Weekly Report for
Week Ending October 27, 2005
The LIGO Executive
Committee Agenda for Monday October
31, 2005 will be:
(Meeting time: 10:30 am Pacific Time)
1. Announcements
2. Comments
on Weekly Report
3. LSC
Issues (Saulson)
4. LIGO
Lab Operations
- Administration
(Lindquist)
- Sites
(Raab, Zucker, Shoemaker)
- Commissioning
(Fritschel), Detector (Coyne)
- Campus
Research Facilities
- 40
Meter (Weinstein)
- TN,
( Libbrecht)
- LASTI (Shoemaker)
- Data
Analysis and Computing (Lazzarini)
5. R&D
and Advanced LIGO (Shoemaker)
6. CHANGE CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION AS
NEEDED
Special Items:
Special Announcements:
Weekly
Report Highlights
Status of Observational Results publications
Just this past week, two Inspiral search papers
from S2 were published on the Physical Review D website. "Search for
gravitational waves from galactic and extra-galactic binary neutron stars"
is now Phys. Rev. D 72, 082001. "Search for gravitational waves from
primordial black hole binary coalescences in the galactic halo" is now
Phys. Rev. D 72, 082002. These papers join the papers about the S2 known pulsar
search (PRL 94, 181103), GRB030329 triggered burst search (Phys. Rev. D 72,
042002), and the S2 untriggered burst search (Phys.
Rev. D 72, 062001.)
Other papers are approaching publication. The S3 stochastic background
search paper has been accepted by Phys. Rev. Letters, and the S2 Hough
transform pulsar search paper has just been accepted by Phys. Rev. D. The S2
LIGO-TAMA burst search paper has reached the stage of responding to reviewers'
comments. The paper on the S2 search for binary black hole inspirals
has been posted on gr-qc, and is about to be
submitted to Phys. Rev. D.
Many more results are in the pipeline, of course, and will be the subject of
discussion at the November LSC Observational Results meeting at MIT.
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
- Completed
changes for IAP, IUCAA, Michigan, Moscow, NAOJ, Oregon,
Penn State, Sannio,
and SLU. They were posted and
submitted to Saulson for signature.
- Submitted
Goddard, Trinity, and Rochester
to Saulson for review.
- Working
on GEO600 and Northwestern changes.
Non-LSC MOUs (Lloyd)
- Received an MOU from outside the LSC from the
Experiment "Ricerca di
Onde Gravitazionali"
(ROG) of the Istituto Nazionale
di Fisica Nucleare (INFN), submitted by Eugenio
Coccia. This MOU was formatted and posted and
submitted to Saulson for signature.
SITE TELECONFERENCE (Lindquist)
- A
site teleconference was held Thursday, October 27, 2005. The following issues were among those discussed:
- Operations
Finances – During October we project $2 million in costs of
which $1.2 million will be charged against FY 2005 accounts. So far we are consistent with estimated
$2.5 million residual FY 2005 charges in FY 2006.
- Commingling
Taxable and Non-Taxable Procurements – Ed Jasnow
has been requested to prepare a note for distribution regarding the
commingling of taxable and non-taxable items on a purchase order (action 132). If materials to be sent to Caltech, which
are taxed by California, are mixed with
materials to be sent to the sites, which are not taxed by California, the result will be the application of California tax to
the entire order.
- Visitor
Housing in Louisiana
– The temporary housing situation is still stressed. Livingston
has been able to accommodate enough people to support commissioning, but larg gatherings are still not a good idea. Livingston
may attempt to expand the current facilities.
- SEC
Data for LSU – M. Zucker to address
issue with J, Giaime. Expect to discuss needs with EDR Friday,
October 28 and talk to LSU next week.
- The
list of assigned actions updated through October 27, 2005 will be found Here.
PROPERTY MANAGEMENT (Chargois)
>From: Ed Chargois <chargois_e@ligo.caltech.edu>
- Provided
assistance to the Detector Group (C. Torrie)
with packing and shipping of ten (10) machined stainless steel parts to
MIT (L. Ruet).
Account Number P204317.
- Assisted
Caltech's Property Services Division (T. Benjakalykorn)
with the required information to complete the Federal Automotive
Statistical Tool (F.A.S.T) Report.
- Assisting
the Detector Group (H. Armandula) with arranging
the shipment of six (6) Optic Transit Cases to LHO (D. Cook) for
storage. Account Number LIGO.TEC
1.3 NSFLIGO.FY02ON.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- Completed
processing presentations from the 2005 Gingin
Workshop on GW Detection.
- Processed
and distributed two DCN's.
- **Scanning Project Update** - Progress continues on
Larry Jones' boxes of files. To
date, we have 5 of the 16 boxes scanned.
|
Week Ending
10/27/05
|
In
|
Out
|
|
Packages
|
22
|
7
|
|
Faxes
|
22
|
13
|
FINANCIAL SYSTEMS (Cronin, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Completed
change order #1 to Sun Microsystems S001939 for the return and replacement
of the monitors. The monitors have been returned today by LLO to the
vendor for credit. The replacement has shipped out.
- Completed
the new subcontract for the construction of the SEC at LLO.
- Completed
change order #2 to JPL and submitted the change to JPL and appropriate
parties.
- Completed
the Arland contract and have routed it for the
appropriate approvals. Waiting for the return of the signed contract
package for distribution.
- Working
on both subcontracts to Limerick and Filehold Systems.
- Working
on the MIT change order.
- Working
on closing several blanket purchase orders which were not extended for
FY2006.
>From: Florence Kaufman <fkaufman>
- Worked
on updating reports for October. I
am reviewing the expenditures made in October to determine whether they
should be charged to the FY2005 Award or to the FY2006 Award. If the expenditure was for services
rendered or goods purchased prior to September 30, 2005, it is charged to
the FY2005 Award. Of the
approximately $2 million of expenditures recorded thus far in October,
$1.2 million will be charged to the FY2005 Award.
- Prepared
and submitted a schedule, at the request of the Sponsored Research
Department, showing how the $16 million awarded to date for FY2006 should
be recorded in ORACLE.
- Noted
that the telephone expenses paid to AccuConference
for conference calls were all charged to the Business account instead of
to the accounts indicated on the invoices.
Cost Transfers will need to be submitted to charge the expenditures
to the appropriate POETAs.
- Assisted
Terry Gunter with some issues related to the Hanford conference account.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence).
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone
<gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow
<jasnow@ligo.caltech.edu>
- The
contract for the LLO Science Education
Center was executed by Caltech on
October 25, and sent to the contractor, Cangelosi-Ward
of Baton Rouge.
- A
kick-off meeting on the LLO SEC was held on October 28. Present were representatives of Cangelosi-Ward, his subcontractors, Eskew-Dumez-Ripple, the architects, and LIGO
representatives Mike Zucker (phone), Allen
Sibley, and Ed Jasnow (phone). The agenda covered many of the
conditions of the construction as well as the schedule. The original schedule of August 1 is no
longer achievable, but the contractor may be able to make the third week
of September, 2006.
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
>
>Dorothy Lloyd
- Processed
the usual invoices for payment and followed up on problems. Updated
contract invoice log book.
- Processed
the usual requisitions for purchases over $10K and standard POs, as SOS
buyer, for those under.
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
PROPOSALS and REPORTS (Lindquist)
We have received $16 million representing the first half of the FY 2006
funding for LIGO Operations. Florence is providing the
Office of Sponsored Research a “resume” distributing budget to the
various operating accounts.
The NSF has requested that we submit the Cangelosi-Ward
subcontract for the Outreach building electronically via FastLane. This information has been entered but not
submitted yet.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- A
Staffing Committee meeting was held on Monday, October 24. The minutes and action items have been
posted on the SC web page.
- All files for the Staffing Committee are up-to-date
and posted on the SC web page.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
No report.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of Commissioning Activities at LIGO Hanford Observatory (compiled by M. Landry)
With one week to go prior to the start of S5, efforts
on commissioning are threefold: i) to resume stable,
reliable high power locks on both instruments, which has been lacking over the
last month and the last seven days in particular ii) complete remaining
commissioning tasks such as the implementation of the new timing system, and
iii) housekeeping and cleanup chores to bring the lab to a state of readiness
for the long S5 run.
Commissioning highlights are bulleted below:
- last
week it was noted that protection circuitry was added to LOS modules; summary
data on that were added to the elog
- hamster
houses that prevent most dust from falling through beams on the antisymmetric beam paths were re-installed
on ISCTs 4 and 10
- lots
more excitations have been added to AWG for the science run... these
include the typical calibration excitations (3), the new photon calibrator
ones (2), the addition of the ETMY_EXC excitation for some hardware
injections, and those associated with the new gentler 1pps ramp (sinusoids
at 960 and 961Hz). AWG cpus have been
shown to handle the additional load; slots too have been added.
- better
living through automation: remote
optical lever centering now available
4K IFO
- ASPD2
was swapped
(reported last week but now elogged). This
is a new-style PD (the only one of the four on the table, the others are
old), so we will be on guard to see if any latching problems are evident in
AS_I, as was the case previously when a new diode was tried.
Elliptical burn spots were observed on the old diode, although it is
curious that the major axes are perpendicular.
- One
of the observations on H1 this week has been alignment instability
presenting as a wobbling AS spot on video, but a reasonably stable REFL
beam. WFS have been suspected and unity gain frequencies were measured
and tweaked. Optical lever compensation problems were noted at LLO
and this was suggested as a possible culprit here.
- like
the 2k previously, ISCT4 received 2"
supermirror optics
- ongoing
crashes of sequencers and IOCs that impacted
uptime led to a divorce
of TCS and power sequencers
- bi-stable
states in the 4k power were observed - configuration control through multiple
paths, boths sequencers and scripts, can lead to
5% power level differences. These simply have to be chased down
before S5
- like
the BS last week, the RM was now better compensated
and the PRC correction to DARM should be cleaner
2K IFO
- high
frequency noise on the 2k periodically gets bad,
then good again, with a broad hump from 40-160Hz
- unnecessary
blown fuses led to this power
supply modification, in which the fuse holder is separated from the
all-too-hot power receptacle
- the
fibre-coupled timing
system was installed, and some details are shown here
- ASPD3
was sick
in that it loses 40% of its gain and phase shifts a wopping
53 degrees when the IFO goes to full power. In bench tests it was
noted that the DC compensation circuit not trimmed and at 50mA the phase
began to drift strongly. Repairs
were made and the ASPD reinstalled.
DAQ/CDS
- Monday
marked the typical barrage of software updates
- for
S5 hardware injections: an ETMY excitation point was added
- the
much anticipated replacement for 1pps ramp was installed and testing
has begun
- phase
calculations for the AS_Q/I fast channel were shown to be problematic;
this resulted in a code
mod and now all looks good
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
L1 Interferometer (Zucker)
We completed mini-run M8 this weekend, mostly successfully. A good fraction
of DMT monitors functioned well and feedback has been transmitted on those that
didn't fare as well. However, machine uptime was affected by elevated
microseism from Hurricane Wilma, as well as some general "commissioning
fragility".
A primary component of the latter was weakness in the WFS servos, which was
addressed this week by new filters and gain optimization.
Laser trouble reported last week and the week before is evolving, but
persistent. The unusual beam shape of the post-post-cleaning MOPA realignment
has proven difficult to match to the PMC, so net transmitted power is less than
needed to make our sensitivity target. We are patiently waiting on JDSU to
finish rebuilding our spare laser and ship it to us. Until it arrives we're
holding off any further invasive diagnostics on the installed unit, since
everything we do seems to make things worse. No LIGO without the L.
A framebuilder update and new CDS realtime code have brought us up to spec for S5. Lots of
patches and fixes and M8 inspired tasks remain, but CDS software is mostly over
the hump and ready to run.
A very subtle "bug" was discovered in our main demodulator
circuits, which are mostly passive (and previously considered elegant, simple
and bulletproof; is nothing sacred?). Their noise was found to depend
nonlinearly on RF carrier level. The esteemed designer is looking into the
issue on the test bench. Meanwhile boards were reshuffled to place those least
afflicted in the most critical locations, and RF phases were adjusted to put
each one's best foot forward.
CDS (Bogue)
- Worked
on troubleshooting our problems with the atomic clock. It needs to be shipped back to the
manufacturer for repair. Szabi arranged a loaner for us to use while ours is
out.
- Spent
some time with John Z. while he was here.
The dmt box with the most problems is
pickerel. John and I rebuilt it
starting from my jumpstart base image.
It seems clear at this point that the biggest problem with this box
is the epics ioc that
is running on it. I will need to
revisit this issue at some point, but it is in a holding pattern for now.
- Spent
some time with Keith Riles and got his todo list
for sci mon
support.
- Rewrote
the environment for ops. This both
streamlined the environment and unearthed some previously unforseen problems.
Right now we are probably at around 90% sure of the new
environment. Most of the scripts
have been exercised and the biggest glitches have been fixed. Thanks to both Tom and Matt Evans for
their help with this.
- We
had a big code drop on wed. We
should be in good shape for S5 now.
Computing and Network Security (Roddy)
The Sun Java Enterprise System saga continues. I think I have the issue nailed down and will
know shortly with a little more testing.
All of this week has been spent troubleshooting the JES issue other than
several miscellaneous tasks like ordering hardware, a laptop, etc.
CDS code support (Khan)
No report.
Education and Outreach (Thacker)
Saturday, 22 Oct assisted in conducting teacher Professional Development
Workshop for Tangipahoa Schools Math Science Partnership through Southeastern Louisiana University.
29 middle school science & math teachers attended.
Monday, 24 Oct conducted teacher Professional Development Workshop for LSU's Cain Center Math & Science Partnership. 14 middle
school science/math teachers from East Baton Rouge Parish attended.
Thursday, 27 Oct met with Doyle
High School physics
teacher to establish connection with that (local) school. Met with the
principal who is quite interested in the school pursuing some kind of closer
relationship with LIGO..
Site Safety and Security (Riesen)
Working on stopping the PSL acoustic enclosure door from
closing "bounce", hoping to minimize the LSS from activating and
closing the laser internal shutter.
The site speed limit & quite zone signs have been ordered and should
arrive next week. (the guard shack electrical work has
been completed) Found no laser safety nor site safety concerns this reporting period.
Janeen Romie completed
her laser eye exam and I will order prescription laser eyewear when I receive
the proper paperwork.
New laser safety glasses cabinets are being installed at the End stations,
LVEA, and the HPLF. This should help users find appropriate laser eyewear when
entering a laser hazard zone.
The LSS "bugless" software should arrive
next week and will be installed asap
after arrival.
HPLF (Franzen)
HPLF news: Packed the high power laser in order to send it to University of Florida. There it will be used for high
power Faraday Isolator and EOM tests by visiting scientists from IAP, Russia before
being returned to LLO in about two months.
General Computing (Giardina)
- visiting
Caltech this week, met with everyone, toured the LIGO sites on campus
- overview
of GC at Caltech
- CDS
DNS entries/modifications per request from Lisa B.
AdL SUS/SE Mechanical Engineering (Spjeld)
Quad SUS Installation Fixtures
- completed
redesigning parts and assemblies, submitted approx. 10 drawings to Calum for machining on 10/25
- meeting
with Calum and Ken Mailand
on 10/25 to discuss manufacturing drawings
- revised
support table brace assembly, resubmitted drawing and also finished
drawing for lift table drive interface washer
- currently
uploading SW files to vault
- revision
of assembly drawings in progress
LDAS/Condor and data analysis (Yakushin):
1) Finished upgrading the cluster to FC4. There are 6 computers which had
hardware problems and are not fixed yet: nodes 89, 90, 173, 191 cannot use
their CD drives; node122 would not boot, most likely power supply problem; node
210 died with a kernel panic twice after dd was
started.
2) Disk 5 @3510 failed. The replacement was ordered.
Initial LIGO Detector Science & Engineering (Coyne)
CDS
see also the CDS weekly meeting
minutes in the commissioning
archives
CDS Software
Rolf Bork
- Made
a fix to the fast ADCU code for both sites.
- Last
code download to LLO prior to S5 was made yesterday. This included:
o Latest
ETM controller code to properly filter decimate DAQ channels at 256Hz
- LSC
code w/shutter control output.
- Latest
Framebuilder code.
- RBS
software with input gain and on/off switch.
CDS Hardware
Jay Heefner
Refl Beam Stabilization: Boards for spares are being
stuffed.
Ben Abbott
Fast Shutter
I have modified the machined shutters, and am finishing up the wiring of the
electronics parts. All of the units will go through an extended reliability
test, and then will be sent out early next week to the sites.
ISS PDs
I have written up the test procedure for the ISS PDs,
and am just finalizing their packaging and paperwork. They will be sent out to
the sites sometime today or tomorrow.
DMT
John Zweizig
This week we had a successful mini-engineering run at LLO (M8). After installing
all the software changes resulting from the M7 run at LHO, we performed further
tests of the software and configurations at LLO. A few new bugs were discovered
and fixed including a lack of validity checking in the Monitor data request
handler and an unresolvable URL in the trigger xml
files. Other bug fixes and upgrades were made to individual monitors.
PSL
PeterKing
NPRO S/N 393 was shipped off to JDS Uniphase to be
used as a replacement MO for the 10W laser that JDSU is refusrbishing.
(The new NPRO from JDSU's production line did not
have adequate performance.)
40-Meter Interferometer (Weinstein)
Osamu completed and submitted the talk he gave at Amaldi
6: "Lock Acquisition Scheme for the Advanced LIGO Optical Configuration,
for the proceedings of the 6th Amaldi Conference on
Gravitational Waves", Osamu Miyakawa, 9/20/05, pdf.
Osamu will
give a LIGO/Caltech seminar on recent results from the 40 meter, on November 1,
11 am in the SCR.
IFO commissioning
- Osamu
realized last week that the reason we aren't seeing the optical spring
peak in the DARM transfer function may be because we were locking the signal
recycling cavity in the wrong place, on the "other side" of the
spring (so that it's an anti-spring). He flipped the sign of the SRC servo
loop, and then found that he needed to flip the sign of several more loops
before he was able to regain full lock in the AdLIGO
configuration. And there, in addition to the clear RSE peak at ~ 4 kHz,
was a beautiful optical spring peak at ~ 40 Hz!
- Rob,
independently, arrived at exactly the same set of sign flips to achieve
lock in the optical spring configuration.
- In
this correct locking point, the spot at the asymmetric port is now much
nicer. The spot is much rounder, and the optical spectrum analyzer shows
that the carrier is now nearly dark. It looks like the correct locking
point exhibits "mode healing", while the wrong locking point
exhibits "mode damaging". This is not yet understood.
- It
appears to be more difficult to lock in the "correct" point,
which Osamu theorizes is due to its proximity to other, incorrect and less
stable locking points. It is still possible to lock at the wrong point; it
is clear from the optical spectrum analyzer at the asymmetric port when
this happens, and one has to break lock and try again. We need to develop
a more reliable procedure.
- Rob
and Osamu use different procedures, scripts, and make different use of the
analog common mode servo during their lock acquisition procedures. They
will work together to find a common procedure that makes use of the best
benefits of both.
- Dan
and Monica will calibrate the DARM channel and take a calibrated noise
spectrum, and then develop the noise model.
IFO Modeling
- Rob
used FINESSE to model the DARM transfer function at the correct and
"wrong side" SRC locking point, and gets excellent
semi-quantitative agreement with the measurements. He then modeled the
CARM transfer function with various offsets, and again sees excellent
agreement with the measurements, including clear optical spring peaks at
various CARM offsets. We continue to learn more about the complex optical
configuration that we've built.
- Monica
has implemented Hiro's new e2e dual recycling
cavity module into her optical model and is testing and debugging it.
- Monica
is gearing up to study the optical spring in her e2e optical model.
DC Detection Development
- Mike
Smith completed and submitted to the DCC a drawing package for the 40m
output mode cleaner. The drawings were also submitted to CES for
machining. The OMC will be built out of copper, to provide damping of its vibrational modes.
Electronics, Controls
- Dan
and Ben installed and commissioned new RevB coil
drivers for the three mode cleaner optics, MC1, MC2, and MC3. Ben put in
the new 4116, ran a cable, did all the cross connect
wiring, changed the database, and fixed the screens. These modules provide
separate paths for the bias voltages and the drive voltages to the coils.
Now all 10 suspended optics at the 40m use these coil drivers. Dan
transferred all the pitch and yaw biases from the drive to the bias paths,
re-established the mode cleaner alignment, and made sure the mode cleaner
locked happily.
- Now
that we have RevB coil drivers on the MC optics,
Dan can proceed to diagonalize the coils and
output matrix to decouple POS, PIT, YAW without fear of introducing
misalignments.
- Dan
will collect data on the oplev noise to see if
there is a significant contribution from the stack motion. If so, we will
want to move the in-vac mirrors used in the oplevs so that they are mounted on the chambers rather
than on the seismic stacks. Steve continues to develop plans for this.
First priority, at the next vent, is to adjust the OSEMS on the BS, PRM
and SRM suspensions to minimize bounce mode coupling, and diagonalize these suspensions better.
- Ben is preparing fast-triggered mechanical shutters
for the sites, and will make a couple for us.
Thermal Noise Interferometer (Black)
No report.
LASTI (Ottaway)
LASTI Mechanical Tests (Mittlemann, Ruet, Ottaway, MacInnes)
We spent some time characterizing the best place to lay our optical fiber
that will couple the PSL table to the Xend HAM triple
experiemnt. Encapsulating
it in an air tight stiff structure should give us appreciable isolation from
ambient acoustic noise.
Ponderomotive Squeezing Experiment (Corbitt, Ottaway, Innerhofer, Mavalvala)
Continued measurements of the optical spring and
parametric instability. We
resolved the discrepancy between the theoretical and measured optical spring
frequency by accounting for the VCO path gain.
We implemented an analog division circuit to divide the PDH error signal of
the cavity by the transmitted power. This allows us to detune the cavity
further from resonance and retain linear error signals.
We tuned a second notch filter board (D000053-00) to 668 Hz to suppress a
violin mode that is sometimes excited.
We measured the transmission of the cavity end mirror to be 9ppm.
New ITMs were received from REO.
Mini-suspension OSEM design was finalized, RFQs
have been sent out.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
e2e-3.0.2
(Hiro) e2e-3.0.2 has been released. A few minor
issues were found after the release, and 3.0.3 will follow soon.
FFTprop_v1.0
(Biplab) A new version (1.0) of FFTprop is now available at http://www.ligo.caltech.edu/~bbhawal/FFTprop/
This Matlab code can propagate light using both
Adaptive-Grid and
ordinary FFT method. New addition is the cavity calculation that
uses these methods. Three examples are there: (1) Simple propagation of beam from COC to Table location or,
backcalculation to know beam at COC knowing beam profile at a table
location (2) Calculation of steady state
light in AdvLIGO cavity when a pure Hermite-Gauss mode
is injected into the cavity (3) Same as 2 except this is for Laguerre-Gauss mode.
Simulation of 40m Advanced LIGO interferometer
(Monica) The dual summation cavity
has been implemented in the e2e 40m package; the
debugging of the package including this new module is almost complete.
Simulations of optical springs effect will be
performed soon as well as simulations of locking strategies.
Alfi
(Melody) Currently working on a new feature to swap
different nodes without removing the connections (PR 280).
Data Analysis Activities (Lazzarini)
Mandic:
I ran the all-sky stochastic analysis on S4 H2L1 data with 192-sec segments
and at 1/32 Hz resolution. I post-processed it using bad GPS times
calculated using 60-sec segments, which should better capture noise transients.
I repeated the same postprocessing on H1L1 data.
Finally, I combined the S4 H1L1 and H2L1 results.
I calculated the H2L1 coherence at 1 mHz
resolution, and the 1 Hz harmonics problems is present, but much smaller than
for the H1L1 case.
I have also written a first draft of the paper discussing these results,
geared for the ApJL.
Shawhan:
- Did
a major re-organization of LIGOtools software,
with various improvements and bug fixes.
- Helped
Alex Dietz with inspiral veto studies.
Sutton:
This week I've done further editing of the LIGO-TAMA bursts paper in
response to comments from Keith Riles.
I'm also working on the cheese paper, concentrating lately on
understanding the uncertainty principle for real 2-polarization signals. The network analysis group met plan testing
and simulations of our pipeline, and to review Tinto's
Bayesian formulation of the detection problem.
Finally, I'm running jobs to test banks of FIR filters for GWB
detection, generating ROC curves for various fcombinations
of filters and GWBs.
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS
The LDAS 1.8.0 release candidate at Livingston
has experienced many lock ups in the diskcacheAPI.
The last 7 lock ups that occurred all had the same stack traces and thread
allocations. This does indicate that there is something about this combination
at Livingston that is causing problems for
LDAS. Several attempt as making the code more robust did not yield a stable diskcacheAPI. As of last night, the three directories that
do not exist on physical media but were in the MOUNT_PT list variable have been
removed from the MOUNT_PT list. Since the change, the diskcacheAPI
has not locked up. It will be monitored this weekend to see if this
configuration change does stabilize the diskcacheAPI.
[It should be noted that this particular issue has not been seen on any other
running LDAS system, including LHO using the pre-release code base.]
On LDAS's main development system (ldas-dev) there were too many versions of ldas software. Investigation of the issue revealed that a cron job entry was absent. With its re-introduction, the
system once again purged all but the last 10 days worth of builds.
Cleaned up several coding issues in the controlMonitorAPI and managerAPI
associated with the proper use of TclGlobus.
Updated createRDS scripts to perform RDS
generation more in line with the method used by Greg Mendell's
script for the purpose of testing. This included adding a loop for generating
the L4 RDS frames.
Ran system test for ldas 1.7.78 and updated cvs with test results. Set up Greg's LHO createRDS scripts to run on cit and dev.
TCLGLOBUS:
Completed GT XIO client/server open and close
functionalities using Tcl channel. I have a simple test case to verify the
functionalities.
Still working on blocking XIO read and write
functionalities. Having an issue passing the data from Tcl application layer down to Globus
layer. The data from Tcl app layer is chopped
off into a segment of 4096 bytes before calling GT XIO blocking read/write
functions.
Began generation of the TclGlobus
release 0.3.0 rpms for FC3 and FC4, for both GT4 and
GT3. Will also provide a patch file for GT4 on Solaris
10 and the documentation for building from source code. This activity is
at the request of the DASWG.
OSG/GRIPHYN/IVDGL:
OSG Council met this week to discuss content of "Plan of Work" to
be presented to the NSF and the DOE this week. LIGO contributed significantly
to the writing of this document through member representation on the Interim
Executive Board, the OSG Council and the LSC Computer Committee.
CIT_CMS_PG installed the VDS components for the LIGO applications. Testing
the LIGO Inspiral pipeline on CIT_CMS_PG has demonstrated a
data transfer rate from the CIT repository of 9 GB/hour while moving the 38 GB dat set.
Using the VDS property vds.transfer = Chain
supports computation while gsiftp transfers are occuring.
DAG node submissions to CIT_CMS_PG have aborted with rescue DAGs in approx- imately four (4)
percent of the submissions to date. Testing with gsiftp
v2 may improve these statistics and are planned.
Nebraska OSG Production system administrator suspects that the LIGO Inspiral workflow may have crashed the head node at that
site. Testing has been suspended to Nebraska
due to this report and because the data transfer rate from the CIT data
repository has never exceeded 2 GB/hour which will be too slow for effective
demonstrations at SC2005.
UCSandiegoOSG_Prod site has asked for a number of
site dependent changes to the Inspiral work flow for
storage managment of the 38 GB data set at UCSD and
the location where executables and data products are placed on worker node
disks. As these requirements are not supported in the disk placement model of
VDS, hand- modification of the gencdag generated
submission scripts and input files will be necessary to meet UCSD requirements.
These requirements are under study.
Ewa Deelman from the ISI
VDS team visited this week. As a best practice, she recommended against pooling
multiple sites for processing an individual Inspiral
pipeline as this requires distributing data to the N sites in the pool. A
better practice is
to map each Inspiral pipeline to a single pool during
gencdag plan generation.
Techniques for third party transfer of archived gravity wave files are being
explored with the VDS team so that this technique can be used as an alternative
to having the OSG cluster pull the data with the jobmanager-fork.
Successfully generated a voms
proxy certificate with the LIGO voms server.
Performed a yum update and reboot of all nodes of
LIGO-CIT-ITB.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Set
up (with Igor's help) the use of distinct fibres
for metadata & /export from the 3510 at LLO.
- After
manually unloading two stuck tapes from the 9940B tape drive in 0,0,10,12, I had STK come out and replace the drive.
- Assisted
with the Solaris 10/SAM-QFS 4.4.5 upgrade at LLO & LHO.
- Figured
out that -fillvsns (maybe in combination with
-drives 2) was causing data to be written to too many tapes at LHO.
- Repacked
tapes at LHO to fix this (still in progress).
- Made
sure that samfsdumps were running every night at
LHO/LLO after the upgrades.
- Modified
the LDR local storage module at CIT to correctly handle L4 frames. Cleaned up incorrectly filed L4 data in
RLS.
- Worked
with Sun to address the problems with SAM-QFS (stat()ing certain files causes reboot & umount of QFS filesystem
causes reboot). 4.4.5 patch fixes first problem, patch for umount problem coming in 4.5. Ongoing.
- Configured
LDR to transfer M8 data to CIT.
- Gave
Dwayne intro to fibre channel, SAM-QFS and LDR.
- Started
data integrity check of M7/M8 data (ongoing).
- Worked
with Steffen to allow him access to CIT data via LDR.
- Restarted
Astrowatch data flow via LDR.
- Got
grid intro from Duncan.
(Phil Ehrens)
- Worked
with Ed Maros to debug intermittent frame file
write failure. Currently testing a
non-threaded frame writing strategy for the Tcl
layer.
- Finished
upgrading ldas-sw-backup.
- Investigated
cause of failure of diskcache API at LLO. Could
not detect anything indicative of the failure mode.
- Installed
hostcerts and keys for user ldas
gateway machines at all sites (except MIT).
- Began
upgrading John Zweizig's desktop machine, Atlas
to Solaris10. The Solaris 10 OS requires >4 Gb of disk space, which Atlas did not have.
Larry provided a Sun Blade 1500 to replace Atlas and I am currently
configuring it.
- Attended
Techmart training at the Caltech ATC office.
- Met
with Duncan Brown and the sysadmin staff to
discuss the installed GRID related tool suites, thier
locations on the LIGO computers, and their configuration.
(Erik Espinoza)
- Updated
LLO sendmail configuration for all public
interface machines.
- Resolved
architecture related issues with v40z.
- Writing
Bugzilla for v40z FC4 SCSI driver problem.
- Updated
Linux sendmail config
for machines behind ldas-dev, working on new solaris config.
- Assisting
LLO with package synchronization.
(Stuart Anderson)
- Working
on problems introduced by the recent Solaris/Fedora Core/LDAS/LDR upgrade.
- Provided
some training for Dwayne Giardina.
- Working
with CIT engineers on the final configuration of the renovated computer
room in Synchrotron.
- Working
on the large cluster CIT procurement.
MIT
(Keith Bayer)
- Build
shelves in order to move DMT nodes (lancelot,
enoki, and old linux
grape cluster nodes) out from the optics lab and into the pump room.
- Installed
Solaris 10 on E450 trying out disksuite
utilities.
- Swapping
out failing data disk on cluster node36.
- Turned
on and minimally tested Foundry switch from LLO.
Livingston
(Igor Yakushin)
- Finished
upgrading the cluster to FC4. There are 6 computers which had hardware
problems and are not fixed yet: nodes 89, 90, 173, 191 cannot use their CD
drives; node122 would not boot, most likely power supply problem; node210
died with a kernel panic twice after dd was
started.
- Disk
5 @3510 failed. The replacement was ordered.
(Dwayne Giardina)
- travel to CIT.
- Overview
of LDAS with Stuart Anderson.
- Overview
of SAMQFS with Dan Kozak.
- Overview
of Grid/Condor with Duncan Brown.
Hanford
(Greg Mendell)
- Level
1, 3, and 4 RDS data for M8 was generated at LLO. The Level 3 and 4 data
has been transferred to CIT. The
raw data will be transferred later this week. The data exist from GPS time
813948928 = Oct 21 2005 11:55:15 CDT = Oct 21 2005 16:55:15 UTC to GPS
time 814079968 = Oct 23 2005 00:19:15 CDT = Oct 23 2005 05:19:15 UTC.
There are no gaps in the raw data. There were some RDS job failures during
the run due to an unknown bug that caused the diskcacheAPI
to hang at times at LLO. This is
being tracked down this week. The createrds
driver script was updated to better handle the job failures, and as a
result there are no gaps in the RDS data, and all the M8 data was
successfully reduced. Further
testing to fix the bug discovered during M8, and to test the S5 channel
lists, will run this weekend.
(Ben Johnson)
- Most
of the old nodes at LHO are up and running user jobs on FC4. Some are
still down, reasons unknown at the moment.
- Got
L1-L4 publishing up and running at both sites again. Trend publishing
delayed pending bug fixes, L0 and /frames publishing should be up today
with the start of realtime segment publishing.
- Contractors
removed the top of the 22-Ton Liebert plenum.
Building noise was reduced only slightly. The contractor has still not
unhooked the 5-Ton Leibert's condensor
from the pipes/concrete. Their boss is on vacation.
- Continuing
to full cable up the 70 new nodes with the goal of installing a working
image of FC4 today.
General Computing (Wallace)
MIT
(Keith)
- Turned
on WEP for wireless hubs in NW22
- Spec'd out and purchased new laptop for scientist
- Installed
solaris 10 on test node
- Built
new firewall router / gateway for local cds
network
- Ordered
various spare parts etc
Livingston:
(Dwayne)
- visiting
Caltech this week, met with everyone, toured the LIGO sites on campus
- overview
of GC at Caltech
- CDS
DNS entries/modifications per request from Lisa B.
(Shannon)
- The
Sun Java Enterprise System saga continues.
I think I have the issue nailed down and will know shortly with a
little more testing. All of this
week has been spent troubleshooting the JES issue other than several
miscellaneous tasks like ordering hardware, a laptop, etc.
Hanford
(Christine)
- Still
working with Gina to get a contract written for the GigE
WAN connection. Gina was able to
get PNNL to agree send her a detailed cost list.
- Tried
to get a Solaris 10 AMD computer set up as a NIS+ client. The keyserv is
not able to authenticate with the NIS+
server. Also had a problem in that
Solaris 10 doesn't automatically start up services like the nis_cachemgr and keyserv.
- Still
working on upgrading the license server.
I'm building it on a new V120 computer and then will just swap the
old computer for the new one. This
avoids lengthy down time.
- The
/tmp directory on the mail server was full which
prevented anyone from getting their mail.
It also prevented me from logging in at the console. A re-boot cleared the directory and
everything is working again.
- Provided
phone support for one user who needed to set up a remote computer to get
his email from LHO.
- Investigating
a "mystery" email for another user. The email doesn't have a subject or from
line and it keeps being re-sent to the user.
CIT
(Mike)
- Ken
Mailand: Worked on transferring over his data
from the old Engineering workstation to the updated Eng. workstation located on the 2nd floor
of West Bridge. I also am looking in to a video issue on
Ken's workstation, regarding a video driver when running Solid Works.
- Burning
Ghost backups of NTSRV's to DVD, to get ready
for end of month backups.
- Working
on a Server for Larry Wallace. This is a Raid Array system that has some
bad hard disks that are making loud clicking noises. They were also coming up with bad
sectors. I have replaced these drives and sent back the bad ones to the
manufacturer to get them replaced. Once
I swapped out the drives I reloaded this server with Fedora 4.
- Spam
Filters: Continuous work with Larry, searching for false positives in the
Spam Filters.
- Setup
some user account and added additional wireless Mac addresses to our
Access Point list.
- Patrick
Sutton: Called Dell to get his hard disk replaced due to bad sectors on
his current hard disk. I placed this service request a week ago and still
have not received his replacement drive. I called Dell again this morning
and they claim there is a problem in their warehouse, and they are
shipping one out today. This is very time consuming process talking to
Dell's tech support to make this happen.
- Other
onsite/phone misc. user support.
(Veronica)
- LIGO: Webcast
/videotaped a suspensions meeting Tuesday morning. Compressing the footage for
streaming. Updates to the NSF
review website. Posting documents
for the review. Updates of the PAC
meeting website, installed a password-protected area. Did some troubleshooting of the machines
at the SCR: Installed the patches on one and ran a scan on both but it
didn't pick up anything. Updates to
the MIT seminars webpage.
- LSC: Updates of the November meeting
website. Updates to the results
page.
- Project
Science: User support. Website updates, posted the remaining
presentation from the last workshop.
(Christian)
- 3rd
flr W/B - Replaced toner cartridges on HP 5500
printer
- Millikan - Replaced toner cartridges on HP 5500
printer.
- Working
on building a WSUS server. WSUS is a web-based application that integrates
with Windows' built in Windows Update client to form a managed patch
distribution system for Windows desktops and servers.
- Other
misc.: Continued onsite software/phone support.
(Larry)
- Worked
a number of procurement issues. In the process of buying equipment for the
40M, DCC and a couple of the users.
Still working the Caltech SUN contract. Received a number of items and have them
distributed.
- We've
started installing the new quad CPU dual core sandbox units. We should
have the first one on-line by next week. We need to make up a shelf for
one of the units to still be installed in the rack. Both units arrived with SUSE installed.
The companies were unable to get Fedora Core 4 and 3 to work on the units.
- Installed
another network switch and KVM unit in the extension computer room.
- Supported
a couple of meetings this past week. One using the teleconference system
took more time than planned. We needed someone to control the phone
system, to mute out locations when they were not needed in order to keep
feedback down to a minimum. The
Italian group participating were able to observe the conference via the webcam which worked out well once the lighting
situation was taken care of.
- Resolved
a couple of printer issues for different people. Everything from paper
jams to updating their printer drivers.
- Copied
data off of an old Sparc Classic running SUNOS
4.1 (being used by the PMA group). The unit was still running solid after
all these years. The configuration of the unit made it difficult for the enduser to get the data he needed but with a few
modifications the data was burned to a CD and now the unit can be turned
over to Caltech.
- Made
a number of modifications to user accounts as well as setup a new user.
- Continual
work on the spam filters. Just of note that the top spam relay systems we
are getting spam from are Caltech and UWM machines, which have been whitelisted because of the amount of legitimate e-mail
we do receive from those machines.
Mail Statistics Oct 20-26, 05
|
Mail Statistics
|
October 20-26, 2005
|
|
Rejected Messages
|
17.706
|
|
Virus Messages
|
679
|
|
False Positives
|
|
|
Accepted Messages
|
16,122
|
|
Total Messages
|
33,828
|
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Systems
Systems
from Dennis
Coyne
See also:
AL
Systems web page
AL Systems email
archives
Records Of Decision or Agreement (RODA)
See also the RODA
status web page
- nothing
significant to report
Requirements
- nothing
significant to report
Interface Issues
See also the "Interfaces" section of the AL Systems web page
- nothing
significant to report
Systems Design/Support
- nothing
significant to report
Vacuum Compatibility & Preparation
See also the Vacuum Bake Lab
Bob Taylor
- I
have delivered the second set of 4 OSEMs for
Reaction mass on the Quad to Mohana.
- I
have done the 2 inter-connect cables for SUS OSEMs
and they are waiting to be picked up.
- I
completed doing the FTIR test samples on the 4 Tube Mount Ends from Astro Pak and Helena
will take them to JPL today. I will began
cleaning these parts today and they should be baking by tomorrow. ( I will detail how and where the test samples were
taken.)
- I
have changed my thinking on using the electric screw driver to clean holes
in parts, instead I will use a air driven rotory tool to do that. I think it would be much
safer. ( no ignition source!)
- I
have 2 of the 4 OSEMs done for the third set of OSEMs for the reaction mass done the other 2 will be
ready tomorrow.
- I
have met with Lee and discussed the cleaning of Calum
and Myrons parts.
- I
think we are on schedule for the controls quad prototype and cleaning the
seismic spacer parts for LASTI.
High-Irradiance, Contamination-Exposure Cavities
Lee Cardenas, Liyuan Zhang
Another absorption measurement for the 4km ITM07 (removed from LHO 4k ITMx) has been completed. Working on data
reduction.
|
Cavity
(Location)
|
Material/Item
|
Start
|
End
|
Comments
|
|
Cavity #1
(OTF Lab,
Bridge)
|
MMG nickel
plated Nd-B-Fe magnets 40 pieces (Helena Armandula, SUS )
|
~6/8
|
TBD
|
Cavity re-alignment is in progress due to power drop and
oscillation. Cavity is
in Standby
~2 more weeks to completion??
|
|
Cavity #2
(OTF
Lab, Lauritsen)
|
NA
|
NA
|
NA
|
No
Change
cavity is close to being ready for samples
|
|
Cavity #3
(OTF
Lab, Lauritsen)
|
OSEM Flexi-circuit cable,
qty ~ 45
(Helena Armandula,
SUS)
supplied by Univ. Birmingham (Stuart Aston)
|
~6/10
|
~9/10
|
No change:
taking daily absorption & ring down measurements
DuPont Flexible Circuits. The whole part to be
constructed of 'flexi' i.e. no 'rigid' sections. (Stuart Aston,Univ. of Birmingham, SUS/UK subsystem)
- Start Laminate: Kapton (LF8515)
(document link: http://www.dupont.com/fcm/products/H-73244.pdf
Coverlay (x2): Kapton
(LF0110)
(document link: http://www.dupont.com/fcm/products/H-73245.pdf
DuPont Pyralux
Series - Kapton / Acrylic Adhesive system.
(document link: http://www.dupont.com/fcm/products/H-73246.pdf
--------------------------------------------------------------
OSEM
emitter & photodiode 40 of each, (Dennis Coyne, SUS
) Test has been completed. Results to be posted by Liyuan
Zhang soon.
|
|
Queue
Priority 1
|
2 Cleaned 50ppm transmission mirrors, 1 in dia., REO coated --
|
TBD
|
TBD
|
witness samples for the LHO vertex volume (added in
6/29/2005 vent)
|
|
Queue
Priority 2
|
Stepper
Motor (Riccardo DeSalvo,
possible SUS or ISC use)
|
TBD
|
TBD
|
Stepper Motor sample had been placed
into Cavity #1: Power dropped from 175 mW to ~25 mW after introducing the stepper motor sample, and
continues to decrease. It is very hard to keep cavity locked. The stepper motor
may have contaminated the mirrors. Will re-test when a cvity
becomes available again.
To be rebaked soon using the self-heating capability of the
stepper motor (not just the oven heater controls)
|
From: Rolf Bork rolf@ligo.caltech.edu
Began working with the Myrinet networking boards
as a possible replacement, in future apps, for our reflected memory networks.
This is a 2.5GHz full duplex network which is laid out as a star switched fabric.
This is as opposed to the reflected memory network, which is a 2GHz serial loop
layout. The Myrinet also provides a feature which allows
one node to send data directly into the local memory of another node, without
the receiver node CPU having to do any work in the data transfer. For testing,
I set up a Ligo type application of a front end sending
data to the Framebuilder. The Framebuilder,
or receiver, code registers memory for receipt of messages and a number of
memory buffers for direct receipt of data. It then essentially sleeps, waiting
for an interrupt from the network hardware that a message has been received. The front end, or sender, initializes by
setting up a transmit buffer and then sending an initialization request message
to the receiver. The receiver code gets the node id from this initialization
request and ends back a message which includes the recievers
memory location for the direct transfer of data. The sender then goes into its 16
KHz control loop, sending data to the receiver once per msec
(1024bytes, which is equivalent to our present limit per front end of
1MByte/sec). The data transmission involves two parts 1) Data directly into the
receiver memory and 2) a control message to the receiver that new data has been
sent and information on where the data is to be put in the frame. The reciever gets an interrupt when the message part is
received, and moves the data to the Framebuilder
accordingly. In this test arrangement, the sender uses less than 1usec of CPU
time to move its data into the send buffer and start the transmission of data
and the control message. Once the NIC is commanded to send the data, it takes
care of moving the data out of CPU memory space and onto the network and the
local CPU is free to move on to other things. Similarly, the receiver takes about
1usec after reciept of the message to decode the
message and move the data to the proper location in the frame. The time from
start of transmission to receipt by the sender of an acknowledgment message
that indicates that the whole transaction completed successfully is about
23usec. The computers used for the test were a Sun V40 and Sun V20, both
running realtime Linux.
From: Jay Heefner <jay@ligo.caltech.edu>
AdL SUS SEI and DAQ
- The
boards for the Anti-Image filters chassis and Anti-Alias chassis have been
received and will be sent out to Screaming circuits for stuffing on 10/28.
The stuffed boards should be received back by 11/4. Once received they
will be installed in the chassis and tested.
- Jay
and Alex will be visiting LASTI starting Nov 14 in preparation for the
quad and SEI controls installation. Racks have been requested from LLO.
Seismic Isolation
Advanced LIGO Seismic Structure
A purchase order was issued to Limerick Machine for the actuator mounts and
locator/lock subassemblies.
The hole pattern on the drawing and model for the
optics table was changed from 1150 1/4-20 helicoil
inserts on a 2x2 pattern to 4400 3/8-16 helicoil
inserts on a 1x1 pattern. An amendment to the purchase contract has been
issued.
A visit was made to Arland Tool to go over the
contract and technical issues with the large machined parts. All the material
has arrived and engineering is currently creating CNC programs.
Joe Giaime <jgiaime@ligo.phys.lsu.edu>
Agenda for the weekly SEI telecom
Friday, Oct 28, 2pm Eastern, 1pm Central, 11am
Pacific time
Announcements
BSC SEI status, Ken/ Dennis
- PO issued for actuator mount / locators assemblies.
- PO issued to Nor Cal for pod enclosures. Vender will leak-check each item before shipment.
- Amendment
issued to large part vender to account for 1" x 1" hole pattern on optics table. Extra cost is $10k.
- Drawings
prepared for Jay, so he can design the internal pod harnesses. Jay
still needs to see the devices. They should be shipped to him in a
week or so.
- DCNs in preparation for all of these changes.
BSC work (Rich M)
- FIR
filter trainer simulator in simulink is
running. Next step is optimize the filter
parameters by using the simulator. After that, we can try on the
hardware.
- LHO
work: STS-2's placed on crossbeams at end stations. He is trying to
close 1-DOF active isolation loop. They might also consider putting
the STS-2 on the floor, in a box, and trying sensor correction to the fine
actuators, added in with tidal.
HAM control with VME (Pradeep)
- Working
on control law design for HAM HEPI.
ETF platform work - Matt DeGree
- Stage
1 control laws being constructed. Pitch and roll implemented.
The other four under way.
- William
preparing temperature sensors to be installed in ETF. Dennis has an Algor model that can be used to interpret the measurements,
after some modification.
Seismometer work - Aaron
- Ordering
materials, doing mechanical design calculations.
Other news?
- Mike
Thielvoldt working on suspension design for an interm upgrade.
- Shyang has designed resonant gain filters for the BSC
chamber HEPIs, to add gain in the geophone path
around the suspension pos resonance and two stack modes. ITMX goes
unstable with the resonant gains, and will require more
modification. AS_I sees excess around 0.5 Hz when the resonant gains
are enabled.
Suspension
From: Ken Mailand kmailand@ligo.caltech.edu
I have demonstrated a bearing setup for Calum, he
asked me to follow up, and modify the suspension fixture rotating table, and
after a meeting with Oddvar re. the
design, to incorporate other modifications to the fixture.
Im working on a vertex BSC layout for Mike Smith
that will show stay clear areas inside for the beam path.
From: Helena Armandula ahelena@ligo.caltech.edu
Core Optics
No report.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
Although the circumstances of the laser failure are not clear, at least not
to me, it appears that something went wrong with the fibre
optic setup that allows communications between the controlling computer and the
temperature controllers in each diode box. The manufacturer of the system
was contacted. The laser is back up and running
although the output power is around 130-150 W.
Auxiliary Optics
From: Michael Smith <smith@ligo.caltech.edu>
I am in the process of reworking the development schedule and man power
requirements for the SLC, PO MIRROR/TEL, INITIAL ALIGNMENT,
OPTLEV, OMMT, AND VIEWPORTS subsystems of the AOS.
Other Laboratory R&D
From: Riccardo DeSalvo
<desalvo@ligo.caltech.edu>
Juri
I wrote a document for LMA in which are analyzed various options for the
design of the “spherical” Mexican Hat mirror for our cavity.
I wrote a Mathematica program for the calculation
of optical cavities eigenmodes without assuming
cylindrical symmetry. This could be another instrument beside FFT to study the
effects of misalignment and real mirror maps on the modes shape and spectrum of
optical cavities.
The program is working well but Mathematica is not
optimized for matrix calculation and an accurate simulation requires too much
memory. I’m translating the program in Matlab
which seems much more efficient for this kind of calculations. First tests are
very encouraging.
Chiara
We prepared the material (maragin steel plates for
the blades) for the hardening process and we started the baking on Monday.
Since now I've back all the instruments I'm going through measurement of the
transfer function of the system. I found the resonance of the bottom level so
now I can control the amplitude of the signal from the actuator in different
frequency ranges.
For additional information about this report, contact Stan Whitcomb or Phil Lindquist