start
|
End
|
Comments
|
|
Cavity #1
(OTF Lab,
Bridge)
|
“Cable wire” (material type?)
|
~11/17
|
TBD
|
Taking
measurements daily.
|
|
Cavity #2
(OTF
Lab, Lauritsen)
|
NA
|
NA
|
NA
|
We
continue working on setting up the optical path. We have received the optics
needed to recover the whole optical path and be able to mount all the
required optics in place.
|
|
Cavity #3
(OTF
Lab, Lauritsen)
|
OSEM Flexi-circuit cable,
qty ~ 45
(Helena Armandula,
SUS)
supplied by Univ. Birmingham (Stuart Aston)
|
~9/30
|
TBD
|
taking daily absorption & ring down measurements
DuPont Flexible Circuits. The whole part to be
constructed of 'flexi' i.e. no 'rigid' sections. (Stuart Aston,Univ. of Birmingham, SUS/UK subsystem)
- Start Laminate: Kapton (LF8515)
(document link: http://www.dupont.com/fcm/products/H-73244.pdf
Coverlay (x2): Kapton
(LF0110)
(document link: http://www.dupont.com/fcm/products/H-73245.pdf
DuPont Pyralux
Series - Kapton / Acrylic Adhesive system.
(document link: http://www.dupont.com/fcm/products/H-73246.pdf
|
|
Queue
Priority 1
|
2 Cleaned 50ppm transmission mirrors, 1 in dia., REO coated --
|
TBD
|
TBD
|
witness samples for the LHO vertex volume (added in
6/29/2005 vent)
|
|
Queue
Priority 2
|
Stepper
Motor (Riccardo DeSalvo,
possible SUS or ISC use)
|
TBD
|
TBD
|
Stepper Motor sample had been placed
into Cavity #1: Power dropped from 175 mW to ~25 mW after introducing the stepper motor sample, and
continues to decrease. It is very hard to keep cavity locked. The stepper
motor may have contaminated the mirrors. Will re-test when a cvity becomes available again.
To be rebaked soon using the self-heating capability of the
stepper motor (not just the oven heater controls)
|
Kickoff of subsystem leaders charged to prepare materials for AdL Baseline Review.
Seismic Isolation
From: "Joseph A.
Giaime" jgiaime@ligo.phys.lsu.edu
Agenda for the weekly SEI telecom,
Friday, Feb. 10, 2pm Eastern, 1pm Central, 11am
Pacific time
Announcements
- Gas or oil prospecting near
LLO should finish in a few days. Now they are blasting and running
thumpers. Contact has been made with the engineer. Perhaps we
can get access to his data and learn something we don't already know about
surface wave propagation near LLO.
Single Stage HAM - Joe,
Brian (no progress on models)
- Corwin preparing solid model
of new version of bolted structure, to be shown next week.
- Carol wants to consider change
to baseline on or about April 1, so we would want to have a fairly
complete conceptual design in mid March.
BSC SEI status, Ken/
Dennis
- Pods didn't ship to LLO last
week, but are now expected to ship 2/20. Ken to send us info
regarding flexible bag glove box.
- Jay has prototype of the seismo cables and will show Ken next week, then
replicate them and send to LLO.
- L4-C and GS-13 preamps
prototyped.
- Arland stage 0 parts to be delivered
2/20, stage 1 on 3/1, and stage 2 before 3/16.
- Lavallee has machined the
blades. One of the 1-2 blades got nicked near the narrow end near
where the rod attaches.
- Ken will rev his heat
treatment technical note to reflect the actual treatment we do the the blades.
- Blade calibration fixture
design finished. Ken will lead a discussion on the design and cal
process during next week's meeting.
BSC work, adaptive
modeling and FIR (Rich M)
- Rich's latest adaptive feedforward results, posted
in LASTI log demonstrate better than a factor of ten improvement around the peak between 10 and 20 Hz.
There is still some unintended feedback to the feedforward
sensor on the tank, as well as motion measured by the floor-mounted STS-2.
- When run with sensor
correction (following log entry), the feedback to the STS-2 causes some
problem.
LLO HEPI (O'Reilly & Wen)
- Plan to improve HAM
performance above 1 Hz: (1) Engage tilt removal filter to remove tilt
signal in HAM HEPI actuator to geophone TF. (2) This will allow us to
blend at 0.5Hz. (3) Add RG at least at 1st (1.5Hz) and 2nd (2.3Hz) stack
modes in X and Y. (4) Add 12Hz bounce mode RG in HAM3 Z. Shyang is finalizing the filter design for (1) - (3).
- GS-13s installed on one of the
HAM tanks to allow for better calibration of the HAM platform motion.
- HAMs: blended controllers and tilt
correction cross term designed in order to add resonant gain.
ETF platform work, thermal
testing, frame testing - Brian
- SUS frame resonance tests on
ETF tech. demo. optics table with 'lower' SUS
frame structure replaced by equivalent SS weights, as requested by Calum. The 'U' channel is probably not stiff
enough to really simulate point mass. The lowest rx mode moved from 61 -> 76 Hz, which is not
as much as would have been expected. We don't plan to continue this
study.
- Thermal testing: Can't
casually see any temperature change on actuator sensor at more than millidegree level as a result of actuator function
during normal platform running. The stage-0 Al table sensor was
changing, probably due to contact with room through feedthrough.
More careful quantitative measurements to be done next week.
- Frame damping (Tarm): Drawings of end blocks for damping strut posted
on SEI log. The plan is to use dyad 601 as damping sheet, with glue
to be determined.
- Matt has set up control desk
panel to allow easy direction probe pulses for his tickle tester.
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
At MIT for Quad depacking and
installation.
From: Calum Torrie ctorrie@ligo.caltech.edu
Quad at LASTI
As
already mentioned in previous weeks the quad has arrived at LASTI.
Installation fixtures
Ken Mailand
and I continue to work on the installation fixtures. One time we have added to
our effort at LASTI next week is some "pushers and "movers" to
allow us to better align the quad on the solid stack. It is hoped these parts
will be ready for Saturday.
Quad to PDMWorks
I am arranging all of the
files to the CAD data management vault. In particular to
create a controls specific assembly.
Release to DCC
Once the previous item is
complete I will work with the other SUS folks to complete the release of the
drawings and assemblies to the DCC.
Pick Off Mirror
Mike Smith and I have
started discussion on the design of the pick off mirror suspension.
FEA of Quad Structure
I am working with RAL to
look at the interface between the upper and lower structure.
From: Ken Mailand kmailand@ligo.caltech.edu
I've completed a
preliminary assembly of the installation plate style fixture, in the CES in the
shop. I will be able to do a complete assembly and a load test early next week, I will get the
steel plates plated asap after the test.
Also for Calum, I'm working on a layout option, to use the lift
table inside the LASTI BSC chamber, minus the bridge and circular track
assembly.
From: Jay Heefner jay@ligo.caltech.edu
AdL SUS Quad Prototype
- Installation and test of the DSpace controls and electronics is 90% complete. All
that remains is to checkout the ESD driver. The system should be ready for
support of the controls prototype testing on the test stand by Friday.
AdL SEI ISI
- More L4C preamp boards have
been ordered for Brian Lantz. They are due next week. Once they are
stuffed and tested the will be shipped to the ETF.
- Prototypes of the pod cables
for the L4C and the GS13 have been delvered to
Ken Mason for a fit check. The STS2 cables are on hold for the delivery of
the proper connector collet from Fischer.
Core Optics
No report this week.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
The communication issue
with the Xilinx DSP board has not really been resolved
with Xilinx nor their software partners. The end result looks like
they will not support 64-bit operating systems, now or any time in the near
future. In the meanwhile I have been familiarising
myself with the software tools provided for interfacing and programming the DSP
board. Suffices to say that the
documentation could only have been written by a programmer
Auxiliary Optics
From: Michael Smith <smith@ligo.caltech.edu>
VERTEX LAYOUT
A functioning Brewster's
angle Faraday isolator was added to the IO optical train in ZEMAX, in order to
indicate the direction of the Refl port beam. A word
of caution if a Brewster's angle Faraday isolator is used--the reflected beam
will have approx 20% elliptical beam shape that may need to be corrected, with
either a Brewster's angle turning mirror, as was done in the 40M, or with an
external anamorphic telescope.
The errant beams resulting
from mis-aligned suspended optics in the IO train
were identified in ZEMAX and appropriate baffles were added to the layout.
The PRM and BS wedge
angles were adjusted to force the beam height at ITMX to be -80 mm
global. The ITMY height is -88.7 mm.
All the APS beams and
ITMXPO were routed to HAM6. The BSPO beam was routed to HAM1. There are no optics on HAM2, so the HAM2 SEI may be eliminated.
OPTLEV
Luke at FLA is in the process of adding optical
lever beams to all of the IO suspended optics.
SLC
Hiro is still working on obtaining
transfer functions for scattered light noise in the ADLIGO RSE configuration
with the optical spring effect.
Other Laboratory R&D
From: Riccardo DeSalvo desalvo@ligo.caltech.edu
Virginio, Valerio
developing Maple model of HAM SAS
Yumei
studying various aspects of HAM SAS
Nicky
resuming writing some of the creep paper during spring
break
Riccardo, Anamaria
GM
measurements
For additional information about this report, contact S. Whitcomb or P. Lindquist