Weekly Report for
Week Ending December 8, 2005
The LIGO Executive Committee meeting for December 12,
2005 will not be held because of the PAC meeting scheduled for that day.
Special Announcements:
Weekly
Report Highlights
No report.
LIGO Laboratory Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
LSC MOUs and Research Plans and Progress Reports
Non-LSC MOUs (Lloyd)
SITE TELECONFERENCE (Lindquist)
A site teleconference was conducted Thursday, December 8, 2005. The following were among the issues
discussed:
- Budgets
– we are reviewing the fy
2005 actual costs and budgets. We
spent 96 percent of the budget for labor and 88 percent of the funds
allocated for travel. However, we
only spent about one half of the funds assigned in fy 2005 for supplies, materials, equipment, and
other purchases. We are reviewing
this to determine how much relates to deferred procurements and tasks.
- Property
– E. Chargois and R. Luna visited Hanford this week to
conduct a review and to introduce Mr. Luna to the site and personnel. The spare AC unit was packaged and
shipped to MIT.
- There
are no open assigned actions. The
list of assigned actions updated through December 1, 2005 (the last time
that it was updated) will be found Here.
PROPERTY MANAGEMENT (Chargois)
>From: Ed Chargois <chargois_e@ligo.caltech.edu>
- Nothing
significant to report.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
>From: Cleveland Mak mak_c@ligo.caltech.edu
|
Week Ending
December 8, 2005
|
In
|
Out
|
|
Packages
|
24
|
5
|
|
Faxes
|
15
|
15
|
- Scanning Project - Progress continues on scanning
of F. Asiri boxes of files. To date about 5+ boxes have been
scanned. Progress continues on
scanning of old blanket purchase order files.
COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Issued
two one time purchase orders to Limerick
for custom fabrication of additional parts for MIT.
- Placed
several orders for the purchase of goods for delivery to MIT and to
Caltech.
- Working
on several invoice issues pertaining to taxability on orders for the
sites. Have requested the vendors to issue credits for the sales tax
amounts billed.
- The
A-133's are being audited and MIT's file was requested. The file along
with the current A-133 along with MIT's audit report has been submitted.
It was also requested for Triad, for which this requirement is not
applicable.
- The
California
state tax auditors will be on campus in April 2006.
- Transferred
funds on the Excel subcontract [to facilitate FY 2005 payments and set up
the subcontract for FY 2006 - pel].
- Completed
the change order for the purchase of optics from REO under the subcontract
and faxed it to Katherine.
- Requested
for the credit invoice to zero out the invoice billed for the one
evaluation unit returned to ASA Computers.
The vendor will get back to me on the pending credit for the two evaluation
units billed at the higher amounts.
- Returned
the low-profile jack for credit to McMaster Carr. Once the credit invoice
is generated, it will be matched against the billed invoice.
- Completed
change order #32 to GSI and submitted it to the vendor.
- Completed
change order #10 to Benton
County which adds
funds for FY2006 to cover electricity usage at LHO.
- Completed
change order #15 to Gennaro, Gianni and
submitted it to the vendor.
- Completed
change order #1 to Total Energy Management and submitted it to the vendor.
- Completed
the large-dollar order to ASA and routed it for approvals before it is
submitted to the vendor.
- Completed
change order #2 to Eskew Dumez Ripple to add
$5,040 to increase the number of site visits and submitted it to the
vendor.
>From: Florence Kaufman <fkaufman>
- Issued
monthly reports for FY05 and FY06 Operations for data through November 30,
2005.
- Provided
information for analysis of unspent funds in FY05.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- Construction
of the LLO SEC remains on schedule despite intermittent rain in Livingston.
The noise of the construction, however, is effectively taking LLO
out of the S5 run during the day.
- Two
bids have already been received for the installation of the LDAS HVAC at
LLO, with a third bid expected tomorrow.
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
- Processed
the paper work for fifteen (15) new/revised trips. At this time there are six (6) trips
completed or in the works but are awaiting the necessary paper work to
enter the P-Card system.
- Completed
eight (8) Expense Reports and there are twenty-two (22) reports yet to be
done. I continue to contact
travelers who have outstanding Expense Reports (more than one (1) month
old) to ask for their cooperation in sending me their receipts so that
these can be closed in a timely manner.
Presently there are zero (0) report more than thirty (30) days old. I have no reports awaiting signature at
this time.
>
- Working
on details for PAC 19 meeting in LHO.
>Dorothy Lloyd
- Processed
invoices for payment and followed up on invoice problems. Reviewed and
recorded invoice payments for the month of November. Processed the usual requisitions for
purchases
- Jim
continued with data entry in the LIGO database and helping out in the
DCC. [Contact Jim for December
Supplies orders – pel.]
PROPOSALS and REPORTS (Lindquist)
- Requested
a one year extension for the Visitor’s Program Grant.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- No special activities to report.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
Nothing significant to report this time.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of
Commissioning Activities at LIGO Hanford
Observatory (compiled by M. Landry)
Highlights from the last week of elogs are
bulleted below:
- the
Tuesday maintenance period was limited to about a five hours... in this
time the H1 fine actuator controller box was fixed (see below), the photon
calibrator output was swapped
to other arm (both IFOs), H2 laser work ensued
(below), and pulsar injections turned off for two weeks to ensure we
have some running without them. The latter point is of great
interest to the burst search group, as there was some concern that the
pulsar injections were responsible for low-level transients observed in
the data.
- AWG
code loaded last week appears to have improved
the situation somewhat regarding calibration line drop-outs: long term
(~1s) dropouts have now not been observed, but single-point glitches have
been seen.
- S5
PEM injections were begun
on the 4k and the 2k instruments, and later, nearly completed
- coil
magnetometers in the external, buried vault were recommissioned and calibrated
4K IFO
- since having its calibration updated, H1 has indeed run
for stints at 12 Mpc, however this week it has
run typically at 11Mpc during evenings. The reasons for the lower
range are not yet understood, but coherence between AS_Q and AS_I in the
10-few hundred Hz range is now large. FJR has suggested upconversion from times of higher microseism is
responsible. The useism loop was broken
during POPI commissioning, so this is currently off but will be recommissioned next week. All ASI loops have
been observed to saturate
during the day. REFL_I was seen to be coherent
with AS_Q during times of lower binary inspiral
range; the coherence was decreased by better aligning the light on the
reflected photodiode.
- The
x-arm fine actuator was responsible for some lock-losses,
as the PZT actuator railed. This meant the controller box had two be
swapped out on a Tuesday maintenance session.
- we
continue to struggle at times with configuration control issues, e.g.
notch filters erroneously
applied in the ASC were removed and gold-standard and STAT variables reset
- it
was suggested that AS_I phase tuning could minimize junk
modes in AS_Q
- windowing,
and possibly single precision floating point calculations in DTT explain
the lack of perfect coherence
observed between DARM_CTRL and AS_Q
2K IFO
- the new calibration for H2 impacted the binary inspiral range (upwards) by about 10%, neatly moving
us from 4.5Mpc to the S5 design goal of 5Mpc. This calibration of
course applies retroactively back to the start of the run.
- an alignment of the PSL clawed back 1W in laser
power during maintenance; the alignment had clearly drifted in the
last fifteen days and was temporarily improved. About 1/2W has been
lost since this Tuesday alignment, so drift continues..
more here
noting that simply removing the cover improved the power
- the
source of the broad bump near 1.6kHz remains unknown
although there are suggestions of aliased high frequency lines
DAQ
- multiple disk failures
plagued fb0 last Friday, with fixes
in place by Saturday morning.
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
L1 Interferometer (Frolov)
The cumulative duty cycle for science data taking has approached the current
daily and weekly average level of 50%. This week it was mostly limited by
seismic noise from construction and exceptionally bad weather (high winds and
microseism exceeding the 95th percentile of historical levels). The Tuesday
maintenance period had to be extended to continue investigation of the
persistent ITMX HEPI instability and to diagnose an electrical short in one of
the piezo actuators on the Mode Cleaner input beam
periscope. The ITMX HEPI malfunction was finally traced to a stuck bit in its Pentek digital to analog converter (now replaced).
The interferometer BNS range improved to 10+ Mpc
during quiet times after retuning of gains for subtraction of the Michelson and
recycling cavity degrees of freedom from differential arm motion.
Modification of the anti-symmetric port photo detectors to increase the RF
coupling increased the range of the AS_I servo, which in turn reduced apparent upconversion in the electronics at frequencies below 100
Hz.
Unfortunately despite all these improvements we still have non-stationary
components in the interferometer noise below 100 Hz; these are thought to be
related to excitation and upconversion of one of the
optics' suspension bounce mode.
Other activities this week:
- the new Statevector code was
installed.
- measurements of the acoustic, seismic, and magnetic
couplings from the ambient LVEA and VEA noise to the interferometer dark
port were performed.
- diagnostics on the readout of the weather stations
identified a synchronization problem in some legacy software.
- a piezo actuator on the PSL
periscope shorted out and let the smoke out of its driver board. It was
disconnected and mirrors were aligned manually. A replacement actuator
and driver board are being prepared.
- the
missing channel on one of the WFS1 quadrants was finally found to be due
to a bent connector pin on the whitening board interface, and fixed
Outreach (Zucker)
Hosted members
of the Delta Kappa Gamma society (women in education), the 6th grade at Runnels
School of Baton Rouge, and 80 high school physics seniors from Tara High in Baton Rouge. The latter group was a record size but went
spectacularly well, on account of good logistics and planning and excellent
help from the science and engineering staff, starring the enigmatic Dr. Brian o'Reilly and Professor Rai, who
gave out autographs (!).
SEC construction has picked up in intensity (to the detriment of S5 locking
during daytime hours). Pile drilling and concrete pouring finished this week
and grade beam excavation is in progress. Intensive concrete work is expected
next week. Steel is on order and should begin arriving in about 10 days.
LLO Facilities (MZ)
See Outreach for SEC status. Bids are in for the LDAS computer room HVAC
upgrade, selection is imminent. The gate repair is stuck waiting for special
tube stock, vendor is looking for a workaround.
CDS (Bogue)
- This
week finds me in the middle of a few different things. I spent many hours looking into problems
with the scimon plots that are automatically
generated out to the london
web site. I've determined that the scripts are
running properly and that Keith Riles and I should take a close look the
data being requested.
- Tuesday
maintenance went well. The dmt switch to jumbo frames has been delayed until
problems with passing traffic through the switch can be resolved. Similarly, upgrade of our dtt code has been delayed by the programmer. Thanks to Dave Barker, we now have the
latest and greatest state vector code.
Most of the rest was channel maintenance.
- I
now have email alerts running on the core cds
servers. Among other things, this
lets me see the errors from cron jobs that have
problems. I am fixing those as I
go.
Computing and Network Security (Roddy)
Spoke with Brian Nichols, LSU's IT Security &
Policy Officer, about the Nessus scan last week. They had a group of network security auditors
in from REN-ISAC. He agrees that in the
future we should coordinate scans. He
said that the scan did not turn up anything that needed attention.
Working with Foundry Networks on a support issue on a
switch. I am trying to get two
fiber taps on a couple of gig ports to be monitored on a mirror port. However, the switch is giving errors on 100%
of the packets. I may work on another
long term solution, but it would be nice to have this working as a passive
solution.
Have an issue with the Arkeia software. The upgraded hosts are showing up twice. Haven't had a chance
to get on the phone with them yet to figure out how to solve the issue.
Working some with Solaris 10, ZFS, & SMF under Vmware. Need
to script a few things security related.
Usual round of ordering hardware, user & email account
mods, etc.
General computing (Giardina)
- installed
new release of Arkeia on mail and alix
- changed
operatoradmin permissions on the security server
- finished Janeen's laptop
migration.
- creating HTML/PHP interface to security server activity
logs.
will
include search feature eventually.
these
logs are copied over from the entrapass server to
abundance.
LDAS admin (Giardina)
- node134
reporting badblocks on hdb,
will replace soon
- two power strip failures in the last couple of
weeks. replacements
arrived with the wrong plugs.
Bernie and I will replace when new ones arrive.
- shipped tapes LL0600,
LL0605, LL0649, LL0657, LL0658 to CIT.
Initial LIGO Detector Science & Engineering (Coyne)
CDS
see also the CDS weekly meeting minutes in the commissioning archives
CDS Software
No report
CDS Hardware
Ben Abbott
Fast Shutter
The solenoids have arrived from Electromechanisms.com. They seem
promising for use in a newer style of fast shutter.
DMT
No report
PSL
Nothing significant
Optical Characterization
No report.
40 Meter Interferometer (Weinstein)
IFO commissioning, PSL
- The
"new" (50K hours!) MOPA was putting out ~5.9 W when it was first
turned on at the 40m lab, and the beam scan showed a long non-gaussian tail to the west. After some power cycling,
the power went down to 5.4 W, and the tail disappeared. The theory is that
it was on the wrong mode, and now it's hopped to the right mode.
- The
water cooling on MOPA was found to be leaking a bit, so Steve replaced the
plastic elbow joints (in which he found cracks) with brass. It's still
sweating; Steve and Dan are keeping an eye on it.
- The
MOPA power is still at ~ 5.4 watts. At present, it's being attenuated to
~1/2 watt right after the beam exits the MOPA, while Steve and Rana re-establish the rest of the PSL.
- Rana discovered that a jumper in the MOPA, required
for SLOW temperature control of the NPRO, was missing. He put one in, and
now the SLOW control works.
- Rana fiddled with the optics in the MOPA box to get a
pickoff beam onto the AMPMON photodiode.
- There
are some problems with the EPICS readout of the MOPA monitoring signals. Rana traced it to the signals being pulled down by the
DAQ interface board. He's working on it.
- Rana and Steve moved the FSS pickoff to BEFORE the PMC
(it used to be after it). The pickoff is just leakage from a HR mirror.
Steve will replace it with a 1-2% pickoff mirror.
- Rana designed and coarsely tuned the mode matching
into the PMC and re-established lock. He went on to put in a new lens to
get the FSS pickoff beam through the EOM, and then re-established lock of
the frequency reference cavity.
- The
plan now is to re-establish mode cleaner lock, then go back and swap in
the new TT FFS. Then tune up the PMC transmission and the FSS path. Steve is
installing a camera at the PMC reflected port to help in tuning.
- Steve
and Rana plan to install a bigger pickoff for
the ISS photodiodes, and Rana will get a good
ISS diagnostic going.
- Rana plans to make changes to the PMC servo board like
the ones he made at LLO. We're also expecting new MC servo and CM servo
boards, which we will install in due course. We also need to implement the
PSL FSS slowpid servo.
IFO modeling
- Rob
continues to work on modeling with OpTickle,
Bench, Finesse, Corbitt's code. He's preparing a
talk to give at the quantum optics workshop in Germany next week.
- Osamu
has been working with Hiro on e2e simulations of
the 40m with radiation pressure. He has new predicted noise curves that
agree qualitiatively with theory (theory has
quantum correlations, e2e does not).
- Osamu
is investigating modification required to the detector calibration
procedure when homodyne detection is used. These mods
are also required with RF heterodyne detection with unbalanced sidebands,
as predicted by Kentaro.
- Osamu
is refining the calculation of the predicted seismic noise at the 40m.
DC detection development
- Sam
Waldman will be testing PZT drivers and servos for the in-vac steering mirrors that steer from the AP to the
OMC. He will develop a high-BW (~100 Hz) loop to supress
intensity noise at the DC readout port. Once Sam has a design, he'll work
with Jay to draw it up and build it.
- Mike
will show Steve, Sam and Dan how to mount the PiezoJena
PZT tilting platform to the DLC mounts without torquing
them.
- Mike
updated his drawing of the in-vac DC readout beamline. He designed a new baseplate
to mount the output sub-assy, consisting of the
following components: 2 DLC steering mirrors, OMC, GWD beamsplitter,
focus lens, GWD, OMC reflected beam steering mirror. He is changing the
drawings of the components to shorten their heights accordingly to accomodate the new baseplate.
Lee Cardenas is assembling two DLC PZT mounts for a test of the OMMT
steering mirrors.
- Steve
and Mike will assemble the output mode matching telescope in the lab, and
begin assembly of the rest of the beamline.
Electronics, controls
- Ben
has finished running all of the 10 custom cables for the TTFSS
installation. I have drawn up a schematic for the system, and assigned
cable names to the cables. I will install the new system today, 12/8
following the installation plan E040423-00.
- Our
old RAID array finally seems to have given up. Alex Ivanov
installed a new 1.5 TB raid array, and after great struggle, is getting
the 4 years of minute-trend frames off of the old RAID array and on to the
new. Thanks, Alex!
- Alex
fixed the epics screens' date and time display, by re-starting the NTP
daemon on the appropriate cpu
(c1dcuepics) and correcting the time.
- Rob
worked on some scripts for autolocking the FSS
and PMC servos, with the help of some triangle-wave scanning scripts.
- Rob
continues to work on rewriting the LSC code; don't expect it before he
returns from his trip, next year.
Lab Infrastructure
- Dan
got his appendix taken out.
- Kelvin is our new
janitor.
Thermal Noise Interferometer (Black)
No report.
LASTI (Ottaway)
The majority of the last months
activity have been installing infrastructure and preparing upgrades for the
triple pendulum experiment and the ponderomotive
squeezing experiments.
Quad Controls Prototype Infrastructure
This week we began assembling the test stand
for supporting the quad and the solid spacer. The new clean room has arrived
and after assembling the initial frame it was realized that the clean room was
not structurally strong enough so we negotiated with the manufacturer to get
additional stiffeners. Once these two items have been fully installed we will
begin the installation and assembly of the solid spacer that
substitutes for the AdvLIGO Seismic isolation
system in the initial quad suspension tests.
We have been consolidating electronics rack
space to make way for the electronics for the quad and later the BSC Seismic.
Triple Pendulum Experiment
The second pendulum is ready to be installed
in LASTI. It was tested with the initial triples electronics. We are now
shaking down the electronics for the second triple.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
Advanced LIGO simulation
(Hiro) The sensitivity curve of 40m was calculated
using e2e.
www.ligo.caltech.edu/~hiro/talks/40m_e2evsABYC.pdf
This is based on classical mechanics and optics and independent quantization
of the radiation pressure noise and shot noise. There are still issues to be
understood, including the control system and observation.
In a similar strategy, Adv.LIGO configuration was
tested, but the arm lock becomes unstable due to (probably) large radiation
pressure and high finesse. This will be studied more systematically.
FFT study
(Biplab) Had a meeting with Bill Kells, Kip Thorne and his student Pavlin
Savov regarding the simulation of parametric
amplification. As a first step Pavlin will develop his code for calculation of eigenmodes of cavity and results of that will be compared
with FFT results already obtained for various single-mode studies. After that,
more complex studies using mirror accoustic modes
will be attempted.
Doing more studies on Adv LIGO cavity modes for comparison with some results
obtained (by Pablo Barriga, Univ. W. Australia) for
frequency shifts of these modes.
Modeler
(Melody) Building other versions of the gcc compiler (4.0.2, 4.1.0, 3.3.6) in saiph
to see if the application performance is improved.
Alfi
(Bruce)
- Completed
work on new data object to track changes in bundler I/O names in inherited
bundlers. Now testing that the new
system does not break the current use of bundlers (PR 511.)
- More
work on multiple warning handling (PR 476).
(Melody) Working on Problem Report(PR) 296 - easier
access to settings.
Data Analysis Activities (Lazzarini)
Mendell:
In the last weekly I reported that a few minor issues to do with SFT
cleaning remain to be sorted out. These turned out to be caused by a one line
bug in the StackSlide code that has since been fixed
(and does not affect any other work by the pulsar group.) The SFT cleaning code is the newest and last
section of the StackSlide pipeline undergoing review.
Tomorrow I will present updated tests of this section to the reviewers, to
finish the code review, and to set the stage to move on to reviewing S4
results.
I also reported that I was working on problems with S5 SFT generation. These problems were due to memory usage and
spectral contamination at high frequencies by low frequency noise. The memory
usage problem was solved by compiling with different options, reducing the
amount of memory used. The spectral contamination problem was due to a lack of high
pass filtering, needed when you have very non-white data with a large dynamic
range that has very large amplitude noise at low frequencies. Now that S5 SFT
generation is more reliable (though not completely automated yet), I am
starting to study whether the 1 Hz lines exists in the S5 data, using the StackSlide code on the SFTs.
Shawhan:
- Prepared
GWDAW talk about S4 LIGO-only untriggered burst
search.
- Critiqued
a few other people's GWDAW presentation drafts.
- Debugged
and fixed problem with SeqInsert at LLO.
Lazzarini:
Worked with Brian O'Reilly (chair of the cailbration
committee) to perform a review of the V4 S4 calibrations. Need to continue on
this early next week. Report looks good; hopefully the calibration can be
vetted next week. This will enable groups to perform a final pass through the
S4 analyses with finalized calibrations. In summary: H1 and L1 will be revised
upward (i.e., less sensitive) by ~ 10% each w.r.t. V3
S4 calibrations; H2 will remain the same.
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS
The nightly test runs have been measured to loose about 250KB per job in
file system space. Running FSCK by a system administrator has been shown to
clean up some fraction of this. We need to make a few more measurements to
determine what the fraction is.
With the inclusion of large file support, we have seen a slight increase in
the amount of memory used by running processes. This is thought to be
associated with larger static and initialized objects associated with 64 bit
file I/O. Once full 64 bit support is implemented, the increase will be trivial
relative to the available memory space of the processes.
Started working on 64-bit compilation. I learned how to build 64-bit
applications using automake/autoconf/libtool. As a
proof of concept, I was successful with compiling lib/general 64-bit on Solaris
10. Before I can go further, I need to
compile many 3rd party libraries 64-bit as all of the other libraries have
dependencies on 3rd party software. Among these are Tcl/Tk,
FFTW, libCURL, BLT, lam, ObjectSpace,
and clapack.
TCLGLOBUS
- Updated
TclGlobus documentation with XIO-based Tcl channel section.
- Still
working on server functionalities of Globus FTP
control test units.
- Fixed
minor issue related to Tcl channel
implementation of server-to-server communication using host certificates.
- Investigated
on how to use service certificates instead of host certificates within
XIO-based Tcl channel.
GRID COMPUTING
- Worked
with OSG Executive Board to rewrite several sections of the "OSG
Management Plan." The document is expected to be part of the
discussion at a mid December teleconference with the funding agency.
- Worked
with the OSG Council on developing a section of the "OSG Plan of
Work" document to address advanced workflow management and Virtual
Data Services which could enhance the ability of LIGO and other VOs to submit jobs seamlessly to the OSG Grid.
- Attended
Griphynligo meeting and determined that
documentation on new Inspiral Hipe 16,000 Dag node
production code is incomplete.
Requested completion from Duncan Brown via existing Inspiral web page.
- Determined
that Duncan Brown has tested third party copy. Plan on testing this with
latest VDS in OSG 0.3.1 in the future.
- Provided
Alex Sim, implementor
of SRM at LBL an account on osg-itb-se for port of SRM to FC4 [JKB: With Kent's
approval].
- Continued
validation tests related to MonALISA reporting
to determine the extent of valid reporting of jobs from osg-itb to GOC web server.
- Corrected
error in OSG Twiki document related to LIGO VO
nomenclature.
- Updated
Validation page in OSG Twiki related to
validation testing of osg-itb with OSG 0.3.1
- Reviewed
new document related to CEMon and related
infrastructure and lack of FC4 support.
- Attended
OSG-INT meeting related to OSG releases 0.3.2/0.3.3
- On-going
monitoring and systems administration:
(a)
Yum updated osg-itb and osg-itb-se.
(b)
Added Ganglia monitoring infrastructure to osg-itb.
Lazzarini -
Stuart, Kent,
and Albert met with Duncan to discuss hand off
of a number of collaboration-critical software infrastructure projects to
others to allow Duncan
to focus on S5 science.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Talked
with Ed Maros about how to have LDAS determine
where it's .md5 files should go.
- Have
not had a recurrence of the "data strewn across too many tapes"
problem since getting Ben to use '-w' when labeling tapes (and ejecting
tapes after labeling before restarting archiving).
- Did
the standard tape exporting, shipping, ingesting.
- Did
some cleanup work in Synchrotron.
- Have
(at the request of the development team) run samfsck
on dev's /export a few times to clean up the
leaking disk space problem.
- Worked
with STK to get a replacement drive for 0,0,10,10
which had a tape (CL0462) stuck in it.
The tape broke but can be repaired once we get a leader block
splicing kit (Marty was going to get us one). The drive has been replaced but the WWNs were not copied from the old drive, so I still
need to update the software before the new drive is functional.
- Dealt
with staging problems at both sites (samu 'n'
showed staging activity but was frozen in place, samu 't' showed no tape
activity) requiring the stagerd to be killed and
the SAM robot daemons restarted. My
guess is that these problems were related to "duplicate" VSNs (tapes that had been imported twice and then SAM
marked them 'd' for duplicate in the
catalog). In both cases I've
cleared the duplicate condition and haven't had a recurrence of the
problem...if we go another few days without the problem occurring then I think it's fixed.
- /archive/home
was not marked release -n at LLO (fixed recursively). Checked at LHO and CIT and it was fine
there.
- Pursuing
the question of why some files are not being archived for a very long time
and then only with human intervention.
(Erik Espinoza)
- Kickstarted 80 nodes from the old cluster.
- Wrote
management system for kickstarts.
- Assisted
in cleaning process @ Synchrotron
Data Center.
- Assisted
in moving racks @ Synchrotron
Data Center.
- E-mailed
Sean @ ASA Computer testing and configuration details for new cluster.
- Updated
wiki with Kickstart
instructions.
(Stuart Anderson)
- Traveled
to vendor [ASA] selected for next CIT cluster to discuss details of the
large order placed last week.
- Construction
of the computer room at Caltech (215 Synchrotron) is now complete, and we
are starting to turn back on the computer systems that where down during
the upgrade--including 80 dual-Xeon cluster nodes.
- Lots
of cleanup in 215 Synchrotron after construction was completed.
- Worked
with Bill Tyler to order the equipment racks for the next cluster.
- Placed
a work order to install 12 30A/3-phase electrical circuits for the new
cluster.
- Obtained
price quotes for 17kW power strips for each computer cluster rack to
handle the estimated 14kW per rack of the new cluster.
(Lazzarini)
- Working with
Stuart, Phil, Florence
to determine end-of-year actual expenditures from 1.5.1 including the
recent cluster purchase.
MIT
(Keith Bayer)
- Upgraded
ldas-gridmon to FC4 - this completes the FC4 linux upgrades for MIT.
- Installed
host certificates for ldas-sundev and
ldas-pcdev1.
- Submitting
sun contract support for 2006 ldas computers.
Livingston
(Dwayne Giardina)
- node134
reporting badblocks on hdb,
will replace soon
- Two
power strip failures in the last couple of weeks. Replacements arrived with the wrong
plugs. Bernie and I will replace
when new ones arrive.
- Shipped
tapes LL0600, LL0605, LL0649, LL0657, LL0658 to CIT.
Hanford
(Greg Mendell)
- Reports
on gaps in the S5 data from last week are posted here:
http://ldas.ligo-wa.caltech.edu/ldas_outgoing/GapChecker/gapReport01DEC2005LHOS5.txt
http://ldas.ligo-la.caltech.edu/ldas_outgoing/GapChecker/gapReport01DEC2005LLOS5.txt
- The
gaps in the raw (L0) data are due to times when the framebuilder
and its backup goes down at the same time. This
can happen during maintenance or when unexpected problems with the DAQ
system occur. Gaps in the raw data
produce corresponding gaps in the RDS data. Note that the gaps in the L1 and L4 data
are 64 seconds wider than the gaps in the L0 and L3 data because L1 and L4
RDS generation involves downsampling. Data right
next to a gap cannot be downsampled since this
requires extra data at the start and end of the time series to work
properly. The only gap in the RDS data that is not due to a gap in the raw
data is the first gap in the LHO L1 RDS data. This is an extra gap that
occurs because on Nov 8, H2:LSC-SPOB_MON was
changed to H2:LSC-SPOB_I during the times this jobs runs on. When I get a
chance I hope to further automate gap checking. In conclusion, there are
no unexplained gaps in the S5 data, and S5 data archiving and RDS
generation is running smoothly.
(Ben Johnson)
- Fixed
misconfiguration on about 8 nodes. Some still
have symbolic links to CIT's Condor
configuration.
- Helping
some users debug their cluster jobs; mainly in relation to the Condor
restart this past Tuesday.
- I
have nearly finished with apache setup on ldas-pcdev2. I am finishing it
up presently.
- Working
on tape catalog program to help us make effective use of the tape cabinets
at the sites, plus keep track of all our tapes in general.
General Computing (Wallace)
MIT
(Keith)
- Troubleshot
grad student linux desktop - (bad power supply
forced machine into sleep mode at random times)
- Hosting
CSR ultra 5 box on subnet for admin network troubleshooting and testing
Livingston
(Dwayne)
- Installed
new release of Arkeia on mail and alix
- Changed
operatoradmin permissions on the security server
- Finished
Janeen's laptop migration.
- Creating
HTML/PHP interface to security server activity logs. Will include search feature
eventually. These logs are copied
over from the entrapass server to abundance.
(Shannon)
- Spoke
with Brian Nichols, LSU's IT Security &
Policy Officer, about the Nessus scan last
week. They had a group of network
security auditors in from REN-ISAC.
He agrees that in the future we should coordinate scans. He said that the scan did not turn up
anything that needed attention.
- Working
with Foundry Networks on a support issue on a switch. I am trying to get two fiber taps on a
couple of gig ports to be monitored on a mirror port. However, the switch is giving errors on
100% of the packets. I may work on
another long term solution, but it would be nice to have this working as a
passive solution.
- Have
an issue with the Arkeia software. The upgraded hosts are showing up
twice. Haven't
had a chance to get on the phone with them yet to figure out how to
solve the issue.
- Working
some with Solaris 10, ZFS, & SMF under Vmware. Need to script a few things security
related.
- Usual
round of ordering hardware, user & email account mods,
etc.
Hanford:
(Christine)
- A
DNS change at Caltech caused some problems with emails being bounced and
LSC grid users not being able to enter files in CVS. As a quick fix the MIT DNS servers are
now being used instead of the Caltech servers.
- Changing
to the MIT DNS servers didn't fix all the problems. Sometimes web URLs return host unknown
and then a retry works. SSH from a
local computer to another local computer resulted in an inability to authenticate
the host, then moments later it worked.
All of this is pointing to an internal network problem. There are several possible causes that I
am working on to see if they will fix the problem.
[Lazzarini
note: it appears that Caltech has changed its policy and will now allow LIGO to
manage its own DNS server for the ligo-wa and ligo-la domains. This should allow us the freedom to
optimize the configuration and to correct the problem.]
- The
WAN backup circuit is finally in place and "working". We are seeing link lights from LHO
through to ESnet in Seattle.
A test will be scheduled shortly after the first of the year to
bring down the primary GigE WAN circuit and throughly test the 10 Mb backup circuit.
- I
have received some information on the output drops and overruns I'm seeing
on the GigE interfaces on the router. Cisco advises updating the IOS and
setting up QoS to manage the overruns. PNNL thinks that adding more memory
might be a better place to start. I
will be trying all of the above.
- Purchased
several new laptops for operators.
- Requested
that any user who is bringing their own personal laptop from home sign a
form so they know the rules to using a personal computer at work. This created quite a stir and I have
spent much time defining what it means to bring a personally owned
computer to use as a work computer.
This is not the same as working from home on your own computer and
it is not the same as LSC members bringing their institution supplied computers
to LHO and it is not the same as a visitor bringing a laptop to use during
a conference.
- Working
with Greg Mendell to define a standard Lab wide
setup for access to LSC Grid tools from GC computers.
Preparing for the PAC meeting next week.
CIT:
(Mike)
- Worked
on a Laptop that would not recognize the hardware key for Solid Works. I
ended up having to download the driver from Aladdin's website in order to
get this laptop to recognize the dongle. I also installed Primavera on
this laptop.
- DCC:
Loaded 2003 Server, SQL server 2000, ColdFusion
ver5 server edition, and finally Synergy software. Synergy is our new
database software for DCC. There is a lot of work involved here and a good
chance that I will have to reload this software again. I have also been on
the phone with Synergy's tech support. This is an on going project.
- Spam
Filters: Continued work on spam filters searching for false positives.
- DHCP
Server: Ran out of leases. I had to manually free up expired leases.
- Loading
a laptop with Fedora for a user to take on travel.
- Dead
Sun box over in Lauritsen. I am reloading a sun
box to replace this unit.
- Other
misc. user support.
(Veronica)
- LIGO: Roster database updates. Website updates. Prepared a high-resolution image for an
APS-sponsored publication. Updates
to the PAC meeting website. Miscellaneous
user support.
- LSC: Usual upkeep. Updated a number of bouncing email
addresses in lsc-all and lsc-nonligo.
- CaJAGWR:
Website update.
(Christian)
- Irene
Baldon; Replaced drum kit cartridge on Irene's
local printer.
- 3flr
W/B - Replaced toner cartridges on HP 5500 printer.
- Dorothy
Lloyd; Configured a loaner laptop with Eudora and a dialup account for
Dorothy to use.
- Wilson house;
Installed Norton AV on Mohana Mageswaran laptop.
- Re-imaged
two laptops that were returned to the loaner pull this week.
- Other
misc.: Continued onsite software/phone support.
(Larry)
- Worked
a number of procurement issues. A couple of Dell orders have shipped and
should arrive this week.
- Spent
a deal of time working on room 18&19 (server rooms). The fire suppression system was tested
and did pass but it also revealed a couple of other logistical issues
concerning power and the air-conditioning system that need to be
addressed. Assisted the PMA group
on setting up a new SUN server in room 19.
Did some testing on the remaining dual core quad cpu unit in relation to
performance issues. Some items are running as they should but the E2E
group is seeing a performance problem in their application. The group is
doing some more testing when they get time.
- Assisted
in getting things ready to send the Monarch system back for repairs.
- Worked
the mail filters. There was a new source of spam causing a lot of items to
be caught in the filters which had to be cleaned out by hand.
- Worked
on a couple of accounts which needed to be cleaned up.
- Performed
the monthly backups on the user home directories. Reset the daily backup server. Reset one
of the internal web servers that was having some
issues starting some web applications.
- Attending
the LISA conference.
Mail Statistics for Dec 01-07, 05
|
Mail Statistics
|
December 01 - 07, 2005
|
|
Rejected Messages
|
17,467
|
|
Virus Messages
|
2,146
|
|
Accepted Messages
|
15,143
|
|
Total Messages
|
32,610
|
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Systems, Management
Systems
from Dennis
Coyne
See also:
AL
Systems web page
AL Systems email
archives
- Held
an Optomechanical Layout Working Group, 12/8
focused on collaborative use of SolidWorks and PDMWorks
Records Of Decision or Agreement (RODA)
See also the RODA status web
page
- M050175-01, Initial Alignment
Requirements on COC Coating Reflectivity, is in the signature cycle
- M050397-00, Core Optic sizes,
including TMs, BS, FM and RM, is in the signature cycle
- M050418-01, Separation of
chains in quad suspensions, is in the signature cycle
Requirements
- Revised
the SUS Universal Design Requirements, T000053-04, to include a
duration for the low temperature, non-operational, in-vacuum bake
Interface Issues
See the
"Interfaces" section of the AL Systems web
page
- Nothing
significant to report
Vacuum Compatibility
Vacuum Preparation [Cleaning, Baking, Residual Gas Assay (RGA)]
See also the Vacuum Bake Lab
Bob Taylor
- I
have completed most of the metallic parts for the Quad Controls Prototype
and have began working on the magnetic and
optical assemblies.
- The
connectors for the Electro-Static Drive (ESD) have been delivered from AccuGlass. Mike Gerfen in
the CIT machine shop is making the PEEK clamping beads that go in the ends
of the connectors. He says that they will be ready next week, then I can put the connectors on the ESD cables.
High-Irradiance, Contamination-Exposure Cavities
Lee Cardenas, Liyuan Zhang
Changes
highlighted in yellow
|
Cavity
(Location)
|
Material/Item
|
Start
|
End
|
Comments
|
|
Cavity #1
(OTF Lab,
Bridge)
|
“Cable wire” (material type?)
|
~11/17
|
TBD
|
No
Change: The cavity has been aligned & locked. Taking daily ring down
and absorption measurements.
The
digital oscilloscope failed so a new one is being ordered, along with a
refurbished pulse generator.
----------------------------------------------------------
The test for 40 pieces of MMG nickel plated Nd-B-Fe magnets (for Helena Armandula,
SUS ) has been completed and removed from the
cavity.
|
|
Cavity #2
(OTF
Lab, Lauritsen)
|
NA
|
NA
|
NA
|
Cavity
not ready. It needs some other optics(such as:
polarizing cube, 1/4 wave plate and some curve mirrors and lens) and the
electronics. We have used/borrowed some of the optics from this system to
accomplish
the completion of the other two cavities. Recently the 700 mw NPRO laser was
used for Garilynn’s experiment and it needs
to be realigned to the cavity.
|
|
Cavity #3
(OTF
Lab, Lauritsen)
|
OSEM Flexi-circuit cable,
qty ~ 45
(Helena Armandula,
SUS)
supplied by Univ. Birmingham (Stuart Aston)
|
~9/30
|
TBD
|
No change:
taking daily absorption &
ring down measurements
DuPont Flexible Circuits. The whole part to be
constructed of 'flexi' i.e. no 'rigid' sections. (Stuart Aston,Univ. of Birmingham, SUS/UK subsystem)
- Start Laminate: Kapton (LF8515)
(document link: http://www.dupont.com/fcm/products/H-73244.pdf
Coverlay (x2): Kapton
(LF0110)
(document link: http://www.dupont.com/fcm/products/H-73245.pdf
DuPont Pyralux
Series - Kapton / Acrylic Adhesive system.
(document link: http://www.dupont.com/fcm/products/H-73246.pdf
--------------------------------------------------------------
OSEM
emitter & photodiode 40 of each, (Dennis Coyne, SUS
) Test has been completed. Results to be posted by Liyuan
Zhang soon.
|
|
Queue
Priority 1
|
2 Cleaned 50ppm transmission mirrors, 1 in dia., REO coated --
|
TBD
|
TBD
|
witness samples for the LHO vertex volume (added in
6/29/2005 vent)
|
|
Queue
Priority 2
|
Stepper
Motor (Riccardo DeSalvo,
possible SUS or ISC use)
|
TBD
|
TBD
|
Stepper Motor sample had been placed
into Cavity #1: Power dropped from 175 mW to ~25 mW after introducing the stepper motor sample, and
continues to decrease. It is very hard to keep cavity locked. The stepper
motor may have contaminated the mirrors. Will re-test when a cvity becomes available again.
To be rebaked soon using the self-heating capability of the
stepper motor (not just the oven heater controls)
|
Seismic Isolation
Shipments of clean rooms, support systems, and assembly
granite tables to LASTI.
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
Working with Nergis on her
fixtures. Was successful in accessing a number of old
Ideas designs and drawings. Ordering some parts for the quad.
From: Calum Torrie
<ctorrie@ligo.caltech.edu>
There are still one or two loads being baked. All of these should be
completed by Friday. Lee and I have assembled the upper structure. All of the
wire assemblies, except the top stage wires, have been completed.
Ric Paniagua and i have prepared a plate that will be bolted to the floor of
the clean room this will allow us to test the resonances of the lower structure
in clean conditions.
I have prepared a concept drawing for the advanced LIGO pick off mirror.
I have been preparing for a PDMWorks tutorial that
I am giving on Thursday.
Tim Hayler and I have continued to look at bolted
connection in the overall quad suspension structure. We are applying contacts
between sections of the structure and the associated bolts.
The installation tooling work with Mike Gerfen is
progressing well Questions are being answered as they arise. Ken Mailand, Mike Gerfen and I are
looking over Ken's design of an alternative for the air bearing and XY stage.
We are continuing to deal with some vendor questions ahead of placing an order
for the linear drives and had a successful meeting with the vendor this week.
From: Ken Mailand kmailand@ligo.caltech.edu
I’m working on shop drawings for the SUS installation plate style
fixture for Calum, we will met with Mike Gerfin
this morning re. a CES estimate. This is an alternate
to the air bearing setup, and uses the same table frame.
Core Optics
From: Bill Kells kells@ligo.caltech.edu
From: Helena Armandula ahelena@ligo.caltech.edu
Advanced LIGO Coatings
We had a teleconference with
Jean-Marie Mackowski on which the paper on doped tantala that Gregg is writing, on behalf of the coating
group, was thoroughly discussed. (Jean-Marie and some of his group are
co-authors)
Other coatings
The order for the manufacture
of 4 TNI mirrors has been placed with REO.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
I had a discussion with Hiro about calculating the
beam pointing requirements after the suspended modecleaner
to get an idea of whether or not it would be a problem for the intensity stabilisation. More data is required.
The beam pointing for the Innolight NPRO was
measured. Most of the variation is in the horizontal direction during a
2-hour warm-up period. The output beam
size variation is quite small (about 1%).
Both Rich and I are getting some details together for controlling the Innolight NPRO digitally.
Auxiliary Optics
From: Phil Willems <willems@ligo.caltech.edu>
Advanced LIGO Thermal Compensation
I have analyzed the fundamental mode shape of the Advanced LIGO arm cavity,
using Juri Agresti's basic
FFT code, which quickly and easily models single cavities, with thermoelastic deformations of the mirrors included (as
calculated by my FEMLAB model). At very low power the code predicts the
correct Gaussian mode. At high power, the modes remain Gaussian, but with
a spot size on the mirror of ~5.4cm. With a ring heater surrounding the
back half of the mirror, it was possible to restore the 6cm Gaussian spot size
with high precision, as determined both by direct comparison of the mode with a
Gaussian and by monitoring the power buildup of the cavity for fixed input
beam. This implies that direct compensation of test masses can maintain
the arm cavity mode shape, although changes to the higher order mode spectrum
still require study.
Stable Recycling Cavities
It is possible to design stable signal recycling cavities such that the
coupling of the gravitational wave sidebands out of the arm through the signal
cavity is independent of the thermal lensing in the
ITM, to first order. In these configurations, the sidebands exiting the
interferometer remain gaussian, and are extracted
efficiently, although the spot size changes with the thermal lens. These
configurations are likely to minimize the TCS requirements as far as GW
sideband extraction efficiency is concerned. Cavities having this
property are practical for km-scale recycling cavities and for the intra-cavity
telescope design by Guido Muller.
From: Michael Smith <smith@ligo.caltech.edu>
VERTEX LAYOUT
I have added the IO beam line, steering mirrors for the PO
telescopes, OMMT, and an output modecleaner. Calum has a
conceptual drawing of the PO mirror
suspension, which I will incorporate.
Other Laboratory R&D
No report this week.
For additional information about this report, contact S. Whitcomb or P. Lindquist