Weekly Report for Week Ending December 22, 2005



Due to the holidays we will not schedule the LIGO Executive Committee meetings for December 26, 2005 and January 2, 2006.


Special Announcements:  Happy Holidays!


Weekly Report Highlights


LSC Issues (Saulson)


No report.


LIGO Laboratory Administration (Lindquist)


STATUS OF LSC MOUs (Lloyd)

LSC MOUs and Research Plans and Progress Reports

  • No report this week (vacation).

SITE TELECONFERENCE (Lindquist)

No site teleconference was scheduled Thursday, December 22, 2005.

  • There are no open assigned actions.  The list of assigned actions updated through December 1, 2005 (the last time that it was updated) will be found Here.

PROPERTY MANAGEMENT (Chargois)

>From: Ed Chargois <chargois_e@ligo.caltech.edu>

  • Provided assistance to the Detector Group (K. Mailand) with packing and shipping of a Chiller to (C. Vorvick) at LHO.  Account Number P386540.
  • Provided assistance to the Detector Group (J. Romie) with packing, shipping, and the preparation of a Commercial Invoice for US Customs Clearance of Maraging Steel 24x96x.27 to RAL ( I.Wilmut) OXON, UK.  Account Number LIGO.PRLAS 5.16 NSFLIGO.FYO2CA.
  • Provided assistance to LDAS (S. Anderson) with the preparation of a Purchase Requisition to complete the transaction between LHO and MIT for the Air Condition Unit.  Account Number LIGO.DAT 1.5.1 NSF.FYO20F.

DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

  • No report (leave)

>From: Cleveland Mak mak_c@ligo.caltech.edu

Week Ending

December 22, 2005

In

Out

Packages

17

9

Faxes

15

12

  • Scanning Project - Scanning of F. Asiri boxes of files is very near completion.  They should be done within another day or two.  Progress continues on scanning of old blanket purchase order files.

COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman)

>From: "Cronin, Holly" <Holly.Cronin@caltech.edu>

>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

  • Completed change order 168 to Triad and submitted it to the vendor.
  • Working on change order #10 to add $127K for FY2006 to the Air Liquide contract which expires in 2007.
  • Working on completing the custom fabrication order for the actuators from SouthWest Controls Inc.
  • Completed the reimbursement and submitted it for payment.
  • Completed the change order to Support Services and submitted it to the vendor.
  • Working on the maintenance contract for Sun.

>From: Florence Kaufman <fkaufman>

SUBCONTRACTS MANAGEMENT (Jasnow, Salone)

>From: Gina Salone <gsalone@ligo.caltech.edu>

  • Nothing significant to report.

>From: Ed Jasnow <jasnow@ligo.caltech.edu>

  • Progress on the LLO Science Education Center continues on schedule, with concrete being poured this week and the steel being delivered next week.  The end of heavy construction, particularly involving the use of big trucks, should only be a few weeks away.
  • A consultant contract has been issued to Eric Myers for the performance of grid computing outreach work under the subaward from FermiLab.

SUPPORT (Baldon, Hiroto, Lloyd)

>Irene Baldon

Processed the paper work for six (6) new/revised trips.  At this time there are five (5) trips completed or in the works but are awaiting the necessary paper work to enter the P-Card system.

Completed nine (9) Expense Reports and there are nineteen (19) reports yet to be done.  I continue to contact travelers who have outstanding Expense Reports (more than one (1) month old) to ask for their cooperation in sending me their receipts so that these can be closed in a timely manner.  Presently there are zero (0) report more than thirty (30) days old.

>Julie Hiroto

Party for LIGO [Thanks to everyone who helped make the LIGO Party a success –pel]

>Dorothy Lloyd

  • No report (vacation).
  • Jim continued with data entry in the LIGO database and helping out in the DCC.

PROPOSALS and REPORTS (Lindquist)

We are going to have to put together an annual report for the Outreach Program immediately following the holidays.

DCC Steering Committee (Lindquist)

Nothing to report.

CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)

  • Change Request CR-050010, Prototype Seismic Attenuation System for the HAM Chamber (HAM-SAS) will be found at: http://www.ligo.caltech.edu/~phil/ChangeBoard/CR050010.pdf.  This change request was submitted by Dennis Coyne.  If approved, the change request will add the fabrication and test of a predominantly passive, seismic isolation system prototype for the HAM chamber to the Advanced LIGO R&D program.  We will schedule a meeting of the LIGO Change Board to discuss this request.

HUMAN RESOURCES (Akutagawa)

>From: Cindy Akutagawa <cindy@ligo.caltech.edu>

  • No report (sick).

Quality/Safety (Tyler)

>From: Bill Tyler tyler@ligo.caltech.edu

Nothing significant to report.


LIGO Hanford Observatory (LHO) and Interferometer Operations (Raab)


Summary of Commissioning Activities at LIGO Hanford Observatory (compiled by M. Landry)

Some highlights from the elog are bulleted below:

  • Network access to and from LHO was down for about 24h on Wed/Thurs
  • pulsar injections were restarted on all IFOs, with new parameters (reduced amplitudes for all but two pulsars), new calibration (actuation) functions, and a new (proper) injection sign
  • new versions of StochMon have been started, we can now display 1-live and 2-live versions simultaneously
  • the effects of the IFOs triggering from ASPD1-4 to ASPD5 on DMT monitors is summarized

4K IFO

  • A study was made of the H1 and L1 loop and optical gain stability
  • if we threshold on pixel fraction (say, 0.3-0.7) instead of binary inspiral range, running the interferometer at reduced power 1dB helps, even during the evening shifts.  Here, 1dB of reduction in laser power reduces the range by a Mpc or so, and brings the pixel fraction down to 0.2-0.25.
  • changing the origin of the power source and isolating cable shields reduced coil driver noise on MMT3 during our Tuesday maintenance period
  • Recall that the fine actuator distribution box had be replaced at EX; once this was done and high useism returned, we re-tested the DARM->fine actuator feedback.  The useism servo gained us over a Mpc at these times, so the loop is now closed in all science stretches.
  • new WFS1 notch filters were readied, as were MICH and PRC ones for RM violins
  • LHO IFOs show a propensity to burst on 1/16s intervals.  LLO does not show this behaviour quite as markedly

LIGO Livingston Observatory (LLO) and Interferometer Operations (Zucker)


L1 Interferometer (Frolov)

The interferometer BNS sensitivity remained at 10 Mpc this week when the level of micro-seismic activity was below the 95% historic average. The duty cycle showed modest improvement to 57% from 50% last week but was at the design 90% for the weekend.  The main loss of duty cycle was due to very high micro-seism on Friday and due to PSL work on Tuesday.

The Tuesday maintenance period had to be extended to install and later uninstall the new PSL periscope PZT driver electronics. The driver board had to be disconnected from PZTs due to the high level of noise introduced into the interferometer from Mode Cleaner input beam motion. The second PZT was found to be broken on Wednesday.

We are currently running with only one PZT connected. In this configuration the slow drift of the MC input beam can mostly be compensated without going to the PSL room. Once again the 40m lab team helped us out by kindly lending us their spare PZT. It is expected to arrive to LLO on Friday. The plans for the PZT replacement and additional diagnostics will be discussed later today at the LLO commissioning meeting.

Other activities this week:

  • The new LSC code was installed to allow the readout of individual AS photo detector signals at lower bandwidth
  • The signal from the software trigger to the fast shutter was properly mapped in the software and connected on the cross-connect - there is an instability in the multi loop plant between the Mode Cleaner and Common Mode loops. One of the small optics resonances around 15 Hz was reported to be excited during the power up script. The current solution is to lower the Mode Clean angular control gain during the up script and bring it up to the nominal value at the end of the script. The excitation could be related to the slow drift of the Mode Cleaner input beam alignment during the weekend running with both PZTs disconnected, which produced excess frequency noise and therefore larger Mode Cleaner drive.
  • The performance of the software anti-symmetric port trigger was characterized. The goal of the study is to reduce the rate of the false triggers while remaining sensitive to the large seismic disturbances such as a train.
  • The investigation of the seismic motion with a period of thousands of seconds showed that it is correlated with the excitation of the bounce modes. The mechanism of this correlation is being explored.
  • It was found that the Beam Splitter Centering servo has a large turn on transient.  The transient could be related to the clearing of the history buffer which was done differently at LLO and LHO. After switching to the LHO scheme of not zeroing the buffer, the transient was found to be dramatically reduced in three instances of going through the up script.

CDS (Bogue)

  • Helped Rolf install new LSC code.
  • Saw some suspicious behavior on a delaronde, a dmt box.  Worked with Shannon to verify that there had been no break-in on the box.  Turned off unnecessary services.  Fixed the last log.  Fixed syslog.  Configured syslog reporting to a central server.
  • Worked with Valera on a beam centering problem.

Computing and Network Security (Roddy)

  • Ran a nessus scan on the internal net and DHCP machines.  Found several windows boxes that were not auto-updating the microsoft patches.  One box was one that does not have a user assigned to it and usually sits idle.  Took care of this one... It had not been patched in MANY months.  A couple others were just users that were not setting windows to auto-update.  The problem was that there were certain vulnerabilities created on the network due to this, but the firewall mitigated any risk.  However, if the user were to connect to a VPN on another site (such as caltech) then it is likely that a compromise could have happened, unless it is filtered on the VPN end.
  • Investigating some items on Delaronde with Lisa today.  More on this later...
  • fixed a bug in the Arkeia backup software.  Several hosts were showing up twice in the software after we upgraded the client versions.
  • still experimenting with Solaris 10 and ZFS, etc.
  • documenting what I have done in the past with LDAP so that the other GC sysadmins have access to my many iterations of installing LDAP and migrating NIS+.  As often is the case, documenting it seems to take nearly as long or longer as doing the task itself.
  • looked through the server logs on mail.ligo-la for some evidence of weird behavior.  A couple of users have noticed odd email behavior, but I have not been able to find anything as yet.
  • usual rounds of pouring through IDS logs.  Just a couple of statistics, in the last 2 weeks, we have had:

~1500 port scans

~51,324 ssh brute force attempts

>800 IIS hack attempts (glad we don't run IIS)

>6000 hits by search engines

>1,100 php server attempts

etc. etc.

General computing (Giardina)

  • new auditorium PC installation, and application installs.
  • Mac GPG and mail plugin installation on my laptop
  • ran Windows update on a rogue PC

LDAS admin (Giardina)

  • troubleshooting problems with node9
  • sent tapes LL0561, LL0562, LL0629, LL0680, LL0682, LL0684 to CIT
  • added 20 tapes to L700 library

Data analysis (Yakushin)

Storage/Condor/LDAS admin:

1)      Configured a web server on ldas-jobs.ligo-la.caltech.edu for users to display the results of online searches.

2)      Getting SG1_S5 burst MDC from PSU through LDR to be used for sensitivity studies of online burst searches.

3)      Helped Xavi to setup hoft account for online h(t) generation.

4)      Received new SUN storage hardware for fb0 and cluster user disk space.

Data analysis:

1) Worked on automating the generation of waveburst scalograms for loud triggers. For an example, see 

http://ldas-jobs.ligo-la.caltech.edu/~waveburst/S5_LIGO_ONLINE_0/ 818784013-818870413/OUTPUT/coin/1/scalograms.html

2) Released the first version of standard waveburst S5 online search page:

http://ldas-jobs.ligo-la.caltech.edu/~waveburst/S5_LIGO_ONLINE_0

3) Working on estimating waveburst pipeline sensitivity on hardware and software injections.


Initial LIGO Detector Science & Engineering (Coyne)


CDS

see also the CDS weekly meeting minutes in the commissioning archives

CDS Software

No report

CDS Hardware

Nothing significant

DMT

No report

PSL

Nothing significant

Optical Metrology

No report


40 Meter Interferometer (Weinstein)


IFO Commissioning, PSL

  • Rana and Steve have been tuning up the PSL. Rana did a temperature scan on the MOPA, and found a good stable spot far from any mode-hopping. The beamline to the FRC was re-aligned. The PMC transmission is measured to be ~ 76%, which isn't great (we've had more than 85%) but is acceptable. The ISS pickoff beamline was adjusted, and 2 optics were removed from the path.
  • The FSS, PMC, ISS, MZ and MC servos are all working, although their gain and UGF will be optimized once we increase the power.
  • The FSS slow loop was updated to the current version by Peter King.
  • Steve and Rana will redo the PMC reflected beamline to get the right amount of light on the RFPD and the camera.
  • The PSL periscope steering mirror is still unplugged. To be investigated.
  • Still need to adjust the FRC periscope position, and the mode matching.
  • The mode cleaner locks reliably, but the alignment seems off, probably because of a misaligned input beam due to the PSL periscope steering mirror being off. The WFSs don't work in this state.
  • Osamu has realigned the PSL periscope steering mirror and MC. Now, IP-POS and IP-ANG QPDs look good, and the beam is centered on the ITM.
  • Both arms can be locked. The BS needed some adjustment in pitch. The arms have about 0.5 W incident.

IFO Modeling

  • Osamu continues to work on the e2e model of the 40m, and is now adding realistic seismic motion.
  • Rana has been thinking about lock acquisition with AdvLIGO. Given the available force at the test mass, he estimates that AdLIGO is a factor 50 away from being able to aquire lock. He's thinking about what can be done, especially with suspension point interferometers. He suggests that we use e2e to investigate the lock acquisition difficulties with realistic TM velocities.

DC Detection Development

  • Ben is continuing to work on the Solidworks design of the DCPD mount assembly. Should be finalized in the beginning of the new year.
  • The output mode cleaner is fabricated. Steve is having them build a protective fixture before we bring it to the lab.
  • Lee Cardenas is assembling two DLC PZT mounts for a test of the OMMT steering mirrors. Mike showed Steve and Dan how to assemble the PZT tilting platform to the DLC mounts without torquing the PZTs. Mike submitted DCNs for the changes.

Electronics, Controls, Computers

  • There hasn't been any progress in Alex's attemps to recover the 3.7 years of minute trends on our failed RAID array.
  • Ben is finishing a diagram of the new TT FSS as implemented at the 40m.
  • Five RFPDs are well underway in their final assembly at Wilson House. They will soon be ready for Ben to tune their RF frequencies.
  • Steve notes that there are still OSEM glitches on MC2 UR, although most of the other OSEMs look ok. This is believed to be a problem with the ICS110 ADC in one crate.
  • Mike Pedraza is setting up a new operator consolde (Blade 1500) for us.

Lab Infrastructure

  • The portable air conditioner in the control room is bad; out for repair.

Thermal Noise Interferometer (Black)


No report.


LASTI (Ottaway)


No report.


Data Analysis and Computing (Lazzarini)


Simulation and Modeling (Bhawal)

Simulation Tool

(Hiro) modeler_freq, a spectrum analyzer in e2e framework, was improved to support various features supported in modeler. Transfer function measurements using the system developed for modeler becomes much easier.  Various ideas to make e2e more attractive for experimentalists were discussed with Osamu.

AdvLIGO

(Hiro) Yi Pan calculated the effect of mirror curvature errors and finite aperture. We discussed about the implication in terms of the requirement of polishing.  Various transfer function calculations for the scattering noise estimation is still under way.

FFT

(Biplab) More calculations to cross-check AdvLIGO cavity results with Pablo Barriga (Univ. of W. Australia). Preprint of our paper "Numerical Calculations of Diffraction Losses in Advanced Interferometric Gravitational Wave Detectors" is currently available for review by LSC members.

Simulation of 40m Interferometer

(Hiro) DC readout simulation still going on. - Difference between e2e and twiddle simulation has not been resolved yet.

Alfi

(Bruce)

Last Week: [PR -- Problem Report]

  • Completing work on multiple warning handling (PR 470.)
  • Fixed a serious bug where multiple node deletes was causing confusion for background bundle content update threads (related to PR 470).
  • Starting work on complete enabling of bundler I/O renaming in inherited instance nodes (PR 511).

This Week:

  • Completing enabling of bundler I/O renaming in inherited instance nodes (PR 511).
  • Fixed related bugs with associated to deletions of connections connected to bundler ports, and the re-designation of bundler primary i/o as the bundler secondary i/o.

Data Analysis Activities (Lazzarini)

Shawhan:

  • Attended GWDAW
  • Fixed problem with DMT triggers at Livingston
  • Worked on conlog configuration reporting and control
  • Organized planning for S5 burst data analysis

Yakushin:

1) Worked on automating the generation of waveburst scalograms for loud triggers. For an example, see http://ldas-jobs.ligo-la.caltech.edu/~waveburst/S5_LIGO_ONLINE_0/818784013-818870413/OUTPUT/ coin/1/scalograms.html

2) Released the first version of standard waveburst S5 online search page:

http://ldas-jobs.ligo-la.caltech.edu/~waveburst/S5_LIGO_ONLINE_0

3) Working on estimating waveburst pipeline sensitivity on hardware and software injections.

LIGO Data Analysis System

Software Systems (Maros for Blackburn)

LDAS

Work continues on supporting 64-bit compilation of LDAS (PR#2958).  The datacondAPI is the one API which currently fails its "make check". The issue appears to be related to LDAS's interface into the third party package cLAPACK.

There appears to be an issue with the TCL Channel interface to TclGlobus sockets. A problem report describing the failure mode has been written.

Successfully completed the system and integration testing on last Friday's build (1.8.30) of LDAS.

TCLGLOBUS

TclGlobus has been extended to verify the environment variables X509_USER_KEY and X509_USER_CERT and unsets them if they do not reference a valid file. This prevents spinning in the globus layer when trying to validate user information.

Work has started to support service certificates within the XIO-based  Tcl channel interface.

GRID COMPUTING

Patches provided for the Inspiral job for L4 gwf files does not produce a DAX when run from Verruca nor is it parsable with the SAX parser from Pegasus on Verruca.

It was discovered that Condor-G does not function after a clean shutdown. Extended documentation by system admins is needed.

Gcc 3.2 was added to support Alex Sim's port of SRM to FC4 which currently has issues with pthreads. Testing of the changes has been deferred due to testing of new OSG 0.3.4 release.

OSG 0.3.4 was installed on Verruca (osg-client) and on LIGO-CIT-ITB.  Site-verify indicates that daemons are up and configured properly on LIGO-CIT-ITB head node. Reorganizing NFS mounts to Worker Nodes to conform to existing Condor installation  and new OSG local storage configuration requirements for "CE storage".

Attended OSG-INT meeting related to OSG releases 0.3.4

Hardware Systems (Anderson)

no report for 2005.12.22

General Computing (Wallace)

MIT:

(Keith)

  • Continuing to work on LDAP
  • Extracted data off of a failing hdd on scientist's desktop
  • Replaced / rebuilt filesystem on new hdd for scientist
  • Post doc linux laptop issues
  • Building XP desktop for data acquisition lab use

Livingston:

(Dwayne)

  • new auditorium PC installation, and application installs.
  • Mac GPG and mail plugin installation on my laptop
  • ran Windows update on a rogue PC

(Shannon)

  • Ran a nessus scan on the internal net and DHCP machines.  Found several windows boxes that were not auto-updating the microsoft patches.  One box was one that does not have a user assigned to it and usually sits idle.  Took care of this one... It had not been patched in MANY months.  A couple others were just users that were not setting windows to auto-update.  The problem was that there were certain vulnerabilities created on the network due to this, but the firewall mitigated any risk.  However, if the user were to connect to a VPN on another site (such as caltech) then it is likely that a compromise could have happened, unless it is filtered on the VPN end.
  • Investigating some items on Delaronde with Lisa today.  More on this later...
  • Fixed a bug in the Arkeia backup software.  Several hosts were showing up twice in the software after we upgraded the client versions.
  • Still experimenting with Solaris 10 and ZFS, etc.
  • Documenting what I have done in the past with LDAP so that the other GC sysadmins have access to my many iterations of installing LDAP and migrating NIS+.  As often is the case, documenting it seems to take nearly as long or longer as doing the task itself.
  • Looked through the server logs on mail.ligo-la for some evidence of weird behavior.  A couple of users have noticed odd email behavior, but I have not been able to find anything as yet.
  • Usual rounds of pouring through IDS logs.  Just a couple of statistics, in the last 2 weeks, we have had:

~1500 port scans

~51,324 ssh brute force attempts

>800 IIS hack attempts (glad we don't run IIS)

>6000 hits by search engines

>1,100 php server attempts

etc. etc.

Hanford:

(Christine)

  • Attended several meetings about I2U2, an outreach proposal to create web access to PEM data for high school classrooms.
  • I have scheduled testing and troubleshooting of the backup network for Tuesday, 1/3/06.  We don't have a time yet.  Some initial testing showed that while we do have link lights all the way to the ESnet router, we can't ping or send packets between LHO and ESnet.
  • There was another network outage from 10:40 a.m. 12/21/05 to 10:15 a.m. 12/22/05.  I was unable to contact anyone at PNNL.  Larry finally contacted ESnet who confirmed that the problem was between PNNL and LHO.  ESnet was able to contact someone at PNNL who thought the problem was at LHO.  Magically at 10:15 this morning the network suddenly started working again.  The problem was apparently caused by swapped fibers some where along the line between LHO and PNNL.
  • This network outage was another un-scheduled test of the backup network.  I was able to confirm that my router is properly failing over to the backup network.  Packets are being sent from the internal network to the backup circuit.  The backup interface on my router is not reporting any errors, but it is not routing packets off-site.
  • We continue to have problems with some email addresses being returned with a host unknown error despite the fact that only moments earlier email sent to the same address went through.  The addresses that we are having problems with are all CNAMES for other computers that are actually the mail servers.  These CNAME records do not correspond to A-records and sometimes the DNS servers return no A records found which is then reported by the LHO mail server as host unknown.  I'm still trying to determine what I can do to fix this problem.
  • Started setting up a new laptop for a user.

CIT:

(Mike)

  • Work on wireless access points adding new users to the mac address filtering list. Removing mac addresses from database on laptops that have been surplus.
  • DCC: Getting familiar with the administration side of this new database software. "SYNERGY" I am now ready to load this software to put into action. Instead of running the software on one server I will be splitting up these services on two servers per Larry's request.  Database (SQL Server) will be loaded on one server, and Web services for user access (SYNERGY) will be loaded on another server.
  • Spent a lot of time looking for Primavera software (Monte Carlo) but came up empty. After talking to Primavera sales people trying to get an additional media package shipped out to us. Found out this is going to be quite expensive. I am on hold with this issue for now.
  • Spam Filters: Continued work on the spam filters searching for false positives.
  • Other misc. user support and account maintenance.

(Veronica)

  • LIGO:  Website updates.  Roster database updates.
  • LSC:  Updates of the database of the papers under review.  Website updates.
  • CaJAGWR:  Taped and compressed the last talk.  The stream pointer is posted at the seminars webpage.  Website updates.

(Christian)

  • Dorothy Lloyd - Helped Dot move files that were located in her local drive to the network so she can access them from home.
  • Alan Weinstein - Configured new workstation with the standard Ligo image for Alan. I also Installed additional software from ITS that he needed.  Other misc.: Continued onsite software/phone support.

(Larry)

  • Working a number of procurement related items for different groups.  This includes purchasing licenses, maintenance contracts and misc. h/w supply items.  Just purchased a few more items for the engineering sandbox. The new h/w should improve the performance on their analysis programs.
  • Spent a great deal of time working phone problems. Hopefully, they are all cleared up.
  • Assisted a number of users so they can work remotely while they are on travel during the holiday.
  • Assisted the DCC with a couple of document issues. Also, working with Mike on the setup of the new DCC system.
  • Setup a couple more accounts as well as removed a few more.  Reworking the list of old accounts for approval for removal.
  • Resolved a couple of problems on the backup server. Resetting of the volume system has taken care of the error messages and let the system continue doing the backups.
  • Assisted Christine in resolving the LHO network problem.
  • Mail Statistics for Dec 15-21, 05

Rejected Messages        18,964

Virus Messages                  927

Accepted Messages      12,361

Total Messages            31,325.


Advanced LIGO and Supporting R&D (Shoemaker)


Advanced LIGO Systems, Management

From: Dennis Coyne coyne@ligo.caltech.edu

Systems

See also:

AL Systems web page

AL Systems email archives

Records Of Decision or Agreement (RODA)

See also the RODA status web page

  • Nothing significant to report

Requirements

  • Nothing significant to report

Interface Issues

See the "Interfaces" section of the AL Systems web page

  • Justin Greenhalgh and Dennis Coyne are working through the comments on the SUS related Interface Control Documents (M050438).

Vacuum Compatibility

Vacuum Preparation [Cleaning, Baking, Residual Gas Assay (RGA)]

See also the Vacuum Bake Lab

  • No report

High-Irradiance, Contamination-Exposure Cavities

Lee Cardenas, Liyuan Zhang

Changes highlighted in yellow

Cavity

(Location)

Material/Item

Start

End

Comments

Cavity #1

(OTF Lab, Bridge)

“Cable wire” (material type?)

~11/17

TBD

No Change: The cavity has been aligned & locked. Taking daily ring down and absorption measurements.

The digital oscilloscope failed so a new one has been ordered, along with a refurbished pulse generator.

----------------------------------------------------------

The test for 40 pieces of MMG nickel plated Nd-B-Fe magnets (for Helena Armandula, SUS ) has been completed and removed from the cavity.

Cavity #2

(OTF Lab, Lauritsen)

NA

NA

NA

Cavity not ready. It needs some other optics(such as: polarizing cube, 1/4 wave plate and some curve mirrors and lens) and the electronics. We have used/borrowed some of the optics from this system to accomplish
the completion of the other two cavities. Recently the 700 mw NPRO laser was used for Garilynn’s experiment and it needs to be realigned to the cavity.

Cavity #3

(OTF Lab, Lauritsen)

OSEM Flexi-circuit cable, qty ~ 45

(Helena Armandula, SUS)

supplied by Univ. Birmingham (Stuart Aston)

~9/30

TBD

No change:

taking daily absorption & ring down measurements

DuPont Flexible Circuits. The whole part to be constructed of 'flexi' i.e. no 'rigid' sections. (Stuart Aston,Univ. of Birmingham, SUS/UK subsystem)
- Start Laminate: Kapton (LF8515)

(document link: http://www.dupont.com/fcm/products/H-73244.pdf

Coverlay (x2): Kapton (LF0110)

(document link: http://www.dupont.com/fcm/products/H-73245.pdf

DuPont Pyralux Series - Kapton / Acrylic Adhesive system.

(document link: http://www.dupont.com/fcm/products/H-73246.pdf

--------------------------------------------------------------

OSEM emitter & photodiode 40 of each, (Dennis Coyne, SUS ) Test has been completed. Results to be posted by Liyuan Zhang soon.

Queue

Priority 1

2 Cleaned 50ppm transmission mirrors, 1 in dia., REO coated --

TBD

TBD

witness samples for the LHO vertex volume (added in 6/29/2005 vent)

Queue

Priority 2

Stepper Motor (Riccardo DeSalvo, possible SUS or ISC use)

TBD

TBD

Stepper Motor sample had been placed into Cavity #1: Power dropped from 175 mW to ~25 mW after introducing the stepper motor sample, and continues to decrease. It is very hard to keep cavity locked. The stepper motor may have contaminated the mirrors. Will re-test when a cvity becomes available again.

To be rebaked soon using the self-heating capability of the stepper motor (not just the oven heater controls)

Seismic Isolation

From: "Joseph A. Giaime" jgiaime@ligo.phys.lsu.edu

Agenda for the weekly SEI telecom

Friday, Dec 16, 2pm Eastern, 1pm Central, 11am Pacific time

Announcements

  • HAM SAS report in preparation.

BSC SEI status, Ken/ Dennis

  • Blade/flexure PO issued, maraging steel delivered to vender.
  • Decided not to pre solution anneal the steel, but to be sure that we support the flexures vertically when precipitation hardening.
  • Test stand anchors being modified to bolt down to floor.  One side leveled optically.  Clean room going up.

BSC work, adaptive modeling and FIR (Rich M)

  • Adaptive FF tried with single chamber-mounted Wilcoxon accelerometer as the source, with some success, limited by stop touching.

HAM control with VME (Pradeep)

  • No report.

LLO HEPI update, Shyang Wen.

  • Since ITMX was fixed, Shyang has been working to redesign the ITMX and ETMX to address the test mass bounce mode.  No results yet.
  • Design for the HAM2 tilt filter has been constructed and tested.  Results analyzed and will soon go on the llo ilog.

ETF platform work - Matt & Brian

  • Sercel L-4C lock-up issue: we should contact Sercel and work toward solving this problem in the long term.
  • All 12 DOF loops worked as of last night, open to air currents.  (So, no noise performance measured.)  10 Hz gain of tilt loops tweaked up a bit since last time around.
  • Quad pendulum frame installed.  Some tests expected before the holiday break, perhaps followed by other ETF tank being moved on top to keep out wind.
  • William East has finished thermal instrumentation and is testing it on a block of metal in an insulated box.
  • L-4C readout noise investigation underway, to quantify (e.g.) current noise at very low frequencies of OPA-27 and LT1012.

Seismometer work - Aaron

  • No report.

From: Jay Heefner jay@ligo.caltech.edu

AdL SEI ISI controls at LASTI

  • Wiring diagrams are 990% complete. Rack layout drawings are 90% complete.
  • A sample of the Fischer connector for the STS2 pod cable has been received. Initial fit check was successful. Connectors for the STS pod harnesses are on order.
  • Pod cable drawings for the L4C and GS13 will be completed in early January.

LASTI HEPI Controls

  • Wiring diagrams and rack layout drawings for the conversion of 3 HEPI systems to PCIX controls have been started and should be complete by mid-January.

Suspension

From: Janeen Romie romie_j@ligo.caltech.edu

Worked at Caltech last week on the quad.  Also worked with Ric in the Physics Machine Shop on Nergis's fixtures. He hopes to have them out to her before Christmas.  Met with Carol and Dwight on suspension schedule, review schedule, labor loading for production. I have a number of actions due to them by Jan 6th.  Provided a rework of the test mass drawing to Gari for the noise prototype ETM.  Coordinating with Brian O'Reilly on his visit to LASTI for quad installation

From: Calum Torrie ctorrie@ligo.caltech.edu

Quad Suspensions

We are continuing with the re-assembly of the quad in the Caltech clean-room. Photos to follow.  We hope to have it all assembled by the end of today. (Maybe even suspended.)

Install Fixtures

Ken and I have put in the order for the actuators.  Mike Gerfen has started to make the adjustment tooling (the alternative to the air bearing etc ...)  The original set of install fixtures are now almost complete and Ken and I hope to lay these out in the workshop today.

Structure FEA

Not much to report from ANSYS. Although I have measured the resonances of various configurations of the lower structure, results to follow.

From: Ken Mailand kmailand@ligo.caltech.edu

I’m working on shop drawings for the SUS installation plate style fixture for Calum, I have the major details complete, and Mike Gerfin at CES, has ordered the 5 plates, for the main assembly. Calum is ordering the lift actuators specified in Oddvar’s assembly.

Core Optics

Nothing significant to report

Pre-Stabilized Laser

From: Peter King pking@ligo.caltech.edu

Nothing significant to report

Auxiliary Optics

From: Michael Smith smith@ligo.caltech.edu

I am building a complete 4K Vertex with Zemax optical beam lines in Solid Works. HAM and BSC chambers are in place, PO telescopes and steering mirrors, I added cavity beam dumps mounted to the existing BSC mounting structures in LIGO1.

Phil Willems and I scrubbed the manpower needs and revised the scheduling for Photon Drive Subtask.

Hiro is working on obtaining transfer functions for scattered light noise in ADLIGO.


For additional information about this report, contact S. Whitcomb or P. Lindquist