Weekly Report for
Week Ending November 3, 2005
The LIGO Executive
Committee Agenda for Monday November
7, 2005 will be:
(Meeting time: 10:30 am Pacific Time)
1. Announcements
2. Comments
on Weekly Report
3. LSC
Issues (Saulson)
4. LIGO
Lab Operations
- Administration
(Lindquist)
- Sites
(Raab, Zucker, Shoemaker)
- Commissioning
(Fritschel), Detector (Coyne)
- Campus
Research Facilities
- 40
Meter (Weinstein)
- TN,
( Libbrecht)
- LASTI (Shoemaker)
- Data
Analysis and Computing (Lazzarini)
5. R&D
and Advanced LIGO (Shoemaker)
6. CHANGE CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION AS
NEEDED
Special Items:
Special Announcements:
Weekly
Report Highlights
No report
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
Non-LSC MOUs (Lloyd)
SITE TELECONFERENCE (Lindquist)
- A
site teleconference was held Thursday, November 3, 2005. The following issues were discussed:
- Financial
Tracking Report – The FY 2005 reports have been published for
the end of October. We remain on
course for expected carry forward of $6.9 million after adjustments to
reflect LDAS acquisitions.
- Transfer
of AC Equipment – Moving companies have been contacted to move
the AC equipment from Hanford
to MIT. Expect move to occur next
week. May want to disassemble unit
because of height. J. Worden
reports that outside condenser has been moved into shipping and receiving
in preparation for move.
- Speed
Limit during S5 – The speed limit will be reduced at Livingston for the S5 run. The gate will be closed during S5. Contractors will be admitted by
appointment.
- The
list of assigned actions updated through November 3, 2005 will be found Here.
- No meeting next week (November 10) due
to NSF Review.
PROPERTY MANAGEMENT (Chargois)
>From: Ed Chargois <chargois_e@ligo.caltech.edu>
- Provided
assistance to the Detector Group (H. Armandula) arranging the
relocation of three (3) Optic Transit Cases and one (1) Optic Case insert,
from the Synchrotron Hi-Bay to Bridge OTF lab.
- Provided
assistance to the Director's Office, with packing and shipping of one (1)
Laptop computer and two LCD Projectors to MIT (M. Woods) in support of the
upcoming LSC. Account Number
P204198.
- Provided
assistance to the Detector Group (H. Armandula)
by preparing US
Customs Documentation (Commercial Invoice and FedEx Shipment) for Synthetic Sensor to RAL,
attn : Mr. Ian Wilmut. Account Number P204317.
- Note: Researching the most economical way to
transport the 5-ton Air Conditioner from LHO to MIT.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
- The
contract for the new Document Management System was prepared almost three
weeks ago, was sent to FileHold for signature,
and was returned to us. On Tuesday
Ruth approved it, and a purchase order was generated. Payment of the invoice from FileHold for the software was processed yesterday. FileHold
should receive this on Monday or Tuesday.
They will then ship the software for installation on the server. Meanwhile the hardware has been ordered
and will hopefully be here and configured by the end of November.
- I
am hoping to have a chance to look over the software manuals before
leaving for Boston
(or take them with me)..
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- Update
on Scanning Project - Progress continues on Larry Jones' boxes of
files. To date, we have 7 of the 16
boxes scanned.
- Activity:
|
Week Ending
11/03/2005
|
In
|
Out
|
|
Packages
|
28
|
8
|
|
Faxes
|
15
|
34
|
FINANCIAL SYSTEMS (Cronin, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Completed
the new subcontract for Limerick and have
routed it for approvals.
- Working
on the change order to Triad.
- Working
on the rent check for the visitor. There have been complications.
- Looking
into taxability of the professional services for the custom computer
changes order to Filehold.
- Responding
to invoice issues on tax being charged on orders for Livingston
that are not taxable.
- MIT
is still in routing in Procurement.
Received the current A-133 and included it in the package.
- Submitted
my monthly statistical reports. Closed out the blanket purchase orders.
>From: Florence Kaufman <fkaufman>
- Monthly
report for FY2005 Operations, FY2006 Operations and the
Outreach Award have been prepared and are posted on the network.
- Submitted
three Cost Transfers to correct the allocation of telephone conference
charges to various task numbers.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone
<gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow
<jasnow@ligo.caltech.edu>
- Resolution
has been reached with Eskew-Dumez-Ripple, the
architect for the LLO
Science Education
Center, concerning
their fee for increased construction management costs. The fee will be increased by the
percentage difference of the original estimated cost of the building and
the contracted cost.
- The
construction contractor for the LLO SEC, Cangelosi-Ward,
has submitted construction schedule.
This schedule is being reviewed to determine the impact on S5.
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
- Processed
the paper work for sixteen (16) new/revised trips. At this time there are three (3) trips
completed or in the works but are awaiting the necessary paper work to
enter the P-Card system.
- Completed
ten (10) Expense Reports and there zero (0) reports yet to be done. I continue to contact travelers who have
outstanding Expense Reports (more than one (1) month old) to ask for their
cooperation in sending me their receipts so that these can be closed in a
timely manner. Presently there zero
(0) reports more than thirty (30) days old.
>
>Dorothy Lloyd
- Processed
the usual invoices for payment and followed up on problems. Reviewed and
recorded invoice payments for the month of October.
- Worked
with Ruth in closing out blanket orders by adjusting receipts as needed.
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
PROPOSALS and REPORTS (Lindquist)
We have received the first half of our funding for FY 2006. We have provided the Office of Sponsored
Research with a “resume” indicating the proposed distribution of
funds to LIGO accounts.
DCC Steering Committee (Lindquist)
See above (Linda Turner) for information regarding
contract.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- No special activities to report.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of
Commissioning Activities at LIGO Hanford
Observatory (compiled by M. Landry)
S5 began at 8am Pacific on Friday 4th. Leading
into the run, neither IFO was in a fully optimized state. H2 was locking
with binary inspiral ranges in excess of 4Mpc but
suffering from glitches, while H1 spent most of the week unlocked. Work
is underway to improve the 4k locking and stability, including mitigating
glitches on the RF distribution system and a swapping of the SPOB photodiode
(both links to elogs available below).
Commissioning highlights are bulleted below:
- dust levels have been found to be high
when we employ a hamster house on 2k and 4k antisymmetric
ports, but turn off the purge air fan. Dust levels were also
observed to ratchet
up during lock loss. The theory that contamination, possibly
oil, on razor-blade beam dumps is burn-off during lock loss appears to hold
together.
- new
timing ramps and IRIG B signals were tested and working
- an
annoying test of a DMT monitor: recently, a plane has been buzzing
EY, and observed with PlaneMon
- provisional S5 DC calibrations in simple MICH and single-arm
configurations were performed on both interferometers. More
calibration measurements including frequency sweeps are planned neared the
beginning of the run
- a (remote) vault seismometer has been added to the
frames; we may finally understand our problem with wind and locking, i.e.
does the wind shake the buildings and disallow locking, or does it shake
the earth which shakes the slab?
4K IFO
- a PEPI-like feedback servo was designed
for the 4k using STS-2 seismometers mounted on crossbeams, feeding back to
the fine actuators. The loop clearly suppresses the error point, but
we've not yet investigated the effects on the spectrum of the fully-powered
up IFO
- SPOB
glitching was ultimately found to be due to the RF
distribution
- ASPD3
was found to be saturating
and limiting the 4k binary inspiral range.
The photodiode shows larger noise than the other three on the AS
port. Later, the photodiode's performance inexplicably improved
for a time.
- 1/2"
mirrors swapped
out for REO versions, and the SPOB diode was found to be
non-uniform, leading to its replacement
2K IFO
- clipping
was reduced
on the WFS3 REFL path
- optical
levers were trended,
and some found to be tanking
so that they were replaced
- the new fiber-based timing system was installed and
tested on the 2k. The system is based on a clock in the mass storage
room, with fiber distribution system to the LVEA and mid stations. Comparisons
with a portable rubidium clock were made and the system checked out well.
More on comparitors
here.
DAQ
- the
new excitation AWG configuration is summarized
- test point problems
and framebuilder instability caused some delays
this week in commissioning and calibration
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
L1 Interferometer (Frolov)
After another week of round o'clock commissioning, interferometer inspiral range improved to 10.5 Mpc.
Long lock stretches lasting up to several hours were achieved during night
time. The commissioning efforts were mainly directed on tuning the digital and
analog suspension filters as well as on improving the sensing chain electronics
noise and filtering.
There was a minor setback on Monday when large excess noise appeared in the
interferometer spectrum from an suspected intermittent
cable connection in one of the wave front sensors. As often happens with
intermittent problems, the excess noise disappeared in the process of examining
and wiggling the cables.
The laser power into the interferometer remains at the below-nominal level
of 5 W despite several attempts to increase the output of the laser and the
transmission through the PSL optical table.
Resonant gain filters were installed and tested on all BSC HEPI chambers.
The effect was a reduction of the noise by as much as a factor of seven in the
1 to 3 Hz band in many of the interferometer signals, including DARM, ASI, REFLI.
CDS (Bogue)
- Tweaked
my jumpstart configuration and began jumpstarting the control room
machines.
- Still
working on the RMA of the atomic clock.
- Dropped
new code from D. Sigg for awg.
- Installed
the dvd robot on lloscript. The
drivers are working but I need new license keys before I can begin
programming it.
- Created
a short list of files for nightly permanent archive (based on Dave's list
from Hanford)
and began doing a nightly permanent archive.
- General
commissioning support.
Computing and Network Security (Roddy)
- The
new mail server seems to be working well.
There are the usual user migration issues, but those seem to be
mostly taken care of now.
- This
week has mostly been spent wrapping up the last bits of the server swap.
- The
new tape backup hardware is in and I started unpacking it and getting it
ready to install.
- Installed
a new foundry switch in the rack to replace our Dell switch in the
CUR. Needs to be configured and put
in use.
CDS Code Support (Khan)
no report
Education and Outreach (Thacker)
no report
Site Safety and Security (Riesen)
no report
General Computing (Giardina)
- helped
Rich Riesen with email migration issues
- been tied up with LDAS,
this is all the GC I have to report this week.
AdL SUS/SE Mechanical Engineering (Spjeld)
Quad SUS Installation Fixtures
- assembly
drawings nearly complete (80%), will send to Calum
over the weekend
- attempted
to upload files to PDMWorks, but was unable to
submit SW models and assemblies, will send a CD-ROM to Calum
instead
- following
up on linear drives correspondance to provide Calum with supplier information
LDAS/Condor and data analysis (Yakushin):
*It's a girl!!*
LDAS Admin (Giardina)
- this
spans more than just the past week, but I didn't report it until
completed:
replaced disks in nodes 7,
8, 18, 20, 23, 26, 28, 38, 60, 63, 64, 78, 84, 101, 107, 111, 113, 121, 125, 128,
134, 137, 139, 154, 161, 166, 182, 183.
This was mostly finished prior to FC4 upgrade.
- nodes
61,81,122,138,184,205,210 were not upgraded due to problems with disk, cdrom, or power supply
replaced power supply in
node122, and then used cloned disks in all to complete upgrade.
- Shipped
tapes LL0426,LL0520,LL0639,LL0509,LL0521,LL0535,LL0633 and LL0637 to Dan Kozak at CIT
- node48 was DOA upon visual inspection. replaced power
supply and all is well.
I used the last remaining spare power supply in
node48, need to order a couple extra to keep on hand.
*** ALL nodes 1-210 at LLO are FC4 and, at
the time of this email, are up and running. Node2 is currently used as ldas-gridmon
and is not part of Condor (per note from Igor)
- revamped a couple scripts that will run starting at
00:00 on Sat, Sun, and Mon to check the nodes for badblocks
and email status to myself and Igor.
It will check 70 nodes per run.
- we have a metric boatload
of Maxtor disks that are still under warranty and I will RMA them today or
tomorrow.
Initial LIGO Detector Science & Engineering (Coyne)
No report.
40-Meter Interferometer (Weinstein)
Osamu gave a LIGO/Caltech seminar on the Optical spring and optical
resonance in the 40m Detuned RSE interferometer, on November 1. G050568: ppt, pdf.
IFO commissioning:
- Osamu
measured the optical gain of the X arm. The xarm
cavity pole appears to be at 2.8 kHz, not the spec of 1.6 kHz. Osamu
believes this is due to analog whitening and/or anti-aliasing filters, not
the actual optical response. Using this assumption, he extracts the
effective response of the analog filters and applies this to get the
optical response of the full optical configuration. This agrees very well
with the theoretical expectation, lending credence to the assumption.
- Rob
has outlined a variety of alternative procedures for bringing the
interferometer from no-control to full-control in a
"deterministic" procedure (ie, no
waiting for the mirrors to swing into resonance and the servos to
"catch"); AKA "no-bang" locking. He tried one of the
simplest methods, with some success.
- Two
paths have been forged to acquire lock and control the interferometer, one
by Osamu and the other by Rob, Rana, and Matt.
All interested parties will work together to forge one
"official" length sensing and control front end code, and one
set of lock acquisition and control scripts. We also all agreed to make
good use of the ilog and the new 40m Wiki.
- Dan
measured the oplev noise spectra with the loops
on and off, in an attempt to identify excess noise as the stack
frequencies due to oplev folding mirrors on the
stack optical tables. There does seem to be a noticable
effect, but it is not large; so, for now, we do not plan any major effort
to get the folding mirrors off of the stack optical tables.
- Dan,
Monica and Osamu are going through the calibration of the noise spectrum.
Osamu notes that the optical response function at the 40m is considerably
more complicated than at the sites due to the RSE and optical spring
resonances, so the calibration must be done with more care. We will need
to carefully measure the analog electronics in front of the A/D and after
the D/A.
IFO modeling:
- Monica
has implemented Hiro's new dual-recycling
summation cavity in her e2e model, and is busy debugging it. She will
focus her work on the main goal of learning how to extrpolate
from 40m to AdLIGO.
- Hiro has used his new dual-recycling summation cavity
to make a prediction for the location of the optical spring at the 40m,
with two different power levels. It seems to agree well
(semi-quantitatively) with our measured spectrum.
DC detection development:
- Steve
ordered and received two HR supermirrors from Newport for the
output mode cleaner. He and Liyuan measured the
mirror transmittance at 0degrees: one was T=0.08%, other was 0.2%. Steve
sent te worse one back,
with a promise that they'll replace it with a better one.
- Mike
Smith made some corrections to the OMC and OMMT drawing packages that were
released to the DCC. Many of the parts for the OMMT have been received.
Mike is scribing numbers on the parts and is in the process of
pre-assembly.
Electronics, controls
- Dan
is going through the scripts used to diagonalize
the mode cleaner suspensions, tweaking them to get excitations right.
- Our
RAID disk array for storing frames went belly up on Friday. On Monday,
Alex uploaded new firmware to the RaidWeb RAID
array and it works now. No frames were logged from Oct 28 15:59 -to- Oct
31 11:59, 814575568 -to- 814823984, and minute trend frames for a small number
of channels were lost.
- Our
RAID disk array for storing frames is dying. We are looking into getting a
replacement, and also getting a fiber link to the disk/tape archive system
at CACR. In the meantime, we need to back up all of our trend frames, BURT
snapshots, conlog database, etc, before we lose
them.
- Larry
Wallace is getting us a new Sun Blade 1500 to use as a badly-needed fully-functioning
operator console.
- Ben
and Rana are discussing the DC photodiode in-vac electronics. A prototype is being prepared. They
are looking for suitable vacuum-compatible resistors. He's also working on
the mechanical mounts.
- Ben
is also working on getting new RF PDs for us,
and also new fast mechanical shutters.
- A
new common mode servo board (Sigg design) is,
supposedly, "in the mail" from LHO. We look forward to it!
Lab Infrastructure
- The
STACIS seismic pre-isolators are not useful. Several months ago, Steve
shorted out the ones supporting the ITMX and ETMX chambers. He has now
done the same for ITMY and ETMY chambers.
- Rob
set up a new online 40m Wiki to post things like
To-do lists, procedures, etc. This is NOT a replacement for the ilog!!
- Rob
assembled many months of vacuum RGA spectra into a "movie".
Steve gives it two thumbs up.
- A
new (spare) Osaka
maglev turbo pump has been received. Our main maglev turbo pump is more
than 10 years old, and is showing signs of impending death.
- Steve has a setup for measuring ringdown
frequencies, using a phonograph needle.
Thermal Noise Interferometer (Black)
No report.
LASTI (Ottaway)
No report.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
Weekly E2E Physics Meeting
Sany Yoshida talked about simulation of Mode
Cleaner and its misalignments. Hiro described how e2e
has been used to simulate Optical Spring effect in Advanced LIGO
interferometer.
e2e-3.0.4
(Hiro) A few more bug fixed version of e2e were
released, now e2e-3.0.4. The e2e
Primitive manual is updated to include new primitives and change of features
(still underway). Optical Spring of 40m
was simulated to show that the basic ingredients are in the e2e framework.
Simulation of 40m Advanced Interferometer
(Monica) Two e2e packages for the 40m are now available, the usual one
(including the modal model) and a new one in which the dual summation cavity
(only plane wave approximation) has been implemented. Basically, for future
simulation purposes (optical springs effect and
locking strategies) the more recent package will be used: the simulation time
increased by a factor 10.
FFT studies
(Biplab) Had discussion with Bob
Spero on diffraction loss calculation.
He used his code to validate my results for the proposed AdvLIGO arm cavity. Similarly, I used my Matlab code to validate his results for a cavity with
mirrors of 2667m radius-of-curvature and g-factor=0.5 (for the proposed cavity,
these numbers are 2076m and 0.92). This new cavity may not be of consideration
for AdvLIGO because of its still small beam-size at mirrors (~4cm), but
this is an interesting case for
calculation of diffraction loss -- in this case the truncated Gaussian
approximation for loss calculation overestimates the actual loss calculated in
a numerically rigorous way, while in the proposed cavity or LIGO-I cavity the
reverse is true.
Alfi
(Bruce) Reworking the error reporting methodology to give more control to
the user and prevent multiple error dialogs from
swamping the user if there is a bad load (Problem Report 476 (related))
(Melody) Worked on a new feature to swap different nodes without removing the
connections (PR 280). Working
on PR 296 - easier access to settings.
Data Analysis Activities (Lazzarini)
Mandic:
I made a calculation estimating the stochastic background of GW that would
be generated by the population of LMXBs in the
Universe. The generation mechanism is density non-uniformity of a spining neutron star (caused by accretion from the white
dwarf), so the signal is expected to appear in the LIGO band. The calculation
is not complete yet, but the first results indicate that the signal is very
small, likely undetectable even by AdvLIGO.
I also worked on preparing the hardware injection code and waveforms for S5.
Mendell:
I will start generating SFT for S5 soon after the run starts. This will be
done by submitting condor DAGs by hand until I get
this working with onasys. There is also a memory
issue to sort out in the MakeSFT code, though this is
not a show stopper. I am also continuing with StackSlide
code reviews and preparations to produce results on the S4 data for the
November LSC meeting. At the last review we went over new validations of the StackSlide Monte Carlo Simulations; a report is posted on
the protected pulsar investigations page: http://www.lsc-group.phys.uwm.edu/cgi-bin/enote.pl?nb=puls4stackslide&action=view&page=10
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS
LDAS release 1.8.0 was deployed to CIT, LLO and LHO this week to support the
hardware upgrades to Solaris 10 and Fedora Core4 and to support the start of
the S5 science run. This release now has support for X.509 certificates for
authentication in both the managerAPI and the controlMonitorAPI's server. Currently only the LDAS controlMonitorAPI client has been developed to take
advantage of this new grid technology, but with the availability of the Tcl- Globus package others such
as GUILD and LIGOTools should soon be able to use
this method of authentication with LDAS.
There was an issue with 9 system test unexpectedly failing to recast *.tmp frame files into *.gwf frame
files that was traced to a missing rename() function
call in TCL code over the weekend. This
was fixed and made part of the 1.8.0 release. There still remains
6 other regression tests failing with a similar problem that has been around
since the migration to Solaris 10 which will need further analysis to resolve.
On Wednesday of this week an issue with LDAS Tcl
code applying the January 2006 leapsecond now to the
labeling of GPS times in LDAS log files was discovered. A fix for this has been
found and we will be patching the LDAS system today. This does not effect any frame output products.
Weekend runs of createRDS frame generation at LLO
and LHO are showing only a 1.5 times realtime RDS
frame generation margin. This is due to
the increase in size for the S5 frames, the addition of a Level 4 RDS and
increased load on the dataserver by non-LDAS
applications demanding file services. A close watch will be needed once data
analysis starts using these servers to assure that the RDS frames are generated
in a timely manor. (This has been reported at both the DASWG and S5 Run
Planning Meetings).
TCLGLOBUS
The version 0.3.0 of TclGlobus was released this
week to the larger LSC community (it had already been released internally for
LDAS). The community release also
utilizes the LDG 3.5 client software for its source of Globus
and is distributed as LSCSoft compatible RPMs for FC3 and FC4 (it is distributed under LDCG for LDAS
use).
Documentation on the TclGlobus website was also
updated to support the use of these RPMs by the LSC
community with simple test programs for use in validating installation onto of
LDG 3.5.
OSG/GriPhyN/iVDGL
The binary inspiral search code has now been
successfully run on four different OSG Production sites. Two of these are
within the LIGO VO (UWM and PSU). The other two are both part of CMS (Caltech
and Nebraska).
We have also attempted to run at San
Diego but there are issues with using the
job-fork-manager and disk space that are preventing the successful running of
the code there.
The binary inspiral search code has also been
unsuccessfully tested on an OSG 0.3.0 software stack system at Florida State University. More information is needed to resolve the
issues running there.
The bulk of the effort on OSG this week has been toward participating in the
Super Computing 2005 demostration. All OSG VOs with OSG based applications have been asked to get as
many jobs running on the system as possible and to assure that the monitoring tools
are reporting the staging and running of these jobs. A number of accounting
issues were discovered as part of this preparation. UWM and PSU had userID issues with the configuration of unix user which prevented LIGO jobs from being
counted there. There remains an issue at UWM reporting to the MonALISA monitoring system even after the userID problem was fixed.
This is still being tracked down but mostlikely
an issue with the configuration of ganglia there.
The LIGO CIT Integration Testbed remains at OSG
software stack level 0.2.1. The effort in support of the SC05 demonstration has
left no time available to upgrade until after the meeting next week. However,
the system's OS was updated through yum update to have the latest patches.
Hardware Systems (Anderson)
LDAS System Administration
Caltech
(Dan Kozak)
- Worked
with Steffen to get CIT's LDR to recognize his certs.
- Combined
grid-mapfiles for LSCdataFind
and LSCsegFind everywhere.
- Isolated
tape drive problem at CIT (57 was failing, but not being marked down).
- Finished
repacking M7 tapes at LHO.
- Validated
M7/M8 L1/L3 data and found a couple of files that hadn't been published.
- Did
lots of work on the "eject tapes at the sites" script.
- Actually
did eject tapes at LLO and had Dwayne ship them. Imported and verified at CIT. Still working on "import and
verify" script.
- Got
/archive/home at LHO/LLO going to tape (it hadn't been since the Sol10
upgrade).
(Phil Ehrens)
- Began
writing document outlining location of all grid related software and
configuration files, including user specific information for use of the
environment, including debugging hints.
- Debugged
problem in generic API of LDAS which caused gps
timestamp values in logs to be off by one second. Further rework of the gpstime.tcl module beyond the already implemented
short-term fix is required.
(Erik Espinoza)
- Configured
IPMI, tested SOL & power control.
- Got
FC4 to work on Supermicro Mobos.
- Troubleshooted issue with mail on
ldas-grid.ligo-la.caltech.edu.
- Contacted
Appro on lagging demo unit.
- Built
kickstart usb stick.
- Built
dos usb stick w/ bios utils.
(Stuart Anderson)
- Testing
and bencharmking the first set of evaluation
cluster nodes for the new CIT cluster.
- Working
with vendors on technical and pricing information for the new CIT cluster
procurement.
- Mirroring
various software updates associated with S5.
- Researching
next generation Sun servers and storage.
- Installed
new 7500VA UPS for CIT cluster switch.
MIT
(Keith Bayer)
- Replaced
two 200GB maxtor drives which were failing and
sent both back to Maxtor for warranty replacements.
- Upgrading
cluster this week: new switch, Solaris 9->10, Intel Boxes to FC4,
Cluster to FC4
Livingston
(Dwayne Giardina)
- Replaced
disks in nodes 7, 8, 18, 20, 23, 26, 28, 38, 60, 63, 64, 78, 84, 101, 107,
111, 113, 121, 125, 128, 134, 137 , 139, 154, 161, 166, 182, 183.
This was mostly finished prior to FC4 upgrade.
- nodes 61,81,122,138,184,205,210 were not upgraded due
to problems with disk, cdrom, or power supply.
Replaced power supply in node122, and then used cloned disks in all to
complete upgrade.
- Shipped
tapes LL0426,LL0520,LL0639,LL0509,LL0521,LL0535,LL0633
and LL0637 to Dan Kozak at CIT.
- node48 was DOA upon visual inspection. replaced power
supply and all is well. I used the
last remaining spare power supply in node48, need to order a couple extra to keep on
hand.
- ALL
nodes 1-210 at LLO are FC4 and, at the time of this email, are up and
running. node2 is currently used as
ldas-gridmon and is not part of Condor (per note from Igor)
- Revamped
a couple scripts that will run starting at 00:00 on Sat, Sun, and Mon to
check the nodes for badblocks and email status to
myself and Igor. It will check 70
nodes per run.
- We
have a lot of Maxtor disks that are still under warranty and I will RMA them today or tomorrow.
Hanford
(Greg Mendell)
- Level
1, 3, and 4 RDS generation has been running 24/7 at LHO and LLO since last
Friday, Oct, 28, using the S5 channel lists (up to a few minor changes to
be made a LLO). All data is being reduced successfully. S5 RDS generation is ready to go!
(Ben Johnson)
- Published
S3 L3 RDS data and URLs for the data under /archive.
- Started
D2D script to archive data at LHO starting at 07:30 PST, November 3 2005.
- Setting
up realtime, L0, L1, L3, L4_H1, L4_H2 publishing
scripts for S5@LHO. Segment insertion is being tested by AstroWatch scripts, and presenly
looks good.
- Slowly
bringing back a few of the original nodes (1-138) which did not take the
FC4 install/reconfiguration well. Nodes 160-169 also have setup problems
and were turned off after many user jobs were failing on them.
General Computing (Wallace)
MIT
(Keith)
Nothing to report.
Livingston:
(Dwayne)
- helped
Rich Riesen with email migration issues
- been tied up with LDAS,
this is all the GC I have to report this week.
(Shannon)
- The
new mail server seems to be working well.
There are the usual user migration issues, but those seem to be
mostly taken care of now. This week
has mostly been spent wrapping up the last bits of the server swap.
- The
new tape backup hardware is in and I started unpacking it and getting it
ready to install.
- Installed
a new foundry switch in the rack to replace our Dell switch in the
CUR. Needs to be configured and put
in use.
Hanford:
(Christine)
- Reinstalling
Solaris 10 on an AMD computer hoping that if I set it up from scratch as a
NIS+
client then it will be able to authenticate with the server.
- Started
a cron job to clear the /tmp
directory on the mail server every night.
This directory gets full and causes "out of space" errors
when users try to get their email off the server. This is a temporary fix until I get the
new mail server built.
- I
am still waiting for LMSI to inspect the fiber for the backup network
between LHO and PNNL. There are two
places along the fiber run which PNNL reports have a lot of
reflections. Everything else along
the circuit has been tested and passed.
We are still unable to get a link on the circuit between LHO and
PNNL.
- Working
on some mail aliases for LDAS.
- Created
a new user account. Reset the
password for another user.
CIT:
(Veronica)
- LIGO: Updates of the website for the NSF
review. Installed a webpage of the
documents for review. Webcast and taped the talk by Osamu Miyakawa. I ran
a test broadcast the day before and on the day of the talk to let the
sites to try it out and test the readability /audio. Compressed the video footage for
on-demand streaming. Updated the roster
database and various mailing lists.
LIGO website updates.
Installed the Fall newsletter. Updated the MIT seminars webpage. Assisted Helena with an AudioCom
issue. Assisted Julie with
Photoshop and Roxio Easy CD Creator. Other misc. user support.
- LSC: Updates of the November meeting
website. Worked with Marie Woods and
the MIT ecommerce to resolve an issue with the online credit card
transactions being declined seemingly in error. I checked the form that collects the
values on our side to see if there's a mismatch in passing them over to
the MIT secure server but it wasn't the case. I then ran a test transaction and it
went through. So it seems to have
been a one- time issue. Updates of
the database of the LSC publications and minor changes to the frontend.
- CaJAGWR:
Website updates.
(Christian)
- Osamu
Miyakawa- Upgraded Osamu's workstation from
Windows 2000 to Windows XP.
- Patrick
Sutton- Retrieved all of Patrick's data after his laptop's hard drive
crashed. I configured the new hard drive with the standard Ligo image and transferred all data back.
- Irene
Baldon- Replaced toner cartridges on Irene's
local printer.
- Configured
new system with the engineering Ligo image for
Ken and transferred all his data. I
went through and updated the firmware of all Ligo
network printers. Mike and I went
through the 2nd and 3rd floors of W/Bridge moving and replacing old
monitors and PC's.
(Mike)
- Bruce
Sears: Loaded a LINUX for Bruce Sears, due to a hardware failure on his
old workstation.
- Monica
Varvella: Had to move her Sun box up to the
second floor, but when I brought up her computer back up I the hard disk
failed. I end up having to put together another Sun workstation for her.
She is back up and running.
- Ken
Mailand: Reloaded an updated computer for him.
This took a lot of time due to Hardware issues and compatibility issues
with Solid Works. He is now swapped out. Christian helped me with this
load.
- Dennis
Coyne: Worked on his laptop trying to fix a hardware issue. No luck!
Larry has ordered him a replacement laptop. I have backed up his
laptop and getting it ready to ship back to IBM.
- Worked
with Larry W. installing rack mount servers in room 19 Bridge Annex.
- Relocated
many users to other locations with in the project. This turned out to be a
big job that took up most of the week.
- Surplus
a lot of equipment that we can across while moving users to their new
locations.
- Spam
Filters: Continuous work with Larry, searching for false positives.
- Other
onsite/phone misc. user support.
(Larry)
- Continual
work on procurement items. Ordered the s/w for the new DCC system and now
waiting for the company to approve the chosen h/w for the same system. Ordered items for the 40M and LDAS
groups. Ordered a new laptop for a
user with a unit that was beginning to fail. Resolved a SUN order that was placed for Livingston some months ago. Working on a number of misc. items that
need to be purchased.
- Rebuilt
a couple of computers and assisted Mike on a couple of rebuilds he was
working on. One computer needed a
rebuild because the latest set of patches that were installed corrupted
the OS on the machine. This past
week we had a number of machines go down with h/w problems. There are still a couple of machines
that need to be repaired or replaced.
- Assisted
Mike and Christian in moving a couple of computers and getting rid of some
of the old equipment. Mike and Christian really got a workout from all of
the equipment they moved.
- Installed
the second dual-core quad cpu
sandbox unit into the rack. The
first unit is now on-line but will probably get a rebuild in a couple of
weeks.
- Assisted
a number of users in trouble shooting different problems on their
computers. Most were environment issues but a couple needed updated
library files.
- Still
working the e-mail filtering issues. This will be a never ending task.
Mail statistics for Oct 27 - Nov 2, 2005
|
Mail Statistics
|
Oct 27 - Nov 2, 2005
|
|
Rejected Messages
|
13,511
|
|
Virus Messages
|
818
|
|
False Positives
|
|
|
Accepted Messages
|
16,300
|
|
Total Messages
|
29,811
|
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Systems, Management
From: Rolf Bork <rolf@ligo.caltech.edu>
- Alex has succeeded in compiling and running the Framebuilder codeon one of
the new dual AMD64 machines. We now need to purchase a few large SCSI
drives for this computer (can hold up to six, 300GBytedrives) for use as
the Framebuilder at LASTI.
- I continued work on software for using the Myricom network cards, building sender and receiver
modules. Alex has incorporated the receiver into the Framebuilder
and I have integrated the sender code into the quad controller front end.
We now have a front end sending its data to the Framebuilder
over this new network. It appears to work well, but still requires a fair
amount of work for error checking and exception handling. For the test,
the front end was configured to run the present Ligo
maximum of 1MByte/sec to the Framebuilder. Even
with this load, the quad controls software cycle time is still down at
17usec. So, I believe we are ready at this point to commit to this network
type for LASTI and should purchase the network switch and a couple more NICs for further testing.
- On the disappointing side, we have not yet received
the PCI express expansion chassis that we need for our I/O cards. It was
scheduled to ship on Oct. 31, but the latest word from the manufacturer is
a ship date of Nov. 18. At this point, it is not a problem, but a delay
past the end of this month will delay the quad controls installation and
test here at Caltech in early December.
Seismic Isolation
Advanced LIGO Seismic Structure
|
Assembly
|
Status
|
|
Top Assembly Components
20007970-A
Stage 0 Assembly
2000795-A
Stage 1 Assembly
20007825-A
Stage 2 Assembly
20007825-A
|
Purchase order placed with Arland Tool for all large parts. All material has been recieved. Project currently in Engineering for CNC
programming. Amendment made to purchase order to change mounting holes on
optics table from 2 x 2 to 1 x 1 hole pattern.
Purchase order placed with Limerick Machine for the end milled plates and
remaining Top Assy, Stage 0,1,
and 2 Componants.
<!--[if !supportLineBreakNewLine]-->
|
|
Stage 0-1 Spring Assembly
20007878-A
Stage 1-2 Spring Assembly
20007890
|
Fabrication drawings are complete. Drawings must now be
checked.
RFQ for blades and rod flexures complete. Quote due 11/22.
Maher Limited holding maraging steel for blades and
flexures
|
|
GS-13 Pod Assembly
20007810-A
L-4C Pod Assembly
20007820-A
STS-2 Pod assembly
20007941-A
|
Geophones, seismometers and lockers are in house.
Purchase order placed with Norcal for vacuum
housings.
RFQ complete for machined components. Quotes due 11/16
Design of harnesses completed. RFQ required for internal pod harnesses.
|
|
Stage 0-1 Kinematic Lock
20007941-1-A
Stage 1-2 Kinematic Lock
20007941-2-A
|
Tooling design complete.
Purchase order placed with Limerick Machine for kinematic
Lock Assemblies.
|
|
Stage 0-1 Actuator Assy.'s
20007966-A
20007967-A
Stage 1-2
Actuator Assy.'s
20007968-A
20007969-A
|
Tooling design complete.
Purchase order placed with Limerick Machine for actuator mounts and tooling.
|
|
Stage 0-1 Standoff Pin
Stage 0-2 Alignment
Tower and Washer
Stage 2 Keel Plate Alignment
Tower
Blade Pre-Load Tooling
Blade Calibration Fixture Modifications
LASTI Test Stand and Spreader Bar
|
Solidworks part files exist for
the standoff pin and alignment towers. They will require a dimensioned
drawing and checking prior to soliciting bids.
The blade pre-load tooling and calibration fixture tooling will require
redesign following the redesign of the blade springs by ASI.
Purchase order for test stand issued to Southern Enterprises. Delivery to MIT
by 11/16
|
"Joseph A. Giaime" <jgiaime@ligo.phys.lsu.edu>
Agenda for the weekly SEI telecom
Friday, Nov 4, 2pm Eastern,
1pm Central, 11am Pacific time
Announcements
BSC SEI status, Ken/ Dennis
- Ken
coordinating with Riccardo talking about HAM SAS
installation, tooling, etc.
- Ken
has received questions from vender, and has answered some of them
- Barrel
nuts: ASI specified an unavailable steel, which
is hard to get. ASI now recommends a magnetic stainless material for
the barrel nuts that would meet the strength requirements. We said
that this is OK.
- Maher
still hasn't returned an updated quote with the new blade geometry.
Ken will call them early monday morning.
HEPI work (Rich M, Shyang W)
- Unconditionally
stable loop closed by Rich at LHO X end, from crossbeam STS-2 to fine
actuators. The results to the error point look OK. See log
entry on Monday's
LHO log.
- H1
has not been running since this was done, so no interf
tests are available. There are also other loops actuating the fine
actuators, and the interaction isn't yet measured.
- Y
end still not yet stable.
- Shyang has been testing resonant gain suppression of
the stack and pendulum features at LLO. Please see the LLO
elog for details
HAM control with VME (Pradeep)
Stanford report
- Stanford
anticipates arrival of suspension frame next week for structure
interaction studies.
- William's
thermal study: he is running wires and connecting instrumentation.
- Aaron's
adv seismometer study: material arriving, machining beginning.
- Matt
working on ETF platform controls. Damping and angle loops
closed. XYZ sys-id data collection has resulted in very noisy
transfer functions due to windowing issue. Maybe the FIR filter
wasn't settled long enough. They are working on it.
- Brian
is using Finesse to revisit HAM isolation requirements. Arm cavity
mismatch determines the noise requirements on the signal recycling mirror,
due to the DC readout.
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
Participated in the Ribbon/Fiber/Ear/Bonding PDR on
Monday. Working with Norna
and others on the answers for the mode cleaner questions asked by the Ribbon/Fiber/Ear/Bonding
reviewers.
Working with Caroline on stiffening the faux optical plate
of the gazebo in the Synchrotron.
Working with Dot on paying Galli & Morelli for the drum ended wires.
Had a telecon with Joe Hanson, Calum and Ken Mailand on the XY
Translation stage and the air bearing. I will be FedExing
an additional component to them tomorrow.
Working on the quad suspension eddy current damper
alignment tool design.
From: Jay Heefner
<jay@ligo.caltech.edu>
AdL Quad SUS and SEI Controls
- All
of the boards required for the Anti-Image and Anti-Alias have been sent to
Screaming Circuits to be stuffed. They are due back at CIT on 11/7. The
chassis have been received and front and rear panels are due next week
also.
- We
are still on schedule for a test of the system at CIT the second week of
December.
- It
is planned that the same AA and AI board design will be used for the AdL SEI controls at LASTI.
- Jay
and Alex will be at LASTI starting Nov 14 to make plans for the SUS and
SEI installations.
From: Calum Torrie <ctorrie@ligo.caltech.edu>
Covering 2 weeks:
Quad
Mark and I measured the
pendulum resonances of the quad suspension, results to follow. We also damped
the quad with the local control.
2nd Suspension
I meansured a couple of extra configurations of the structure
for comparison. Mike Gerfen and I weighed the upper structure and the overal structure. Mark and I hope to start work on the
modal survay next week (mode shapes).
Install Fixtures
Ken Mailand
and I are continuing on the design of the fixtures. With Oddvar's
help we have a set of drawings in the shop and hope to have the rest started in
the
next week or so.
(more) Quad
Helena, Mark, Lee and I have
started to dis-assemble the quad. Lee, Helena and I
are preparing various packages for cleaning and baking.
Noise Prototype
I continue to support RAL
with the work associated with the noise prototype.
Core Optics
No report this week.
Pre-Stabilized Laser
No report this week.
Auxiliary Optics
From: Michael Smith <smith@ligo.caltech.edu>
I have completed the revision of the development schedule and man power
requirements for the SLC, PO MIRROR/TEL, INITIAL ALIGNMENT,
OPTLEV, OMMT, AND VIEWPORTS subsystems of the AOS.
Other Laboratory R&D
Juri
With the help from Virginio and Phil I translated
in Matlab my program for the calculation of eigenmodes of optical cavities with general shape mirrors.
I’m testing the code for AdLIGO mirrors in
order to check the results with the program for cylindrically symmetric
mirrors. One limitation is given by the computer’s memory which
constraints the mesh size for the problem. Moreover I’m writing my Ph.D.
thesis.
Chiara
We made the hardening process for the maraging
steel plates, heating the material in argon atmosphere for about 100h at a
temperature of 435°C. I measured the
transfer function of the system, with four Inverted Pendula, in the range of frequencies from 0.5Hz to100Hz
with a load of 624Kg.
Valerio
We have prepared for the Mathwoks support another
example that gives physically inconsistent results. At the same time, with the
help of V. Sannibale, we are evaluating other tools
for simulating the HAM-SAS, such, for example, the MSE library developed by G. Cella.
Another alternative is to use the transfer function measurements on the SAS
prototype, located in the synchrotron lab, that have been recently made by C. Vanni. Using Matlab System
Identification toolbox, it will be possible to extract from these measurements
a state-space model of the SAS prototype and then to simulate feedback control
loops in many configurations on a system similar to the future HAM-SAS.
Yu-mei
The summary of last week’s work
- Work
with Chiara Vanni to
heating the material
- Read
the book “Finite Element Analysis”
- Read
the paper “inverted pendulum studies for seismic attenuation”
- Read
the paper “performance improvement of the geometric anti spring (GAS)
seismic filter for gravitational waves detectors”
For additional information about this report, contact Stan Whitcomb or Phil Lindquist