Weekly Report for
Week Ending October 20, 2005
The LIGO Executive Committee meeting for October 24,
2005 is cancelled for the Staffing Committee meeting scheduled for that day
and time.
Special Announcements:
Weekly
Report Highlights
No report.
LIGO Laboratory Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
LSC MOUs and Research Plans and Progress Reports
- Saulson has been reviewing the MOU's
that I submitted to him in September for approval, and has just about
completed the group that I submitted. Of those submitted, minor changes
were made to ACIGA, Balearic, CaRT, CEGG,
Columbia, Stanford, Syracuse, and TexasB, and
they have all been posted.
- I'm
still working on changes for GEO, IUCAA, Michigan,
Moscow, NAOJ, Oregon,
Penn State, Sannio,
and SLU.
Non-LSC MOUs (Lloyd)
SITE TELECONFERENCE (Lindquist)
A site teleconference was held Thursday, October 20, 2005. The following issues were among those
discussed:
- The
list of assigned actions updated through September 1, 2005 (the last time
that the actions were statused) will be found Here. There
are no open action assignments
- FY
2006 budgets were discussed during the Executive Committee meeting on
October 17. To first order the
budgets presented were deemed adequate for proceeding. Minor iteration will continue
- Property—the
computers are up and working in the temporary space at Livingston. Remodeling of the computer room is in
progress. Bids are needed for the
HVAC upgrade.
- Note If materials are procured for
different sites on a single purchase order and one of those sites is
Caltech, then sales tax will be charged at the California
rate for the total PO. To avoid being charged excess sales tax,
such POs should be separated. Ed Jasnow accepted an action to send a statement to
LIGO-all pertaining to this issue.
PROPERTY MANAGEMENT (Chargois)
>From: Ed Chargois <chargois_e@ligo.caltech.edu>
- Provided
assistance to the Detector Group (J. Romie) by
preparing a request to CIT's Carpentry Shop to
construct a crate 9.5"x16.5"x25.5" to ship a LOS structure
to MIT (G. Harry), all phases of this process are complete. Account Number LIGO.SUS 5.10
NSFLIGO.FY02ON.
- Provided
assistance on two (2) occasions to the Detector Group (H Armandula) packing and shipping nine (9ea.)
2"dia. Windows coated for "S" polarization and 2"dia.
coated substrate (E040514-L1, 4ea) Lenses and E040512-B1 (9ea.) B/S-50/50
"P" to LHO (D Cook). Account
Numbers P204324/P204422.
- Provided
assistance on two (2) occasions to the Detector Group (H Armandula) packing and shipping four (4ea.)
2"dia. Windows coated for "S" polarization and 2"dia.
coated substrates (E040514-L1 (2ea.) lenses and E040512-B1 (9ea.)B/S-50/50
"P" to LLO (V Frolov) Account Numbers
P204324/P204422.
- Prepared
a Report of Excess Personal Property (SF 120) for the National Science
Foundation (Michelle Gerald) to remove the Carrier Air Handling Unit from
the LHO.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
- Worked
on the cost justification for selection of File Hold over other bidders
for the issuance of a contract with File Hold for a document management
system.
- Continued
to review areas of current database needing to be cleaned up or prepped
for upcoming migration to new system.
- Continued
monitoring ongoing scanning tasks with Annie, Jim and Cleveland.
>From: Cleveland Mak mak_c@ligo.caltech.edu
|
Week Ending
October 20, 2005
|
In
|
Out
|
|
Packages
|
31
|
9
|
|
Faxes
|
23
|
22
|
- Processed the large number of presentations from
the 2005 Gingin Workshop on Gravitational Wave
Detection.
- Assisted
in sending out an RFQ for "Fabrication for Advanced LIGO Seismic
Isolation System Blades and Flex Rods."
- **Scanning
Project Update** - Progress continues on Larry Jones' boxes of files. A lot of prep work is being done prior
to scanning. With that being said,
we are looking to reduce prep time as much as possible. To date, we have 3 of 16 boxes scanned.
COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Completed
change order #2 to the CSIRO subcontract for the no-cost extension through
10/1/06. Submitted the change to the vendor.
- Completed
change order #1 to Excel's time and material. Received the signed Supplemental
Agreement back from Excel.
- Working
with LIGO Livingston Observatory on a return and replacement of two
computer monitors. The replacement
has been sent out and the returns will be shipped out.
- Working
on the three new subcontracts: Cangelosi Ward, Arland, and Limerick.
- Working
on the change order to MIT.
- Completed
change order #4 to Ezus Lyon 1 and submitted the
change to the vendor.
- Reconciled
the October report for Pcard which consisted of
22 transactions totaling $18,351.49 and submitted the completed report to
management for approval. The remaining open pcard
orders are current and only go back to late September '05.
>From: Florence Kaufman <fkaufman>
- Prepared
a summary of discussion during Executive Committee meeting on Monday, October
17th pertaining to FY05 budget approval.
- Submitted
a Fabrication Equipment Request for the Computer Cluster at Caltech.
- Financial
reports can be found at: http://docuserv.ligo.caltech.edu/~fireport.
(For passwords contact Florence)
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone <gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow <jasnow@ligo.caltech.edu>
- We have
received the signed contract from Cangelosi-Ward
for the construction of the LLO
Science Education
Center. The contract is now being processed for
signature by Caltech. The
contractor is also submitting his performance and payment bonds for the
job, which will allow for the issuance of a Notice to Proceed. The planned Notice to Proceed date is
Monday, October 24, with a kick-off meeting tentatively set for Wednesday,
October 26, at LLO.
- Eskew-Dumez-Ripple, architects for the LLO SEC, are preparing a proposal for additional construction
management on site.
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
- Processed
the paper work for two (2) new/revised trips. At this time there are eight (8) trips
completed or in the works but are awaiting the necessary paper work to
enter the P-Card system.
- Completed
twenty (20) Expense Reports and there zero (0) reports yet to be
done. I continue to contact
travelers who have outstanding Expense Reports (more than one (1) month
old) to ask for their cooperation in sending me their receipts so that
these can be closed in a timely manner.
Presently there is only one (1) report more than thirty (30) days
old. I have two (2) reports
awaiting signature at this time.
Worked on copying and recording all the expense reports completed
last week to be sent to Travel Audit for final auditing and payment.
>
>Dorothy Lloyd
- Processed
the usual invoices for payment and followed up on problems.
- Processed
the usual requisitions for purchases over $10K and standard POs, as SOS
buyer, for those under.
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
NSF Review (Lindquist)
The NSF Review is scheduled for November 9-11, 2005. I am collecting materials to be sent to the
reviewers in advance. Contributions
should be provided no later than Monday, October 24.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- A staffing Committee meeting is scheduled for
Monday, October 24. The DRAFT
agenda has been posted. All files
are posted and up-to-date on the web page..
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
No report.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of
Commissioning Activities at LIGO Hanford
Observatory (compiled by M. Landry)
Better performance on both machines was observed during the week, with H1 at
times in excess of 10Mpc, and H2 beyond 4Mpc.
Commissioning highlights are bulleted below:
- activity
in the optics lab (adjacent to the 4k mode cleaner) increases 1.5 and
1.6Hz stack modes as seen in MC sensors, but did not appreciably raise the
noise level (upconverted or otherwise) in DARM_ERR
- various
forms of sledgehammer
were tested against burst coincidences seen in S4; forklift-induced
seismic noise best resembles the coincidences seen in H1-H2 AS_Q and
microphones
4K IFO
- Friday
14th marked the return of some of the best locking we've had in a
while. ASI_CORR was improved
over past weeks, after a careful recentering the beams on the antisymmetric
port photodiodes. Some of the problems we've encountered in the past
few weeks may have been due to slight re-alignments suffered by the
installation of heavy meat lockers on the technical slab. MMT3 are
PSL periscope mirrors show evidence of a dodge around installation time.
- ASPD2
has been shown in the past to have a problem region on the middle of the
diode, an thus when running, we risk drifting
into to a bad regime. Despite that spare photodiodes are the new
kind that may(!) induce AS_I latching, we'll swap
this one out and see what happens. Multiple PDS on 4k have such
problem spots, probably due to burning. When this installation of
ASPD2 is done, the beam will be expanded some (as was done on H2 already)
to reduce the energy density on the PDs.
- the
PSL NPRO power supply was swapped out, and chiller hoses shortened
- to
better understand and match the high frequency calibration at ~37kHz, to
that of the low frequency calibration (our standard 10Hz-7kHz), a high f
(37.5kHz) calibration line was injected
via the coil drivers
- the
REFL beam stabilization servo was commissioned
- S5
hardware injection code was tested;
it was shown that the impact of burst/inspiral
injections on IFO duty cycle would be less than five minutes per day
- Bias
modules of the large optics were retrofitted
with power-supply protection. Cooling fans added a factor of 20 in
low frequency noise so we'll maintain standard running configuration: fans
off, racks open. We can't typically run in science mode for long
with closed racks.
- In
order not to impress extraneous noise on DARM via the MICH correction, the beamsplitter dewhitening
compensation was modified from "design" to the inverse
of the "as-built" dewhite. Next:
the RM and the PRC correction.
2K IFO
- ISCT10
remains floating, and the idea is to leave it that way for the science
run, unless long term drifts are shown to be problematic
- Nice
save! a new trigger feature was added such that ASPDs can transition
automatically from run photodiodes to ASPD5, saving the IFO from unlocking
and the associated downtime of rerunning fullup
scripts.
- Noise
above 400Hz was better
for reasons unkown. Another look, here.
- Super-polished
2" optics were swapped
in on ISCT10.
DAQ/CDS
- no
long-term drift is observed in the new timing system; see the 20 day trend
here
- new
code went in, one feature added was the AS port shutter with RF trigger,
as described above in the 2k section
Outreach (D. Ingram)
LHO welcomed astronaut Bonnie Dunbar for a visit
on 10/15/05.
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
L1 Interferometer (Zucker for a cast of
thousands)
A virtual commissioning frenzy:
- The
excess 1/f2.5 noise reported last week was traced to a failed
DAC driving the beamsplitter and recycling
mirror with glitchy spikes. Coincidentally, this occurred in the
middle of the bias module protection retrofit, confounding the diagnosis.
- We
got the new, latest & greatest noise budget code running
- One
component is a more realistic estimate of the OSEM noise coupling,
unmasking it as the dominant source of the "wall" at low
frequencies. Better OSEM POS
filtering knocked down the wall somewhat.
- The
wiggly WFS problem noted for some time (trouble getting through power up,
excess sensitivity to trains) was tracked to divergence between the
"UNOL" filters and the optical levers they are supposed to
model/invert. Not only was this fixed, but a script was built to keep them
within tolerance for ever and ever.
- The
REFL2 common-mode sensing chain (using the non-resonant sidebands at 66
MHz) was commissioned and found to work spectacularly. It is clear that
the lock point is optically closer to the carrier optimum; SNR is about 10
dB better, no "Q" phase overloading, etc, etc. We are setting aside "plan
B" (which was to run a REFLQ
servo to patch REFL1, like the ASI servos on the dark port)
- Some
new HEPI resonant-gain filters were installed to further reduce
susceptibility at pendulum and stack resonant modes. These should further
improve robustness against trains and construction activity.
- New
low-scatter, wide-aperture optics were installed on the antisymmetric port.
- With
everything working well again at 5W into the MC, it was decided to raise
the laser power. To get back the 20% loss incurred two weeks ago during
the laser cleaning incident, the pump current was raised (there's still
some headroom). This brought the laser power up to 10.3 W out of the head
which is pretty close to where it had been.
- Unfortunately,
greed set at that point and an attempt was made to get even more by
realigning the MOPA from scratch. A new alignment was converged but with neglible power improvement. Even worse, the new
alignment required different alignment for the FSS path and PMC, and seems
to also want different modematching into the
PMC. This detour cost us a couple days.
- Plan
is to push to 8W into the MC this weekend.
CDS (Bogue)
- Installed
gamma ray burst code. Configured the new channels into l1iocstat because
it is our only solaris ioc and it is complicated to build a new on.
- Helped
resolve problems with the TCS servo channel outputs.
- Updated/corrected
the reflpd channels - Installed new state vector
code to support injections - Built a new solaris
box for injections called lloinj - Built 3 solaris boxes for use in the lvea.
- Got
with Szabi to reprogram the atomic clock. I
can't get a serial connection into it, so I have a call into tech support.
- Put
my cds jumpstart server through its paces. This
server allows me to quickly roll out control workstations -- about 2 hours
per box but only about 15 minutes of work on my part.
- Offered
my support to Alex on last friday's
code drop. I must say that Alex did such a spectacular job that there was
nothing for me to do.
Computing and Network Security (Roddy)
The LDAP & Java Enterprise services rollout has taken quite a bit longer
than I had hoped for. I had hoped to be
able to shift back over to security concerns at this point. There are a couple of subtle mistakes that
are easy to make, even after reading many of the documents available from Sun
(there are about two dozen manuals, each 100-1200 pages). If one explicitly follows their deployment
scenario for a test installation, one of the subtleties can be a "deal
breaker" for deploying the mail server.
Unfortunately, there is no easy way to back out this configuration
problem, so the only solution is either to completely uninstall the directory
server installation & reconfigure, or start fresh from a cleanly installed
machine. The problem arises from the
configuration of the "administrative domain" on the root of the
Directory Information Tree. If there are
duplicate entries, the administrative tools for adding users, mail domains,
aliases, etc. will break. Additionally,
I found that a native LDAP Solaris client will have issues with the DIT
configured this way. I discovered the bug
yesterday, and worked all night on the issue.
I ran through a test installation with the suspected fix and it appeared
to work. I will be starting this evening
on deploying the DIT and JES with this correction and will then hopefully have
it deployed by the weekend. Most of the
user accounts and modifications are scripted now, so the majority of time
required to install the system is configuration of the services, SSL, etc.
Contacted Sun about a service contract for this software. The quote was a bit higher than I had hoped
for, but might be worth it. At least for the first year.
The PC that was found to be infected with a mIRC
& DDoS bot last
week was cleaned and no further evidence of bad traffic has been seen on the
network since. I have been keeping a
close eye on the IDS system since.
CDS Code Support (Khan)
No report
Education and Outreach (Thacker)
Attended Assoc of Science & Technology Ctrs
(ASTC) annual conference
Site Safety and Security (Riesen)
No report.
HPLF (Franzen)
HPLF news: Tested the 100 W laser for the first
time since the hurricanes. No problems so far. Started to set
up a small test of LZH TFPs.
#MEZ TLA 411: "Laser Zentrum Hannover Thin Film Polarizers"
General Computing (Giardina)
- Rode
shotgun while Shannon cleared a PC of a mIRC bot.
- Norton
would not install on one laptop.
Clearing the registry of anything "Norton" or
"Symantec" (no other Symantec products were installed on this
machine) allowed installation to run after reboot.
- Shannon
and I installed a WAP in the visitor travel trailer.
- Installed
Kantech, repaired Office 2003 install, and
migrated files on Rich Riesen's new PC.
- Installed
Adobe Acrobat Pro on a laptop.
AdL SUS/SE Mechanical Engineering (Spjeld)
Quad SUS Installation Fixtures
- simplifying
parts to reduce cost and lead time of prototype manufacturing in progress
- meeting
with Calum and Ken Mailand
on 10/18 to discuss design progress and manufacturing
LDAS/Condor and data analysis (Yakushin)
Storage/Condor/LDAS Admin
- 3510's
upper controller is replaced. This time it came up fine.
- Upgrading
Linux machines to Fedora Core 4, SUN machines to Solaris 10.
LDAS/Condor sysadmin (Giardina)
- Replacing
disks in nodes with reported disk problems. I will send a complete list upon
completion.
- Nodes
139 and 84 will not boot even after replacing disk, cable and swapping
memory. I will continue to
troubleshoot these nodes after I bring up as many of the others as
possible.
- Finished
labeling all the new nodes.
- Ordered
two replacements disks for T3-13 from Sun.
Case Number: 64780765
- I
will be visiting CIT next week, Oct 24-28
Initial LIGO Detector Science & Engineering (Coyne)
CDS
see also the CDS weekly meeting
minutes in the commissioning
archives
CDS Software
Rolf Bork
- Loaded
new LSC code with shutter controller trip output on LHO2k. It appears to have some problems and we
are still debugging.
- Once
this last change is stable, we will download new code to LLO. We will work with Rana
and Lisa remotely i.e. not travel to LLO, unless we encounter problems.
- Debugged
latest LSC code w/output to fast shutter (undersized array was causing problems). This
code is now fixed and running on LHO2k and LHO4k.
- Added
another useis filter module for LHO4k ETM
controllers. This code was loaded at LHO yesterday.
- Rana noted aliasing in decimated DAQ channels on ETMs at LLO. It turns out that I forgot to set the
compiler flag that enables decimation filtering on the ETMs.
This was fixed on LHO4k yesterday with the new ETM code. This code will be
updated on LHO2k and LLO4k during CDS maintenance next Tuesday.
- All
of the latest code changes will be loaded at LLO next week. Remaining
items are LSC w/shutter output, Fast ADCU, and decimation fix for ETM
controllers. As far as I know now, these are the last changes prior to S5
(possible exception a Hepi change??).
CDS Hardware
Jay Heefner
Refl Beam Stabilization
The new interface boards have been received and are being stuffed. A full
chassis should be ready for shipment to LHO by Monday. The others for LLO and
spares will follow over the next week.
Ben Abbott
LSC RFPD
Todd finished testing, and delivered the last of the requested RFPDs to the sites.
Fast Shutter
The machine shop has finished the mechanical portion of the shutters. I am
performing some minor modification on these, and then will begin the assembly
and testing of the electronics parts (assuming that the parts arrive soon).
ISS PDs
I've finished the assembly of five units that are needed at Hanford
and Livingston. Tests indicate that they are
functioning fine. I need to write up some paperwork on the testing done to the
ISS PDs, and then they can be sent out to the sites
sometime this week.
DMT
John Zweizig
Last week I set up for and participated in the M7 mini-run at LHO. After installing the most recent
version of all DMT monitors, I went on to verify that the monitors were
correctly configured and that everything was running smoothly. Several problems
were discovered with the newly revamped trigger and segment generation and
fixes for these problems were made. These fixes were checked offline, but not
installed online. I am now updating the LHO installation with these and other
changes in preparation for the M8 run at LLO.
40 Meter Interferometer (Weinstein)
To celebrate the full lock of our interferometer in the nominal Advanced
LIGO configuration, we had a party at the 40m on Wednesday. There was quite a
crowd, including many people who made major contributions to this effort, and a
good time was had by all. Thanks for coming to help us celebrate!
The 40 Meter Technical Advisory Committee report from the meeting on
10/13/05 is here
(pdf). Slides presented at the meeting are here (pdf).
IFO commissioning
- As
reported last week, Osamu finally brought the 40m into full RSE
configuration, with the arms and PRC in full resonance, last Thursday.
This was accomplished, despite considerable noise, through careful loop
shaping and gain optimization as the CARM signal was transferred from
transmitted light DC to the POX RF and the offset was slowly brought to
zero.
- On
Monday, Rob and Matt achieved full lock via a different path, using the
POX RF signal to control the analog common mode servo. Because of the high
bandwidth of the analog servo, they reduced the noise enough to make lock
acquisition relatively easy and robust. Longest lock seen: 128 minutes.
Generally locks last until they are broken by operator, dumptruck or earthquake. Unfortunately, there have
been several local quakes with mag > 4 in the
last week.
- Both
Osamu and Rob and Matt took CARM and DARM transfer functions, noise
spectra, etc. There is a clear RSE peak in DARM, and also in CARM with an
offset. It should be at 4 kHz, but (depending on lock) it can be as low as
3.4 kHz. Rb and Matt tried to adjust offsets to
move the peak, with only limited success. Under investigation.
- For
non-zero CARM offset, there is a clear loss of optical gain at frequencies
below 50 Hz, which hampered lock acquisition for a long time. It appears
to be consistent with an optical spring effect (as predicted
quantitatively by Kentaro). We don't see a peak
where we expect it (~50 Hz), but that could be due to larger-than-modeled
losses.
- Rob
and Matt automated the lock acquisition procedure. One manual step
(unplugging a cable on the common mode servo) was eliminated when Ben implemnented a switch on the board. Now, the detector
can be brought to full lock via script, quickly and reliably. The only
hard part is the pre-alignment. We need a better pre-alignment procedure.
- The
lock slowly drifts away from its correct point, presumably due to
alignment drift. We need an in-lock alignment sensing system!
- The
asymmetric port spot looks awful, presumably due to misalignments, mode
mismatches, offsets, etc.
- Rob
and Osamu compiled a long list of near-term to do items, including
pre-alignment and autoalignment, mode matching,
and also a comprehensive approach to setting correct offsets, demod phases, gains etc.
- Dan
is gearing up to work on developing the noise budget model.
IFO modeling
- Kentaro made some plots to illustrate the CARM and transfer
functions, exhibiting optical spring peak and low-frequency-falloff, with
varying CARM offset. We need more predictions for varying optical loss,
and also for DARM.
DC detection development
- Mike's
assembly drawing for the OMC is complete. A drawing package is being
prepared for release to the DCC.
- Steve
is investigating the costs for machining Mike's output mode cleaner design
in copper, which is a low-Q material that is high-vacuum-compatible.
- We
received a pair of REO mirrors from LHO, and Liyuan
measured the transmission to be T=1.55%, resulting in an output mode
cleaner finesse of around 200. This is good enough!
- We
also received REO HR mirrors from LHO, but they're for 43.5degrees
incidence, we need them for near-0degrees. So we're ordering broadband superminrrors from Newport.
Electronics, controls
- Dan
and Ben are working on implementing the RevB
coil drivers on the mode cleaner suspensions.
- Dan
continues to work on suspension diagonalization
and performance evaluation. Wiring is going in, and the 4116 DAC is in
place. The EPICS database and screens are in progress.
- Ben
implemented a switch on the Common Mode Servo, so that one of two input
signals can be switched off when the other is ramped up. He made some
modifications to the board, and installed some cross-connect wiring. He
then modified the database, and screen. Rob tested it out in place, and it
is working fine.
- Rana is trying to acquire a new generation (Sigg) Common Mode servo board for us.
Lab Infrastructure
- Steve
reports that, at long last, rain gutters and downspouts have been
installed on the 40m roof.
Thermal Noise Interferometer (Black)
This week we vented and opened the chamber,
and began working on the transmission of the arm cavities.
LASTI (Ottaway)
No report.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
Weekly E2E Physics Meeting
Biplab talked about 'Diffraction Losses in
Advanced LIGO' based on his LIGO note currently available at
http://www.ligo.caltech.edu/~bbhawal/Blair/T050234-00-E.pdf
Sany Yoshida presented results from modeling of
Seismic Isolation System. There was also discussion about Modal model
calculations.
AdvLIGO Seismic Isolation
(Sany Yoshida) Continued AdvLIGO seismic isolation e2e modeling. Our e2e box
file now shows reasonable impulse response for ground x and ground y
displacement inputs. With this box file, we computed the displacement of the
seismic isolation stage, using actual, calibrated ground x and y displacement
signals recorded at LLO HAM1 chamber via the corresponding DAQ channel. The
time series of the resultant stage 1 and stage 2 displacements vary from -6e-9
m to +1e-8 m at about 0.15 Hz for the computation time of 10 sec. The LIGO I
BSC table x and y motion that we computed for comparison using the e2e BSC
stack model with the same ground x and y input signal vary from -3e-9 m to 3e-9
m at about 1.4 Hz. The frequency series of these computations indicate that the
1.4 Hz peak observed in the LIGO I BSC stack completely disappears in the AdvLIGO seismic isolation (both in stage 1 and stage 2),
whereas the signal level in the entire 1 - 10 Hz range is improved by an order
of magnitude (in stage 1) and another factor of two (in stage 2). Around 0.15
Hz, there is a peak of the same level as the LIGO I BSC case.
AdvLIGO Work
(Hiro) Scattering noise estimation is being
estimated using twiddle and e2e. The design of FFT modeling is in progress.
Modeler
(Hiro) Validation of dual_sum,
fast simulation of dual recycled Michelson is done. During this validation, a
limitation of the use of macro was identified (mystery solved), and alfi will be modified to prohibit defining macros in
instances as an workaround.
Version 3.0.0 is posted in the e2e download folder. This is mainly for users
who are hit by the bug in 2.5.0. 3.0.0 is still alpha
level quality and modeler_freq needs to be
implemented even in a quick and dirty way.
(Melody) Documented Matt's modeler scripts for remote
processing.
Alfi
(Bruce) Completed work on node validation, specifically,
the checking of all nodes in the system for unresolved connections which are
associated with bundlers (PR 495).
(Melody)Currently working on a new feature to swap
different nodes without removing the connections (PR 280).
Data Analysis Activities (Lazzarini)
Shawhan:
- Attended
a workshop on LISA data analysis methods.
- Reviewed
changes made to papers: S3 untriggered burst
search, S2 LIGO-TAMA burst search, S2 Hough
transform pulsar search.
- Studied
accelerometer channels for use as vetoes in S4 analysis.
- Added
a program to lalapps to apply vetoes as part of inspiral analysis pipelines.
- Generated
list of veto time intervals for S4 H1 inspiral
analysis based on recommendations by Gaby Gonzalez.
- Continued
to work with Vuk Mandic
on preparations for hardware signal injections during S5.
Yakushin:
Mendell:
- I am working SFT
generation for S5. In the past week I have checked into lalapps CVS these file, MakeSFTs.c,
Makefile_MakeSFTs,
scripts/MakeSFTDAG, scripts/datafind.sub,
scripts/MakeSFTs.sub
scripts/onasysd.MakeSFTsA4H1.sub, and scripts/onasysd.MakeSFTsA4H1.ini,
under lalapps/src/pulsar/MakeSFTs. The script MakeSFTDAG is a python script that will be used with onasys to generate SFTs.
However, I also will add command line arguments to allow generating DAGs for offline generation of SFTs
as well. Other options, such as Hann windowing
of overlapping SFTs will be added when I get
time. The first working version will generate version 1 SFTs, but once that it is working it should not be
hard to add the option to output version 2 SFTs
for S5. These files are still currently under construction, but I hope to
have this running on astrowatch data by the end
of next week.
Mandic:
- I have performed the
stochastic all-sky analysis on S3 H1L1 data with 1/32 Hz resolution. I
have also calculated the S3 H1L1 coherence at 1 mHz resolution. The results indicate that S3
H1L1 is not suffering from the 1 Hz harmonics. However, some structure has
showed up in the H1L1 coherence which was not observed in the past. I plan
to study this further to check if this structure is real.
- I have also updated the
new code to be used for hardware injections during S5. Several minor bugs
were removed, and we reduced the time-overhead to less than 36 seconds per
injection. Several tests were performed at both LLO and LHO.
Chatterji:
Sutton:
- This week I modified the
LIGO-TAMA bursts paper according to the PRD reviewer's comments. The
new version and a response to reviewer have been circulated in LIGO and
TAMA. I'm editing my paper on the LIGO cheese and GWB characterisation.
- I've continued working on
the coherent network burst search project with Chatterji,
Tinto, Searle, focusing mainly on understanding
Bayesian formulation of the problem, and demonstrating equivalence of
maximum likelihood and null stream approaches.
- I'm also working on Matlab script to compare various FIR filters for burst
detection.
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS
LDAS now has support for server to server X.509 certification using TclGlobus. This will all the controlMonitorAPI server and the managerAPI
to connect through secure GSI sockets using the X.509 host certificates.
Several issues with using the X.509 certificate for authentication in
conjunction with using the old username/password interface have been solved. In
particular a user can bounce back and forth between the two in a single session
if desired.
Fixed an issue wiht the managerAPI not checking if an API is to be part of a
running LDAS system before attempting to extract information from the API.
Updated DB2 documentation to reflect the version of DB2 to
be used in the next LDAS release (8.2.2). Enhanced documentation for
installation of third party software found in LDCG.
In the process of upgrading the LDAS systems at LLO, LHO and CIT with the
new database and resource files in preparation for the new LDAS release.
Ran all system tests on the nightly build for version
1.7.76. Still an issue with renaming .tmp to .gwf in the concatFrameData
command. Efforts to isolate the bug associated with this test failure continue.
The first fix resulted in the frameAPI freezing up
about once a day.
Continuing to wait for the Solaris 10 and Fedora Core 4
upgrades at the sites to take place before releasing the next version of LDAS.
Now looks like early next week is the soonest this will take place.
TCLGLOBUS
Currently developing "TCL Channel" support within TclGlobus for the Globus XIO
open, close, read write and a few other key functions for use in LDAS.
Finished a test case to exercise the TCL Channel client
use of the open and close operations. This has been tested against the
existing "raw" Globus server developed for
unit testing of XIO. The client successfully connects and disconnects from the
server.
Developed a test TCL Channel server which is able to open
up a listening port. Still working on detailed implementation
of the server to handle new incoming client connections.
OSG/GRIPHYN/IVDGL
A demonstration of the Inspiral pipeline
application on OSG has been planned for Supercomputing 2005. OSG planners have
asked the application providers including the LIGO OSG team to provide an
application to support load ing the 15000 (potential)
compute nodes on the OSG production grid.
Working with OSG and site administrators from non-LIGO sites:
CIT_CMS_PG, Nebraska
and UCSandiegoOSG_Prod verified that the LIGO VO is
supported at those sites.
Edited and published a web page detailing how to install the VDS components
necessary to support the LIGO Inspiral pipeline
application, at sites participating in the OSG Challenge at Supercomputing 2005
by supporting the LIGO applications.
Nebraska
and UCSandiegoOSG_Prod sites installed the VDS
components for the LIGO applications.
Submitted the Inspiral pipeline DAG to the Condor
pool at Nebraska
and UCSandiegoOSG_Prod sites. The Inspiral
pipeline DAG failed to transfer all data to Nebraska and failed to run to completion at UCSandiegoOSG_Prod. Testing of gsiftpv2 as a more
reliable ftp protocol is being examined in conjunction with staff of Nebraska. A
detailed analysis of a run at UCSandiegoOSAG_Prod is
planned for next week.
Submission of the Inspiral pipeline DAG to a
Condor pool comprised of PSU and UWMilwaukee failed
with a DAG node at UWMilwaukee aborting but not
returning the error to the submission system. More detailed analysis of this
failure is planned for next week.
Tested voms-proxy-init with the
LIGO voms server. Sent
failure message to voms administrator at PSU for
further analysis and debug. (Late-breaking-news: Murali
has now fixed this at PSU!)
Performed a yum update and reboot of all nodes of
LIGO-CIT-ITB.
Hardware Systems (Anderson)
Caltech
(Phil Ehrens)
- Worked with Ed Maros to debug intermittent frame file write failure.
Discovered a thread safety issue related to Tcl's
'trace' facility. Removing the trace call from frame::writeFile
put an end to the intermittent failures.
- Cleaned up "High Bay" in synchrotron with
Stuart Anderson and Erik Espinoza.
- Debugged issues with
Apache/Subversion that were causing errors to be logged and preventing
transparent challenge-less read/write interaction with repository.
- Upgraded versions of
Apache/OpenSSL/Subversion on Dziban
to patch subversion bugs and to test recently stabilized OpenSSL support for proxy certificates.
- Discussed nature of proxy
certificates and globus certificate management
with Scott Koranda during his visit at CIT on
10/17.
- Worked on unified Big
Brother/Logwatch extension/replacement code that
will be used by sysadmins to monitor all
platforms and systems. This package will consist of a client/server model
log analysis and reporting suite that creates web page reports and
optional email reports. Access to the web pages will be restricted by
password. Dynamic filtered reports based on regex
will be available via URL. Maintenance and configuration of this system
will be required only on gateway machines, with internal machines updated
automatically based on rules defined at the gateway. Primary design
concerns are minimal resource utilization and minimal perceived
"nagging."
- Worked with Ed Maros to clean up some remaining ssh configuration issues on the ldas-tandemN systems.
- Worked with Ben Johnson at
LHO to help clone cluster disks. Wrote a script that removed any
requirement for handwork on the individual systems other than to run a
single script with a single argument.
- Worked with Ed Maros to resolve new issues related to failure of
frame files written by the frame API to be complete. The resolution has
been postponed until the LDAS 1.9 release, since the actual scope of
changes required is not known.
- Updated ldas-sw-backup to Solaris 10. Mostly complete except
for mirroring of internal drives.
(Erik Espinoza)
- Wrote scripts to configure
cluster nodes to send mail for LHO.
- Still debugging kernel
options with v40z.
- Contacted Sun about Fedora
Core kernel issues.
- Writing bugzilla report for fc4 and possibly vanilla kernel.
- Reading over documentation
on System Imager to become more familiar with our current deployment
infrastructure.
(Stuart Anderson)
- Working with Vendors to
obtain price quotes for the next CIT cluster.
- Helping with the
Linux/Solaris/LDAS/SAM-QFS upgrade at LHO/LLO this week in preparation for
S5.
- Updated several security
patches on Solaris.
MIT
(Keith Bayer)
- Building Sol 10 machine.
- Received 3 blade boards
for foundry switch from Caltech.
Livingston
(Dwayne Giardina)
- Replacing disks in nodes
with reported disk problems. I will send a complete list upon completion.
- Nodes 139 and 84 will not
boot even after replacing disk, cable and swapping memory. I will continue
to troubleshoot these nodes after I bring up as many of the others as
possible.
- Finished labeling all the
new nodes.
- Ordered two replacements
disks for T3-13 from Sun.
- I will be visiting CIT
next week, Oct 24-28.
Hanford
(Greg Mendell)
- The new HVAC system at LHO
is running, but causing a fair bit of noise in the offices in the new
building here. I am working with staff here and the contractor on ideas of
how to mitigate this. Robert Schofield and I did a very quick check on
whether this is also having an effect on the siesmic
noise, and tentatively found that it produces the 3rd highest peak in the
seismic spectrum near 30 Hz. Robert doesn't think this is problem for the IFOs, but we plan to do more testing. The unit is on
spring isolators.
- I am also preparing to
generate Level 1, 3, and 4 RDS data for M8 at LLO.
(Ben Johnson)
- Upgrading cluster to FC4.
All 210 nodes will be upgraded.
- Installing Solaris 10 on
gateway and dataserver.
- Continuing to work with
Duncan Brown on getting ldbdbd + publishing
working.
- There was a data gap in
fb1 for several minutes early Wednesday morning. The cause is presently
unknown, will investigate further once the upgrade(s) in ldas-land are complete.
General Computing (Wallace)
MIT
(Keith)
- Added WEP back to wireless
hubs in NW17
- Troubleshot NFS problems
on gall
- Looked into VPN trouble
with visitor
- Investigated specific promail setup for scientist
- Troubleshooting late model
thinkpad
LLO
(Dwayne)
- Rode shotgun while Shannon cleared a PC of a mIRC
bot.
- Norton would not install
on one laptop. Clearing the registry of anything "Norton" or
"Symantec" (no other Symantec products were installed on this
machine) allowed installation to run after reboot.
- Shannon and I installed a
WAP in the visitor travel trailer.
- Installed Kantech, repaired Office 2003 install, and migrated
files on Rich Riesen's new PC.
- Installed Adobe Acrobat
Pro on a laptop
(Shannon)
- The LDAP & Java
Enterprise services rollout has taken quite a bit longer than I had hoped
for. I had hoped to be able to shift back over to security concerns at
this point. There are a couple of subtle mistakes that are easy to make,
even after reading many of the documents available from Sun (there are
about two dozen manuals, each 100-1200 pages). If one explicitly follows
their deployment scenario for a test installation, one of the subtleties
can be a "deal breaker" for deploying the mail server.
Unfortunately, there is no easy way to back out this configuration
problem, so the only solution is either to completely uninstall the
directory server installation & reconfigure, or start fresh from a
cleanly installed machine. The problem arises from the configuration of
the "administrative domain" on the root of the Directory
Information Tree. If there are duplicate entries, the administrative tools
for adding users, mail domains, aliases, etc. will break. Additionally, I
found that a native LDAP Solaris client will have issues with the DIT
configured this way. I discovered the bug yesterday, and worked all night
on the issue. I ran through a test installation with the suspected fix and
it appeared to work. I will be starting this evening on deploying the DIT
and JES with this correction and will then hopefully have it deployed by
the weekend. Most of the user accounts and modifications are scripted now,
so the majority of time required to install the system is configuration of
the services, SSL, etc. Contacted Sun about a service contract for this
software. The quote was a bit higher than I had hoped for, but might be
worth it. At least for the first year.
- The PC that was found to be
infected with a mIRC & DDoS
bot last week was cleaned and no further
evidence of bad traffic has been seen on the network since. I have been
keeping a close eye on the IDS system since.
LHO
(Christine)
- Submitted an
"Agreement for use of a privately owned computer as a LIGO work
computer" to Stan for review. He had a couple of changes,
that I am working on.
- Received an invoice from
PNNL for the GigE network services. Gina is
putting together a subcontract based on the information in the invoice.
- Nothing new with the 10
Mb/s backup network. Still unable to get a link
between LHO and PNNL. PNNL has requested LMSI inspect the fibers. I doubt
there is anything wrong with the fibers as these were used two months ago
for our OC3 network. Everything else checks out ok, so we have to inspect
everything.
- Updated the patches on a
Sun computer that was missing libraries required to run Thunderbird.
- Will be upgrading the
application license server from Solaris 8 to 9 on Saturday. This impacts
all the CDS computers which mount the server. Saturday was selected
because the frame builders will be down for disk installs.
- Installed Symantec AV 10.0
on a couple more computers.
CIT
(Veronica)
- LSC: Updates of the
publications database. Updates to the November meeting website.
- LIGO: Compressed the NASA newsconference footage for streaming and burned some
extra copies of the DVD. LIGO website /roster database updates. Brought up
to date various lists of email aliases. Updates to the NSF review website.
- Project Science: User
support.
(Mike)
- This week I worked mostly
on going through old computers in my office, fixing hardware problems to
see what I could salvage, and surplus the rest. I ended up putting
together three computers, and turned over four to Ed Chargois
to surplus.
- Spam Filters: Continued
work with Larry Wallace, going through the Spam Filters searching for
false positives.
- Inventory on printing
supplies. I placed an order with Gina Salone,
ordering toner cartridges for all buildings.
- GC Server Room: Installed
a new KVM switch, and started switching over servers to this new switch.
Plus additional misc. work that went on which consisted of moving
equipment around to make room for additional equipment, and moving
equipment downstairs for Ed C. to surplus. I also worked with Larry
installing additional equipment in room 19 across the hall from our Server
Room.
- Onsite user support that
consisted of software installs, trouble shooting software, printing, and
some hardware issues.
(Christian)
- Linda turner- Linda is
using Thunderbird as her default e-mail program andneeded
all of her old emails from Eudora imported.
- 3flr W/B - Configured
visitors' workstation with the engineering Ligo
image.
- Wilson House - Replaced
old blurry monitor with new CRT.
- Millikan
- Replaced toner cartridges on HP 5500 printer. Updated 4 loaner laptops
to the Standard Ligo image and Microsoft's
latest patches.
- Other misc.: Continued
onsite software/phone support.
(Larry)
- Resolved a number of
contract issues. Still need to go over the CISCO contract. Working on the
CIT s/w contract renewal for the SUN equipment. Received and started
installing equipment that was ordered some time ago. Most of the equipment
is going into the new computer room. Spent a great deal of time trying to
get paperwork and numbers to match on the P-card reconciliation. Still not
receiving invoices in a timely manner from many companies. Placed a couple
of new orders for the LDAS group.
- Installation of equipment
into the new room has been more of a challenge than planned. It looks like
things will go a little better with some of the changes that have been
made.
- Updated and helped Mike
install some equipment in the computer room. We are trying to get the room
setup to where it is a little more convenient to work in the room. Worked
with Ed and the others on removing a number of old pieces of equipment.
- Spent time on a number of
different file and printer issues. One problem we've been able to narrow
down to a font problem with the Mac. Another problem we ran into this past
week was another Microsoft Office file that would go from a PC to a Mac
cleanly. This is something we will probably have to look into in more
detail in the future.
- Cleaned up a number of
accounts. Modified a few accounts for different users.
- Worked on a couple more
backups and restorations for different users.
- Continual work on
different e-mail issues. Updated the anti-virus engine.
Mail Statistics for Oct 13 - Oct. 19, 2005
|
Mail
Statistics
|
October 13 - 19, 2005
|
|
Rejected
Messages
|
20,234
|
|
Virus
Messages
|
2396
|
|
False
Positives
|
0
|
|
Accepted
Messages
|
15,043
|
|
Total
Messages
|
35,277
|
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Project Management
From: Jay Heefner <jay@ligo.caltech.edu
AdL SUS, SEI , CDS
- The
design and layout of the anti-image and anti-alias chassis needed for
LASTI has been completed and sent to the board house. The boards are due
back next week.
- Initial tests of the PCI-X ADC and DAC cards is very promising.
The input referred noise for the ADCs is ~9uV/rtHz on a 40Vp-p input and a
sample rate of 16384Hz. This is more than a factor of 5 better than the penteks. If the sample rate is increased to 128KSPS
and then the data decimated to 16384SPS, the input referred noise drops to
~2.5uV/rtHz on the same 40Vp-p input. This compares very favorably with
the ICS110B. The board itself is a 32 channel differential input,
simultaneous ADC board and the cost is ~$3900. A quick check of the DAC
output referred noise shows that it is in the 1uV/rtHz range on a 20Vp-p
output. The sample rate is 16384Hz. This board is a 16 channel
differential output board with a cost of ~$3500.
- More
detailed measurements of the boards will be conducted in the coming weeks.
- One
off-shoot of the tests is the discovery (by Rolf) that the CPUs purchased
for the LASTI controls are capable of supporting servo controls and sample
rates much higher than 16384Hz. This possibility will also be investigated
in the coming weeks.
- We
have a telecon with Alberto Gennai
of VIRGO scheduled for 10/20. The subject will be an introduction to VIRGOs plans to develop low noise ADCs and DACs. We are hoping that there are some common ideas
and concepts that we can share between the two projects.
From: Rolf Bork
<rolf@ligo.caltech.edu>
More testing of the PCI-X ADC module using the quad
suspension code. This ADC has 32
channels and +/-20V range. Running at 16KHz, the input
referred noise came in at slightly over 9uV/rHz. I then turned the sampling
clock on the ADC up to 128KHz, ran the samples through
a 7KHz low pass IIR filter and passed every 8th sample to the front end
code. With this setup, the input
referred noise was decreased to 2.5uV/rHz.
With the added load of reading samples at 128KHz
and doing the decimation filtering, the time to process one cycle in the quad
control software increased from 16usec to 24usec. Besides demonstrating that
the front end CPU has enough horsepower to do this type of filtering and still
run at 16KHz, it is also an indication that we should
not have a problem running the ponderamotive controls
at the desired 32KHz rate.
Seismic Isolation
|
Assembly
|
Status
|
|
Top Assembly Components
20007970-A
Stage 0 Assembly
2000795-A
Stage 1 Assembly
20007825-A
Stage 2 Assembly
20007825-A
|
Purchase order placed with Arland Tool for all large parts. Material has been
ordered and will be in by 11/1
Purchase order placed with Limerick Machine for the end milled plates and
remaining Top Assy, Stage 0,1, and 2 Componants.
|
|
Stage 0-1 Spring Assembly
20007878-A
Stage 1-2 Spring Assembly
20007890
|
Fabrication drawings are complete. Drawings must now be
checked.
RFQ for blades and rod flexures complete, awaiting quote.
Maher Limited holding maraging steel for blades and
flexures
|
|
GS-13 Pod Assembly
20007810-A
L-4C Pod Assembly
20007820-A
STS-2 Pod assembly
20007941-A
|
Geophones, seismometers and lockers are in house.
RFQ complete for vacuum housings, awaiting bids. Quotes due 10/21
RFQ complete for machined components. Quotes due 10/21
RFQ required for internal pod harnesses.
|
|
Stage 0-1 Kinematic Lock
20007941-1-A
Stage 1-2 Kinematic Lock
20007941-2-A
|
Tooling design complete.
RFQ complete, awaiting bids. Quotes due 10/21
|
|
Stage 0-1 Actuator Assy.'s
20007966-A
20007967-A
Stage 1-2
Actuator Assy.'s
20007968-A
20007969-A
|
Tooling design complete.
RFQ complete, awaiting bids. Quotes due 10/21
|
|
Stage 0-1 Standoff Pin
Stage 0-2 Alignment
Tower
and Washer
Stage 2 Keel
Plate
Alignment
Tower
Blade Pre-Load Tooling
Blade Calibration Fixture Modifications
LASTI Test Stand and Spreader Bar
|
Solidworks part files exist for
the standoff pin and alignment towers. They will require a dimensioned
drawing and checking prior to soliciting bids.
The blade pre-load tooling and calibration fixture tooling will require
redesign following the redesign of the blade springs by ASI.
Purchase order for test stand issued to Southern Enterprises. Delivery to MIT
by 11/14.
|
From:
"Joseph A. Giaime" jgiaime@ligo.phys.lsu.edu
Agenda for the weekly SEI telecom
Friday, Oct 21, 2pm Eastern,
1pm Central, 11am Pacific time
BSC SEI status, Ken/Dennis/ Joe
- Venders
for first three jobs have started work. Material for big pieces has
been ordered.
- Actuator
mounts and locators bids are in. There is a clear winner, within
budget.
- Pod
vacuum housings bids are in. We need to study the bid specs together
with the bids to determine the winner.
- Official
package has been sent to blade/ blade material vender.
- Vender
expects that the 1" x 1" optics table hole pattern change order
will cost us about $5000.
- inside-pod parts are expected to cost only a few
thousand, and ken will handle it informally.
- Caltech
has received parts for the BSC spacer for the SUS controls prototype, and Astropak has cleaned them to mil-spec 1246
"A/10" and packaged them in a poly-somethingorother
bag. RGA scan of smaller parts at Caltech doesn't look very
good. They will also do an FTIR test. Caltech will re-clean
and air-bake all parts. So, the lesson is we should ask for A/100,
and clean-foil wrapping.
- Suspension
controls quad prototype cage undergoing modal testing, clamped upside-down
to a 10 ton milling base. Lowest mode is 52 Hz rather than the
FEA-modeled value of 80 Hz. This is under study, and the results may
alter the design for the noise prototype. For example, the model may
not have adequately taken bolt compliance into account. Calum has verified that the bolts were tight, though.
BSC work (Rich M)
- Foil-wrapped
clean parts have been found to have dry powdery, sooty residue. It
easily wipes off, and we remember seeing similar stuff on the LIGO-1
seismic parts. MIT will ship an example to Helena, who will arrange
to have it analyzed.
- Rich
has been working on the Simulink model, and my abandon it and switch to straight Matlab.
- Feedforward experiment result in today's LASTI
log. At high frequencies (ca. 15 Hz), the feedforward
is probably also perturbing the chamber sensor. Maybe at lower
frequencies, too.
- Rich
M to spend next week at LHO to work on possible PEPI-like installation.
HAM control with VME (Pradeep)
ETF platform work - Matt DeGree
- Matlab installation was fixed on platform
computer. No other news.
Seismometer work - Aaron
- Matt
working with Aaron on seismometer design study, on thermal compensation in
particular.
Electronics - Jay
- finished anti-alias and anti-image boards for LASTI SEI
and SUS.
- ADC
input-referred noise with 40 Vp-p input is 9 microV/rtHz, or a
factor of 5 better than Pentek. Sampling
at 128 kSa/s and decimating in software, it is
2.5 microV/rtHz, same range as ICS-110B.
DAC is 20 Vp-p, and is also in microV/rtHz at 16kSa/s.
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
Working with Helena, Caroline and Norna
on the Ribbon/Fiber/Ear/Bonding documentation and questions.
Joe Hanson boxed up the XY translation stage and the air bearing for Calum and Mike Gerfen. They
should receive them on Monday. I've sent pictutes to Calum of the components this morning.
Rich Riesen gave me a refresher safety briefing
and a tour of the buildings.
From: ctorrie <ctorrie@ligo.caltech.edu>
Quad Controls Prototype
Tim Hayler from RAL visited to learn about the
assembly of the quad. Mark, Tim and I started with a fully assembled quad and
within 3 to 4 days we had taken it apart down to the individual mass level and
fully re-assembled it, suspended it and aligned the chains. This took as long
as 4 days as we also measured the centre of gravity, measured the position of
the blade tips and weighed the various configuration
for each suspended stage.
Tim has written a draft assembly procedure, a follow up to our original
document, covering in detail all of the steps during the above processes. The three of us have reviewed it and Tim will
distribute once he has updated it.
Ian and I have been meeting to discuss the issues wrt
the blades and clamps.
2nd Quad Structure
Tim, Mark and I have measured the modes for the overall structure in various
configurations as well as the upper structure on its own. Full
results to follow. We will need
to complete some FEA to compare to these specific configurations.
Installation fixtures
Ken Mailand, Oddvar and I
have been meeting bi-weekly to discuss the proposed prototype installation
fixtures. We hope to have all of the drawings completed by Tuesday.
Drum ended wires
The new test set of drum ended wires have been sent to RAL for further
testing. RAL will break test the wires and follow a series of steps suggested
to them by the design team. I will release a technical note covering all
aspects of our testing up to this point in the next week or so.
Visits
Tim returned to RAL earlier today.
Core Optics
No report.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
PSL
Nothing significant to report as I was assembling and
testing shutter timing modules.
AdvLIGO PSL
Last Sunday the temperature
control system for the high power stage malfunctioned. A number of
components have been changed out and at present it is not [shown as provided
–pel]
Auxiliary Optics
From: Michael Smith
<smith@ligo.caltech.edu>
Reviewed the AOS Cost book and discovered numerous cost inconsistensies.
Will discuss these issues with Carol W. and Dwight C. on
10/20/05.
Other Laboratory R&D
From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>
Yumei Huang ,
Visiting grad student from Beijing
Normal University
just joined the group. In the next few weeks she will figure out where to best
contribute to the activities.
Marco Tarallo
Successfully defended his thesis, graduating cum Laudem. He
will proceed writing the paper after the Graduate studies acceptance
exams. The thesis will be available
soon.
Alberto Stochino,
Will defend his 3rd year thesis next week.
Juri
I started an independent analysis of elastic properties of the multilayer
optical coating in order to cross check the formulas found in literature and
apply some results to the Genetic optimized coating. I’ve worked on
various issues on thermal noise calculations and eigenmodes
solution for general optical resonator.
Chiara
I wrote the technical note about the hardening process for Maraging steel.
I started the measurements of the transfer function of the "test
table" system.
Valerio
We have improved our Simulink library of SimMechanics models of the HAM-SAS. Now all the subsystems
of the HAM-SAS mechanical structure are present in the library. We can now
build custom structures just connecting together the subsystems with the
appropriate joints. At the same time we are contacting Mathworks
to better understand the origin of our simulation problems: we have designed a
very simple example that gives meaningless physical result and sent it to the
technical support. Unfortunately we have not received yet satisfying
explanations.
For additional information about this report, contact S. Whitcomb or P. Lindquist