Weekly Report for
Week Ending January 12, 2005
Due to the holiday we will not schedule a LIGO Executive
Committee meeting for January 16, 2006.
Special Announcements:
Weekly
Report Highlights
No report.
LIGO Laboratory Administration (Lindquist)
STATUS OF MOUs (Lloyd)
LSC MOUs and Research Plans and Progress Reports
Listed below are complete MOUs and their
attachments, which were approved and signed off by Peter Saulson
and forwarded on to Barry Barish for his approval,
after minor corrections. After Barish signs off on
these they will be submitted to the DCC.
MOU Attachments
ACIGA ACF, DAT, LAS, OPS, OPT, SUS, Z
Balearic DAT, Z
CaRT ACF, DAT, OPT, Z
CEGG SUZ, Z
Columbia DAT,
OPS, Z
Florida DAT,
ACF, OPS, OPT, OUT, Z
Goddard DAT, OPT, Z
Hobart OPS,
OPT, OUT, Z
IUCAA DAT, Z
Michigan DAT,
OPS, Z
Moscow ACF,
SUS, Z
NAOJ ACF, Z
NWestern ACF, DAT, Z
Oregon DAT,
OPS, OUT, Z
Penn State DAT, OPS, Z
Rochester DAT,
Z
SLU OPS, Z
Southern OPT, OUT, Z
Stanford ACF, LAS, OPS, OPT, SUS, Z
Syracuse DAT,
OPS, OUT, Z
UTB DAT, OPS, Z
Wisconsin DAT, OPS, Z
WashState DAT, Z
LaTech, LSU and UTA were also signed off by Saulson and forwarded to Barish
for signature, but are incomplete, missing various attachments. These will not
be submitted to the DCC until all attachments have been received.
The new MOU from outside the LSC, the Experiment "Ricerca
di Onde Gravitazionali"
(ROG) of the Istituto Nazionale
di Fisica Nucleare (INFN), is now complete with all signatures and
will be submitted to the DCC.
SITE TELECONFERENCE (Lindquist)
A site teleconference was conducted Thursday, January 12, 2006. The following were among the issues
discussed:
- SURF—we
discussed the process for posting potential projects and reviewing them to
make sure that LIGO resources are available to support the project and whether
any coordination between projects is needed. One suggestion was to use and Excomm meeting to review the proposals.
- LDAS—tentatively
planning an S5 shutdown the last week in February or the first week in March,
which would provide a window for moving the Livingston LDAS back into its
permanent facilities.
- Accuconference—A
new access number has been provided that seems to have solved the
problem. We are considering
reestablishing a contract with Raindance as a
backup.
- Property—an
inventory will be conducted at the endo of
January at Livingston. Will address only those assets in the
Caltech system R.
Luna and E. Jasnow
will make the trip. A construction
review will be conducted at the same time.
Complete inventories will be conducted at both sites before the nend of the year.
- There
are no open assigned actions. The
list of assigned actions updated through December 1, 2005 (the last time
that it was updated) will be found Here.
PROPERTY MANAGEMENT (Luna)
>From: Rod Luna <rluna@ligo.caltech.edu>
- Prepared
and send out inventory list for LLO (R. Riesen).
- Tagged
three items for S. Anderson and one for
L. Wallace.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
- Returned
yesterday from five weeks disability so nothing significant to report.
>From: Cleveland Mak mak_c@ligo.caltech.edu
|
Week Ending
January 12, 2006
|
In
|
Out
|
|
Packages
|
20
|
5
|
|
Faxes
|
15
|
27
|
- Completed processing the large batch of drawings
from Promec.
- Scanning
Project--Progress continues on scanning of miscellaneous boxes/files
of documents. Scanning is complete on
those old blanket purchase order files.
COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila,
Kaufman)
>
>From: "Brambila, Ruth"
<Ruth.Brambila@caltech.edu>
- Completed
the expenditure type change on the maintenance purchase order #S006686 to Winternals and the payment has been issued before the
due date.
- Completed
change order #30 to add the individual to assist DCC [replaces two
students who left -pel].
- Completed
the change order to Star Service and submitted it to the vendor.
- Working
on the consulting agreement for Eric Myers.
- Working
on the change order to Northrop Grumman.
- Completed
change order #2 to Excel and submitted it to the vendor.
>From: Florence Kaufman <fkaufman>
- Completed
and posted the report for the Outreach Award as of the end of December
2005.
- Noticed
that the funding showing in Oracle to date for the Operations and R&D
Award was short by approximately $240K, because there was an error when
the Sponsored Research department posted the allocation of the latest
funding installment of $16 million.
Notified Sponsored Research department and it has now been
corrected.
- Responded
to request from Project Accounting to authorize funding realignments
required so that 3 new fabrication accounts LIGO.DAQ/1, LIGO.DAQ/2, and
LIGO.DAQ/3 could be set up.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone
<gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow
<jasnow@ligo.caltech.edu>
- The
site administrators from LHO, LLO, and MIT are visiting on campus this
week for briefings from several Caltech groups. These include Purchasing and Payables,
P-Card, International Services, Human Resources, and others. This is intended to acquaint the
administrators with these people so they know who to contact in each area.
SUPPORT (Baldon, Hiroto,
Lloyd)
>Irene Baldon
- Processed
the paper work for eighteen (18) new/revised trips. At this time there are two (2) trips
completed or in the works but are awaiting the necessary paper work to
enter the P-Card system.
- Completed
sixteen (16) Expense Reports and there are twenty-six (26) reports yet to
be done. Presently there are zero
(0) reports more than thirty (30) days old.
- Arranged
for a new/updated quote from Raindance for
teleconference service; and worked on manually reentering the data from
the old Calendar Program to the new Calendar Program.
>
No report.
>Dorothy Lloyd
- Approved
and submitted ~40-50 invoices (received during my absence) to Accounts
Payable for payment.
- Processed
requisitions for standard purchases and payment requests. For more detail
see Cost Schedule Control Systems report by Ruth Brambilla.
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
DCC Steering Committee (Lindquist)
Linda will provide a status report tomorrow for the document management
system team.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
- Change
Request CR-050010, Prototype Seismic Attenuation System for the HAM
Chamber (HAM-SAS) was submitted by Dennis Coyne. If approved, the
change request will add the fabrication and test of a predominantly
passive, seismic isolation system prototype for the HAM chamber, to the
Advanced LIGO R&D program. This
request is being held pending recommendations.
- Change
Request CR-060001, Project Controls Support to Prepare for NSF
Baseline Review was submitted by C. Wilkinson. The change request
was approved during the Executive Committee meeting held January 9,
2006. Minutes have been distributed
(LIGO-M060002). The change
authorizes the expenditure of funds for temporary support to prepare for
the NSF Baseline Review of our Advanced LIGO Program currently scheduled
for May 2006.
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa
<cindy@ligo.caltech.edu>
- The next Staffing Committee meeting is scheduled
for Monday, January 23, and the DRAFT agenda has been posted.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
Nothing significant to report. Due to illness had to postpone the start of
LIGO campus safety audits until next week.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of
Commissioning Activities at LIGO Hanford
Observatory (compiled by M. Landry)
Winds progressively worsened through the week, reducing duty cycles in both
machines but particularly H1. Range and duty cycle histograms for all
three interferometers were updated and made available here.
Taking advantage of some downtime due to winds at LHO and construction at LLO,
some shorter MC commissioning tasks were attempted on the 4k (see links below
relating to MC SUS filters and WFS1 phases and gain settings).
Commissioning highlights are bulleted below:
- Opening
PEM injections for S5 were analyzed and the results summarized.
- Official
triple
strains were posted at the calibration webpage, using the S5 V1
calibrations on all IFOs.
- A
summary list
of Tuesday maintenance tasks was posted.
- Peaks
near 280Hz in H1-H2 coherence plots were tracked
to the fans used in Kepco power supplies.
- H1
continues to show heightened sensitivity
relative to H2 to anthropogenic noise (this time, local truck traffic).
4K IFO
- rms amplitudes of test mass motions
for all ITMs and ETMs
at the fundamental violin mode were calculated.
- High
Q (50) force-to-pitch filters on the mode cleaner were seen to be doing
more harm
than good. Later, lower Q (3) replacements
were made. Mode cleaner angle-to-length decoupling was performed in
two sessions commissioning sessions, first here,
then here.
- Pentek noise was high on WFS1; the module was swapped
out. As a result, WFS1 phases were remeasured and reset, as were some quadrant
gains.
- A
bug was discovered that impacted the transitioning
of the IFO from LSC photodiodes to the acquire photodiode ASPD5.
2K IFO
- 16.6Hz
noise investigations prompted a move
of MX accelerometers.
- A
hole in the enclosure associated with ISCT10 (2k as port) purge air was sealed,
reducing the impact of dust after incursions onto the table.
DAQ
- Several h2 digital controllers had to be rebooted
on Thursday in order to relock the machine and achieve a low noise state.
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
No report.
Initial LIGO Detector Science & Engineering (Coyne)
CDS
See also the CDS weekly meeting minutes in the commissioning archives.
CDS Software
Rolf Bork
- Added
a filter module to the LSC code to whiten the DARM_CTRL signal before it
gets recorded to the DAQ system. This was due to be installed in LHO2K
during this past Tuesday's maintenance period, but has been deferred to
next week.
- LHO
reported a problem with the LSC code, i.e., the shutter triggers from the
AS_Q signals were not working. I believe the problem here is that the
trigger point in the code is at the outputs of the AS_Q filter modules instead
of the AS_Q signals after the phase shifters. The code has been corrected
and is ready to be installed.
CDS Hardware
No report
DMT
No report
PSL
Peter King
A number of spare PSL Eurocards were tracked down.
Optical Metrolgy
No report
40 Meter Interferometer (Weinstein)
IFO Commissioning
- Rob
has been thinking about deterministic locking strategies, and also quantum
noise in 40m and AdLIGO.
- Rana wrote and tsted a
script to smoothly lock the dual recycled Michelson (DRMI) in a
controlled, "deterministic" way, based on an algorithm from Rob (locking
the Michelson with misaligned recycling mirrors, then slowly bringing the
recycling mirrors into alignment). It works, but will benefit from
stronger DC signals, which Rana is working on.
- Rob
has released a new, somewhat cleaned-up version of the LSC code, with gain
switching for the DC PD signals, and a "pre-Input Matrix" to
implement flexible switching from one LSC error signal to another during
lock acquisition.
- Rana is thinking about how to replace our Mach Zehnder with a single Pockels
cell, driven by a signal which minimizes sidebands on sidebands. To that
end, he evaluated the performance of the RF module built earlier to
generate 4f, 5f, and 6f signals from a 1f input. He found that the module
will work well if he adds some RF filters to improve rejection of
parasitic frequencies. He has read up on the design of suitable RF filters
and says he knows how to do it.
- Monica
and Dan are working together on the calibration of our DARM response and
the associated noise spectrum and noise budget.
PSL Re-commissioning
- The
MOPA laser chiller temperature seems to be increasing; to be investigated.
- The
PSL slow loop was unresponsive, requiring a reboot of the c1psl cpu.
IFO Modeling
- Osamu
continues to develop his e2e model. right now
it's still just a single arm. He has many details implemented (seismic
noise, stacks, pendulum, etc), with more to come. He will merge in
Monica's detailed optical plant for the full dual-recycled FPMI. The
simulation behaves sensibly for lock acquisition of the single arm. He is modelling the common mode rejection of the seismic
noise over the 40m arm length: CM noise is suppressed by a factor of more
than 10 for frequencies below 10 Hz. Next: more tuning, then move to
DRFPMI.
- Monica
continues to develop her e2e model of the full 40m optical configuration,
with length control. She can lock the DRMI plus the Y arm, but the X-arm
is problematic; needs tuning of demod phases.
She measured the OLTF with modeler_fit.
DC Detection Development
- Rob
has started to assemble all of the pieces of the in-vac
DC readout beamline on a breadboard.
- Ben
is continuing to work on the Solidworks assembly
of the DCPD mount design. I have finished the design for the beamsplitter mount, and have given that to the machine
shop for fabrication. The remainder of the pieces should go to the shop
shortly.
- Dan
and Sam have set up the DC readout beamline PZT
steering mirrors and measured the angular noise in pitch and yaw. They see
several resonances; the lowest frequency one is at 120 Hz.
- Keisuke
Goda plans to bring his vacuum squeezer to
Caltech in March and begin plans to implement it at the 40m. There is some
space that can be easily freed up on the PSL table. We hope to begin the
squeezed vacuum experiment by summertime.
Electronics, Controls, Computers
- Ben
has tuned a double-demod RFPD for our LSC
system. He has measured the frequency response, and will measure the transimpedance to compare the shot noise with an older
LSC RFPD. Now that he knows the right component values, the other two PDs can be stuffed and packaged in the near future.
- Ben
contacted Richard McCarthy for an installation drawing for the new Mode
Cleaner servo that we just got. He replied almost immediately with a
comprehensive suite of drawings that will make installation as painless as
possible.
- Rana worked on modifications to the the whitening board for the RFPD DC signals into LSC,
which will be used for a deterministic locking scheme.
- Stuart
set up a script to incrementally back up all of our minute trends and all
of our controls data (scripts, BURT snapshots, etc) to the data achive at CACR.
- We
have a new controls computer (op540m), that needs
some set-up (by Alex).
- Stefan
installed rockIFO, a script that pipes any
channel you want through any filter you want, to the speakers. Now we can
listen to the error signal on whatever loop we're tuning.
Lab Infrastructure
- Bob has been taking care
of the lab and vacuum system while Steve is off this week on vacation at
Mammoth.
Thermal Noise Interferometer (Black)
Nothing significant to
report.
LASTI (Ottaway)
This week we welcomed David Hosken to the LASTI team from Adelaide University.
He will be investigating the use of commercial optical amplifiers to scale up
the power of the initial LIGO amplifiers.
Test Stand Installation (Mittlemann and Shapiro)
After we finished leveling the test stand
last week Brett gave it a scrubbing, then we used the spacing jigs to set the
beams at their proper location. The next step is to move the clean room over
the test stand and to assembly the stiff table on it.
I have a working HEPI-controller for the BSC
in its current configuation (no stack). I am
currently taking sys-id data for sensor correction. Once that is done I will be
able to test the adaptive fir controller in a LIGO-like configuatiion.
Preparation for vent (Ottaway, Corbitt, Innerhoffer, Ruet, MacInnes)
Time this week was spent preparing components
for the double triple cavity test and the high power test cavity. This will be need to be ready for the vent next week.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Yamamoto)
Status of advanced LIGO simulation -
This week, there were many activities related this topic, so I summarize the
status, including progress.
General
There is an e2e framework, SimAdvLIGO, developed
by Matt. This has necessary parts and cabling among components. Matt gave a talk explaining the content of
the package in the today's e2e weekly meeting. A LIGO note, T060010-00-E gives
the overview of the package.
This package was used to demonstrate the lock acquisition of the 40m - like
interferometer June 2005. This model does not model any IFO's, its arm length is 40m
while the Michelson cavity size is that of adv.LIGO.
This design was used because there was no fast simulation of the dual recycling
cavity, and simulating using the 40m Michelson dimension was prohibitively
slow.
But with this IFO setup, the locking problem of the 40m at that time was
reproduced and possible scenario of locking was demonstrated.
40m modeling
Now a fast simulation module of a dual recycling cavity exists and several
complementary 40m simulation works are going on.
Osamu has created a simulation setup of the 40m stack on noisy ground, and a
FP locking was demonstrated to replicate the experience of the 40m system.
Monica has been working, based on Matt's frame work, to study the 40m inlock state.
Hiro has demonstrated the reproduction of the
optical spring effect measured at 40m experiment. He also calculated the 40m
sensitivity curve, which matched reasonably well with the theoretical
calculation, except around the optical spring frequency. e2e's simple
calculation gives too deep a dip at the frequency.
A 40m package will be built by combing these modeling efforts. This will be
used to simulate the 40m locking. Together with reproduction of the spring
effect and the sensitivity curve mentioned above, this will demonstrate that
some of the major ingredients necessary of the simulation of the full adv.LIGO system is in the e2e package.
4k Advanced.LIGO Modeling
The first serious locking study has just started last week. Matt has started
working on the locking procedure, first using a FP cavity without radiation
pressure effect. (See his report below)
This simulation uses only plane wave approximation.
The suspension system uses the state space model calculated by Mark Barton.
Both triple and quad pendulums are included. ETM and ITM are parallel quad
pendulums. There is a version which
includes violin modes. One can choose to use either one with or without violin
modes, depending on the requirement of physic and speed.
The seismic isolation system of Adv.LIGO is not
available yet. Sany Yoshida is trying to incorporate
the state space model of the active BSC system provided by Brian. For now, based on the (required) spectrum
specification of the table top motion of adv.LIGO HAM
and BSC, an idealistic HAM and BSC were made which give the required table top
motion when placed on Hanford
seismic motion.
Missing piece
The major missing simulation tool is the fast simulation of the dual
recycling cavity based on modal model. Right now, the fast dual recycling
simulation is based on a plane wave approximation. It is good for LSC design,
but ASC design cannot be done. The schedule of implementing this piece depends
on other schedules, like COC specification. The development will take several
months.
(Matt Evans)
Worked on AdvLIGO lock
acquisition with quad-pendulum suspension and limited actuation forces. The current limit on the test-mass actuator
is 20uN, and the penultimate mass limit is 20mN. These, in combiniation
with the low light level available for locking, make LA a significant challange for AdvLIGO.
Standard fringe linearization alone appears to result in a threshold velocity
close to 20nm/s. In the coming week I
hope to explore some form of guided locking in the hope that this threshold can
be increased.
(Monica Variella)
Optical spring effect obtained with the e2e package for the 40m after having
locked the central part of the interferometer (PRC,SRC and MICH) and the YARM
and with radiation pressure just on ETMs: some
verifications of the parameters are needed as the peak correspondant
to the optical spring effect is at too high frequency respect to the expected
one.
Verification of the demodulation phases for POX and POY signals.
(Osamu Miyakawa)
Finished building the seismic motion, seismic isolation, pendulum, LSC for a
FP system, and compared with the 40m data.
See 40m weekly report.
(Hiro Yamamoto)
new e2e package released. 3.1.1. Mechanical system of the adv.LIGO is more time consuming, so the state space module
has been improved to speed up. Digital
filter package has been updated to include more standard filters. Other bug fixes and user supports.
(Bruce Sears)
- Completed
implementation of importation of bundle content into not yet externally
connected input bundle ports (PR 478)
- Working
on node swap problems (PR 523) and other misc items
in PR list.
(Melody Araya)
ALFI
Finished implementing the additional features for the Info
Panel. (PR 296)
- Additional
information included such as the module type (PR 530)
- Double
clicking on different items of the list brought up their corresponding
dialogs.
Editors in the setting window are now resizable.
Modeler
Installed and evaluated the Intel C++ compiler on homam. The e2e software was successfully built using
the compiler, but there was not significant increase in performance. Unfortunately, the Intel compiler did not
produce code which took advantage of the Opteron's
features (64-bit).
Data Analysis Activities (Lazzarini)
(Mendell)
S5 SFT generation from h(t) has been started and
goes back to about Dec 17, the time for which the h(t) start. I have checked
the SFTs using SFTdumpall
and SFTvalidate from the lscsoft/sftlib
in CVS. I also put together a report on these checks and other tests. The
report is posted on the S5 investigations page here (usual pulsar group
access): http://www.lsc-group.phys.uwm.edu/cgi-bin/enote.pl?nb=puls5general&action=view&page=2
(Shawhan)
- Discussed
data acquisition and data handling software components with Lisa Bogue.
- Investigated
why science mode wasn't ended when the AS port shutter triggered at LLO
(switching to ASPD5).
- Reviewed
S2 F-statistic pulsar search paper.
(Sutton)
This week I've been editing my cheese paper and working on the metric
problem for the cheese. I've started a
paper with Maria Principe on her bursts Network Simulator project. I'm also preparing my abstract on burst and
stochastic searches for the APS meeting.
(Yakushin)
1) Studied the sensitivity of the waveburst
pipeline in S5 with respect to sine-gaussian software
injections (from SG1_S5 burst MDC frames) in the frequency range from 70 to
2000 Hz and presented the results at the burst telecon:
http://ldas-jobs.ligo-la.caltech.edu/~waveburst/S5_LIGO_ONLINE_0/Investigations/Simulations/index.html
Despite of loud low frequency glitches in L1, waveburst
pipeline is roughly 50 percent more sensitive in S5 than in S4 for the same
false alarm rate for most of the frequencies.
2) Studied L1 loud low frequency glitches detected by waveburst
and presented the results at the burst telecon: http://ldas-jobs.ligo-la.caltech.edu/~waveburst/S5_LIGO_ONLINE_0/Investigations/L1glitches/index.html
Much more
follow up study of these events is needed to understand their nature.
3) Working on the abstract for the April APS meeting where I shall present
the preliminary results for untriggered burst search
during the first few months of S5.
4) Spent several days on making event display run on ldas-pcdev1@CIT. What
works under RedHat Enterprise at PSU, does not
necessarily work under Fedora Core 4 at CIT and requires some porting. Upgraded waveburst S5 online page to use
the latest version of the event display. The next step would be to make
event display run under Condor since it takes 15-20 minutes to process a single
event on one computer.
(Lazzarini)
Developing requirements on Adv. LIG optics surface qualities.
(Brown)
- Worked
on extreme mass ratio inspiral problem with
Tapir group.
- Scimon shifts at LHO:
- The
S5 online inspiral search is working well.
There are some book keeping issues to resolve to
make sure all analyzed data is properly tracked, worked on this while at
LHO.
- Checked
new segment database for any errors: none found, everything has been
performing well.
- Fixed
a bug in pipeline.py that was causing David and Kent
problems and provided instructions for them to continue testing inspiral pipeline on OSG.
- Working
on implementing data quality flag management in segment server and writing
documentation.
(Dupuis)
- Started
to work on my second S5 monthly report for known pulsars wanting to verify
that the pulsar hardware injections are still extractable with new
parameters since Dec 22. And I will
also examine the contamination of the Crab data near 60 Hz. I had problems running the analysis which
seems to be due to a different condor version between LLO and Caltech
clusters (6.7.12 vs 6.7.14). The first S5 monthly report is available
at http://www.ligo.caltech.edu/~rejean/S5/
with username/password, lsc/lsconly.
- Worked
on proofing the F-stat paper before submittal to LSC
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS
Focused on passing objects via data sockets between 64-bit
Solaris build and 32-bit Linux build. The current working theory is that
the ILwd data objects are sending data types that are
being evaluated as different types between the two systems.
Work has started on a unit test to create a frame file that requires large
file routines to access all the data to verify that large file support is
working.
cmonClient - fix for
PR2978 - put back cmd size into each cmd through gsi channel stream to
server so each cmd can be delimited. Working on some issues with the all user cmds
test.
cntlmonAPI(server) - fix for PR2978 - put back code to include cmd size with each cmd through gsi channel stream to client so each cmd
can be delimited.
Testing: performed system test on ldas 1.8.54. Set
up data socket test on tandem-ii for Ed.
TCLGLOBUS
Investigated XIO-based Tcl channel issue in which
LDAS cmonServer receives consecutive LDAS cmonClient commands as a block. It turned out that LDAS cmonServer application needed to parse the consecutive
commands coming from cmonClient application to find
out the correct number of commands.
Continue working on Globus FTP Control (78
functions). 52 functions are tested. 16 functions are unsupported because
they're for Globus internal use. Working
on the remaining 10 functions (unit test and correcting SWIG implementation).
Working on Globus FTP Control
user documentation and tutorial.
GRID COMPUTING
Determined that the latest Inspiral pipe patches
from Duncan Brown for supporting L4 data are working. Data compression of over
9:1 has been achieved by omitting gridftp of unused
data channels.
Began exploring the use of the just released VDT 1.3.10
client for the binary inpiral job submission onto
OSG. This version will be part of the OSG 0.4.1 release scheduled in
about 1 to 2 months.
Yum updated osg-itb and osg-itb-se
and rebooted all systems.
Installed Condor-G from osg-client
cache of OSG 0.3.4 on osg-itb-se (FC4).
Validated Inspiral pipeline application on OSG 0.3.4/0.4.0-pre-release
on two Condor sites on ITB: (LIGO-CIT-ITB) and (FNAL_CMST1_TEST) using L4
data. Condor-G on osg-itb-se
submitted the 700 DAG node test.
Began testing of Inspiral
pipeline on OSG 0.3.4 PBS sites on ITB.
Con- figuration issues at TTU-TESTWULF have been discovered and we are
waiting on Texas Tech resources for fixes to be applied. Also
waiting on resources at PSU for upgrading OSG_ITB_PSU to OSG 0.3.4.
Found bugs and fixes related to OSG 0.3.4, including bad VO URLs in VO-2.1
component (upgraded to VO-4.0) gridftp data
collection for MonaLisa (being worked on by the OSG
and VDT integration team) and memory leaks in GUMS 1.1 server (GUMS 1.0.1
server will be substituted in OSG 0.4.0).
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Updated
firmware in CIT's 3511s and test 3510 to most
current versions (4.13C, etc.)
- Worked
on Solaris 10 "seeing new FC devices" problem.
- Closed
the books on M7 & M8 data transfer (all data at the sites is now at
CIT and on tape).
- Found
34 tapes at LHO to be ejected for shelf storage.
- Worked
on LDR debugging (why is nothing transferring?) and tuning (eliminating
old collections and upping the gpsStart times
for the current collections).
- Made
sure that all 40m backup data was making it to tape.
- Worked
with Sam Waldman to make his jobs play well with others (i.e. not use all
available tape drives).
- The
usual ingesting of S5 data.
(Phil Ehrens)
- Replaced
DVD drive in dataserver-test and installed
Solaris 10 Update 1.
- Made
some cable bundles for the new cluster nodes.
- Wrote
wiki documentation for numerous configuration
items on the various Sun and Linux servers.
- Configured
Sendmail on LDAS-CIT 'beowulf',
datacache*, and ldas-gridmon.
(Erik Espinoza)
(Stuart Anderson)
- Working
on leaking cooling unit in 215 Synchrotron.
- Continued
testing of new version of Condor (6.7.14) on the LDAS-CIT cluster.
- Testing
Solaris 10 Update 1 interactsions with LDAS and
SAM-QFS.
- Worked
on tracking down increasing LDR performance degradation since the start of
S5.
MIT
(Keith Bayer)
- Handling
space issues in lab to accomodate liebert 5ton a/c unit.
- Air
handler has been placed on roof of NW17.
Livingston
(Igor Yakushin)
- Condor
got confused last Sunday and refused to accept any new jobs. Restarting it fixed the problem.
- LDRed corrected SG1_S5 burst MDC set from PSU. One
problem that I have not fixed yet: out of 8353 frames, 250 remained with
*.tmp extension and never got published.
- LDAS
room upgrade status: we expect the new HVAC unit to arrive at the end of
January or beginning of February.
(Dwayne Giardina)
- yum config changes on all
Fedora Core 4 systems.
- autofs changes on ldas-gridmon to mount /imports/mirror.
- *
Tapes ejected and shipped to CIT:
LL0794, LL0795, LL0798, LL0800, LL0802, LL0804, LL0809 note LL0794 reporting media errors and
45% full.
- LL0850-LL0869
imported into L700 library
- 177
out of 209 nodes have been up for 63+ days, since last electrical
maintenance. 2 power strips have
failed and been
replaced, 1 additional power strip required reset, leaving 8
nodes that have been down for maintenance issues during this
timeframe.
- Note
there is not a "node2", as it is currently ldas-gridmon.
Hanford
(Greg Mendell)
- The
main issue this week is tracking down what causes the LHO primary framebuilder filesystem to
become too busy at times. However, S5 Data archiving, publishing, and RDS
generation continues to run smoothly, and monitoring of these has allowed
sys admins to correct minor problems as they
arise with no loss of data. Also, I have started SFT generation from h(t) at the sites.
(Ben Johnson)
- fb1 reboots have been traced to slow writing of raw
minute trends. I have captured the output of iostat
and see if this sheds light on the issue.
- Shipped
2 RAID 351x controllers to Livingston,
and fb0's old 3510 to Caltech (both went out on Wednesday).
- I
am continuing work on a metamonitor page, which
should provide a concise summary of the LDAS monitors for the scimons at both observatories.
- Replaced
the lower controller in the 5 3511's at LHO with JBOD controllers, and
inserted and configured a new FC blade in the FC switch. All went well.
- Continuing
work on publishing files which were missed previously (for runs prior to
S5).
General Computing (Wallace)
MIT
(Keith)
- Patched
a number of windows boxes
- Working
on building some linux boxes for urops
- Spec'ing and ordering several new laptops
- Installed
scsi card / drives into SB1500
Livingston
(Dwayne)
- kantech security server: door schedule was altered a while back
for outreach, schedule was left in place inadvertently and doors weren't
locked on Saturdays. it is now fixed.
- kantech security server: Windows updates
- kantech security server: alarm notifications that require
operator to acknowledge were not sounding, researched issue with Gary
Traylor and Harry Overmier, we changed some
settings and now it is working.
- Adobe
Acrobat reinstall on Janeen's laptop
- HP
755CM large format plotter belt had crumbled to pieces, received quotes
for replacement, and Bonnie ordered from local vendor.
- Installed
new Outreach image on 6 PCs in Outreach area.
- rack
mounted two new Sun x2100s with Shannon
- One
of the 2100s will be ligo-op.ligo-la.caltech.edu and will house the
associated website, eventually to server our current 'www' pages as well.
(Shannon)
- Fixed
some scaling issues on the mrtg graphs. Also fixed the bps ratings for the
interfaces.
- Found
a windows machine over the weekend that was tripping the Norton antivirus
signatures for Blodhound.Unknown. This machine is having some serious
issues and will have to be reinstalled.
This is the guest machine at LLO.
- Installed
a Wiki for some GC documentation.
- Dwayne
and I set up the two new sun servers which will host the new web server
and the spam filter. Dwayne did
most of the web server setup.
- Set
up a laptop for Nessus use. This is temporary until I can find a
more suitable laptop for this.
Fedora Core 4, Nessus, various other
network/security tools were installed.
- Patched
several machines with the windows .WMF patches.
- Installed
the latest snort signatures.
- Still
working on getting a netflow solution going.
- Made
changes to the firewall to accommodate the new ligo-op
server.
Hanford
CIT
(Veronica)
- LSC: Working on the website for the March LSC
meeting. Updates to the
Observational Results webpage.
- LIGO: Installed security patches on several
Windows servers. The rest need to
be tested for compatibility before installing the patches. Loading a test server for MySQL /php work. LIGO website updates. Working on the website for the Elba conference.
Misc. user support.
- Project
Science: Addressed the issue of
migrating the website to the ITS hosting service.
(Christian)
- Created
a backup of Cindy Akutagawa,Gina
Salone and Florence Kaufman workstations.
- Installed
new drivers on Rod Luna's system in order for him to use the
scanner/copier located in E.Bridge.
- Configured
Jay Marx's laptop to print to the network printer in Cindy and Julie's
office.
- Finished
creating the unattended Windows XP CD. The CD will include the latest Windows
security patches and additional software like Norton 10, Adobe 7, Exceed
7, F-Secure, Office 2003, FireFox, Windows
installer and WinZip.
- Other
misc.: Continued onsite software/phone support.
(Larry)
- Worked
a number of procurements. Ordered items for different groups and
distributed a number of previous orders that have arrived. Took care of the billings of other misc.
items for different people. Talked
with a number of people that will need items procured in the near
future. This includes both hardware
and software. Contacted Monarch concering the repair of the quad cpu computer. They are presently testing out the
system with the replacement parts and it should ship next week.
- Worked
a number of calendar issues. The transition of the meeting room calendars
is now taking place. The URL's will be updated in the near future.
- Resolved
a number of web related items. Most of the recent issues stem from the automount file on the web server being outdated.
- Started
the installation of a new SUN box. Depending on its performance it may be
used as a new gateway box.
- Worked
a number of DCC items. We've had a
number of hoops to jump through on getting the new system setup. Still a number of logistical items to
work out.
- Backed
up and updated the OS on the CDS core computer system. Everything worked
out OK, other then a font problem on one of the applications.
- Worked
various user account issues.
- Continual
work on the e-mail filters. Those that have provided whitelist
locations have helped in cutting down the time we have to check for false
positives.
Mail Statistics January 05-11, 2006
|
Mail Statistics
|
January 12, 2006
|
|
Rejected Messages
|
28,914
|
|
Virus Messages
|
1,552
|
|
Accepted Messages
|
15,258
|
|
Total Messages
|
44,172
|
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Systems, Management
Seismic Isolation
From: "Joseph A.
Giaime" jgiaime@ligo.phys.lsu.edu
Agenda for the weekly SEI telecom Friday, Jan 6, 2pm Eastern, 1pm Central, 11am Pacific time
Announcements - single stage plans
- Design
exercise at Stanford in two weeks with goal to produce draft conceptual
design.
BSC SEI status, Ken/ Dennis
- Arland ahead of schedule with big plates
manufacture. Limerick about 2 weeks
behind. Lavalle grinding blades and rods
for stage 0/1.
- Alignment
pin drawings sent to shops.
- Blade
load tooling appears to be compatible with new blade geometry, so Ken has
sent it out.
- Blade
spring constant measurement jig under final design.
- ASI's modified designs still need to be archived on
PDM works.
- Test
stand leveled and grouted. Next step is to adjust support beam
spacing and fitting of clean room.
LASTI dspace space - Jay
- Jay
wants to remove old dSpace system from racks at
LASTI to make room for new instrumentation; we would need to either
relocate it or put it on wheels. The consensus is that we need to
have it there somehow.
- BSC
work, adaptive modeling and FIR (Rich M)
- Adaptive
feedforward FIR filter tests are noted in an
entry in the LASTI log, using two Wilcoxsin,
accelerometers for the source and two L-4Cs as witness sensors. One DOF,
y, is studied.
- 1-40
Hz band targeted, with nice reduction right where it is needed, 1-10 Hz,
and good reduction below.
HAM control with VME (Pradeep)
ETF platform work - Brian
- Inverted
suspension cage installed on the platform, studied in air with the cage
sticking out of the chamber top. All 12 DOFs
are controlled, though no noise was studied.
- Rx
and ry modes of stage 2 changed significantly
around the cage resonance frequencies.
- Rx
and Ry active isolation performance is OK except
at the cage resonances, where there are transmission peaks.
- Next
step is to study passively damping these with a set of tuned mass dampers.
- Started
work on using the stage 2 vertical loops to damp the cage modes.
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
- Finished
up the noise prototype ETM test mass drawing with Gari
and Dennis. Dwayne uninstalled and reinstalled Acrobat so pdfs are now possible from my laptop.
- Working
on actions from Dwight about the suspensions estimate.
- Working
on fleshing out the ear alignment/bonding fixture, concepted
in T050205. Caroline has identified the ear drawing and part on the PDMWorks vault, D050169. I'll incorporate that into a goniometer/translation stage based fixture. I have a
meeting with Helena and Caroline about this tomorrow.
- Working
on an agenda for the suspensions workshop after the LSC at Hanford, tentatively
March 23 and 24.
- Coordinating
with Dave Ottaway on the quad delivery.
- Working with Gregg Harry on the issue of testing
the silica tipped earthquake stop prototypes.
From: Calum Torrie ctorrie@ligo.caltech.edu
Quad
Mark, Bob, Jay, Helena and I
worked to suspend both pendulums. We have now added all of the local control
OSEMS and these are now in the process of being tested with the new
electronics. The Global control and the electrostatic drive have also been
installed and the cabling added to the reaction chain. Some of the parts
associated with the eddy current dampers have had to be re-worked,
these should be completed by the end of the month. (Since these are an add on, they will not have any impact on the schedule.)
Install Fixtures
Oddvar sent me a DVD with all of the files on it
for the lift and transport table (the ones we are having a prototype made for
LASTI). I am in the process of adding these files to the PDMWorks
vault. In order to do this I have to first of all tidy up some of the file
history. I also plan to add a "red-line" release of the drawings
based on comments from the workshop.
Gazebo (Caltech)
Mark and I have been measuring the response of the Gazebo loaded with the
entire suspension. Details to follow.
Lower Structure
Mark and I measured the resonances of the lower structure, in 4
configurations. Details to follow.
Visits
Ian Wilmut is visiting from RAL next week.
From: Ken Mailand kmailand@ligo.caltech.edu
I’ve completed shop drawings for the SUS installation, plate style
fixture, for Calum, and working on an assembly and
list of purchase parts.
Core Optics
From: GariLynn
Billingsley <Billingsley_G@ligo.caltech.edu>
Fused silica ITM blanks arrived from Heraeus
glassworks, courtesy of our colleagues at Glasgow.
The pieces have not yet been inspected, no surprises are anticipated.
From: Bill Kells <kells@ligo.caltech.edu>
I will be trying to coordinate new TM scatter measurements during any
"intervention" period which may be imminent. To that end I have been going carefully
through all the previous observation data and analysis. Recently this has come
up also with respect to Albert L's commencing to re-analyze beam tube baffle
scattering with respect to AdL. I am providing him
with the best knowledge we have of the LIGO I situation (source).
Regrouping in this New Year we (Liyuan, myself, Garilynn) are focusing redetermined effort on elucidating the puzzle of ITM07 absorption.
So far we just don’t see in the lab what was concluded from H1 operation.
Of course we have not been exhaustive as of yet.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
Coherence measurements of the intensity noise of the Innolight
NPRO were taken. The results are being examined for consistency.
Auxiliary Optics
From: Michael Smith <smith@ligo.caltech.edu>
Solid Works Vertex Model:
I added baffles for all
additional primary ghost beams. I
changed the "straw-man OMC" to a 4-mirror design identical to the 40M
OMC, and added a SUS outline. The vertex
integrated layout model was checked-in to the PDM vault
SLC
Hiro is working on obtaining transfer functions
for scattered light noise in ADLIGO.
PO MIRROR
I established a pitch and yaw specification for the suspended BS and ITMx PO mirrors, based on the output beam position at the
PO beam viewport displacing less than 10% of the
100ppm beam diameter. ISC optics should then form an image of the viewport onto the WFS PD.
Other Laboratory R&D
From: Riccardo DeSalvo desalvo@ligo.caltech.edu
Alberto
- Written
some of the magic wand paper to compensate the GAS filter Center Of Percussion effect.
Yumei
- Working
in Solid works and ANSYS on HAM SAS.
- Measuring Q vs. frequency for the HAM SAS IP legs
by varying the load.
For additional information about this report, contact S. Whitcomb or P. Lindquist