Weekly Report for
Week Ending October 13, 2005
The LIGO Executive
Committee Agenda for Monday October
17, 2005 will be:
(Meeting time: 10:30 am Pacific Time)
Announcements
Comments on Weekly
Report
LSC Issues (Saulson)
LIGO Lab
Operations
- Administration
(Lindquist)
- Sites
(Raab, Zucker, Shoemaker)
- Commissioning
(Fritschel), Detector (Coyne)
- Campus
Research Facilities
40-Meter (Weinstein)
TNI (Libbrecht)
LASTI (Shoemaker)
- Data
Analysis and Computing (Lazzarini)
R&D and Advanced
LIGO (Shoemaker)
CHANGE CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION AS
NEEDED
Special Items: Status
of Advanced LIGO Budgets for FY 2006.
Special Announcements:
Weekly Report Highlights: Last night, after much work by Rob, Rana, Matt, and Osamu, Osamu locked the 40m in the full AdLIGO configuration.
He repeated it, 4 times. Longest lock was ~ 20 minutes. See below.
LSC Issues (Saulson)
No report
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
Non-LSC MOUs (Lloyd)
SITE TELECONFERENCE (Lindquist)
- A
site teleconference was held Thursday, October 13, 2005. The following issues were discussed:
- FY
2006 Budgets – Site budgets seem to be acceptable within $20,000
magnitudes. There continue to be
uncertainties with regard to budgets for commissioning support and travel
in support of science running. MIT
requests have been received and will be entered into the budget model. The primary open issues relate to
Advanced LIGO and Advanced R&D needs.
We will meet tomorrow to review the current status. The status will be queried during the
Executive Committee meeting on Monday.
- Property
Issues – The LDAS Computers are on site in Livingston. Some shipment damage was experienced and
is being reported. Livingston is in the process of firing them up and
checking them out.
- The
list of assigned actions updated through September 01, 2005 will be found Here.
PROPERTY MANAGEMENT (Chargois)
>From: Ed Chargois <chargois_e@ligo.caltech.edu>
- Nothing
significant to report.
DOCUMENT CONTROL CENTER
(Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
Nothing significant to
report...same projects as highlighted last week.
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- Assisted
in sending out three contracts ("Advanced LIGO Seismic Isolation
System", "Document Control and Management System", and
"Seismic Isolation System Miscellaneous and Wall Components").
- Assisted
in sending out the RFQ for "Fabrication for Vacuum Housings for the
Pod Assemblies" to 2 additional companies.
- Processed
and distributed 2 DCN's.
- **Scanning
Project Update** - Progress continues in the preparation, organization and
scanning of of Larry Jones' old files..
- Activity:
|
Week Ending
10/13/05
|
In
|
Out
|
|
Packages
|
26
|
12
|
|
Faxes
|
31
|
10
|
FINANCIAL SYSTEMS (Cronin, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- There
is a TechMart training session scheduled for
October 26, 2005 through the main Procurement office for many LIGO individuals.
If you would like to attend a TechMart training
session and have not yet signed up, please contact Monica Marquez at ext.
2566 for scheduling. There is a new website that provides on-line training
at http://www.atc.caltech.edu/finance/PPS/techmart/
which may provide useful information and supplement your training.
- Provided
basic training in preparing a requisition and approving it in TechMart for two LIGO individuals so that a new order
could be submitted and approved. The requisition was submitted, approved,
and the order has been placed and the bulk of the order has shipped.
- Finishing
up the reconciliation process on the billed credit card orders for October
2005 in preparation for the reconciliation due next week. There are only
two pending invoices, so far, that I am waiting for responses to complete
reconciliation.
- Completed
two computer maintenance orders issued to Dynamic Systems for the first
year of a 5-year agreement for LIGO hardware and software maintenance
support located here at Caltech.
- Working
on completing change order #1 to the JPL work order for Helena so that additional work can be
performed by JPL.
- Working
on finishing the remaining four no-cost extensions for Garilynn.
>From: Florence Kaufman <fkaufman>
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone
<gsalone@ligo.caltech.edu>
- Nothing
significant to report.
>From: Ed Jasnow
<jasnow@ligo.caltech.edu>
- We
are still waiting for the receipt of the signed contract from Cangelosi-Ward contract for the construction of the LLO Science Education
Center. The contractor sent it out earlier this
week.
- The
architect for the Livingston SEC is preparing a proposal for the
performance of construction management on the project.
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
>
>Dorothy Lloyd
- No
report (sick).
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
PROPOSALS and REPORTS (Lindquist)
The Request for supplemental funding for the Outreach
Building in
Livingston has been
enhanced one more time and submitted to the NSF.
DCC Steering Committee (Lindquist)
The purchase order with Synergy for the new document management system and
related hardware requisitions are in process.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- No
special activities to report. The
Staffing Committee meeting is scheduled for October 24, 2005.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
Nothing significant to report this week.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of
Commissioning Activities at LIGO Hanford
Observatory (compiled by M. Landry)
M7 ran last weekend with mixed success. H1 (H2) ran with ~65% (~60%)
up time, or ~50% (~43%) of the run in science mode. Lock stretches were
short on H1, often clipped at several hours, and falling shy of the S5 range
target by several Mpc. The IFO performance was
sufficient however to test DMT monitors, the mandate for the run, and new codes
were exercised and reviewed (see the elog Oct 7-8).
We would like to welcome Malik Rakhmanov
of Penn State,
who has moved to Richland
for an extended stay at LHO.
Commissioning highlights are bulleted below:
4K IFO
- Recall
from previous weeklies that ASPD saturation and AS_I latching issues were
hampering H1 performance. As a test, it was decided that we should swap
back in the old ASPD4 photodiode and see if the situation
improved. Indeed the latching problem has gone,
however, we still have saturations that last for a fraction of a second
that drop the range by many Mpc. So, what
is the difference since the 11.6 Mpc days of
September? One change appears to be that AS_I sits atop a larger DC
offset than before.
- Re:
1Hz lines and subharmonics. We ran with
the 1PPS ramp off during M7: the glitch previously observed in the error
signal went
away but the lines in the control signal remained present. We
look forward to the timing groups sinusoidal
replacement to the ramp signal.
- a
report on the recent REFL beam stabilization efforts is given here
2K IFO
- saving both locks and photodiodes through better
triggering: new LSC code was loaded to trigger the AS fast shutter and
switch back to ASPD5. The code was problematic and backed out for
modification.
- ASPD4
modifications were made
DAQ
- many H1 and H2 CDS processors had new code loaded
on the Monday bootfest, including modifications
to power
sequencers
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
The MOPA laser power started fluctuating erratically by 15 percent last
Thursday causing problems for the interferometer. After cleaning the laser
cooling lines the power fluctuations went away but the beam alignment into the
power amplifier was changed, either during the cleaning or as a result of
temperature change of the master oscillator cooling plate. Re-alignment of the
beam into the power amplifier mostly restored the output power (85% of the
pre-cleaning level).
Another side effect of the cooling line cleaning was excess acoustic noise
in the PSL enclosure from the air trapped in the chiller hose. The coupling for
this noise appears to be surprisingly large, so that it appears in the
interferometer dark port spectrum. The air was driven out by re-connecting the
chiller lines and the acoustic peaks were reduced below the interferometer
noise floor.
The alignment bias modules were upgraded in order to reduce the output noise
and provide better protection against power supply failures. Unfortunately,
coincident with this upgrade a new noise contribution appeared in the frequency
range between 50 and 200 Hz, which is consistent with a pinkish force noise
source (spectrum in displacement falls like f**-5/2 and is essentially
stationary). Investigation of this new noise source is underway in parallel
with efforts to improve frequency noise rejection at high frequencies.
Some other excess intermittent noise in one of the anti-symmetric port photodetectors was tracked to a missing solder connection
on the shield of the RF cable.
The reduction of the low frequency (below 1 Hz) relative motion of HAM1 and
2 was demonstrated by adjusting the angular HEPI correction on HAM2.
CDS (Bogue)
- Installed
new state vector code with the help of Dave Barker.
- Helped
Sam W. with getting the right channels to support his REFLPD work. This is not completely resolved yet.
- Built
a script/ssh server for
cds. I
have not yet migrated the accounts and scripts from other boxes to this
one yet, but the box is installed and available.
- Worked
more on the new raids. There are
some scsi problems that
need to be worked out.
- Restored
data from the backup frame builder after ldas
had a hardware failure.
- Cleaned
and organized the spare parts cabinet in the mass storage room.
CDS Code Support (Khan)
Ash is on vacation this week.
Education and Outreach (MZ for Thacker)
John is at the American Science-Technology Centers annual meeting in Richmond, VA waving the LIGO Science
Education Center
flag.
Site Safety and Security (Riesen)
Most of this reporting period was consumed with the safety/security system
software change over. The site is now
using the new software and all functions are operational. There was some work-around needed due to the
fact the new software has a bug and a new "bug-less" version will be
available around the first of next month.
Updated and posted the Laser User Authorization signage.
Found no laser or site safety concerns during my weekly site walk thru.
LLO General Computing (D. Giardina)
- Kantec software upgrade: had a few problems with the new version
that took a couple days of trial and error testing possible
solutions. Situation temporarily
resolved.
- Assisted
Bonnie with more html documents.
- Norton
will not install on one laptop.
Situation was reported this morning. I am looking at it today. Will advise
when solved.
AdL SUS/SE Mechanical Engineering (Spjeld)
Quad SUS Installation Fixtures
- redesigned
lift table support brace, lift arm, transport table support frame
- meeting
with Calum and Ken Mailand
regarding redesign and manufacturing plan of fixtures
- updating
additional parts and drawings in progress
- uploading
revised files to PDM Works vault in progress
LDAS/Condor and data analysis (Yakushin)
Storage/Condor/LDAS admin:
1) The 140 new nodes are installed. Working on changing IP
addresses and various configuration files. At least 4 nodes have obvious
disk problems and would not boot. The others at first glance are running but I
expect badblocks to find more bad drives.
2) The temporary HVAC (10 tons extra to whatever the building's handicapped
HVAC can currently provide) so far was able to handle the load (all 210 nodes).
However, the generated heat would increase as the new nodes start executing
jobs. The estimated repair time for the building's HVAC is 2 weeks.
3) T3-19 went down on Saturday night. Powercycling
it on Sunday morning brought it back to life. However, syslog
showed memory problems with the controller. The controller in T3-19 was
replaced during Tuesday's fb1 downtime.
4) It turned out that the upper controller in 3510 (that was replaced by SUN
a week ago) never actually came up. I would need another fb1 downtime to either
try to reseat it or replace it again.
5) Got quotes for service contract for the old 15 ton unit from Star.
Data analysis:
1) Revisited LIGO-GEO SG21 simulation triggers to understand the problems
that Siong found in hrss(H1)
vs hrss(H2) plot (besides
the expected diagonal line, there was and extra line at a different
angle). It turned out that that line was
due to the injections that were outside of waveburst
frequency band.
2) Studied a set of LIGO-GEO production triggers in which GEO detector is
shifted by 17 seconds in addition to the standard set of time shifts done by waveburst. Found a problem in the way I did that
shift. Corrected the bug and
regenerating the triggers now.
Initial LIGO Detector Science & Engineering (Coyne)
No report.
40 Meter Interferometer (Weinstein)
There was a meeting of the 40 Meter Technical Advisory Committee (by telecon) on Thursday, 10/13, at 8:30 am Pacific. We
reviewed the status of lock acquisition, e2e simulations, and DC readout design
and procurement. Slides here (pdf).
Nergis reviewed a proposal to inject squeezed
vacuum into the 40m interferometer, sometime next spring. Slides
here (ppt) and proposal here (pdf).
IFO Commissioning
- There
was steady progress towards full lock of the 40m, with Rana,
Rob and Matt (RRM) working at night, Osamu during the day.
- RRM
implemented the analog common mode servo (using the REFL DC signal) to the
PSL AOM (the MCL path), with a UGF @ ~3 kHz, (still being tweaked). They
got a factor 10 rejection of noise at ~ 200 Hz. The only CARM actuation on
the ETMs is a slow script servo to keep the
analog MCF error signal close to zero.
- They
then were able to reduce the CARM offset, to the point where the power was
~ 80% of the way to full arm resonance. That brought them "over the
hump" of the REFL RF (166I) signal; they saw the signal rise and then
fall towards zero as they reduced the CARM offset. So, when they manage to
smoothly hand off the signal from REFL
DC to REFL RF, we're pretty
sure it will bring the ifo
into full resonance. But it's tricky to hand off the signals in the analog
servo (would be easy with the digital servos). Much of this success was
due to careful loop filter shaping.
- RRM
deliberately misaligned the arm cavity so that any beam jitter would
couple more strongly to the arm cavity error signal. But they did not see
any change in the noise above 50 Hz. They conclude that beam jitter (eg, from noisy in-vac PZT
steering mirrors) is not a significant contributor to the noise aboe 50 Hz. The PZT mirrors could still be introducing
significant frequency noise, present on the arm cavity error signal but
not the mode cleaner error signal (the mirrors are in between).
- Osamu,
meanwhile, was using the POX+POY RF signals to control CARM and reduce the
offset. Switching from TRX+TRY DC signals to POX+POY RF is now easy and
routine. After much careful loop shaping, he was able to also "get
over the hump". Late Thursday night, he at last brought the IFO into
full resonance, ie, full AdLIGO
configuration. He was able to hold lock for many minutes, and regain lock
when lost. Arm light power was ~ 78 (arb units),
very close to our expectations given the losses in the arms. He took
transfer functions (clear RSE peak, no sign of an optical spring peak) and
noise spectra. Hooray!
IFO Modeling
- At
the 40m TAC meeting, Ken emphasized the importance of reliable e2e
modeling to address a variety of important issues in AdLIGO.
DC Detection Development
- Mike
has completed the part drawings for the output mode cleaner, and awaits a
decision on the material. We want a well-damped material, so that the PZT
driving does not excite the mode cleaner body resonances too much. We were
considering brass, but Dennis, Dave Tanner and other TAC members cautioned
us against it, due to poor high-vacuum properties. Seems like copper is
the best choice, so we are now investigating availabiliy,
cost, and machining issues.
- Rob
and Rana are thinking about the design of the DC
PD electronics, preparing for potentially large power (up to 250 mW).
- Rick
and Betsy at LHO have sent us two REO supermirrors
with T=1.4%, and five HR mirrors (at 43.5degrees incidence, P-pol) for our output mode cleaner. We need the HR
mirror to work at ~ 10 degrees, P-pol. Helena and company
will test the HR mirrors at different angles; they may work quite well.
Along with a curved mirror from Peter King, this means we have all the
mirrors we need for the OMC.
Electronics, Controls
- The
ETMY oplev laser diode died. Dan changed it out
and got the oplev servo working again.
- Dan
and Ben are preparing the hardware and software to at last install RevB coil drivers on the three mode cleaner
suspensions. These have separate bias and drive paths, so the diagonalization procedure will not throw off the
alignment of the mode cleaner.
- In
preparation for moving the MCR RF PD to greatly reduce the beamline length (and therefore the potential for
misalignment and clipping), Bob put in new RD PD cables on the AP table.
- Ben
has delivered new RFPDs for the sites, and is
now preparing 4 new ones for us.
- Ben
continues to develop the design for his fast meachanical
shutters.
Lab Infrastructure
Thermal Noise Interferometer (Black)
No report.
LASTI (Ottaway)
No report.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
Weekly E2E Physics Meeting
Sany Yoshida presented some
preliminary results from the e2e model of seismic isolation system for AdvLIGO and comparison with Matlab
model from Stanford (details below). The mathematical formulation of Modal Model
was also discussed.
AdvLIGO Scattering Noise
(Hiro) Together with Mike Smith, using twiddle and
analytic formulation, the transfer function corresponding to re-injection from
various ports back into Core optics is calculated - to be completed soon.
AdvLIGO Seismic Isolation
(Sany Yoshida) Made some
progress in AdvLIGO seismic isolation modeling.
We found an error in the ABCD (state space) matrix that we had created based on
the Stanford group's model. After correcting the problem, we tested the matrix
with our e2e code by giving an impulse input to the ground X motion input port
(one of the 87 input ports). The time series of the response from the stage1-X
(the X motion of the first stage of seismic isolation) output port is identical
to the impulse response obtained by the Stanford group with their Matlab code. We still have the problem of having unexpected
output from other output ports. The problem is currently being investigated.
AdvLIGO Diffraction Loss
(Biplab) Had discussion with Juri
Agresti who is calculating diffraction losses using
Huygens-Fresnel integral approach -- basically the
approach followed in Ray Beausoleil's code. We
compared some of his preliminary results with my FFT results and they are in
agreement with each other.
Will complete a LIGO note on AdvLIGO
diffraction losses by tomorrow.
Modeler
(Hiro) 'dual_sum' module
is completed, and now being debugged.
(Melody) Figuring out and documenting Matt's modeler scripts for remote
processing.
Alfi
(Bruce) Completing work on Alfi node validation
and node validation in regards to how it affects the quitting of Alfi.(Problem Report 495)
Data Analysis Activities (Lazzarini)
Shawhan:
- Helped finalize S3 untriggered burst search paper for Amaldi
proceedings.
- Followed up time-shifted
coincidences in the S4 untriggered burst search.
- Did hardware signal
injections during the M7 run. Also worked
with Vuk Mandic on
modifications for S5.
- Modified conlog and gwistat code to
handle the new interferometer state vector information, and cleaned up conlogger channel lists.
Yakushin:
- Revisited LIGO-GEO SG21
simulation triggers to understand the problems that Siong
found in hrss(H1) vs hrss(H2) plot (besides the expected diagonal line,
there was and extra line at a different angle). It turned out that that
line was due to the injections that were outside of waveburst
frequency band.
- Studied a set of LIGO-GEO
production triggers in which GEO detector is shifted by 17 seconds in
addition to the standard set of time shifts done by waveburst.
Found a problem in the way I did that shift. Corrected the bug and
regenerating the triggers now.
Mendell:
- My top priority between
now and the start of S5 is to write driver
scripts for generating SFTs during S5.
- In addition, I continue to
make progress towards producing S4 results for the November LSC meeting
using the StackSlide code. The StackSlide review F2F was held successfully at Caltech
on Sept. 28 and 29 with Mike Landry, Peter Shawhan,
Teviet Creighton, Phil Willems
and myself attending. Several action items coming
out of that meeting will be addressed in the next month by myself and the pulsar group.
Mandic:
- I have calculated the
coherence between H1 and L1 DARMERR channels for all of S4 with 1 mHz resolution. The 1 Hz
harmonics are very clear in the coherence, but the 1/4 Hz harmonics are
not. A couple of simulated pulsars lines could also be observed in the
coherence.
- I also ran the stochastic
analysis for the H1L1 pair with 1/32 Hz resolution. The sensitivity
(theoretical sigma) obtained in this way is similar to previous estimates
(using 1/4 Hz resolution). Removing the 1 Hz harmonics changes the point
estimate from about -1*sigma to +0.5*sigma.
- I have also submitted the
paper studying the accessibility of the pre-Big-Bang models to LIGO to Phys.
Rev. D and to the archive.
Other:
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS
Added the functionality in the contolMonitorAPI
client to pop up a text box for entering username and password when the use of
an X.509 certificate isn't fully supported yet. This will be removed
shortly as the fix for using host certificates to authenticate between two
services running on the same box has been solved in TclGlobus.
The managerAPI has been tested against all ldas commands using X.509 certificates to submit the jobs
via a custom test client. Peter Shawhan has been
contacted about the availability of this test client to use as a template for
incorporating TclGlobus X.509 authentication and job
submission into GUILD and LIGOTools.
The ldas-ps/ldas-kill commands have been modified
to robustly handle some ssh
key problems (PR#2908). Along with these changes, the commands have been
modified to search which APIs are to be running and only gets the host names
for those APIs (PR#2903). Several of the packages in /ldcg
had pkgbuilder corrections to their rules. These include cvsgraph (PR2925), octave (PR#2757), lam
(PR#2858), tkcvs (PR#2928), rxvt
(PR#2929), tkdiff (PR#2930), and
lsof (PR#2927). The solaris
installation of tclglobus was also redone after it
was discovered that a patch needed to be applied for use with Solaris 10.
Efforts continue in understanding why some frame files do not get renamed
from .tmp to .gwf
(PR#2900). It appears as if this condition is isolated to the concatFrameData command.
Continuing to wait for the Solaris 10 and Fedora Core 4
upgrades at the sites to take place before releasing the next version of LDAS.
Looks like early next week is the soonest this will take place.
TCLGLOBUS
Resolved the issue when running XIO GSI clients against
XIO GSI server on Solaris 10. The problem was that IP to host lookup was
not providing a fully qualified hostname on the LDAS-SUNDEV1 workstation. This
was found to be due to the ordering of services to use in this request in the nsswitch.conf file. It was using nis+ before using dns. The nis+ did provide fully qualified
names, while dns does. Globus
is very sensitive to this and will not authenticate if fully qualified names
are not provided for reverse IP lookups.
Resolved the problem with using two XIO GSI servers communitating
with each other using only host certificates whent he
services were running on the same server box. This will be needed by LDAS to
allow the controlMonitorAPI server to communicate
with the managerAPI.
OSG/GRIPHYN/IVDGL
Successfully executed the binary inspiral
work flows on the University of Wisconsin, Milwaukee
and the Penn State University LIGO OSG Production clusters. This did
however require the costum patches to VDS to be
installed over the official 0.2.1 release of OSG. This also is the first
demonstration of running on a non Condor job scheduler - PBS (Portable Batch
Scheduler) at PSU.
Continued to work with Murali at
PSU to configure the voms-proxy-init configuration.
Murali has now made the change and testing will begin
next week.
Performed weekly yum update and reboot of the nodes in the
OSG-ITB cluster.
Reported to Paul Avery LIGO's
historical experiences developing a LIGO application to run on the Open Science
Grid. This resonates with reports from other groups on the difficulties
of making progress in a manpower limited activity driven primarily by
volunteers.
Drafted a plan to the OSG IEB outlining participation LIGO and the LSC have
planned for utilizing the OSG Grid over the next 5 years. The draft has been circulated
to the LSC Computer Committee and is expected to be delivered to the IEB at the
end of this week.
Recieved a request from the public relations
officer for OSG to provide a picture and 130 words describing LIGO's use of the OSG for scientific analysis for a
brochure to be made available at this years Super Computing Conference in
November. Duncan Brown has agreed to construct
the needed material based on the binary inspiral
search.
Hardware Systems (Anderson)
Caltech
(Dan Kozak)
- Helped with 3510
crash/SAM metadata problem at LLO.
- Helped with T3
crash (/frames data problem) at LLO.
- Preserved fb0_frames data
for CDS at LLO.
- Setup SAM-QFS for M7 at
LHO.
- Repacked M7 data strewn
across many tapes (will finish today) at LHO.
- Worked with Ben on several
occurrences of bad md5 values in LDR database at LHO.
- Worked on dataserver-cit problem that caused reboot when a file
in /archive was stat()'d. Recovered, samfsck'd and reported to Sun.
(Phil Ehrens)
- Updated m27 to Fedora
Core 4 and added an additional 512Mb of rambus
800 memory to it.
- Discussed RPM package
building and management with Erik Espinoza.
- Worked with Mary Lei and
Michael Samidi to get tandem2, tandem3, and
tandem5 usable for TclGlobus development.
- Created list of all
machines on 6th Floor Millikan with primary
user, OS version, and GC IP address.
- Updated all desktop
machines on 6th floor with Erik Espinoza's Sendmail
configurations, Octave, and a few other packages.
- Tried and failed to
diagnose (twice) mysterious hard lockup of the machine ldas-suntest3. This
machine drops all ports and video sync without warning.
- Did full yum update plus
install of Octave on all desktop FC4 machines.
- Issued and installed host
and datarobot certs
for ldas.mit.edu which had expired due to expiration email going to Hari Pulapaka or Naveen, or ??.
- Changed nsswitch.conf host order to 'files dns
nisplus' because nisplus
was returning the unqualified hostname which was inconsistent with the globus library host name lookup, and was therefore
preventing correct functioning of TclGlobus on
Sun machines with nisplus active.
- Upgraded dziban to Solaris 10 with mirrored 80Gb
drives. Installed Apache and Subversion. Investigating installation of
"viewsvn", a php
based server-side subversion repository browser.
(Erik Espinoza)
- Contacted 2 vendors for
budgetary quotes.
- Configured system in
cluster to send e-mail out.
- Configured basic kickstart setup.
- Spoke with other cluster admins and vendors about IPMI (more specifically
Serial over LAN woes).
- Researching issues with 64
bit linux on v40z.
- Finalized ligoconf, nis-utils, &
pam_unix2 rpms. Tested on x86_64 & i386.
(Stuart Anderson)
- Researching component
prices for next CIT cluster to optimize the configuration.
- Collecting initial budgetary
quotes for the next CIT cluster.
- Still shuffling cluster
computer equipment between Lab sites for S5.
- Finalized the new L4 RDS
frame configuration for S5.
MIT
(Keith Bayer)
- Received 7 blade Foundry
switch from LLO.
- Troubleshooting condor
job eviction problem.
- Added new condor users to
ldas-grid.
- Rebooted cluster node 49
after fs on hda2 reported errors and switched
into readonly mode.
(Junwei Cao)
- LDRdataFind
server is started at MIT.
- Meta
data in the LDR database is updated to be usable from MIT cluster.
Livingston
(Igor Yakushin)
- The new 140 nodes are
installed. Working on changing IP addresses and various configuration
files. At least 4 nodes have obvious disk problems and would not boot. The
others at first glance are running but I expect badblocks
to find more bad drives.
- The temporary HVAC (10
tons extra to whatever the building's handicapped HVAC can currently
provide) so far was able to handle the load (all 210 nodes). However, the
generated heat would increase as the new nodes start executing jobs. The
estimated repair time for the building's HVAC is 2 weeks.
- T3-19 went down on
Saturday night. Powercycling it on Sunday
morning brought it back to life. However, syslog
showed memory problems with the controller. The controller in T3-19 was
replaced during Tuesday's fb1 downtime.
- It turned out that the
upper controller in 3510 (that was replaced by SUN a week ago) never
actually came up. I would need another fb1 downtime to either try to
reseat it or replace it again.
- Got quotes for service
contract for the old 15 ton unit from Star.
(Dwayne Giardina)
- A few minor modifications
to the badblocks monitoring script I wrote a
week or so ago.
- Labeling the new nodes.
Hanford
(Greg Mendell)
- M7 Data was successfully archived
at LHO. The times archived are: Start: 812746784 = Oct 07 2005 11:59:31
PDT = Oct 07 2005 18:59:31 UTC End: 812876416 = Oct 09 2005 00:00:03 PDT =
Oct 09 2005 07:00:03 UTC Level 1, 3, and 4 RDS data sets were also
successfully generated at LHO. There are no gaps in any of these data
sets, and no errors occurred during archiving or reducing the data. A copy
of this data has been or will be transferred to CIT, and then made
available to Tier II centers via LDR. The new Level 4 RDS frames have 1024
s per frame file with separate frames for each IFO, and with these
channels and downsampling factors for each IFO:
- LSC-DARM_ERR
4
- IFO-ACTIVITY_INDEX
1
- IFO-ACTIVITY_STATE
1
- IFO-ACTIVITY_TYPE
1
- IFO-SV_STATE_VECTOR
1
- The power and HVAC
upgrade has finished at LHO, though we will be working to mitigate ambient
noise from the new unit, and checking that it does not add any noise into
the IFOs. It will take about another week to
finish upgrading the cluster from 280 to 420 CPUs, as well as updating the
operating systems.
(Ben Johnson)
- Networked 16 of the new
nodes. Currently performing some system imager tests (imaging node2,
loading it on several nodes etc.).
- Exported + Imported 142
tapes before M7. Strangely enough, I did not have to restart samd afterwards.
- Worked with Duncan Brown
on the segment database.
- Fixed bad files at LLO, in
/archive, that were caused by t3-9@LLO problems.
- M7 went well this past
weekend. There were no data gaps during the 36hour run.
General Computing (Wallace)
MIT
(Keith)
- Ordered matlab licenses for several new users
- Ordered replacement
projector bulbs
- Reinstalled thinkpad with latest o/s and patches
- Tested external DVD burner
with Fedora IV
LLO
(Dwayne)
- Kantec
software upgrade: had a few problems with the new version that took a couple
days of trial and error testing possible solutions. Situation temporarily
resolved.
- Assisted Bonnie with more
html documents.
- Norton will not install
on one laptop. Situation was reported this morning. I am looking at it
today. Will advise when solved.
(Shannon)
- Working on LDAP. I have all of the authentication encrypted, however the rest
seems to go in the clear. Many of the Sun scripts for migrating data are
set up for migrating from a generic vanilla LDAP installation, and not
from a vanilla NIS+
conversion. Therefore, I am having to rewrite a
lot of the scripts to massage the LDAP store into a compatible format. The
current plan is to continue working on this and have it rolled out by the
end of the week. At which point, I am sure bugs will pop up. Also, after
it is deployed, I plan on documenting the entire process and distributing
the notes to folks at MIT, CIT, and LHO so that they can possibly
duplicate this process sometime in the future. This has been a long
process.
- Working with Sun to get a
quote on a support contract for the messaging and directory server.
- Found an infected machine
late last night. After further inspection, it appears that the machine has
been logged into an IRC channel and is being used as a DDoS
bot. As far as I can tell, there has been no
attempt to use this box as a jumping off point to infect other machines on
site. I will have to investigate further via the snort logs to be sure of
this. I will likely have Dwayne rebuild the machine after we learn the
extent of the intrusion.
LHO
(Christine)
- Trying to get problems
with my Cisco contract sorted out so I can renew it. Then I can get help
troubleshooting problems on the router with the new GigE
connection. The backup network is at a standstill
because we are unable to get a link between LHO and PNNL. With help from
the PNNL engineer, I've tested each part of the circuit separately and it
all tests OK, but when connected up we can't get a link. Amerion is throwing their engineer into the mix as of
today, so we'll see what comes of that.
- Helped a user with a
printing problem which required reinstalling the network printer wizard
and driver software.
- Updating licensed
software to the latest versions.
- Set up accounts and
networking for a long term visitors. Will have to setup a Sun workstation
for his office.
CIT
(Veronica)
- Project Science: Posted
the presentations of the last workshop, other web updates.
- CaJAGWR:
User support.
- LSC: Updates of the LSC
publications database. Website updates.
- LIGO: Website updates. Roster
database updates. Installed security patches on Windows servers. On pictor, the attempt to run
the update failed, I could not trace the error at the WinUpdate
website. Following the advice at the msusenet.com I deleted the contents
of %windir%\SoftwareDistribution, it seemed to
solve it and I was able to install the patches. Worked with LHO on updates
to the Advanced LIGO Schedule website, reset a couple of passwords, posted
the current updates and gave Dwight an introduction on web publishing.
Converted the footage of last week's NASA newsconference
on short GRBs by Albert and others from analog
to DV. Burned a couple of DVD copies.
(Mike)
- Finished up loading Ansys 10.0 on engineering workstations.
- Continued work on
upgrading Norton Anti-Virus and Adobe 7.0 software for users.
- Worked a problem with the
VPN server. This turned out to be a DNS issue on the user's side of the
house.
- PICTOR: Is having some
hardware issues that is causing this server to reboot it self. I am in the
process of loading a new replacement server.
- Finished up cleaning up a
loaner laptop that came back from travel.
- Spent a lot of time this
week working on a parallel dongle issue that is used for Solid Works. I
ended up downloading a driver from the Internet specifically for the
dongle. The problem I was having is XP SR2 has a driver loaded into its
Operating System for any HASP4 dongle. You have to disable that driver in
order for the new driver to load. Aladdin website has a command line tool
to disable the XP driver. I have ordered a USB Dongle to see how XP will
handle going that route.
- Working on getting old
computers ready for surplus.
- Other user misc. user
support.
(Christian)
- Barry Barish
- Updated Barry's workstation to Norton 10 and Microsoft's latest patches.
- 2flr W/B - Configured new
workstation with the engineering Ligo image.
- 3flr W/B - Updated two
visitors workstation to Norton 10.
- Veronica Kondrashov - Added 1GB of additional RAM to Veronica's
workstation.
- Meter - Updated two more
workstation that I missed last week to Norton 10.
- I went through 9
different loaner laptops imaging and updated them with the Standard Ligo image and Microsoft's latest patches.
- Other misc.: Continued
onsite software/phone support
(Larry)
- Still working a number of
procurement issues. The SUN contract is now through the system and we
should have confirmation by the first of next week. Tracking down the
dual-core systems. The companies have had problems getting a OS loaded on the units. So far the Enterprise versions of Linux, Windows
XP64, Solaris 10 and SUSE 10 appear to work
on the machines. The units will ship with SUSE 10 and we will take it from
there. Renewed a number of s/w maintenance contracts and still have a
number to do.
- Resolved a couple of end
user issues. Setup a couple of new accounts and removed a couple of
accounts.
- Updated the backup s/w on
one of the LDAS servers. Also, made a number of small changes on different
severs to accommodate changes being made on LDAS machines.
- Continued on a couple more
of the complete backups on different servers. Still a few more to go.
- Updated some of the DHCP
tables and setups.
- Assisted a number of
users on updating their virus s/w and checking their systems for spyware.
- Assisting the others and
Ed C. clear up a number of equipment related items. Mostly, clearing out
old items that people will not use anymore.
- Finally, had a little
time to do some work on documentation. The IP tables still have a lot of
work needing to be done and I am in the process of updating the GC
computer use policy.
- Spent time tracking down
e-mail issues. One issue concerning duplicate messages is still being
worked on. The issue of missing messages has been resolved, the client
utility had a trigger that was causing false positives for the end-user.
Continue working on the mail-filters on the mail-server.
Mail Statistics for Oct 06 - Oct. 12, 2005
|
Mail
Statistics
|
October 6 - 12, 2005
|
|
Rejected
Messages
|
17,750
|
|
Virus
Messages
|
979
|
|
False
Positives
|
12
|
|
Accepted
Messages
|
15,706
|
|
Total
Messages
|
33,456
|
Advanced LIGO and Supporting R&D (Shoemaker)
Advanced LIGO Project Management
from Carol
Wilkinson
Progress Updates
Progress updates for Advanced LIGO subsystem development for the period from
September 1 through October 31 are due by November 10.
Subsystem leaders will receive update notices by October 24.
Meetings & Reviews
Future near term planned meetings & reviews are indicated in the table
below.
The Ribbon/Fiber/Ear/Bonding PDR is in progress. Panel members have met to
review documents and prepare questions for the SUS tem members.
Changes since last report are listed in blue.
|
Date
|
Sub sys.
|
Review
|
Topic(s)
|
Enabling event(s)
|
Schedule motivation
|
Status
|
|
Jul 11-13
|
SYS
|
SYS Mtg
|
CDS infrastructure & HAM
Isolation Req’s
|
|
|
Report in progress
|
|
12-Jul
8-11 PT
|
SUS
|
PDR, Review 2
|
Electronics req & design;
Focus is on the front end electronics (UK) -- limited Digital
controls/electronics (US) review
|
|
|
Report in progress
|
|
~ Nov 4
|
SUS
|
SUS PDR
Review 8
|
Ribbon/Fiber/Ear/ Bonding PDR
|
Completion of the ribbon, fiber, and ear and fabrication
and bonding design and processes
|
|
Panel first met Oct 12. Review scheduled for first week of
Nov. Documents for review at
http://www.physics.gla.ac.uk/igr/sus/index.html
|
|
~Oct
|
SEI
|
HAM Critical Design Review
|
Recommendations w.r.t. HAM
prototype development based on ETF results
|
Completion of SEI/BSC critical design reviews; LSC review of
ASI HAM configuration design
|
Delay
until requirements are revised. timely decision on proceeding with SEI/HAM
prototype
|
Delayed
from Aug.
|
|
~Oct 12
|
SEI
|
HAM SAS
PDR
|
Review modeling, analysis, design for HAM soft
system
|
Revised HAM SEI requirements.
|
Timely decision for proceeding with HAM SEI prototype.
|
|
|
~Oct
|
SYS
|
PDR, Review 1
|
Engineering & Implementation ('generic') Requirements;
Interfaces
Revised Optical Layout
Optomechanical Layout
|
completion of generic requirements definition; completion
of first draft of ICD; revision to optical layout; establish integrated opto-mechanical equipment layout
|
timely system level definition enables/helps define
subsystem reqmnts & design
|
|
|
~Dec 8
|
SUS
|
PDR, Review 3
|
Quad design
|
Completion of the quad controls prototype
assembly; shipping to LASTI
|
timely transfer, to RAL & UB efforts, of
lessons learned from the controls prototype
|
Delayed until shipping to LASTI.
|
|
~Dec
|
SYS
|
PDR, Review 2
|
CDS Infrastructure
Stable Recycling Cavities
Lock Acquisition
Modulation Scheme
Power Induced Instability
|
Sufficient CDS requirements & concept work (also
7/11-13 mtg)
E2E Modeling for AL
40m Progress on Acq. & Mod.
|
CDS Infrastructure is key to subsystem electronics req.
Stable cavity is key to IO MMT design
|
|
|
~Jan
|
IO
|
PDR Review 1
|
PDD, Faraday Isolator, modulators, mode cleaners, mode
matching design, Mach-Zender
|
SYS PDR?
|
|
Work
delayed on
FI, allows more
systems to be
reviewed
|
|
~Jan
|
SUS
|
PDR, Review 5
|
Triple design
|
Available SUS/US staff
|
Enable SUS/US final design phase
|
Quad controls PT
takes preced.
|
|
~Jan 25
|
AOS
|
AOS DRR/CD
Review 1
|
Stray light control, PO
mirror and telescope, optical lever, initial alignment system
|
SYS PDR?
|
Delay stray light control review until other systems can
be reviewed at the same time.
|
Delayed from
Oct. to allow review of
add. systems.
|
|
~Feb
|
SUS
|
PDR, Review 4
|
Quad Installation
|
Completion of installation at LASTI
|
Inform the UK final design & noise
prototype design effort ASAP
|
Delayed shipping schedule
|
|
~Feb
|
SUS
|
PDR, Review 6
|
quad controls prototype test results
ribbon process/design
|
completion of LASTI testing
|
timely incorporation into final design effort on the noise
prototype
|
|
|
~Feb
|
COC
|
PDR
Review 1
|
Metrology, handling
fixtures
|
Review and
select vender and in-house metrology
|
Need handling fixtures for UK substrates arriving in Dec and
Jan 05
|
Work delayed
|
|
~Mar
|
IO
|
PDR Review 2
|
Adaptive mode matching, Mode Matching Telescope
|
Determination of whether a stable recycling cavity will
become part of the AL
baseline; SYS PDR 2
|
|
Waiting
for stable
RC decision
|
|
TBD
|
AOS
|
AOS DRR/CD Review 2
|
Thermal Comp., Photon drive
|
SYS PDR?
|
|
Moved
forward
for timely finish
of AOS CDR’s
|
|
TBD
|
SUS
|
PDR, Review 7
|
BS, FM/ITM SUS design
RM design
non-cavity SUS
|
design work completion (has yet to start on FM/ITM, not
mature for RM)
|
|
|
|
~May
|
COC
|
PDR
Review 2
|
Cleaning Process, Optics prelim. design
|
SYS PDR?
|
|
|
Seismic Isolation
From: "Joseph A.
Giaime" jgiaime@ligo.phys.lsu.edu
Agenda for the weekly SEI telecom
Friday, Oct 7, 2pm Eastern, 1pm central, 11am Pacific time
Announcements
- Aaron
Streets will be doing a rotation with the group at Stanford this quarter.
Aaron is a first year grad student in Applied Physics, and will be working
with us this quarter (i.e. this 'rotation') on some seismometer
development questions.
- New
Mech. E. graduate student, Brett Shapiro, at MIT. He will begin
working on the quad suspension modeling and testing.
BSC SEI status, Ken M
- First
3 bid packages received, comprising 80% of the structure. The bid on
the large part package was higher than expected, due to material cost
changes; the others were as expected. Delivery in early
February. Winner for small high volume parts is a new (to us) vender
that specializes in 5 axis CNC work.
- Ken
is working to add holes to change the table to the 1" x 1" hole pattern; this will require a revised bid from the
winner. Extra cost will be due to more machine time and inserts.
- Next
set of bids, for the actuator mounts, locators and vacuum housings due in
next Friday.
- The
revised blade and flex rod specs sent to the selected vender.
- Ken
has completed changing the drawings to accommodate the other ASI
changes. Richard F has been helpful, and has fixed some minor errors
in the designs.
BSC work (Rich M)
- 10
Hz amplification, Rubber Creep, and adaptive control
HAM control with VME (Pradeep)
- Feedforward work is delayed due to the very noisy road
construction work behind the lab; work only possible in late
evenings. Rich is working on a Simulink
model to study the adaptive filter method.
- Pradeep has the HAM HEPI horizontal loops working, but
the verticals still not working. SYS-ID is difficult due to the lab
noise.
Electronics (Jay, Brian) - the new readouts are in the GS13s,
and installed in the ETF Tech Demo. The signals are all reasonable. Sys-ID to
begin today, followed by damping.
- Stanford
has received the new GS-13 readouts. Aaron and Matt have installed
the boards in all of the feedback sensors, and the signals look
acceptable. Gains set so that ADC noise will start to limit at 3 or
4 hertz; whitening may be needed later.
- Next:
sys-id, redesign damping loops and control design.
- Jay
traveling.
- Shyang awaits unlocker
device from Stanford.
Other:
Norna notes that lower 3/4 of quad support
structure ready, and upper part in the shop. These will go to Stanford
for the dynamic tests.
Suspension
From: Janeen Romie romie_j@ligo.caltech.edu
From: ctorrie <ctorrie@ligo.caltech.edu>
Mark and I now have a quad with reaction chain suspended in the lab. Still some
work to do but both chains are stable!
See: - http://131.215.114.242/view/index.shtml
From: Ken Mailand kmailand@ligo.caltech.edu
I will have a bearing test setup today for Calum
for re.a quick test for the suspension fixture
rotating table. The test using a piece of teflon
between the plate contact surfaces requires too much break away force.
I’m working on a vertex BSC layout for Mike Smith that will show stay
clear areas inside for the beam path.
From: Helena Armandula ahelena@ligo.caltech.edu
Adv. LIGO SUS - New air bake oven
Arranged for a JPL chemist to take FTIR samples from an aluminum
plate that was cleaned and air baked following LIGO cleaning and baking
procedures. These tests will
serve to qualify the oven.
In the past, the surfaces were sampled by wiping the surface with extracted
fiber-free lens tissue using dichloromethane solvent. This allows to determine
the level and identity of molecular (oily) contamination on the surface.
From: Jay Heefner <jay@ligo.caltech.edu>
AdL SUS
The preliminary design of the AI chassis needed for the quad controls
prototype is complete. The AA chassis is in the works.
Initial measurements of the noise of the PCI-X ADC module shows an input
referred noise of ~3uV/rtHz with a 40Vp-p dynamic range. DAC measurements are in progress.
Discussions last week with the UK electronics group went very well.
Over the next several weeks we will try to finalize the electronics
requirements and the motivation for the requirements. This will include an
estimate for the required whitening and dewhitening.
From: Rolf Bork
<rolf@ligo.caltech.edu>
- Got
PCI-X ADC and DAC drivers working for the quad controls.
- Quad
controller data acq is working via the VMIC5579
reflected memory, which is compatible with what is presently installed at Lasti.
Core Optics
From: Bill Kells <kells@ligo.caltech.edu>
I am now gearing the PI work toward suammarizing
the situation for the NSF review. Most recently a new twist: it had been
unresolved why my model and the BSV (BRag, STregin, Vychanin). model of PI were in considerable discrepancy. Finally I have resolved this. There is NO discrepancy!
What was wrong was the Perth
groups use (apparently in all their papers ....??) of
the BSV analysis. Since The Perth people were here this
summer I was strongly influenced by their adaptation and, in fact, was
making comparision that rather than the BSV original.
So its good now that there is no puzzle.
I have now been focusing on what exactly would we expect if there is a PI
threshold exceeded in a real IFO.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
An hour meter circuit was conjured up for the Innolight
NPRO.
University of
Adelaide
- Installed
a 10-W laser in TAMA, this replaces the laser purchased from Sony. The laser is an air-cooled slab design.
- Work
continues on a 100-W laser. At the
moment they obtain about 50 W from a few hundred watts of pump power. However there are some slab mounting
issues. The end pump slab absorbs
approximately 90% of the pump power.
However there is a need to optimize the thermal lensing
and cooling. The geometry employs a
zig-zag path to increase the absorption length.
Laser Zentrum Hannover
- The
150-W laser is back up and running, although
there are some problems with the power scaling. It is believed that the problems
encountered with the laser at the moment are due to some damage on the
rods. Some spots on the
anti-reflection coatings are noticeable.
Experiments with the position of the quartz rotator showed that as
the quartz rotator was adjusted to improve the alignment into the high
power stage, the polarization changed from being linear to
elliptical. However more output
power is obtained, although the polarization is unknown. The quartz polarizer is no longer adjusted
to improve the alignment.
Stanford
- The
two end-pumped slabs are up and running.
The alignment of the system is being tweaked to improve the
performance. Pump diodes from Limo
and LaserLine are being evaluated.
AEI
- The
latest relative intensity noise (RIN) measurement result is a RIN of
4.0E-9 at 200 Hz. Careful studies
were made of the photodetectors used, servo
electronics and any scattered light.
Thus far the limitation appears to be associated with the
semiconductor the photodiode is fabricated from. The results obtained with InGaAs are better than those obtained with Si photodiodes.
Auxiliary Optics
From: Michael Smith <smith@ligo.caltech.edu>
SLC
Made a preliminary layout of a ring heater using Solid
Works in accordance with Phil Willems calculations of
10/6/05. The ring heater design fits within the "stay-clear"
area of the ITM SUS.
For additional information about this report, contact Stan Whitcomb or Phil Lindquist