Weekly Report for
Week Ending February 2, 2006
The LIGO Executive
Committee Agenda for Monday,
February 6, 2006 will be:
(Meeting time: 10:30 am Pacific Time)
1. Announcements
2. Comments
on Weekly Report
3. LSC
Issues (Saulson)
4. LIGO
Lab Operations
- Administration
(Lindquist)
- Sites
(Raab, Zucker, Shoemaker)
- Commissioning
(Fritschel), Detector (Coyne)
- Campus
Research Facilities
- 40
Meter (Weinstein)
- TNI
( Libbrecht)
- LASTI (Shoemaker)
- Data
Analysis and Computing (Lazzarini)
5. R&D
and Advanced LIGO (Shoemaker)
6. CHANGE CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION AS
NEEDED
- Change Request CR-050010 -
Prototype Seismic Attenuation System for the HAM Chamber (HAM-SAS)
Special Items:
Preparations for Advanced
LIGO Review (Tentatively May 31 – June 2)
- Staffing
Plan (February 10)
- Project
Execution Plan (Draft February 17)
- Revised
Operations Cost Estimate (February 17)
- Revised
Advanced LIGO Cost Estimate
- Advanced
LIGO Operations Plan (March 3)
- Proposal
Update
Special Announcements:
Weekly Report Highlights
This week, we concluded the re-examination of the SciMon system that began a
few weeks ago under the leadership of Rai Weiss. The conclusions that we
reached are given in the following memo, which was sent to lsc-all.
Keith Riles is already hard at work on scheduling for the next four-month
period, during which we will try out the new two SciMon/day paradigm.
Decision memo on scientific
monitoring of LIGO data runs by: Jay Marx, Stan Whitcomb, and Peter Saulson 30
Jan 2006
We are grateful to the ad hoc
committee that recently met to consider the scientific monitoring system for
our science runs. We express our thanks to Rai Weiss for chairing the
discussions of the ad hoc committee, as well as to all of the other members:
Ray Frey, Peter Fritschel, Joe Giaime, Gabriela Gonzalez, David McClelland,
Fred Raab, Keith Riles, Vern Sandberg, Peter Shawhan, Daniel Sigg, Alan
Weinstein, and Mike Zucker.
The ad hoc committee did an
excellent job of exposing the strengths of our present system and ways it could
be improved. We were pleased with the constructive spirit of the discussions.
We were also heartened that the basic value of the system to LIGO was strongly
underlined.
After listening to all of the
arguments, we concur with the majority of the committee that we ought to move
to a system that puts two SciMons per day at each site, instead of the present
three. One SciMon should be assigned a night shift that overlaps with the
loneliest hours of operation (for example, 9 p.m. to 6 a.m.), while the other would
be assigned a day shift. We encourage a choice of 9 or 10 hour shifts instead
of the present 8 hour shifts, as a way of reducing the loss of coverage.
We ask Keith Riles to coordinate the
implementation of this new version of the SciMon system, as he has done so ably
in the past. We will make this change on a trial basis for the upcoming 4 month
scheduling period. If we feel that this implementation is successful, it will
become our normal style of operation.
In addition to the discussion of the
number of SciMon shifts, a number of other good ideas were proposed. We wish to
encourage the exploration of these suggestions:
- Lengthening
the stays of individual SciMons to the extent possible. (As has been the
practice during S5, stays of shorter than one week are strongly
discouraged.)
- Expansion
of the practice of suggesting specific investigations; in addition to
those suggested by the DetChar group, commissioners and the various search
groups should suggest investigations to be carried out.
- The
LIGO Lab should explore increasing support for remote control rooms, so
that experienced SciMons from Caltech and MIT can take some shifts without
traveling to the sites.
- Small
groups may wish to team up to share SciMon duties, if that will help them
to meet their obligations.
To explore these suggestions, we
will schedule a forum at the March LSC meeting. We ask that all interested LSC
members bring their thoughts on these topics, as well as on any other ideas
they have for further improving the scientific monitoring system.
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
SITE TELECONFERENCE (Lindquist)
- A
site teleconference was held Thursday, February 2, 2006. The following issues were discussed:
- Operating
Budgets and Costs – Preliminary numbers are available for the
end of January. We are spending
virtually at the same rate as last year.
Through January three months considering delays) we have spent $8
million. This represents a rate of
approximately 88 percent of budget excluding extraordinary items.
- Property
– Conducted an Inventory at Livingston
this week. Ninety-eight percent of
approximately 120 items were found.
There were, however, several items discovered without property
tags, mostly computers in the data analysis area. Also there were items without an
assigned location in the records.
- Safety
– There will be a Safety Review at Livingston
February 28, 2006.
- The
list of assigned actions updated through December 01, 2005 (the last time
it was updated) will be found Here.
PROPERTY MANAGEMENT (Luna)
>
- Performed
Equipment Inventory at LLO.
- Provided
assistance to the Detector Group (H. Armandula) with packing, shipping,
and the preparation of a Commercial Invoice for US Customs Clearance of
one piece of glass to the University
of Glasgow. Account Number LIGO.OPT - 5.4 -
NSFLIGO.FY02ON.
- Provided
assistance to the Detector Group (H. Armandula) with Packing, shipping,
and the preparation of a Commercial Invoice for US Customs Clearance of 12
pieces of glass to CSIRO in Australia. Account Number
LIGO.OPT - 5.4 - NSFLIGO.FY02ON.
- Provided
assistance to the Detector Group (R. DeSalvo) with packing, shipping, and
the preparation of a Commercial Invoice for US Customs Clearance of
Maraging Steel 22x21x.16 to GALLI & MORELLI in Italy. Account Number LIGO.PRLAS 5.16 NSFLIGO.FYO2CA.
- Provided
assistance to the Detector Group (C. Torrie) with shipping of four crates
to MIT. Account Number LIGO.PRLAS,
5.16, NSFLIGO.FY02CA.
- Provided
assistance to the Detector Group (G. Billingsley) with receiving Fused
Silica Blanks from University
of Glasgow /
Heraeus. Account Number
LIGO.OPT-5.4-NSFLIGO.FY02ON.
- Tagged
two Computers, two Monitors, and two Printers.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
- Received
a skeleton draft of conversion requirements from Ian and have been making
notations and changes. A list of
questions has also been compiles to go over with him during a meeting
scheduled for tomorrow afternoon.
There will be more to report next week.
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- Scanning
of Old Documents -- Progress continues on scanning of contract
closeout files. Note that 30 boxes of files have been
scanned, put on disks, and the boxes destroyed. Another 30 boxes have been scanned and
are ready to be put on disk so that the boxes can be destroyed.
- Activity:
|
Week Ending
02/02/2006
|
In
|
Out
|
|
Packages
|
32
|
8
|
|
Faxes
|
26
|
17
|
FINANCIAL SYSTEMS (Cronin, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Completed
change order #169 to Triad for a two-month no-cost extension.
- Completed
the no-cost extensions for the following subcontracts: Perkins Coie,
George Stokes, Southbridge Sheet Metal, Alliance Spacesystems, Butler, and Frequency
Devices. The modifications were submitted to the vendors.
- Completed
the monthly stats report and the purchase order close out report and
submitted to management. Notified appropriate parties of expired orders
and orders over six months which are still open. Once Sun Microsystems
confirms order cancellation, the funds will be released.
- Working
with researchers on changes to previous credit card orders and an assembly
that has slightly different dimensions than what is needed.
- The
large ASA purchase order for the additional computer units has been
approved and submitted to the vendor.
- Still
working with Sun MIcrosystems on the request for the pending credit which
is holding up payment of their invoice.
Sun has submitted the tax exemption for LHO to their tax department
for approval.
- Working
on the catering services provided by Great Impressions to establish a
pattern for subsequent requests.
- Completed
the internal expenditure type change on the diode bars ordered from JDS to
make the change from “Equipment” to “Supplies.”
>From: Florence Kaufman <fkaufman>
- Completed
and posted report for FY06 Operations and R&D for activity through
January 2006.
- Completed
and posted report for Outreach Award for activity through January 2006.
- Caltech
Benefits Department has agreed to 'refund' charges for health insurance,
etc. for visitors which were
charged in error for period beyond the dates of the visit, however the
adjustment will only be for three months of charges.
- Fabrication
accounts for LIGO.DAQ and LIGO.ISCCA have been set up.
- Revised
account number list has been posted on the LIGO Internal Bulletin Board to
reflect the new fabrication accounts.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- Ed
Jasnow participated in the weekly construction meeting on the Science Education Center
on Tuesday, January 31. The
contractor is performing very well, and has recovered schedule lost during
inclement weather. The steel and
masonry work is scheduled to be completed ahead of schedule.
- A
teleconference was held on Wednesday, February 1, with Carol Wilkinson, Ed
Jasnow, Rod Luna, and Jesus Ayala, the Assistant Director of Caltech's
Financial Asset Accounting Services, to discuss the mitigation of import
duties and state taxes on material for Advanced LIGO. After discussion of the rules and
regulations regarding these issues, the material was divided into three
categories, two of which avoided duties and taxes altogether, and one, raw
material, which could be subject to both.
It was agreed that Advanced LIGO would develop an acquisition plan
that could be used by the LIGO Business Group to assure that duties and
state taxes were reduced as much as possible.
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
- Worked
on the usual new trips, expense reports, reconciling, calendar
reservations, and itinerary entries, as well as pulling all 2005 trip
files for permanent storage with DCC and setting up my 2006.
>
University
of Wisconsin/Madison Proposal
-- The budget sheets have all been signed by Albert and Lucy. The DAF has been signed by Tombrello, and the
Vice Provost, and delivered to Office of Sponsored Research. The budget sheets and statement of work has
been faxed to University of Wisconsin-Madison.
The complete proposal is on file in my office. I will take care of requesting a DCC number
for it and sending a copy to the DCC.
>Dorothy Lloyd
- Updated
contract invoice summary log (Dec 5 - Jan 20).
- Attended
SOS buyer and TechMart meeting.
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
DCC Steering Committee (Lindquist)
No report.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
- Change
Request CR-050010, Prototype Seismic Attenuation System for the HAM
Chamber (HAM-SAS) was submitted by Dennis Coyne. If approved, the
change request will add the fabrication and test of a predominantly
passive, seismic isolation system prototype for the HAM chamber, to the
Advanced LIGO R&D program. This request will be discussed during
the normally scheduled meeting of the LIGO Executive Committee scheduled
for February 6, 2006.
- Change
Request CR-060002, Augment the recent order for the CIT LDAS cluster to
add another 77 nodes plus miscellaneous accessories (e.g.,racks,
cabling). The request was approved during the meeting of the
Executive Committee on January 30, 2005. Minutes of the meeting have
been electronically distributed (LIGO-M060014-00-P).
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- The
next Staffing Committee meeting is scheduled for Monday, February 27, 2006
- All files for the Staffing Committee are up-to-date
and posted on the SC web page.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
Safety audits have now been completed for eight of the eleven LIGO campus
labs to be audited. (The remaining three
labs are scheduled to be audited during the next week.) The labs that have now been audited all show
much improvement in "housekeeping" and reducing personnel safety
hazards.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of
Commissioning Activities at LIGO Hanford
Observatory (compiled by M. Landry)
Duty cycles this week were H1-64%, and H2-76%, compared to last week H1-78%,
H2-79%. Extended and extremely high winds
impacted the duty cycle particularly on H1. More frequent transitions to
ASPD5 from the sensing photodiodes ASPD1-4 were evident on FOM1.
Since the outset of S5, Daniel Sigg has been serving as the LHO local run
coordinator. As Daniel now heads to MIT for several months, Rick Savage
will next take up the duties of local run coordinator at LHO.
Next Monday we head into an S5 interim commissioning
mode for two weeks.
Some S5 highlights from the elog are bulleted below:
- Whitened
DARM_CTRL is now written to frames. The effect of the filter on the
channel is plotted here,
along with the zpk representation of the filter
- Tuesday
maintenance tasks were summarized
- LHO
and LLO range and duty cycle plots were updated
- A
noise study suggests that seismic noise generated by winds couples in due
to motions
of buildings, as opposed to ground motion. This is contrary to
the prevailing view that winds cause the ground to move like a membrane
which shakes the stacks.
- Uncalibrated
Rayleigh plots compare
error signals in S4 and S5 runs.
- The
H1 AS trigger threshold (run ASPDs->ASPD5) was adjusted.
- The
H2 RF phase
of ASPD3 was moved from 214.9 to 183.9 degrees, better separating I from
Q. Furthermore, 2m of cable were added to adjust
the phase of AS3I_CORR. The effect of the mods was to reduce
DC junk light in AS_Q of PD3.
- A
detailed study
of a 2k lockloss sees growing 75Hz ringing in AS_Q.
- A new
REFL2 photodiode will be tried out on H2.
- Revisiting
the scattered light hypothesis suggests that light scattering from the ETM
cages is not
a source of our excess noise in the 40-200Hz region.
Outreach (D. Ingram)
Wapato Middle School students surfed the waves
during a recent LHO visit
to the school. We're getting ready for a public open house here at
the site on 2/11.
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
L1 Interferometer in S5 (Franzen)
Summary of S5 run and commissioning activities at LLO
The duty cycle was around 64% with an inspiral range between 8.5-10.5 Mpc.
The construction is still sometimes preventing us from keeping lock during the
day even during otherwise quite times, but the situation is slowly improving.
The week offered a series of technical challenges:
- Problems
were observed with the MC WFS1 PD quadrant 2 DC readout. A spare unit is
in the process of being prepared at Caltech.
- The
RM bias module failed. It was swapped.
- The
ITMX optical lever laser went noisy. It was exchanged.
- The
RBS lower mirror PZT broke down. It was replaced by our only spare.
Other maintenance highlights:
- There
was a framebuilder code drop
- The
ASQ BRMS DMT monitor was updated and is now also tracking hardware
injections
- Some
good news is that we have not observed any dust type glitches after
turning off the ISCT4 HEPA blower last week.
L1 CDS (Bogue)
- Called
Sun and got a field engineer out to change the controller in the new
3511. While he was here, we
diagnosed the problem with the dual fiber card in fb0. He'll be back out next week to replace
the card.
- Installed
a network based configuration and monitoring interface for the mitsubishi
ups.
- Began
turning off access into cds via shared accounts.
- Shipped
the loaner atomic clock back to the manufacturer.
- Ordered
a dell to be built as the replacement beam centering servo.
- Ordered
2 blade1500s -- one for a test string, the other to support the next round
of commissioning.
- Ordered
a sun server to be an emergency backup for llo1.
CDS software (Khan)
Writing a tutorial on 'How to analyze LIGO Seismic data using Matlab and
Ligotools'.
LLO Outreach (Zucker)
We held a full-day planning workshop for the Outreach partnership at LLO on
2/1. Introspective self-analysis of progress to date by all the partners
indicated gratifying progress, but also underscored how we are victims of our
own success; the demand for LIGO SEC outreach already exceeds planned capacity,
and the Center is still under construction. This introduced a productive
interaction about how to complete our Grant objectives while laying the
groundwork for a sustainable, first-quality program in the future.
LIGO SEC Construction (Zucker)
Steel erection is about 75,percent complete this week and the building
envelope has taken visible shape. Schedule projections are on track. We have
had success negotiating quiet times with our contractor wherever it does not
impact cost or completion; for example Friday 2/3 the contractor agreed to
sychronize planned downtime for his steel and masonry subs, so we have a free
and clear science day with no construction traffic. We hope this will become
more frequent as the installed mass approaches the asymptote.
Computing and Network Security (Roddy)
- Installed
and debugged the windows backup client on a test machine. There were several issues with the
windows firewall. Once I had
everything debugged, I installed the client on a user's desktop machine
who was up until now not doing backups.
- Ordered
various bits of hardware
- Worked
on some documentation and notes - adding info to the wiki, etc.
- Cleaned
a bit of spyware off of one windows PC in particular. The same spyware continues to pop up
occasionally. Users must be getting
infected by a particular website.
Not sure of the vector yet.
- Made
a few changes to the DNS files here.
- Installing
patches on a couple of the Linux servers that have not been patched in a
while. Configuring this to function
automaticlally in the future.
- Did
some broadcast traffic measurements on the CDS interface. This will be useful in later discussions
of remote control rooms. I have
been tossing around some ideas/solutions to the configuration of the
remote control rooms. Need to work
with Dave some on this.
General computing (Giardina)
- (With
Shannon) completed install of CanIt
server. needs to be tested and have
filters created.
- Rebuilt
PC for Simon Stepuk, installed FC4.
finishing configuration today.
- Received
new network attached storage(300 GB).
started configuring it this morning.
LDAS admin (Giardina)
- Tapes
ejected and shipped to CIT: LL0500,
LL0565, LL0570, LL0571, LL1700, LL1702, LL1705.
- LL1696,
LL1697, LL1698, LL1699, LL1707, LL1708, LL1709 imported into L700 library
- Researching
problems with ganglia web front-end.
statistics aren't being displayed properly in some locations. Problem is also happening in some
locations at LHO, but not necessarily in the same locations as at LLO. I have implemented a very nasty and hopefully temporary "fix"
for the cluster-summary section. I
have noticed many strange things in the ganglia PHP code, and will
continue investigating.
Data analysis (Yakushin)
Igor is on travel at Caltech
Initial LIGO Detector Science & Engineering (Coyne)
CDS
see also the CDS weekly meeting minutes in the commissioning archives
Rolf Bork
Microseimic controls are to be added to LHO ETM controller software. The definitive design should come out early
next week for us to start the new software additions.
Optics Characterization
GariLynn Billingsley
Molecular contamination results from the swipe of 4ITM07 (recently removed
from Hanford)were
obtained from JPL. The results are not significantly different from any
other swipes of LIGO optics. See http://www.ligo.caltech.edu/docs/T/T060029-00.pdf.
Compare to previous results at http://www.ligo.caltech.edu/docs/T/T050027-00.pdf.
The particles were clearly included in the swipe, so we can conclude from
this analysis that the particles are not soluble hydrocarbons.
40-Meter Interferometer (Weinstein)
There will be a meeting of the 40m Technical Advisory Committee this
Thursday 2/9/06 ay 8:30 Pacific. All interested parties are welcome to attend;
contact ajw@caltech.edu for instructions.
We are preparing a couple of papers. One, on the measurement of the DARM
transfer function in the full dual-recycled Fabry-Perot Michelson configuration
(featuring the detuned RSE optical resonance and the optical spring resonance).
Another, on the Mach Zehnder solution to the sidebands-on-sidebands problem.
IFO Modeling
- Rob,
Alan and Osamu are fitting the dual-recycled transfer function measured
last November to the theoretical curve from Buonanno & Chen, and
getting excellent agreement. Rob also gets excellent agreement with his
Optickle model. We are now working on errors and degeneracies in the
parameters.
- Osamu
and Rob are developing methods for measuring the arm cavity pole to aid in
getting the model right. They are also thinking about measuring, and
developing a detailed model of, all the analolg and digital filtering in
the XARM and DARM loops.
- Monica
continues to work on e2e simulation of the DARM open loop transfer
function with and without radiation pressure. She's running modeler and
waiting for real data to complete the comparison. She's simulating the
optical response for different demodulation phases and looking for the
values that matches the real measurement. A demodulation phase of pi/15
(12 degrees) could match pretty well : still under investigation.
- Osamu
continues to develop an e2e simulation of the digital suspension system
including local damping model with 40m parameters based on Matt's AdLIGO
quad model with minimum change. It is almost done and he will move to FP
cavity with this suspension model.
- Monica
and Dan continue to work on the NoiseBudget procedure. They are modifying
the code obtained from the sites and working on various software problems.
DC Detection Development
- Rob
and Rana continue to develop the detailed schematic of the DC readout
controls, electronics, cabling, fast and slow channels, DAQ, etc.
- Ben
reports that the DCPD electronics boards are back from PCB Express. He
will stuff them and begin testing. He got some PEEK plastic stock that he
will bring to the machine shop for the manufacture of some parts for the
DCPD.
- Dan
and Sam continue to work out the bugs in the control of the in-vac pzt
steering mirrors.
- Go
and Osamu have prepared a conceptual design schematic for installation of
the MIT vacuum squeezer into the 40m IFO.
Electronics, Controls, Computers
- linux101,
the vacuum operator linux workstation in the IFO hall, had a few problems,
all of which are related to networking. Rob patched the problem, but it
needs the attention of someone who knows how to properly set up
networking.
- Similarly,
our new operator workstation, op540m, sits dormant, since we don't know
how to get it to network. Waiting for help from Alex.
Lab Infrastructure
- We had a safety inspection
last Friday. Steve and Bob escorted the inspectors around the 40m lab and
South Annex Lab. A list of action items were compiled by Steve, and all
are being followed up on.
Thermal Noise Interferometer (Black)
Akira has been measuring the Q's of several
modes of the unconstrained mirrors by ringdown.
The results are not terribly consistent from day to day, sometimes
differing by factors of two. We suspect that the servo is interfering with this
measurement, which is why we had hoped to avoid this method and look at the
intrinsic excitation in the first place.
Right now we are working on eliminating all servo influence on the Q
measurements, and verifying that we can measure a purely mechanical Q.
LASTI (Ottaway)
No report.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Yamamoto)
Adv.LIGO modeling schedule (Hiro)
There was meeting on Jan.27th, discussing priorities and schedules for
modeling for Advanced LIGO.
The priority is
1) QuadFP
: Adv.LIGO high power one arm simulation, to study the locking (velocity,
force) and alignment controls (angular stability).
2) Static
IFO Simulation : Adv.LIGO version of FFT code to study: ROC, surface roughness,
stable vs unstable cavity, etc.
3) Time
domain Full adv.LIGO simulation using modal model : total design of LSC/ASC and
the stability test
QuadFP, high power and modal model based, is almost ready.
The urgency of PathFinder requires Static IFO simulation modeling to be
completed in a very short time - 5 months.
Hiro will spend most of his time for this Static IFO simulation
development. This severely limits Hiro's
activity to upgrade e2e and to support e2e users.
40m modeling (Monica, Osamu)
Monica used her setup to study the DARM loop and the DARM -> A166
transfer function. The DARM open loop
transfer function has been simulated with and without radiation pressure: it is
necessary to increase the UGF to get more stability in the optical spring
frequency range. The optical response
has been simulated for different demodulation phases with and without the DARM
loop: a dependence on the demodulation phase affect the optical spring and the
RSE peaks. A good matching with the real
measurement of the optical response has been found for a demodulation phase of
pi/15 (12 degrees).
Osamu is working to improve the Matt's SimAdvLIGO to filling in many place
holders by actual codes, based on the 40m IFO.
AdvLIGO Mechanics (Sany Yoshida)
We made a simplified e2e box file (called the toy HAM box) that mimics
AdvLIGO HAM seismic isolation. The toy HAM box takes translational ground
motion as input and outputs table-top translational motion in the same
direction. When a typical ground X motion is used, this box file outputs
required (spec) table-top displacement in X direction for Adv.LIGO.
We placed a LIGO 1 SOS box on top of this toy HAM bond and computed the
optics position motion under various local damping conditions to compare the
improvements of performance from LIGO I to Adv.LIGO. The results are currently being analyzed.
ALFI - GUI (Bruce, Melody)
Bruce spent most of his time to update alfi
to handle alfi-bundle more
robustly. A revised algorithm has been
implemented with a sacrifice of speed.
He is working to recover the speed.
Melody, together with Bruce, are cleaning up the final several PR
issues. Almost ready to attach new
challenges.
Data Analysis Activities (Lazzarini)
Chatterji:
1. Continued updating QScan utility:
- Adding
timing information
- Modifying
default configuration to search auxiliary inteferometer channels at lower
frequencies in order to identify glitches due to non-linear upconversion
- Modifying
build script to permit buildling on Solaris in addition to Linux
- Installing
on all LIGO Laboratory computing clusters
- Investigating
launching via globus
2. Preliminary study of burst search sensitivity to inspiral hardware
injections (password required): http://www.ligo.caltech.edu/~shourov/q/qscan/protected/G060018-00-Z.pdf
3. Assisted the installation of new CIT computing cluster nodes.
Dupuis:
- Worked
on tracking down noise sources in TDS S5 analysis.
Shawhan:
- Added
GEO status to the GWIstat display at
http://www.ldas-sw.ligo.caltech.edu/ligotools/runtools/gwistat/ . Now one glance tells you the run status
of eight GW detectors!
- Prepared
for Burst Group face-to-face meeting.
- Did
maintenance on software for hardware signal injections, plus LIGOtools
software.
Sutton:
This week I've been pushing on the metric problem for the cheese, and I finished
most of the rest of the cheese paper.
I've also edited portions of the null-stream analysis paper from GWDAW.
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS
Continuing with the integration of tclglobus into LDAS, globus variables needed
by multiple APIs have been moved into the LDASapi.rsc file. Also, the globus
security information that is needed by LDAS has been moved into
/ldas_outgoing/grid-security. This change has been tested for the cmonClient,
cntlmonAPI and the managerAPI and no failures were observed.
The change from host based certificates to service based certificates for
internal communications have been completed and the nightly loop tests (except
putMetaData which uses SeqInsert) have been converted to optionally use X509
authentication.
The C++ code base has been modified to support the specifying of the md5sum
output directory as requested in PR#2953.
System and integration testing was done on ldas version 1.8.72.
TCLGLOBUS
Within the Tcl Channel Interface, the value of the environment variable
X509_CER_DIR is verified before use.
The number of documented Swig wrapped Globus FTP Control functions has been
extended to 50. There remain 12 more functions to be documented.
GRID COMPUTING
Attended OSG Council Meeting after OSG Consortium Meeting. Reviewed and
approved new executive board. Reviewed status of letter of intent to DOE and
the proposal to the NSF. Also reached a consensus on the new OSG Council
Chairperson, Bill Kramer of LBNL.
Worked closely with Ruth Pordes to wordsmith the OSG proposal to the NSF
which is expected to be submitted this week.
Worked with Harvey Newman (CIT) and Richard Cavanaugh (UF) to provide inputs
to the PLaNetS project proposal on ways LIGO could benefit from the network
solutions being advanced by this technology.
Met with the USC-ISI team to discuss enhancements to the Pegasus work- flow
system that would allow LIGO jobs to make more efficient use of OSG site
storage. This falls into two categories; Adding automated data clean up to the
workflow; Adding support for Storage Resource Management (SRM) to the VDS and
Pegasus. The first would be the easiest to implement and is strictly a client
side feature that would not require any changes to existing OSG software
stacks. The second is now well understood and would probably need both client
and server side software changes. At this time it is not clear how much longer
ISI will be able to collaborate with LIGO on advanced workflows given their
current funding situation. As a result
LIGO is discussing some bolt-on technologies that could be used to acheive
similar clean up, external to Pegasus.
Working with the VDS team, a work around has been found for the failure of
the Pegasus planner to generate DAGs from production level DAX. By using Java
1.5 (aka Java 5) instead of Java 1.4, one can produce the DAGs. Then one needs
to switch to Java 1.4 (part of the OSG VDT) to run the standard configuration
used with the OSG 0.4.0.
Determined that the development version of SRM on the ITB testbed is linked
with GT2 libraries. A GT4 compatible
version of the SRM is only now being tested by the LBL development team. As the gsiftp in GT2 is considerably less
reliable that the gsiftp in GT4, it's not clear the development version of SRM
we currently have is reliable enough for the large data movement requirements
of LIGO. More information will be needed from the SRM user community.
A complete re-analysis of the S4 data using the L4 data set is being
attempted with an 8153 collection of DAGs. As of Feb 2 at 10 am, 1212 of 8153
DAG nodes have completed with zero failures on LIGO-CIT-ITB.
On the OSG Integration Testbed, all nodes have been yum updated. Three new
VOs have been added to the collection of supported VOs.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Removed
long extension cord and rerouted power under the floor in Booth.
- Got
Sun to send replacement power supply for failed on in ldas-cit.
- Dealt
with fall out from inadvertent reboot of ldas-cit caused by the
combination of the previous two items.
- Got
Sun/STK to replace a bad 9940 power supply;it's been working fine since.
- Called
in and received 3 3510 disks.
- Worked
on installing cluster nodes.
- Set
up CIT /home filesystem (2 3511s + dataserver internal disks for metadata)
and began rsync'ing /archive/home to it as a burn in test.
- Worked
with Ben on h(t) publishing problem (md5sums being wrong in LDR metadata
so transfers fail and queue becomes clogged).
- Worked
on LHO /archive filling up, archiving falling behind.
- Educated
user sung about overusing resources to fix CIT gridftp problems (there
were no tape drives available).
(Phil Ehrens)
- Wrote
ks-manager.tcl script which partially automates the pxe/dhcp based cluster
node kickstart process.
- Various
certificate management duties.
- Various
desktop support duties.
- Assisted
in installation of 200 new cluster nodes.
- Installed
Solaris 10 UG1 on ldas-dev and dataserver-dev and documented important
parts of the procedure in the wiki.
(Erik Espinoza)
- Moved
fltk/fltk-devel/mcelog into rc.ligofb.
- Updating
ssh keys.
- Updating
grub for memtest86+.
- Update
fedora-extras.repo.
- Pointed
/etc/profile.d/ligo.[sh|csh] to /ldcg/etc/ligo.[sh|csh].
- Made
usb sticks for mbr killing.
(Stuart Anderson)
- Continued
testing of new opteron node configuration.
- Helped
physically install 208 new opteron computers.
- Working
with condor team on 6.7.14 issues (6.7.15 is DOA, waiting for 6.7.16).
- Installed
the last stable release of LAL on all the Lab cluster head nodes.
MIT
(Keith Bayer)
- Electricity
for a/c unit and for new nodes being worked on.
- ldas-jobs.mit.edu
webserver brought up for ldas-grid users supporting ~public_html
directories.
- Switched
cluster to point to new fedora-ligo yum directory.
Livingston
- (Dwayne
Giardina)
- tapes
ejected and shipped to CIT: LL0500,
LL0565, LL0570, LL0571, LL1700, LL1702, LL1705
- LL1696,
LL1697, LL1698, LL1699, LL1707, LL1708, LL1709 imported into L700 library
- Researching
problems with ganglia web front-end.
statistics aren't being displayed properly in some locations. problem is also happening in some
locations at LHO, but not necessarily in the same locations as at
LLO. I have implemented a very
nasty and hopefully temporary
"fix" for the cluster-summary section. I have noticed many strange things in
the ganglia PHP code, and will continue investigating.
Hanford
(Ben Johnson)
- Transmission/segment
publication of GEO frames help up by possible issues with the FrameL
library.
- Pointed
ldas-grid, ldas-pcdev1, and node* yum.repos.d to the
"fedora-ligo" repository.
- Added
inspiralbbh user at Eirini's request.
- Added
"time window" code to LHO h(t) generation to only publish data
within the window, [now(t) - 1 week, now(t) - 1 day]. The "now(t) - 1
week" entry is useful for restarting the script. I will add the
windowing code to all publication scripts. This will especially help the
trend publication scripts, and as S5 grows, the S5 publication scripts in
general.
- Continuing
to move older data sets to on-site IDE-RAIDs; starting S4 L3 RDS
presently.
General Computing (Wallace)
MIT:
(Keith)
- Installed
new Matlab license server on network verified that it works on gc, ldas,
standalone linux boxes, and windows.
- Built
Solaris 10 box using PADL (3rd party) LDAP libraries works the same way
the Linux boxes 'natively' do now next task is LDAP mail integration
Livingston:
(Dwayne)
- (with
Shannon) completed install of CanIt
server. needs to be tested and have
filters created.
- rebuilt
PC for Simon Stepuk, installed FC4.
finishing configuration today.
- received
new network attached storage(300 GB).
started configuring it this morning.
(Shannon)
- Installed
and debugged the windows backup client on a test machine. There were several issues with the
windows firewall. Once I had
everything debugged, I installed the client on a user's desktop machine
who was up until now not doing backups.
- Ordered
various bits of hardware.
- Worked
on some documentation and notes - adding info to the wiki, etc.
- Cleaned
a bit of spyware off of one windows PC in particular. The same spyware continues to pop up
occasionally. Users must be getting
infected by a particular website.
Not sure of the vector yet.
- Made
a few changes to the DNS files here.
- Installing
patches on a couple of the linux servers that have not been patched in a
while. Configuring this to function
automatically in the future.
- Did
some broadcast traffic measurements on the CDS interface. This will be useful in later discussions
of remote control rooms. I have
been tossing around some ideas/solutions to the configuration of the
remote control rooms. Need to work
with Dave some on this.
Hanford:
(Christine)
- Out
most of last week and all of this week.
- Once
Amerion reprogrammed their VLAN, the backup network started working. The latency problems seen when the
network first started working seem to have fixed themselves. Testing of the backup network by taking
down the primary network is scheduled for 2/14/06.
CIT:
(Veronica)
- LSC: Working on the website for the March
meeting. Implementing an
application for an online registration that will be handled and stored
locally without the use of an ITS-provided utility. This is a Windows-based database and
frontend, which is being tied to a set of LSC meetings webpages at
ligo.org. I am looking into the
ways of making the data available to the meeting organizers for
bookkeeping and tracking of payments.
Working with Terry Gunter and Caltech Treasury on the setup of the
online credit card payment application.
Updates of other LSC- related webpages. Updates of the roster database and the
LSC-related mailing lists.
- LIGO: Website updates. Working on a website for the Elba meeting.
(Mike)
- I
worked on Spam Filters with Larry.
- Finished
up documentation on the Synergy installation.
- Barry
Barish: Tried to ghost his laptop to a new hard disk, but the image
failed. I well have to reload his laptop from scratch on a new hard disk.
This is due to bad sectors on his current hard disk.
- Ran
monthly ghost backups on all NTSRV's.
- Mike
Smith: Having many problems with Solid Works crashing on him. I ended
having to reload the software.
- Added
an additional network connection for Peter King over in Lauritsen; this is
to connect his new workstation to the network.
- Worked
on Graffias setting up an additional raid controller card to make this the
backup system for the DCC database server.
- Rerouted
some network cables in the B/A server plus labeled these cables, plus some
other additional cleanup work.
- Setup
a DCC workstation for Synergy engineer to login to DCC to see our current
database structure. This is to get ready for the migration to the new
SQL/Synergy server.
- Other
misc. support that included networking, email, software issues, ordering
printing supplies, and adding additional visitors to the wireless access
point mac address filtering list.
(Christian)
- Added
1GB of additional memory to Jay Marx's new laptop.
- Stocked
printer cartridges that were delivered to LIGO this week.
- Delivered
new LCD monitor to ED Maros.
- Added
1GB of additional memory to Mike Smith's workstation.
- Re-imaged
laptop that was returned to the loaner pull this week.
- Other
misc.: Continued onsite software/phone support.
(Larry)
- Placed
a number or computer orders. Also, received a number of new computers. A
few have been distributed and Christian is working on s/w installations on
the others.
Resolved a couple of p-card issues.
Items on CIT side and on the vendor side.
Trying to get Monarch computers to
keep the server we purchased 5 mos. ago, or at least give us some compensation
for keeping the unit for such a long time.
- Setup
a new mailman list. That process definitely needs to be updated.
- Worked
on the mail server it had multiple hardware errors.
- Mail server is down again. A power outage we had at
noon may have been the culprit.
Presently, trying to reslove this issue.
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Systems, Management
From Phil Lindquist
Advanced LIGO Review Preparations (Lindquist)
The following documents have been prepared and distributed:
Positions Summary List - The first step in preparing for the Advanced
LIGO Review is to review the Positions Summary List to check whether the
projected positions are consistent with expectations and needs. We also need to know what positions will be
required to support continuing Operations activities through the Advanced LIGO
Construction effort and what positions will be available to help with Advanced
LIGO.
LIGO Operations Budget Model (FY 2006 - FY 2008) - This file is a
full detailed budget projected through FY 2008.
It assumes that funding will be level at $33 million in FY 2007 and FY
2008. Operations Task Managers will be
requested to review and update as needed.
Summary Budget Report - This report summarizes the budgets by WBS and
estimates the reserve.
Projection of Advanced LIGO Operations Costs - This model projects
budgets through 2014 (steady state Advanced LIGO Operations) including a
summary of increments that were provided by task managers for the June 2003 NSF
Review. These estimates have been
escalated to FY 2014 dollars. We will
request a review and update by the Operations Task Managers.
Systems
from Dennis
Coyne
See also:
AL
Systems web page
AL Systems email
archives
Records of Decision or Agreement (RODA)
See also the RODA
status web page
- RODA
M060017-00, “Steel
Wires for the Mode Cleaner Suspensions” has been signed and posted
Requirements/Design
- Nothing
significant to report
Interface Issues
See the
"Interfaces" section of the AL Systems web
page
- Nothing
significant to report
Vacuum Compatibility
Residual Gas Assay (RGA)
See also the Vacuum Bake Lab
Bob Taylor
- I
have been working with Calum and Mark on the Quad SUS all this week in
perp. for shipping to MIT
Scatter/Absorption Test Measurement System
Lee Cardenas, Liyuan Zhang, Bill Kells
Encountered a situation, the housing boring hole is much
smaller by 0.007" for the laser rod diameter. Therefore, a new right
housing is required, and placed in order and get credit for the other one
High-Irradiance, Contamination-Exposure Cavities
Lee Cardenas, Liyuan Zhang
Changes indicated in
yellow highlight.
|
Cavity
(Location)
|
Material/Item
|
Start
|
End
|
Comments
|
|
Cavity #1
(OTF Lab,
Bridge)
|
“Cable wire” (material type?)
|
~11/17
|
TBD
|
Taking
measurements daily.
|
|
Cavity #2
(OTF
Lab, Lauritsen)
|
NA
|
NA
|
NA
|
Cavity
not ready. It needs some other optics(such as: polarizing cube, 1/4
wave plate and some curve mirrors and lens) and the electronics. We have
used/borrowed some of the optics from this system to accomplish
the completion of the other two cavities. Recently the 700 mw NPRO laser was
used for Garilynn’s experiment and it needs to be realigned to the
cavity.
|
|
Cavity #3
(OTF
Lab, Lauritsen)
|
OSEM Flexi-circuit cable, qty ~ 45
(Helena Armandula, SUS)
supplied by Univ. Birmingham (Stuart Aston)
|
~9/30
|
TBD
|
taking daily absorption & ring down measurements
DuPont
Flexible Circuits. The whole part to be constructed of 'flexi' i.e. no
'rigid' sections. (Stuart Aston,Univ.
of Birmingham, SUS/UK
subsystem)
- Start Laminate: Kapton (LF8515)
(document link: http://www.dupont.com/fcm/products/H-73244.pdf
Coverlay (x2): Kapton (LF0110)
(document link: http://www.dupont.com/fcm/products/H-73245.pdf
DuPont Pyralux Series - Kapton / Acrylic
Adhesive system.
(document link: http://www.dupont.com/fcm/products/H-73246.pdf
|
|
Queue
Priority 1
|
2 Cleaned 50ppm transmission mirrors, 1 in dia.,
REO coated --
|
TBD
|
TBD
|
witness samples for the LHO vertex volume (added in
6/29/2005 vent)
|
|
Queue
Priority 2
|
Stepper
Motor (Riccardo DeSalvo, possible SUS or ISC use)
|
TBD
|
TBD
|
Stepper Motor sample had been placed
into Cavity #1: Power dropped from 175 mW to ~25 mW after introducing the
stepper motor sample, and continues to decrease. It is very hard to keep
cavity locked. The stepper motor may have contaminated the mirrors. Will
re-test when a cvity becomes available again.
To be rebaked soon
using the self-heating capability of the stepper motor (not just the oven
heater controls)
|
Working on MOUs, risk analysis, and planning the preparations for the
baseline review.
Seismic Isolation
From: "Joseph A.
Giaime" jgiaime@ligo.phys.lsu.edu
Agenda for the weekly SEI
telecom - Friday, Feb 3, 2pm Eastern, 1pm Central, 11am Pacific time
Announcements
- Joe, Brian and Corwin met at
Stanford to start work on a single-stage HAM platform design.
BSC SEI status, Ken/ Dennis
- Spreadsheet posted with
Limerick's progress.
- Arland's progress awaits
delivery of the thread inserts, not expected for a few weeks.
- Norcal will be shipping all
three pod housings to JG at LLO this week.
BSC work, adaptive
modeling and FIR (Rich M)
- Note
in today's LASTI log on experiments with correcting the BSC-chamber
accelerometers for the motion induced by actuation. This is thought
to hold promise, and will be pursued.
HAM control with VME
(Pradeep)
ETF platform work, thermal
testing, frame testing - Brian
- thermal test instrumentation
installed, system sealed and pumped down. The sensors are currently
on an actuator coil, the stage-0 aluminum pier next to an actuator, and on
the optics table. There is also a non-thermally-sensitive resistor bridge
for diagnostics
- Also, set up to test the
resonance frequency of the 'upper' pendulum frame plus weight equal to the
'lower' portion.
Frame damping - Brian
- aluminum
box stock purchased. Call in to vender for sample damping material.
From: Dennis Coyne coyne@ligo.caltech.edu
HAM-SAS Analysis
In response to the HAM-SAS
Review Committee's report (M060004-00)
on the proposed HAM-SAS prototype & LASTI experiment (G050555-00,
G050620-00),
an analysis of the system dynamics (T060020-00) and
passive performance (T060021-01)
was accomplished. Responses to many of the review committee's findings are also
included in T060021-01.
The passive isolation performance is predicted to meet AL requirements (E990303-03) except
for a region around 0.8 to 1.5 Hz where some modes, associated with GAS Filter
horizontal stiffness, are expected to occur. It should be possible to reduce
the magnitude of the motion at ~1 Hz and it may be that this current passive
performance is acceptable as predicted. Studies are underway (by Peter
Fritschel) to revisit the HAM isolation requirements.
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
Working on coordinating
the SUS Workshop after the LSC meeting in March. Working on coordinating
suspension support at LASTI for the quad uncrating, re-assembly and testing.
Working on the ear placement fixture. Purchasing items for the quad, including
impact sensors for the crates and additional magnets. Planning travel to MIT
Feb 15-22.
From: Calum Torrie ctorrie@ligo.caltech.edu
Quad in a box! Well okay 2
boxes. It should leave for MIT in about 30 minutes (at 03-Feb-06 15:23:22 eastern time….)
From: Ken Mailand kmailand@ligo.caltech.edu
I’ve completed shop drawings for the SUS installation, plate style
fixture, and following up with CES in the assembly. Also for Calum, I’m
working on completing, and modifying the bridge and ring track, to allow for
fewer welds.
From: Jay Heefner jay@ligo.caltech.edu
AdL SUS Quad Controls
Prototype
- Electronics, cables and
connecotrs for the quad have been removed from the lab and are being
packed for shipment to LASTI.
- New cables, connectors and
parts needed for the LASTI install have been ordered and are being shipped
to MIT.
- Installation of the quad
controls at LASTI will begin Feb 13.
AdL ISI
- Cable and connectors for
fabricationof the internal pod cables for the STS2, GS13 and L4Cs are
in-house. Cable assembly will begin this week.
- A
design for the L4C preamp is complete and should be ready for review later
this week.
From: Rolf Bork
<rolf@ligo.caltech.edu>
- Visited MIT last week. We held
an informal review of the control system designs we plan to implement and
further discussed requirements. A
few noteable items came out of this:
- DSpace will be used in the
initial testing of the quad.
Therefore, we will install the electronics to support this the week
of Feb. 13. The new Ligo style controls and electronics will be installed
later, probably early April.
- The new HEPI controls
installation will wait until early April or whenever the new quad controls
go in.
- A DC power distribution rack
will be placed in the optics lab and conduits for distribution of DC power
will be run to the various rack locations.
- The Ponderomotive system will
require control rates of 64KHz for the global loops and 500KHz for the PSL
loop. The 64K loops should be relatively easy to implement, but doing the
500KHz loop in a digital implementation is more interesting. I started
doing some tests with what we have here now and was able to get a small
loop running at a ~1.5usec cycle time. This loop included 8 ADC channels,
8 CDS filter modules, and 8 DAC output channels. These tests are just
preliminary, but at least the 500KHz loop is looking within the realm of
possibility without some sort of new hardware, such as FPGAs.
Core Optics
From: GariLynn Billingsley
<Billingsley_G@ligo.caltech.edu>
CSIRO visited January
30th. We discussed the privatization of the Australian Centre for
Precision Optics," the name by which the group will be known in the
future. The process of privatization will take between 1 and 2 years.
We also discussed the
polishing requirements of Advanced LIGO as known to date. We indicated
our plans for future procurements (LASTI and Pathfinder). The coating
development program was discussed, see Helena Armandula's report for details.
From: Helena Armandula ahelena@ligo.caltech.edu
Advanced LIGO Coatings
CSIRO
delivered a Lu doped Ta2O5 coating on a thin and thick 3" dia
substrates. The 3"dia. thick
substrate was shipped to Glasgow from Caltech
and the thin substrate will be sent to MIT from Australia.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
AdLIGO PSL
I
have been running into some problems relating to installing the device drivers for
the DSP board. There might be some issue with the 64-bit operating system
and the current version of the USB driver. Apart from that I have been
reading up on the various application notes on the Xilinx website.
AdLIGO IO (courtesy of
Dave Reitze)
Testing
of the AdLIGO Faraday isolator was finished for power levels up to 100W.
The
requirements for the Faraday isolator magnetic fields was developed.
The
EOM development was completed. Preliminary design documentation for both
the isolator and modulator is currently being prepared.
A
CO2 laser based adaptive mode-matching telescope has been tested.
Auxiliary Optics
From: Michael Smith <smith@ligo.caltech.edu>
VERTEX LAYOUT
I have modeled the IO
optical train in ZEMAX.
SLC
Hiro is still working on
obtaining transfer functions for scattered light noise in ADLIGO.
Other Laboratory R&D
From: Riccardo
DeSalvo desalvo@ligo.caltech.edu
Valerio, Virginio
We have finished to
develop a 3D Maple model of the HAM-SAS springbox. Each of the four GAS springs
is represented mathematically as an ideal spring attached to a mass M, that is
connected to a rod, free to rotate around a point, supporting a mass m. Various
asymmetries, such as uneven position, resonance frequency, level of attenuation
of the springs, can be easily introduced changing the initial parameters of the
model. This allow us to study many possible configurations of the system.
Since our Maple script generates a state-space representation of the system,
the model can then be imported in Matlab and used in control simulations.
We are now completing an
equivalent model for the HAM-SAS horizontal stage.
This model is a lighter
and probably easier to handle complement to the model recently developed within
Ideas by Dennis.
Yumei
made model of inertial
Eddy current damper in Solidworks, and implemented it into Ansys to simulate
and design its flex joints.
Justin, Sean
finishing report of
silicon flex joints, waiting for internal feedback.
Riccardo
working on production and
installation issues of HAM SAS in LASTI.
For additional information about this report, contact Stan Whitcomb or Phil Lindquist