Weekly Report for
Week Ending November 17, 2005
The LIGO Executive
Committee Agenda for Monday November
21, 2005 will be:
(Meeting time: 10:30 am Pacific Time)
1. Announcements
2. Comments
on Weekly Report
3. LSC
Issues (Saulson)
4. LIGO
Lab Operations
- Administration
(Lindquist)
- Sites
(Raab, Zucker, Shoemaker)
- Commissioning
(Fritschel), Detector (Coyne)
- Campus
Research Facilities
- 40
Meter (Weinstein)
- TN,
( Libbrecht)
- LASTI (Shoemaker)
- Data
Analysis and Computing (Lazzarini)
5. R&D
and Advanced LIGO (Shoemaker)
6. CHANGE CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION AS
NEEDED
Special Items:
Special Announcements:
Weekly
Report Highlights
No report
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
Non-LSC MOUs (Lloyd)
SITE TELECONFERENCE (Lindquist)
- A
site teleconference was held Thursday, November 17, 2005. The following issues were discussed:
- Outreach Center – LSU review is
complete.
- Property
Management – A visit to conduct a property inventory at Hanford is planned
November 28 – 30.
- Entrance
Gate at Livingston – A close
encounter with a liquid nitrogen truck destroyed the gate. A new one is being installed along with
a detector circuit to prevent inappropriate gate closure.
- The
list of assigned actions updated through September 01, 2005 will be found Here.
PROPERTY MANAGEMENT (Chargois)
>From: Ed Chargois <chargois_e@ligo.caltech.edu>
- Assisted
the General Computing Group (M. Pedraza) with
the disposal of various pieces of Data Processing Equipment, through
Caltech's Disposal System.
- Provided
assistance to the Detector Group (C.Torrie) with
the preparation of a Commercial Invoice, packing and shipping of hardware
being transported to Rutherford Appleton Laboratory (Mr. I., Wilmut), Oxon, UK.
Account number P207754.
- Provided
assistance to the Detector Group (C. Torrie) by
arranging Transportation for a Quad Structure 96"x34"34"
being delivered to (Dr. B. Lantz) at Stanford University. Account Number LIGO.PRCIT 5.17 FY02CA.
- Provided
assistance to the Detector Group (G. Billingsley) by arranging
transportation for a High Purity Fused Silica Optic SN: COC-A005 being
delivered to (G. Harry) at MIT. Account
Number P204296.
- Provided
assistance to the Detector Group (C. Torrie)
with packaging and shipping of stainless steel hardware being delivered to
(Dr. B. Lantz) at Stanford University.
Account Number P207754.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- Updated
rosters on mail tray lists in the mailroom.
- Update
on Scanning Project - Progress continues on Larry Jones' boxes of
files. To date, we have 13 of the
16 boxes scanned. These boxes may
be completed by next week.
Preparations are also underway for scanning some old blanket
purchase order files.
- Activity:
|
Week Ending
11/17/2005
|
In
|
Out
|
|
Packages
|
31
|
7
|
|
Faxes
|
23
|
20
|
FINANCIAL SYSTEMS (Cronin, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Completed
the basic order to Limerick and federal
expressed the signed contract to the vendor. Completed change order #1 which adds
funds for fab of the actuator, locator
subassembly, and tooling. Sent the completed change to the vendor.
- The
vendor just received the check for Filehold
which was delayed in the mail.
- Completed
change order #1 to Arland and submitted it to
the vendor.
- Completed
change order #167 to Triad for the renewal of one contracted individual.
Routed this package for approval.
- Completed
change order #28 with Support Services for the annual renewal of two
individuals and submitted it to the vendor.
- Working
with Calum and Gina on the quote for the
actuators.
- Working
on the order for the Lasers for LLO which will be coming from England. Clearing of customs should take no
longer than one week in addition to the 10 week lead time.
- Working
on the change orders to the subcontracts with General Optics and Promec.
- Received
a request to closeout two subcontracts. I'll be sending out the release of
claims to S Osder
and Parker Hannifin.
- Attended
several training sessions during the week, and also attended the weekly
procurement meeting. I was requested to submit a status report on blanket
purchase orders. LIGO is current on the blanket purchase orders and there
is only one expired blanket order which is the subcontract for S Osder that I will be
closing out.
- Working
on the change order to the subcontract with Total Energy.
- Waiting
to hear back from Payables on the payment of small dollar invoices through
pcard.
>From: Florence Kaufman <fkaufman>
- Completed
and sent out reports through October for the Visitor, Low Noise, MIT.GRID,
and US-INDIA Awards. Also reports
for the Hanford Conference account, and the Hanford
and Livingston discretionary accounts.
- Noted
that an incorrect expenditure type was used on a payment to a visitor
which resulted in unwarranted charges for benefits and Indirect Cost of
$4,318.00. An expenditure type
correction will need to be requested to correct this.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone
<gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow
<jasnow@ligo.caltech.edu>
- The
change order for the LLO SEC architect, Eskew-Dumez-Ripple,
to add visits to the construction site has been prepared. Issuance is awaiting a receipt from the
architect of a revised Exhibit D, which details the types of visits and
cost for each.
- A
consensus meeting was held to review the two proposals received on the
HAM-SAS system for LASTI. Although
one company was clearly superior to the other, it was agreed to brief the
Source Selection Official, Stan Whitcomb, on the competitive aspects and
financial aspects of the procurement.
Additionally, it was agreed to firmly establish the LIGO estimate
for this system.
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
- Processed
the paper work for six (6) new/revised trips. At this time there are five (5) trips
completed or in the works but are awaiting the necessary paper work to
enter the P-Card system.
- Completed
five (5) Expense Reports and there are five (5) reports yet to be
done. I continue to contact
travelers who have outstanding Expense Reports (more than one (1) month
old) to ask for their cooperation in sending me their receipts so that
these can be closed in a timely manner.
Presently there zero (0) reports more than thirty (30) days
old. I have no reports awaiting
signature at this time.
>
>Dorothy Lloyd
- No
report.
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- No special activities to report.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
- Nothing significant to report this week.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of S5 Activities at
LIGO Hanford
Observatory
An eventful week to improve the ranges and duty factors of
the two Hanford IFOs to bring them into operations
appropriate for S5. Two new SunBlade
1500 computers have been installed and are running the injections. Fast
shutters were installed on both IFOs' AS-port
tables. Timing systems continues to need attention. A suite of PEM
injections were completed. New filters have been installed and
calibrations taken. Features of various monitors were discovered and
noted (e.g., the 4k's range is large enough to overflow senseMons
floating point variables; ldas-grid condor problems
interrupted the Inspiral Monitor; etc.)
Weather fronts raise the microseismic levels and
either make it difficult to lock (with consequent impact on the duty factor) or
lower our ranges. Large seismic events (Honshu
earthquake, m6.7-7.2) continue to cause interruptions.
But, do not loose hope: last night we ran for ~10 hours of triple coincidence
between H1, H2, and L1.
4K IFO
H1 had difficulty locking during the daytime. Efforts have been
focused on improving its duty factor through updated alignments, new ETM and
ITM filters, and WFS-TCS-AS-I tuning. In the evenings the IFO locked and
attained an inspiral range of 10.5Mpc - 12.0Mpc, with
a steadily improving duty factor. At the end of the week H1 ran at 12Mpc
for 11 hours with only ~1 hour of interruptions from "Science Mode".
2K IFO
H2 is solid and has a near 100% duty factor, but a poor range of 4.1Mpc -
4.4Mpc. It locks day and night. Work on the TCS hints at an
improvement.
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
L1 Interferometer (Frolov)
The Livingston interferometer joined the S5
science run on Monday. The duty cycle is a disappointing 15% after two days of
running. It was mostly limited by the seismic noise from logging and
construction and from an intense storm in the Gulf. The inspiral
range was 10+ Mpc on the opening night but slipped to
7 Mpc last night, in part due to reduced
interferometer power from 7 W to 5.5 W and in part due to the elevated seismic
noise and possible instability in the angular control system. On the bright
side, the laser has been stable after the diode pump current increase last week
to get more power into the interferometer.
#MZ comment: due to 5+ weeks of laser trouble preceding the run, culminating
in last week's forced emergency replacement, we just did not have sufficient
experience at high power to guarantee long-term stability at peak range.
For now we'll compromise power (and range) for uptime, while we work on
debugging that last power step. It's gonna be a long run...
Commissioning activities this week
- one
of the anti-symmetric port photo-detectors was damaged by the beam and
replaced after damage was discovered
- the new fast shutter was installed on the
anti-symmetric port photo-detectors.
The closing time improved from 6 to 4 ms. The
bias kill circuit had to be disconnected to accommodate this improvement.
- the TCS servo was engaged for the first time. It was
stable in the configuration with the interferometer input power of 7 W,
central heating on ITMY and annulus heating on ITMX.
- the digital filtering of the optical lever signals
around 30 Hz eliminated the corresponding DARM peak which for years
thought to be irreducible.
- the purge system for the dust cover on the AS port was
installed - the interferometer calibration was verified. The DC
calibration parameters were found to be within 5% from the previous measurements.
- the beams on the anti-symmetric port photo-detectors
were realigned to minimize the low frequency RF signals in the Q phase of
each individual photo-detector. This procedure gave a factor of three reduction in the rms of the
low frequency ASQ signals.
- the optical lever compensation filter were re-tuned -
the frequency stabilization loops were re-measured and ugf's
were set.
Outreach (Thacker/Zucker)
11/8: about 60 senior High School physics students from Broadmoor High in BR
11/9: Southern University, College of Education, about 8 students +
instructor
11/10: Visit from Inga Peterson
and Dave Fleming from Exploratorium to discuss customizing 4 exhibits
11/11 Glen Oaks Elementary; about 20 pre-K students +
parents + teachers
11/12: Middle School Science Teacher professional
development
11/14 & 11/15: 35
sixth grade students from The Runnels School
SEC construction: Intense fill and compaction activity impaired
interferometer operation during the day. We granted a Saturday exception to
allow some schedule catch-up last weekend. Rainy weather interfered Tuesday and
Wednesday but we are told the fill is about done; next phase will be drilling
for pilings and concrete forming.
CDS (Bogue)
- Spent
a lot of time working with Valera on our channels.
- Worked
with K.Riles on updating our scripts that put
automated entries in the elog and that produce
automated plots on london's web site. 75% of this is now working correctly.
- Installed
channels and medm screens to support FAST ADCU -
Installed channels and medm screens to support
Shutter Timer.
- Took
another look at some problems with the gamma ray burst notifications.
- Working
on a problem with our statevector code.
- Installed
the loaner atomic clock. It has
been rewired so that it does not output a 1pps signal. I am working with the manufacturer to
see if we can get the specs to rewire this thing ourselves. Concurrently, I have been working
through shipping issues to get our clock sent back to the manufacturer for
repair.
- Our
injection box had hard disk failure.
Installed a spare hard disk and jumpstarted the configuration. RMA'd the
original disk. It is still under
warranty.
Computing and Network Security (Roddy)
Spent a couple of days working with and IDS/IPS/event
correlation software package.
This is an open source package that ties many tools together. Because of its string of dependencies, it is
quite an intense install and is fairly difficult to manage. I am concerned about this, since it is
conceivable that when it comes time to upgrade, it will be very difficult. It is possible that we could end up with an
insecure security monitoring package, which is certainly not ideal or
desirable. The software is quite useful
despite the pains in working with it.
Worked some with Dwayne on the new backup library.
Ordered various parts, a computer for the auditorium and a
few other items.
General Computing (Giardina)
- configured Thunderbird email client to point to new mail
server on laptop for Allen Sibley -
installed drivers for video capture on PC for John Thacker and
Outreach - configuring a new laptop
for Janeen Romie, was
initially installing everything from scratch. after talking
with Mike Pedrazza I may swap drives with her
old laptop. this
is dependent upon some diagnostics to be run on the old drive.
- installed perl 5.8.7 and Tk modules on ilog.ligo-la.caltech.edu to fix errors
experienced by Bruce Sears -
applied the latest Windows updates to the laser security server
- created a weekly CSV extract of
the activity logs on the laser security server. After discussing with Shannon and Lisa,
these extracts will be copied over to the ilog
server
- with
Shannon, installed new rack mounted tape
library, and barcode labeled the additional tapes
LDAS Admin (Giardina)
- replaced
disks in nodes 130 and 166
- node126
required reboot with fsck and is now OK
- replaced
failed disks in t3-8 and t3-23, received replacements from Sun
- reconfigured volume on t3-13 to include u1d8 and u1d9,
it has been a couple of months since they were included.
- shipped
tapes LL0373, LL0526, LL0544,
LL0555, LL0567, LL0569, LL0573, LL0577, LL0583, LL0604, LL0613, LL0627,
LL0647, LL0656, LL0659, LL0678 to CIT
CDS Code Support (Khan)
Developing a device driver for the New Focus Pico Motor
Controller. The advantage of this device driver is that it requires only
a database and no state code to control the XY motion. This would enable us to
design servo system without the need of a full blown state notation code.
Site Safety and Security (Riesen)
Found no site/laser safety concerns this period.
The main gate repair/replacement is underway. Have not heard as to when the
gate will be operational again.
#MZ For those who missed it on the news, an LN2 tanker mistimed his approach
Tuesday, thereby causing a "misadjustment"
of the access gate. We're asking visitors to please pause and pretend there is
still a gate there until a replacement unit arrives ;)
AdL SUS/SE Mechanical Engineering (Spjeld)
Quad SUS Installation Fixtures
- completed
release DCN and drawing package for manufacturing, submitted to DCC
- meeting
with Calum and Ken Mailand
on Nov. 16 to discuss design and manufacturing
- looking
into off-the-shelf parts for the linear bearings, shaft and shaft blocks
for lift table
LDAS/Condor data analysis (Yakushin):
Storage/Condor/LDAS admin:
1) As the weather got colder, it became apparent that there might be a
configuration problem with the air conditioner in the high bay: the colder the
weather outside, the more heat is produced by HVAC. Setting termostats'
low threshold temperature to the lowest possible 40F helped a lot but not
entirely and the temperature is still a few degrees higher than it should be.
2) Ordered 4 more spare power supplies for the nodes.
3) Fixed several configuration issues with the cluster as users discovered
missing software or accounts when trying to start online jobs.
Data analysis:
1) Working on online waveburst scripts.
2) Reran 28 S4 waveburst jobs affected by a
recently discovered minor bug in the whitening procedure.
Initial LIGO Detector Science & Engineering (Coyne)
CDS
see also the CDS weekly meeting minutes
in the commissioning
archives
CDS Software
Rolf Bork
- Made
requested changes to LSC code for triggering shutter on
- ASI-CORR
signals. This code will be transferred to LHO on Tuesday.
CDS Hardware
Nothing significant to report
DMT
no report
Optical Metrology
no report
40-Meter Interferometer (Weinstein)
IFO Commissioning
- Our
old laser appears to be serving LLO well. They installed it, got up to 8.9
watts, and recovered 11.5 Mpc inspiral range, in less than
a day.
- Doug
Cook is preparing the old H2 laser for us as a replacement. It will have
the old (noisy) NPRO. He shipped it on Wednesday and we expect it on
Friday. We will begin installation on Monday, but vacations and
Thanksgiving will interrupt the remainder of the week.
- Osamu
is working on a paper about the seismic noise and its contribution to the
40m noise budget, with David Blair and Ryan Kinney. He is taking more
data, and fixing some problems with the measured noise spectra.
- Steve
has been measuring resonant frequencies of various components on the PSL
table, and he and Osamu are correlating these with peaks in the PSL frequency
noise spectrum as measured by the mode cleaner. A few shaky mounts have
been identified. He will also check the in-vac
DLC mounts that we have for the DC readout beamline,
as well as Mike's new OMMT.
- Rob
is continuing to rework the front end LSC code to make it more robust,
flexible, and functional.
- Dan
and Monica continue to work on developing the noise budget for the 40m.
IFO Modeling
- Osamu
has been discussing the modeling of radiation pressure in e2e, with Hiro. He is trying to understand the approximations
made.
- Monica
has validated her e2e package with Hiro's dual
recycling summation cavity. She and Hiro found
and fixed all the bugs, and she has verified that all the equilibrium
fields are correct, as is the DARM transfer function. She will repeat
error signal sweeps. She's also using Matt's 5dof control plant, with mods including 40m filters, to simulate full lock. So
far, she can hold lock in e2e for 10 msec. Trying to figure out reason for lock loss.
- Rob
is working with Matt on yet another frequency domain IFO model, with full
quantum formalism. This one is matlab-based.
DC Detection Development
- Ben
has been working on the DCPD design for the DC readout. He sent out PCB
files, and the boards should be here tomorrow.
- Ben
has ordered the parts for the DCPD electronics, including several
resistors that will be evaluated for their vacuum compatability.
- Mike
Smith now has all the parts for the DC readout beamline,
(including the OMMT mechanical parts and mirrors, the in-vac mirrors, mirror mounts and steering mirror PZTs, etc) except for those being made by CES (the OMC
body and a couple of mirror mounts). Mike has pre-assembled the OMMT, and
everything seems to fit.
Electronics, Controls
- Ben
replaced the mixer on the Mach Zehnder Servo
board with a lower, level 7 mixer which should work better with the signal
levels that we actually have.
- Steve
ordered a new RAID array for our DAQ system, to replace our dying one.
- Dan continues to work on suspension diagonalization.
Thermal Noise Interferometer (Black)
With the new, corrected mode matching, we
have achieved a visibility of 90 percent in the north arm cavity (NAC). This is
a significant improvement over the 70 percent we had before. We are now working
on the south arm cavity (SAC).
LASTI (Ottaway)
No report.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
(Hiro)
The Optical Spring issue has been studied further using e2e. e2e showed that the
radiation pressure noise excites the optical spring resonance in the same way as the actual
signal. Any noise or control
which include Differential Arm (DARM) mode can excite the optical
spring in the same way as the signal.
The 40m sensitivity curve limited by the radiation pressure and shot noise
was calculated using e2e and the result showed qualitative agreement with the
A. Buonanno and Y.Chen's
calculation. Quantitative comparison will be done after applying a better lock
and proper servo correction.
Hiro talked with Nergis
and Corbitt about the possibility / necessity of
including the two photon formalism in e2e, and it was
concluded that all dynamical effects are implemented in e2e using classical
mechanism and that it is not necessary to implement the two photon formalism in
e2e. The extra effort is to allow accurate prediction of the sensitivity in the
locked state, and it can be done easier using a frequency domain model.
Simulation of 40m Advanced Interferometer
(Monica) The optical configuration of the new e2e package for the 40m IFO
(i.e. including the dual_sum cavity) has been
validated following the same procedure as the previous one. Values of
equilibrium-state field values and expected main signals (e.g. DARM at the dark
port) reproduce Twiddle results. The package is now used to keep the
interferometer at the operating point: Test of the control plant are being performed to verify and correct its behaviour.
Mode-Cleaner
(Sany Yoshida) Uzma and
I analyzed pointing fluctuation of the LIGO I input mode cleaner's transmitted
beam. We fed ground motions recorded at HAM1 and HAM2 via LLO DAQ channels to
our e2e HAM stack model to compute the HAM1 and HAM2 table-top motions. The
resultant table motions were fed into our Mode Cleaner(MC)
model consisting of three suspended optics (for mirrors MC1 through MC3).
We compared the computed MC transmitted beam's pitch and yaw
motions with the corresponding DAQ pitch and yaw signals recorded at the same
time as the above ground motions. The power spectra of the computed and
recorded MC transmitted beam pitch signal show reasonable agreement with each
other.
The power spectrum of the recorded MC transmitted beam yaw motion appears to
be much closer to the computed HAM1 yaw motion than computed MC transmitted
beam yaw motion. More detailed analysis is undertaken.
Alfi
(Bruce)
- Continuing
work on new data object to track changes in bundler I/O names in inherited
bundlers (PR 511.)
- Full-path
include-directive problem has been addressed- the user now has more
options and information about why and how to avoid using them.
- Alfi exit problems have been addressed. An exception
at quit time will no longer prevent Alfi from
exiting.
(Melody)
- Fixed
the code exceptions which were encountered using the newest release of JGo (5.14).
- Working
on Problem Report 296 - easier access to settings.
Data Analysis Activities (Lazzarini)
Shawhan:
- Worked
on organizing Burst Group presentations at the LSC Meeting, and the Burst
Group face-to-face meeting afterward.
- Helped
organize reviewing of burst analyses.
- Maintenance
on conlog configurations at the sites.
Weinstein
- Review
of LIGO-TAMA S2/DT* BNS re-analysis, and careful read of final draft.
- Working
with Lisa on S4 ringdown analysis
- Working
with Drew on chirps with massive gravitons.
Yakushin:
- Working
on online waveburst scripts.
- Reran
28 S4 waveburst jobs affected by a recently
discovered minor bug in the whitening procedure.
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS
With the start of S5 at Livingston, the
code freeze on the LDAS CVS repository has been lifted. New code and nightly
builds addressing the targeted list of PRs for the
next release of LDAS have begun.
At the top of the list are the request for being able to specify the
location of the directory for storing md5sums of created RDS frames to allow
separating the tranfer mechanism for RDS frames and
md5sums into two paths. Also improvements to use of X509 certificates, better
performance in the diskcacheAPI and migration towards
64 bit executable are on the list.
A bug in the genericAPI TCL code that used the TclGlobus package was found to lock up the Solaris 10 operating
system to the point that the system required rebooting. The bug in the LDAS TCL
code was one of scope on an environment variable (local scope when it should
have been global). This caused the Globus Toolkit
4.0.1 release to go into a tight loop trying to read the certificate file from
the hard coded location in the GT4 XIO source code instead of from the place
that should have been specified by the environment variable if it had global
scope. Since the certificate is not stored in the default location on the LDAS
systems, the read was unsuccessful, but somehow cause the Solaris OS to become
non-responsive. Fixing the scope to global resolved the issue, but we are
working on a simple sample code to provide to Sun and Globus
developers so that this sort of application level bug doesn't bring down a box.
The initial enhancements to the c++ diskcache
performance test have been completed. The reults did
not show the significant scaling issue for either local file
system or Sam-QFS file system as reported in pr2753. The test was
modified to do both an assending and descending
addition of the mount point entries. In either direction the scaling is linear.
The next step is to have it run on the actual /archive file system. This will
require additonal modifications.
Worked on having Object Space compile with the pedantic
flag for GCC. It has revealed several errors that are being corrected.
This effort is to support large files.
Put a new package into the controlMonitorAPI's
client to utilize TCL Channels via the TclGlobus
package when support is ready. Fixed the reset bug in the submit button in the
client. Added scrollable window to the display of the
resource variable diffs. These address problem
reports 2951, 2950 and 2838.
Changed over to using system "rm"
to clean up the results and logs associated with test scripts. The TCL
delete was causing the QFS filesystem to leak diskspace and requiring fsck to
be performed by system administrators to recover the lost diskspace.
This was seen in both the TCL used by LDAS and the TCL shipped by Solaris 10 so
it should be a problem reported to Sun.
Reduced the amount of logging noise in the genericAPI
associated with globus calls and the number of
characters logged in the frameAPI for defunct jobs.
Corrected Frame accessor
documentation to correctly reflect the frame file objects that can be accessed
by user commands.
LDAS continues to generate RDS frames at the sites without any issues for
S5.
TCLGlOBUS
Completed testing of an additional ten Globus
FTP Control functions. 25 out of 77 functions have now been SWIG-wrapped
and tested.
Still testing and debugging Globus FTP control
data functions:
- globus_ftp_control_data_connect_read
- globus_ftp_control_data_connect_write
- globus_ftp_control_data_read
- globus_ftp_control_data_write
- globus_ftp_control_send_command
- globus_ftp_control_send_response
- globus_ftp_control_read_commands.
The above functions are for sending and retrieving raw FTP commands to and
from GSIFTP server, in this case tclproxy.ligo.caltech.edu. A test client program is able to authenticate
to the server and send LIST command, but it fails when trying to read the
response from the server. This needs more work to resolve.
OSG/GRIPHYN/IVDGL
During the SC05 conference, the LIGO VO ran with an average job rate of
roughly 5 to 10 jobs at a time on the OSG Production Grid with about half this
number of jobs in the queue idling at any given time.
The upgrade of the OSG Integration Testbed Cluster
here at Caltech was started with the operating system upgrade to Fedora Core 4
being completed late last week. The upgrade to the 0.3.0 ITB release of the OSG
software stack has not been completed yet and some rework will be required to
get a consistent installation on the head node.
The yum updates still need to be done on the nodes once the yum repository
is properly configured and exported from the gateway onto the individual worker
nodes.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Changed
archiver.cmd at LLO & CIT to be more like
the tweaked one at LHO.
- Called
in (and received) replacement T3 drives under new Sun support contract.
- Replaced
1 3510 drive.
- Ejected
tapes at LHO for shelf storage (mostly A4 L1 data).
- Have
been importing tapes arriving from sites and working on
ingestion/verification scripts.
- Heard
back from Sun vis a vis SAM ACL bug (that caused kernel panic), they think
the problem is solved in 4.4.13, but we haven't experienced any problems
since going to 4.4.5. Queried them
about that...
(Phil Ehrens)
- Refactored gpstime.tcl
module of the LDAS generic API to make it more robust against new leapsecond additions.
- Discussed
wrapping of Tcl internal file command to change behaviour of 'file delete -force' to delete files and
directories from the bottom up. Provided functional recursive example.
- Supported
the LDAS development team's analysis of hard lockup issues associated with
the use of globus-xio enabled LDAS.
- Worked
on unified grid resources documentation.
(Erik Espinoza)
- Debugging
NFS FC4-Kernel Issues, posting new bugzilla.
- Testing
fedora kernel patches on vanilla kernel.
- Working
with supermicro on IPMI issues.
- Configured
PXE Server.
- Tested
FC4 with Desktop yum repo.
- Western
Digital SATA Tests.
- Returned
Appro demo units.
- Further
digging into the Areca card, driver update resolved previous issues.
(Stuart Anderson)
- Placed
an order for the next Caltech cluster (2.2HHz 64-bit Opterons
totaling ~2.25 THz of CPU power).
- Placed
an order for 5TB of backup framebuilder disk
space (fb0) and a new 10TB cluster home directory filesystem
for LHO, LLO, and CIT.
- Dan
started the near real-time transfer of level 3 (L3) RDS frames bi-directionaly between LHO and LLO for coincident
analysis of S5 data directly at the Observatories.
- Successfully
obtained wire-speed (920MBit/s) NFS reads between 2 test Opteron machines with Erik's help.
MIT
(Keith Bayer)
- Troubleshooting
memory errors on MIT V880 dataserver box with
Sun.
- Requested
grid host keys for ldas-pcdev1 and ldas-sundev1.
Livingston
(Igor Yakushin)
- As
the weather got colder, it became apparent that there might be a
configuration problem with the air conditioner in the high bay: the colder
the weather outside, the more heat is produced by HVAC. Setting termostats'
low threshold temperature to the lowest possible 40F helped a lot but not
entirely and the temperature is still a few degrees higher than it should
be.
- Ordered
4 more spare power supplies for the nodes.
- Fixed
several configuration issues with the cluster as users discovered missing
software or accounts when trying to start online jobs.
(Dwayne Giardina)
- Replaced
disks in nodes 130 and 166.
- node126 required reboot with fsck
and is now OK.
- Replaced
failed disks in t3-8 and t3-23, received replacements from Sun.
- Reconfigured
volume on t3-13 to include u1d8 and u1d9, it has been a couple of months
since they were included.
- Shipped
tapes LL0373, LL0526, LL0544, LL0555, LL0567, LL0569, LL0573, LL0577,
LL0583, LL0604, LL0613, LL0627, LL0647, LL0656, LL0659, LL0678 to CIT
Hanford
(Ben Johnson)
- Had
to power cycle the Foundry switch this Sunday. It has not otherwise had
problems since the whole system was powered off list past September.
- D2D
and publishing started at LLO this Monday. Email is still not working
there so I am not receiving any gap reports when the framebuilder(s)
is(are) rebooted.
- Due
to ~3000 slow channels being added to the frames, the daqd
being writing corrupt trend frames (affecting both framebuilders). Removal of the channels caused the
symptom to go away. Raw frames did/do not seem to be affected.
- Shipped
9 tapes to CIT this Tuesday.
- Presently
setting up a web server so users can see their cluster output more easily.
General Computing (Wallace)
MIT
(Keith)
11/10/05
- Adjusting
wireless routers for upcoming LSC conference
- Accepting
CSR test sun box for network troubleshooting
- Ordered
scsi jbod 4bay chassis
for CAD workstation
11/17/05
- Helping
w/ visitor issues for LSC conference
- Building
dual boot system for new grad student
- Ordered
spare parts
- Added
new grad student to gc - Pranesh
Sundararajan
- Troubleshooting
wireless issues
- Adjusted
wireless hub channel in NW22
- Helped
Alex install cds utilities on FC4 box
Livingston
(Dwayne)
11/10/05
- helped
Rich Riesen with e-mail migration issues
- been tied up with LDAS,
this is all the GC I have to report this week.
11/17/05
- configured
Thunderbird e-mail client to point to new mail server on laptop for Allen
Sibley
- installed
drivers for video capture on PC for John Thacker and Outreach
- configuring a new laptop for Janeen
Romie, was initially installing everything from
scratch. after
talking with Mike Pedrazza I may swap drives
with her old laptop. This is
dependent upon some diagnostics to be run on the old drive.
- installed
perl 5.8.7 and Tk
modules on ilog.ligo-la.caltech.edu to fix errors experienced by Bruce
Sears
- applied the latest Windows updates to the laser
security server - created a weekly
CSV extract of the activity logs on the laser security server. After discussing with Shannon and Lisa,
these extracts will be copied over to the ilog
server - with Shannon,
installed new rack mounted tape library, and barcode labeled the
additional tapes
(Shannon)
- Spent
a couple of days working with and IDS/IPS/event correlation software
package. This is an open source
package that ties many tools together.
Because of its string of dependencies, it is quite and intense
install and is fairly difficult to manage.
I am concerned about this, since it is conceivable that when it
comes time to upgrade, it will be very difficult. It is possible that we could end up with
an insecure security monitoring package, which is certainly not ideal or
desirable. The software is quite
useful despite the pains in working with it.
- Worked
some with Dwayne on the new backup library. Ordered various parts, a computer for
the auditorium and a few other items.
- Going
through the alerts on the IDS console I noticed a number of sadmind probes to a DMT machine here. This is the first I have seen of sadmind probes in years. This is fairly relevant due to the
recent incident at CIT.
Hanford
(Christine)
- Helped
a user with an e-mail problem.
There was an improperly formatted message in their Inbox on the
server which prevented the user's e-mail from downloading to their e-mail
software.
- Monday
LMSI put in a trouble report to inspect the fibers between LHO and PNNL
which will be used for our backup network.
There has been no further status from them.
- Investigated
upgrades to the main switch for the internal network. The upgrades will be needed so the new
phone system can use the switch.
- Still
working on getting the Cisco contract problems resolved.
- Still
working on making the AMD Solaris 10 computer a NIS+ client.
- Still
working on building an updated application server.
CIT
(Bruce Sears)
11/10/05
- Ilog Maintenance: Added users and fixed a problem I
caused when doing so at LLO and LHO.
11/17/05
- Fixed
a bug iLog has in which quote characters were
corrupting the title and comment text when the Replace function was being
used.
(Veronica)
- LIGO: Website updates for the NSF review. Based on the database of the LSC
affiliates, prepared a report for David Shoemaker on the affiliation of
the members. Other misc. user
support during the review. Assisted
Larry in the disassembly of the 114 E. Bridge setup. Burned several DVDs of the film about
LIGO, to be shown to the review committee.
Installed latest patches on Win servers. Updates to the LIGO website.
- LSC: Updates to the website of the upcoming
meeting. Updates to the database of
LSC documents for review. Updates
of various mailing lists.
- CaJAGWR: Video
stream of the last seminar. Website
updates.
(Christian)
- Ghosted
workstations for Cindy, Julie, Dot and Florence.
- Linda
Turner - Linda was having problems printing her PowerPoint presentation in
a HP network printer this week. Linda was using HP PCL 6 drivers to print
and every time she would try to print her presentation, she would get an
"Illegal Attribute Value" message. After working on it for some
time, the only driver that Larry and I can get to work was the HP PCL 5c.
- I've
started to update users who have X-Terminator V4 to V5.
- I
went through and labeled PCs' with the current CPU and Ram speed in the
basement storage.
- I
also moved locations this week to the office right next to Mike -Other misc.:
Continued onsite software/phone support.
(Mike)
- NSF
Review: Helped out with setting up a temporary wireless network and
printer.
- David
Meyers: Installed Linux on a loaner laptop for him to take on travel.
- Dennis
Coyne: Sent his laptop to IBM for repairs. Dump a GC ghost image to a new
laptop for him. I also installed many additional Engineering packages,
plus restored his data.
- Worked
on loading a sun box to replace DHCP server for the 125 subnet.
- Loading
a LINUX box for Hiro's group.
- Continued
work on the Spam Filters searching for false positives.
- DHCP
114 Subnet: Freeing up IP numbers that should be releasing automatically.
For now this is being done manually.
- Other
misc. onsite/phone user support.
(Larry)
- Helped
out with the setup and logistical support for the NSF review. We had a few more technical problems
than we have had in the past. Mostly bad cables but the printer also
needed to be replaced in order to accommodate the MAC units. Overall things went well.
- Placed
a number of orders of equipment for other groups as well as GC
support. The Blade1500 for the 40M
has arrived and the OS is being installed.
Most of the items for LDAS have been received and picked up. Renewed the licenses for the CANIT and Matlab.
Reconciled p-card for the month. Still working on getting tax
charges put on from different companies.
- Still
cleaning out and replacing old equipment.
- Added
a number of new accounts and cleaned up a couple of alias files.
- Worked
with Linda in getting a number of DCC items resolved. The biggest issue
was getting a file to print. It took Christian and me some time to fix the
problem by using and older print driver.
Still working on getting the h/w in for the new DCC system.
- Resolved
a couple of backup issues. Setting
up a new system for the monthly backups. Hopefully, it will be up and
running for this months monthly backup.
- Worked
with Mike on setting up a new dhcp server.
- Worked
on a number of patch updates on different sandbox units. Now installing Fedora Core 4 on the quad
cpu dual core units.
Thanks to Erik the OS is now installing but there are still a few problems
to overcome. Even though the SUSE
installation for these boxes is cleaner we are still going to the FC4
installation for compatibility reasons.
- Typical
user assistance and account modifications.
- Still
working the e-mail spamming issues.
Mail Statistics for Nov 03-16, 05
|
Mail Statistics
|
November 03 - 16, 2005
|
|
Rejected Messages
|
25,558
|
|
Virus Messages
|
1,861
|
|
Accepted Messages
|
30,712
|
|
Total Messages
|
56,270
|
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Systems, Management
from Dennis
Coyne
See also:
AL
Systems web page
AL Systems email
archives
Records of Decision or Agreement (RODA)
See also the RODA status web page
- Tim
Hayler (RAL) has submitted a revised RODA on
chain separation, M050418-01, which is under review.
Requirements
- Cleaning
requirements for in-vacuum hardware have been re-formulated in terms of an
industry standard specification, IEST-STD-CC1246D, Product Cleanliness
Levels and Contamination Control Program [Note: This document supersedes
MIL-STD-1246C], for particulates and non-volatile residues (NVR). See for
example G050557-00.
Interface Issues
See the "Interfaces" section of the AL Systems web page
- Nothing
significant to report
Vacuum Compatibility
Residual Gas Assay (RGA)
See also the Vacuum Bake Lab
Bob Taylor
- I
have completed two bake jobs for Calum for the
SUS quad control prototype.
- I
have have four Bake jobs going at the present
time, 3 for calum and one for the RGA test to
correlate to FTIR measurements on post air baked parts (two parts from the
set of large LASTI parts from Myron).
- Lee
and I have been cleaning more quad parts to bake as soon as there are
ovens available.
- I
have ordered all the parts for the SUS quad controls prototype ESD cables
and will assemble those as soon as the part arrive.
- I
have all the SUS OSEM diode boards built and will start assembling them On
Friday.
- I
have shipped the first of Myron's LASTI solid stack parts. Lee and I will
pack the Large Parts to be shipped to Myron this afternoon.
High-Irradiance, Contamination-Exposure Cavities
Lee Cardenas, Liyuan Zhang
|
Cavity
(Location)
|
Material/Item
|
Start
|
End
|
Comments
|
|
Cavity #1
(OTF Lab,
Bridge)
|
“Coil wire” (material type?)
|
~11/17
|
TBD
|
New sample has been put into the cavity and the system is
pumping down. Going through a re-alignment now.
----------------------------------------------------------
The test for 40 pieces of MMG nickel plated Nd-B-Fe magnets (for Helena Armandula,
SUS ) has been completed and removed from the
cavity.
|
|
Cavity #2
(OTF
Lab, Lauritsen)
|
NA
|
NA
|
NA
|
No
Change
cavity is close to being ready for samples
|
|
Cavity #3
(OTF
Lab, Lauritsen)
|
OSEM Flexi-circuit cable,
qty ~ 45
(Helena Armandula,
SUS)
supplied by Univ. Birmingham (Stuart Aston)
|
~6/10
|
~9/10
|
No change:
taking daily absorption & ring down measurements
DuPont Flexible Circuits. The whole part to be
constructed of 'flexi' i.e. no 'rigid' sections. (Stuart Aston,Univ. of Birmingham, SUS/UK subsystem)
- Start Laminate: Kapton (LF8515)
(document link: http://www.dupont.com/fcm/products/H-73244.pdf
Coverlay (x2): Kapton
(LF0110)
(document link: http://www.dupont.com/fcm/products/H-73245.pdf
DuPont Pyralux
Series - Kapton / Acrylic Adhesive system.
(document link: http://www.dupont.com/fcm/products/H-73246.pdf
--------------------------------------------------------------
OSEM
emitter & photodiode 40 of each, (Dennis Coyne, SUS
) Test has been completed. Results to be posted by Liyuan
Zhang soon.
|
|
Queue
Priority 1
|
2 Cleaned 50ppm transmission mirrors, 1 in dia., REO coated --
|
TBD
|
TBD
|
witness samples for the LHO vertex volume (added in
6/29/2005 vent)
|
|
Queue
Priority 2
|
Stepper
Motor (Riccardo DeSalvo,
possible SUS or ISC use)
|
TBD
|
TBD
|
Stepper Motor sample had been placed
into Cavity #1: Power dropped from 175 mW to ~25 mW after introducing the stepper motor sample, and
continues to decrease. It is very hard to keep cavity locked. The stepper
motor may have contaminated the mirrors. Will re-test when a cvity becomes available again.
To be rebaked soon using the self-heating capability of the
stepper motor (not just the oven heater controls)
|
From: Rolf Bork
<rolf@ligo.caltech.edu>
The quad front end, Framebuilder and TP man are now
working together over the new network. We still have work to do to get AWG
fully functional. The idea is that the front end code, a TP man and AWG will
all run together on each front end control computer. As a test, we ran all
these, plus Framebuilder on our dual AMD64 computer,
and they all worked fine together. The processors barely noticed the load.
While the Framebuilder will be separate at Lasti (due to multiple systems needing to access it and to
merge the data together), this would be a good configuration for test stands or
small lab setups. It would only involve a single computer box at a relatively
low cost ($10-15K, depending on number of I/O channels and disk drives for the Framebuilder).
Worked further on the front end code to get Tp/Exc
channels working and the drivers to detect and configure multiple I/O cards.
The code is being written a bit differently this time around. There are still
the basic generic modules for I/O, DAQ and GDS, somewhat as before. However,
the code for the front end is developed as a "skeleton", that is it
is genernic for all front end applications. It
handles all the calls to I/O code, synchronization, network monitoring and
error correction, DAQ/GDS calls, etc. The call to the application specific code
is then simply placed in the this generic code's
control loop. So, the skeleton takes care of all system initialization, then goes into a synchronized infinite loop. In this loop,
it reads out the ADC channels at the proper time, checks for overflows and
other errors, then calls the application specific code
with this ADC information. The application code then does all it's specific
control algorithms, filter modules calcs, etc., and
returns the DAC output values. The skeleton then packages and sends out the DAC
values to I/O, calls the DAQ/GDS functions, moves EPICS variables, does various
network and other error checking, then returns to the beginning of the loop.
This method should improve things in a couple of ways. One, new applications
should be quicker to develop, as the skeleton software takes care of all the
"systematics". Plus, once I get back to the
graphical editor for front end software, it will only need to generate the
application specific code. Secondly, as we add features to the skeleton and/or
make it more rebust, it should allow these changes to
be easily recompiled into all front ends.
Seismic Isolation
From: Ken Mason
<kmason@ligo.mit.edu>
From: "Joseph A.
Giaime" jgiaime@ligo.phys.lsu.edu
Agenda for the weekly SEI telecom
Friday, Nov 9, 2pm Eastern, 1pm central, 11am Pacific time
Announcements
- HAM
SAS mechanical contract bids are in.
Carol is planning a procurement readiness review after
Thanksgiving.
BSC SEI status, Ken/ Dennis
- We
are reminded that solution anneal according to the metal supplier's specs
must precede the machining. Ken is
to author a LIGO E document that details the required material processing
steps.
- Ken
has been working with ASI on the topic of blade design changes.
- Ken
has built the blade test fixture, and has some dummy test blades.
- Jay
visited Ken at MIT and they have gone over the feedthrough
and wiring harness designs. There
is a question about whether the wire quotes from Larry are correct; we
should have round cables with twisted pairs, not ribbon cables.
BSC work, adaptive modeling and FIR (Rich M)
- Results
of simulink model of adaptive FIR filter are
posted here. Rich is running the
adaptive FIR generator and asking it to fit a fake plant made with a stable
zpk filter.
Rich also will try to hand the adaptive filter generator a pre-made
more perfect FIR to see whether it can adapt with plant changes. Rich hopes to have it running on hardware
in a week or two.
HAM control with VME (Pradeep)
- Two
vertical geophones and one horizontal signals are
not working. The horizontal was
'fixed' by knocking on it. We need
to evaluate other geophone models.
ETF platform work - Matt DeGree
- Brian
has recovered most but not all critical files and now have
a working experiment control computer (set up by William last
summer). Missing the alignment
matrix and FIR definitions; these will be regenerated with Hua's help, and Stanford will also send the busted
disk out for data recovery.
- Now
using the newer dSpace hardware, too. Now using 400 µs sample time. I/O takes 80 µs. 53 µs used for non-polyphase-FIR
filter. Lots of time left.
- Quad
pendulum frame received from Caltech yesterday. May be installed the week after
Thanksgiving.
Seismometer work, therman
monitor project.
- Rotational
seismometer parts received from shop, and assembly is under way by Aaron.
- William
continues assembling in-vac cables for thermal
monitor project. (he is working 6 hr/week.) First task is to assemble monitors on a
very small test block in an insulated box to make sure that calibration,
noise and drift are understood.
Other news?
- Shyang is shipping the broken STS-2 to Jay.
Suspension
From: Janeen Romie
romie_j@ligo.caltech.edu
Advanced LIGO
Working with Caroline and Calum
on understanding the gazebo's input to the quad suspension mode measurements.
Creating gazebo models for Calum to perform fea (as I do not currently have fea
software available.) Dwayne is loading software on my new laptop.
Working on ECD alignment parts.
Working with Jay and Dwight on costing issues for Advanced
LIGO suspensions production phase.
From: Calum Torrie
<ctorrie@ligo.caltech.edu>
From: Ken Mailand
kmailand@ligo.caltech.edu
I have finished a preliminary SUS installation plate style fixture layout
for Calum, and estimating cost and time, this is an an alternate to the air bearing using the same table frame,
or the genie lift.
We talked with Oddvar re. the
air bearing design, and the alt. style fixture, he inquired about some of the
features, and thought it could do what the spec. requires.
I’m working on a vertex BSC layout for Mike Smith that will show stay
clear areas inside for the beam path, and gathering P O Telescopes details.
From: Helena Armandula
ahelena@ligo.caltech.edu
Adv. LIGO SUS - New air bake oven
From: Jay Heefner <jay@ligo.caltech.edu>
AdL SUS
From: Rolf Bork <rolf@ligo.caltech.edu>
Core Optics
From: Bill Kells <kells@ligo.caltech.edu>
Last week was spent mostly preparing for and attending the NSF review.
Since, I have been using that as a springboard for finishing off a review of
yet another verison of the Perth PI paper that I have been
"tasked" to since mid summer. It’s getting much more
reasonable! I have transmitted some further questions to Ju
Li about their analysis, to be able to turn this around.
This week I have been going back over the details of what I had worked out
almost a year ago on the concept of a stable PRC/SRC for AdL.
Have done a bunch more modeling and put everything together in preparation for
the meeting on this at MIT this Friday.
See you there!
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
I finally finished packaging the hour meter circuit for the NPRO. Testing of the circuit showed that the
variable threshold levels and trigger points were within tolerance levels. Although there is a nasty two-step behaviour in the falltime
response. Since this occurs in less than
0.6 microseconds I don't expect it to cause too many problems.
Auxiliary Optics
From: Michael Smith <smith@ligo.caltech.edu>
I resolved the problem and have traced rays and have inserted stay clear
models of the ITMx and ITMy
SUS, a BS SUS, PO mirror BS SUS, PO mirror ITMx SUS, cavity beam dumps and HAM and BSC chambers into
the ZEMAX layout of the ADLIGO vertex. Unfortunately, ZEMAX does not support
the export of the cylindrical object I used to model the COC mirrors with the
current revision, so I can't export the ray trace to the Solid Works CAD
program. I will try to find an exportable object for modeling the COC mirrors.
Other Laboratory R&D
From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>
Juri
I worked on my FFT code; I added a routine in order to make a scan of the
cavity through a full FSR and another to find the position and the amplitude of
the power peaks. In this way it is easier to select the point where we want to
lock the FP cavity.
Yumei
I am starting learning how to use the ANSYS and practice simple program by
ANSYS.
Chiara
I made the measurements of transfer function for the system with four
inverted pendula in the range from 0.2Hz to 100Hz.
I started with a load of 624Kg and I arrived at 2006Kg.
Below 10Hz the measurements are good; I found the expected behavior of the
function. Above 10Hz there are several picks that we identified as
environmental noise (the same visible on the quadruple pendulum) and resonances
from the structure of the shaker.
For additional information about this report, contact Stan Whitcomb or Phil Lindquist