Weekly Report for
Week Ending December 15, 2005
The LIGO Executive
Committee Agenda for Monday December
19, 2005 will be:
(Meeting time: 10:30 am Pacific Time)
1. Announcements
2. Comments
on Weekly Report
3. LSC
Issues (Saulson)
4. LIGO
Lab Operations
- Administration
(Lindquist)
- Sites
(Raab, Zucker, Shoemaker)
- Commissioning
(Fritschel), Detector (Coyne)
- Campus
Research Facilities
- 40
Meter (Weinstein)
- TN,
( Libbrecht)
- LASTI (Shoemaker)
- Data
Analysis and Computing (Lazzarini)
5. R&D
and Advanced LIGO (Shoemaker)
6. CHANGE CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION AS
NEEDED
- Change
Request CR-050010, Prototype Seismic Attenuation System for the HAM
Chamber (HAM-SAS), if approved, will add the fabrication and test of a
predominantly passive, seismic isolation system prototype for the HAM
chamber to the Advanced LIGO R&D program. We will probably not be ready to discuss
this request during this meeting.
Special Items:
Special Announcements:
Weekly
Report Highlights
Lindy Blackburn reports that the S3 untriggered burst search paper has been
accepted for the Amaldi proceedings, which will be published in Classical and
Quantum Gravity. It can be found at
gr-qc/0511146.
Steve Fairhurst announces the posting of the LIGO/TAMA S2 inspiral paper, as
gr-qc/0512078.
The LSC Detection Committee is being revived, with Rai Weiss as Chair. It had a re-organizational meeting on 9 Dec;
it will meet Monday.
A large subset of LSC member groups presented their new NSF proposals at the
LIGO PAC meeting on 12-13 Dec at LHO. In the Spokesperson's opinion, they did a
very good job.
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
SITE TELECONFERENCE (Lindquist)
A site teleconference was held Thursday, December 15, 2005. The following issues were discussed:
- Livingston
Science Education Center – construction reported as going
well. The steel work for the
foundation has been completed and the concrete will be poured Monday.
- Property
– The AC Unit is on its way from Hanford to MIT and should arrive
any day now.
- Security
Gate at Livingston – Having a problem with the delivery of the
replacement gate. Other than that
all ready to go.
- Visitors
to Livingston – the sense is that the availability of hotel
rooms in the Livingston area is beginning to improve. After hurricane Katrina, it was
impossible to find any kind of lodging in the area, and a trailer or two
was set up on site to accommodate people involved in commissioning and
operation. More on this as things
improve further, but it would appear that on site Camp Katrina may be
going away soon.
- The
list of assigned actions updated through December 01, 2005 will be found Here.
PROPERTY MANAGEMENT (Chargois)
>From: Ed Chargois <chargois_e@ligo.caltech.edu>
- Nothing
significant to report.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- Scanning
Project - Progress continues on scanning of the F. Asiri files. To date about 8+ boxes have been
scanned. Progress continues on
scanning of old blanket purchase order files.
- Activity:
|
Week Ending
12/15/2005
|
In
|
Out
|
|
Packages
|
33
|
8
|
|
Faxes
|
24
|
23
|
FINANCIAL SYSTEMS (Cronin, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Shopped
several models of oscilloscopes for discounts. Found one vendor that
offered a 20% educational discount on a newer and better model. The
discount allowed us to get the better model.
- Completed
change order #168 to Triad and submitted it to the vendor.
- Completed
change order #29 To Support Services and received the signed mod.
- Completed
change order #10 to Star Service and received the signed mod.
- Working
on the maintenance agreement with Sun.
- Following
up on pending credits to be issued for sales tax differences and for a
return.
- Completed
the purchase order close out report as requested.
>From: Florence Kaufman <fkaufman>
- Submitted
four Fabrication Request forms and the related PTA Set up forms for Detector
improvements.
- Submitted
PTA set up form for PO received from FERMILAB. Account requested is LIGO.I2U2/1
FERMILAB.LIGO.
- Updated
schedule of unspent FY05 funds for the Data Group.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- A
Work Order for electrical work associated with the HVAC system for LDAS at
LLO has been issued to the Excel Corporation in the amount of $8,000.
- Funding
has been received from FermiLab for outreach on grid computing. A subcontract will be issued to
consultant Erik Myers as soon as the new account code has been
established.
- Construction
of the LLO SEC continues on schedule with the metal framework being worked
on now.
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
- Processed
the paper work for seven (7) new/revised trips. At this time there are ten (10) trips
completed or in the works but are awaiting the necessary paper work to
enter the P-Card system.
- Completed
sixteen (16) Expense Reports and there are sixteen (16) reports yet to be
done. I continue to contact
travelers who have outstanding Expense Reports (more than one (1) month
old) to ask for their cooperation in sending me their receipts so that
these can be closed in a timely manner.
Presently there are zero (0) report more than thirty (30) days
old. I have no reports awaiting
signature at this time.
>
- Meeting to plan
Administrative Review for Jan 12-13 (Marie/MIT, Terry/LHO, Bonnie/LLO
coming to Caltech for meetings with various administrators and
departments).
>Dorothy Lloyd
- No
report.
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
PROPOSALS and REPORTS (Lindquist)
We received funding from Fermi Lab for I2U2 effort at Hanford. We are waiting for information needed to open
an account number.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
- Change
Request CR-050010, Prototype Seismic Attenuation System for the HAM
Chamber (HAM-SAS) will be found at: http://www.ligo.caltech.edu/~phil/ChangeBoard/CR050010.pdf. This change request was submitted by
Dennis Coyne. If approved, the
change request will add the fabrication and test of a predominantly
passive, seismic isolation system prototype for the HAM chamber to the
Advanced LIGO R&D program. We
will schedule a meeting of the LIGO Change Board to discuss this request.
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- The
next Staffing Committee meeting is scheduled for Monday, January 23, 2006.
- All
files for the Staffing Committee are up-to-date and posted on the SC web
page.
- Prepared
miscellaneous appointments and reappointment memos for various Visitors.
- Processed time sheets in KRONOS [the new Caltech
time keeping system that we are all apparently going to have to use
–pel] and submitted hard copies to payroll.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
- Nothing significant to report this week.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of
Commissioning Activities at LIGO Hanford
Observatory (compiled by M. Landry)
PAC19 took place at LHO at the beginning of the week; thanks to Terry Santini, Terry Gunter, Richard McCarthy and Christine
Barker for all their hard work in this regard.
As of Dec 15, we have 261h of accumulated triple-coincidence
data in S5. Daniel's PAC talk breaks
down duty cycles in various histograms; we're only meeting our single-IFO duty
cycle goal on H2. Our best duty-cycles occurred during the Thanksgiving
holiday week, a rare luxury of extended low anthropogenic noise. Recovery
from this week's Tuesday maintenance
was too long, particularly on H2 in which the optics were thought to have drifted,
especially the RM.
This will impact how we go into the maintenance period in the future, e.g.
relieving alignment and WFS offsets etc. Details and a mathematica notebook on duty cycles here.
Some highlights from the elog this week:
- calibration
line dropouts
continue
- GRBs during S5 are being catalogued
by U of Oregon, now available
off of the S5 webpage
- we
continue to be visited by a single-prop plane doing stunts
over Rattlesnake
Mt. (seen by PlaneMon); glider pilot Dick Gustafson hopes to
intercept (at the airport) and convince him or her to try the Blue Mts instead
4K IFO
- new SUS filters were added
to MMT1, MC1 and MC3. In order to apply the MC ones, we had to go to
a 2-stage application by script
- first getting to common mode with the old filters, then switching in the
new ones
- large excursions in the H1 range are observed but not
yet understood. Some times they are coincident
with H2
- beamsplitter internal modes appear to couple
to optical modes
2K IFO
- the PSL PMC servo electronics were swapped
out.
DAQ, CDS
- we
lost our external network link
for several hours
Outreach (D. Ingram)
Our thanks to LIGO PAC member and Goddard scientist Niel
Gehrels, PI of NASA's Swift mission, who extended his
PAC visit to deliver a GRB
talk on 12/14.
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
L1 Interferometer (Frolov)
The interferometer BNS sensitivity and duty cycle have not changed from the
previous week levels of 10 Mpc and 50% respectively.
The up-conversion of the low frequency motion into the interferometer
detection band remains the main investigation issue for the commissioning team.
The switching of the beam splitter electronics into the low noise mode produces
a transient which sometimes causes the lock loss during the power up sequence.
The new electronics is being prepared which will have smaller transient while
still providing sufficient noise suppression.
The Tuesday maintenance tasks were completed within the scheduled four hour
time window.
List of this week activities:
- PEM
injections were completed. The corner station pulsed heaters were disabled
based on the results of the analysis of the magnetic couplings.
- A
failed hard drive on the back up frame builder computer was replaced
- The
duo-tone timing monitor was connected
- Improved
communication code allowed uninterrupted data collection from one of the
three weather stations for up to several days, which allegedly has never
happened before. More diagnostics are needed to resolve the remaining
infrequent communication drop-outs and bring the remaining weather
stations online.
- The
"fast ADC" ifo
readout channel at the upper cavity free spectral ranges was
re-tested. The response was found
to be commensurate with the excitation and with the response of the
nominal low frequency channels.
- Protective
fast software triggering on the ASQ signal was enabled and tested. The DARM control signal has now switched
to the lock acquisition photo detector several times automatically during the
train, saving the "lock" and avoiding cavity cool down and
re-acquisition delays
- The
DARM open loop transfer function was measured with improved accuracy.
- Frequency
noise data were taken to be used for the interferometer noise budgeting.
- There
was an unexplained change of gain in the sideband power monitoring chain
by 3 dB after last week's work on the ASC electronics. The compensation
with a hardware gain returned the SPOB level and all dependent gains to
nominal values. More investigation is needed to track down the ultimate
cause of this change.
Outreach (Thacker)
- Worked
on NSF annual report
- Met
with Southeastern
Louisiana University
physics department individuals to discuss potential outreach partnership
- Met
with Lisa Szechter (Tulane) to discuss LIGOSEC
outreach research agenda
- Worked
on activities for upcoming teacher professional development workshop
LLO Facilities (Sibley)
Work on the Science
Education Center
is progressing well despite several days of light rain. Dirt work is
essentially complete for the foundation and the steel has been placed in the
grade beam forms. Concrete for the foundation is scheduled for next week.
LDAS HVAC upgrade PO has been issued to
Corporate Mechanical of Baton Rouge. The equipment has been ordered and may be
in in early February.
Work on the piping will start next week. Excel has been issued a work
order for the electrical work and it too will start next week.
Safety & security (Riesen)
The latest time frame for completing construction of our new main gate is 5
to 7 weeks.
Waiting for the return of the fire alarm people for the logic change needed
to change the FM-200 system to alarm the main fire system on the 1st detector
alarm rather than the 2nd.
Found no laser nor site safety concerns this
reporting period.
Completed the LLO safety indoctrination with Prof. Edward Doomes (Southern U., under Steve Mcguier).
CDS (Bogue)
- Replaced
a failed disk in fb0 3510.
- Worked
with Brian on adding photon calibration channels.
- Worked
with Valera
on l1adcufast. From my perspective
everything seems to be working with this except for the status
channels. The status channels
aren't working because the status comes off of the framebuilders
which aren't currently transmitting onto reflective memory. This issue will be brought up for group
discussion at one of our working meetings.
- Working
with Dave Barker on CDS disk management and getting the raids (delayed
because of other S5 issues) up and running at both sites.
- Added
the seismic plots as figure of merit 5 to the elog.
CDS Code Support (Khan)
Developed the weather station interface software.
The code has been working properly on Y-end without any communication dropout,
but the X-end looses communication in the evening. I am suspecting it may be
related to the battery not being charged by the Solar panel. I have requested
Doug to communicate with LSC people to see if they are communicating with the
station. This would eliminate the battery charging as one of the reason for
communication dropout.
Computing and Network Security (MZ for Roddy)
Shannon is away this week representing LIGO at the NSF Cybersecurity
Summit for Large Research Facilities in Washington
D.C.
General Computing (Giardina)
- changes to HTML/PHP interface for security server activity
logs.
- scripted retrieval of security server activity
logs. script
also "cleans" (removes identifying information from) the
published files. Originals are kept
in multiple locations, both copies are backed up
on tape. process
is scheduled to run weekly after the activity log report is created on the
kantech server.
- monitor on einstein linux box had minor issue.
LDAS Admin (Giardina)
- replaced the two power strips that recently
failed. All nodes are back
operational.
- shipped tapes LL0539, LL0563, LL0578, LL0579, LL0582,
LL0584, LL0677 to CIT.
Data Analysis (Yakushin)
Storage/Condor/LDAS admin:
- Installed
FC4 on ldas-gridmon and configured ganglia.
There still seems to be some problems with it though: it sees only about
90% of the nodes, today all of a sudden it stopped working and I had to
restart it.
- Twice
during the recent week node9 stopped working without any apparent reason
or error message and I had to reboot it.
Data Analysis:
Working on online waveburst web
page.
Initial LIGO Detector Science & Engineering (Coyne)
CDS
see also the CDS weekly meeting minutes in the commissioning archives
CDS Software
Rolf Bork
- Updated
LLO end station ADCU software to send photon calibrator excitation signals
back to DAQ.
- Rusyl found some questionable wiring to the LSC xycom module at LLO. I believe this is straightened out now,
so we will download new LSC code in the next few days.
CDS Hardware
Ben Abbott
Fast Shutter: One of the control boxes came back from Hanford with a
problem. I swapped out the FET, and it now works fine. I will ship
it back to Hanford
today.
DMT
No report
PSL
Nothing significant.
Optical Characterization
No report.
40-Meter Interferometer (Weinstein)
IFO Commissioning, PSL
- Rana and Steve have been working on re-commissioning
the PSL. The old FSS board seems to be fried, possibly due to a flaky
power supply. So they went ahead and implemented the new tabletop FSS
(TTFSS). They spent a long time debugging before they found and replaced a
flaky cable. Now the TTFSS is in and working, coarsely tuned, with a
~<1% FSS pickoff. The UGF is 400 kHz with plenty of gain margin, and
the gain slider is maxed out. Steve has installed a ~4% pickoff, so we
should be able to get the UGF above 650 kHz. Rana
tuned a notch on the phase-correcting pockels
cell. He also needs to tune a notch on NPRO PZT (fast) path. The FRC
periscope is 3-5 mm offset from beam center; will be tweaked.
- The
FSS RFPD has some DC offset on output, and the resonant gain is not in
right place. Ben will tune it up with the AM laser setup at Wilson House.
- The
PMC loop gain is low, because the beam on RFPD is attenuated. Rana and Steve will rearrange the PMC reflected beamline to simplify it and get more light onto the
RFPD, and Steve put a camera there. (He borrowed it from the SP beamline; now we need a camera there!). Rana's mods to the LLO PMC
board are still under discussion at LHO, so for now, we will continue to
use our old PMC board.
- Autolocking scripts for FSS and PMC work.
- Rana installed and ran a script to do a slow scan of
the NPRO temperature, to put the NPRO frequency in a stable place, far
from where it likes to mode-hop.
- Steve
installed a new ISS pickoff. Now there will be plenty of light on the ISS
photodiodes (when we turn the input power up to 1 watt or more).
- The
PZT steering mirror on the periscope from the SL to the MC has some
electronics problems. Rana, Steve and Ben are
checking it out.
- When
Rana tried to lock the MC, he noticed that MC2
had anomolously high force-to-pitch coupling.
Indeed, Dan found that the SUS Pos gains were all screwed up for unknown
reasons. He set them to 1.
- Osamu
and Rana realigned the beam path, starting with
the PMC, then the Mach Zehnder, and the
periscope, each time gaining significant amounts of transmitted power.
Alignment to the MC is pretty good now, and the MC is locked again.
IFO Modeling
- Rob
is at Hannover
for a QND workshop. He's giving talks on the optical spring as observed at
the 40m, various modeling tools used to understand the AdvLIGO
configuration, and his new modeling tool OpTickle.
See QND.
- Osamu
worked on e2e and Bench modeling of the 40m noise. He verified with e2e
that the RF demod phase of the photodiode at the
AP changes the effective homodyne phase, as predicted by Kentaro, and the transfer functions measured with e2e
with different RF demod phases agree well with
the prediction from the Buonanno/Chen theory
with different homodyne phases. This means that we can investigate
different homodyne phases with the 40m, even with RF readout!
- Osamu
notes that e2e is currently the only software tool that has both RF
readout and radiation pressure effects. Corbitt's
code doesn't have RF, Finesse doesn't have radiation pressure. The OpTickle code being developed by Matt and Rob will have
both.
- Osamu
has been modifying Bench to get more realistic predictions for the
seismic, thermal and suspension noise. He predicts that it may be possible
to observe the dip in the noise spectrum associated with the optical
spring if we can get all technical noise sources down.
DC Detection Development
- Mike
has changed the drawings of the OMC beamline
components to shorten their heights accordingly to accomodate
a baseplate. Updated the 40M optical layout to
add the changes. Steve is making the new baseplate.
CES is modifying the OMC reflected beam steering mirrors mounts, and is
fabricating the OMC. Lee Cardenas
is assembling two DLC PZT mounts for a test of the OMMT steering mirrors.
Mike will show Steve how to assemble the PZT tilting platform to the DLC
mounts. He is in the process of submitting DCNs
for the changes.
- Rana noticed that the in-vac
DC readout beamline has no beam dumps. He and Steve
will get some black glass.
- The
AP table will need some rearranging for the OMC reflected and transmitted
monitor beamlines. Rana
will see if he can use Mike's ACad layout.
- The
MIT squeezing group propose to build a 2nd level
on our AP table to hold their squeezer. We will look for simpler
alternatives that don't require periscopes.
- We
would like to dispense with the Mach Zehnder and
drive a single pockels cell with one cleverly
synthesized waveform to get all our sidebands and no
sidebands-on-sidebands. We'll talk to Reitze
about the work they're doing on this at Florida.
- Dan
and Sam are discussing how to proceed with testing and developing suitable
drivers for the in-vac PZT mirrors for DC
readout.
- Rana is thinking about how to most easily control the
OMC length and input beam alignment, using all-digital dithering and
demodulation, with existing hardware (so we wouldn't need to but an analog
lock-in).
- Ben
is continuing to work on the DCPD mount design. The PD electronics
prototype is assembled and waiting to be tested.
Electronics, Controls, Computers
- Ben
and Rana installed the Table Top FSS following
the installation plan E040423-00. Ben has drawn up a schematic for the
system, and assigned cable names to the cables.
- Some
of the FSS signals to EPICS were being pulled down by the DAQ interface
board. Ben discovered that the board was not wired correctly, and he fixed
it. We still need to check out the signals through the Sander box to the
DAQ.
- 5 RFPDs are beginning their final assembly for the 40m
lab. Ben will tune them to the appropriate RF frequencies next week.
- Alex
restarted our DAQ frame building and logging to our new 1.5 TB RAID array.
- Alex
tried many ways to recover the 3.7 years of minute trends from our old
failed RAID array. There's some partial success, but he's still at it.
Stuart Anderson came by to help.
- Stuart
is setting up a path to back up our code and frame data onto disk/tape
archive at the CACR SAM-QFS system.
Lab Infrastructure
- We
have two new 20" LCD monitors on the operator consoles.
- The air conditioning thermostat failed. It was
replaced and recalibrated.
Thermal Noise Interferometer (Black)
Improving the visibility of the arm cavities
has reduced both the shot and electronic noise to about 7x10-20
m/rtHz in both cavities. Added in
quadrature, this comes to 1.4x10-19 m/rtHz for the differential
signal. Attached is a plot of the latest noise curve. Red is data. Top blue curve is old coating
noise (undoped). Lower blue curve is doped coating noise. The green curve is
the shot/ electronic noise floor, and the black curve is the quadrature sum of
this noise floor and the doped coating noise.

LASTI (Ottaway)
LASTI Weekly (Harry, Penn, Mittlemann, Ruet, Ottaway, Sarin, Mason, MacInnes and
Shapiro)
Electronics
We are currently sorting through and simplifying our electronics. The electronics
for the two triples have been consolidated into a new rack located next to the
HAM Xend Chamber. They have been tested and are fully
operational again
BSC Installation Fixturing
Last week we received the new clean room and test stand for assembling and
testing the internal seismic system and quad-pendulum controls prototype. Both are currently being assembled, some
pictures can be found on the Lasti ilog, on December 15, 2005.
The frame of the clean room has been erected and the final gussets are being
installed, after which the blowers and lights will be mounted.
Holes in the floor for the test stand have been drilled and we are testing
our assembly procedures to see if they will meet the required accuracy. So far
we have mounted two feet and a connecting beam, which are within the needed
tolerances.
Initial LIGO Suspension Testing
Working with visiting scientist Steve Penn, we are assembling a mock up initial
LIGO suspension to explore suspension thermal noise issues for initial LIGO and
any potential enhancements.
We now have nearly all the components, including a suspension cage from Caltech
(courtesy of Janeen), a pathfinder optic from Caltech
(courtesy of Gari) with standoffs and guide rods put
on by Doug at LHO, and various cabling etc.
This all being installed in the old PNI chamber/Ryan's
bell jar at MIT.
The plan is to measure violin mode Q's to see what influence the clamps and
standoffs have on the suspension wire loss.
With this setup we will be able to vary aspects of the clamping, wire
length, etc. that are not accessible at the sites.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
Weekly Physics Meeting
Sany Yoshida presented results from his studies of
the effects of violin modes in a LIGO I arm cavity. He also talked about his
toy model for advLIGO HAM using an e2e box file of
zeros and poles to mimic the required AdvLIGO HAM
table top displacement.
modeler 3.1.0
(Hiro) A new version of modeler 3.1.0 is released.
Major changes are (1)
modeler_freq is reactivated which was disabled in
version 3.0 because of the change of the data stream (2) dual recycling cavity module can utilize
threads. With 5 frequencies, on homam.ligo.caltech.edu, the 40m simulation runs
30% faster using 4 threads. Still, the overhead of activating threads is not
negligible when compared to the tasks which run in parallel using threads, and
thus the benefit is not so great. In the future, when the modal model is
implemented, the performance improvement should be greater.
40m model
(Hiro) DC readout scheme is studied using a simple
40m model which was used for the study of optical spring. With Osamu, we start
looking into the possibility of building the full 40m model based on the AdvLIGO framework setup by Matt.
FFT Study
(Biplab) Using matlab
FFT model, computed the numbers for frequency shifts for higher order eigenmodes in Advanced LIGO arm cavity (with finite-sized
mirrors). Sorted out some differences in results with Pablo Barriga (Univ of W. Australia).
Alfi
(Melody) Working on PR 296 - easier access to settings.
Made initial release
of the Info Panel. Currently implementing additional features.
Data Analysis Activities (Lazzarini)
Mendell:
I worked with LDAS to set up a pulsar user with service certificates to
generate SFTs at LHO and LLO, and SFTs
generation from uncalibrated DARM_ERR is running
under onasys. Using these SFTS, a report on an
initial StackSlide search for lines in the S5 data is
posted here (usual pulgroup group access required): http://www.lsc-group.phys.uwm.edu/cgi-bin/enote.pl?nb=puls5stackslide&action=view&page=2
Shawhan:
- Attended
the LISA International Science Team meeting at Caltech.
- Reviewed
pulsar analyses.
- Finished
preparing S4 LIGO burst search talk for GWDAW.
- Made
suggestions/comments on other people's GWDAW talks/posters.
- Currently
attending GWDAW.
Sutton:
This week I've prepared a talk on the LIGO cheese for presentation at GWDAW
10. I also helped Maria Principe with
her presentation on modelling networks of detectors
for GWBs searches.
I've spent the rest of the week at the conference.
Yakushin:
Working on online waveburst web
page.
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS
The focus has been on generating 64 bit version of tools and libraries
required by LDAS (PR#2958) now that support for large files has been
successfully implemented. Have been successful in compiling
the following packages 64bit: Tcl, Tk, FFTW, ObjectSpace, lam, lynx
and cURL. Have also
been successful compiling the lib directory of LDAS 64bit and all unit tests
have passed. Will now begin working on the LDAS API source code.
Are nearing completion of the rework of LDAS managerAPI and the controlMonitorAPI
to use the newly available TCL-Channel tools from TCLGLOBUS. Testing of
these code changes has re-introduced the previously discovered issue with
GLOBUS locking up the SUN Solaris 10 kernel when the Globus
environment variables are not valid.
Addressed the controlMonitorAPI PRs 2969 and 2964 associated with the running of the
"All Users Command" test from the GUI interface.
The code is now in place, but further testing will be needed once LDAS-DEV
is back up from the being shutdown for the Millikan
power outage last night.
Successfully completed the system and integration testing
on last Friday's build (1.8.24) of LDAS.
TCLGLOBUS
TclGlobus 0.4.0 has been released with the
following support XIO-based Tcl channel. This release
is only for LDAS development to convert from using raw Globus
GSI socket to XIO-based Tcl channel.
Resolved the issue with Globus FTP control and
data channel synchronization. Based on FTP response code <= 150, the
callback clenup routine MUST NOT be invoked because
the requested action expects another reply using the same state information
from previous action in which the routine MUST be invoked.
Modified MyProxy service
configuration on tclproxy.ligo.caltech.edu box to accept DOE-issued
certificates only.
GRID COMPUTING
Working with the data repository staff, obtained registered Level 4 data for
optimizing storage resources for binary inspiral work
flows on storage constrained OSG resources so that wide spread testing of Inspiral work flows can be accomplised.
Determined that a problem exists in latest patch to
support Level 4 data in lalapps. Working with developer to resolve the problem.
Discovered that the OSG 0.3.1 release did not have the VDS
installed in the base cache. Worked with Kent Blackburn and OSG-INT team
on resolving this issue for the release of OSG 0.3.3
Successfully testing Inspiral pipeline from DAG
generated with the OSG 0.3.1 release and running on the LIGO-CIT-ITB test bed
with OSG 0.3.1 installed.
Fixed error in OSG:vo-0.2.1 pacman
cache that had omitted the LIGO VO.
Updated Validation page in OSG Twiki related to
latest validations.
On-going OSG-ITB Cluster monitoring and systems administration:
- Yum
updated osg-itb and osg-itb-se.
- Installed
GUMS components including tomcat, mysql and the
GUMS server under fc4 on tclproxy. Determined
that a new Hibernate object-relation mapping in GUMS 1.1 will require
additional engineering effort to update the GUMS 1.0 configuration for osg-itb.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Still
pursuing the question of why some files are not being archived for a very
long time and then only with human intervention.
- Loaded
1025 tapes (barcodes C0????) into the CIT silo. 200 of these will be used for LIGO, the rest may be used by Teravoxel.
- Helped
Lisa Bogue at LLO with replacing a disk in a
3510 (/ fb0_frames).
- Did
several samfscks of export-dev and collected
data to assist with the debugging effort.
- Ended
up making export-dev back into a UFS filesystem.
- Hunted
down and accounted for damaged files at all CIT/LLO/LHO.
- Did
the standard tape exporting, shipping, ingesting.
(Stuart Anderson)
- Attended
NSF Cybersecurity workshop
- Tested
new 21kW power strip for each Opteron cluster rack.
- Shutdown
and restarted all the LIGO computers in Millikan
for building electrical work.
- Installed
latest SAM-QFS patch on test systems at Caltech which should fix the
system crashes we observed at the Observatories at Thanksgiving.
- Working
on a solution to archive 40m frame data.
(Erik Espinoza)
- Built
ldas-kickstart machine for deploying nodes.
- Deployed
80 nodes using PXE.
- Configured
Condor on 80 nodes.
- Replaced
drives in 'ldasadm1' w/ Western Digital Drives.
- Replaced
memory in 'albireo' w/ Transcend memory for
testing.
- Testing
1UIPMI-B Card Revision 1.1 from Supermicro.
- Deployed
desktop for Dan Kozak.
- Shutdown
systems on Wednesday 12/14 for Millikan powerdown.
MIT
(Keith Bayer)
- Renewed
Sun contract for equipment.
- Reset
foundry switch after it locked up.
Livingston
(Igor Yakushin)
- Installed
FC4 on ldas-gridmon and configured ganglia.
There still seems to be some problems with it though: it sees only about
90% of the nodes, today all of a sudden it stopped working and I had to
restart it.
- Twice
during the recent week node9 stopped working without any apparent reason
or error message and I had to reboot it.
(Dwayne Giardina)
- Replaced
the two power strips that recently failed.
All nodes are back operational.
- Shipped
tapes LL0539, LL0563, LL0578, LL0579, LL0582, LL0584, LL0677 to CIT.
Hanford
(Greg Mendell)
- I
continue to work on a number of issues. The air conditioning noise in the
LSB at LHO is an annoyance for people working in the offices (not a
problem for the IFOs). I am working on ways to
reduce this. The LDAS and GC sys admins also met
to discuss how to make the LSC Data Grid tools more accessible to GC
users. I also worked with LDAS to set up a pulsar user with service
certificates to generate SFTs at LHO and LLO,
and SFTs generation from uncalibrated
DARM_ERR is running under onasys. The photon
calibration channels, L1:LSC-ETMX_CAL_EXC_DAQ and L1:LSC-ETMY_CAL_EXC_DAQ
have been added to the Level 1 RDS frames being generated at LLO, starting
from GPS 818543232 = Dec 13 2005 15:06:59 CST = Dec 13 2005 21:06:59
UTC. (These have been in the
Hanford Level 1 RDS frames since the start of the run.) S5 RDS generation
continues to run smoothly.
(Ben Johnson)
- Fixing
broken nodes. All nodes which have working network connections are
working. Some are not cabled, others have odd
packet losses.
- Helping
Xavi get his h(t) code
optimized for the cluster nodes.
- Ran
Dan's weekly L0 data export script. It was successful.
- Upgraded
laptop to FC4. No data loss occurred.
- Set
up webserver for cluster user output. It is
password protected, a completely-GC machine, and mounts /archive
read-only.
General Computing (Wallace)
Lazzarini NOTE: I attended an NSF-hosted workshop
on Cybersecurity.
The NSF plans to issue a set of cybersecurity
guidelines applicable to large NSF programs, such as LIGO. THe
impact is being evaluated, but it is likely that some of our less secure
practices will need to be changed.
Shannon, Barker, and I have started a dialog about potential impacts.
MIT
(Keith)
- Received
replacement power supplies from Sun for SB1500's
- Working
on OpenLDAP server for gc
linux support (and then eventual gc solaris support)
- Copied
Linux dmt software to central NFS mount location
- Built
linux gc workstation
(FC4) and am testing it on gc network with LDAP
- Researching
local VPN install on wireless router
Livingston
(Dwayne)
- Changes
to HTML/PHP interface for security server activity logs.
- Scripted
retrieval of security server activity logs. script also
"cleans" (removes identifying information from) the published
files. Originals are kept in
multiple locations, both copies are backed up on
tape. process
is scheduled to run weekly after the activity log report is created on the
kantech server.
- Monitor
on einstein linux box had minor issue.
Hanford
(Christine)
- Participated
in a meeting to discuss consolidation of data analysis configuration at
LHO among LDAS and GC. Conclusion is that there is already a method for
accessing grid tools from GC Solaris and Linux. Windows has some support. Long term goal
is to have a FC4 GC computer in the Control Room for access to the grid
tools.
- There
was a network outage on Tuesday night, 12/13, from about 20:00 to 21:30
PT. The LHO router did not
fail-over to the new backup network as it should have. I will schedule testing of the backup
network with all parties concerned ASAP.
- Finally
was able to get an answer from Cisco on renewing my support contract. Apparently Cisco is not issuing any new
contracts, and since my contract expired more than 60 days ago I have to
buy a new contract and have my equipment re-certified. There are about 50 Cisco partners in Spokane, the closest
to the Tri-Cities. I am hoping to
use the same company as PNNL.
- Lots
of user support this week for Kronos and Tech
Mart.
- Purchased
two more new laptops for users.
- Finished
setting up a new DMT/GC AMD computer running Solaris 10 as a NIS+. Still have to do some hardening of
Solaris 10 and install the latest patches.
John Zweizig has a collection of
application software on his other DMT machines that need to be mounted.
- Started
mounting LDAS directories on all GC Sun computers to allow use of the grid
tools from Solaris.
- On
going troubleshooting of the local network experiencing periods of slow
performance. Still have an
occasional problem with remote host names not resolving. This could be caused by the network slow
down or by the router dropping packets.
- Other
misc. user support.
CIT
(Mike)
- Finished
up loading and swapping out a sun workstation for Peter King.
- Loaded
a 2003 server for Dennis Coyne to run some simulations using Algor and Ansys software.
- Worked
on a Laptop for Janeen Romie.
This laptop had a driver issue, and it would not recognize the hardware
key for Solid Works. She is up and running. The instructions I have put
together on the Solid Works dongle issue does work. I have posted the fix
for Solid Works on my homepage ~mpedraza.
- Problem
with the wireless access points. This turned out to be a network
connection issue over in Synchrotron.
- Working
on loading my new laptop "IBM T43 2668-CEU" I have made this a
dual boot laptop to run Fedora core 4. The internal wireless card is not
compatible with LINUX. I have a few more tricks that I found on the web to
try before switching to an Orinoco
wireless card. IBM does have a compatible internal card for LINUX, if you
purchase an IBM for someone that is planning to run LINUX make sure the
internal wireless card is not "11a/b/g Wireless LAN Mini PCI Adapter
II" It looks like all other cards are compatible with LINUX.
- Worked
on the new DCC system installation. Was finally able to get the software
installed. Now we need to go back and re-install everything from scratch
to make sure we have it installed correctly.
- Spam
Filters: Continued work on the spam filters searching for false positives.
- Other
misc. user support.
(Veronica)
- LIGO:
Updates to the PAC meeting website. Posted the meeting presentations.
Roster database updates. Prepared high-resolution images for OSA. Updates
of various LIGO webpages. Installing Windows updates
onWin servers.
- LSC:
Updates of the database of the papers under review. Updates to the
Observational results pages. Mailing list updates.
(Christian)
- Replaced
toner cartridges on HP 2550 printer at the 40M. Also, I replaced two old
CRT monitors with two LCD monitors.
- Replaced
toner cartridges on HP 5500 printer in Millikan.
- Re-imaged
3 laptops that were returned to the loaner pull this week.
- Working
on creating a Windows XP Unattended Installing Disc.
- Other
misc.: Continued onsite software/phone support.
(Larry)
- Resolved
a couple more procurement issues. Mainly supply related items.
- Worked
a number of licensing issues. Need to review all of the licenses once
again to make sure they have all been renewed for the year. Setup some special temporary licenses to
cover a couple of people on travel.
- Worked
with Mike on setting up a couple of new boxes. One needs additional memory
to be useful for the engineering group.
- Worked
a couple of backup issues. Stuart
has given us the go ahead to move the tape storage to the LDAS computer
room.
- Assisted
the PMA group with their installation of a quad cpu dual core unit. It is using the RH
Enterprise OS. The latest version was missing some drivers so they went
back to version 3. Also, discovered
that the fiberchannel card needed to be
installed into the slower PCI slots.
- Continue
working on mail filters and user accounts.
Mail Statistics for Dec 08-14, 05
|
Mail Statistics
|
December 08 - 14, 2005
|
|
Rejected Messages
|
19,865
|
|
Virus Messages
|
974
|
|
Accepted Messages
|
15,629
|
|
Total Messages
|
35,494
|
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Systems, Management
from Dennis
Coyne
Systems
See
also:
AL Systems
web page
AL
Systems email archives
Records of Decision or Agreement (RODA)
See also the RODA
status web page
Requirements
Interface Issues
See the "Interfaces" section of the AL Systems
web page
- LIGO Lab is in the process of
reviewing and revising our full scale prototype test plan at LASTI, and in
particular the seismic isolation system options which support the LASTI
program plan. We conclude that LIGO Lab can not benefit from a delivery of
the quad noise prototype any earlier than Feb, 2007. We also have
concluded that critical information from the evaluation of the quad
controls prototype will not be available soon enough to support a
currently planned Feb, 2006 Preliminary Design Review of the Quadruple
Suspension. We suggest that the SUS/UK team plan for a PDR no earlier than
April, 2006 and a delivery of the noise prototype on or about Feb, 2007.
The SUS/UK group are considering how to
accommodate this delay.
Vacuum Compatibility
Vacuum Preparation [Cleaning, Baking, Residual Gas Assay (RGA)]
See also the Vacuum
Bake Lab
Bob Taylor
- I
have received all of the parts to assemble the ESD connectors and have
half of them done. I will finish those today.
- I
am currently baking the eddy current assemblies and magnets. They will be
out of the oven on Monday.
- I
have an oven load of top mass stainless parts baking in oven F now and
that load will be done tomorrow.
- I
have made all 20 OSEM spares and I am putting pinplates
on them today.
- All
cabling has been done for the Quad OSEMs and has
been cleaned / ready for baking.
- The
FTIR test sample has been taken and I am waiting for Mark to e-mail me the
results.
- Glass
plates and optics have been cleaned and will go into oven F as soon as the
top mass parts are out. ( probably tomorrow).
High-Irradiance, Contamination-Exposure Cavities
Advanced LIGO Data Acquisition
From: Rolf Bork rolf@ligo.caltech.edu
- Still
having problems getting the PCI Express to PCI-X expander unit to work. We
now have an RMA to return the unit to the manufacturer for testing. The
unit will not be back before Jan. 12.
- In
light of our problems with that unit and the need to field something
quickly for the quad testing, I ordered a PCI-X to PCI-X expander from a
different company and it arrived yesterday. It appears to be working well
in our quad development test setup. It uses a 5Gbit/sec serial link
instead of the 10Gbit/sec serial link of the PCI express version, but
still quite acceptable for our application. This manufacturer has a PCI
express version due out in January and the system I bought can be field
upgraded to this version when it comes out. It will just require a new daughtercard in the expansion chassis along with a PCIe card in the host.
- Ported
about 98% of the Hepi software necessary to run
3 chambers at Lasti. Remainder of the work is
mostly testing the watchdog code.
- Recieved PCI-X binary I/O modules for use with Hepi controls. I am in the process of writing the
driver (50% complete). These modules have 24 IO channels, programmable as
input or output in 8 channel blocks.
Seismic Isolation
Advance LIGO SEI Procurement
Purchase orders were placed this week for the maraging
steel springs and rods with delivery planned for 2/15/2005. Some assembly
tooling and fasteners still remain to be ordered.
Additional in-vacuum cabling and feedthrus were
ordered for the installation of the BSC seismic isolation, quad controls
prototype, triple suspension, and Ham seismic isolation.
The granite table which will be used for seismic isolation sub-assembly has
been installed at LASTI. Work continues on the installation of the test stand
and clean room.
From: "Joseph A. Giaime"
jgiaime@ligo.phys.lsu.edu
Agenda for the weekly SEI telecom
Friday, Dec 9, 2pm Eastern, 1pm Central, 11am
Pacific time
Announcements
- HAM
SAS committee has met, and is working on consensus report.
Single-stage active stage study, Brian L:
- Finesse
modeling estimates 10 Hz requirement at 1e-15 m/rtHz
for the SRM itself. Other optics need
study. For RMS requirement, more detailed servo and optical
detection SNR calcs need to be done.
- Requirements
review in March, preliminary design sketched out and costed
by May NSF review. Goal is to estimate the cost savings from
dropping back to single stage in HAMs.
- issue of whether all output detectors are in vacuum;
extra cost?
BSC SEI status, Ken/ Dennis
- Limerick parts should begin shipping next week
- Maraging steel received. Still no quotes on
machining
- Still
working on heat treat specs.
- Cable
order still in prep.
- LASTI
prep underway, including assembly of test stand.
BSC work, adaptive modeling and FIR (Rich M)
HAM control with VME (Pradeep)
- some trouble with GPS antenna under snow.
LLO HEPI, partial end to the madness - Brian O'R.
- ITMX
HEPI fixed: the instability was a bad Pentac
DAC, a stuck bit or the equivalent.
- It
may be still ringing up the test mass bounce mode, and this is under
investigation.
ETF platform work - Matt & Brian
- Stage 1, all 6 DOFs are
controlled. Stage 2, controller under design.
- System
is at air now. Next big goal is to test pendulum frame dynamics.
- L4-C
dissection photos and movie on web. Gaps are quite small. Some
of the spider disks seem to be rotated about the cylinder's axis, enough
that the little legs can interfere with each other. Hua says that one can tell when they get stuck by
measuring main coil resistance.
Seismometer work - Aaron
Electronics, - Jay
- The
design of the chassis and interface boards for the capacitive position
sensors has been restarted. I am working with Ken Mailand
to make it fit in the allotted space.
- The
actuator coil driver prototyping has been restarted.
- Pod
internal cable harness designs are in progress and should be ready to
order in the
- next couple of weeks.
- Electronics
designs and rack layouts for LASTI ISI and HEPI are in progress.
Suspension
From: "Mark Barton"
<mbarton@ligo.caltech.edu>
This week I integrated a lot of contributions from the design team (especially
Ian Wilmut, Justin Greenhalgh,
Norna Robertson and Calum Torrie) to come up with a Mathematica
model of the quad controls prototype that for the first time accounts for the
observed behavior with all as-built numbers and no fudges. New physics had to
be added in two areas:
First the fact that some of the wires are diagonal puts the blades into compression
along their length, which affects their vertical compliance. Ian discovered this in CAD simulations, I
confirmed it with a single-blade test pendulum, and then showed it can be
simply accounted for by treating the blades as sideways inverse pendulums. The
blade tip moves on an arc with a radius of curvature a little less than the
physical length of the blade, and the horizontal
compression creates a negative component of vertical restoring force. This
resolves mysteries with the vertical mode frequencies as well as the mass
budgeting used to match springs and clamps to payloads.
Second, the fact that the blades have significance lateral compliance turns
out to be the cause of the instability of the fundamental pitch mode in the
first build. As the masses pitch, a component of the load begins to act
laterally on the blade, changing the lever arm between payload force and pitch
so as to exaggerate the pitch. Justin and Norna argued
that the lateral compliance effect mimics the wire stiffness effect in that it
changes the effective flexure points (although in the opposite sense). I
confirmed this by adding lateral movement of the blades to my Mathematica model, using values of lateral compliance supplied
by Ian. It resolves the mystery of why the reworked pendulum was stable with a
satisfactory fundamental pitch frequency with only about half the wire flexure
correction originally designed for.
Together these refinements mean that we should be able to make fairly robust
designs for future pendulums, even for steep wire angles and/or blades that are
less than ideally stiff in the non-working directions.
From: Janeen Romie romie_j@ligo.caltech.edu
Here at Caltech, working with the SUS team on assembling the quad. Provided comments, with Helena,
to Caroline and Russell on the penultimate mass and reaction mass drawings for
the noise prototype. Hope to have a telecon
with them this week. Will meet with Gari this morning
about the noise prototype test mass drawing.
Checked with Ric on the progress of fabrication
From: Calum Torrie ctorrie@ligo.caltech.edu
Assembly (re-build)
Janeen is visiting this week. Janeen,
Helena, Lee and I have been putting together the top stages and the top masses.
Lee and I have finished all of the wires and are waiting on the glass fact
plats to complete the lower structure assembly. No major problems to report
with respect to the clean build apart from one of the top blade assemblies had
to be taken apart and re-assembled due to a bolt that was damaged due to a mis-aligned blade.
Cleaning and Baking
Bob, Lee and I are continuing with the cleaning and baking. As of Friday we
will only have the osems, magnet assemblies and glass
face plates to bake. With 3 working ovens All of this
should be complete by Thursday. one final item, some Viton, will be baked over the holidays!
FEA and lab experiment on the lower structure
Working with Tim Hayler on the structure FEA and
in particular considering bolted connections.
Mark and I measured the resonances of one half of the lower structure. Results to follow.
SolidWorks, PDMWorks
and CAD
At last weeks opto-mechanical meeting I ran a
tutorial on PDMWorks. At a follow up discussion Ken,
Mike and I spent 90 minutes or so going through some of the detail of how to
use PDMWorks.
From: Ken Mailand kmailand@ligo.caltech.edu
I’m working on shop drawings for the SUS installation plate style
fixture for Calum, I have the major details nearly
complete and was able to get estimates of cost and delivery from Mike Gerfin at CES, and a local shop.
From: Helena Armandula ahelena@ligo.caltech.edu
From: Jay Heefner jay@ligo.caltech.edu
AdL SUS and SEI Controls at LASTI
- Work
continues on design and layout of the quad controls prototype, the
Internal Seismic Isolation, HEPI and triple suspension controls.
- Chassis
ordered for prototype of the capacitive position sensor field interface
box. Design of the electronics for the chassis are 80% complete.
- Connectors
ordered for STS2 pod cable s.
- A
block diagram and some preliminary requirements for the LASTI timing
system has been completed.
- All
electronics are completed and ready for the quad controls test at CIT.
These tests will begin when quad reassembly is complete.
Core Optics
From: GariLynn
Billingsley <Billingsley_G@ligo.caltech.edu>
A "low birefringence" sample of 311 from Heraeus
has been sent for polishing. This will be tested by Steve Penn for
mechanical loss. RFQ has gone out for polish of four small samples of Heraeus 311 and 312. These various sizes will be used
for pre and post annealing tests.
From: Bill Kells <kells@ligo.caltech.edu>
I have been going over the initiatives which were brought up at MIT with
respect to the "stable PRC/SRC". As of now there are many issues in
this which are separately being looked at and only loosely connected (different
"designs", whether it should be PRC, SRC, or both; how much focusing
is sufficient; impact on PI, etc). Specifically I have taken up the question:
"how would SRC stability affect the need and/or design of the [apparently]
necessary OMC? A distinct OMC would seem to be, in itself, a substantial beast.
So could it be subsumed in a particular SRC (stable )
design?
More generally, it seems to me that we need to focus on some particular "straw
man" PRC/SRC stable design and carry that through to a much more refined
level. The concept now (since MIT) seems to have been accepted as worthy.
However a reasonable implementation is by no means clear,
and then how much actual performance would a "real" design give? The
May "deadline" you have emphasized seems alarming, since really
vetting even a "straw man" design ought to use the new AdL simulation code which evidently with hardly be available by then.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
The relaxation oscillation of the Innolight NPRO
was measured. It occurred at a relatively low frequency of 363 kHz.
Whilst the noise eater suppressed the relaxation oscillation, it added
intensity noise at lower frequencies
Auxiliary Optics
From: Michael Smith smith@ligo.caltech.edu
Other Laboratory R&D
From: Riccardo DeSalvo desalvo@ligo.caltech.edu
Yumei: learning Solid works
Valerio: out for exams
Riccardo: Working on the installation strategy of
HAM SAS in LASTI and other HAMs
For additional information about this report, contact Stan Whitcomb or Phil Lindquist