Weekly Report for
Week Ending January 05, 2006
The LIGO Executive
Committee Agenda for Monday,
January 9, 2006 will be:
(Meeting time: 10:30 am Pacific Time)
1. Announcements
2. Comments
on Weekly Report
3. LSC
Issues (Saulson)
4. LIGO
Lab Operations
- Administration
(Lindquist)
- Sites
(Raab, Zucker, Shoemaker)
- Commissioning
(Fritschel), Detector (Coyne)
- Campus
Research Facilities
- 40
Meter (Weinstein)
- TN,
( Libbrecht)
- LASTI (Shoemaker)
- Data
Analysis and Computing (Lazzarini)
5. R&D
and Advanced LIGO (Shoemaker)
6. CHANGE CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION AS
NEEDED
- Update
on Status of Change Request CR-050010, Prototype Seismic Attenuation
System for the HAM Chamber (HAM-SAS)
- CR-060001,
Project Management Resources for Advanced LIGO (C. Wilkinson)
Special Items:
- Financial Reports through December and Deferred
Items List from FY 2005
Special Announcements:
Happy New Year!
Weekly
Report Highlights
Note
[pel]: the LSC Meeting scheduled to begin March 19, 2006 will be held in Hanford because of
the potential difficulties related to lodging for large groups. All attendees should be sure to make
reservations to and from and in the appropriate location.
The LIGO/TAMA S2 Burst paper is now published in Phys Rev D, vol. 72,
article 122004 (2005).
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
SITE TELECONFERENCE (Lindquist)
- A
site teleconference was held Thursday, January 4, 2006. The following issues were discussed:
- Lodging
in LivingstonHotel rooms seem
to be becoming available in the Livingston area. It should now be possible to support
normal functions.
- Science
Education Center in Livingston—Progress seems slower than
hoped. Steel work may not end until
the end of February. A field change
order has been issued to cover the costs related to the discovery of
additional water connections.
- The
list of assigned actions updated through December 01, 2005 (the last time
that the list was updated) will be found Here.
PROPERTY MANAGEMENT (Luna)
>From: Rod Luna <rluna@ligo.caltech.edu>
- Provided
assistance to the Detector Group (G. Billingsley) with receiving the Fused
Silica Blanks from University
of Glasgow /
Heraeus. Account Number
LIGO.OPT-5.4-NSFLIGO.FY02ON.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- Distributed
2006 Personnel Directories (including packaging/shipping directories to
MIT, LHO and LLO).
- Began
processing a large batch of HAM drawings from Promec.
- Update
on Scanning ProjectScanning of
Fred Asiri's files is complete.
Scanning has begun on miscellaneous other boxes.
- Activity:
|
Week Ending
01/05/2006
|
In
|
Out
|
|
Packages
|
9
|
7
|
|
Faxes
|
10
|
3
|
FINANCIAL SYSTEMS (Cronin, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Completed
change order #1 to Cangelosi Ward for the
removal and replacement of the waterline at LLO and submitted it to the
vendor.
- Working
on the change order to Support Services for the clerk for DCC.
- Reviewed
purchase orders and completed close outs for December 2005. Submitted the
monthly report to management.
- Working
with Calum on completing the order for the
custom-made actuator to issue change order #1 to increase the funds to purchase
all the options and accessories on the quote.
- Completed
the routing of the change order for Air Liquide.
The change order has been completed and signed by both parties. Air Liquide
notified us of a change in their billing procedures for facility fees.
Passed along this information to the appropriate individuals.
- Followed
up on the status of pending shipments on purchase orders with long lead
times. The repair of the spectrum analyzer has begun and is estimated to
be completed within the next two weeks.
- Submitted
the returned check from Gennaro so that a wire
transfer can be made in its place. Still waiting for a response on the set
up of the name.
- Obtained
the insurance certificate to complete the purchase order package on the
contractor providing the AC work at LLO.
- Attending
the weekly procurement meeting which brought up current issues and also
changes in procedures.
>From: Florence Kaufman <fkaufman>
- Completed
the monthly financial report for FY2006 Operations for activity through
December.
- Alerted
David Shoemaker about some p-card expenditures made at Caltech which were
charged to the MIT - LIGO.STO/5.1 account in December, so that he could
determine whether the charges were appropriate. As a result, Dennis Coyne is looking
into whether these charges should more appropriately have been made in a
fabrication account.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- The
contract with Cangelosi - Ward for construction of the LLO Science
Education Center has been modified to cover a field change order for a
revision to the water connections.
This resulted in an increase to the contract price of just under
$7,000.
- At
this time, construction of the LLO SEC appears to be about three weeks
behind schedule, primarily due to weather.
- A
preliminary agenda has been finalized for the visit of the three site
administrators to Caltech on February 11 - 13.
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
- Catching
up after the holidays.
>
- Reference
letters, Travel arrangements, and Holiday party follow up.
- Setting
up Jay Marx's calendar.
>Dorothy Lloyd
- No
report (vacation).
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
- Change
Request CR-050010, Prototype Seismic Attenuation System for the HAM
Chamber (HAM-SAS) was submitted by Dennis Coyne. If approved, the change request will add
the fabrication and test of a predominantly passive, seismic isolation
system prototype for the HAM chamber, to the Advanced LIGO R&D
program.
- Change
Request CR-060001, Project Controls Support to Prepare for NSF Baseline
Review was submitted by C. Wilkinson.
If approved, the change request authorizes the expenditure of funds
for temporary support to prepare for the NSF Baseline Review of our
Advanced LIGO Program currently scheduled for May 2006.
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- No report (personal time).
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
- Nothing significant to report this week.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of
Commissioning Activities at LIGO Hanford
Observatory (compiled by M. Landry)
The LHO machines ran well over Christmas (~90% double coincidence), but fell
back to more typical numbers during New Years (~80% double). Only H2
makes it's single IFO duty cycle goal, and given it takes on average H1 about
40m to return to science mode after unlocking, we have to extend H1 locks in
order to meet the duty cycle goal. Below, find several duty-cycle related
links.
Some elog highlights:
- If
only every day could be Christmas: check out the state vector from the
early morning hours of Dec 25: smooth
glassy sailing
- weather
in the Snoqualmie pass can impact Tuesday maintenance
, stranding loads west of the Cascades
- communication
losses result in the control rooms not
receiving GRB alarms (this is thought to happen fairly infrequently,
about once every 2 weeks)
- events
of the recent Tuesday maintenance period were summarized
- statistics
on all three IFOs range and duty cycle numbers
were updated
- Recall
that we had a stunt plane buzzing EY; the craft is in fact a biplane, and
the owner and pilot identified
as a physicist. Seriously.
4K IFO
- glitchiness in the FSS is a concern and we are
watching this, however it is not clear if it impacts the searches.
More on FSS glitches here.
plus, reducing the FSS ISS gain
helped clear them up
2K IFO
- while
the 2k PSL laser power derivative was positive,
this was later understood (thanks to the 40m lab) to be due to
photodiode sensitivity to humidity
- TCS
laser glitches were observed to sometimes coincide with lock losses
CDS, DAQ
- The
CDS hanford1 disk system was upgraded.
However, later in the week there were more problems
with either the scsi devices on the bus, or the
disk itself
- The
leap second: leap seconds were handled by new
framebuilder code, which promptly crashed.
Unrelated to the handling of a leap second, AWG failed on the
year-rollover, knocking the IFOs out of lock.
Conlog was upgraded
to handle a leap second. On the LDAS side, as the frame builders
were down, there was no problem handling the leap second (at LLO, raw and
minute trend frames generated errors so no RDS frame was made for that
time).
- fb0 crashed
due to raid disk problems, later restarted
and trends returned
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
L1 Interferometer (Frolov)
The 68% science duty cycle for the last two weeks is LLO's
best since the start of S5, helped by the shortened construction work
week. The interferometer BNS sensitivity
remained around 10 Mpc during quiet times and 9 Mpc during seismically noisy times. The leap second
transition was accomplished without noticeable problems, but data taking was
nevertheless interrupted on the start on the new year due to the inability of
the arbitrary waveform generator to change the year.
Other activities:
- the
IRIG-B signal for timing monitoring was connected
- a
new version of StochMon started
- two
weather stations (Y end and LVEA) have been reported working without
software crashes for two weeks
- During
Tuesday maintenance the PSL smoke detector was found making the beeping
sound due to low battery, which was audible in the LVEA. It is not known
yet when the sound started, but no DARM glitches were reported on that day
so far.
- the
initial testing of the ETMX driving chain electronics did not show non-linerity that could be responsible for up-converting
the 12 Hz bounce mode motion into the detection band
- The
dropouts of the photon calibration line were reported. The cause of the dropouts is still under
investigation.
Safety (R.Riesen)
- New
main gate to arrive within 3 weeks.
- Setting
up for installation of Retro-Reflective Photoeye
gate closing interrupter for both the main and side gates.
- Working
on the annual LLO Safety Audit schedule.
- Looking
into the latest rash of after hour site "forced door"
alarms. ### (MZ comment: weak door closers and high winds, not a
crime spree!)
- Ordered
site camera fiber transmitter and receiver (replacement for inop units).
- Performing
internal LLO property audit.
- Still
waiting for the FM-200 fire system people for the requested alarm logic
changes.
- Found
no safety concerns this reporting period.
LLO Outreach (Thacker)
- finished
2nd draft of NSF annual report for LIGOSEC
- completed
preps for Feb 1st partnership meeting
- continued
preparations for teacher workshop commencing 1/27
- provided
LLO outreach visitor numbers pie chart
- Revised
the LLO tour guidelines and developed the tour providers list for two
months
LLO SEC construction (Zucker)
Foundation excavation and concrete work is accelerating after a slow spell
during the holidays. Grade beams are nearly complete and slab lifts are
anticipated next week. Activity is still
of a nature that prevents science operation during day shift hours.
CDS (Bogue)
- At
Caltech this week where I've had the great opportunity to sit down with
various people and get a better understanding of how some of our software
works.
- Spent
time troubleshooting a hard disk problem on procyon,
the cds remote control machine at CIT.
CDS Code Development (Khan)
1) Diagnosing the LVEA Weather Station interface software. There was an
occasional drop out of communication with the Weather Station data logger. I
believe it is attributed to the serial port of the MV162-262 controller. I have
replaced the controller to MV162-333 and so far it is behaving ok.
2) Developing a matlab program to display the DC
values of the HEPI position and Geophone sensors. The software will display the
motion of the pier in a three dimensional way as to visualize the pier motion
over a period of time and also display statistics to show maximum and minimum
displacement etc.
Computing and Network Security (Roddy)
- Reinstalled
the MRTG graphs. This used to be
hosted on a machine that is no longer in service.
- Working
on getting flowtools going again. This package went away when the MRTG
graphs went away. This was a
valuable resource that was needed over the weekend and was not available.
- Started
working on migrating the user groups to a GID that is not in conflict with
linux GIDs.
- Received
and posted a copy of the ligo-op web pages from
Caltech. Dwayne or I will need to
set up a permanent home for them within the next couple of weeks.
- Usual
round of updating snort signatures, checking logs, etc. I have been updating the signatures
twice daily this week because of the Windows WMF flaw.
- Lots
of reading keeping up with the flaw mentioned above.
General Computing (Giardina)
- working
on creating a standard outreach PC image, almost complete
- installed
6 DVD-RW/CD-RW drives in outreach PCs
- usual
user support questions, html assists
LDAS Admin (Giardina)
- Brought
wrong 3511 to MSR with Lisa. it was already installed in rack before I
caught my mistake. swapped
controller during downtime(non-locked state) on next day.
- RMA'd 22 Maxtor disks
- Power
strip had tripped for nodes 55-62 Tuesday AM. resetting breaker on power strip fixed
problem. expect it to fail
completely soon, as it has already happened with two other strips.
- Nodes
56, 95, and 131 had disk errors, replaced disks. have two more in warranty to RMA now.
- Tapes
ejected and shipped to CIT since last status update: LL0512, LL1060, LL1062, LL1064, LL1067,
LL1069, LL1072, LL0791, LL1074, LL1077, LL1080, LL1082, LL1085, LL1086,
LL1089
- Tape
LL1085 was reporting media error and only 3% full. SAMU is also reporting media errors on
tapes LL0484, LL0676, LL0182, and LL0384 all currently in the library
- Tapes
imported to library since last status update: LL1060 - LL1089 and LL0790 - LL0819
Data Analysis (Yakushin)
1) Processed SG1_S5 MDC frames only to discover that they contain no
injections at all in DARM-ERR channel. Keith Thorne is redoing SG1_S5 to
correct the error.
2) Added a summary to the waveburst online page
that contains various information obtained on all S5 data up to now in addition
to reports generated daily.
3) Demonstrated that L1 generates much more low frequency glitches than H1
or H2. Trying to understand the cause
and properties of those glitches.
Initial LIGO Detector Science & Engineering (Coyne)
CDS
See also the CDS weekly meeting minutes in the commissioning archives
CDS Software
No report
CDS Hardware
No report
DMT
No report
PSL
Nothing significant
Optical Metrolgy
No report
40-Meter Interferometer (Weinstein)
IFO Commissioning
- Osamu
realigned the mode cleaner and re-commissionined
the MC WFS system.
- Rob
exercised some configure scripts for locking the interferometer in various
configurations, including one and two arms, Fabry-Perot
Michelson, and short dual-recycled Michelson. In other words, everything
except the full dual-recycled Fabry-Perot
Michelson (which comes next).
- Last
night, Rob, Rana, Stefan and Matt got the IFO to
fully lock, but it didn't hold long. They switched over to locking with
the SRM is the wrong place (opposite side from optical spring) and it
seemed to lock reasonably well. Lots of little things to tune up better.
PSL Re-commissioning
- Steve
measured the throughput of the PSL beam through the PMC (a dismal 58%;
we've seen it above 85%) and total throughput from MOPA to periscope is
only 42%. Still, it'll do for now.
- Rana spent some time optimizing the PSL frequency
stabilization servo.
- Steve
and Rana redid the layout of the PMC reflected
path to give enough light onto the RFPD to get the servo bandwidth up to
snuff (about 1.5 kHz). Steve installed a new ccd
camera in the PMC reflected beamline and
re-installed the SP camera. Bob will wire the new camera into the video
switch.
- Ben
and Rana made some modifications to the PMC
board, tuning some notches. He also re-set the demod
phase. The PMC servo bandwidth is now ~ 8 kHz with plenty of phase margin.
- Our
Mach Zehnder appears to be working well with the
new MOPA laser, but throughput appears to be a bit low. We might want to
tune up the servo board. But Rana is instead thinking
about eliminating the Mach Zehnder, and instead
developing a synthesized signal to send into a single broadband Pockels cell which will produce our two pairs of
sidebands without generating sidebands on the sidebands (or, only
generating very small AM sidebands on sidebands).
- Rana noted that our mode cleaner servo board is of an
undocumented vintage, and he had a hard time figuring out what it was
doing. He measured the OLG, and found a UGF of 22 kHz, which is pretty
low. He decided to await a new Siggian MC servo
board, which LHO will ship to us next week.
IFO Modeling
- Monica
has used her e2e model to produce a transfer function that shows a clear
optical spring peak, although it's at a somewhat higher frequency than
expected or seen.
- Osamu
continues to develop his e2e model. He is implementing the 40m seismic
noise and stacks, and is developing a detailed model of the controls,
including all the analog and digital filtering.
DC Detection Development
- Mike
Gerfen finished machining the output mode cleaner
(OMC) body, out of copper. It's beautiful. A few minor fixes to the mirror
bezels are in progress.
- Ben
is continuing to work on the Solidworks assembly
of the DCPD mount design. He talked to Rick at the machine shop, and he
said that the fabrication should go relatively easily.
- Bob
has tested the resistors that Ben and Rana plan
on using for the DC photodiode electronics; they are safe for use in high
vacuum.
- Ben
plans on testing the DC photodiode circuit that he and Rana
developed, in the coming week.
- Rana and Rob will draw up a detailed scheme for length
and alignment control of the DC readout system, and begin ordering parts.
- Sam
and Dan are beginning to build a prototype alignment servo system for the
DC readout beamline, using our two in-vac Piezo-Jena steering
mirrors as actuators. They assembled the mirrors (without breaking the PZT
stacks!!) and wired up one degree of freedom to a spare IO pzt steering mirror board, and verified that it works.
- Sam
is thinking about the alignment servo design. It's not clear whether QPDs or dithering will be used to sense the beam
position/angle going into the output mode cleaner. Because any beam jitter
going in to the OMC translates into transmitted intensity noise and thus
GW signal noise, Sam is aiming to develop a high-bandwidth system.
- Dan
and Mike Gerfen are fixing several small
problems with the output mode matching telescope machined parts.
- Steve
will install a "dirty" picomotor into
the output mode matching telescope and test the mechanical resonances with
his phonograph needle apparatus.
- The
breadboard for pre-alignment of the in-vac DC
readout beamline is in the shop, expect it in a
week.
Electronics, Controls, Computers
- Alex
Ivanov has succeeded in recovering our 3.7 years
of minute trend frames from the failed RAID array, and has made them
available once again to dataviewer. Next step is
to get a regular and reliable backup system. We hope to be able to push
the data to CACR archives in Powell-Booth, with help from Stuart and Dan.
- Ben
has begun the tuning of some double-demod RFPDs for the 40m lab.
- Larry
installed non-ligo-specific GC software onto a
new Blade 1500 for use as a new operator workstation (op540m); we'll put
it into service by the end of the week.
- Rana added a bunch of DAQ indicators into frame
channels.
- Rana reworked the DAQ interface board which routes
signals from the PSL FSS, PMC and ISS systems to the data acquisition
system. He stuffed it with the appropriate amps and filters for all the
various signals. The table-top ISS servo board is rev 0.1, needs some mods to get into DAQ. Rana
modified the ini files to get the right signals
into the frames, correctly labeled.
Lab Infrastructure
- After the rains, Steve reports that there were NO
roof leaks. There are, however, plenty of ants.
Thermal Noise Interferometer (Black)
Nothing significant to report this week.
LASTI (Ottaway)
No report.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
Advanced LIGO mirror size
(Hiro) Yi Pin delivered a new result with the
curvature error is +-1m and +-2m. The SNR is very sensitive to the curvature
error and the (non) degeneracy of the recycling cavity configuration. We need to use a tool like FFT to conclude
any definitive answer, but it can be that the requirements could be very
stringent.
modeler
(Hiro) The statespace
module is very slow and the ABCD matrices sizes are large. An optimization is
being investigated using only part of the
matrices which actually
contribute to the answer.
Alfi
(Bruce) [PR -- Problem Report]
- Fixed
connection making bug (PR 529)
- Starting
work on importation of bundle content names into not yet externally
connected input bundle ports (PR 478)
Data Analysis Activities (Lazzarini)
Chatterji:
- Spent
9 days as a SciMon at LHO
- Performed
an in-situ calibration of coil magnetometers installed in the remote vault
at LHO.
- Drafting
report on anomalous detector behavior from Dec 9 to Dec 12 as part of the
glitch and detector characterization group: http://ldas-pcdev1.ligo.caltech.edu/~shourov/S5/glitch/Shift_20051209_20051212_SC.html
- At
GWDAW10, I gave a talk describing LSC burst group data conditioning
activities. I also presented a
poster on the current status of the Q Pipeline.
- I
Performed follow-up study on calibration line glitches in H1 on 18 Dec
2005 (hanging awg process) and L1 on 25 Dec 2005
(single sample dropout):
http://ldas-pcdev1.ligo.caltech.edu/~shourov/2005DEC18_calibration/
http://ldas-pcdev1.ligo.caltech.edu/~shourov/2005DEC25_calibration/
- I
am continuing to develop a tool to automatically scan large numbers of
channels for statistically significant content around times of
interest. The tool has been
extended to display both time-series data and time-frequency spectrograms
with and without data conditioning applied.
- I
am working to automate the postprocessing of the
online S5 Q Pipeline analysis.
- Regenerating
triggers for the LIGO/Virgo joint data analysis working group to target a
new agreed upon signal space.
Mendell:
I have finished adding new options to the SFT generation code. These include:
a. Options to write version 2 SFTs, using
LALWriteSFT2file and the specification given in T040164-01. This includes
options for the comment field for the SFT header, and the misc. desc. field of the file name.
b. Options to apply various windows with an overlap factor. The default is to use the tukey
window function, as defined in Matlab, and no
overlap. The other window options are to use the tukey-like
window defined in lalapps/src/pulsar/make_sfts.c and
to Hann window, as defined in Matlab
(which can be used with a 50% overlap).
c. Options to created the output SFT directories on the fly, based on GPS
time. This works identically to the way RDS directories get named, will allow
the code to run through-out S5 without putting too many files in one directory.
d. One can set the start freq. and freq. band from the command line
(defaults are the usual f0 = 48 Hz, band = 2000 Hz).
Previous options already included were high pass filtering, use of double
vs. single precision, the channel name, and preprocessor flags to check memory
use and print example values.
I next plan validate the version 2 SFTs, and start
generating them from hoft, and then publish these SFTs. The code is in
lalapps:
lalapps/src/pulsar/MakeSFTs/MakeSFTs.c
lalapps/src/pulsar/MakeSFTs/scripts/MakeSFTDAG
In the meantime, 1800 s SFTs continue to be generated
from uncalibrated DARM_ERR, with the output on ldas-grid at LHO and LLO respectively under:
/cluster/pulsar/S5H1_1800s_DARM_ERRNoCal_v1SFTs/
/cluster/pulsar/S5L1_1800s_DARM_ERRNoCal_v1SFTs/
Shawhan:
- Revamped
the GWIstat web page at http://www.ldas- sw.ligo.caltech.edu/ligotools/runtools/gwistat/ .
- Maintained
conlog code at the sites.
- Worked
on burst hardware injections
Yakushin:
1) Processed SG1_S5 MDC frames only to discover that they contain no
injections at all in DARM-ERR channel. Keith Thorne is redoing SG1_S5 to
correct the error.
2) Added a summary to the waveburst online page that contains various information
obtained on all S5 data up to now in addition to reports generated daily.
3) Demonstrated that L1 generates much more low frequency glitches than H1
or H2. Trying to understand the cause and properties of those glitches.
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS
Continued to focus on 64-bit compilation for Solaris. As of this week, all
unit tests now pass. Several of the integrated system tests work (ilwd to ligolw conversion, ligolw to ilwd conversion and
several createRDS to mention a few). Of the
integrated system tests that do not work the common failure is with the
transmission of data via the data sockets. More investigation is required to
figure diagnose the cause of the problem.
The pkgbuilder rules for OpenSSL
and Apache were modified to embed the runpath for the
64-bit libraries. This eliminates the need for LD_LIBRARY_PATH to include the
64-bit library directories.
It was discovered this week that FrVerify
complained about frames spanning the addition of the January 1, 2006 leap
second addition. The code has been corrected and will be available with the
next release of LDAS.
The open PR (2962) to address failure to display more than one API's memory
graph has been closed
Discovered that the TCLGLOBUS channels sometimes do not invoke the fileevent and sends block commands to the controlMonitorAPI's server. A PR has been opened.
The All-Users-Command test failure to detect failing jobs (PR 2969) has now
been fixed and closed.
Performed system and integration tests on LDAS development version 1.8.48.
Found a few issues with the test programs which have now been fixed.
TCLGLOBUS
Worked on PR #44 where LDAS managerAPI accepts the
new connection but failed to get fileevent triggered
using XIO-based Tcl channel. This problem was
discovered when running managerAPI on
ldas-dev.ligo.caltech.edu. I have a fix for this problem and it's caused by
incorrect implementation when allocating a new handle for a new client.
Worked on service credentials within LDAS. Mary has tested the code on
ldas-suntest3.ligo.caltech.edu and it's working. I need to work some more code
implementation to handle a default location of service credentials.
GRID COMPUTING
Received fix from Duncan Brown related to a patch for supporting L4 data
with Inspiral pipe. Will be validating this fix with
Level 4 data.
Yum updated Fedora Core 4 packages on osg-itb and osg-itb-se.
Installed OSG 0.3.4 release on osg-itb and osg-itb-se. Validated the osg-itb
installation with site-verify gridex and gridcat.
Installed osg-client form OSG 0.3.4 on osg-itb-se and setup up vds
tools. Attempted to run Level 3 data set
(38 GB) used to validate OSG 0.3.1.300 of the 724 DAG nodes failed. More
testing will be needed to determine if problems are in the OSG 0.3.4 osg-client package or related to FC4 as this is the first
time the osg-client package has been tested on FC4.
The OSG Council held its second "Town Meeting" to discuss with the
Executive Board Director candidates their positions on issues of concern to the
council. The earlier concerns about the
focus being to LHC specific have been mostly addressed by the candidates.
Shortly after the meeting it was learned that only one candidate intends to run
on the ballot.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Still
pursuing the question of why some files are not being archived for a very
long time and then only with human intervention. Mostly just doing the manual intervention
and hoping that the spliting out of /
archive/home to it's own filesystem (with it's
own archive parameters) will fix the problem.
- Did
the standard tape exporting, shipping, ingesting. Now have the admins
at the sites are running the tape eject script themselves.
- Released
old data pinned to disk at LHO (Greg had noticed that / archive was
getting full).
- Installed
new blade in CIT's FC switch and provided
instructions to the admins at the sites how to
do the same.
- Made
LLO only use 4 (of 6) tape drives for staging (user requests were taking
over all the drives and causing archiving to stop).
- Twice
identified publishing scripts dying, but in both cases Ben had to make
changes before they could be restarted.
- Installed
2 new 3511s at CIT, have been working on setting them up. Before we got a second controler from LHO, experimented with making a single
10Tb+ LUN between the two boxes (which worked as far as the 3511 was
concerned, tho' it took the better part of a day
to build).
- Discovered
that Sol10 doesn't see new FC devices without a reboot. Submitting to Sun.
- Rerouted
internal GigE fibre
for ldas-cit & ldas-archive
so they use the switch in Synchrotron (not Millikan).
(Phil Ehrens)
- Upgraded
LDAS-test beowulf, metaserver,
and datacon boxes to Fedora Core 4.
- Upgraded
ldas-gridmon to Fedora Core 4.
- Finished
configuring LDAS on the LDAS-CIT system.
- Upgraded
ldas-test gateway to Solaris 10 Update 1.
- Upgrade
of dataserver-test failed due to broken dvd drive.
Currently investigating "jumpstart" and pxe/dhcp based network install schemes.
(Stuart Anderson)
- Received
and installed 8 equipment racks for the new cluster.
- Received
power and network cords for the new cluster.
- Ordered
high capacity power strips for each rack of the new cluster.
- Continuing
to investigate minor water leaks from Liebert coolling unit.
- Started
testing Solaris 10 Update 1.
- Created
LIGO specific yum repository for Fedora Core 4.
- Sent
FC equipment to LLO to support the new 3511 RAID units.
MIT
(Keith Bayer)
- Rebuilt
pcraid#1 with FC4 - copied backup of dso-test
home directories back to its raid.
- Received
liebert 5 ton a/c unit from LHO.
- Working
with MIT facilities to spec installation.
(Junwei Cao)
Livingston
(Dwayne Giardina)
- Brought
wrong 3511 to MSR with Lisa. it was already installed in rack before I
caught my mistake. swapped
controller during downtime (non-locked state) on next day.
- RMA'd 22 Maxtor disks.
- Power
strip had tripped for nodes 55-62 Tuesday AM. resetting breaker on power strip fixed
problem. expect it to fail
completely soon, as it has already happened with two other strips.
- Nodes
56, 95, and 131 had disk errors, replaced disks. have two more in warranty to RMA now
- Tapes
ejected and shipped to CIT since last status update: LL0512, LL1060, LL1062, LL1064, LL1067,
LL1069, LL1072, LL0791, LL1074, LL1077, LL1080, LL1082, LL1085, LL1086,
LL1089
- Tape
LL1085 was reporting media error and only 3% full. SAMU is also reporting media errors on
tapes LL0484, LL0676, LL0182, and LL0384 all currently in the library
- Tapes
imported to library since last status update: LL1060 -
LL1089 and LL0790 - LL0819
Hanford
(Greg Mendell)
- The
addition of the Dec 31 2005 23:59:60 UTC leap second caused minor issues
with frame generation. At LLO these frames span Dec 31 2005 23:59:60 UTC:
/archive/frames/S5/L0/LLO/L-R-8201/L-R-820108800-32.gwf
/archive/frames/trend/second-trend/LLO/L-T-820/L-T-820108800-60.gwf
/archive/frames/trend/minute-trend/LLO/L-M-82/L-M-820108800-3600.gwf
and have ULeapS set to
32. At LHO this frame spans Dec 31 2005 23:59:60 UTC:
/archive/frames/trend/minute-trend/LHO/H-M-82/H-M-820108800-3600.gwf
and has ULeapS set to
33. (No other DAQ frames were generated at LHO that span this time.) However,
in all cases frames that span Dec 31 2005 23:59:60 UTC have a somewhat
ambiguous leap second, since the change in leap seconds occurred during the
frame.
- No
RDS was generated for the times that span the leap second addition.
- We
have decided to mark these times with a NO_RDS data quality flag.
- Otherwise,
S5 Data archiving, publishing, and RDS generation continues to run
smoothly, and monitoring of these has allowed sys admins
to correct minor problems as they arise with no loss of data other than at
times when both framebuilders are down.
(Ben Johnson)
- Currently
publishing h(t) data at both sites. The scripts use diskcacheAPI
for file discovery, and a bit of modification to the metadata and PFN
generation routines.
- Fixed
rls-server crash at LLO. Most of my scripts
there handled the crash as intended (caught exception, exited). But one
had an unhandled exception. I need to do more work to make the scripts
more robust.
- Replaced
fb0's 3510 with a new 3511 (single RAID controller unit). The unit was set up with a 10+1 RAID
plus a global spare giving 4.5TB of space for /fb0_frames. The firmware is
still at 4.11I and needs to be upgraded to 4.13.
- I
have tweaked the webserver at LHO (ldas-jobs) to meet user requirements. Some users are
finding it very useful.
General Computing (Wallace)
MIT:
(Keith)
- Rebuilding
laptop o/s after fatal harddrive crash
- Worked
with Mike P. to setup VPN connection from MIT
- Installing
Solaris 10 on test box(s)
- Will
attempt to contact sun regarding LDAP questions related to client side
certificates.
LLO:
(Dwayne)
- Working
on creating a standard outreach PC image, almost complete
- Installed
6 DVD-RW/CD-RW drives in outreach PCs
- Usual
user support questions, html assists
(Shannon)
- Reinstalled
the MRTG graphs. This used to be
hosted on a machine that is no longer in service.
- Working
on getting flowtools going again. This package went away when the MRTG
graphs went away. This was a
valuable resource that was needed over the weekend and was not available.
- Started
working on migrating the user groups to a GID that is not in conflict with
Linux GIDs.
- Received
and posted a copy of the LIGO-op web pages from Caltech. Dwayne or I will need to set up a
permanent home for them within the next couple of weeks.
- Usual
round of updating snort signatures, checking logs, etc. I have been updating the signatures
twice daily this week because of the Windows WMF flaw.
- Lots
of reading keeping up with the flaw mentioned above.
LHO
(Christine)
- Configured
the LAN main switch for a second vlan for the
new phone system being installed this week. Just set up 24 ports on the new vlan to test with.
Also tried to set up two ports for testing with auxiliary vlans which allow one port to be assigned to two vlans, one designated as voice and one as data.
- Testing
of the backup network circuit has been postponed until 1/10/06. I may need to replace the media
converters between LIGO and PNNL from 10 Mbs to
100 Mbs converters in order to be compatible
with the ESnet Juniper router.
CIT
(Veronica)
- LIGO: Ongoing troubleshooting of the web
server migration. End-of-year
maintenance/changes. Added a 2006
search category to the DCC database.
Roster database update.
Mailing lists update.
Updates to the LIGO website.
Christian and I went over a new webcam
package with better resolution, which is being considered for use. Addressed an issue regarding the terms
of use of an image owned by the Caltech Archives for an educational
project, per a user request.
Updates to the MIT LIGO website.
User support.
- LSC: Updates to the database of LSC-reviewed
documents. Updates to the
Observational Results webpage.
Posted a couple of late talks to the November meeting website. Updates of the LSC-related mailing
lists.
- CaJAGWR:
Website updates. Taped and
compressed the video of the last seminar, posted a stream pointer at the
website.
(Mike)
- DCC:
Spent most of this week reloading Server 2003 for new DCC database. Going
with the new configuration on how to implement these services using
SYNERGY software is a lot of work. Running SQL server 2002 on one server
as our database storage and then running the SYNERGY, plus ColdFusion server 5.0 on an additional server is a
challenge. I have been working with SYNERGY's
tech support + engineers on how to get this working; we are almost there
but we are still having some problems that need to be resolve. This is an
on going project.
- PRIMAVERA:
Worked on this setting up a user to connect here at Caltech to view and
add data to the primavera database.
- Testing
of unofficial Microsoft WMF patch: I tested this patch on XP, Win2000,
2000 server, and 2003 server, and it seems not to affect these Operating
Systems, including all GC software. I have loaded this patch on our NTSRV's. We are also loading this patch on our
administrative PC's.
(Important) The unofficial
patch must be un-installed before you install the Microsoft patch, which
is scheduled to release on Tuesday the 10th.
- Other
misc. user support.
(Christian)
- Created
a backup of Julie Hiroto's workstation. Also, I
replaced the toner cartridges on local printer.
- Upgraded
Gina from Microsoft Office 2000 to 2003.
- Replaced
toner cartridges on HP 5500 printer.
- Created
a backup of Irene Baldon's workstation.
- Worked
on automating the installation of a emergency Microsoft patch from a third
party. Microsoft is now releasing a patch earlier than previously
announced so the automation script no longer needs to be distributed. Other misc.: Continued onsite
software/phone support.
(Larry)
- Placed
a number of purchases. Cables and Misc. items as well as a maintenance
contract for the LDAS group. A number of misc. items for the GC group.
Also, worked a couple of the supply items for the bus. group.
- Installed
updated licenses for a number of packages that expired over the holiday
period.
- Replaced
the CIT LIGO web server with a newer unit. The timing worked out in that
the disk on the older server went bad a few days later. The new server now has all of the same
functionality as that of the old one. We are now working on modifications
to improve performance and security on the unit.
- Installed
various s/w pkgs. on one of the 40M servers.
- Updated
one of the Engineering sandbox servers.
- Setup
a number of new calendar sets. The listings for the conference rooms will
be moved to the newer calendars.
- Assisted/Assisting
Mike on the setup of the new DCC systems.
- Assisted
a large number of users that had problems which turned out to be typo's.
It must be something in the air, usually it is just one or two a week but
over the holiday period it has been more like a dozen a week.
- Worked
a number of server related issues. Mostly moving accounts around to get
more disk space for the active users.
- Did the monthly backups for the home accounts. Now
working on the backups of the server OS directories.
|
Mail Statistics
|
December 22, 2005 – January 4, 2006
|
|
Rejected Messages
|
48,030
|
|
Virus Messages
|
1,836
|
|
Accepted Messages
|
15,240
|
|
Total Messages
|
63,270
|
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Systems, Management
Advanced LIGO Project Management
from Carol
Wilkinson
Preparation for NSF Baseline Review
The advanced LIGO project office has started preparing for the upcoming NSF
review of the Advanced LIGO Project final baseline. This review is expected to take place in May
2006 and is the next step in obtaining approval for funding. Preparation
entails producing the final cost, schedule, and funding profiles as well as the
Project Execution Plan, Personnel Transition Plan, and other documents. The project office will be asking for
cooperation and support from various members of LIGO and the LSC as we tackle
the impressive work load ahead of us.
Progress Updates
Progress updates for Advanced LIGO subsystem development for the period from
September 1 through December 31 are due by January 12.
Meetings & Reviews
Future near term planned meetings & reviews are indicated in the table
below. Changes since last report are
listed in blue.
|
Date
|
Sub sys.
|
Review
|
Topic(s)
|
Enabling event(s)
|
Schedule motivation
|
Status
|
|
Jul 11-13, ‘05
|
SYS
|
SYS Mtg
|
CDS infrastructure & HAM
Isolation Req’s
|
|
|
Report in progress
|
|
12-Jul, ‘05
|
SUS
|
PDR, Review 2
|
Electronics req & design;
Focus is on the front end electronics (UK) -- limited Digital
controls/electronics (US) review
|
|
|
Report in progress
|
|
~Oct 05
|
SYS
|
PDR, Review 1
|
Engineering & Implementation ('generic')
Requirements;
Interfaces
Revised Optical Layout
Optomechanical Layout
|
completion of generic requirements definition;
completion of first draft of ICD; revision to optical layout; establish
integrated opto-mechanical equipment layout
|
timely system level definition enables/helps
define subsystem reqmnts & design
|
|
|
~ Nov 4, ‘05
|
SUS
|
SUS PDR
Review 8
|
Ribbon/Fiber/Ear/ Bonding PDR
|
Completion of the ribbon, fiber, and ear and fabrication and
bonding design and processes
|
|
Report in progress
|
|
Nov 29, ‘05
|
SEI
|
HAM SAS
PDR
|
Review modeling, analysis, design for HAM soft
system
|
Revised HAM SEI requirements.
|
Timely decision for proceeding with HAM SEI
prototype.
|
Draft report out
|
|
~Dec 05, ‘06
|
SYS
|
PDR, Review 2
|
CDS Infrastructure
Stable Recycling Cavities
Lock Acquisition
Modulation Scheme
Power Induced Instability
|
Sufficient CDS requirements & concept work
(also 7/11-13 mtg)
E2E Modeling for AL
40m Progress on Acq. & Mod.
|
CDS Infrastructure is key to subsystem
electronics req.
Stable cavity is key to IO MMT design
|
|
|
~Jan17. ‘06
|
SUS
|
SUS PDR Review 9
|
Wires for MC Triples
|
|
Timely report to allow progress on MC triple final design
work
|
|
|
~Jan 06
|
IO
|
PDR Review 1
|
PDD, Faraday Isolator, RTP-based modulators
|
SYS PDR?
|
|
Work
delayed on
FI, allows more
systems to be
reviewed
|
|
~Feb 21 , 06
|
SUS
|
PDR, Review 5
|
Triple design
|
Available SUS/US staff
|
Enable SUS/US final design phase
|
Quad controls PT
takes preced.
|
|
~Feb 22, 06
|
AOS
|
AOS DRR/CD
Review 1
|
Stray light control, PO
mirror and telescope, optical lever, initial alignment system
|
SYS PDR?
|
Delay stray light control review until other systems can be
reviewed at the same time.
|
Delayed from
Oct. to allow review of
add. systems.
|
|
~Feb ‘06
|
|
|
|
|
|
|
|
~Mar 1, 06
|
SEI
|
HAM isolation req’s review
|
Isolation requirements in HAM chamber
|
|
Need before reviews on single stage stiff system and SAS
|
|
|
~Mar 15 ‘06
|
SEI
|
CDR on single stage HAM SEI
|
Evaluation of single stage ISI design against revised
requirements
|
HAM Isolation req’s review
|
Need for NSF baseline review in May
|
|
|
~Mar 06
|
IO
|
PDR Review 2
|
Mach-Zender, Adaptive mode matching, Mode
Matching Telescope
|
Determination of whether a stable recycling
cavity will become part of the AL
baseline; SYS PDR 2
|
|
Waiting
for stable
RC decision
|
|
~April ‘06
|
SUS
|
PDR, Review 3
|
Quad design
|
Completion of the quad controls prototype
assembly; installation at LASTI
|
timely transfer, to RAL & UB efforts, of
lessons learned from the controls prototype
|
Delayed until shipping to LASTI.
|
|
~April 06
|
SUS
|
PDR, Review 6
|
quad controls prototype test results
ribbon process/design
|
completion of LASTI testing; may need to have
partial review with quad PDR before end of testing
|
timely incorporation into final design effort
on the noise prototype
|
|
|
~May 06
|
SEI
|
HAM Critical Design Review
|
Recommendations w.r.t.
HAM prototype development based on ETF results
|
Completion of SEI/BSC critical design reviews;
LSC review of ASI HAM configuration design
|
Delay until requirements are revised. timely decision on
proceeding with SEI/HAM prototype
|
Delayed from Aug.
|
|
~May 06
|
COC
|
PDR
|
Metrology, Handling fixtures, Coating,
Cleaning Process, Optics prelim. design
|
SYS PDR?
|
|
|
|
TBD
|
AOS
|
AOS DRR/CD Review 2
|
Thermal Comp., Photon drive
|
SYS PDR?
|
|
Moved
forward
for timely finish
of AOS CDR’s
|
|
TBD
|
SUS
|
PDR, Review 7
|
BS, FM/ITM SUS design
RM design
non-cavity SUS
|
design work completion (has yet to start on FM/ITM, not
mature for RM)
|
|
|
Seismic Isolation
Advanced Ligo Seismic Isolation Procurement
Status
|
Assembly
|
Status
|
|
Top Assembly Components
20007970-A
Stage 0 Assembly
2000795-A
Stage 1 Assembly
20007825-A
Stage 2 Assembly
20007825-A
|
Purchase order placed with Arland
Tool for all large parts. Delivery scheduled for 2/15/2006.
http://emvogil-3.mit.edu/~kmason/SEI%20machining/
Purchase order placed with Limerick Machine for the end milled plates and
remaining Top Assy, Stage 0,1, and 2 Componants. Supplier is on schedule for 2/1/2006
delivery with 10% of parts recieved at MIT.
|
|
Stage 0-1 Spring Assembly
20007878-A
Stage 1-2 Spring Assembly
20007890
|
Purchase order placed with
Lavallee Machine for springs and rods. Lavallee has recieved the maraging steel for all rods and the stage 1-2 springs.
The stage 0-1 spring material will be drop shipped to Lavallee
Machine next week. Delivery of finished parts is scheduled for 2/15/2006.
Purchase order placed with Limerick
Machine for remaining spring assembly parts. Delivery scheduled for
2/15/2006.
|
|
GS-13 Pod Assembly
20007810-A
L-4C Pod Assembly
20007820-A
STS-2 Pod assembly
20007941-A
|
Geophones, seismometers and lockers are in house.
Purchase order placed with Norcal for vacuum
housings. Delivery confirmed for 2/2/2006.
Purchase orders placed with Limerick Machine and Lavallee
machine for pod machined parts. Delivery scheduled for 2/1/2006.
Design of harnesses completed. RFQ required for internal pod harnesses.
|
|
Stage 0-1 Kinematic Lock
20007941-1-A
Stage 1-2 Kinematic Lock
20007941-2-A
|
Tooling design complete.
Purchase order placed with Limerick Machine for kinematic
Lock Assemblies. Delivery scheduled for 2/15/2006.
|
|
Stage 0-1 Actuator Assy.'s
20007966-A
20007967-A
Stage 1-2
Actuator Assy.'s
20007968-A
20007969-A
|
Tooling design complete.
Purchase order placed with Limerick Machine for actuator mounts and tooling.
Delivery scheduled for 2/15/2006.
|
|
Stage 0-2 and stage 1-2 Alignment Pins
Blade Pre-Load Tooling
Blade Calibration Fixture Modifications
LASTI Test Stand and Spreader Bar
|
The design of stage 0-2 and stage 1-2 alignment pins is
complete. The drawings were sent for quote.
The blade pre-load tooling design is complete. The drawings have been sent
for quote.
The blade calibration fixture has been assembled for the stage 1-2 blade
configuration. A blade of 4140 steel has been made for testing the fixture.
Several new parts are needed for the new longer stage 0-1 blades.
Installation and leveling of the test stand at MIT is complete.
|
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
Nergis's fixtures were delivered to her in
December. Ric/Physics
Shop has finished the ECD parts for the controls prototype. They are fixtures,
so only need Class B cleaning and baking. The ECD
parts themselves have been fabricated a while ago. Working on the noise prototype ETM test mass
drawing with Gari and Dennis. Coordinating with Brian O'Reilly on his visit
to LASTI for quad installation. Working
on actions from Carol and Dwight about staffing and schedules.
From: Jay Heefner jay@ligo.caltech.edu
Adl SUS Quad Controls Prototype
- All
electronics and cables are now installed in the Sync Lab in preparation
for testing using a LIGO-like control system. Testing will begin later
this week.
- All
cable drawings are complete for the LASTI system, minus rack designations
which are pending completion of the HEPI and ISI wiring diagrams.
AdL SEI ISI
- PA07
amps have been received for resumption of tests on the actuator driver
prototype.
- LASTI
system drawings are complete minus rack designations.
- Chassis
for the capacitive position sensors has been received. Design of the power
supply and interface boards are 90% complete.
LASTI HEPI Conversion
- System
drawings for the HEPI conversion to PCIX controls are complete minus rack
designations.
Core Optics
From: Bill Kells <kells@ligo.caltech.edu>
I have accelerated the calculation of PI effects for "all HTMs at once". This issue has been mulled over for about
6 months now. We had seen a way to exactly calculate it within the FFT scope.
But now, with Biplab
Bharwal leaving up, I have taken up the reigns (and
his program !) to actually start this. The present "missing link" is
the lack of available acoustic mode surface maps. Also, I am cotinuing
with design considerations of an optimized "stable"
SRC/PRC for AdL. In this a major consideration immerging is whether both the SRC and
PRC ought to be "stabilized" , or only the SRC.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
I have begun analyzing the data obtained from the high power laser. The broad peak seen in the Innolight NPRO intensity noise is present in the 12-W
master laser output with the noise eater on. In retrospect it would have
been handy to have performed the measurements beyond 100 kHz.
Of the three laser heads that transfer functions measurements were
performed, two of the laser heads appeared similar. The reason for the
discrepancy with the third laser head is unknown at this time. I assumed
that all diodes were of the same vintage but will have to check with LZH.
Auxiliary Optics
From: Michael Smith <smith@ligo.caltech.edu>
Solid Works Vertex Model:
I have drawn beam envelopes at the 100ppm diameter for the main beam, the PO beams, and the ghost beams that are to be dumped, and
am in the process of adding baffles for additional primary ghost beams.
I have added an output mode-matching telescope (OMMT), a Faraday isolator,
and a "straw-man" 3-mirror OMC (LIGO1 PMC).
Other Laboratory R&D
From: Riccardo DeSalvo desalvo@ligo.caltech.edu
Marco's weekly (04 Jan):
Working on some issues of the data taken this
summer from the Mesa beam Fabry-Perot cavity
prototype. I'm keeping in touch with John Miller to discuss about the silt
sensitivity results and to discuss about the paper that I'm already writing.
Yumei
Working on a solid works representation of
HAM SAS. Starting to apply ANSYS on some
parts.
Alberto
Writing paper on Center of Percussion Point
compensation in GAS filters.
For additional information about this report, contact Stan Whitcomb or Phil Lindquist