Weekly Report for
Week Ending January 26, 2006
The LIGO Executive
Committee Agenda for Monday,
January 30, 2006 will be:
(Meeting time: 10:30 am Pacific Time)
1. Announcements
2. Comments
on Weekly Report
3. LSC
Issues (Saulson)
4. LIGO
Lab Operations
- Administration
(Lindquist)
- Sites
(Raab, Zucker, Shoemaker)
- Commissioning
(Fritschel), Detector (Coyne)
- Campus
Research Facilities
- 40
Meter (Weinstein)
- TNI
( Libbrecht)
- LASTI (Shoemaker)
- Data
Analysis and Computing (Lazzarini)
5. R&D
and Advanced LIGO (Shoemaker)
6. CHANGE CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION AS
NEEDED
- Change Request CR-060002, Augment
the recent order for the CIT LDAS cluster to add another 77 nodes plus
miscellaneous accessories (e.g.,racks,
cabling).
Special Items:
Advanced LIGO Review Preparations
- Personnel
Plan
- Project
Execution Plan
- Advanced
LIGO Operations Plan
- Proposal
Update
Special Announcements:
Weekly Report Highlights
Another meeting of the ad hoc committee on the SciMon
system was held on Wednesday 25 Jan. A consensus recommendation was drawn up by
Rai Weiss, and submitted to the Directorate, who will
announce a new policy next week.
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
- Southern,
Trinity, Loyola, LSU and GEO MOUs were completed
and submitted to Saulson for review and
signature.
- Carleton, Hobart, IAP, UWashington
and UTA require additional documentation before their MOUs
will be complete and submitted to Saulson for
final review and signature.
SITE TELECONFERENCE (Jasnow)
- A
site teleconference was held Thursday, January 26, 2006. The following issues were discussed:
- There
was a discussion of the items purchased from JDSU, the successor company
to Lightwave.
The discussion centered on whether the items purchased under a
separate purchase order met the requirements to be classified as
equipment. After several opinions
were expressed, it was concluded that these items did, indeed, meet the
requirements for equipment.
- Also
discussed was the purchase of tooling and other items from JDSU so that
LIGO staff will be able to maintain the lasers, since JDSU wants to leave
the business. It was agreed that we
will try to purchase these items under the original contract now with
JDSU.
- The
construction of the LLO
Science Education
Center has recovered
its original schedule with the completion of the steel structure.
- With
the arrival of the second representative from the University of Florida
at LLO, the question arose as to whether or not these staff members
required visitor appointments.
After some discussion, it was agreed that they do not.
- There
was a discussion of the status of docents at the site. It was reported
that they are considered "authorized volunteers" and are covered
by at least workmen's compensation.
It was agreed to distribute the forms that they have to sign, see
if there is additional coverages, and determine
whether this category could also apply to student volunteers in lieu of
visitor appointments.
- A
revised FY06 budget model is being prepared and will be reviewed by LIGO
management to determine available funding for FY07 and FY08.
- The
list of assigned actions updated through December 01, 2005 (the last update)
will be found Here.
PROPERTY MANAGEMENT (Luna)
>
- Nothing
significant to report.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
Scanning
- The
last box of Asiri documents was finished -- we
now have more than 30 boxes ready to destroy once CD's have been burned.
- Scanning
began on all the contractual close-out files as this set of documents will
reduce two full file cabinets of paper.
Additionally, this group is fairly organized and easy to scan, name,
and bookmark, and will require little supervision.
Synergy Software
- Work
continued on reviewing the tables of our current system, and doing any
housekeeping necessary to make clean carry over into the new system. The table identifying the various types
of media was matched to the corresponding documents for each type.
- Another
table worked on, and the bulk of effort for the week, was the keyword
table. After identifying duplicate
or similar entries and cleaning that up, a master list of documents linked
to each keyword was created. This
list involved nearly 150,000 records.
The number of documents associated with each keyword was
determined. From this analysis, we
will be able to make better design use of the historical data as well as
design the use and user's process for keywords in the new system.
- Tomorrow
I will be receiving from Ian at FileHold the
first rough cut of conversion and installation requirements. Together we will work on a solid draft
that will be distributed for review and comment. Distribution to the committee is
anticipated by the third week of February.
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- Processed
a large set of seismic drawings recently submitted by Ken Mason.
- Editing/renaming
a large batch of scanned files.
- Scanning
Project--Progress continues on scanning of miscellaneous boxes/files
of documents.
- Activity:
|
Week Ending
01/26/2006
|
In
|
Out
|
|
Packages
|
20
|
8
|
|
Faxes
|
20
|
26
|
FINANCIAL SYSTEMS (Cronin, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Placed
orders on pcard as requested. Made arrangements for exchange of the
assembly sent in error by the vendor. Ordered additional replacement parts
for the equipment.
- Coordinating
the renewal for Year 2 of the computer maintenance agreement for hardware.
The requisition will soon be submited.
- Completed
change order #15 to Praxair and submitted it to the vendor.
- Completed
the order for the compressor rebuilt for LLO.
- The
order for the oscillators was submitted for approval and the purchase
order has been submitted to the vendor.
- Submitted
the new consultant order to Squid. It is pending their signature.
- Provided
additional training to requisitioners on TechMart.
Responded to inquiries pertaining to TechMart
invoices, authorization limits, and order workflow.
- Working
on the change order to add an additional 77 units to the large ASA order. Working
on several no-cost extensions submitted for the subcontracts.
- Submitted
the fully signed consulting agreement to Eric Myers.
>From: Florence Kaufman <fkaufman>
- Completed
and sent out reports for DIA, Hanford
and Livingston Discretionary accounts, US India Award, MIT Grid Award, Low
Noise Award, and the Hanford Conference Account for activity through
December 2005.
- Attempting
to resolve an issue where the 40-Meter account was charged for health
insurance payments for a visitor beyond the period of the visit.
- Working
with P. Lindquist to adjust the FY06 budgets to reflect the latest
information such as current labor rates, change requests, and
modifications requested to original budgets.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- The
consultant contract for Eric Myers to perform outreach work under the subaward from Fermi Laboratories has been issued.
- A
teleconference was held with Carol Wilkinson, Rod Luna, and import broker
Roger Bichard to discuss ways of minimizing
import duties on silica substrate blanks imported from Germany and paid for by the U.K. The substrates are currently here on a
temporary import bond, which avoids customs duties, but requires that the
items be exported within three years.
Further research would be performed by the broker to determine the
best course of action.
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
- Worked
on the usual new trips, expense reports, reconciling, calendar
reservations, and itinerary entries.
>
>Dorothy Lloyd
- Processed
the usual requisitions for POs and payment request, and approved and
submitted the weekly incoming invoices to accounts payable for payment.
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
- Change
Request CR-050010, Prototype Seismic Attenuation System for the HAM
Chamber (HAM-SAS) was submitted by Dennis Coyne. If approved, the change request will add
the fabrication and test of a predominantly passive, seismic isolation
system prototype for the HAM chamber, to the Advanced LIGO R&D
program. This request is being held
pending a written report and recommendations.
- Change
Request CR-060002, Augment the recent order for the CIT LDAS cluster to
add another 77 nodes plus miscellaneous accessories (e.g.,racks, cabling). The request was submitted by A. Lazzarini. I
have it on the agenda for discussion January 30, 2005 during the Executive
Committee meeting. A .pdf version of the request has been distributed
electronically.
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- A Staffing Committee meeting was held on Monday,
January 23, 2006. All files for the
Staffing Committee are up-to-date and posted on the SC web page. The minutes and action items from the
Staffing Committee meeting have been posted on the SC web page.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
- We have started the LIGO campus lab safety
audits. One general observation
regarding the labs audited so far is the need to improve
"house-keeping" and disposal of boxes/containers.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of
Commissioning Activities at LIGO Hanford
Observatory (compiled by M. Landry)
Science run and commissioning highlights from LHO are bulleted below:
- Not
since Boucher's streak of 04 has there been so many consecutive saves: the
demod phase in ASPD5 was adjusted to minimize
junk, now transitions from ASPD1-4 to 5 have a smaller DC jump, producing
more lock saves
and fewer lock losses. More here.
The save rate is thought to have quadrupuled.
- excess
low frequency noise
since S4 will hurt the continuous wave search (crab spindown)
and the stochastic search (bbn upper limit)
- burst
and inspiral injections resumed on both machines
- the
UPS system that supplies power to many cpus failed
on Thursday, taking out hanford1, fb0 and fb1, and both IFOs
4K IFO
- an
H1 spectrogram from S5 was posted
- noise
trending down from 18 to 17 Hz over several-minute timescales was seen in
both seismometers and AS_Q
2K IFO
- Glitching, initially attributed (erroneously) to TCS
parameter modifications were in fact due to a glitching
MMT3 optical lever laser, which was swapped out. We continue to run with
those new TCS parameters and 2k ranges have been improved
- the
H2 duty cycle took a significant hit on Wednesday when the machine was
offline for the day due to a harddrive failure
on h2susepics
DAQ
- H2 received new code, include the whitening filter module for DARM_CTRL
output.
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
L1 Interferometer in S5 (Franzen)
The duty cycle was around 55% with an inspiral
range between 9-10.5 Mpc. Late Friday January 20:th
an LVEA HEPI Streckeisen STS-2 seismomter
failed. The instrument was therefore off-line until Saturday afternoon when we
received a spare unit from MIT. Since then the interferometer has been running
smoothly except for some periods when the ASQ software trigger went off without
any apparent reason. The problems we
observed in the WFS4 chain some time ago has not reappeared. The construction of the outreach center is
rapidly proceeding and has reached a state where we can keep lock during some
periods of the day if the seismic noise from other sources is low.
Commissioning highlights:
- The
atomic clock was swapped.
- There
was an LSC code drop.
- The
HEPA blower to the ISCT4 table was turned off in order to reduce the
coherence between the accelerometers and DARM observed at 235 Hz.
- The
modulation index at 25 MHz was increased by 1 dB in order to get some more
sideband power. This seems to have increased the inspiral
range by something like 0.5 Mpc.
- The
ASQ trigger threshold was increased a little in order to reduce the
frequent science mode drop which have been observed.
- It
was observed that the harmonics of the bounce mode are mostly gone thanks
to the change of the beamsplitter dewhitening electronics last week.
L1 CDS (Bogue)
- Our
atomic clock came back from being repaired. Swapped that in and reset the timing
distribution system.
- Began
working on the new 3511 disk array for fb0 with the help of Dan Kozak. Right
now we are verifying that the firmware is completely updated before
beginning the data transfer.
- Worked
on a boot problem with the LSC front end.
- Had
a meeting with Shannon and Dave to work out a time line for when new
security measures would be implemented in cds.
LLO Outreach (Thacker)
- Assisted
teacher Professional Development onsite, Saturday, Jan 21st; Math/Science
Partnership, SELU and Tangipahoa
Schools
- Conducted
educational outreach for Sacred Heart Homeschool
Group on-site, Friday, Jan 20th.
- Prepared
for Teacher Professional Development workshop upcoming Friday/Saturday,
Jan 27th & 28th.
- Conducted
educational outreach off-site at Louis Vincent
Elementary School
(Young Astronaut Club) on Thursday, Jan. 26th.
LIGO SEC Construction (Zucker)
The foundation slab was poured and finished Tuesday; structural steel was
delivered concurrently and is now being erected. The building envelope is
taking shape quickly. So far the
steelwork is much less vibration-intensive than excavation and concrete work,
so we're actually grabbing some science hours during the day. Hope this lasts.
Computing and Network Security (Roddy)
- Last
week was spent at LHO installing an IDS and
discussing security with Dave and Albert.
It was a productive week and several issues were solved.
- Had
a laptop die here and I am working on migrating the user's data to a new
one. This is proving to be a bit
difficult due to some quirks in the backup software.
- The
backup software died on Tuesday due to running out of inodes
on the file system it was installed on.
I have worked with Arkeia tech support
and have things up and running again.
- Ordered
various bits of hardware.
- Working
out some storage space for drawings, etc. on site. This will need to be shared storage
between a few people here.
- Had
a telecon today to discuss DMT account &
gateway issues.
- Working
with Dwayne on setting up our LLO spam filter.
- Reviewing
much of the NIST FISMA guiding documents.
We will likely need to revise many of the LIGO security
policies/documents to reflect requirements that are contained in these
documents. The NSF references these
documents in their draft guidelines.
General Computing (Giardina)
- applied
more windows updates to kantech security server
- CanIt appliance server install wouldn't work on the
new Sun Fire x2100 server with only USB keyboard and mouse. Tried with serial console redirect,
still didn't work. Started
installing it on another server. not yet
completed.
- going to rebuild a spare PC for Janeen,
started earlier this week, but disk needs to be replaced.
- reset whawkins email and
desktop passwords.
- Norton
would not update on mfyffe's PC. Ran online scan that found one bug. Removed it, then Norton updated
successfully.
LDAS Admin (Giardina)
- tapes
ejected and shipped to CIT: LL0856,
LL0865, LL0867, LL0869, LL1710, LL1712, LL1715
- LL1700
- LL1706 imported into L700 library
- restarted
samd when import would not start
Data Analysis (Yakushin)
Storage/Condor/LDAS admin:
1) Moved ldas-gridmon
functionality from node2 to the old VPN machine;
2) Sprayed S4 L3 RDS, h(t), some burst MDC sets and GEO data
on the nodes to speed up S4 LIGO-GEO burst analysis and the remaining tasks for
S4 LIGO only burst analysis;
3) Upgraded firmware on the two new 3511 units; built RAID5
logical drive on each unit with two global spares.
Data analysis:
1) Still testing the modified version of waveburst
in which whitening procedure is improved and linear predictor filter is used.
Production triggers look good. Studying the sensitivity and
event property reconstruction on burst MDC frames.
2) Optimizing the procedure for generating waveburst scalograms of
interesting triggers. Currently triggers are processed sequentially which is
too slow.
E2E (Jamal, Yoshida)
Considered the effect of pitch misalignment of MC1 (the input flat mirror in
LIGO I Input Mode Cleaner) on the MC transmitted lightþfs
beam shift. Analytical investigation
with the actual parameters (the mirror curvature, MC length etc) indicates that
if MC1 pitches up/down by a pitch angle (theta_pitch)
and if the MCþfs LSC (Length Sensing Control) on MC2
works ideally, the MC transmitted beam pitches up/down by 0.99 times theta_pitch, and, at the same time, the MC transmitted
light shifts vertically (if theta_pitch is
upward/downward, the transmitted light shifts upward/downward) by 5.2 times theta_pitch (for example, if theta_pitch
= 1e-6 rad, the transmitted lightþfs
vertical shift = 5.2e-6 m where the MC beam diameter at the waist is 1.6 mm).
If the MCþfs Angular Sensing Control is engaged in
addition to LSC, the vertical shift of the transmitted light becomes zero while
the beam pointing is the same as the case where the LSC only is engaged. Similar analysis on MC1þfs yaw and position
misalignment is in progress.
Initial LIGO Detector Science & Engineering (Coyne)
Nothing significant to report for IL
DET/TEC.
40-Meter Interferometer (Weinstein)
IFO commissioning
- Rob
and Rana made some progress in deterministic
locking (lock acquisition by slowly bringing mirrors into alignment
without needing to wait for them to swing through resonance in an
uncontrolled way; and using normalized DC signals which are insensitive to
changes in other degrees of freedom). They can deterministically lock the
PRFPMI, with either a CARM offset or a DARM offset. Re-aligning the SRM
didn't work, but they got lots of ideas for things to try next.
- Dan
and Monica are making some progress in understanding the noise budget code
and adapting it to the 40m.
- Osamu
and Ben are at LHO for shifts. Rana is on
vacation. Not much activity this week.
IFO modeling
- Monica
continues to work on her e2e simulation of the 40m optical configuration.
She and Hiro found a 2pi bug in her pendulum
filter; now, the optical spring peak is in the right place. She continues
to work on her control system. She is measuring transfer functions with
varying demod phases.
DC detection development
- Rob
is assembling all the in-vac hardware for the DC
readout beamline.
- Rob
is drawing up a complete list of channels, cabling, etc for the DC readout
control and monitoring. Looks like we might need another Pentek ADC. And, we need a PZT driver for the output
mode cleaner, and PZT drivers for the steering mirrors. The PZT steering
mirror on th BS chamber
has no available in-vac caling.
We might have to drape a cable over from the Input Optic chamber.
- Dan
and Sam continue their measurements of the PZT steering mirror
performance. There appear to be so many resonances, as low as 150 Hz, that it may prove impossible to get an alignment
servo UGF much higher than ~ 20 Hz. They are experimenting with changing
the mirror or the DLC mounts.
- Steve
is purchasing various items needed for the DC readout: in-vac beamsplitter with
3degree wedge; SR 830 digital lockin amplifier,
etc.
Lab Infrastructure
- Bob,
Steve and Alan are getting the 40m ready for the safety audit that will
take place this Friday the 27th.
- Bob bought a load of booties and gloves for the 40m
and South Annex labs.
Thermal Noise Interferometer (Black)
Akira has been measuring Q's by ringdown of various mechanical modes in the TNI's output mirrors, in preparation for the ring-damper
experiment. We had tried, at first, to
measure and catalog the Q's from passive observations of the intrinsic
excitation, presumably thermal. However,
our mirror Q's are relatively high, and measuring and
fitting the extremely narrow peaks proved impractical. The ringdown
measurements are going much better and are producing cleaner results.
LASTI (Ottaway)
Quad Controls Prototype Tests
The solid stack assembly for the quad is now more or less complete. Some of
the screws for the stiffening I-beams had to be shortened and are now waiting
to be re-baked. They will not be ready until next week but they were not
crucial to the rest of the assembly.
MC Double Triple Test
Installation into the vacuum will begin next Monday.
Ponderomotive Tests
Installation into the vacuum will begin on Friday.
LASTI Electronics
Jay, Rolf, Rich A and Mohanna visited MIT to plan
the electronics for upcoming LASTI installations. It was decided that the
initial installation and commissioning of the Quad Controls prototype would be
done with Dspace and would then be converted to LIGO
style controls in time for interfacing with the internal seismic stage.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Yamamoto)
QuadFP (Hiro)
The QuadFP made by Matt was modified to study a
high power adv.LIGO arm cavity with alignment
DOF. A basic study is under way, and,
this will be handed off to Osamu and Rana to design
the alignment control of a high power system.
40m model (Osamu, Monica)
Osamu is building a 40m simulation setup. He asked from Hiro
several new features and changes of functionalities of e2e. Hiro
will address some of the requests.
Monica keeps working to validate the locking loop of her setup of 40m
model. The dependence of the optical
response of the 40m from the demodulation phase is under investigation. After Bruce fixed the ALFI bug the extraction
of the signals from bundlers is fine and the feedback signals can be sent from
the LSC to suspensions. The previous configuration with the lock of the central
part of the interferometer has been confirmed; the control of the others degrre of freedom is in progress.
MC dynamics and noise [Sany Yoshida]
Considered the effect of pitch misalignment of MC1 (the input flat mirror in
LIGO I Input Mode Cleaner) on the MC transmitted light™fs
beam shift. Analytical investigation
with the actual parameters (the mirror curvature, MC length etc) indicates that
if MC1 pitches up/down by a pitch angle (theta_pitch)
and if the MC fs LSC (Length Sensing Control) on MC2
works ideally, the MC transmitted beam pitches up/down by 0.99 times theta_pitch, and, at the same time, the MC transmitted
light shifts vertically (if theta_pitch is
upward/downward, the transmitted light shifts upward/ downward) by 5.2 times theta_pitch (for example, if theta_pitch
= 1e-6 rad, the transmitted light™fs
vertical shift = 5.2e-6 m where the MC beam diameter at the waist is 1.6 mm).
If the MC fs Angular Sensing Control is engaged in addition to LSC, the vertical shift of the
transmitted light becomes zero while the beam pointing is the same as the case
where the LSC only is engaged. Similar
analysis on MC1 fs yaw and position misalignment is
in progress.
Alfi [ Bruce, Melody ]
Almost all the issues in PR have been addressed.
Main work in this week is the refinement and bug fixes of alfi bundle. This
is a very useful function to clean up the code and to make the maintenance very
easy.
Data Analysis Activities (Lazzarini)
Brown
- Attended
inspiral f2f in Milwaukee last week.
- Continued
theoretical work on LIGO EMRI project.
- Met
with Diego to try and track down problem using LAL spinning waveform
injection code to generate 1.4-100 M_sun inspirals.
- Helped
Lisa debug problems with the ringdown search
software injections.
- Went
through the steps necessary with Lisa to complete the coincidence part of
the ringdown analysis.
- Fixed
some bugs in the new data quality flag tool for Keith; he is now testing
it.
- Started
looking at S5 hardware injections.
Chatterji
- Investigating
LHO and LLO data quality and detector glitches from Jan 19 through Jan 22.
- Installed
QScan on the LHO computing cluster. It is now possible to launch QScan jobs on the cluster using the Condor
scheduler. Working on improved
documentation and a simple interface for remotely launching QScans.
- Working
on methods paper describing Q transform tools for gravitational-wave data
analysis.
- Verifying
the performance of null stream based coherent network analysis methods
when both H1 and H2 are included.
Collaborating on paper describing a consistency test based on a
modified null stream approach.
Dupuis
- Investigated
noise sources near Crab and other pulsars in S5 TDS analysis
Mandic
I finished the all-sky stochastic reanalysis of the S4 H1L1 and H2L1 data,
with the new version of the calibrations. I have also recalculated the H1L1 and
H2L1 DARMERR coherence, both at 1 mHz
and 0.1 Hz, and recovered all stochastic hardware injections performed during
S4. No surprizes were found - we still have to notch
1 Hz harmonics, the sign of the hardware injections is correct etc.
With Sam W., I calculated the S5 H1L1 coherence over the whole run (so far).
We observed the structure at 60 Hz and 100 Hz, that was
already found in the previous calculation by Nick F., but we found that
the structure comes from two particular intervals during the run. More study
should follow.
I am also working on several changes to stochastic.m
- in particular, I am moving the post-processing steps (including the
definition of badGPSTimes cut) into stochastic.m, so that the post-processing time is
minimized. This is becoming important in the online analysis, where there are
already many jobs to post-process. I am also making modifications to make
time-shifting easier.
Shawhan
- Diagnosed
S5 science-mode segment numbering anomalies due to computer reboots.
- Worked
with Vuk on fixing bugs / improving log files
for hardware injections.
- Tracked
down problem with ringdown software injections
in LAL.
- Reviewed
S4 Hough pulsar search code.
Sutton
I've been working on my paper analyzing and quantifying burst search
sensitivity to the waveform space detectable by LIGO, mainly estimating the
variation of the sensitivity of excess power searches over the cheese. I've also done a little editing of the
network analysis / null stream consistency test paper (GWDAW proceedings).
Yakushin
1) Still testing the modified version of waveburst
in which whitening procedure is improved and linear predictor filter is used.
Production triggers look good. Studying the sensitivity and
event property reconstruction on burst MDC frames.
2) Optimizing the procedure for generating waveburst
scalograms of interesting triggers. Currently
triggers are processed sequentially which is too slow.
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS
As part of the effort to resolve the 64-bit run time issues, tcl was upgraded to 8.4.12 on tandem-ii. This has caused
several other problems to present themselves. The corruption of list variables
was solved by insuring that the list was always initialized. Other
issues that remain deal with TCL panics. These are currently under investigation.
To reduce the kernel time when doing I/O within the frameAPI
at the sites, a work around was presented to the administrators which allows
them to set values for individual devices. The full solution of supporting file
system types and ensuring the proper setting of the DEVICE_IO_CONFIGURATION
variable via the resource file paradigm is well under way.
Work has also started on using service certificates in place of host
certificates. This work is being done on a tandem system and should soon find its
way to ldas-dev.
System testing was performed on LDAS 1.8.65.
TCLGLOBUS
Data transmission lockup when using the TCL Channel interface have been resolved (PR#44). This was accomplished with the introduction
of a 4-byte prefix which contains the message length to every message. This new version of tclglobus
(0.4.42) is currently running on ldas-dev.
GRID COMPUTING
Attempts to generate DAGs with 2000 - 4000 DAG
nodes that represent production using gencdag have
failed apparently due to resource limitations on a submission engine running on FC4 with
Java 1.4. The problem has been reported to vds-support
and VDS engineers are examining the problem.
Developed a DRAFT proposal for an SRM test bed with Alex Sim, Senior member of the SDM staff.
Both Kent and David attended the OSG Consortium Meeting this past week.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Helped
Lisa work on getting the new LLO 3511 (fb0_frames) configured.
- Worked
on archiving problems at LHO and tuning for all 3 SAM-QFS instances.
- Swapped
failed 3510 disk here at CIT.
- Generated
list of old tapes to eject at LHO (twice).
- Worked
on LDR problem caused by h(t) files from LHO
being md5sum'd while they were being written.
- Counted
up CACR tapes in our silo.
- The
usual ingesting of S5 data.
(Phil Ehrens)
- Working
with Mary Lei and Michael Samidi to get
LDAS-TEST up and running LDAS. All necessary configuration and setup
information is linked from the sys-admin wiki at
LDAS_Machine_Configuration.
- Replaced
bad disk drive in node129.
- Investigated
strange NFS dropouts on ldasbox3 and ldasbox5, both of which were losing
their mounts every 20 minutes.
- Made
up 20 bundles of 6 network cables each for new cluster nodes. (There are sufficient cables for ~150
nodes bundled as of today.)
- The
usual various grid certificate related activities.
(Erik Espinoza)
- Deployed
42 new nodes from ASA.
- Reconfigured
IPMI IP addresses.
- Submitted
bugzilla for 3ware calltrace.
- Rewrote
kickstart file to use rsync
for file changes.
- Troubleshooted node116 and node125.
- Updated
wiki docs for:
- Using
"ldas-kickstart".
- Properly
shutting down condor on nodes.
- Gateway
mail configuration.
- Assisted
in rack mounting of new nodes.
(Stuart Anderson)
- Helped
bring up the first 42 Opteron nodes in the
LDAS-CIT cluster.
- Placed
an order for an additional 77 Opteron nodes.
- Working
on various Condor configuration issues.
- Helped
tune the LHO system to increase 2-3x the tape archiving performance.
- Obtained
permission and moved another Sun rack over to Powell-Booth for use by
LIGO.
Livingston
(Igor Yakushin)
- Moved
ldas-gridmon functionality from node2 to the old
VPN machine;
- Sprayed
S4 L3 RDS, h(t), some burst MDC sets and GEO data on the nodes to speed up
S4 LIGO-GEO burst analysis and the remaining tasks for S4 LIGO only burst
analysis;
- Upgraded
firmware on the two new 3511 units; built RAID5 logical drive on each unit
with two global spares.
(Dwayne Giardina)
- Tapes
ejected and shipped to CIT: LL0856,
LL0865, LL0867, LL0869, LL1710, LL1712, LL1715
- LL1700
- LL1706 imported into L700 library.
- Restarted
samd when import would not start.
Hanford
(Greg Mendell)
- Last
week it was reported that the primary framebuilder
filesystem froze. The backup framebuilder
took over providing data. However,
the backup framebuilder also had problem that
produced a 192 s gap in the raw data, producing the missing GPS interval
[821756544 821756736) = Jan 19 2006 17:42:10 PST, Jan 19 2006 17:45:22
PST. Both framebuilders have been down at other
times during maintenance or due to other hardware failures. This gap is of
note since it occurred when the IFOs where
locked and may be the first gap in science mode data. However, since the
segment database gets its segments from the frames, LSCsegFind
will not return science mode for the times of this gap.
(Ben Johnson)
- A
lot of time was devoted to the slow metadata disk, and slow data archiving
problem(s). The resulted in the reduction of nfs
daemons on dataserver, (intentional) slowing of diskcacheAPI, 3511 optimizations, and SAM-FS
optimizations.
- I
have grabbed two GEO frames from charlie@Hannover.
I'm currently working on a segment extraction utility, and publisher, for
the GEO data files.
- Inserted
61 new tapes last night, which should carry us for a couple of weeks. In
general, I think we need to start ejecting all L0 S3 and S4 data.
- Setting
up FC4-based web server for Eric Meyers using a cluster node.
- Replicated
S3 L3 data to datagateway2 IDE-RAID. I have not yet edited the LSCdataFindServer's config
to point to the new units, yet.
General Computing (Wallace)
MIT:
(Keith)
Livingston:
(Dwayne)
- Applied
more windows updates to kantech security server
- CanIt appliance server install wouldn't work on the
new Sun Fire x2100 server with only USB keyboard and mouse. Tried with serial console redirect,
still didn't work. Started
installing it on another server. not yet
completed.
- Going
to rebuild a spare PC for Janeen, started
earlier this week, but disk needs to be replaced.
- Reset
whawkins email and desktop passwords.
- Norton
would not update on mfyffe's PC. Ran online scan that found one bug. Removed it, then Norton updated
successfully.
(Shannon)
- Last
week was spent at LHO installing an IDS and
discussing security with Dave and Albert.
It was a productive week and several issues were resolved.
- Had
a laptop die here and I am working on migrating the user's data to a new
one. This is proving to be a bit
difficult due to some quirks in the backup software.
- The
backup software died on Tuesday due to running out of inodes
on the file system it was installed on.
I have worked with Arkeia tech support
and have things up and running again.
- Ordered
various bits of hardware.
- Working
out some storage space for drawings, etc. on site. This will need to be shared storage between
a few people here.
- Had
a telecon today to discuss DMT account &
gateway issues.
- Working
with Dwayne on setting up our LLO spam filter.
- Reviewing
much of the NIST FISMA guiding documents.
We will likely need to revise many of the LIGO security policies/documents
to reflect requirements that are contained in these documents. The NSF references these documents in
their draft guidelines.
Hanford:
(Christine)
Nothing to report
CIT:
(Mike)
- Continued
work searching for false positives on the Spam Filters.
- Ghosted
the new DCC servers.
- Worked
more on the DCC Synergy web-server, by enabling SMTP and SSL services.
- Started
documenting the installation of new DCC servers.
- Called
in two IBM laptops one with a motherboard issue and the other had a bad battery
that is still under warrantee. One of these laptops needed to be reloaded
before I sent it back to IBM.
- Tried
to backup a users laptop but drive had bad
sectors, all backups attempts failed. I have called this into the
manufacturer to get the hard disk replaced. This is on back order.
- Other
misc. support that included restoring users e-mail, printing and a few
software/hardware issues.
(Christian)
- Created
a backup of Dorothy Lloyd's workstation.
- Installed
new local printer for Phil Lindquist.
- Replaced
toner cartridge on HP 4000 LaserJet.
- Re-imaged
3 laptops that were returned to the loaner pull this week.
- Working
on configuring a Windows XP 64 bit system for Peter King.
- Other
misc.: Continued onsite software/phone support.
(Veronica)
- LIGO: Working on possible changes in the
layout of the website. Trying
different approaches in regrouping and presenting the information in a
more efficient way. Continued
loading the test linux box, configured a
firewall. Updates to various webpages.
Updates to the roster database and several mailing lists.
- LSC: Worked on a database of LSC
presentations. Updates to the
database of talks under review.
Working on a website for the upcoming March LSC meeting.
(Larry)
- Worked
a number of procurement issues for different groups. We were able to overnight a new MAC to Livingston to replace a broken unit there. Delivered a number of newly procured
items. Ordered a couple of
workstations and will be ordering a few more for the engineering group.
- Went
through another IDEAS account setup. The default configuration file
doesn't work with the new accounts. The error message deals with the
graphics resolution but changing the memory allocation appears to resolve
the problem.
- Spent
a great deal of time trying to discover why one of the home accounts will
not work correctly on the web server. We've got a work around but the
actual cause of the problem still has not been worked out.
- Assisted
the LDAS group with a number of small items.
- Cleaned
off a few accounts and removed a couple of accounts of people that have
recently left the project.
- Still
working the new DCC issues with Mike and Linda. There are still a number
of logistical items to take care of.
- Continual
work on the spam filters.
Mail Statistics for January 19-25, 2006:
|
Mail Statistics
|
January 26, 2006
|
|
Rejected Messages
|
36,239
|
|
Virus Messages
|
521
|
|
Accepted Messages
|
16,834
|
|
Total Messages
|
53,073
|
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Systems, Management
Systems
from Dennis
Coyne
See also:
AL
Systems web page
AL Systems email
archives
Records of Decision or Agreement (RODA)
See also the RODA
status web page
- Plan
to issue a RODA for discussion/review to allow for a clear path for a
Suspension Point Interferometer (SPI) beam just below the penultimate mass
in the ITM/ETM suspensions (see comments below).
Requirements/Design
- Discussed
means to accommodate a Suspension Point Interferometer (SPI) in the Optomechanical meeting. Mike Smith prepared a 3D
layout for the arm cavity with an SPI added. Seems that the only practical
approach is to hang a mirror (~125 mm dia.) from
the reaction chain penultimate mass. Currently there is an opening in the
quad suspension structure which would allow this SPI beam. However, the
SUS group is considering approaches to increase the structure stiffness,
which include possibly closing this aperture, or reducing it.
- Held
a Systems meeting to discuss (1) quad actuator strength & magnet size
and (2) violin mode damping for the quad.
Interface Issues
See the
"Interfaces" section of the AL Systems web
page
- Nothing
significant to report
Vacuum Compatibility
Residual Gas Assay (RGA)
See also the Vacuum Bake Lab
Bob Taylor
- I
have been spending most of my time helping Calum
and Mark with the Quad SUS this week.
- I
helped Steve get the 40m ready for the safety audit that will take place
this Friday the 27th.
- I
have started a bake job on some tooling and a couple of small spacers that
will be used on the Quad SUS for Calum.
- In
my spare time I continue to do maintenance on ovens.
Scatter/Absorption Test Measurement System
Lee Cardenas, Liyuan Zhang, Bill Kells
We are waiting on the right parts from Laser Quantronix
for the 30 watt laser. We have removed
the pumping housing and found the cover screws are completely loose from its
original setting. We are changing new
housing and we'll replace new "o" rings. We also found the laser
jacket flow tube broken. All these parts are being ordered and ASA received
we'll replace.
High-Irradiance, Contamination-Exposure Cavities
Lee Cardenas, Liyuan Zhang
Changes indicated in
yellow highlight.
|
Cavity
(Location)
|
Material/Item
|
Start
|
End
|
Comments
|
|
Cavity #1
(OTF Lab,
Bridge)
|
“Cable wire” (material type?)
|
~11/17
|
TBD
|
The
cavity is once again aligned & locked. Taking measurements daily.
|
|
Cavity #2
(OTF
Lab, Lauritsen)
|
NA
|
NA
|
NA
|
Cavity
not ready. It needs some other optics(such
as: polarizing cube, 1/4 wave plate and some curve mirrors and lens) and the
electronics. We have used/borrowed some of the optics from this system to
accomplish
the completion of the other two cavities. Recently the 700 mw NPRO laser was
used for Garilynn’s experiment and it needs
to be realigned to the cavity.
|
|
Cavity #3
(OTF
Lab, Lauritsen)
|
OSEM Flexi-circuit cable,
qty ~ 45
(Helena Armandula,
SUS)
supplied by Univ. Birmingham (Stuart Aston)
|
~9/30
|
TBD
|
taking daily absorption & ring down measurements
DuPont Flexible Circuits. The whole part to be constructed
of 'flexi' i.e. no 'rigid' sections. (Stuart Aston,Univ. of Birmingham, SUS/UK subsystem)
- Start Laminate: Kapton (LF8515)
(document link: http://www.dupont.com/fcm/products/H-73244.pdf
Coverlay (x2): Kapton
(LF0110)
(document link: http://www.dupont.com/fcm/products/H-73245.pdf
DuPont Pyralux
Series - Kapton / Acrylic Adhesive system.
(document link: http://www.dupont.com/fcm/products/H-73246.pdf
|
|
Queue
Priority 1
|
2 Cleaned 50ppm transmission mirrors, 1 in dia., REO coated --
|
TBD
|
TBD
|
witness samples for the LHO vertex volume (added in
6/29/2005 vent)
|
|
Queue
Priority 2
|
Stepper
Motor (Riccardo DeSalvo,
possible SUS or ISC use)
|
TBD
|
TBD
|
Stepper Motor sample had been placed
into Cavity #1: Power dropped from 175 mW to ~25 mW after introducing the stepper motor sample, and
continues to decrease. It is very hard to keep cavity locked. The stepper
motor may have contaminated the mirrors. Will re-test when a cvity becomes available again.
To be rebaked soon using the self-heating capability of the
stepper motor (not just the oven heater controls)
|
Seismic Isolation
- 5
of 9 of the large machined parts are complete at Arland
Machine. The remaining parts are scheduled for a 2/15 completion.
- We
have received 32 machined parts this week from Limerick Machine.
- The
last of the maraging steel needed for the blade
springs has been sent directly to Lavallee
Machine. Material has been rough cut and blanchard ground.
- Racks
have been set up for kitting of screws, hardware, and other miscellaneous small
parts.
- Meetings
were held this week at MIT with Jay Heefner,
Rich Abbott, Rolf Bork, and Mohanna Mageswaren to review seismic cabling, electronics, and
controls
Suspension
From: "Mark
Barton" <mbarton@ligo.caltech.edu>
This week, as well as a lot of work in the lab with Calum
Torrie and Ian Wilmut on
the controls prototype, I did a study for Daniel Sigg
on the mechanical effect of the light in the cavity on the pendulum. There are
two components to the force, a symmetrical restoring force that tends to bring
a misalignment like // back to ||, and an antisymmetrical
destabilizing force that amplifies a misalignment like /\. The result appears
to be that the stabilizing component almost rigidifies the joint symmetrical
mode for 1 MW (pitch and yaw frequencies go from around 0.4 Hz to 5 Hz),
whereas the asymmetric mode is unstable above about 300 kW in pitch and 600 kW
in yaw.
Calum and I worked with Ian Wilmut
to develop an alignment procedure for getting all four levels of the double
chain properly aligned, and to identify DOFs where
extra adjustment was needed and DOFs where it was a
nuisance. We eventually got all DOFs aligned with the only big surprise being that the
chains were initially off by about 2-3 mm in transverse at all levels. This was
not a possibility that we had allowed for but we worked around it by slotting
the holes for the screws holding the upper blade cartridges.
From: Calum Torrie ctorrie@ligo.caltech.edu
Quad suspensions
Tomorrow, Friday we start preparing the quad for shipping to LASTI!
From: Ken Mailand kmailand@ligo.caltech.edu
I’ve completed shop drawings for the SUS installation, plate style
fixture, for Calum, and working on an assembly, the
majority of purchase
parts have been ordered.
I’m working with Mike Smith on the Adv. Ligo
Layout.
From: Jay Heefner jay@ligo.caltech.edu
AdL Quad Controls Prototype
- We
have been at MIT this week discussing the installation of the quad
prototype at LASTI.
- Rack
locations have been determined. AC power will be need for the 4 new racks
to be installed along the Xarm. These racks will
be used for the quad controls, and future suspension and ISC controls.
- Installation
of the electronics is scheduled to begin the week of Feb 13.
- The
new AA filter interface boards have been
received and are being assembled. They will be installed in the chassis
and tested starting next week.
AdL SEI
- I
have been finalizing the design of the internal pod cables for the STS2,
L4C and GS13. Fabrication should begin next week. The Fischer connectors
for the STS2 have been recieved. All other
connectors are due later this week.
- Rich
Abbott has started the design of the fine and course actuator driver.
Ponderomotive Experiment
- We
had discussions with Thomas Corbitt, Edith Innerhofer and Dave Ottaway
concerning the required electronics and controls required for the
experiment. These discussions will continue.
- The
racks for the experiment will most likely be installed near the Ymid HAM.
Core Optics
From: Helena Armandula ahelena@ligo.caltech.edu
LMA
Jean-Marie Mackowski is working on improving mechanical loss on the Ti
doped Ta coatings. He is confident that
the optical absorption on these coatings can be brought down from the 0.8 .ppm level we have now to the 0.5 ppm
Adv. LIGO coating requirement. He is
planning on tweaking the coating design, specifically the last coating layer to
accomplish that. He is also exploring
materials with negative dn/dt.
CSIRO
Roger Netterfield will deliver one thick coated Lu
doped Ta sample and a coating witness piece to Caltech next Monday.
Here is part of a report on the Lu doped Ta from Mark Gross, until now just
a thick substrate got coated:
"... we have not been able to confidently work out how much Lu is in
the film. According to XPS there is certainly an Lu
peak there, but quantification has proven to be problematic. Using the full
area of the Lu sheet that we bought (32 mm x 32 mm x 1mm - hung by a Ta wire at
the center of the Ta target), we consistently get ~3 at% Lu, 37at% Ta and 60at%
O from the XPS measurements on different runs. The trouble is this doesn't make
sense. Pure Ta2O5 would be 28% Ta and 72% O. Pure Lu2O3 (the standard oxide of
Lu) would be 40% Lu and 60% O. A mixture of the two should therefore have 60 %<
O <72 % and closer to 72% for the small quantities of Lu2O3 which we
certainly expect. The films are not
under-oxygenated since they are not absorbing and the amount of oxygen that is
'missing' would make the film almost black. We can only assume at this stage that the
sensitivity values in our XPS database aren't accurate - there isn't a lot of
info on Lu out there - in fact the XPS analyser that
comes with the XPS system we have doesn't even have entries for Lu - we have
had to use other data. On the basis of
the area of the Lu target and comparison with the results we got from the
Silica-doped Titania, which we did in basically the
same way, we should have expected ~5-10% of Lu in the film if the sputter
yields were roughly the same (that is also data which isn't readily available
for Lu) - so 3% Lu in the film isn't too surprising - it's just the oxygen is
so low.
Anyway, the refractive index of the lutetia doped tantala is only a little bit higher than TaO (2.16 against 2.14 at 633 nm) and even these values are
probably the same within error. Certainly, the 30 layer growth times are basically
the same for doped or undoped TaO.
I guess Lu2O3 is much the same optically as Ta2O5, or else it means we really
do have so little of it in there that it makes no serious optical difference.
Apart from that everything we did was the same as for a TaO-based
mirror. All the coatings are annealed at 450C for >12 hours.
We'll discuss more details during Roger's visit to Caltech next Monday.
SPIE - San Diego
meeting
Gathered some interesting information while visiting the exhibits:
John Tardif and Jim Lapp that worked for Wave Precision and were involved
with most of the LIGO I polishing, are not longer there. John is now working for Mindrum
Precision, Jim is at another outfit.
Talked with Scot Mittl, from Insaco,
they used to cut to size and shape our sapphire substrates,
they would like to do the same with Adv. LIGO fused silica substrates.
Talked with Len Mott from MLD, they have a large chamber now that could
handle Adv. LIGO Optics. They are still interested in LIGO but, only for
production type runs.
Visited the Advanced Thin Films (Ramin) exhibit,
talked with Rob Patterson they are steadily growing, they have now 16 people
working. They also started a polishing group.
Stopped by CVI - CVI bought Optical Components, a
small polishing and coating house that we use often for non-critical work. Now, with CVI's
backing they expect to grow more.
Visited REO exhibit, talked with Mark Damery and
got an up-date on the polishing schedule for the TNI substrates.
Stopped by many of the other exhibits, every company in optics was
represented there.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
(On scimon shifts)
Auxiliary Optics
From: Michael Smith <smith@ligo.caltech.edu>
VERTEX LAYOUT
In process of adding the IO optical train to the ZEMAX
vertex optical layout. Added some more baffles. Added a tube section
between HAM1 and HAM2 the size of the manifold beyond the ITM chambers with
optical viewports for possible optical lever beams.
The spool pieces that will connect to HAM1 and HAM2 restrict the IO beams, so
the IO beams will have to be moved closer to the axis of the tube.
SLC
Hiro is still working on obtaining transfer
functions for scattered light noise in ADLIGO.
TCS
Looked into incandescent IR sources as an alternative to
the CO2 laser. Commercially available small blackbody sources seem to be
limited to approx.10W total emitted power, which would provide approx 2 W in
the absorption band of the fused silica ITM. Updated the drawing of the ring
heater mounted to the ITM suspension and put into the PDM Works vault.
SUSPENSION POINT IFO
(SPI)
I Created a SW layout showing possible ray paths for a SPI. The minimum spot
size on the confocal cavity mirrors with 4000m
separation is 21 mm with a 670nm wavelength. The 100ppm diameter is 125 mm.
This beam appears to fit on a mirror located at the edge of the penultimate
reaction mass. There is also a free space between the penultimate mass and the
ultimate test mass that could be used to place a mirror attached to the
penultimate reaction mass.
Other Laboratory R&D
From: Riccardo DeSalvo desalvo@ligo.caltech.edu
Yumei
- measuring
the quality factor versus frequency of the HAM SAS IP and compare the
results with those in ANSYS
- implementing HAM SAS in Solid works.
Valerio
- working
on modelling and feedback o HAM SAS
Alberto
- still
working on the magic wand paper
Justin, Sean
- working
on final report on silicon flex joints
For additional information about this report, contact Stan Whitcomb or Phil Lindquist