Weekly Report for
Week Ending December 1, 2005
The LIGO Executive
Committee Agenda for Monday, December
5, 2005 will be:
(Meeting time: 10:30 am Pacific Time)
1. Announcements
2. Comments
on Weekly Report
3. LSC
Issues (Saulson)
4. LIGO
Lab Operations
- Administration
(Lindquist)
- Sites
(Raab, Zucker, Shoemaker)
- Commissioning
(Fritschel), Detector (Coyne)
- Campus
Research Facilities
- 40
Meter (Weinstein)
- TN,
( Libbrecht)
- LASTI (Shoemaker)
- Data
Analysis and Computing (Lazzarini)
5. R&D
and Advanced LIGO (Shoemaker)
6. CHANGE CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION AS
NEEDED
Special Items:
Special Announcements:
Weekly
Report Highlights
No report
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
- Saulson signed off on the new MOU from the Waves Group
University of Sannio at Benevento
and University of Salerno (TWG), submitted by Innocenzo
M. Pinto. He also signed off on the new MOU from outside the LSC from the
Experiment "Ricerca di
Onde Gravitazionali"
(ROG) of the Istituto Nazionale
di Fisica Nucleare (INFN), submitted by Eugenio
Coccia. Both are being prepared for submission
to Barry Barish and Albert Lazzarini
for their approval and signatures
- GEO 600 revisions were completed and posted, and
submitted to Saulson for review..
SITE TELECONFERENCE (Lindquist)
- A
site teleconference was held Thursday, December 1, 2005. The following issues were among those discussed:
- Action
132 – to prepare and distribute a note concerning commingling
taxable and non-taxable items on a purchase order, E.
Jasnow has completed this action
and it will be closed. There are no
other open action items. The list
of assigned actions updated through December 01, 2005 will be found Here.
- Excel
Invoices – waiting for the return of R. Brambilla
next Monday to process.
- November
Costs – numbers not yet final, but it looks as though the
projected carry-forward is holding. Carry-forward is due primarily to
deferred expenses including data analysis equipment, the installation of a
new data management system, seismic isolation hardware, and advanced
R&D activities.
- Science Education Center
– rain delays were encountered earlier in the week. However, materials are being delivered
and “stuff” is happening.
The first contract meeting is scheduled for Tuesday.
- LDAS
HVAC – the LDAS HVAC job walk at Livingston
was conducted this morning. There
were no questions from the interested bidders.
- Property
– E. Chargois will conduct a property
visit to Hanford
December 5 – 7. He will be
accompanied by R. Luna who will be the new LIGO Property Administrator.
- Repair
of Livingston Gate – a new gate
has been ordered. The actuator has
been repaired and tested.
PROPERTY MANAGEMENT (Chargois)
>From: Ed Chargois <chargois_e@ligo.caltech.edu>
- Provided
assistance to the Detector Group (H. Armandula)
by providing packing and shipping of eight (8) E040514-L2 Optic Lenses,
seven (7) E040516 Mirrors, and three (3) E040512-B1 [and a partridge in a
pear tree –pel] to (D. Cook) at LHO. Account Number P204324.
- Provided
assistance to the Detector Group(H. Armandula) by providing packing and shipping of four
(4) E040514-L2 Optic Lenses to (V.Frolov) at
LLO. Account Number P204324.
- Provided
assistance to the Low Frequency Noise Suppression Group (J. Agresti) by preparing US Customs Documentation (Commercial
Invoice), providing packing and shipping of professional documents and
Hardware. Account Number P204289.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- Processed
documents from LSC Meeting @ MIT.
- Sorting
through an old box of files from F. Asiri and
verifying if documents are in DCC Database.
- Scanning
Project - Completed scanning L. Jones boxes of files. CD's still need to be burned for these
files. Scanning has commenced on F.
Asiri boxes of files. There are approximately a total of 11 -
13 boxes to scan. To date about 3
boxes have been scanned. Progress
continues on scanning of old blanket purchase order files.
- Activity:
|
Week Ending
12/01/2005
|
In
|
Out
|
|
Packages
|
12
|
8
|
|
Faxes
|
13
|
7
|
FINANCIAL SYSTEMS (Cronin, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- No
report (family sick leave).
>From: Florence Kaufman <fkaufman@ligo.caltech.edu>
- Worked
on updating reports for November 2005.
- Sent
out e-mail outlining actions to be taken to reflect Excel PO 1055977
correctly.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow
<jasnow@ligo.caltech.edu>
- Change
Order No. 2 was issued on the contract with Eskew-Dumez-Ripple,
the architect for the LLO SEC. This
change inserts a revised Schedule D which provides for increased
construction visits.
- A
job walk for the LLO LDAS HVAC system was held on Thursday, December
1. Representatives of all three
firms that received the RFQ were present.
Bids are due on Friday, December 9.
- The
Caltech Office of Corporate Relations submitted a proposal on behalf of
LHO to the M.J. Murdoch Charitable Trust for funds to sponsor the
internship of a high school teacher during the summer.
- Fermilab is now processing a proposal from LHO for the
performance of outreach activities related to teaching LIGO physics.
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
- Processed
the paper work for fourteen (14) new/revised trips. At this time
there are seventeen (17) trips completed or in the works but are awaiting
the necessary paper work to enter the P-Card system.
- Completed
five (5) Expense Reports and there are twenty-two (22) reports yet to be
done. I continue to contact travelers who have outstanding Expense
Reports (more than one (1) month old) to ask for their cooperation in
sending me their receipts so that these can be closed in a timely
manner. Presently there is one (1) report more than thirty (30) days
old. I have no reports awaiting signature at this time.
>
>Dorothy Lloyd
- Processed
the usual invoices for payment and followed up on invoice problems.
Processed payment requests and requisitions as requested.
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- A
Staffing Committee meeting was held on November 28, 2005. The minutes and action items from the
Staffing Committee meeting are in progress and when completed will be
posted on the SC web page. All
files for the Staffing Committee are up-to-date and posted on the SC web
page.
- I
am in the process of preparing numerous appointments for several Visitors.
- The
next Staffing Committee meeting is scheduled for January 23, 2006.
- Human Resources is replacing
our traditional paper time sheets with an on-line system called Kronos.
AFTER training, each individual will need to access their
electronic time card and enter exception time, i.e., Sick Time, Vacation,
Jury/Witness Duty, or Bereavement Time; they will receive an email
reminder the Thursday prior to the end of the pay period. The last step
will be for me, as the Payroll Activity Monitor (PAM), to enter the final
approval on the Monday following the pay period. Once approved, any/all
changes will need to be made retroactively, and I will need to make those changes. I will begin entering all time keeping
information beginning with pay period 25, November 28. Employees will
continue completing paper time sheets and submitting them to me and I will
do the data entry. PMA plans to go
live for the employees on January 9, 2006 (after all employees have been
trained). In the meantime, I have
not been trained and I must review the handbook and go through the on-line
tutorial before my training on December 8.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
- Nothing significant to report.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of
Commissioning Activities at LIGO Hanford
Observatory (compiled by M. Landry)
We ran a more modest and achievable maintenance shift this Tuesday. This was
seemingly more successful than last week (in which the total downtime was
nearly 16h), as we recovered nearly within the 4h window allotted for the work.
Some recent duty factors and lock times are shown here.
H2's duty cycle is 3/4 and recent H1 performance has matched this. We're able
to post 12Mpc on H1 during evenings and 10Mpc during the day, while H2 is
steady at 4.3Mpc (this will be boosted 10% when the V1 calibration is added to
online Sensemon).
Sundry highlights from the elog are bulleted
below:
- channel
hopping problems appear to be rectified after an AWG
code change
- automated
linefinding is providing quick feedback on the
state of the instrument of particular interest to pulsar and stochastic
groups
- excess
burst pixel fraction for N>2 (effectively the hrss@50% channel) can be
used as a figure of merit to decide when to touch the machine; how to
weigh this against other searches' figures of merit is an outstanding
question
4K IFO
- we've been running in the day with 2dB lower input
laser power, to tolerate higher noise and upconversion
at this time. Reduced power is the source of the 2Mpc drop noted above
- we
saw some drop in inspiral range (~10%) when the
V1 calibration was added to Sensemon, but
offline Sensemon tests showed only half
of this drop could be accounted for by the calibration
- despite
the fact that the fine actuator distribution box was fixed
last week, some lock losses
are still due to FA range issues
- 1Hz
lines have seen with DTT but not
with Stackslide algorithm. This discrepancy
is being actively investigated
2K IFO
- the H2 S5 V1 calibration was completed and checked into
CVS. This required new run/acq hardware
filter measurements
during Tuesday maintenance
DAQ
- maintenance
work from Tuesday is summarized here
Outreach (D. Ingram)
New visitor exhibits
are proving popular with students. One more event
remains in LHO's World Year of Physics series.
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
L1 Interferometer (Frolov)
After two weeks of science data taking the cumulative duty factor has
climbed to 45 percent. During the weekdays it was mostly limited by seismic
noise from logging and construction.
During the Thanksgiving holiday, instability of the ITMX HEPI system
required a day long investigation which continued later in the week and is
still ongoing. The inspiral range was between 8.5 and
9.5 Mpc most of the interferometer uptime. The power into the interferometer remains at
a reduced level of 5.6 W (7 W available) due to the non-stationary noise which
is suspected to be due to the electronics saturations.
Commissioning activities this week:
- excitation channel swapping was identified to be the
source of transients in DARM that were causing the lock losses. New AWG
code was loaded that should help diagnose this problem.
- the MICH
control signal was found to be driving a broad noise peak in DARM loop
around the second violin mode of the suspension wire. Filtering the
control signal mostly eliminated the noise bump.
- the broad line in the DARM noise around 235 Hz was
identified to be due to the ISCT4 purge air flow. The flow rate was
lowered to minimum which dramatically reduced the 235 Hz peak, to the
point were it can't be seen in the running spectrum with several second
average.
- the anti-symmetric photo detectors were modified to
improve the efficiency of RF coupling from the AS_I suppression servo.
This should reduce the upconversions and
saturations in the AS_I servo electronics.
- the loaner atomic clock was received and installed. The
testing of the timing monitoring is in progress.
Outreach (Thacker/Zucker)
Conducted 2 labs at Doyle HS (local) physics class, as we
begin to develop ties with this school.
Prepared for Tara HS visit (approx 70 physics
students) on Friday, Dec 2nd.
SEC construction: Rain has delayed the planned drilling for piers and
footings until this coming Monday, affording a few openings for daytime
operation this week.
LLO Facilities (Sibley)
The damaged front gate has been shipped the Southern Fab
for repair. It will be at least 4 weeks to repair it. The operator has been
repaired and tested good.
The pre bid walk thru for the LDAS HVAC upgrade was held today. All three of
the vendors that got the package were present. No notable questions were asked.
Bids are due 12/09.
CDS (Zucker for Bogue)
- Fixed
state vector code (a particularly subtle file permission bug)
- Fixed
atomic clock and timing comparators
- Added
channels to DAQ to handle front end overflows (for
- post-facto
monitoring of data dropout and skew problems)
- Installed
and tested new DTT and AWG code
- Fixed
GRB alarm script so it stays alive
- Miscellaneous
forays to smite entropy and foster peace and order
Computing and Network Security (Roddy)
Just received the PC to replace the one in the auditorium. Several items have not arrived. I need to check and see if it is a lost
shipment, or if Dell has shipped partial. Working with a
fiber tap for network monitoring.
It has not been flawless so far.
The syskonnect card refuses to capture traffic
that is on the fiber. This may be a
driver issue. I have contacted the tap
manufacturer. Next step will be to
contact syskonnect. Usual round of pouring through
the IDS logs brought to light a nessus scan yesterday
originating from the LSU campus. I
blocked the source of the scan at the border, to find out later that it was
presumably a legitimate scan. I have sent an email to the person responsible for such things at
LSU and suggested that we meet sometime to discuss coordination of such
activities. We'll see what comes
of it. Ironically, I had been working on
a new updated nessus install here. I was planning on beginning scans in a couple
of weeks.
The last nessus scan was done here ~6 months ago. Unfortunately for LSU, their scans likely
will not yield anything since most of the traffic is blocked by default. Have been working with Dwayne on upgrading and updating the Arkeia software.
We have successfully installed a new library, ran a couple of backups,
full & incremental, and Dwayne upgraded the client versions of the software
that was previously installed. Next is
to work on schedules and email notifications. Discussing our
new mail server with the CanIt folks lead to a plan
to integrate a relay server into our mail system. I have a server on order to handle this. I will work with Dwayne on installing it when
it comes in. Perhaps we can get a handle
on our spam problem here soon... Working on travel
reservations for the security conference in VA on the 12-13th.
General computing (Giardina)
- restored
Tom Evans files from tape
- installed
new release of Arkeia on baronne
and abundance
- with
Shannon, ran two new fibers to Computer
Users' room, configured new Foundry switch
- cloning Janeen's laptop has
yielded a slight problem, as DELLUTILITIES partition would not copy
over. Now machine won't boot. working on this
now.
- assisted
Bonnie with more HTML
LDAS admin (Giardina)
- replaced
disk in node5
- ssh key authentication for kipp
and bmoe to ldas
- onasys database setup
- shipped
tapes LL0596, LL0601, LL0679, LL0364, LL0642, LL0644, LL0508, LL0534,
LL0612, LL0643, LL0683, LL0691, LL0693, LL0695, LL0697 to CIT
CDS code support (Khan)
Working on a software generated phase lock loop timing signal, that would
take 1 PPS GPS input and provide 2^16 and 2^12 divider clock pulse. It would
generate precise timing signals for an A/D converter sample and hold circuit,
so that a single chip microcntroller (running on 40
MHz Clock) could perform A/D conversion of the PEM channels close to the sensor
location. Using USB 1-Wire interface with 1 Mb data transfer rate it is
expected to reduce noise and cable interface problem for the data acquistion of the LIGO PEM channels.
Site Safety and Security (Riesen)
Nothing of substance to report this period.
AdL SUS/SE Mechanical Engineering (Spjeld)
Quad SUS Installation Fixtures
- completed
release DCN and drawing package for manufacturing, submitted to DCC
- meeting
with Calum and Ken Mailand
on Nov. 16 to discuss design and manufacturing
- looking
into off-the-shelf parts for the linear bearings, shaft and shaft blocks
for lift table
LDAS/Condor data analysis (Yakushin):
Storage/Condor/LDAS admin:
1) On Nov 23 dataserver@LLO had a kernel panic. 9
minutes later the same happened at LHO. According to SUN this is the result of
a bug in SAMFS and they are working to find a solution. The time coincidence
between two sites is presumably due to the identical archiving program started
simultaneously at both sites. We had no more crashes so far.
2) Power srip for nodes 4-11 got burnt. This is
the third power strip failure during a month. The first two ones were fixed by
resetting a breaker.
3) On Nov 29 gateway:/export ran out of disk space causing all LDAS jobs to
stop. Current createRDS and publishing jobs generate
a lot of intermediate files. After some cleaning the
situation is back to normal.
Data analysis
1) Integrating event display and CorrPower into
the waveburst online pipeline;
2) Participating in the GWDAW10 talks review telecons.
Initial LIGO Detector Science & Engineering (Coyne)
CDS
see also the CDS weekly meeting
minutes in the commissioning
archives
CDS Software
Rolf Bork
Still testing new LSC code that we tried to load on LHO4k
a couple of weeks ago. I can't
find a problem with the new code, but found possible initialization problems in
EPICS code that has been there quite a while. This initialization problem may or may not
have been the cause of strange QPDX readings. As for DAQ problems attributed to
the new LSC code, I think the problem was most likely introduced by the many Framebuilder restarts and loss of sync by the DAQ
controller at the time. The LSC code was
just backed out when this was noticed as it was the latest change. Anyway, I think we should try again next
Tuesday.
CDS Hardware
Fast Shutter:
I have ordered a sample of solenoids from Electromechanisms.com to assess
their usefulness in a newer style of fast shutter.
DMT
No report
PSL
Nothing significant
Optical Scattering Analysis
Bill Kells
I have launched into a renewed effort to resolve the mystery of LIGO I TM
surface scatter. (Of course we are still
mainly pursuing the absorption question on 4ITM01.) There is quite a lot of OTF scatter scan data
by now. This has perhaps not all being sifted through for maximum information. I have come to realize this in reviewing it. There is some possibility that a comprehensive
interpretation of all the data is consistent with what is observed at the
sites. Between Liyuan
and I this is now underway.
40-Meter Interferometer (Weinstein)
IFO commissioning
- The
replacement laser from LHO (originally on H2; MOPA SN#102 with 42,943 hrs)
arrived last week. Steve and Osamu unpacked it Monday morning, and saw no
obvious damage. They carefully noted everything that was different between
our old faithful laser ("Assisi",
after St. Francis of Assisi)
and this one. They placed it on the PSL table with 6 spherical washers underneath.
- Steve
hooked up the water cooling to the master oscillator with needle valve
fully open. There was a leak, and Steve got new parts and fixed it. New
elbows were added to water in and out of mopa
box.
- The
NPRO power was measured to be 0.8W with the Newport power meter. However, 60-80% of
the beam was rejected from the last thin-film polarizer and so most of the
light didn't make it to the amplifier, even on the first pass. Rana minimized the reflection at this polarizer by
rotating the half wave plate by ~60 degrees, thereby maximizing input into
the amplifier. They measured 5.4W with the calorimeter at the exit of the
MOPA. Effort to get current reading on our old power supply failed. Laser
was turned off and on during this process and it resulted in power to drop
to 5W.
- They
then scanned the beam profile, and saw a nasty tail. After Rana tweaked the PBS, the tail is gone and the beam looks
nicely gaussian and round.
- Steve
and Osamu measured the beam waist size and position coming out of the MOPA
in preparation for mode matching into the phase-correcting pockels cell (which is now mounted outside of the MOPA
box, as at the sites).
DC detection development
- The
DCPD PCB boards have arrived and been stuffed. Ben will begin testing
shortly.
- Ben
ordered several types of resistors for the DCPD and gave a sample to Bob
so that he can evaluate their vacuum compatibility.
- Mike
reports that CES is having technical difficulties with the NC mill, and
the OMC body completion has been delayed for a week or two.
Electronics, controls
- From Ben: I have finished making all of the 10
custom cables for the TTFSS installation. I'm going to draw up a schematic
for the system, and assign cable names for labelling
the cables prior to installation. I will then install the new system
following the installation plan E040423-00.
Thermal Noise Interferometer (Black)
Since our last report, we have improved the
visibility to just over 90 percent in both arm cavities, due to improved mode
matching. We also found that the polarization was not optimum going into the
beamsplitter, and we were able to increase the total power going into the arm
cavities by about a factor of two.
Over the Thanksgiving break, we closed the
vacuum chamber and pumped out. This week, we recovered the alignment that was
lost when the chamber was closed and took some preliminary data. With the increase
in both power and visibility, the electronic gain had to be reduced to keep the
servos stable. Akira did this, as well as fine tuning the notch filters, and he
took noise spectra late last (Wednesday) night.
The individual arm cavities are now
exhibiting the best noise curves we have seen, bottoming out at about 3e-19 m/rtHz, but the difference data has an unexpected, flat noise
source that limits its sensitivity to about 1e-18 m/rtHz.
We suspect this is something in the measurement electronics, since it does not
show up in the individual arm cavities, and we are working on identifying and
removing this noise source.
LASTI (Ottaway)
No report.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
Weekly e2e Physics meeting
Sany Yoshida presented his results on (i) study of the beam pointing of transmitted light from
mode-cleaner and (ii) simulation of Advanced LIGO HAM seismic isolation.
Advanced LIGO simulation
(Hiro) In order to assist Mike Smith to calculate
the scattering noise, I am calculating the transfer function of injected fields
at various ports to the signal output port. This is done using the same setup I
used to calculate the optical spring effect for the 40m configuration. I.e., a
very simple lock of each arm using POX and POY, with radiation pressure and
radiation pressure noise enabled in the simulation.
Simulation of Mode Cleaner
(Sany) Uzma and I
continued the e2e modeling of pointing fluctuation of the LIGO I input mode
cleaner. With OSEM gain setting of 5 (in the unit of SimLIGO's
FilterPos(Pitch/Yaw).OSEM.gain
setting), the computed MC transmitted beam's pitch and yaw spectra show
reasonable agreement with the spectra of the corresponding DAQ MC_trans_P/Y signal. Here the e2e computation takes the
ground DAQ signal recorded at the same time as the DAQ MC_trans_P/Y
signals. In 0 - 10 Hz, the e2e pitch spectrum produces all the main peaks
observed in the DAQ pitch spectrum (optic's resonances plus HAM stack
resonances). While the e2e yaw spectrum
in the same frequency range also shows all the peaks of the optic's and HAM
stack's resonances, the DAQ yaw spectrum does not show the HAM stack resonance
peaks except for the ones at 1.5 Hz and 1.6 Hz (U-U and V-V transfer resonance,
respectively); In fact, the DAQ yaw spectrum is closer to the e2e HAM table yaw
spectrum, for some reason. Further investigation is being undertaken.
Simulation of 40m Interferometer
(Monica) The control plant for the e2e 40m package has been tested using
different optical configuration: a Michelson, a Fabry-Perot
Michelson, a Power Recycled Fabry-Perot Michelson and
a Dual recycled Fabry-Perot Michelson (40m). The
control seems to work well but other tests will be performed to verify its
robustness with stronger noises.
Research Paper
(Biplab) Wrote my part for a
paper with Ju Li et al (Univ
of W. Australia) on parametric amplification. Working on the draft of
another paper on diffraction losses with Pablo Barriga,
Ju Li and David Blair.
Modeler
(Hiro) Working on e2e-3.1.0
release. The major addition is to
support modeler_freq (frequency analyzer in e2e),
which does not work in 3.0.
Computers
(Hiro) I tested the performance of the new dual
core quad CPU machines newly available. Unfortunately, the performance is half
of homam (single core quad CPU machine) with the
current system, FC4, and Larry is working on it.
(Melody) Did some performance benchmarks for saiph
and homam (4 cpu
dual core systems). Researched on possible compile flags to
speed up the application.
Alfi
(Bruce)Fixed copy/paste of primitives bug related to the checking for full
paths being used in include statements (which should not apply to primitives.
- Redesigned
the Bundler I/O objects and their associated handler methods in ALFINode. (Related to PR 511.)
- Reimplementing Bundlers to use Bundler I/O objects
which will be tracked by individual container nodes instead of data static
to bundler objects through all container nodes it may be inherited
into. (More PR 511 work.)
(Melody) Working on PR 296 - easier access to settings.
Data Analysis Activities (Lazzarini)
Chatterji:
As of this week, single detector Q Pipeline searches are now running for H1,
H2, and L1. An initial manual inspection
of triggers shows a large excess low frequency high Q
glitches in both H1 and L1, but not in H2.
I am now working on automating the production of daily trend information
and histograms and posting these results on-line.
I am also working on merging Q Scan results with the event displays being
used to follow-up interesting events. A
prototype version has been circulated within the glitch group for comments.
I prepared abstracts for a detector characterization talk and Q Pipeline
poster at GWDAW10.
Mendell:
1. Presented plans to analyze the S4 data with the StackSlide
code at the November pulsar F2F and LSC meetings. The code review has made signficant progress, and the final S4 calibration is
done. A few minor issues to do with SFT
cleaning remain to be sorted out, but it should be possible to start producing
what should become final S4 results within a month.
2. Virginia Re visited LHO, and we worked on code to StackSlide
the F-statistic, as a part of a hierarchical search strategy to be used for S5
analysis.
3. I am currently closing in on solving problems with SFT generation for S5,
and also issues related to 1 Hz lines in the data.
Shawhan:
- Attended
the LSC Meeting at MIT, plus the LIGO-VIRGO meeting and a face-to-face
meeting of the Burst Group.
- Reviewed
pulsar F-statistic paper draft, plus Einstein@home
and time-domain analyses.
- Spent
time on the reviews of burst analyses, in preparation for GWDAW.
- Gave
a seminar talk about LIGO at UCLA.
Sutton:
I drafted and distributed to the LIGO-Virgo group a short set of slides
describing why we should use SNR at 50% efficiency as the sensitivity measure,
rather than the efficiency at fixed SNR.
I studied cross-correlations in the DFM supernova population, and found
cross-correlations mostly "small" when comparing waveforms of
different types (i.e., comparing DFM types I-II,
I-III, II-III). I picked a set of 3 DFMs (one of each type) to use in the network analysis
simulations for our GWDAW presentation.
I also drafted a short matlab script and note
on optimal tuning for LIGO-AURIGA 3X vs 4X data sets,
and sent this to Cadonati.
Weinstein -
- Reviewing
Inspiral group submissions to GWDAW
- Working
with Lisa on ringdown search
Yakushin:
1) Integrating event display and CorrPower into
the waveburst online pipeline;
2) Participating in the GWDAW10 talks review telecons.
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS
Much work has gone into making LDAS fully support large files (PR#2135). At
this point, all of the unit tests now pass under Solaris 10 and Fedora Core 4.
It will next be tested on a tandem system and then thread safety will be tested
on ldas-dev. [NOTE: this is one step in the direction
of full 64 bit support.]
Work was also done to verify a fix for not all frame files being renamed
from .gwf.tmp to .gwf
(PR#2900). This code will be committed to CVS today and be part of the weekend
testing.
PR2119 (request to have a -force option for the createRDS
command) and PR1604 (reduction of duplicate history information for SFT frames)
have been closed as Greg Mendell wrote in e-mail that
the functionality was no longer needed.
Greg had reported the frameAPI being locked up.
Upon investigation of a gcore, it appears as if the
Solaris 10 thread library may have some issues as all threads were waiting for
the release of a mutex. More investigation is needed to resolve this
issue.
cmonClient - more
progress with PR 2951 tclglobus channels after adding
a flush for the socket following a puts: fileevent
proc was triggered. Working on data parsing. Closed
PR2949 - default cursor to entry widget instead of button; Closed PR2906 -
handle error when flushing file handle.
cntlmonAPI - working on
PR 2969 - all user cmd test failed to detect aborted
jobs; PR2964 - all user cmds test should delete lock
file for exceptions.
frameAPI - closed PR2956
- delete frame resource variable from resource, ::DEBUG_DEFUNCT_JOB_REAPER; PR
2879 -always log removal of defunct jobs; added code to log 30 jobIds each time for defunct jobs.
TCLGLOBUS
Worked on Globus FTP control control and data channel through GSI socket.
Previously, the data channel wasn't able to retrieve the data eventhough the server had already replied the client's
request. Need to set client data channel
characteristics to match with the server's. Still have an issue with closing
the control and data channel properly.
Fixed several issues with XIO-based Tcl channel
based on Mary's feedback:
- Previously,
the application wasn't able to get the full data because the data didn't
get flushed from the channel.
- Modifying
and testing server code with multiple client connections. When multiple
remote client closes the connections, the server
doesn't close corresponding channels properly.
Upgraded the TclProxy server box
to Fedora Core 4. Installed Globus
Toolkit 4.0.1 the box. Setting up
the following grid
services:
- GridFTP 2.0 service is running.
- MyProxy 3.2 service is running.
GRIPHYN/IVDGL/OSG
Inspiral work flows on OSG-PROD: Testing Inspiral pipeline with 603 DAG Nodes at SDSC and CIT
production sites and reached a new peak of 60 jobs running simultaneously the
week of SC2005.
On-going monitoring and systems administration: Upgraded osg-itb
to OSG-0.3.1 and Condor 6.7.13 Added support for new VOs:
DES, DOSAR, GLOW, SAM, SAMGRID. Installed fc4 on osg-itb-se in anticipation of future work with SRM. Completed upgrade of osg-itb to OSG-0.3.0
and Condor 6.7.12 with fc4. Successfully tested Inspiral pipeline with 603 DAG Nodes on OSG-0.3.0/Condor
6.7.12/fc4. Tested
VRVS as a future collaboration technology for OSG use. Backed up gsiftp and /etc/grid- security
information on tclproxy.ligo.caltech.edu for upgrade to fc4. Restored this information
after upgrade.
OSG Activities: Participated via telecom at a two day workshop on test and
integration of OSG 0.3.1. Attended ITB Ops Telecom and discussed collaboration
on more accurate VO web report generation with Doug Olson, Rob Quick and
others. Began discussions with Arie
Shoshana/Alex Sim PI and implementor of SRM at LBL about resource requirements to
support a port of
SRM to fc4.
Recieved request from OSG Council to participate with ANL and ISI on a
section of the OSG proposal to address advanced workflows and VDS.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Worked
with the site admins on nearly simultaneous
crashes of dataservers at both observatories. Figured out that the problem probably
isn't the same bug we had at CIT with corrupt ACLs. The admins at
the observatories are working with Sun on this.
- Handled
the ejection of L0 data tapes at the sites and their ingestion after
they've been shipped to CIT. Still
fine tuning this process, but it's way more
automated than it used to be.
- Freed
up tape slots at LHO (140+ tapes).
- Got
some A4 L0 data that Murali had requested staged
in and made available via LDR.
(Phil Ehrens)
- Did
general cleanup (including about 30% of subfloor)
of Lauritsen computer room.
- Various
LDG certificate related tasks... added users, issued service certs.
- Edited
various GRID related documents describing the use of user, host, and
service certificates in the context of LDG resources.
- Released
ldas sysadmin wiki for general use.
(Erik Espinoza)
- Added
PXE docs to the wiki.
- Writing
PXE config automation script.
- Preparing
for trip to ASA Computers.
- Testing
IPMI for network issues.
- Prepping
documentation to be added to wiki (sendmail, IPMI, etc).
(Stuart Anderson)
- The
order for the next 1000 "CPU" computer cluster at Caltech was
placed with the vendor today (Dec 1).
- The
computer room facility upgrade at Caltech should be completed tomorrow
(Dec 2) with an active test of the fire surpression
system.
MIT
(Keith Bayer)
- Moved
data to make room for more S5 data.
- Monitoring
dataserver after memory replaced on two banks..
- pcraid9 hung itself after NFS traffic overloaded it this
also affected ldas-grid which needed to be
rebooted as well.
- Installed
xorg-x11-Xvfb on cluster and headnode.
- Attempting
to get host certificates for ldas-pcdev1 and ldas-sundev1.
Livingston
(Igor Yakushin)
- On
Nov 23 dataserver@LLO had a kernel panic. 9
minutes later the same happened at LHO. According to SUN this is the
result of a bug in SAMFS and they are working to find a solution. The time
coincidence between two sites is presumably due to the identical archiving
program started simultaneously at both sites. We had no more crashes so
far.
- Power
strip for nodes 4-11 got burnt. This is the third power strip failure
during a month. The first two ones were fixed by resetting a breaker.
- On
Nov 29 gateway:/export ran out of disk space causing all LDAS jobs to
stop. Current createRDS and publishing jobs
generate a lot of intermediate files. After some cleaning the situation is
back to normal.
(Dwayne Giardina)
- Replaced
disk in node5.
- ssh key authentication for kipp and bmoe to ldas.
- Onasys database setup.
- Shipped
15 S5 L0 tapes to CIT .
Hanford
(Greg Mendell)
- S5
RDS generation is running smoothly at LHO and LLO most of the time. A few times the software or servers have
hung for several reasons. LDAS is
working to follow-up on each of these, and to implement fixes as these are
determined. However, in each case we were able to restart things and
quickly catch up with no loss of data.
(Ben Johnson)
- With
Dan's help, exported 140 S3/M7/A4 Level 0 data tapes, and replaced them
with blank ones. This should allow us to not have to worry about archive
space until early January 2006.
- Finally
got a working systemimager image + install cd. There are now 378 CPUs configured properly, and
available to cluster users. The rest are stragglers, and or nodes with
hardware problems, TBD (To Be Diagnosed).
- Helped
get a new local user here get his cert/account set up.
- Have
two cases open with sun. The first is the old L700 import/export problem.
The second is the dataserver kernel panic from
the 23rd. The L700 problem is still there; dataserver@LHO
has not panicked since the one-and-only time on the 23rd.
General Computing (Wallace)
MIT:
(Keith)
- Building
desktop for new grad student
- Ordered
computer parts etc
Livingston:
(Shannon)
- Just
received the PC to replace the one in the auditorium. Several items have not arrived. I need to check and see if it is a lost
shipment, or if Dell has shipped partial.
- Working
with a fiber tap for network monitoring.
It has not been flawless so far.
The syskonnect card refuses to capture
traffic that is on the fiber. This
may be a driver issue. I have
contacted the tap manufacturer.
Next step will be to contact syskonnect.
- Usual
round of pouring through the IDS logs brought to light a nessus scan yesterday originating from the LSU
campus. I blocked the source of the
scan at the border, to find out later that it was presumably a legitimate
scan. I have sent an email to the
person responsible for such things at LSU and suggested that we meet
sometime to discuss coordination of such activities. We'll see what comes of it. Ironically, I had been working on a new
updated nessus install here. I was planning on beginning scans in a
couple of weeks. The last nessus scan was done here ~6 months ago. Unfortunately for LSU, their scans
likely will not yield anything since most of the traffic is blocked by
default.
- Have
been working with Dwayne on upgrading and updating the Arkeia
software. We have successfully
installed a new library, ran a couple of backups, full & incremental,
and Dwayne upgraded the client versions of the software that was
previously installed. Next is to
work on schedules and email notifications.
- Discussing
our new mail server with the CanIt folks lead to
a plan to integrate a relay server into our mail system. I have a server on order to handle
this. I will work with Dwayne on
installing it when it comes in.
Perhaps we can get a handle on our spam problem here soon... Working on travel reservations for the
security conference in VA on the 12-13th.
(Dwayne)
- Restored
Tom Evans files from tape
- Installed
new release of Arkeia on baronne
and abundance
- With
Shannon, ran two new fibers to Computer
Users' room, configured new Foundry switch
- Cloning
Janeen's laptop has yielded a slight problem, as
DELLUTILITIES partition would not copy over. Now the machine won't boot, presently
trying to resolve this issue.
- Assisted
Bonnie with more HTML
Hanford:
(Christine)
- Helped
a user setup a password protected web directory.
- Purchased
two laptops for users.
- Worked
with Richard a little on the setup of the new VoIP
phone system.
- Took
care of a problem with the mail server not being able to NFS mount the
home directories and not being able to resolve DNS names.
- Discovered
that one of the DMT computers is flooding the local network with UDP
broadcasts. Contacted John Zweizig for help to stop the broadcasts.
- Created
two new user accounts required for the Science run.
CIT:
(Christian)
- W.
Bridge -Upgraded visitors' workstation from 2000 to Windows XP.
- Millikan- Created a backup of Irene Baldon's workstations. Also, I replaced the black
toner cartridge and image transfer kit on the HP 5500 printer.
- Julie
Hiroto - Replaced the cartridge on the
scanner/copier.
- I
re-imaged three loaner laptops that were returned this week.
- Mike
and I cleaned out the server to prepare for the fire suppression test on
Friday.
- Other
misc.: Continued onsite software/phone support.
(Mike)
- Loaded
a couple of SUN workstations, one for me and the other for 40 meter.
- Worked
the Spam Filters with Larry Wallace.
- Cleaned
up the Bridge Annex server room to be ready for the testing of the fire
suppression system.
- My
replacement laptop came in. I have started loading this with GC software.
- Held
down the fort while Larry was out on vacation.
(Veronica)
- LSC: Updates to the November meeting website;
installed the webpage for the meeting's presentations. Updates to LSC-related mailing
lists. Updates to the database of
the LSC-reviewed publications.
Updates to the Observational Results website. Posted a few belated presentations from
the earlier meetings.
- LIGO: Updates to the CIT and MIT
websites. Updates to the PAC19
website. Prepared a high-resolution
image for the Optical Society of America monthly publication. Per Ed Jasnow's
request, prepared a high- resolution LIGO logo and posted it at the
internal bulletin board for the Lab users.
Assisted Jay with email access issues. Assisted Cindy with PDF document
preparation. Transferred files from
Sydney's
laptop to his user account. Other
miscellaneous user support.
Christian and I tested a live stream capturing setup per a user
request; did not have time to troubleshoot it due to a short notice, will
need to look into it more closely.
- Project
Science: Worked with ITS on the migration of the Proj.
Sci. website to the ITS
hosting. Provided the ITS with the updated codes and DSN. The codes are now loaded,
we will be testing it shortly before the local cutoff.
(Larry)
- Worked
a number of procurement issues.
Purchased a couple of desktop machines which should arrive next
week. Working on the purchase of a
new engineering workstation.
Finalized a couple more s/w maintenance contracts. Received and distributed various items.
- Started
the monthly backups. Working on a new box to perform the monthly backups
and moved a number of related items to different locations.
- Assisted
in getting more locks switched to the new key system for the LIGO offices
on campus.
- Assisted
Cindy with information gathering for the kronos
system.
- Spent/spending
a great deal of time trying to get some license keys from Microsoft. Both
Mike and I have been getting the run around in getting the keys. Hopefully, we will receive them in the
next day or two.
- Received
some new racks and started their installation. One is installed in room 19
in order to help out one of the PMA groups get their equipment up and
running while they are waiting for their rack. Otherwise they would have
had to take up the rest of space in the room.
- Preparing
for the testing of the fire suppression system.
- Working
on getting the monarch quad cpu
unit sent back to the company for repairs. One of the internal boards
fried and may have damaged other components of the system. The pictures I
sent them of the boards convinced them that something was seriously wrong
with the system.
- Spent
a great deal of time working on the dual core FC4 machines. There are a number of items that need to
be tweaked in order for things to run efficiently. Still have a lot of work to do in that
area. Erik has been a big help and
we really appreciate the assistance he has given the group.
- Setup
a few new user accounts and cleared out a couple of mail aliases. Assisted in setting up a couple of
computers in different offices.
- Continual
work with the mail servers.
Mail Statistics for Nov 24-30, 05
|
Mail Statistics
|
November 24 - 30, 2005
|
|
Rejected Messages
|
17,883
|
|
Virus Messages
|
1,402
|
|
False Positives
|
|
|
Accepted Messages
|
11,236
|
|
Total Messages
|
29,119
|
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Systems, Management
Systems
from Dennis
Coyne
See also:
AL
Systems web page
AL Systems email
archives
- Held
a SYStems meeting 11/30: meeting minutes
Mostly a review of status for near term subsystem reviews and a recap of
the Stable Recycling Cavity workshop held at MIT, 11/18
- Held
a first meeting of the Optomechanical Layout
Working Group, 12/1. Establishing a common set of 3D models in the SolidWorks and PDMWorks
framework. Determined high priority needs and actions for providing simple
3D envelop models of key in-vacuum components.
- Dennis
C. and Albert L. have discussed the need for, and approach to, re-visiting
the scattered and diffracted light analysis for the arm cavity baffles
with the intent to set a new limit on the maximum beam de-centering for
AL. Latest information on mirror surface BRDF (including particulates) and
ground noise will be included.
Records Of Decision or Agreement (RODA)
See also the RODA status web
page
- Nothing
significant to report
Requirements
- Nothing
significant to report
Interface Issues
See the "Interfaces" section of the AL Systems web page
- Nothing
significant to report
Vacuum Compatibility
Residual Gas Assay (RGA)
See also the Vacuum Bake Lab
Bob Taylor
- I
have been cleaning and baking parts for the Quad all week. We are just
about done and I have only a few loads to finish.
High-Irradiance, Contamination-Exposure Cavities
Lee Cardenas, Liyuan Zhang
Changes highlighted in
yellow
|
Cavity
(Location)
|
Material/Item
|
Start
|
End
|
Comments
|
|
Cavity #1
(OTF Lab,
Bridge)
|
“Cable wire” (material type?)
|
~11/17
|
TBD
|
The
cavity has been aligned & locked. Taking daily ring down and absorption
measurements.
----------------------------------------------------------
The test for 40 pieces of MMG nickel plated Nd-B-Fe magnets (for Helena Armandula,
SUS ) has been completed and removed from the
cavity.
|
|
Cavity #2
(OTF
Lab, Lauritsen)
|
NA
|
NA
|
NA
|
Cavity
not ready. It needs some other optics(such
as: polarizing cube, 1/4 wave plate and some curve mirrors and lens) and the electronics.
We have used/borrowed some of the optics from this system to accomplish
the completion of the other two cavities. Recently the 700 mw NPRO laser was
used for Garilynn’s experiment and it needs
to be realigned to the cavity.
|
|
Cavity #3
(OTF
Lab, Lauritsen)
|
OSEM Flexi-circuit cable,
qty ~ 45
(Helena Armandula,
SUS)
supplied by Univ. Birmingham (Stuart Aston)
|
~6/10
|
~9/10
|
No change:
taking daily absorption &
ring down measurements
DuPont Flexible Circuits. The whole part to be
constructed of 'flexi' i.e. no 'rigid' sections. (Stuart Aston,Univ. of Birmingham, SUS/UK subsystem)
- Start Laminate: Kapton (LF8515)
(document link: http://www.dupont.com/fcm/products/H-73244.pdf
Coverlay (x2): Kapton
(LF0110)
(document link: http://www.dupont.com/fcm/products/H-73245.pdf
DuPont Pyralux
Series - Kapton / Acrylic Adhesive system.
(document link: http://www.dupont.com/fcm/products/H-73246.pdf
--------------------------------------------------------------
OSEM
emitter & photodiode 40 of each, (Dennis Coyne, SUS
) Test has been completed. Results to be posted by Liyuan
Zhang soon.
|
|
Queue
Priority 1
|
2 Cleaned 50ppm transmission mirrors, 1 in dia., REO coated --
|
TBD
|
TBD
|
witness samples for the LHO vertex volume (added in
6/29/2005 vent)
|
|
Queue
Priority 2
|
Stepper
Motor (Riccardo DeSalvo,
possible SUS or ISC use)
|
TBD
|
TBD
|
Stepper Motor sample had been placed
into Cavity #1: Power dropped from 175 mW to ~25 mW after introducing the stepper motor sample, and
continues to decrease. It is very hard to keep cavity locked. The stepper
motor may have contaminated the mirrors. Will re-test when a cvity becomes available again.
To be rebaked soon using the self-heating capability of the
stepper motor (not just the oven heater controls)
|
Systems-level Electronics
From: Rolf Bork <rolf@ligo.caltech.edu>
- It
looks like we have AWG and TP manager now fully functional on the new
computers. Initial testing looks good. There is still some minor cleanup
work to be done.
- We
received the PCIE to PCIX expander chassis. However, it did not work. I
called the manufacturer and they admit to having a problem with their PCIE
card when installed in computers that have a nVidia PCIE bridge (which, of course, is what we
have). They say they have a new card coming out to fix this, but not until
mid January. Since we do not have enough PCIX slots in the computer we
plan to use for the Lasti quad, we have had to
move everything into our SunV40 development machine. We will use this for
our tests at Caltech. Hopefully, we will have the new PCIE card in time for
installation at Lasti, but my guess is it will
be late.
- Of
possible interest elsewhere, we were doing noise measurements on our PCIX
ADC card, and kept getting a noise 'pop' at a very periodic rate of once
per minute. After a day of chasing ghosts, finally switched the ADC clock
from the GPS receiver to a signal generator. We no longer get this noise.
We then noticed that the GPS sync lite was not
on the GPS module, even though it had the right time. It is looking like
the GPS receiver does some sort of correction or has some other clock anamoly at a 1 minute intervals when not fully synced
up. We are trying various different antennas now to get our sync lite back, and will repeat the tests to see if this
clock noise goes away.
Seismic Isolation
Advanced Ligo Seismic Isolation Procurement
Status
|
Assembly
|
Status
|
|
Top Assembly Components
20007970-A
Stage 0 Assembly
2000795-A
Stage 1 Assembly
20007825-A
Stage 2 Assembly
20007825-A
|
Purchase order placed with Arland Tool for all large parts. All material has been recieved. Amendment made to purchase order to
change mounting holes on optics table from 2 x 2 to 1 x 1 hole
pattern.
Purchase order placed with Limerick Machine for the end milled plates and
remaining Top Assy, Stage 0,1,
and 2 Componants.
<!--[if !supportLineBreakNewLine]-->
|
|
Stage 0-1 Spring Assembly
20007878-A
Stage 1-2 Spring Assembly
20007890
|
Quotes for blades and rod flexures due 12/3.. Maraging steel has been ordered from Dyanamic
Metals and scheduled for delivery by 12/20.
Quotes for remaining spring assembly parts have been recieved.
|
|
GS-13 Pod Assembly
20007810-A
L-4C Pod Assembly
20007820-A
STS-2 Pod assembly
20007941-A
|
Geophones, seismometers and lockers are in house.
Purchase order placed with Norcal for vacuum
housings.
Purchase orders placed with Limerick Machine and Lavallee
machine for pod machined parts.
Design of harnesses completed. RFQ required for internal pod harnesses.
|
|
Stage 0-1 Kinematic Lock
20007941-1-A
Stage 1-2 Kinematic Lock
20007941-2-A
|
Tooling design complete.
Purchase order placed with Limerick Machine for kinematic
Lock Assemblies.
|
|
Stage 0-1 Actuator Assy.'s
20007966-A
20007967-A
Stage 1-2
Actuator Assy.'s
20007968-A
20007969-A
|
Tooling design complete.
Purchase order placed with Limerick Machine for actuator mounts and tooling.
|
|
Stage 0-1 Standoff Pin
Stage 0-2 Alignment
Tower and Washer
Stage 2 Keel Plate Alignment
Tower
Blade Pre-Load Tooling
Blade Calibration Fixture Modifications
LASTI Test Stand and Spreader Bar
|
Design of stage 0-2 and stage
1-2 alignment pins complete.
The blade pre-load tooling and calibration fixture tooling will require
redesign following the redesign of the blade springs by ASI.
The test stand has been delivered to MIT and assembled in its low height for sei assembly.
|
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
Working with Nergis on her pondromotive experiment. Her optics are a bit larger than the nominal SOS optics. She'd hoped to
use the initial LIGO fixtures but will not be able to use the ring fixture (to
mount the magnets) without some rework. I've been looking at the changes to the
drawing and have asked Mike Gerfen in CES to quote
for a new fixture.
Working with Gregg Harry and Steve Penn on their thermal
noise experiment. They have an initial LIGO Pathfinder optic and a
prototype LOS suspension structure. They
need wire standoffs and a guide rod but not magnets. Doug Cook has agreed to
install the components, as soon as the optic is sent to him. He will send it back
to MIT when he is done. Mark Barton has already sent them some spare bits from
Caltech, including some music wire.
Working with Shannon and Dwayne on loading my new laptop.
Made sure we are up to date on our ANSYS and Algor
subscriptions.
From: Calum Torrie
<ctorrie@ligo.caltech.edu>
Almost all of the parts of the quad controls prototype have been cleaned and
baked. We have a few loads still to complete. I am aware of at least one load
that had to be re-cleaned in order to pass its FTIR test and another that was
sent back through the cycle after we ran into a problem vented the customised stops. Bob did have a problem with an oven which
has delayed us a little. Lee and I have now assembled the lower structure and I
have completed about half of the clamp wire clamp assemblies.
Tim Hayler has been looking at bolted connection
in the overall quad suspension structure. I have been offering him some support
on this effort. I should note that at Caltech we now have two versions of
ANSYS. Ansys University with
a 128,000 node limit and Ansys Research with access
to 512,000. (This was set up a while ago by Janeen
and I have to confess I had forgotten.) With the Research version it is
possible to run examples with a fully meshed (as built) overall suspension
structure.
Mark Barton and I completed a bench test in the lab looking at angled blades
with vertical wires, reference Mark's weekly and his
write up.
The 2nd structure has now been delivered to Stanford for further testing.
The installation tooling work with Mike Gerfen is
progressing well. Ken Mailand is working on an
alternative for the air bearing and XY stage. We are currently dealing with
some vendor questions ahead of placing an order for the linear drives.
Ken Mason and I have been in discussion about tooling for the quad build at
LASTI in January.
From: Ken Mailand kmailand@ligo.caltech.edu
I’m working on shop drawings for the SUS installation plate style
fixture for Calum, I gave him cost and time estimates last week. This is an
alternate to the air bearing setup, and uses the same table frame.
From: Jay Heefner jay@ligo.caltech.edu
AdL SUS and SEI
- Anti-alias
and Anti-Image chassis for the AdL quad controls
prototype are now operational and running with the ADCs and DACs. We are on schedule for a test of the system in
the Synchrotron lab starting next week.
- System
drawings for the LASTI installation of the SUS and SEI components are
being refined in preparation for an install starting in January.
- Racks
and power supplies for the LASTI systems have been shipped to MIT from
LLO.
Core Optics
From: Bill Kells <kells@ligo.caltech.edu>
Since the MIT stable cavity workshop I have been working on refinements
(with Phil) on the concepts discussed there. Its further along in
the details now. After today's AdL systems meeting ,and your comment that a general design needs to be tightened
up for May, I realize that it is unlikely that full modeling (via the
"new" FFT code) will not likely happen by then. Recall that this was
much discussed at MIT as a final arbiter of a stable configuration.
Also, I have cycled through a further round of PI review on yet another draft
of the Perth PI estimates for AdL. There is a lot of
emphasis we disagree on, but it has been agreed that the lastest
draft is "close enough" and "fair enough" to pass internal
muster. This has involved a lot of work (basically I have checked all their
detailed results with my own calculations, etc.), and provide much insight all
around as fall out.
From: Helena Armandula ahelena@ligo.caltech.edu
CSIRO - Oxygen deficient coating
Report from Roger Route:
"As I reported on the telecon, we were forced
to move our controlled-atmosphere annealing furnace to a new room. I
re-plumbed the argon delivery system and tested the purifier to less than 0.1 ppm. I completed one run on the Ta-coated optic at
350C overnight with a 250 C/hr heating rate and a somewhat higher cooling
rate. The single issue that I have been trying to deal with is that the
RF generator in the same room is often in use for heat-treating ceramics and
every time it exceeds 1200C, the external temperature recorders on my furnace
become noisy and go high by hundreds of degrees which they did during the annealing
run. I think this is a pickup problem and have tried to duplicate
conditions to verify that the LIGO optic did not exceed 350C even though the
recorder trace suggested significantly higher temperatures. I am not sure I can
ever do this to my satisfaction, but a trace yesterday with the rf generator off did not have any
problems. The furnace is controlled by a Eurotherm
controller which was set for 350 C and whose readout does not seem to be affected
by the rf. Eurotherms are usually much better protected from rf than are strip chart recorders,
so for now, I am assuming the optic did not exceed 350 C unless some other
evidence arises.
The coating looks OK under the microscope. I don't see strong visual evidence
of crystallization having occurred.
Vlad ran the attached scans of the optic at 4
points, one on-center and the others at 1 cm right, left, above and below
center. The numbers seem high, in the 12 - 14 ppm
range. No idea if this is characteristic of oxygen deficient
coatings. I was hoping we had measured the optic before annealing, but he
could find no records of having done so. I remember being reluctant to risk
contaminating the surface before annealing and it is probable we did not.
If you have a witness sample in the pre-annealed state, we can measure that to
get the as-deposited loss."
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
The hour meter circuit was tested and works as
desired. The relative intensity noise of the Innolight
NPRO was measured. One difference between the Innolight
NPRO and a Lightwave NPRO is the effect of the noise
eater on the low-frequency intensity noise. A broad peak is present in
the spectrum at about 600 Hz that is not present in the Lightwave
models. Some problems were encountered in measuring the low-frequency
noise because of some noise in the power lines. Which I suspect is either
due to the machine shop beneath or the machine shop next to the PSL Lab.
Auxiliary Optics
From: Michael Smith <smith@ligo.caltech.edu>
VERTEX LAYOUT
I can now export all of the ZEMAX features into a SW assembly. I have
created optical rays in ZEMAX for the smallest wedge angle of the BS that gives
zero clearance of the PO beam from the main beam (I will increase the BS wedge
angle to provide minimum clearance later). I inserted those rays into a Solid
Works model of the ADLIGO vertex, which includes mock-ups of SUS towers, PO
mirrors, cavity beam dumps, baffles, working PO
telescopes, etc. I am in the process of optimally placing the PO mirrors on the
BSC tables to enable access to the PO beams. The
beam dumps and baffles have been placed so they can mount to the existing cross
mounting tubes in the LIGO1 BSC chambers. I am planning to use the existing arm
cavity baffle support structures, with a new baffle surface to match the larger
beam sizes and optical lever placement.
Luke Williams has sent me coordinates of the IO beam lines, which I will
incorporate into the ZEMAX model.
Other Laboratory R&D
From: Riccardo DeSalvo desalvo@ligo.caltech.edu
Virginio, Valerio, Riccardo
Presented HAM SAS to LIGO review panel. The documentation prepared for the review is
available in http://www.ligo.caltech.edu/~desalvo/HAMSAS/Review20051129
Yumei
Continuing measurements of IP attenuation table. Continuing studying ANSYS.
For additional information about this report, contact Stan Whitcomb or Phil Lindquist