Weekly Report for Week Ending October 6, 2005
The LIGO Executive
Committee Agenda for Monday October
10, 2005 will be:
(Meeting time: 10:30 am Pacific Time)
- Announcements
- Comments
on Weekly Report
- LSC
Issues (Saulson)
- LIGO
Lab Operations
- Administration
(Lindquist)
- Sites
(Raab, Zucker, Shoemaker)
- Commissioning
(Fritschel), Detector (Coyne)
- Campus
Research Facilities
- 40
Meter (Weinstein)
- TN,
( Libbrecht)
- LASTI
(Shoemaker)
- Data
Analysis and Computing (Lazzarini)
- R&D
and Advanced LIGO (Shoemaker)
- CHANGE CONTROL BOARD/TECHNICAL REVIEW BOARD SESSION
AS NEEDED
Special Items:
Review
of Advanced LIGO Budgets
Special Announcements:
Weekly
Report Highlights
LSC Issues (Saulson)
No report
LIGO Laboratory
Administration (Lindquist)
STATUS OF LSC MOUs (Lloyd)
Non-LSC MOUs (Lloyd)
SITE TELECONFERENCE (Jasnow)
- A
site teleconference was held on October 6, 2005. Discussions were
held regarding finalization of the FY06 budgets for the sites.
Review of the budget is still ongoing, with some questions to be
answered. These are expected to be resolved shortly.
- The
signed contracts from Cangelosi - Ward for the
construction of the LLO SEC have not yet been received. These
contracts, plus the performance and payment bonds, must be received before
a Notice to Proceed can be issued. Additionally, Robert Ward, of Cangelosi - Ward, indicated that a Notice of Contract
is needed to reduce the costs of filing with the State Clerk. Ed Jasnow stated that it would be issued with the
executed contract.
- A
Contract Work Order form has been designed for use on the Excel contracts
at LLO. It has been sent for review by Mike Zucker
and Allen Sibley.
- HR
has scheduled a "benefits fair" at LHO and has requested that
LIGO see if it could pay for travel to the site. After some
discussion, it was agreed that it would not be allowable to pay directly
for an overhead function. Additionally, LIGO did not pay travel
costs when HR went to LLO for similsr reasons.
- The
LDAS computers have still not been delivered to LLO from the warehouse in Baton Rouge. It was agreed to put
more pressure on the transportation company to deliver them.
- Repairs
on the damage at LLO caused by Hurricane Katrina have not yet started due
to communications problems with the manufacturer of the exterior panels
that were blown off. Attempts to contact this company are
continuing.
- The
list of assigned actions updated through September 01, 2005 (the last time
that it was updated) will be found Here.
PROPERTY MANAGEMENT (Chargois)
>From: Ed Chargois <chargois_e@ligo.caltech.edu>
- Nothing
significant to report.
DOCUMENT CONTROL
CENTER (Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
- Continued
to add abstracts to the database for publications. Included cite
references where available.
- Geared
up to begin scanning of all boxes packed from Larry Jones (16).
Organized file and naming conventions and showed staff how to apply to
each of the boxes. Hopefully this will help streamline the process
while keeping some uniformity among each of the workers.
- Began
to review keyword list in preparation for migration to the new DCC
system. Need to consolidate those that are duplicates, rename as
necessary and just do general cleanup of the list.
>From: Cleveland Mak <mak_c@ligo.caltech.edu>
- Revised/altered
a Contract Work Order form.
- Spent
time searching through the database to locate a tax exemption letter for
the LLO Site.
- Considerable
amount of filing this past week.
- **Update
on Scanning Project** - The remaining boxes of account files have been
scanned and book-marked. The cd's still
need to be burned for these files. There are 10 boxes of these
account files that need to be shredded and it has yet to be determined if
they will be done in house or not. Mostly prepping and some scanning
have begun on those Larry Jones' boxes I had mentioned last time.
We're currently down to one temporary employee.
- Activity:
|
Week Ending
10/06/05
|
In
|
Out
|
|
Packages
|
15
|
9
|
|
Faxes
|
20
|
19
|
FINANCIAL SYSTEMS (Cronin, Brambila, Kaufman)
>
>From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
- Completed
the no-cost extensions and submitted the changes to the vendors on the
following subcontracts:
Corning
1026782
Creath, Katherine 1054775
Goodrich
Corp 1035388
Heraeus Optics 1025997
Crystal Systems 1012376
REO
1002093
CSIRO 1063039
- Completed
change order #1 to Dynamic Light Control and sent the change to the
vendor.
- Submitted
the request for the name change on Waveprecision
to General Optics so that I can complete the no-cost extension.
- Completed
the change order to FKM.
- Completed
change order #8 to LSU AG and submitted it to the vendor. Requested for
new certifications.
- Working
on the change order to Great Impressions.
- Working
on the change order to Thomas Nash.
- Provided
training for a LIGO requisitioner in preparing TechMart requisitions..
>From: Florence Kaufman <fkaufman>
SUBCONTRACTS MANAGEMENT (Jasnow, Salone)
>From: Gina Salone
<gsalone@ligo.caltech.edu>
>From: Ed Jasnow
<jasnow@ligo.caltech.edu>
- The
contract for the construction of the LLO
Science Education
Center has been
signed by Cangelosi - Ward and is being sent
here. Upon submittal of the performance and payment bonds, a formal
Notice to Proceed will be issued, and the date
for a kickoff meeting will be set.
- A
Contract Work Order form has been designed for use on both Excel contracts
at LLO. This form is based on one successfully used at JPL.
This will document work issued and cost estimates for the work.
SUPPORT (Baldon, Hiroto, Lloyd)
>Irene Baldon
- Processed
the paper work for six (6) new/revised trips. At this time there are
four (4) trips completed or in the works but are awaiting the necessary
paper work to enter the P-Card system.
- Completed
twelve (12) Expense Reports and there six (6) reports yet to be
done. I continue to contact travelers who have outstanding Expense Reports
(more than one (1) month old) to ask for their cooperation in sending me
their receipts so that these can be closed in a timely manner.
Presently there are three (3) reports more than thirty (30) days
old. I have two (2) reports awaiting signature at this time.
Worked on copying and recording all the expense reports completed last
week to be sent to Travel Audit for final auditing and payment.
>
- Travel
arrangements for Barry. Proposal processing for Albert and Phil.
>Dorothy Lloyd
- No
report.
- Jim
continued with data entry in the LIGO database and helping out in the DCC.
PROPOSALS and REPORTS (Lindquist)
Supplemental material for the Request for an extension and supplemental
funding for FY 2007 and FY 2008 for LIGO Operations has been sent to the
NSF. The Request for supplemental funding for the Outreach
Building in Livingston
has been enhanced and resubmitted to the NSF.
DCC Steering Committee (Lindquist)
The purchase order with Synergy for the new document management system seems
to be held up pending the return of personnel key for processing the
procurement.
CHANGE CONTROL/CONTINGENCY MANAGEMENT (Lindquist)
HUMAN RESOURCES (Akutagawa)
>From: Cindy Akutagawa <cindy@ligo.caltech.edu>
- The
next Staffing Committee meeting is scheduled for Monday, October 24, 2005.
- All
files for the Staffing Committee are up-to-date and posted on the SC web
page.
Quality/Safety (Tyler)
>From: Bill Tyler tyler@ligo.caltech.edu
No report.
LIGO Hanford
Observatory (LHO) and Interferometer Operations (Raab)
Summary of Commissioning
Activities at LIGO Hanford
Observatory (compiled by M. Landry)
M7 begins Friday at noon, running into the mid-weekend (Saturday night
24:00). The IFOs are functioning at or above S4
ranges but locks have been short in the last 24h, in part due to commissioning
work.
ASPD4 latching and saturations were problematic on H1 and H2. H2
received a new photodiode to mitigate AS_I saturations
(recall ASPD4 on H1 was swapped out last week). Burn spots were found
on ASPD2 and 4 on the 4k.
Commissioning highlights are bulleted below:
4K IFO
- configuration
control continues to be and issue: IFO performance got a whole lot better
this week after it was noted that the WFS output matrix (particularly the
off-diagonal elements) were simply wrong
- Time
domain studies indicate that 1Hz and subharmonics
observed in S4 in DARM_CTRL are indeed also resident in the error signal (here,
and later, here).
We still don't understand why the lines are not seen by the pulsar group nor in DTT in the error signal. The source
however appears to have been isolated to the 1PPS
GPS ramp. We will run without the 1PPS in M7, and work is
underway to produce a kinder, gentler ramp that won't crosstalk into
everything, perhaps a sinusoid.
- REFL
beam stabilization (RBS) was installed
on ISCT1. In other REFL investigations, it was found that the waveplate was stuck, the source of CM troubles late
last week
- coherence was seen at acoustic (200-300Hz)
frequencies with ISCT3 accelerometers and DARM_ERR during S4.
Lately, likely due to mods of the beam path, the
coherence has moved to slightly higher frequencies.
- end
station velocities
(larger in the anthropogenic band up to 20Hz in EY than EX due to the
proximity of route 240) argue for a PEPI-like solution to be added to the
currently-implemented POPI one
- WFS
stability at high power was investigated.
ADC saturation was observed to be problematic.
2K IFO
- The
ADCU associated with the fast ASQ channels was responsible for the ~122Hz howler on H2 that was killing binary inspiral range. Cards that were pulled from
H2adcuFAST and have been left this way
- the
big Thermos: CP6 at the X midstation was being
clad in insulation to mitigate lockloss-inducing
pinging
- an
ill-named fast shutter was swapped,
now closing in ~7ms
- ISCT10
was refloated
DAQ
- new
REFL beam steering code
was installed before last weekend, to prepare for installation and
commissioning this week (above)
- new
statevector code was loaded
for both IFOs; this impacted several monitors
who read out the statevector and construct
trends based on what they find
Outreach (D. Ingram)
LHO hosted Hungarian
physicist Rácz István and camerman Páp Ferenc
this week for their work continuing on a gravitational wave film. A
Hungarian foundation supports the film's development.
LIGO Livingston
Observatory (LLO) and Interferometer Operations (Zucker)
L1 Interferometer (Frolov)
The interferometer has been running for two days with the reflected beam
stabilization (RBS) turned on. Several hours-long lock stretches with inspiral range up to 8.5 Mpc were
achieved. The issues with starting the RBS from cold or hot states have been
resolved by insuring that the interferometer input beam alignment is restored
to the cold state after each lock loss.
The presence of 1 Hz lines in the interferometer dark noise was confirmed.
Similarly to the Hanford
interferometers, an impulse in the DARM signal appears to be phase locked to
the GPS timing signal.
The beam size on the anti-symmetric port was increased to prevent the
burning of photo-diodes at high interferometer input power.
CDS (Bogue)
No report.
CDS code support (Khan)
No report.
Education and Outreach (Thacker)
No report.
Site Safety and Security (Riesen)
Rich is on vacation this week.
LLO General Computing (D. Giardina)
- installed
Protel for Ken Watts
- Kantech security software installation with Chuck
Brannon of Excel. System scheduled to be switched over to new
version next Monday. Requires replacing some hardware. During
installation noticed some doors reporting incorrectly. Their sensors
are now fixed. Also fixed the side gate 'fully opened' sensor, which
was not detecting the gate being opened.
- DNS
changes for Lisa B: l1awg.cds.ligo-la.caltech.edu is new alias for
gdslvea1.cds.ligo-la.caltech.edu and
lloscript.cds.ligo-la.caltech.edu replaces llo2.cds.ligo-la.caltech.edu
AdL Mechanical Engineering (Romie)
Working with Helena and Caroline on Ribbon/Fiber/Ear PDR
documentation, due today.
Working on Estimate to Complete budget for Carol.
LDAS/Condor Sysadmin (Giardina)
- replaced
failed disk in T3-14
- At
Igor's suggestion and guidance, wrote small script to run badblocks during night hours on weekend and monitor
output, sending email on detection.
- node63 reported bad blocks on hda,
to be replaced soon.
- Donnie
Buzbee came in to troubleshoot problems with
3510 controllers and disks. He worked with Igor since I was scheduled to
do Kantech software upgrade with Chuck Brannon
of Excel.
LDAS/Condor and data analysis (Yakushin):
1) The biggest problem after LDAS move downstairs is malfuctioning
HVAC in the high bay area. The temperature in the high bay area is about 8
degrees above the optimal operating point. The humidity is about 10% higher
than it should be despite the fact that HVAC in the high bay area was designed
for much larger heat loads than LDAS computers can generate. Allen is working
on finding the way to fix the cooling problem by either fixing the existing
HVAC or bringing the temporary AC unit.
#MZ NOTE: TEMPORARY CHILLER IS RUNNING, SITUATION IS STABILIZED
The situation should be resolved next week. Another potential problem is the
presence of mice in the high bay area (Allen and Mike have been alerted). I
also asked for the high bay area to be regularly vacuum
cleaned to protect the equipment from dust.
2) 3510 unit developed a problem in the I/O module of the primary
controller. The primary controller failed on Friday morning, the unit switched
to the secondary controller. On Friday night the secondary controller froze as
well. On Saturday morning I power cycled the unit, it came back on the primary
controller, but since then it periodically generated error messages in 3510
event logs. Also drive 9 failed. I have replaced the primary controller, the
failed disk, reseated secondary controller and all the disks. At first glance
that fixed the problem but we need to use the system for several days to make
sure. Currently we are working on restoring damaged /archive file system from
tape. There were also some errors corrected in /frames file system that is used
by fb1.
3) Failed power supply was replaced in node8.
4) Moving company keeps rescheduling the delivery date for 140 nodes from
CIT.
**MZ NOTE: WE HAVE LOCATED THE COMPUTERS AT A WAREHOUSE IN BATON ROUGE AND
ARE STAGING A RESCUE OPERATION
5) The old GigE switch was shipped to MIT.
Initial LIGO Detector Science & Engineering (Coyne)
CDS
see also the CDS weekly meeting
minutes in the commissioning
archives
CDS Software
Rolf Bork
After a decision made at the CDS meeting, we will back out
the filter module change which allows limiting the outputs/histories of
individual filters. In its place, we will code up the change as outlined by D. Sigg. This new change will not be coded prior to the start
of S5.
The last change to go in will be the LSC control of the fast shutter, along
with the auto switching to ASPD5. This code change is complete and will be
loaded onto LHO2k during next Monday's CDS maintenance period.
Once this last change is tested, all of the latest code will be downloaded
to LLO. This will happen sometime after Rana arrives
there (late next week or early week of Oct. 17).
CDS Hardware
no report
PSL
PeterKing
Dave Grimmett and I spent some time fixing an 80
MHz VCO that was modified
for use in a SURF project. Unfortunately undoing the modifications was
not all that was required to bring the unit back to life. Afterwards the tuning curve and output power
versus gain control voltage was measured. The unit will be shipped off to
LASTI.
Optical Metrology
Bill Kells
Since Liyuan returned last week, I've been
discussing with him and building a more detailed model of the surface absorption
setup in the OTF. His latest checks are reassuring (that we are not doing
something terribly wrong), but don’t obviate the need finally for an
accurate calibration.
40 Meter Interferometer (Weinstein)
Matt Evans is visiting for a couple of weeks, and is working closely with
Rob and Rana on locking. Osamu is still at LHO
working on commissioning tasks. Ben is off getting married.
There will be a meeting of the 40 Meter Technical Advisory Committee (by telecon) next Thursday, 10/13, at 8:30 am Pacific. All are
welcome; see Alan (ajw@caltech.edu) for details.
IFO commissioning
- Matt
wrote a "watch-down" script which watches for lock loss, runs
the down script, and then runs the tickle script to reaquire
lock.
- Rob,
Matt and Rana have been making good progress
towards full lock. As usual, locking all 5 length degrees of freedom is
routine; but CARM is offset, so that the arms are not at full resonance
and the power recycling isn't kicking in. They have automated the lock
acquisition, and the step-by-step reduction in the CARM offset. Until this
week, it was possible to climb ~ 20% of the way up to full resonance, but
then the noise would overwhelm the servos, the arm power would fluctuate
wildly, and lock is lost. This week, after much work, they're ~ 50% of the
way up to full resonance, and power fluctuations are much reduced, so they
can hold lock in this state for as much as 10 seconds. Frequency noise is
the biggest problem.
- The
above progress was made possible by
many improvements to the servo filters, permitting increased
gain in CARM and DARM.
They also
improved the MCL path, reducing the crossover frequency and thus the frequency
noise.
They also diagonalized the short degree of freedom loops; now, there
is significantly less noise on these.
They also
found and fixed bugs in the length sensing code which forms the (non-linear)
CARM error signal from the DC transmitted power; but they suspect there may
still be a problem there, limiting gain at critical frequencies (e.g., 30Hz).
They also
looked for saturations of RF demod signals in the LSC
rack, but found no smoking guns.
They also
attempted to figure out why the signal coming from SP 166I (RF signal for CARM)
is so small. In the process, they burnt the PD, and then replaced it. Work in
progress.
- They
are trying to get the digital common mode servo (to MCL) working again, in
progress.
- They
are now at the point where they are unable to increas
the CARM gain because of apparent mysteries in the optical plant at lower
frequencies. Under intense investigation. It may have something to do with
the optical spring; Rana estimates that it
should show up somewhere below 40 Hz.
- Many
more ideas and things to try; intense effort underway!
IFO modeling
- Monica continues to make
progress in simulating sweeps through arm resonances in the full IFO, at
various velocities, and comparing with measurements.
DC detection development:
- With
help from Peter King, Peter Fritschel, Helena Armandula, and the folks at LHO, we have been promised
high-quality optics for our output mode cleaner, without having to order
anything new. Many thanks!
- Mike
Smith has redesigned the OMC to reduce the proximity of scattering
surfaces within the beam path. In the process of making final part
drawings for the OMC. Redesigned the mounting pads to increase the lowest
resonant frequency. Analyzed the resonant modes using ALGOR: with
"red brass" material, the lowest normal mode frequency is
approximately 670 Hz with four mounting pads pinned.
- Parts
(optics and such) are coming in for the DC readout beamline,
and Mike is gathering them.
- Nergis and Keisuke Goda have
prepared a preliminary proposal for experimental demonstration of a
squeezing-enhanced gravitational wave interferometer at the 40m; see Nergis for details.
Electronics, controls
- At
Rana's suggestion, Steve is looking into the
design of beam paths for our optical lever beams which eliminate all
on-stack mirrors, thus decoupling the oplev measurements
from the stack motion (especially the resonances at 3-5 Hz). Steve is
formulating a plan, but we do not intend to implement it until we vent for
some other reason.
- Steve
has placed our 6 accelerometers at strategic places around the lab and is cabling
them up into the PEM system in a semi-permantent
way.
- Steve
is looking to procure a fiber-coupled AM laser for in-lab testing of RF
photo-diodes.
- Dan
has run the MC diagonalization script and
adjusted the output matrices, and has re-adjusted the biases to get the MC
aligned the way it was before. In order to avoid mis-alignment
during the diagonalization procedure, he (and
Ben, when he returns) will implement RevB coil
drivers on the MC suspensions in order to decouple the biases from the
drive voltages.
- The
oplev laser diode for MC2 died. Steve and Dan
replaced it. We need that oplev to adjust coil
gains to decouple POS-> ANG.
- The
MC3 UL OSEM sensor is flaky; sometimes it reads zero. Bob replaced the
cables from the satellite amp to the vacuum feedthroughs,
but it didn't help. Steve swapped the satellite amp itself with a spare.
If it reads zero again, Bob will replace the long cable from the satellite
amp to the rack (first, just the connector on the satellite amp end).
- Rana and Rob tried to debug the problems with the end
QPD whitening switch controls, but they need Jay's help. It's some problem
in the Wiring/code/DB.
- Rob
went through all the EPICS channels that are useful for length sensing
(and SUS_OVERFLOW), and added them to the trend data (MANY new channels).
Lab Infrastructure
Thermal Noise Interferometer (Black)
Nothing significant to
report this week.
LASTI (Ottaway)
(Rich Mittleman for David Ottaway)
Vacuum System
The noise in the main Lasti vacuum system turbo
pump seems to have gone away and it has been running continuously since last
Friday. This turbo was purchased used, so we don't know how many hour that it
has on it. Up to now we have been operating it within the manufacturer’s
specifications, but have now resolved to be more conservative.
With the BSC stack removed the pump down is proceeding much faster and we
are now below 2E-6torr.
Laruent
I have created a solidworks model of the HAM vaccum chamber + optical table to add every parts we will need for the cavity experiment and check that
everything is going to be ok. The 2 triples fit without any trouble and only 1
geophone needs to be moved by 4 inches to let the laser beam pass.
I am working on a matlab interface for the modal control
and estimator. Even though it takes a bit of time now, I think it's going to
save more later by simplifying the way to generate
plot and simulations. It's about 1/3 done now.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
Weekly E2E Physics Meeting
Mark Barton talked about "Effect of wire stiffness on pitch modes and
correction thereof" (Details below). Viewgraphs are available here: http://www.ligo.caltech.edu/~e2e/ME2ET/Minutes05/051006/
Ash Khan from LLO discussed a problem related to the conversion of huge
matrix outputs (~300X300 dimension)from Matlab model of seismic isolation system to ASCII files so
that e2e can properly read it.
Mechanical Simulation
(Mark Barton) This week I spent lots of time in the lab with Calum assembling and balancing the quad pendulum and
reaction chain, as well as giving yet more thought to why it hadn't been stable
when first assembled. I did a lot of theory and modeling to see whether the
corrections we had made to the wire attachment points to allow for the
stiffness of the wires were appropriate. I concluded that we had been applying
slightly too much correction because we had not allowed for the slant of the
wires at the top two levels, but that this was not nearly enough to explain the
observed instability.
Advanced LIGO modeling
(Hiro) Rana has provided
a simple design spectrum of table top, both BSC and HAM. SEI+SUS in SimAdvLIGO will be modified to reproduce this by using a
toy BSC and HAM.
Modeler
(Hiro)
Hiro and Biplab
developed the primitive module interface of fast dual
recycled Michelson cavity.
- The
e2e code related to frequency noise (used in SimLIGO
for Common mode ARM control) has been improved by tracing the history of
the frequency. This expands the frequency region under control from 100kHz to much much larger so
long as the variation of frequency noise is not large. Test will
continue to validate the code and this frequency noise issue.
(Melody) Documenting Matt's modeler scripts for remote
processing.
Alfi
[In the following PR =>Problem Report]
(Bruce)
- Completed
work on a secondary alternative to starting Alfi
via Web Start for those who may only be able to use Alfi
remotely displayed on an X server. (PR 483)
- ALfi release generation scripts all updated for the
upgrade to Alfi 6. (associated with PR
483)
- Beginning
work on Alfi node validation (a general check
for any inconsistency mostly focused for now on whether bundle I/Os are in
a completed state. It will also check for various other possible
inconsistencies if and when they are determined to be an allowed state of Alfi. I.e., there are states which are valid in
interim work on an Alfi system which may not be
a valid state for a completed system to be handed to themodeler.)
(PR 495)
(Melody) Continuing with fixing the PRs.
Finished improvements on the miniature view of all opened windows (PR 474).
Also finished fixing PR 499.
Data Analysis Activities (Lazzarini)
Shawhan:
Zanolin:
Organized LSC-virgo burst workplan
and LSC-virgo f2f agenda. Further
testing on the parameter estimation. Sprayed some Auriga frames and set up a web page storing cachefiles. Partecipated to Burst f2f. Some activity on WB5
review.
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS
The managerAPI now has a new socket based on TclGlobus that allow clients to connect and authenticate
based on X.509 certificates and is a GSI secured socket.
The controlMonitorAPI has had a similar new socket
based on TclGlobus for the cmonClient
(GUI to the controlMonitorAPI) to use to establish a
GSI secured socket for X.509 authentication for about a week. However, new
issues were discovered this week to allow the controlMonitorAPI
to act as a "proxy" to forward job requests to the managerAPI using X.509 certificate protocols.
At issue is the need to use the host certificate to authenticate between the
two processes running on the same server box. This requires use of
functionality that currently isn't available through the TclGlobus.
This functionality is likely to be absent from the next LDAS release.
The LDAS-CIT system is now running a pre-release of the Solaris 10 and
Fedora Core 4 versions of LDAS (since LDAS-CIT has now been upgraded). The IBM
DB2 database on LDAS-CIT and the resource files were upgraded to be concurrent
with the components of the next release of LDAS in the effort this week.
Efforts continue in the understanding of why some output frame files do not
get renamed from their temporary names to their final names (PR#2900).
Several tests were modified to correctly find some of their missing data.
Continuing with the cleanup of /ldcg, pkgbuilder (formerly known as sinstall)
has been modified to supply the LD_RUN_PATH environment variable so libraries
and applications and users making use of /ldcg do not
have to explicitly have /ldcg/lib in their
LD_LIBRARY_PATH environment variable. This also resulted in a full rebuild of /ldcg for Solaris 10.
Some small cleanup of /ldcg continues to happen.
Less has been removed from /ldcg for Solaris as the
system provided less supports all needed functionality. Curl has been upgraded
to 7.14.1. LDAS has successfully used this version for the past week. The
utility lsof has been removed from the Fedora Core
version of /ldcg as Fedora Core 4 supplies a version
in /usr/sbin. The installation of cvsgraph
has been corrected to remove an extra directory layer. The building of the
XML-Parser module for perl has been placed after the
building of apache as the module requires files supplied by the apache
installation. Finally, the building of gnats now includes the creation of
several symbolic links. This allows the site specific data not to be lost when
newer versions of gnats are built.
Testing: ran system test for ldas 1.7.52 and
updated cvs with test results. Develop model tclglobus client ( RawGlobusClient
package ) to submit jobs to managerAPI.
TCLGLOBUS
Worked with Mary on LDAS managerAPI
and Globus XIO integration problem. The
problem was typo on LDAS managerAPI callback procs causing the application in spin loop.
Worked on the possible solution of using Tcl channel to encapsulate all the detailed implementation
of setting up Globus XIO from Tcl
programmer.
Discovered a problem when two Globus XIO services
(LDAS managerAPI and cmonControl
server) communicating each other using host certificates only to authenticate
each other.
OSG/GRIPHYN/IVDGL
{Inspiral work flows on OSG-ITB}
Successfully executed a 603 DAG node DAX of Inspiral work flow on the LIGO-CIT-ITB cluster from host Verruca using a condor DAGman
component with a bug fix supplied by the condor team.
Recruited the assistance of Brian (UWM) and Murali (PSU) to test the Inspiral
work flow job submission on OSG PROD clusters at their sites.
Determined that the OSG PROD cluster UWMilwaukee
had insufficient space to meet the Inspiral work flow
requirements: 50 GB free space. Brian believes he can add disk capacity to meet
this requirement on or about Monday October 10.
Determined that the OSG PROD cluster OSG_LIGO_PSU has a missing directory
$VDS_HOME/bin/linux and missing executables from its
configuration. Requested Murali check the
integrity of the VDS installation and report back.
Received information from the VDS team to examine the database version of
the Transformation Catalog (TC) and use that
database as an alternative to vds-get-sites for
managing the physical mapping of transfer and dirmanager
files.
{GUMS and PRIMA configuration}
With the assistance of Murali, the LIGO Privilege
page is installed in the OSG Twiki at: http://osg.ivdgl.org/twiki/bin/view/Provisioning/LigoPrivilege
required of LIGO in order for other VOs to configure
their sites to allow LIGO access.
At the Monday systems engineering meeting, Murali
committed to providing support for voms-proxy-init
functionality on the voms server.
{On-going monitoring and systems administration}
Performed a yum update and reboot of all nodes of
LIGO-CIT-ITB.
The necessary version of VDS identified by the GriPhyN-LIGO
collaboration with ISI has made it into the next version of VDT which will be
the bases for the next release of OSG software stack.
Hardware Systems (Anderson)
Caltech
(Phil Ehrens)
- Installed
Solaris 10 and Fedora Core 4 on tandem-iii and tandem-v machines.
- Performed
various DOE cert related tasks.
- Investigated
reconfiguring Fedora Core 4 install on systemimager
to be a raid 1 mirror between disk A and disk B. Incomplete.
- Helped
Mary Lei and Mike Samidi with TclGlobus issues.
(Stuart Anderson)
- Updated
LDAS-CIT with a pre-release of LDAS.
- Researching
the next generationg CIT cluster including a
possible Cisco network switch upgrade.
- Monitoring
the Synchrotron facilities upgrade and had some of the electrical work
moved to increase the airflow under the raised floor.
- Helped
upgrade several Solaris 9 test machines to Solaris 10.
- Cleaned
up web services on ldas-sw after the upgrade to
Solaris 10.
- Brought
to conclusion a proposal to add L4 RDS frames for S5.
MIT
(Keith Bayer)
- working on LSCdataFind .
- troubleshot another problem with the Foundry switch
(reboot fixed it).
Livingston
(Igor Yakushin)
- The
biggest problem after LDAS move downstairs is malfuctioning
HVAC in the high bay area. The temperature in the high bay area is about 8
degrees above the optimal operating point. The humidity is about 10
percent higher than it should be despite the fact that HVAC in the high
bay area was designed for much larger heat loads than LDAS computers can
generate. Allen is working on finding the way to fix the cooling problem
by either fixing the existing HVAC or bringing the temporary AC
unit. The situation should be resolved next week. Another potential
problem is the presence of mice in the high bay area (Allen and Mike have
been alerted). I also asked for the high bay area to be regularly vacuum cleaned to protect the equipment from dust.
- 3510
unit developed a problem in the I/O module of the primary controller. The
primary controller failed on Friday morning, the unit switched to the
secondary controller. On Friday night the secondary controller froze as
well. On Saturday morning I power cycled the unit, it came back on the
primary controller, but since then it periodically generated error
messages in 3510 event logs. Also drive 9 failed. I have replaced
the primary controller, the failed disk, reseated secondary controller and
all the disks. At first glance that fixed the problem but we need to use
the system for several days to make sure. Currently we are working on
restoring damaged /archive file system from tape. There were also
some errors corrected in /frames file system that is used by fb1.
- Failed
power supply was replaced in node8.
- Moving
company keeps rescheduling the delivery date for 140 nodes from CIT.
- The
old GigE switch was shipped to MIT.
(Dwayne Giardina)
- Replaced
failed disk in T3-14.
- At
Igor's suggestion and guidance, wrote small script to run badblocks during night hours on weekend and monitor
output, sending email on detection.
- node63 reported bad blocks on hda,
to be replaced soon.
- Donnie
Buzbee came in to troubleshoot problems with
3510 controllers and disks. He worked with Igor since I was scheduled to
do Kantech software upgrade with Chuck Brannon
of Excel.
Hanford
(Ben Johnson)
- DB2
has been initialized with the segment database at LHO. It was populated
from the L3 LHO RDS frames yesterday. Duncan Brown is currently getting
the segfind server up and running.
- The
22-Ton air conditioner was started last night. Though it doesn't have all
the coolant it needs, it still cools the room more than adequately. It is
producing low frequency vibrations that are shaking the building despite
the seismic isolation springs.
- With
the new 22-Ton AC, ear protection is now required to work in the LDAS room
at LHO.
- The
D2D scripts are ready for M7. I will set up the publishing scripts today
(should only take a config file change).
- Another
node's power supply died (node104), and I replaced it with the one spare I
had left. I will order more replacement power supplies.
General Computing (Wallace)
MIT
(Keith)
- Helped
support burst f2f meeting Monday and Tuesday
- Swapped
out failed hdd on workstation anthias - will send back as it's under warranty
- Installed
and tested freeware Gantt chart software
- Created
gc account for new grad student (Brett Shapiro)
- Ordered
several more standalone matlab licenses
LLO (Dwayne)
- Installed
Protel for Ken Watts
- Kantech security software installation with Chuck
Brannon of Excel. System scheduled to be switched over to new
version next Monday. Requires replacing some hardware. During
installation noticed some doors reporting incorrectly. Their sensors
are now fixed. Also fixed the side gate 'fully opened' sensor, which
was not detecting the gate being opened.
- Multiple
DNS changes for Lisa B.
LHO
(Christine)
- Started
installing Symantec Antivirus version 10 on all PCs.
- Started
installing the latest versions of Matlab, Mathematica and Exceed.
- Renewed
the maintenance contracts for Winzip, Exceed, Matlab and Mathematica.
- Trying
to determine the status of the Cisco support contract so I can request
troubleshooting help with my router. The router is not able to keep
up with the traffic requests and is dropping packets. Last year my
support contract was sent to Larry and it appears that efforts to separate
my contract have not worked.
- We
have been unable to get a link working between LHO and PNNL for the 10 mb/s backup network. The media converters check
out OK, the fiber path is lossy(DB link loss), but still in the range of the media
converters. We've tried just about everything we can think of, but
still no link. I continue to work with PNNL to get this working.
CIT
(Christian)
Calum Torrie
- Removed 4 different types of adware/spyware running
on Calum's workstation. I also added 2GB of RAM to his
workstation.
Helena Armandula - Configured new
laptop with the standard Ligo image.
Phil Willems - Updated Phil's
laptop with Norton 10.
Mike Smith - Configured new workstation and transferred all
of Mike's settings and files.
40 Meter - Updated workstations and
laptops with Norton 10.
Millikan - Replaced toner
cartridges on HP 5500 printer.
Other misc.: Continued onsite software/phone support.
(Veronica)
- LSC:
With MIT, continued troubleshooting of the credit card entry form for the
upcoming meeting. Seems we have it working well now.
Updates to the meeting website. Updates to the database of the LSC
documents under review. Updates to the observational results
webpage.
- LIGO:
Some Windows server support. Updates to the roster database.
Updates to the LIGO website. Working with Dwight Carter on training
him to edit the webpages for the Advanced LIGO
cost /scheduling.
- CaJAGWR: User support.
- Project
Science: Website updates and user support.
(Mike)
- Loaded
an engineering workstation with Solid Works and GC software.
- Worked
on the Spam Filters.
- Continued
work on updating users Anti-virus software from ver.
9 to 10.0. This was a rush due the Norton 9.0 software not updating
its definition files. We have most of this work finished.
- Calum Torrie: Problems with
his new laptop recognizing hardware key (dongle) for Solid Works. I have
contacted GoEngineer regarding this issue. I
have been on the phone with support trying many debugging options, but as
of now I am not getting anywhere. This is an on going process. On
the new dual core Dell workstations they do not come with a parallel
port. Therefore our parallel dongles will not work with these
workstations. I contacted Go-Engineer and to swap our parallel dongle to a
USB dongle this will be an additional charge of $50.00 dollars per dongle.
- Added
additional users to the wireless access point list.
- Ghosted
all NTSRV'S for end of month backups. I had some problems with a few of
the servers. This was due to DHCP issues on the network. I had to free up
some addresses to pick up a DHCP number to connect to the ghost server.
- Started
installing Ansys 10.0 on our Engineering
workstations. This is a big job that will probably take me well into the
rest of the week.
(Larry)
- Still
going through maintenance contracts. The SUN contract is now going through
the Caltech system and should be wrapped up next week. Foundry just mis-handled some paperwork and they should have it
cleared up in the next few days. CISCO has a huge problem. It looks
like they put all of the CIT CISCO equipment on to one contract and now
that all has to be separated out. ITS has the
most work to do but I still have to check through everything to make sure
our items were not included. Purchased a number of fiber related
items. Also checking on termination kits to see if it is viable to change
out the connectors on all of our spare fibers. Purchased a number of
misc. items. It appears another small scanner and a portable DVD burner is
still needed. Working on getting the media for the Matlab update and the purchase of a new toolbox.
- Still
installing equipment into room 19. This will take a few more weeks. The
power connection going from room 18 to room 19 has been completed and the
UPS has been installed and is charged up. Need to order another edge
switch for the room. We will use the spare switch until then.
- Setup
a number of new user accounts. Also, setup a couple of new boxes.
- We
have reworked the IP address layout in order to accommodate the DHCP
usage. This should only affect a few people and the sandbox units, this should not affect any of the server setups
we presently have.
- Performed
the monthly backups. However, with the change of some of the LDAS
equipment there are a few more backups to be performed and some s/w
installations need to be done to get things back on-line.
- Helped
debug a few minor issues on different servers. The LDAS server swap over
caused a few links to quit working but all were quickly updated.
- Spent
time working on a interesting e-mail problem. ITS had sent a message in-which the recipients client
utility would not read the message. We tested a number of client utilities
on the message and so far only pine and dtmail
have the capability of reading the message without corrupting the spool
file or mailclient in some manner. Hopefully,
we'll get some more time to investigate this anomaly.
- Assisted
a number of users in getting to the CIT Oracle database in order to
register their vehicle. The link is not quite setup correctly and if the
DNS paths are not setup correctly you get taken to another location on the
web.
- The
changes made on the spam filters has cut down the
time we spend on checking for false positives. However, there is more spam
getting through the system but we are still blocking a good percentage.
Mail Statistics for Sept. 29 - Oct. 05, 05
|
Mail Statistics
|
September 29 -
October 05, 2005
|
|
Rejected Messages
|
19,774
|
|
Virus Messages
|
631
|
|
False Positives
|
12
|
|
Accepted Messages
|
15,157
|
|
Total Messages
|
34,931
|
Advanced LIGO and Supporting R&D (Shoemaker)
Systems
from Dennis
Coyne
See also:
AL
Systems web page
AL Systems email
archives
Records Of Decision or Agreement (RODA)
See also the RODA
status web page
- nothing
significant to report
Requirements
- nothing
significant to report
Interface Issues
See also the
"Interfaces" section of the AL Systems web
page
- nothing
significant to report
Systems Design/Support
- nothing
significant to report
Vacuum Compatibility & Preparation
Residual Gas Assay (RGA)
See also the Vacuum Bake Lab
Bob Taylor
- Completed
a bake job on quad parts today for Calum.
- Began
a bake job on magnets for Calum
- Completed
the Bake out of the big air bake oven and will began
Qualification process today. I expect to submit qualification tests to
Dennis Coyne next week for approval.
- Finished
reassembling the vacuum system for oven C and have began check out of the
entire oven system.
- I
have installed a new pump on oven E and will complete the bake out of the
RGA by tomorrow.
- Have
ordered new diodes for the OSEMs and should be
able to start building and replacing the diodes in the existing OSEMs for the Quad.
High-Irradiance, Contamination-Exposure Cavities
Lee Cardenas, Liyuan Zhang
|
Cavity
(Location)
|
Material/Item
|
Start
|
End
|
Comments
|
|
Cavity #1
(OTF Lab,
Bridge)
|
MMG nickel
plated Nd-B-Fe magnets (Helena Armandula, SUS )
|
~6/8
|
TBD
|
No
Change
Cavity re-alignment is in progress due to power drop and oscillation.
~2 more weeks to completion
|
|
Cavity #2
(OTF
Lab, Lauritsen)
|
NA
|
NA
|
NA
|
No
Change
cavity is close to being ready for samples
|
|
Cavity #3
(OTF
Lab, Lauritsen)
|
samples have been put into the chamber
OSEM Flexi-circuit cable, qty ~ 45
(Helena Armandula,
SUS)
supplied by Univ. Birmingham (Stuart Aston)
|
~6/10
|
~9/10
|
taking daily absorption & ring down measurements
DuPont Flexible Circuits. The whole part to be
constructed of 'flexi' i.e. no 'rigid' sections. (Stuart Aston,Univ. of Birmingham, SUS/UK subsystem)
- Start Laminate: Kapton (LF8515)
(document link: http://www.dupont.com/fcm/products/H-73244.pdf
Coverlay (x2): Kapton
(LF0110)
(document link: http://www.dupont.com/fcm/products/H-73245.pdf
DuPont Pyralux
Series - Kapton / Acrylic Adhesive system.
(document link: http://www.dupont.com/fcm/products/H-73246.pdf
--------------------------------------------------------------
OSEM
emitter & photodiode 40 of each, (Dennis Coyne, SUS
) Test has been completed. Results to be posted by Liyuan
Zhang soon.
|
|
Queue
Priority 1
|
2 Cleaned 50ppm transmission mirrors, 1 in dia., REO coated --
|
TBD
|
TBD
|
witness samples for the LHO vertex volume (added in
6/29/2005 vent)
|
|
Queue
Priority 2
|
Stepper
Motor (Riccardo DeSalvo,
possible SUS or ISC use)
|
TBD
|
TBD
|
Stepper Motor sample had been placed
into Cavity #1: Power dropped from 175 mW to ~25 mW after introducing the stepper motor sample, and
continues to decrease. It is very hard to keep cavity locked. The stepper
motor may have contaminated the mirrors. Will re-test when a cvity becomes available again.
To be rebaked soon using the self-heating capability of the
stepper motor (not just the oven heater controls)
|
From: Rolf Bork <rolf@ligo.caltech.edu>
- Jay
and I put together a cost estimate for CDS systems to be installed at Lasti over the course of the next year or so.
- The
computer to be used for the Quad controller has arrived. I do not as yet
have a delivery date for the PCI-X expansion chassis for the I/O cards. In
the meantime, we will install the I/O modules directly into the PCI-X
slots of this computer for driver development.
- The
driver for the ADC card is almost complete. I only need to change the
sample clocking from the ADC internal clock to an external clock. Unlike
our VME Pentek modules, this ADC does not have a
downcounter for external clocks and therefore
requires a 16384Hz sample clock supplied. In the short term, the plan is
to use a DAC clock output of the old Variable Delay Timing Module, which
is a 16384Hz square wave synched to our 4MHz GPS
timing clocks.
Seismic Isolation
From: Ken Mason kmason@ligo.mit.edu
Advanced LIGO Seismic Structure Procurement Status
|
Assembly
|
Status
|
|
Top Assembly Components
20007970-A
Stage 0 Assembly
2000795-A
Stage 1 Assembly
20007825-A
Stage 2 Assembly
20007825-A
|
RFQ complete, awaiting bids. Quotes due 9/30. Quotes recieved.
RFQ complete, awaiting bids. Quotes due 9/30. Quotes recieved.
RFQ complete, awaiting bids. Quotes due 9/30. Quotes recieved.
|
|
Stage 0-1 Spring Assembly
20007878-A
Stage 1-2 Spring Assembly
20007890
|
Fabrication drawings are complete. Drawings must now be
checked.
RFQ for blades and rod flexures complete.
Maher Limited holding maraging steel for blades and
flexures
|
|
GS-13 Pod Assembly
20007810-A
L-4C Pod Assembly
20007820-A
STS-2 Pod assembly
20007941-A
|
Geophones, seismometers and lockers are in house.
RFQ complete, awaiting bids for vacuum housings. Quotes due 10/16
RFQ complete for machined components. Quotes due 10/16
RFQ required for internal pod harnesses.
|
|
Stage 0-1 Kinematic Lock
20007941-1-A
Stage 1-2 Kinematic Lock
20007941-2-A
|
Tooling design complete.
RFQ complete, awaiting bids. Quotes due 10/21
|
|
Stage 0-1 Actuator Assy.'s
20007966-A
20007967-A
Stage 1-2
Actuator Assy.'s
20007968-A
20007969-A
|
Tooling design complete.
RFQ complete, awaiting bids. Quotes due 10/21
|
|
Stage 0-1 Standoff Pin
Stage 0-2 Alignment
Tower and Washer
Stage 2 Keel Plate
Alignment Tower
Blade Pre-Load Tooling
Blade Calibration Fixture Modifications
LASTI Test Stand and Spreader Bar
|
Solidworks part files exist for
the standoff pin and alignment towers. They will require a dimensioned
drawing and checking prior to soliciting bids.
The blade pre-load tooling and calibration fixture tooling will require
redesign following the redesign of the blade springs by ASI.
Purchase order for test stand issued to Southern Enterprises. Delivery to MIT
by 10/16
|
From: "Joseph A. Giaime"
jgiaime@ligo.phys.lsu.edu
Agenda for the weekly SEI telecom
Friday, Sept 30, 2pm Eastern, 1pm Central, 11am
Pacific time
Announcements
- New
group member at Stanford: Matthew DeGree
- Meeting
later this afternoon to discuss HAM SAS procurement bid prep.
BSC SEI status, Ken M
Gina has sent
out all RFQs. First work package (main
structure) bids are due to us today. We need to have a small committee,
recommending a selection, late next week.
Ken points
out that the ballast masses are quite expensive and may be amenable to value
engineering.
Next batch of
bids due Oct 15 or so.
ASI has
finished the spring redesign and delivered the results on CDROM. Ken is
starting to fold the changes into our PDMWorks model
and drawing database.
Ken wants to
get new bid on blade and flexures reflecting the new shape
BSC work (Rich M)
HAM control with VME (Pradeep)
no report.
Electronics (Jay, Brian)
- received
new GS13 readouts (Thursday)
- needs
for cables (Jay)
- New
boards received at Stanford; Brian has vented the ETF and will test them
soon.
- Shyang assembling parts for locker/unlockers to be sent to Jay. Brian will
liberate the stamp unit and send it to Shyang.
- Rolf
and Jay continuing work on the new PCI/X ADC/DAC boards and DSP, plus
software. Test results expected within a few weeks.
- Brian
to send an STS-2 to LLO before the beginning of the S5 run. It will
be our spare for the run.
Suspension
From: ctorrie ctorrie@ligo.caltech.edu
Mark and I now have a quad with reaction chain suspended in the lab. Still
some work to do but both chains are stable! See: -http://131.215.114.242/view/index.shtml
for a live view
From: Janeen Romie romie_j@ligo.caltech.edu
Working with Helena and Caroline on Ribbon/Fiber/Ear PDR
documentation, due today.
Working on Estimate to Complete budget for Carol.
From: Helena Armandula ahelena@ligo.caltech.edu
The bonding of magnets to aluminum holders / flags with a sodium silicate
solution seems to work properly; the bonding strength seems to be similar to
the one obtained with Vac Seal.
From: "Mark Barton" mbarton@ligo.caltech.edu
This week I spent lots of time in the lab with Calum
assembling and balancing the quad pendulum and reaction chain, as well as
giving yet more thought to why it hadn't been stable when first assembled. I
did a lot of theory and modeling to see whether the corrections we had made to
the wire attachment points to allow for the stiffness of the wires were
appropriate. I concluded that we had been applying slightly too much correction
because we had not allowed for the slant of the wires at the top two levels,
but that this was not nearly enough to explain the observed instability. I
summarized this work in a talk G050496-00-D, for the E2E group, which I'll
reprise next Tuesday for the SUS group.
From: Ken mailand kmailand@ligo.caltech.edu
I have suggested an idea to Calum for a quick test
for the suspension fixture rotating table, using a piece of Teflon between the
contact surfaces.
Cheryl installed the flow meter mounts at LHO and the drawing is in the DCC.
Core Optics
From: Bill Kells
<kells@ligo.caltech.edu>
I've been preparing for the TCS meeting Phil is calling (next week ?) by
running Bench to determine how much cold arm mode mismatch can be tolerated to
run AdL at low power (but full input beam power !)
with no diminution of [matched] sensitivity.
Also: ongoing development of a better take on the
PI situation. Mostly trying to reconcile the different views: UWA, MSU, Caltech.
Pre-Stabilized Laser
From: Peter King pking@ligo.caltech.edu
An cost estimate-to-completion for the LASTI laser
was done, largely based on a previous costing.
Testing of the 200-W laser is pencilled in for the
first week in November.
Auxiliary Optics
No report this week.
Other Laboratory R&D
Chiara
I made the hardening process for the maraging
steel wires. The first step for this process is heating the material, in argon
atmosphere for about 100h at a temperature of 435°C. The second step is heating
the material at 470°C for about 2h. I put a thermometer inside the material in
the oven in order to check the temperature of the maraging
steel during all the heat-treatment. From the measurement of the internal
temperature I found that the steel reached 435°C in about 20h. With the fit of
these data I could figure out a time plan for the second step of the process.
To reached 470°C I set the temperature of the oven at 500°C for 2h ( time for
the material to reach 460°C ) and after at 470°C for 1h and half.
About the measurement on the test for horizontal attenuation system with four Inverted Pendula, I
found some problems with the signals from one of the two accelerometers. The
signal was too noisy. I figured out that the problem was in the cable.
Valerio
I've redesigned my SimMechanics model of the
HAM-SAS in a hierarchical structure. For this reason I have created a custom Simulink library containing blocks that represent the
single parts of the suspension such as the GAS, the IP leg, the ground. Now
it's possible to create simple structures just dragging and dropping these
blocks in a Simulink model. In this way it should be
easier to find out the origin of our unexpected simulation results. In
particular we need to understand whether or not these problems are coming from
the incapacity of SimMechanics to simulate these
structures correctly.
Juri
I extended the analysis of tilt sensitivity for our MH cavity including the
measured maps for the three cavity mirrors (input, folding and end-MH). The
deformations of the input and folding mirrors have a great impact on the
resonant mode shape and power distribution. The orientation of the three
mirrors is a critical issue and a meaningful comparison with the experimental
data should require a better knowledge of the actual mirrors orientation.
However my simulations support the idea that the discrepancies with the
theoretical prediction using perfect optics can be explained by the deformed
mirrors.
For additional information about this report, contact Stan Whitcomb or Phil Lindquist